SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021

1. AUTOSTRĂZI

1.1. AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020. A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN ANUL 2022 6 LUNI - ETAPA DE 14.09.2020 - EMITERE ORDIN DE MARTIE 2022 (CONFORM SANTIER ANTREPRENORULUI. AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – DRUMURI BIHOR SECTIUNEA 3C, SUBSECTIUNEA 3C2 SUBSECTIUNEA 3C2: CHIRIBIS - PROIECTARE; 18 LUNI - ETAPA DE 1 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 30+550 59+100 28.55 0.50% 0% INCEPERE PENTRU ETAPA DE CONTRACT) 326.51 MIL. LEI FARA TVA DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE: ORADEA SA – DRUM ASFALT SRL – EAST WATER DRILLINGS SRL CHIRIBIS - BIHARIA BIHARIA EXECUTIE LUCRARI; 120 LUNI - PROIECTARE (PROIECT TEHNIC) IUNIE 2022 (CONFORM PROGRAM) 6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020. PERIOADA DE GARANTIE 18 LUNI - ETAPA DE EXECUTIE LUCRARI 120 LUNI - PERIOADA DE GARANTIE

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE: SECTIUNEA 3A SI SECTIUNEA 3B, SUBSECTIUNEA 3A2 NADASELU - • 12 LUNI PERIOADA DE PROIECTARE, AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – SUBSECTIUNEA 3A2: NADASELU - MIHAIESTI KM 8+700 - 25+500+ 2 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 8+700 38+760 30.06 0% 0% 25.01.2021 2023 ANUL 2023 1.390,614 MIL. LEI FARA TVA • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, ORADEA S.C. ELECTROMONTAJ S.A MIHAIESTI SI 3B1: MIHAESTI 3B1, MIHAIESTI – ZIMBOR KM 0+000 - • 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. ZIMBOR 13+260 AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE2021. PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3A2 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: IULIE 2021 PENTRU SECTORUL 3B1 - AVIZARE DTAC SI OBTINERE AUTORIZATIE DE CONSTRUIRE : IUNIE 2021

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020; 6 LUNI PERIOADA DE PROIECTARE ; 18 LUNI PERIOADA DE EXECUTIE AUTOSTRADA BRASOV - TARGU MURES - CLUJ - SECTIUNEA 3B, SUBSECTIUNEA 3B5 SUBSECTIUNEA 3B5: NUSFALAU - 3 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 66+500 80+054 NUROL INSAAT VE TICARET S.A 13.55 0% 15% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023 384.14 MIL. LEI FARA TVA ; 120 LUNI PERIOADA DE GARANTIE ORADEA NUSFALAU - SUPLACU DE BARCAU SUPLACU DE BARCAU LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500 FINALIZARE ETAPA PROIECTARE (PTE) - IULIE 2021

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020; DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ASOCIEREA SC SA&PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC SECTIUNEA 3B, SUBSECTIUNEA 3B2: SUBSECTIUNEA 3B2: ZIMBOR - 4 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 13+260 25+500 12.24 0% 0% 31.05.2021 - ORDIN DE INCEPERE 2023 ANUL 2023 680.40 MIL. LEI FARA TVA 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, ORADEA TEHNOSTRADE SRL ZIMBOR - POARTA SALAJULUI POARTA SALAJULUI 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS IN DATA DE 10.08.2020 A FOST SUSPENDAT PANA LA EMITEREA HG PENTRU DECLANSAREA PROCEDURII DE EXPROPRIERE

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020. 2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR. LOT 1 - TARGU MURES - UNGHENI 2022 (CONFORM CONTRACT) 3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA: AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORDIN DE INCEPERE PENTRU 5 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA (4.5 KM) + DRUM DE LEGATURA (4.7 9.2 57.40% 42.45% 2021 - CONFORM ESTIMARE ANUL 2022 192.06 MIL. LEI FARA TVA 18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR; ORADEA EXECUTIE - 22 IULIE 2020 KM) ANTREPRENOR/ CNAIR SA 108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR; LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA.

IN DATA DE 11.03.2021 S-A TRANSMIS ANTREPRENORULUI INSTIINTAREA DE REZILIERE A CONTRACTULUI. PROCEDURA DE REZILIERE A FOST SUSPENDATA IN URMA DECIZIEI TRIBUNALULUI BUCURESTI. DUPĂ DECIZIA INSTANȚEI PRIVIND REZILIEREA, PROCEDURA VA FI RELUATĂ URMÂND SĂ FIE PARCURSE URMĂTOARELE ETAPE: - FINALIZARE CAIET DE SARCINI, REFERAT DE NECESITATE SI TRANSMITERE LA DIRECTIA ACHIZITII PUBLICE; 18.09.2020 - NOD CHETANI (1.3 KM) - - FINALIZARE DOCUMENTATIE DE ATRIBUIRE (CRITERII DE CALIFICARE, MODEL CONTRACT, FACTORI EVALUARE); DESCHIDEREA TRAFICULUI AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ASOCIEREA SC STRACO GRUP SRL & SPECIALIST CONSULTING SRL & TRONSON OGRA - CAMPIA TURZII - TRANSMITERE DOCUMENTATIE DE ATRIBUIRE SPRE VALIDARE LA ANAP; 6 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 21+500 37+191 LOT 3 15.691 37.86% 41.97% 04.05.2016 2021 - INTARZIERI MAJORE ALE REZILIAT 279.74 MIL. LEI FARA TVA ORADEA SC TOTAL ROAD SRL (2A3 CHETANI - CAMPIA TURZII) PUBLICARE ANUNT DE PARTICIPARE IN SICAP; CONTRACTULUI DE PROIECTARE SI - DEPUNERE OFERTE; EXECUTIE - CONTRACT REZILIAT - ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR; - COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA; CONTESTATII; - SEMNARE CONTRACT.

2023 DURATA CONTRACTULUI ESTE DE 90 LUNI SI CUPRINDE 12 LUNI AUTOSTRADA DE CENTURA A MUNICIPIULUI ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION UMB PERIOADA DE PROIECTARE, 18 LUNI CONTRACT SEMNAT IN DATA DE 31.08.2020. 7 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 47+600 52+070 SECTOR NORD LOT 4 4.47 0% 0% 31.08.2020 ESTIMAT 2023 312.63 MIL. LEI FARA TVA BUCURESTI (A0) S.R.L. - S.C. TEHNOSTRADE S.R.L. PERIOADA DE EXECUTIE A ESTIMAT EMITERE ORDIN DE INCEPERE A ETAPEI DE PROIECTARE (ELABORARE PROIECT TEHNIC) - TRIM. IV 2021 LUCRARILOR SI 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL ""PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA. AUTOSTRADA DE CENTURA A MUNICIPIULUI ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - LUNGIME: 19 KM 8 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 20+000 39+000 SECTOR NORD LOT 2 19 0% 0% 2021 2024 831.92 MIL. LEI FARA TVA BUCURESTI (A0) SPEDITION UMB - TEHNOSTRADE S.R.L. SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR 120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR

ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700 DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020 10.04.2019 - ORDIN DE INCEPERE A A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR) 22.78% - PROGRES FINANCIAR AUTOSTRADA DE CENTURA A MUNICIPIULUI ACTIVITATII DE PROIECTARE ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE 9 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 69+000 85+300 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 17.36% (INCLUSIV AVANS LUCRARI SI FEBRUARIE 2023 FEBRUARIE 2023 750.85 MIL. LEI FARA TVA BUCURESTI (A0) 18.08.2020 - ORDIN INCEPERE FIIND 05.11.2020 (14,6 KM) ACTUALIZARI PRETURI) LUCRARI KM 69+000 - KM 70+700 A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021. IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE

SECTOR NORD - KM 52+070 – KM A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020 AUTOSTRADA DE CENTURA A MUNICIPIULUI 19.73% - PROGRES FINANCIAR 03.10.2019 - DATA DE INCEPERE A 10 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. 52+770; SECTOR SUD - KM 52+770 – LOT 1: GLINA - VIDRA 16.93 3.69% IUNIE 2023 ANUL 2023 830.68 MIL. LEI FARA TVA A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021. BUCURESTI (A0) (INCLUSIV AVANS LUCRARI) ACTIVITATII DE PROIECTARE KM 69+000 ORDIN DE INCEPERE LUCRARI 01.03.2021

