DOCUMENT 7.19
Design Guide Proposed Tunnel Head Houses & Permanent Site Landscaping National Grid (North Wales Connection Project)
Regulation 5(2)(q) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
Application Reference EN020015 September 2018
Environmental Statement Chapter # iii Ecology and Nature Conservation Document #.#
Document Control
Document Properties
Organisation Jacobs
Author Nivedita Vijayan
Approved by Stewart Samson
Title Tunnel Head House Design Guide
Document Reference 7.19
Version History
Date Version Status Description/Changes
Sep 2018 A Final First Issue
North Wales Connection Project 1.0 Introduction 4 1.1 Background to the Project 4 CONTENTS 1.2 Purpose and Structure of the Report 5 1.3 Proposed Infrastructure 6 1.4 Design Context 8 1.5 Initial Stakeholder Engagement 10 2.0 Braint Tunnel Headhouse and CSEC 12-36 2.1 Introduction 12 2.2 Regional Context 13 2.3 Strategic Landscape Context 14 2.4 Landscape Designations 16 2.5 Sensitive Visual and Cultural Heritage Receptors 18 2.6 Site and Wider Context Analysis 19 2.7 Vision, Design Options & Principles - Braint 24 2.7.1 Vision and Design Approach 24 2.7.2 Braint Site Building Form Preferred Option and Key Design Principles 26 2.7.3-2.7.5 Braint Site Building Form Initial Options 28-30 2.8 Landscape Design Approach 31 2.9 Photomontages 32 2.10 Materials Pallet 34-36 3.0 Tŷ Fodol Tunnel Headhouse and CSEC 37-63 3.1 Introduction 37 3.2 Regional Context 38 3.3 Strategic Landscape Context 39 3.4 Landscape Designations 41 3.5 Sensitive Visual and Cultural Heritage Receptors 43 3.6 Site and Wider Context Analysis 44 3.7 Vision, Design Options & Principles - Tŷ Fodol 50 3.7.1 Vision and Design Approach 50 3.7.2 Tŷ Fodol Site Building Form Preferred Option and Key Design Principles 52 3.7.3-3.7.6 Tŷ Fodol Building Form Initial Options 54-57 3.8 Landscape Design Approach 58 3.9 Photomontages 59 3.10 Materials Pallet 61-63 4.0 Pentir, Gwynedd 64-69 4.1 Site analysis 64 4.2 Pentir 400kV Substation Technical Design 65 4.3 Landscape Design Approach 69 5.0 Conclusion 70 Tunnel Head House Design Guide Document 7.19 4 1.0 Introduction 1.1 BACKGROUND TO THE PROJECT National Grid operates the electricity transmission system in Great Britain and owns the system in local context. It should be read in conjunction with other documents being submitted as part of the DCO England and Wales. The system operates at 400 kV and 275 kV, connecting electricity generators to application. substations where the higher voltages are transformed to lower voltages, enabling the power to be distributed to homes and businesses by the Distribution Network Operators. This Design Guide has helped to inform the proposed parameters within which the final design for the Tunnel Head Houses at Braint and Tŷ Fodol would need to comply, as defined in the draft Development National Grid has a statutory duty to promote competition in the supply of electricity and is obliged Consent Order for the North Wales Connection Project. This Guide will also inform the final detailed to offer a connection to the system to anyone who applies for a connection. Horizon Nuclear Power architectural form and treatment for the Head Houses, together with the landscape treatment at the two (HNP) has applied to National Grid to connect their proposed new nuclear power station to the tunnel compound sites and in the vicinity of Pentir Substation. The design guide sets out the design national system at Wylfa, Anglesey (Wylfa Newydd). The proposed power station would be within a concepts for each of the sites exploring ideas, approaches and materials that reflect the individual nature site already identified for this type of development in the UK government’s National Policy Statement of each of the sites. Contents will be developed further at detailed design stage based on the design (NPS) EN-6 ‘Nuclear Power Generation’. principles established in this document. The detailed design will be developed with full compliance of the current health and safety regulations and in accordance with CDM regulations. National Grid owns and operates an existing substation at Wylfa, which the proposed Wylfa Newydd power station would connect to. This substation is connected to the main transmission system The sites included within this Design Guide are: on the mainland in North Wales by a 400 kV overhead electricity line, connecting at the existing • Braint Tunnel Headhouse and CSEC; National Grid substation at Pentir, in Gwynedd. To provide reliable electricity supplies, National Grid • Tŷ Fodol Tunnel Headhouse and CSEC; and cannot allow more than 1,800 mega-watts (MW) of power generation to be connected by any single overhead line. As the HNP proposal would have a total output of 2,940 MW, a second connection is • Pentir Substation. required between Wylfa and the transmission system on the mainland.
The Preferred Route Corridor Selection Report (Document 9.2) stated: The large number and concentration of sensitive sites on both shores of the Menai Strait was acknowledged. Given the nature of the landscape and the importance of these sites an overhead line crossing of Anglesey AONB and the Menai Strait would result in significant adverse landscape and visual effects. The Report went on to conclude that: The significant economic cost of using cables instead of overhead lines to cross the Menai Strait would be considered appropriate when set against the significant environmental effects of an overhead line option. Further work would be required at the detailed design stage to confirm the BRAINT TUNNEL TŶ FODOL TUNNEL preferred SEC locations, crossing location and construction methodology for the Menai Strait HEADHOUSE AND HEADHOUSE AND crossing and link to Pentir Substation. CSEC CSEC
Following a detailed appraisal of the options available for crossing the Anglesey AONB and the Limit of deviation Menai Strait National Grid concluded that the most appropriate means of achieving the crossing was Tunnel Head House Locations and tunnel alignment Contains Ordnance Survey data © Crown through the installation of cables in a new deep tunnel. This conclusion is explained in more detail in copyright and database right 100024241(2018) National Grid’s published ‘Menai Strait Crossing Report’ (Document 9.6).