IN PREZENT ANTREPRENORUL A REUSIT SA FINALIZEZE DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE SECTOR SUD - KM 85+300 - KM PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE AUTOSTRADA DE CENTURA A MUNICIPIULUI 85+300 - 0+000 - 2+500 ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - 1,03% (PROGRES FINANCIAR 23.05.2019 - DATA DE INCEPERE A 11 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 100+765; SECTOR NORD - KM 0+000 LOT 3: BRAGADIRU - JOITA 17.965 0.00% DECEMBRIE 2022 DECEMBRIE 2022 853.42 MIL. LEI FARA TVA PROIECTARE). BUCURESTI (A0) 100+765 SUD NORD S.C. EURO CONSTRUCT TRADING 98 S.R.L. INCLUSIV AVANS PROIECTARE) ACTIVITATII DE PROIECTARE + KM 2+500 PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021. LA DATA PREZENTEI, ANTREPRENORUL ELABOREAZA PTE.

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, APRILIE 2022 - CONFORM GRAFIC DE DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI; ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - ESTIMARE DESCHIDERE TRAFIC - 12 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 17+000 41+250 SANTIMBRU - AIUD LOT 2 24.25 85.90% 76.98% 02.12.2014 LUCRARI 549.33 MIL. LEI FARA TVA PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI S.C. EURO CONSTRUCT TRADING 98 S.R.L. NOIEMBRIE 2021 LUCRARILOR. STADIU PROCESUAL: FOND. IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300 DESCHIDERE TRAFIC (RESPECTIV 14,8 CONFORM GRAFICULUI DE LUCRARI INAINTAT DE ANTREPRENOR CONTRACTUL SE VA FINALIZA IN LUNA IUNIE 2021, DUPA FINALIZAREA LUCRARILOR A KM AUTOSTRADA, BRETELE 5,6 - NOD DESCHIDERE TRAFIC - 03.12.2020 CELOR 2.2 KM DE AUTOSTRADA, A PASAJULUI PESTE CF 201A DE LA KM 15+350 CALEA 2, NODULUI RUTIER SEBES CU 4 BRETELE RESPECTIV BRETEA ASOCIEREA IMPRESA PIZZAROTTI & C SPA POMPONIO 93.86 % (DIN VALOAREA DE RUTIER SEBES, BRETELE - 1,3 NOD 13 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 0+000 17+000 LANCRAM - SANTIMBRU LOT 1 17 96.01% 02.12.2014 FINALIZARE CONTRACT: AUGUST 541.73 MIL. LEI FARA TVA NR.1,2,3,4 SI STRUCTURI AFERENTE ACESTOR BRETELE, RESPECTIV NOD RUTIER ALBA IULIA NORD CU BRETELE 2 SI 4, AFLATE IN EXECUTIE. CONSTRUCTII SRL CONTRACT ACCEPTATA) RUTIER ALBA IULIA NORD, RESPECTIV 2021 DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, NOD RUTIER ALBA IULIA SUD IN DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500. DATA DE 03.12.2020.

22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI) 2025 IN CF CU PREVEDERILE CTR CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600- DURATA DE REALIZARE A ACESTUI KM 122+950" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM INGINERIE INTERNATIONALA S.R.L.- CTR ESTE DE 60 DE LUNI, RESPECTIV: IUNIE 2020 - EMITERE ORDIN ETAPA METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020 12 LUNI PERIODA DE PROIECTARE SI 14 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 1.34% DE PROIECTARE, AUTORIZATIA DE ANUL 2025 1710 MIL. LEI FARA TVA In data de 30.12.2020 a fost publicata Hotararea de Guvern nr.1134 pentru realizarea exproprierilor pentru suprafetele de teren aflate pe aza localităţilor 48 DE LUNI PENTRU EXECUTIA CONSTRUIRE NR.31/17.06.2021 Budeasa, Curtea de Argeș, Mălureni și Municipiul Pitești, din județul Argeș. LUCRARILOR. PERIOADA DE 17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, GARANTIE A LUCRARILOR OFERTATA MALURENI SI MUN. PITESTI DE ASTALDI SPA ESTE DE 120 DE LUNI PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020. 29.05.2019 - EMITERE ORDIN DE SECTIUNEA 1: SIBIU - BOITA (KM INCEPERE ETAPA DE PROIECTARE, AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020. 15 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170 13.17 42.45% 35.83% 28.05.2023 ANUL 2023 612.65 MIL. LEI FARA TVA 0+000 - KM 14+150), LOT 1 30.03.2020 - EMITERE ORDIN DE INCEPERE ETAPA EXECUTIE LUCRARI CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 19.10.2020

DRUM BRAILA-JIJILA - 19,095 KM; SECTIUNEA 2 DECEMBRIE 2021 POD SUSPENDAT PESTE DUNARE IN DECEMBRIE 2021 SECTIUNEA 2 16 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI DRUM NATIONAL POD BRAILA ASOCIEREA ASTALDI S.P. A - IHI INFRASTRUCTURE SYSTEM CO. LTD. 1 DRUM DE LEGATURA CU DN22 39.00% 48.66% 21.12.2018 TOTAL CONTRACT: ESTIMAT 1.996 MLD. LEI FARA TVA CONTRACT IN DERULARE. ZONA BRAILA PODUL SUSPENDAT SMARDAN-MACIN - 4,328 KM DECEMBRIE 2022

1.2. AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

http://www.cnadnr.ro/ SUBSECTIUNEA 3C1: SUPLACU DE sites/default/files/AUTO AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA BRASOV - TARGU MURES - CLUJ - SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE SECTIUNEA 3C, SUBSECTIUNEA 3C1 BARCAU - CHIRIBIS *KM 4+200 STRADA_BRA%C8%98O 1 AUTOSTRADA 4+200 30+550 26.35 0% 0% 2021 2023 ANUL 2023 465.14 MIL. LEI FARA TVA DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS LUCRARI ORADEA ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE SUPLACUL DE BARCAU - CHRIBIS COINCIDE CU KM 80+054.044 DIN V_T%C3%82RGU%20M 3B5 URE%C8%98_CLUJ_ORA DEA_CALENDAR.pdf

SECTIUNEA 3B,SUBSECTIUNEA 3B3: SUBSECTIUNEA 3B3: POARTA http://www.cnadnr.ro/ POARTA SALAJULUI - ZALAU (KM SALAJULUI - ZALAU (KM 25+500 - KM sites/default/files/AUTO 25+500- KM 40+637) + 40+637) + 3926.81 MIL. LEI FARA TVA, DIN AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA BRASOV - TARGU MURES - CLUJ - SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE STRADA_BRA%C8%98O 2 AUTOSTRADA 25+500 66+500 SUBSECTIUNEA 3B4: ZALAU - SUBSECTIUNEA 3B4: ZALAU - 41 2021 2025 ANUL 2025 CARE VALOAREA TUNELULUI MESES DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS LUCRARI ORADEA ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE V_T%C3%82RGU%20M NUSFALAU (KM 40+660- KM NUSFALAU (KM 40+660 - KM ESTE DE 1075.36 MIL LEI FARA TVA URE%C8%98_CLUJ_ORA 66+500), INCLUSIV TUNEL RUTIER 66+500), INCLUSIV TUNEL RUTIER DEA_CALENDAR.pdf MESES MESES

http://www.cnadnr.ro/ 842.14 MIL. LEI FARA TVA (VALOARE sites/default/files/AUTO AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A MUNICIPIULUI SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE ESTIMATA PROCEDURA DE LICITATIE) STRADA_DE_CENTURA_ 3 AUTOSTRADA 2+500 20+000 SECTOR NORD LOT 1 17.5 0% 0% 2020 2023 ANUL 2023 LUCRARI BUCURESTI (A0) ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE 746.763.568,57 LEI, FARA TVA A_MUNICIPIULUI_BUC (VALOARE OFERTA CASTIGATOARE) URE%C8%98TI_CALEND AR.pdf

http://www.cnadnr.ro/ sites/default/files/AUTO AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA A MUNICIPIULUI SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE STRADA_DE_CENTURA_ 4 AUTOSTRADA 39+000 47+600 SECTOR NORD LOT 3 8.5 0% 0% 2020 2024 466.28 MIL. LEI FARA TVA LUCRARI BUCURESTI (A0) ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE A_MUNICIPIULUI_BUC URE%C8%98TI_CALEND AR.pdf

TERMEN DEPUNERE OFERTE PROCEDURA DE ATRIBUIRE CONTRACT DE PROIECTARE SI EXECUTIE - 27.11.2020 PANA LA TERMENUL LIMITA AU DEPUS OFERTE 15 AGENTI ECONOMICI. VALOAREA ESTIMATA A CONTRACTULUI ESTE DE 5.324.779.469,00 LEI FARA TVA. DURATA CONTRACTULUI ESTE DE: 14 LUNI PERIOADA DE PROIECTARE, 59 LUNI PERIOADA DE EXECUTIE ŞI 60 LUNI PERIOADA DE GARANTIE A LUCRARILOR. TRASEUL ARE O LUNGIME DE 37.4 KM http://www.cnadnr.ro/ AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. sites/default/files/AUTO 5 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+500 81+900 CORNETU - TIGVENI SECTIUNEA 3 37.4 0% 0% 2021 2025 4784.02 MIL. LEI FARA TVA LUCRARI ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE PRINCIPALELE LUCRARI ALE ACESTEI SECTIUNI SUNT: STRADA_SIBIU_PITE%C • 95 DE PODURI SI PASAJE 8%98TI_CALENDAR.pdf • TUNEL CU DOUA GALERII INDEPENDENTE IN LUNGIME DE 1.7 KM/ GALERIE • NOD RUTIER CORNETU SI NOD RUTIER VALENI • ECODUCT IN ZONA LOCALITATII CALINESTI

http://www.cnadnr.ro/ AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE SECTIUNEA 1: SIBIU - BOITA, LOT 2 SI sites/default/files/AUTO 6 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 13+170 44+500 SECTIUNEA 1, LOT 2 SI SECTIUNEA 2 31.33 0% 0% 2021 2025 ANUL 2025 4081.78 MIL. LEI FARA TVA LUCRARI ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE SECTIUNEA 2: BOITA - CORNETU STRADA_SIBIU_PITE%C 8%98TI_CALENDAR.pdf

IN DATA DE 04.03.2021 AU FOST TRANSMISE ADRESELE DE COMUNICARE A REZULTATULUI PROCEDURII DE ATRIBUIRE A CONTRACTULUI. http://www.cnadnr.ro/ ESTIMAT 2025 IN FUNCTIE DE DATA AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE OFERTANTUL DESEMNAT CASTIGATOR ESTE S.C. PORR CONSTRUCT S.R.L., CU PRETUL DE 1.678.873.121,77 LEI FARA TVA. sites/default/files/AUTO 7 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 81+900 91+761 TIGVENI - CURTEA DE ARGES SECTIUNEA 4 9.86 0% 0% 2021 2025 LA CARE VA FI FINALIZATA 2000.17 MIL. LEI FARA TVA LUCRARI ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE AU FOST DEPUSE 2 CONTESTATII STRADA_SIBIU_PITE%C PROCEDURA DE ATRIBUIRE CONTRACTUL VA FI SEMNAT IN FUNCTIE DE SOLUTIA INSTANTEI 8%98TI_CALENDAR.pdf

http://www.cnadnr.ro/ AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE ORDIN DE INCEPERE 12.11.2018 - A FOST LANSATA PROCEDURA DE LICITATIE PENTRU ATRIBUIREA CONTRACTULUI DE EXECUTIE LUCRARI 01.06.2021. TERMEN DE DEPUNERE A sites/default/files/A7%2 8 AUTOSTRADA AUTOSTRADA PLOIESTI - BUZAU 0+000 63+250 PLOIESTI - BUZAU 63.25 2021 1146.6 MIL. LEI FARA TVA LUCRARI ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE ETAPA PROIECTARE OFERTELOR 04.08.2021 0PLOIE%C8%98TI%20- %20BUZ%C4%82U.pdf AU FOST DEPUSE NOUA CANDIDATURI PENTRU REALIZAREA ACESTEI PORTIUNI, DINTRE CARE SASE APARTIN UNOR ASOCIERI DE FIRME:

AKTOR S.A. (GRECIA) ASOCIEREA SC ALSIM ALARKO SANAYI TESISLERI VE TICARET A.Ș – MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S. (TURCIA) 1. FINALIZAT SECT. A - C (KM 27+620 - 1560.50 MIL LEI FARA TVA - ASOCIEREA FCC CONSTRUCCION SA – GULERMAK AGIR SANAYI INSAAT VE TAAHHUT A.S. (SPANIA – TURCIA) http://www.cnadnr.ro/ MARGINA - HOLDEA KM 43+060); REPREZINTA VAL ESTIMATA TOTALA, ASOCIEREA IMPRESA PIZZAROTTI & CSPA – PIZZAROTTI SA – RETTER PROJECT MANAGEMENT SRL (ITALIA – ) AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE 28.6 (9.13 KM SECTIUNEA E SI sites/default/files/AUTO 9 AUTOSTRADA AUTOSTRADA LUGOJ - DEVA 27+620 56+220 SECTIUNEA E (KM 47+090 - KM LOT 2 27.11.2013 2. SECTIUNEA E SI REST DE EXECUTAT ANUL 2025 CARE CONTINE ATAT VAL ESTIMATA ASOCIEREA TERNA SA – INTRACOM CONSTRUCTIONS SOCIETE ANONYME TECHNICAL AND STEEL CONSTRUCTIONS (INTRAKAT) (GRECIA) LUCRARI ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE FINALIZARE SECTIUNE D) STRADA_LUGOJ_DEVA_ 56+220) SI FINALIZARE SECTIUNEA D DIN SECTIUNEA D (KM 43+060 - KM A LUCRARILOR, CAT SI VAL KOLIN INSAAT TURIZM SANAYI VE TICARET ANONIM SIRKETI (TURCIA) CALENDAR.pdf 56+220) - ESTIMAT DECEMBRIE 2023 POSIBILELOR LUCRARI NOI SIMILARE ASOCIEREA MAPA INSAAT VE TICARET A.S. – CENGIZ INSAAT SANAYI VE TICARET A.S. (TURCIA) ASOCIEREA RIZZANI DE ECCHER SPA – OZGUN INSAAT TAAHHUT SANAYI VE TICARET LIMITED STI – CIPA SPA (ITALIA – TURCIA) STRABAG SRL (ROMANIA)

DETALII PRIVIND CALENDARUL PROCEDURII SE VOR VIZUALIZA LA LINK-UL DE MAI JOS:

http://www.cnadnr.ro/ sites/default/files/DRU LEGATURA CENTURA ORADEA AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE SI MURI_NA%C8%9AIONA 10 AUTOSTRADA DRUM DE LEGATURA A3 0+000 18+960 (GIRATIA SANTANDREI) - 18.96 0% 0% 2020 2023 DECEMBRIE 2023 546.4 MIL. LEI FARA TVA DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL ALATURAT LUCRARI EXECUTIE IN DERULARE LE_%C8%98I_VARIANTE AUTOSTRADA A3 (BIHARIA) _DE_OCOLIRE_CALEND AR.pdf