Two sites on either side of the Menai Strait have been identified as locations for Tunnel Head Houses (THH): Braint on the Anglesey side and Tŷ Fodol on the Gwynedd side. This Design Guide describes the context analysis carried out around both these sites. This document explains the various design approaches that have been considered for the Tunnel Head Houses and the surrounding landscaping and presents a preferred design approach that takes account of the site’s
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 5
1.2 PURPOSE AND STRUCTURE OF THE REPORT In May 2017, a series of stakeholder engagement meetings were held with the Isle of Anglesey County Council and Gwynedd Council to discuss the potential design approaches for the proposed tunnel head houses at the Anglesey and Gwynedd tunnel shaft sites. Subsequently National Grid has agreed that a Design Guide presenting overall site and context analysis followed by potential design approaches, colour and materials palettes should be presented as part of the DCO application to provide a clearer understanding of the likely final form for these elements of the proposed development.This Design Guide considers the immediate site contexts as well as wider landscape character. It presents site specific design approaches to the tunnel head house buildings and describes the associated landscape treatments. Objectives set out in the National Policy Statement (NPS) EN-1 and EN-5 have been addressed. Relevant Landscape Character Areas and LANDMAP visual and sensory aspect areas, as well as the strategic contextual landscape issues have been considered.
Braint Site, Anglesey This Design Guide supplements the North Wales Connection Project Design and Access Statement (DAS) (Document 7.16). It relates to the following sites identified as part of the North Wales Connection Project: • Braint Tunnel Headhouse and CSEC; • Tŷ Fodol Tunnel Headhouse and CSEC; and • Pentir Substation.
This Design Guide focuses on the proposed tunnel head houses on the Braint and Tŷ Fodol sites and technical design and landscape treatments for the Pentir Substation site. While this document focuses on the site-specific infrastructure listed above, this does not change National Grid’s commitment to good design, as set out in Design and Access Statement (Document 7.16) in relation to all aspects of the North Wales Connection (NWC) Project.
The primary purpose of this document is to provide a framework of design principles within Tŷ Fodol Site, Gwynedd which National Grid will develop detailed design proposals for the tunnel head houses associated with the NWC Project.
The Design Guide includes: • design Context including National Policy Statement (NPS) EN-1 and EN-5; • a summary of the initial stakeholder engagement on the general design approach that was favoured; • landscape context analysis, design vision, built form design approaches, landscape design approaches, materials palettes and design examples for the Braint and Tŷ Fodol sites; and • technical design and landscape design approach for the Pentir Site.
Existing Pentir Substation
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 6
1.3 PROPOSED INFRASTRUCTURE
Overhead line terminates at The new 400 kV connection would comprise the following: • Tunnel Head Houses: Tunnel head houses would be required pylon and ‘down-droppers’ • Overhead Line approaches to the tunnel compounds: The key on top of the shaft cover slabs to provide direct access into the connect to steel gantry components of an overhead line are as follows: shafts and tunnel for inspection and maintenance. The head -- Pylons: Steel lattice structures, which typically would be house also contains all necessary ventilation equipment and utilities. Typically equipment inside the head house, shaft and We will use landscape 52.5 m in height, and spaced approximately 360 m apart. and planting to help On Anglesey National Grid proposes that the three pylons tunnel would comprise: limit visual impact closest to the site would be low height pylons to reduce -- lighting systems; effects upon more distant views. These are typically around -- heating and air conditioning units; 35 m in height, but wider than more conventional pylons. -- radio systems (for personnel to communicate with each Within Gwynedd the first pylon from the site is proposed to other when in the tunnel during construction and over be low height; operational life of the asset); -- Earth Wire: The highest most line connecting the pylons -- stairwell ventilation (required to maintain safe and clean air and connected to the ground at every pylons in order for personnel to enter the tunnel via the shaft); to protect the overhead line and towers during lightning -- person and goods lift (capable of taking personnel and strikes; equipment into the tunnel); -- system ventilation (needed primarily to maintain a correct -- Conductor: Wire strung between pylons, used for Security fence transmitting electricity; temperature in the shaft and tunnel to ensure that the approx 2.8m high cables do not overheat. It can be natural air flow backed up -- Crossarm: Arms of the pylon that carry the wires and keep Steel gantry supports them separated; and with mechanical fans if required); ‘down-droppers’ -- gas monitors (to ensure tunnel is free from gas ingress and connection to -- Insulator: Holds the conductors to the pylon arms and underground cable sealing Surge diverters provide electrical before workers persons enter); ends provides electrical clearance from the ground and tower protection for underground cables -- Distributed Temperature System (DTS) (to measure the structure. National Grid temperature of a core/cable. This is part of the overall Schematic of Typical Sealing End Compound • Cable Sealing End Compounds: A Cable Sealing End Compound system design and works in conjunction with the system (CSEC) is required when an overhead line changes to an ventilation); underground cable or vice versa. CSECs are secure sites -- pumped drainage (to collect and pump out ground water in surrounded by a palisade fence where the overhead conductors the tunnel and shaft); are connected to the ends of buried cables which are brought -- generators (maybe permanent or temporary) (a tunnel vertically upwards out of the ground; requires a power supply, and a backup system should this • Underground Cables: There are several methods for installing supply fail. Generators can either be brought to site in the underground cables. The preferred technique, due to significantly event of a failure or left in situ); and lower installation costs, is laying underground cables in open cut -- tunnel inspection vehicle (a vehicle used travel along a trenches (or directly on the seabed for marine crossings); tunnel for the purpose of inspection of the cables and • Anglesey AONB and Menai Crossing: A number of techniques carrying equipment to point of any cable or joint failure). have been considered for crossing the Menai Strait by the use • This Design Guide is mainly focused on the design approaches, of new National Grid infrastructure. The proposal to cross the design principles, material pallets, colours and design treatments Menai, is a tunnel; of the Tunnel Head Houses and their interface elements. The technical details of all of the infrastructure are described in other associated documents. National Grid Example of a Tunnel Head House under construction