1.3. AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

22.05.2020 - DATA SEMNARII DURATA CONTRACTULUI ESTE DE 30 LUNI. CONTRACTULUI DE PRESTARI SEARCH CORPORATION& PRIMACONS GRUP SRL - CONTRACT ORDINUL DE INCEPERE: 10.07.2020 SERVICII DE PROIECTARE (STUDIU DE PROIECTARE ELABORARE STUDIU DE FEZABILITATE SI PROIECT 2023 - FINALIZARE PROIECTARE ANUL 2023 - FINALIZARE PRESTATORUL A ELABORAT ANALIZA MULTICRITERIALA PRIVIND ALEGEREA ALTERNATIVELOR DE TRASEU, ETAPA 1. 1 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BRASOV - BACAU 0+000 165+000 BRASOV - BACAU LOT 1 165 0% 0% FEZABILITATE SI ELABORARE PROIECT 8858.21 MIL. LEI FARA TVA TEHNIC (SF+PT) PROIECTARE (SF+PT) A FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1. TEHNIC) (VALOARE CONTRACT PROIECTARE: 20.093.359,86 LEI FARA TVA) AU FOST FINALIZATE STUDIILE DE TEREN AFERENT PROIECTULUI PRELIMINAR (STUDII TOPOGRAFICE SI GEOTEHNICE). 10.07.2020 - ORDIN INCEPERE ETAPA ESTE IN DERULARE ANALIZA MULTICRITERIALA NR. 2 DE PROIECTARE

CONTRACT SEMNAT IN DATA DE 17.03.2021 A1(KM 326+155) - DJ ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 22.04.2021 704(CUGHIR),A1(KM 362+813) - DC DURATA CONTRACTULUI ESTE DE 14 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE: ELABORARE STUDIU DE FEZABILITATE 129(SANTUHALM),A1(KM 485+030 - -6 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE, SI PROIECT TEHNIC DE EXECUTIE 2 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A1 SI A3 SEARCH CORPORATION SRL DJ 609E(RECAS),A1(KM 450+210) - DJ 0% 0% 22.04.2021 22.06.2022 - 4 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE, PENTRU 6 NODURI RUTIERE PE A1 SI 609(BETTHAUSEN),A1(KM 528+509) - - 3 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI A3 IN ZONA DE VEST A ROMANIEI DJ 682G(CRUCENI),A3(KM 39+940) - - 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI. DN1P(SPINUS) A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 22.04.2021. A FOST TRANSMIS RAPORTUL DE INCEPUT. AU FOST FORMULATE OBSERVATII LA RAPORTUL DE INCEPUT.A FOST APROBAT RAPORTUL DE INCEPUT.

IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII „COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE P.A.C., P.A.D. SI P.T.E. PENTRU OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L. PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA 58.83 MIL. LEI FARA TVA (VALOARE IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT 2021 -SERVICII DE PROIECTARE FAZA ANUL 2025 - PERIOADA ESTIMATA CONTRACT AUTOSTRADA TARGU NEAMT - IASI - TARGU NEAMT - IASI (LETCANI) - 2023 - FINALIZARE PROIECTARE 3 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA 0+000 100+140 SC CONSITRANS S.R.L. 100.14 S.F. + P.A.C. + P.T.E. SECTIUNE TARGU DESCHIDERE TRAFIC PENTRU COMPLETARE/REVIZUIRE/ACTUALIZA UNGHENI UNGHENI DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA: NEAMT - IASI-UNGHENI PRIMELE SECTIUNI RE S.F. SI ELABORARE P.A.C. + P.A.D. 12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE; + P.T.E) 5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE CONSTRUIRE; 5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)

TRIM III 2021/ FINALIZARE CONSITRANS FINALIZARE PROIECTARE (EMITERE CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN 4 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 68+050 SIBIU - FAGARAS LOT 1 68.05 22.00% ORDIN DE INCEPERE 11.05.2015 PROIECTARE FAZA REVIZUIRE STUDIU 5170 MIL. LEI FARA TVA (VALOARE CONTRACT PROIECTARE: 16.313.855,49 FARA TVA) ACORD DE MEDIU) - TRIM. III 2021 DERULARE DE FEZABILITATE

http://www.cnadnr.ro/ sites/default/files/STUD 5 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 48+410 FAGARAS - BRASOV LOT 2 48.41 0% 0% 2021 2023 17.712 MIL LEI FARA TVA II_DE_FEZABILITATE_% C8%98I_PROIECTE_TEH NICE_CALENDAR.pdf

IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT”. TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021. CONTRACT DE REVIZUIRE SF IN DERULARE IN DATA DE 31.07.2020 A FOST SEMNAT ADITIONALUL NR. 1, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE CU 6 LUNI. TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 25.07.2021 ANUL 2021 - FINALIZARE 25.07.2021 (CONFORM ACT EMITEREA DECIZIEI ETAPEI DE INCADRARE INITIALE ANPM IN DATA DE 18.09.2020. PROIECTANT: INGENIERIA ESPECIALIZADA OBRA CIVIL E PROIECTARE 6 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA TARGU MURES - TARGU NEAMT 0+000 211+000 TARGU MURES - TARGU NEAMT LOT 1 211 52% 11% 28.05.2019 ADITIONAL LA CTR DE PRESTARI 17.58 MIL. LEI FARA TVA IN DATA DE 31.09.2020 A AVUT LOC SEDINTA PENTRU AVIZAREA IN CTE / CNAIR A TRASEULUI CORECTAT CONFORM CONSTRANGERILOR IDENTIFICATE. INDUSTRIAL SA 2025 - PERIOADA ESTIMATA PENTRU SERVICII) PENTRU FINALIZAREA AVIZARII CTE A FOST SOLICITATA COMPLETAREA DOCUMENTATIEI. DESCHIDEREA PRIMELOR SECTIUNI IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR. IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800. AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES SI JUD. HARGHITA SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. HARGHITA SI JUD. MURES - IN DATA DE 16.04.2021 A FOST INAINTATA O VARIANTA PRELIMINARA A STUDIULUI DE FEZABILITATE AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. NEAMT SI JUD. IASI SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. NEAMT SI JUD. IAS

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE. MAI 2022 - TERMEN FINALIZARE SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 PROIECTARE; PERIOADA MAI 2022 - TERMEN FINALIZARE 7 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA TIMISOARA - MORAVITA 0+000 60+000 ELABORARE SF SEMNAT IN DATA DE 4 MARTIE 2020 TIMISOARA – MORAVITA LOT 1 60 04.03.2020 - ELABORARE SF 141.6 MIL. LEI FARA TVA A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA IN CURS DE ANALIZA LA BENEFICIAR SI LA EXPERTII JASPERS.IN DATA DE CONTRACTUALA DE PRESTARE A PROIECTARE (VALOARE CONTRACT PROIECTARE: 8.727.474,68 FARA TVA) 27.05.2021 RESPECTIV 02.06.2021 A FOST ORGANIZATA O SEDINTA DE ANALIZA CU EXPERTII JASPERS.PRESTATORUL IMPLEMENTEAZA OBSERVATIILE SERVICIILOR - 24 LUNI JASPERS

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 SI ETAPA 2 (AMC1 + AMC2). SE EFECTUEAZA INVESTIGATII GEOTEHNICE - PROCENT DE REALIZARE 95%. INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA - ORDIN DE INCEPERE 01.03.2019 - ANUL 2021 - FINALIZARE ETAPA SE EFECTUEAZA INVESTIGATII ARHEOLOGICE - IN CURS DE ANALIZA RAPORTUL DE DIAGNOSTIC INTRUZIV. 8 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BACAU - PASCANI 0+000 77+394 CONTRACT ELABORARE SF SI PT IN DERULARE BACAU - PASCANI LOT 1 77.283 0% 21% 2021 1750.27 MIL. LEI FARA TVA ETAPA PROIECTARE PROIECTARE S-AU OBTINUT TOATE CELE 3 CERTFICATE DE URBANISM. (VALOARE CONTRACT PROIECTARE: 16.950.944,23 FARA TVA) IN PREZENT SUNT IN CURS DE OBTINERE AVIZELE. PRESTATORUL A INAINTAT STUDIUL DE FEZABILITATE -Au fost emise observatii A FOST ANALIZAT IN CADRUL CTE SIGURANTA CIRCULATIEI PROIECTUL-IN CURS DE IMPLEMENTARE OBSERVATII.