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 7
The development of the design approaches outlined in this cost effective designs are available. Design Guide was based on several considerations regarding the National Grid appreciates that stakeholders and communities need functional requirements for the tunnel head houses in terms of both to be reassured about the final scale and form of the building, engineering as well as design and contextual issues. Some key especially given the rural, sensitive settings that these tunnel head considerations in the design development discussions included: houses would be located in. Hence there is a hierarchy of control • the industrial fans for cooling and ventilation are key features in measures that are being proposed which include: the THHs. They do tend to determine the highest point of the built • the Parameter Plans impose absolute restrictions on the building form. Generally air is expelled at the highest point of any tunnel, location and scale. They determine zones within which the tunnel working with rather than against the natural direction of airflow. head houses would need to be sited and suggest maximum In this case the highest point of the tunnel would be at Tŷ Fodol, heights and maximum volume for the buildings, which are specific and therefore it is proposed that air is extracted using larger fan to the functional requirements at each of the two sites. Maximum units located at this end of the tunnel. In Braint, the height is kept footprint dimensions in terms of length and width have not been at a minimum as high ventilation fans are not required at this stipulated as it is believed that a modest increase in building end of the tunnel. The Tŷ Fodol built form needs to be higher to footprint (albeit within the location parameters imposed) might accommodate bigger fan units; allow some elements of the building to be reduced in height, and • the THHs also need to accommodate associated welfare facilities potentially afford opportunities to further break up the overall and some of the control rooms which could be lower in height; and massing; and • vehicle access points for maintenance and plant replacement, • Requirement 4 of the draft DCO states: Unless otherwise agreed shaft access gantry cranes etc. are other key design with the relevant planning authority, the above ground elements considerations. The design approaches include placing such of the authorised development comprised in Works No 8 (Braint features along less sensitive interfaces. Tunnel Head House and Cable Sealing End Compound to Tŷ Fodol Tunnel Head House and Cable Sealing End Compound) The functional requirements have influenced the overall design must be carried out in general accordance with the Key Design approaches that are outlined in later sections of this document Principles set out in the “Tunnel Head House Design Guide”. in terms of determining internal heights, placement of single and double storey areas, minimum likely footprint dimensions, minimum Hence the Tunnel Head House Design Guide as well as the height requirements etc. There is often limited design flexibility due Parameters Plans combine to establish and impose the key design to the fact that functional requirements of the complex infrastructure principles for the proposed tunnel head houses. that these tunnel head houses enclose are often determined by mechanical and safety specifications. However, the Design Guide presents design approaches that take into account these restrictive functional design requirements but balances them with the contextual setting and local sensitivities. The key aim is to balance the functional requirements against the need to limit apparent scale of the buildings in rural, generally undeveloped, locations.
National Grid is not able to submit a detailed fixed design for the tunnel head houses at this stage. This is because a final contractor has not been appointed at this early design stage. Hence, there is a need to retain flexibility to accommodate design innovation and allow a range of design solutions to be put forward, ensuring high quality,
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 8
1.4 DESIGN CONTEXT
EN-1 EN-5
Section 4.5 of Overarching National Policy Statement for Energy (EN-1) sets out the Section 2.5 of National Policy Statement for Electricity Networks Infrastructure (EN-5) states criteria for “good design” for energy infrastructure, whilst recognising the importance of the that proposals for electricity networks infrastructure should demonstrate good design in their functional requirements and physical constraints which apply to infrastructure projects of this approach to mitigating the potential adverse impacts which can be associated with overhead nature. lines, particularly those relating to: • landscape and visual; EN-1 states that applying “good design” to energy projects should produce sustainable • biodiversity and geological conservation; infrastructure that is sensitive to place, efficient in the use of natural resources and energy • noise and vibration; and used in it’s construction and operation, matched by an appearance that demonstrates good aesthetic as far as possible. EN-1 acknowledges, however that the nature of much • electric magnetic fields (EMFs). energy infrastructure development will often limit the extent to which it can contribute to the enhancement of the quality of the area. EN-5 paragraph 2.8.2 states that new substations, sealing end compounds and other above ground installations that form connection, switching and voltage transformation points on the electricity networks can also give rise to landscape and visual impacts. In considering applications, EN-1 states that the Secretary of State should take into account In accordance with EN-5 paragraph 2.8.10 this Design Guide sets out the opportunities for the ultimate purpose of the infrastructure and bear in mind the operational, safety and mitigating potential adverse landscape and visual impacts. security requirements that the design has to satisfy.
EN-5 paragraph 2.8.11 identifies specific measures that might be used. This Design Guide explains how the Proposed Development has taken into account functionality (including fitness for purpose and sustainability) and aesthetics (including This Design Guide identifies site-specific mitigation comprising peripheral planting and contribution to the local context and quality of the area) in the design approach to the tunnel sensitive re-profiling of landforms in views into the THHs and Pentir substation in order to help head houses. screen or soften the visual effects of the sites. It also provides built form massing and design options that show design responses to limit potential effects on views.
This Design Guide explains the studies, principles and design approaches that have influenced the siting, building design (including form, colour and materials), and landscape design approach for the tunnel head houses to ensure they respond to the site context and are attractive, durable and adaptable. This has included consideration of existing landscape character, landform and vegetation in order to help mitigate adverse impacts and other effects.
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 9
DOCUMENT 7.16
Design and Access Statement
National Grid (North Wales Connection Project)
Regulation 5(2)(q) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
Application Reference EN020015 September 2018
National Grid’s Substation Siting Guidelines The North Wales Connection Project Design and Access Statement
The Substation Siting Guidelines set out National Grid’s approach to substation siting and Section 3 of the Design and Access Statement (DAS, Document 7.16) considers the policy context design in the context of National Grid’s duties under Schedule 9 of the Electricity Act to have for the consideration of design issues, focusing on EN-1 and EN-5. regard to amenity considerations. Substation Siting Guidelines were applied in determining the location of proposed site-specific infrastructure comprising substation and CSE Local Planning Policy compounds and aim to: The Joint Local Development Plan (JLDP) for Anglesey and Gwynedd was adopted in July 2017 • limit environmental effects; (Ref 19) and is the planning policy document for Anglesey and Gwynedd (excluding that area • seek to avoid internationally and nationally designated areas of the highest value; within the Snowdonia National Park Planning Authority). It contains the key policies and land use • protect areas of local amenity value, important existing habitats and landscape features; allocations that will facilitate the Plan area’s development up to 2026. • take advantage of screening provided by landform and existing features and utilise site layout and levels to minimise intrusion into surrounding areas; As set out in NPS EN-1 (para 4.1.5), Local Development Plans are one of the matters which the • consider land-use effects of the proposal when planning siting; decision-maker may consider to be important and relevant. • consider options available for terminal pylons, equipment, buildings and ancillary development appropriate to individual locations, seeking to keep effects to a reasonably The Proposed Development has therefore also been considered against JLDP for Anglesey and practical minimum; Gwynedd (2017) (Ref 19). The compliance of the Proposed Development as a whole with relevant • use space effectively to limit the development area and provide appropriate mitigation to planning policy is considered in the Planning Statement (Document 7.14). minimise adverse effects on land use and rights of way; • ensure the design of an access road, perimeter fencing, earthworks, planting and The development plan policies do not provide criteria for determining the acceptability of ancillary development forms an integral part of the site layout and design to fit in with the NSIPs, and in their detail they are not always directly applicable to linear infrastructure projects. surroundings; Notwithstanding this the overarching principles of responding to place, minimising adverse impacts • keep high voltage line entries visually separate from low voltage lines and other overhead and enhancing the local environment have been objectives for the Proposed Development. lines to avoid a confusing appearance; and • ensure the inter-relationship between pylons and substation structures and background and foreground features are studied to reduce the prominence of structures from main viewpoints.
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 10
1.5 INITIAL STAKEHOLDER ENGAGEMENT At the initial stakeholder engagement meeting National Grid The examples in the adjoining photos are drawn from existing National Grid substation and tunnel sites in the case of the ‘Standard presented three suggested design approaches for the tunnel Industrial’ and ‘Architectural Statement’ examples. These photos seek to illustrate how the first two design approaches are significantly head house structures: different from the ‘Rural Architecture’ approach that aims to reflect the local rural vernacular in the vicinity of the two sites in North Wales to • Standard Industrial approach; draw design inspiration for the tunnel head houses designs in either site based on their distinct local characteristics. • Architectural Statement; and • Rural Architecture Approach.