CONTRACT PROIECTARE IN DERULARE - ETAPA ELABORARE STUDIU DE FEZABILITATE ANALIZA MULTICRITERIALA ETAPA 1 SI ETAPA 2. A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2) CONSITRANS - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE 12.11.2018 - 9 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BUZAU - FOCSANI 0+000 82+440 BUZAU - FOCSANI 82.44 10.35% 2021 FINALIZARE 2021 1270.62 MIL. LEI FARA TVA INVESTIGATIILE GEOTEHNICE AU FOST REALIZATE IN PROPORTIE DE 100%. IN CURS DE ELABORARE TESTELE DE LABORATOR. (VALOARE CONTRACT PROIECTARE: 13.933.291,10 LEI, FARA TVA) ETAPA PROIECTARE A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII. A FOST INAINTAT STUDIUL DE FEZABILITATE - IN CURS DE ANALIZA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE. S-A AVIZAT IN CADRUL CTE CNAIR SA - STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (ANALIZA MULTICRITERIALA ETAPA 1 SI ANALIZA MULTICRITERIALA ETAPA 2). AU INCEPUT INVESTIGATIILE ARHEOLOGICE. CONSITRANS - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE 10.01.2019 - ANUL 2021 - FINALIZARE ETAPA STUDIILE GEOTEHNICE IN CURS DE REALIZARE-PROCENTUL DE REALIZARE ESTE DE 61%. 10 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA FOCSANI - BACAU 0+000 96+052 FOCSANI - BACAU 96.052 0% 0.37% 2021 1927.35 MIL. LEI FARA TVA (VALOARE CONTRACT PROIECTARE: 20.123.408,52 LEI, FARA TVA) ETAPA PROIECTARE PROIECTARE STUDIUL ARHEOLOGIC ETAPA NR. 2 A FOST TRANSMIS LA MINISTERELE DE CULTURA DE PE RAZA JUDETELOR VRANCEA SI BACAU IN VEDEREA OBTINERII AVIZELOR. IN DATA DE 09.03.2021 AU FOST ANALIZATE IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII IN DATA DE 05.05.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE SUB FORMA DRAFT- Au fost emise observatii http://www.cnadnr.ro/ SECTIUNEA 6, CONEXIUNE DN 73C CU sites/default/files/STUD AUTOSTRADA SIBIU - PITESTI (NOD ANUL 2021 - FINALIZARE 11 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+800 68+000 SECTIUNEA 6 23.2 0% 0% 2020 2021 4364.7 MIL. LEI FARA TVA II_DE_FEZABILITATE_% TIGVENI) SI MODERNIZARE DN 73C PROIECTARE C8%98I_PROIECTE_TEH (KM 44+800 – KM 68+000) NICE_CALENDAR.pdf

IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTELE PENTRU LOTURILE 2 SI 3, CU URMATORII ANTREPRENORI: LOTUL 2: BISTRITA - VATRA DORNEI - SC EXPLAN SRL., CU PRETUL DE 15.793.026,12 LEI FARA TVA. LOTUL 3: VATRA DORNEI – SUCEAVA - ASOCIEREA BEST CONSULTING & DESIGN SRL – INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL, CU PRETUL http://www.cnadnr.ro/ DE 14.475.000,00 LEI FARA TVA. LOT 1 BAIA MARE - BISTRITA sites/default/files/STUD AUTOSTRADA BAIA MARE - DEJ - BISTRITA - BAIA MARE - DEJ - BISTRITA - VATRA PENTRU FIECARE DINTRE CELE TREI LOTURI, DURATA CONTRACTULUI ESTE DE 18 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI. 12 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA LOT 2 BISTRITA - VATRA DORNEI 335 2020 2022 ANUL 2022 6681.19 MIL. LEI FARA TVA II_DE_FEZABILITATE_% VATRA DORNEI - SUCEAVA DORNEI - SUCEAVA LOTUL 1: BAIA MARE – BISTRITA LOT 3 VATRA DORNEI - SUCEAVA C8%98I_PROIECTE_TEH A FOST DESEMNATA CASTIGATOARE ASOCIEREA SEARCH CORPORATION – EGIS INTERNATIONAL SAS – EGIS ROMANIA S.A. – SC FORMIN S.A., CU PRETUL NICE_CALENDAR.pdf DE 15.206.688,64 LEI FARA TVA. A FOST DEPUSA O CONTESTIE PENTRU LOTUL 1 DETALII STADIU PROCEDURA DE ATRIBUIRE IN LINK-UL DE MAI JOS.

CONTRACT IN DERULARE. PLOIESTI - BRASOV (FARA VARIANTA 2021 - DEMARARE SERVICII DE 2023 - FINALIZARE SERVICII DE S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA https://ploiesti- 13 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA PLOIESTI - BRASOV SC CONSITRANS S.R.L. DE OCOLIRE COMARNIC SI SECTOR 97.3 0% 0% PROIECTARE FAZA S.F. + P.A.C. + PROIECTARE FAZA S.F. + P.A.C. + 1000.8 MIL. LEI FARA TVA EVENTUALELOR CONSTRANGERI. brasov.ro/ RASNOV - CRISTIAN) P.T.E. P.T.E. A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE INCEPUT SI RAPORTUL DE PROGRES NR. 1.

2.POD UNGHENI - STUDIU DE FEZABILITATE FINALIZAT CU EXCEPTIA ACORDULUI DE MEDIU ; PROCEDURA DE MEDIU IN DERULARE OBTINERE DEROGARE DE LA ART ART. 23 ALIN. (2) SI ALE ART. 27 ALIN. (1) DIN ORDONANTA DE URGENTA A GUVERNULUI 2016 - DEMARARE PROIECTARE POD 2021 - FINALIZARE PROIECTARE FAZA NR. 57/2007 PRIVIND REGIMUL ARIILOR NATURALE PROTEJATE, PRIN OUG NR. 105/2020, SEMNARE MEMORANDUM IN VEDERE PROMOVARII UNGHENI; 2020 - DEMARARE SF, DEMARARE SERVICII DE ANUL 2024 - DESCHIDERE TRAFIC ACORDULUI BILATERAL ROMANIA-MOLDOVA NECESAR OBTINERII ACORDULUI DE MEDIU. 14 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA S.C. EXPERT PROIECT 2002 S.R.L. POD PESTE PRUT LA UNGHENI 1 80% 45% 0.8 MIL. LEI FARA TVA POD PESTE PRUT LA UNGHENI PROIECTARE SECTIUNEA IASI - PROIECTARE SI EXECUTIE POD POD PESTE PRUT LA UNGHENI ESTE IN PREGATIRE LA MTIC ACORDUL BILATEARAL ROMANIA-MOLDOVA. UNGHENI UNGHENI IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE EVALUARE INITIALA DE CATRE A.N.P.M. IASI. IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE INCADRARE INITIALA NR. 133/2020 ANMP . PENTRU CONTINUAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU S-A TRANSMIS MEMORIUL DE PREZENTARE CATRE APM IASI. IN DATA DE 22.02.2021 A FOST EMISA DECIZIA ETAPEI DE INCADRARE NR. 15 DE CATRE APM IASI.