The general consensus from discussions with officers working for both local authorities was that the Rural Architecture style would be more appropriate in the given contexts of both the Braint and Tŷ Fodol sites. However, it was suggested that they have distinctly different landscape and characteristics, which need to be considered in the design development. Some key differences include: • the Braint landscape character is considered as being more planned and is heavily influenced by the estate architecture found in the surrounding context; and • the Tŷ Fodol context is characterised by individual farmsteads, with a more diverse range of agricultural built form, that have extended gradually over time. Further characteristics of these two sites have been explored in ensuing sections of this report. National Grid Standard Industrial approach National Grid Architectural Statement
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 11
Examples of local agricultural buildings that has influenced the RuralArchitecture Approach
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 12
THE NATIONAL GRID (NORTH WALES CONNECTION PROJECT) ORDER GORCHYMYN NATIONAL GRID (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) DESIGN PLAN: PARAMETER PLAN FOR BRAINT TUNNEL HEAD HOUSE AND CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF DŶ TWNNEL AFON BRAINT 2.0 Braint Tunnel Headhouse and CSEC CABLE SEALING END COMPOUND A'R COMPOWND SY'N SELIO PENNAU CEBLAU REGULATION 5(2)(o) RHEOLIAD 5(2)(o) SHEET 1 OF 8 DALEN 1 O 8 2.1 INTRODUCTION ISLE OF ANGLESEY COUNTY COUNCIL CYNGOR SIR YNYS MÔN ANGLESEY
The Braint site is located within pasture land in order to understand the local vernacular GWYNEDD between properties known as Rhosbothan (500 m), architecture and landscape further; Llwyn-ogan (200 m) and Tyddyn Fadog (340 m). • it was agreed that although the area is Legend / Allwedd
TEMPORARY CONSTRUCTION The general local character of the area is rural influenced by estate style architecture, COMPOUND AREA INDICATIVE AREA WITHIN WHICH POSSIBLE LANDSCAPING / MITIGATION pasture land with agricultural plots bordered by this shouldn’t be slavishly replicated for WILL TAKE PLACE
ZONE WITHIN WHICH FULL small blocks of woodland, spinneys and coverts the operational compound, but it is a good LINE TENSION GANTRIES AND CABLE SEALING END WILL BE LOCATED
associated with the local estates. design cue that needs to be developed in a ZONE WITHIN WHICH TUNNEL HEAD HOUSE WILL BE contemporary manner; LOCATED ZONE WITHIN WHICH PERMANENT ACCESS ROAD Initial Stakeholder Engagement • the Braint site is visible from a number of WILL BE LOCATED AREA WITHIN WHICH TUNNEL HEAD HOUSE AND CABLE viewpoints, hence careful consideration should SEALING END COMPOUND Some of the key themes that emerged from the WILL BE LOCATED
ILLUSTRATIVE SIZE OF THE be given to views to and from Bryn Celli Ddu TUNNEL HEAD HOUSE AND initial stakeholder engagement with the officers CABLE SEALING END Schedule Monument, the community of Star and COMPOUND from Isle of Anglesey County Council were as ILLUSTRATIVE LOCATION OF THE TUNNEL HEAD HOUSE (MAXIMUM DIMENSIONS A4080; MEASURED EXTERNALLY follows: (H) 8m VOLUME 4,350m³)
ILLUSTRATIVE ROUTE OF • the site is visible from the community of Star, PERMANENT ACCESS ROAD • there was a general preference within the three THE NATIONAL GRID (NORTH WALES CONNECTION PROJECT) ORDER GORCHYMYN NATIONAL GRID (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) 1. This drawing is scaled at paper size A1, therefore any prints taken at DESIGN PLAN: PARAMETER PLAN FOR BRAINT TUNNEL HEAD HOUSE AND CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF DŶ TWNNEL AFON BRAINT smaller sizes will affect accuracy of the measurement units and should not against a background of existing land form; be scaled against. THE NATIONAL GRIDCABLE (NORTH SEALING WALES END CONNECTION COMPOUND PROJECT) ORDER GORCHYMYN NATIONALA'R COMPOWND GRID (PROSIECT SY'N SELIO CYSYLLTIAD PENNAU CEBLAU GOGLEDD CYMRU) suggested design approaches for the building DESIGN PLAN: PARAMETERREGULATION PLAN FOR BRAINT 5(2)(o) TUNNEL HEAD HOUSE AND CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDRRHEOLIAD AR5(2)(o) GYFER PRIF DŶ TWNNEL AFON BRAINT CABLE SEALINGSHEET END 1 OF COMPOUND 8 A'R COMPOWND DALENSY'N SELIO 1 O 8 PENNAU CEBLAU • a stark,ISLE OF ANGLESEYREGULATION modern COUNTY 5(2)(o) COUNCIL design approach would be CYNGORRHEOLIAD SIR YNYS 5(2)(o) MÔN 0 30 60 Metres design to be reflective of rural architectural SHEET 1 OF 8 DALEN 1 O 8 unlikelyISLE OF ANGLESEY to COUNTY be COUNCIL appropriate in this area. A low- CYNGOR SIR YNYS MÔN ANGLESEY character, but with due regard to the estate style ANGLESEY architecture and character found in this part key built form with natural materials that might