CONTRACT SEMNAT IN DATA DE 23.09.2020. ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 26.10.2020 DURATA CONTRACTULUI ESTE DE 8 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE: -3 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE, ELABORARE STUDIU DE FEZABILITATE - 2 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE, SI PROIECT TEHNIC DE EXECUTIE - 1 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI 15 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A4 16+700 16+700 SEARCH CORPORATION SRL 0% 0% 26.10.2020 26.06.2021 674,39 MIL LEI FARA TVA PENTRU NOD RUTIER CUMPANA A4 - 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI. (KM 16+700)-DN 39E A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 26.10.2020. S-A EMIS ORDINUL ADMINISTRATIV NR. 1 - APROBARE EXPERTI NON CHEIE. A FOST TRANSMISA DE CATRE PRESTATOR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 1-S-AU TRANSMIS OBSERVATII. A FOST RELUATA ACTIVITATEA PROIECTANTULUI INCEPAND CU DATA DE 16.04.2021 A FOST AVIZATA IN CADRUL CTE CNAIR IN DATA DE 20.05.2021 ANALIZA MULTICRITERIALA ETAPA 1

IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 2 BISTRITA – VATRA DORNEI. DURATA CONTRACTULUI ESTE DE 18 LUNI. ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021. IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE AUTOSTRADA BAIA MARE - DEJ - BISTRITA - 15,79 MIL LEI FARA TVA (VALOARE 16 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA SC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2022 ANUL 2022 VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR. - 14 LUNI ELABORARE STUDIU DE FEZABILITATE; VATRA DORNEI - SUCEAVA PROIECT SF) - 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN FONDURI STRUCTURALE; - 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR;

IN DATA DE 15.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/20422 ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 3 VATRA DORNEI- SUCEAVA. DURATA CONTRACTULUI ESTE DE 18 LUNI. ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 28.04.2021. IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 2 BISTRITA – VATRA DORNEI. DURATA CONTRACTULUI ESTE DE 18 LUNI. AUTOSTRADA BAIA MARE - DEJ - BISTRITA - ASOCIEREA BEST CONSULTING & DESIGN S.R.L. – INGENIERIA 14,47 MIL LEI FARA TVA (VALOARE ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021. 17 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA VATRA DORNEI-SUCEAVA LOT 3 107 2021 2022 VATRA DORNEI - SUCEAVA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL S.A. PROIECT SF) IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR. - 14 LUNI ELABORARE STUDIU DE FEZABILITATE; - 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN FONDURI STRUCTURALE; - 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR;

2. DRUMURI EXPRES

2.1. DRUMURI EXPRES PROIECTE IN EXECUTIE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ""PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC http://www.cnadnr.ro/ SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. sites/default/files/DRU ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - ORDIN DE INCEPERE 01.07.2021 - VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA. MURI%20EXPRES_PROI 1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES BRAILA - GALATI 0+000 11+088 BRAILA - GALATI LOT 1 11.08 0% 0% MAI 2024 ANUL 2024 371.42 MIL. LEI FARA TVA SPEDITION UMB - TEHNOSTRADE S.R.L. ETAPA PROIECTARE SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. ECTARE_%C8%98I_EXEC DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA U%C8%9AIE_CALENDAR DE GARANTIE ESTE DE 120 DE LUNI. .pdf

SECTOR 1: 0+000 - 1+850 IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE. 24.97% (PROGRES CONSOLIDAT) 27.12.2018 - PROIECTARE; INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI SECTOR 1: 0+000 - 1+800 16.09.2019 - EXECUTIE SECTOR 3 ; DRUM EXPRES CRAIOVA - PITESTI TRONSON 1 - CRAIOVA - ROBANESTI 2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA) SECTOR 2: 1+800 - 10+000 17.7 SECTOR 1: 12% 22.89% 13.07.2020 - EXECUTIE SECTOR 1; TRIM IV 2021 ANUL 2022 358.18 MIL. LEI FARA TVA SECTOR 2: 1+850 - 10+000 (KM 0+000 - KM 17+700) SECTOR 3: 10+000 - 17+700 SECTOR 2: 10.11% 01.03.2021 - EXECUTIE SECTOR 2 - A FOST EMISA HG EXPROPRIERE NR. 843/2020 (aporx. de la km 5+190 -km 10+000). IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE SECTOR 3: 44.65% km 5+245 - km 10+000 CONSTRUIRE. PENTRU RESTUL ZONELE RAMASE NEEXPROPRIATE URMEAZA A FI INTOCMITA DOC. PENTRU HG DE EXPROPRIERE SECTOR 3: 10+000 - 17+700 – IN EXECUTIE

TRONSON 2 - ROBANESTI - BALS - 21.12.2018 - ACTIVITATEA DE DRUM EXPRES CRAIOVA - PITESTI ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC VALEA MARE (KM 17+700 - KM PROIECTARE, 24.09.2019 - EXECUTIE 3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 17+700 36+200 LOT 1: KM 17+700 - KM 36+200 18.5 80.93% 41.81% TRIM IV 2021 ANUL 2022 661.45 MIL. LEI FARA TVA TEHNOSTRADE SRL - SC CONSITRANS SRL 57+550) (ETAPELE I, II SI III), 21.11.2019 - Lot 1 km 17+700 - km 36+200 EXECUTIE (ETAPA IV)

TRONSON 2 - ROBANESTI - BALS - 21.12.2018 - ACTIVITATEA DE DRUM EXPRES CRAIOVA - PITESTI ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC VALEA MARE (KM 17+700 - 57+550) PROIECTARE, 24.09.2019 - EXECUTIE 4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 36+000 57+500 LOT 2: KM 36+200 - KM 57+550 21.35 80.16% 47.94% TRIM IV 2021 ANUL 2022 792.18 MIL. LEI FARA TVA TEHNOSTRADE SRL - SC CONSITRANS SRL Lot 2 - km 36+200 - km 57+550 (ETAPELE I, II SI III), 21.11.2019 - EXECUTIE (ETAPA IV)

ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 10.11.2020.

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC TRONSON 3, VALEA MARE - 5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 57+550 89+300 TRONSON 3 31.75 0% 0% 18.01.2021 2024 ANUL 2024 670.71 MIL. LEI FARA TVA • 12 LUNI PERIOADA DE PROIECTARE, TEHNOSTRADE SRL COLONESTI • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, • 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. INCEPAND CU DATA DE 18.01.2021 A FOST EMIS ORDIN DE INCEPERE. PAC AVIZAT IN CADRUL CTE IN LUNA MARTIE 2021 2.2. DRUMURI EXPRES PROIECTE IN LICITATIE EXECUTIE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

http://www.cnadnr.ro/ sites/default/files/DRU TRONSON 4 MURI%20EXPRES_PROI 1 DRUMURI EXPRES PROIECTE IN LICITATIE EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 89+300 121+115 TRONSON 4 31.82 0% 0% 2021 2024 ANUL 2024 ESTIMAT 617.08 MIL. LEI FARA TVA COLONESTI - OARJA - PITESTI ECTARE_%C8%98I_EXEC U%C8%9AIE_CALENDAR .pdf

2.3. DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

CONTRACT ELABORARE SF IN DERULARE. SEPTEMBRIE 2021 - TERMEN IANUARIE 2022 - TERMEN AU FOST TRANSMISE CATRE CNAIR SA VARIANTELE DE TRASEU ANALIZATE IN BAZA STUDIILOR PRELIMINARE - AMC ETAPA 1 REVIZIA 4. SEARCH CORPORATION & EGIS ROMANIA FINALIZARE PROIECTARE; PERIOADA 1 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BACAU - PIATRA NEAMT 0+000 61+000 BACAU - PIATRA NEAMT LOT 1 61 0% 0% MARTIE 2020 - ETAPA PROIECTARE FINALIZARE PROIECTARE (CONFORM 1123.86 MIL. LEI FARA TVA AMC ETAPA 1 REVIZIA 4 A FOST TRANSMIS CATRE CONSULTANTUL JASPERS PENTRU PUNCT DE VEDERE IN DATA DE 02.04.2021. IN DATA DE 18.05.2021 (VALOARE CONTRACT PROIECTARE: 8,923,930.03 LEI, FARA TVA) CONTRACTUALA DE PRESTARE A AA NR. 1 DIN 01.07.2021) A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS. IN DATA DE 07.06.2021 A FOST TRANSMISA CONSULTANTILOR JASPERS SERVICIILOR - 18 LUNI DOCUMENTATIA REVIZUITA DE CATRE PRESTATOR CA URMARE A SEDINTEI DIN DATA DE 18.05.2021.