more comfortably be accommodated within the A FOR DCO SUBMISSION KJ SR RP of Anglesey. The preference was for a design GWYNEDD
GWYNEDD landscape might be more appropriate; THE NATIONAL GRID approach that doesn’t stand out, but pays due (NORTH WALES CONNECTION PROJECT) ORDER DESIGN PLAN: PARAMETER PLAN FOR BRAINT TUNNEL HEAD HOUSE AND CABLE SEALING END COMPOUND REGULATION 5(2)(o) regard to the existing, and often different styles • in terms of building materials, it was suggested SHEET 1 OF 8 Legend / Allwedd ISLE OF ANGLESEY COUNTY COUNCIL
THE NATIONAL GRID (NORTH WALES CONNECTION PROJECT) ORDER GORCHYMYN NATIONAL GRID (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) GORCHYMYN NATIONAL GRID Legend / AllweddTEMPORARY CONSTRUCTION (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) evident in the localDESIGNTHE NATIONAL PLAN:vernacular PARAMETER GRID (NORTH PLAN WALES FOR BRAINT CONNECTIONwhich TUNNEL PROJECT) HEAD are HOUSE ORDER ANDheavily thatCYNLLUN stoneGORCHYMYN DYLUNIO: shouldCYNLLUN NATIONAL O'R GRID PARAMEDR (PROSIECT be AR CYSYLLTIADconsideredGYFER PRIF GOGLEDDDŶ TWNNEL CYMRU) AFON BRAINTbut rendered CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF COMPOUND AREA CABLE SEALING END COMPOUND A'R COMPOWND SY'N SELIO PENNAU CEBLAU DŶ TWNNEL AFON BRAINT A'R COMPOWND SY'N SELIO DESIGNTHE NATIONAL PLAN: PARAMETER GRID (NORTH PLAN WALES FOR BRAINT CONNECTION TUNNEL PROJECT) HEAD HOUSE ORDER AND CYNLLUNGORCHYMYN DYLUNIO: CYNLLUN NATIONAL O'R GRID PARAMEDR (PROSIECT AR CYSYLLTIADGYFER PRIF GOGLEDDDŶ TWNNEL CYMRU) AFON BRAINT PENNAU CEBLAU CABLE REGULATIONSEALING END 5(2)(o) COMPOUND A'R COMPOWNDRHEOLIAD SY'N SELIO 5(2)(o) PENNAU CEBLAU TEMPORARY CONSTRUCTION RHEOLIAD 5(2)(o) DESIGN PLAN: PARAMETER PLAN FOR BRAINT TUNNEL HEAD HOUSE AND CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF DŶ TWNNEL AFON BRAINT INDICATIVECOMPOUND AREA AREA WITHIN DALEN 1 O 8 REGULATIONSHEET 1 OF 5(2)(o) 8 DALEN 1 O 8 WHICH POSSIBLE CYNGOR SIR YNYS MÔN influenced by the estateCABLE architectureSEALING END COMPOUND found at finishes wereA'R COMPOWND unlikelyRHEOLIAD SY'N SELIO 5(2)(o) PENNAU to CEBLAU be appropriate. ISLE OF ANGLESEYSHEET 1COUNTY OF 8 COUNCIL LANDSCAPING / MITIGATION REGULATION 5(2)(o) CYNGORRHEOLIADDALEN SIR 1YNYS 5(2)(o)O 8 MÔN INDICATIVEWILL TAKE PLACE AREA WITHIN ISLE OF ANGLESEYSHEET 1COUNTY OF 8 COUNCIL CYNGOR SIR YNYS MÔN WHICH POSSIBLE DALEN 1 O 8 ANGLESEY LANDSCAPING / MITIGATION the Plas Newydd and PlasISLE OF ANGLESEY Coch COUNTY COUNCILestates; Similarly, CortenCYNGOR steel SIR YNYS MÔN was not considered ZONEWILL TAKE WITHIN PLACE WHICH FULL Application Number / Rhif y Cais ANGLESEY LINE TENSION GANTRIES EN020015 AND CABLE SEALING END N National Grid Drawing Reference / Cyfeirnod Lluniad National Grid ANGLESEY ZONE WITHIN WHICH FULL WILL BE LOCATED DCO_DE/PS/09_01 appropriate; LINE TENSION GANTRIES • whilst it has been suggested that cues might AND CABLE SEALING END ZONEWILL BE WITHIN LOCATED WHICH TUNNEL 1:1000 A1 SHEET 1 OF 8 A HEAD HOUSE WILL BE LOCATED be taken from Horizon Nuclear Power’s • more traditional roof forms would be better Braint Tunnel Headhouse and CSEC Outline PlanZONE WITHIN for WHICH DCOTUNNEL application Contains Ordnance Survey data © HEAD HOUSE WILL BE GWYNEDD LOCATED ZONE WITHIN WHICH GWYNEDD PERMANENT ACCESS ROAD Crown copyright and database right design approach to the buildings on the Wylfa suited in this locality rather than wavy or organic WILL BE LOCATED GWYNEDD ZONE WITHIN WHICH PERMANENT ACCESS ROAD 100024241(2018) WILL BE LOCATED Newydd site, it is considered that the lack of roof forms; AREA WITHIN WHICH TUNNEL HEAD HOUSE AND CABLE LEGEND SEALING END COMPOUND Legend / Allwedd WILLAREA BE WITHIN LOCATED WHICH TUNNEL HEAD HOUSE AND CABLE any visual relationship between the two sites Legend / Allwedd SEALING END COMPOUND • extensive mounding would be alien to ILLUSTRATIVEWILL BE LOCATED SIZE OF THE Legend / AllweddTEMPORARY CONSTRUCTION TUNNEL HEAD HOUSE AND COMPOUNDTemporary AREA construction compound area CABLE SEALING END TEMPORARY CONSTRUCTION Illustrative size of the tunnel head house ILLUSTRATIVECOMPOUND SIZE OF THE COMPOUND AREA (given the intervening distance) and their TUNNELand HEAD cable HOUSE AND sealing end compound INDICATIVETEMPORARY AREA CONSTRUCTION WITHIN this landscape and would very likely be CABLE SEALING END COMPOUNDWHICH POSSIBLE AREA Indicative area within which possible COMPOUND INDICATIVELANDSCAPING AREA / MITIGATION WITHIN ILLUSTRATIVE LOCATION OF WHICH POSSIBLE WILL TAKE PLACE THE TUNNEL HEAD HOUSE INDICATIVE AREA WITHIN differing landscape characters would make this LANDSCAPINGLandscaping / MITIGATION / Mitigation would take place (MAXIMUMIllustrative DIMENSIONS location of the tunnel head WILLWHICH TAKE POSSIBLE PLACE inappropriate; ILLUSTRATIVEMEASURED EXTERNALLY LOCATION OF LANDSCAPING / MITIGATION ZONE WITHIN WHICH FULL (H)THE 8m TUNNEL VOLUME HEAD 4,350m³) HOUSE WILL TAKE PLACE house (Maximum dimensions measured LINE TENSION GANTRIES (MAXIMUM DIMENSIONS ZONEAND CABLE WITHIN SEALING WHICH FULLEND inappropriate; LINEZone TENSION GANTRIESwithin which full Line tension MEASUREDexternally EXTERNALLY (H) 8 m volume 4,350 m³) WILL BE LOCATED (H) 8m VOLUME 4,350m³) ZONEAND CABLE WITHIN SEALING WHICH FULLEND ILLUSTRATIVE ROUTE OF • the access design should not overuse tarmac LINEWILLgantries TENSIONBE LOCATED GANTRIES and cable sealing end would PERMANENT ACCESS ROAD AND CABLE SEALING END ZONE WITHIN WHICH TUNNEL WILL BE LOCATED HEADbe HOUSE located WILL BE ILLUSTRATIVE ROUTE OF ZONE WITHIN WHICH TUNNEL PERMANENTIllustrative ACCESS ROAD route of permanent • the landscape in this part of Anglesey differs LOCATED 1. This drawing is scaled at paper size A1, therefore any prints taken at HEAD HOUSE WILL BE or other visually stark materials in this rural smaller sizes will affect accuracy of the measurement units and should not LOCATEDZONE WITHIN WHICH TUNNEL be scaled against. access road HEADZone HOUSE WILL within BE which tunnel Head house LOCATED 1. This drawing is scaled at paper size A1, therefore any prints taken at ZONE WITHIN WHICH smaller sizes will affect accuracy of the measurement units and should not greatly from that in Gwynedd, in that the would be located be scaled against. environment. A mosaic of different materials and PERMANENT ACCESS ROAD WILLZONE BE WITHIN LOCATED WHICH PERMANENT ACCESS ROAD 0 30 60 WILLZONEZone BE WITHIN LOCATED WHICH within which permanent access Metres landscape is significantly more planned and PERMANENT ACCESS ROAD surfaces, reinforced grass or coloured aggregate AREAWILL BE WITHIN LOCATED WHICH TUNNEL 0 30 60 road would be located Metres HEAD HOUSE AND CABLE SEALINGAREA WITHIN END WHICHCOMPOUND TUNNEL HEADWILL BE HOUSE LOCATED AND CABLE is based around and heavily influenced by SEALINGAREA WITHIN END WHICHCOMPOUND TUNNEL with complementary landscape treatments to HEADWILLArea BE HOUSE LOCATED ANDwithin CABLE which tunnel head house ILLUSTRATIVESEALING END COMPOUNDSIZE OF THE TUNNELWILLand BE LOCATEDHEAD cable HOUSE AND sealing end compound would ILLUSTRATIVECABLE SEALING SIZE END OF THE estate architecture and therefore the building TUNNEL HEAD HOUSE AND COMPOUND screen access routes should be considered; and ILLUSTRATIVEbe located SIZE OF THE CABLE SEALING END COMPOUNDTUNNEL HEAD HOUSE AND CABLE SEALING END A FOR DCO SUBMISSION KJ SR RP form, materials and colour palette for the Braint ILLUSTRATIVECOMPOUND LOCATION OF THE TUNNEL HEAD HOUSE • local geology and earth colours to be considered ILLUSTRATIVE(MAXIMUM DIMENSIONS LOCATION OF A FOR DCO SUBMISSION KJ SR RP MEASUREDTHE TUNNEL EXTERNALLY HEAD HOUSE THE NATIONAL GRID ILLUSTRATIVE LOCATION OF (H)(MAXIMUM 8m VOLUME DIMENSIONS 4,350m³) (NORTH WALES CONNECTION PROJECT) ORDER operational compound should be different to the MEASUREDTHE TUNNEL EXTERNALLY HEAD HOUSE DESIGN PLAN: PARAMETER PLAN FOR BRAINT TUNNEL HEAD HOUSE AND (H)(MAXIMUM 8m VOLUME DIMENSIONS 4,350m³) THE NATIONAL GRID CABLE SEALING END COMPOUND but existing built forms, both historic and MEASURED EXTERNALLY (NORTH WALES CONNECTION PROJECT) ORDER REGULATION 5(2)(o) ILLUSTRATIVE ROUTE OF DESIGN PLAN: PARAMETER PLAN (H) 8m VOLUME 4,350m³) SHEET 1 OF 8 FOR BRAINT TUNNEL HEAD HOUSE AND PERMANENT ACCESS ROAD ISLE OF ANGLESEY COUNTY COUNCIL Tŷ Fodol operational compound; ILLUSTRATIVE ROUTE OF CABLE SEALING END COMPOUND PERMANENT ACCESS ROAD REGULATION 5(2)(o) SHEET 1 OF 8 new, were often imported and hence do not ILLUSTRATIVE ROUTE OF GORCHYMYN NATIONAL GRID ISLE OF ANGLESEY COUNTY COUNCIL 1. This drawing is scaled at paperPERMANENT size A1, therefore ACCESSany prints taken ROAD at (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) smaller sizes will affect accuracy of the measurement units and should not CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF be scaled against. 1. This drawing is scaled at paper size A1, therefore any prints taken at DŶ TWNNEL AFON BRAINT A'R COMPOWND SY'N SELIO GORCHYMYN NATIONAL GRID • a Local Characterisation study was suggested smaller sizes will affect accuracy of the measurement units and should not PENNAU CEBLAU be scaled against. (PROSIECT CYSYLLTIAD GOGLEDD CYMRU) necessarily reflect the local geology. 1. This drawing is scaled at paper size A1, therefore any prints taken at RHEOLIAD 5(2)(o) CYNLLUN DYLUNIO: CYNLLUN O'R PARAMEDR AR GYFER PRIF smaller sizes will affect accuracy of the measurement units and should not DALEN 1 O 8 DŶ TWNNEL AFON BRAINT A'R COMPOWND SY'N SELIO be scaled against. CYNGOR SIR YNYS MÔN PENNAU CEBLAU 0 30 60 RHEOLIAD 5(2)(o) Metres DALEN 1 O 8 0 30 60 CYNGOR SIR YNYS MÔN Metres 0 30 60 Application Number / Rhif y Cais Metres EN020015