CONTRACT ELBORARE S.F. IN DERULARE. INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA - DOCUMENTATIA AMC ETAPA 1 REVIZIA 2 A FOST TRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII. DRUM EXPRES BRAILA - TULCEA (JIJILA - CONTRACT PROIECTARE (ELABORARE STUDIU DE FEZABILITATE SI 2 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 59+700 BRAILA - TULCEA LOT 1 59.7 0% 0% IUNIE 2020 - ETAPA PROIECTARE IUNIE 2022 1674.75 MIL. LEI FARA TVA DOCUMENTATIA AMC ETAPA 1 REVIUITA A FOST RETRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII IN DATA DE 10.05.2021. CATALOI) PROIECT TEHNIC) SEMNAT IN LUNA MAI 2020. IN DATA DE 09.06.2021 FOST ORGANIZATA O NOUA SEDINTA CU EXPERTII JASPERS. (VALOARE CONTRACT PROIECTARE: 14.159.206,13 LEI, FARA TVA) IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

CONTRACT ELABORARE SF IN DERULARE. AMC - ETAPA 1 SE AFLA IN ANALIZA CONSULTANTILOR JASPERS. INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA - APRILIE 2022 - TERMEN FINALIZARE DOCUMENTATIA AMC 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSERVATIILOR JASPERS. 3 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BUZAU - BRAILA 0+000 98+000 CONTRACT ELABORARE SF SI PT IN DERULARE BUZAU - BRAILA LOT 1 98 0% 0% 03.04.2020 - ETAPA PROIECTARE APRILIE 2022 1805.55 MIL. LEI FARA TVA PROIECTARE DOCUMENTATIA AMC 1 REVIZUIT A FOST TRANSMISA CATRE CNAIR, CARE A EMIS NOI OBSERVATII CATRE PRESTATOR. (VALOARE CONTRACT PROIECTARE: 16.591.031,97 LEI, FARA TVA) IN DATA DE 26.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS.IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

IN DATA DE 17.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L. ORDIN DE INCEPERE 16.04.2021 - VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA, SURSA DE FINANTARE FIIND DIN FONDURI EUROPENE NERAMBURSABILE. 4 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES CRAIOVA - TARGU JIU ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L CRAIOVA - TARGU JIU 108 0% 0% APRILIE 2023 20.25 MIL LEI FARA TVA ETAPA PROIECTARE IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE) A FOST APROBAT RAPORTUL DE INCEPUT DE CATRE BENEFICIAR. A FOST APROBAT RAPORTUL DE PROGRES NR. 1 DE CATRE BENEFICIAR.

CONTRACT SEMNAT IN DATA DE 19.06.2020. ORDINUL DE INCEPERE 27.07.2020 INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL S.A. ORDIN DE INCEPERE 27.07.2020 - ANUL 2022 - FINALIZARE ETAPA DURATA CONTRACTULUI ESTE DE 24 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI 5 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES FOCSANI - BRAILA 0+000 76+000 SEMNAT IN DATA DE 19.06.2020 FOCSANI - BRAILA 76 0% 15% IULIE 2022 1400.22 MIL. LEI FARA TVA ETAPA PROIECTARE PROIECTARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 (AMC1) FOST AVIZATA IN CTE CNAIR SA. (VALOARE CONTRACT PROIECTARE: 15.001.446,99 LEI, FARA TVA) A FOST APROBATA TEMA PENTRU STUDII ARHEOLOGICE ETAPA1 SI STUDIUL ARHEOLOGIC ETAPA 1. IN CURS DE ELABORARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 2 (AMC 2).

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE CONTRACT IN DERULARE. DRUM EXPRES OVIDIU (CONSTANTA) - ORDIN DE INCEPERE 10.08.2020 - AUGUST 2022 - TERMEN FINALIZARE 6 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 112+000 ELABORARE SF SI PROIECT TEHNIC SEMNAT IN DATA DE 13.07. 2020 CONSTANTA - TULCEA 112.5 0% 0% Aug-22 2664.38 MIL. LEI FARA TVA AMC ETAPA 1 ESTE IN CURS DE REVIZURIRE CONFORM OBSERVATIILOR JASPERS. PRESTATORUL ANALIZEAZA REALIZAREA UNOR DRUMURI DE LEGATURA TULCEA ETAPA PROIECTARE PROIECTARE (VALOARE CONTRACT PROIECTARE: 17.845.626,28 LEI, FARA TVA) CU MUN. TULCEA.

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS INTERNATIONAL SAS. CONTRACT IN DERULARE. OCTOMBRIE 2022 - FINALIZARE 7 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PASCANI - SUCEAVA 0+000 61+000 CONTRACT PROIECTARE ELABORARE SF SI PROIECT TEHNIC SEMNAT PASCANI - SUCEAVA 61 0% 0% OCTOMBRIE 2020 1304.96 MIL. LEI FARA TVA IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA ETAPA DE PROIECTARE IN DATA DE 07.09.2020 (VALOARE CONTRACT DE PROIECTARE: 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR. 11,721,430.96 LEI FARA TVA)

SEARCH CORPORATION & – MEGA MUHENDISLIK MUSAVIRLIK A.S. CONTRACT IN DERULARE. (MEGA ENGINEERING CONSULTING INC.) - CONTRACT PROIECTARE PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU. AUGUST 2020 – DEMARARE ETAPA OCTOMBRIE 2022 - FINALIZARE OCTOMBRIE 2022 - TERMEN 8 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PLOIESTI - GAESTI 0+000 76+000 ELABORARE STUDIU DE FEZABILITATE SI PROIECT TEHNIC DE PLOIESTI - GAESTI 76 0% 0% 1671.37 MIL. LEI FARA TVA AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA. DE PROIECTARE ETAPA DE PROIECTARE FINALIZARE PROIECTARE EXECUTIE SEMNAT IN DATA DE 25.08.2020 (VAL CTR PROIECTARE: IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR. 15.86 MIL LEI FARA TVA) A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021.

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS CONTRACT IN DERULARE. INTERNATIONAL SAS. DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI. 9 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES SUCEAVA - SIRET 0+000 40+000 CONTRACT PROIECTARE ELABORARE SF SI PROIECT TEHNIC SEMNAT SUCEAVA- SIRET 40 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022 882.9 MIL. LEI FARA TVA IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA IN DATA DE 07.09.2020 (VALOARE CONTRACT DE PROIECTARE: 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR. 10,092,839.13 LEI FARA TVA)

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE CONTRACTUL IN DERULARE ELABORARE STUDIU DE FEZABILITATE SEMNAT IN DATA DE 09.07. AUGUST 2020 DEMARARE ETAPA DE OCTOMBRIE 2022 - FINALIZARE OCTOMBRIE 2022 - TERMEN A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI. 10 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES TISITA - ALBITA 0+000 160+000 TISITA - ALBITA 160 0% 0% 3563.3 MIL. LEI FARA TVA 2020 PROIECTARE ETAPA DE PROIECTARE FINALIZARE ETAPA DE PROIECTARE PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021 (VALOARE CONTRACT PROIECTARE: 11.057.073,07 LEI FARA TVA) PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR.

IN DATA DE 10.07.2020 A FOST SEMNAT CONTRACTUL PROIECTARE SF+PAC/DTAC+PT DURATA DE REALIZARE A CONTRACTULUI DE SERVICII ESTE DE 18 LUNI SEARCH CORPORATION SRL AUGUST 2020 - DEMARARE SERVICII 2022 - FINALIZARE SERVICII DE ANUL 2022 - TERMEN FINALIZARE IN DATA DE 10.08.2020 S-A DAT ORDINUL DE INCEPERE. 11 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES OAR - SATU MARE 0+000 10+900 SEMNAT IN DATA DE 10.07. 2020 SATU MARE - OAR (GRANITA RO/HU) 10.9 0% 3% DE PROIECTARE FAZA S.F. + P.A.C. + PROIECTARE FAZA S.F. + P.A.C. + 311.79 MIL. LEI FARA TVA FAZA DE PROIECTARE IN DATA DE 05.03.2021 A FOST AVIZATA IN CADRUL CTE CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU AMC1 + AMC2 (VARIANTA 1) (VALOARE CONTRACT PROIECTARE: 3.646.308,36 LEI FARA TVA) P.T.E. P.T.E. INVESTIGATIILE GEOITEHNICE SUNT REALIZATE IN PROCENT DE 70%. IN DATA DE 17.05.2021 A FOST EMIS CERTIFICATUL DE URBANISM.