National Grid Drawing Reference / Cyfeirnod Lluniad National Grid Application Number / Rhif y Cais DCO_DE/PS/09_01 EN020015
National Grid Drawing Reference / Cyfeirnod Lluniad National Grid 1:1000 A1DCO_DE/PS/09_01SHEET 1 OF 8 A
1:1000 A1 SHEET 1 OF 8 A
A FOR DCO SUBMISSION KJ SR RP
A FOR DCO SUBMISSION KJ SR RP
A FOR DCO SUBMISSION KJ SR RP THE NATIONAL GRID (NORTH WALES CONNECTION PROJECT) ORDER North Wales Connection Project DESIGNTHE PLAN: NATIONAL PARAMETER GRID PLAN (NORTHFOR WALES BRAINT CONNECTION TUNNEL HEAD PROJECT) HOUSE AND ORDER CABLEDESIGNTHE SEALING PLAN: NATIONAL PARAMETER END COMPOUNDGRID PLAN (NORTHFOR WALES BRAINTREGULATION CONNECTION TUNNEL HEAD 5(2)(o) PROJECT) HOUSE AND ORDER CABLEDESIGN SEALING PLAN:SHEET PARAMETER END 1 OF COMPOUND 8 PLAN FORISLE BRAINT OF ANGLESEYREGULATION TUNNEL COUNTY HEAD 5(2)(o) HOUSE COUNCIL AND CABLE SEALINGSHEET END 1 OF COMPOUND 8 ISLE OF ANGLESEYREGULATION COUNTY 5(2)(o) COUNCIL GORCHYMYNSHEET NATIONAL 1 OF 8 GRID (PROSIECTISLE OF ANGLESEY CYSYLLTIAD COUNTY GOGLEDD COUNCIL CYMRU) CYNLLUN DYLUNIO:GORCHYMYN CYNLLUN NATIONALO'R PARAMEDR GRID AR GYFER PRIF DŶ TWNNEL(PROSIECT AFON CYSYLLTIAD BRAINT A'R GOGLEDDCOMPOWND CYMRU) SY'N SELIO CYNLLUN DYLUNIO:GORCHYMYN CYNLLUNPENNAU NATIONALO'R CEBLAU PARAMEDR GRID AR GYFER PRIF DŶ TWNNEL(PROSIECT AFON CYSYLLTIAD BRAINTRHEOLIAD A'R 5(2)(o)GOGLEDDCOMPOWND CYMRU) SY'N SELIO CYNLLUN DYLUNIO: CYNLLUNPENNAUDALEN O'R CEBLAU 1 OPARAMEDR 8 AR GYFER PRIF DŶ TWNNEL AFONCYNGOR BRAINTRHEOLIAD SIR A'R YNYS 5(2)(o) COMPOWND MÔN SY'N SELIO PENNAUDALEN CEBLAU 1 O 8 CYNGORRHEOLIAD SIR YNYS 5(2)(o) MÔN DALEN 1 O 8 CYNGOR SIR YNYS MÔN Application Number / Rhif y Cais EN020015 Application Number / Rhif y Cais National Grid Drawing ReferenceEN020015 / Cyfeirnod Lluniad National Grid Application Number / Rhif y CaisDCO_DE/PS/09_01 National Grid Drawing Reference / Cyfeirnod Lluniad National Grid EN020015 DCO_DE/PS/09_01 National1:1000 Grid Drawing ReferenceA1 / CyfeirnodSHEET Lluniad 1 OF 8National GridA DCO_DE/PS/09_01 1:1000 A1 SHEET 1 OF 8 A
1:1000 A1 SHEET 1 OF 8 A Tunnel Head House Design Guide Document 7.19 13
2.2 REGIONAL CONTEXT
Anglesey
Wales
Anglesey is the largest of the Welsh islands, covering some 720 square kilometres and separated from the mainland by the Menai Strait; a narrow stretch of tidal water approximately 25 km long and about 250 metres wide at its narrowest. The main towns on the island are Llangefni, Holyhead, Amlwch, Benllech, Menai Bridge and Llanfairpwll.
The topography of the island is generally subdued with a rolling, undulating pattern interspersed by harder, rocky outcrops such as Holy Island, Mynydd Parys, Mynydd Bodafon and Mynydd Llwydiarth. The landform generally falls east to west, with a number of low lying areas along the west coast including Aberffraw, Malltraeth Marsh and Newborough Warren. This landform pattern is reflected in the north-east – south-west alignment of water courses. This general character belies a complex, underlying geology and effects of geomorphological processes such as glaciation. The island contains some of the oldest rocks in Wales and Britain as a whole, and these are clearly illustrated in the topography of the island.
In broad terms, inland Anglesey can be described as lowland farmland with relatively sparse tree cover in the north, where there is a more open, rolling and windswept character, which becomes increasingly well treed towards the south; in particular towards the Menai Strait. There are a number of fens and extensive areas of drumlins, especially in the north and west and parkland landscapes are found to the south and east. The island’s rural coastline has been designated an Area of Outstanding Natural Beauty and features many sandy beaches, especially along its eastern and western coast. The northern coastline has dramatic cliffs interspersed with small bays and the southern coast is focussed on the Menai Strait. The Jim Linwood, Flickr Anglesey Coastal Path (which forms part of the Wales Coast Path) is a 200 km path, The Menai Bridge which follows nearly the entire coastline.
North Wales Connection Project Tunnel Head House Design Guide Document 7.19 14
2.3 STRATEGIC LANDSCAPE CONTEXT Le end Le end 1 / Head House raint nglese 1 / Head House raint nglese Braint site, Anglesey N tion L nd c e C r cter Are N tion L nd c e C r cter Are 1 r ordir n nglese Coast N 1 r ordir n nglese Coast 5km 1 Canol arth dn Central nglese 1 Canol arth dn Central nglese r on r on