CONTRACT IN DERULARE. DOCUMENTATIA AMC ETAPA 1 A FOST ANALIZATA SI S-AU EMIS OBSERVATII. DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021. ORDIN DE INCEPERE 09.12.2020 - IULIE 2022 - TERMEN FINALIZARE IN DATA DE 08.04.2021 A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2 SI SE AFLA IN ANALIZA IN CADRUL CNAIR. 12 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+000 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10 0% 0% 222.71 MIL. LEI FARA TVA ETAPA DE PROIECTARE ETAPA DE PROIECTARE IN DATA DE 21.04.2021 AU FOST TRANSMISE OBSERVATII ASUPRA DOCUMENTATIEI AMC 2 CATRE PRESTATOR. DOCUMENTATIA AMC ETAPA 2 REVIZUITA CONFORM OBSERVATIILOR FORMULATE DE CATRE BENEFICIAR (SOLICITARE PRIM. PITESTI RECONFIGURARE NOD A1-DEX) A FOST TRANSMISA BENEFICIARULUI. DOCUMENTATIA ESTE IN CURS DE ANALIZA LA BENEFICIAR. DOCUMENTATIA AMC ETAPA 2 SE VA ANALIZA IN CADRUL CTE- CNAIR SA. 3. DRUMURI NATIONALE

3.1. DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

PROBLEME: CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE DN79 ARAD - ORADEA, KM 4+150 – KM 1 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 4+150 107+745 ASTALDI S.P.A. 103.55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA 266.31 MIL. LEI FARA TVA EXECUTAT DE CATRE ANTREPRENOR. 107+745 1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635 2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR

ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - IMPRESA DI 126.323 MII LEI FARA TVA - VALOARE DATA INCEPERII ACTIVITATII DE 2 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 1+350 44+600 COSTRUZIONI ING. E. MANTOVANI S.P.A. – S.C. PEGASUS ALEXANDRIA - TURNU MAGURELE 43.25 PROIECTARE ȘI EXECUȚIE PENTRU PROIECTARE: 09.06.2020 ENGINEERING S.R.L. AMBELE SECTOARE

ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - IMPRESA DI 126.323 MII LEI FARA TVA - VALOARE TURNU MAGURELE - PORT TURNU DATA INCEPERII ACTIVITATII DE 3 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 49+194 52+649 COSTRUZIONI ING. E. MANTOVANI S.P.A. – S.C. PEGASUS 3.455 PROIECTARE ȘI EXECUȚIE PENTRU MAGURELE PROIECTARE: 09.06.2020 ENGINEERING S.R.L. AMBELE SECTOARE

REALIZARE LARGIRE VALEA OLTULUI S.C GEIGER TRANSILVANIA SRL – SERVICII DE PROIECTARE SC 4 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 251+475 254+315 LA 4 BENZI DE CIRCULATIE INTRE KM 2.84 40% 25% 01.11.2019 SEPTEMBRIE 2021 22.141 MIL. LEI FARA TVA A FOST OBTINUTA AC NR. 50 DIN DATA DE 04 SEPTEMBRIE 2020. ORDINUL ADMINITRATIV DE RELUARE A FOST DAT CU 21.09.2020. CONSIS PROIECT SRL IN CALITATE DE SUBCONTRACTANT 251+475 – KM 254+315

MODERNIZARE DN 5, ASOCIEREA EUROCOGEN - FILIALA ANINOASA SRL & ALEANDRI SPA DRUM MODERNIZAT - LUCRARI 5 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN5 7+573 19+220 BUCURESTI – ADUNATII COPACENI 11.647 98.00% 93.80% 23.04.2015 ESTIMAT SEPTEMBRIE 2021 76.13 MIL. LEI FARA TVA EXECUTIE LUCRARI & BEOZZO COSTRUZIONI SRL & SMART BUILDING PROJET SRL FINALIZATE IN ANUL 2020 KM 7+573 - KM 19+220

A FOST RECEPTIONAT UN SECTOR DE 28,85 KM. MODERNIZARE: PITESTI - PENTRU RESTUL SECTORULUI CONTRACTUL ESTE IN CURS DE REZILIERE SI SE VA LANSA O PROCEDURA DE LICITATIE AVAND CA OBIECT ACTUALIZAREA CAMPULUNG - BRASOV 6 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN73 13+800 128+250 ASOCIEREA AZVI SA - STRACO GRUP SRL - TRACTEBEL 103.25 49.82% 51.00% 19.05.2014 DECEMBRIE 2023 275.86 MIL. LEI FARA TVA PROIECTULUI PENTRU REST DE EXECUTAT. KM 13+800 - KM 42+850; KM 54+050 DOCUMENTATIA DE ATRIBUIRE PENTRU SERVICII DE ACTUALIAZARE PROIECT FINALIZATA, PROCEDURA DE LICITATIE SUSPENDATA CA URMARE A UNOR - KM 128+250 CONTESTATII .

RECEPTIE LA TERMINAREA RECEPTIE LA TERMINAREA LUCRARILOR - PREVIZIUNE SEPTEMBRIE 2021, INCLUSIV CONSOLIDAREA ZONELOR CU ALUNECARI KM 65+358 - KM 65+448 7 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 55+425 69+350 ASOCIEREA SC SYLC CON TRANS SRL/HIDROSTROY AD IONESTI - VARFURILE LOT 3 13.93 98.90% 74.35% 15.03.2019 LUCRARILOR - PREVIZIUNE 55.95 MIL. LEI FARA TVA DREAPTA SI KM 65+843 - KM 65+996 STANGA SEPTEMBRIE 2021

8 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33.83 100% 91.43% 03.09.2012 16.06.2021 81.94 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.

DECEMBRIE 2021 - RECEPTIE LA CONTRACTUL PENTRU FINALIZAREA LUCRARILOR A FOST SEMNAT IN DATA DE 08.05.2020; ASOCIEREA SC DRUM ASFALT SRL – VAHOSTAV SK A.S. – TRAMECO 9 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 69+350 102+660 VARFURILE - STEI LOT 4 33.31 51.28% 30.65% 29.06.2020 TERMINAREA LUCRARILOR ANUL 2021 74.78 MIL LEI FARA TVA ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 29.06.2020; SA – ILE VIOREL CONSTRUCT SRL. DECEMBRIE 2026 - RECEPTIE FINALA PREDARE AMPLASAMENT - 02.07.2020.

LOT 1 - ASOCIEREA SC AQUA PARC LOT 1 (SECTOR 1): BALDANA - http://www.cnadnr.ro/ SRL - SC MAVGO HOLDING SRL - TARGOVISTE KM. 0+000 - KM 44+130 sites/default/files/DRU HYDROSTROY AD - VDH AD LOTUL 1 - IN DATA DE 14.01.2021 A FOST INAINTATA NOTIFICAREA DE REZILIERE. LARGIRE LA 4 BENZI DE CIRCULATIE; MURI_NA%C8%9AIONA 10 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN71 0+000 109+905 (VODSTROI 98 AD) - SC BDU MAXI 102.99 0% 0% 1567.03 MIL. LEI FARA TVA LOTUL 2 - PROCEDURA RELUATA LOT 2 (SECTOR 2): TARGOVISTE - LE_%C8%98I_VARIANTE CONSTRUCT SRL PROCEDURA DE ACHIZITIE PUBLICA IN DERULARE SINAIA KM. 51+041 - KM 109+905 - _DE_OCOLIRE_CALEND CONSTRUCTORUL A FOST NOTIFICAT DRUM LA 2 BENZI) AR.pdf PENTRU REZILIERE

MODERNIZARE DN28B, TARGU CONTRACT PROIECTARE SI EXECUTIE IN DERULARE - SEMNAT IN DATA DE 20.05.2020 ASOCIEREA SC AQUA PARC SRL - SC MAVGO HOLDING SRL - 15.07.2020 - ORDIN INCEPERE 11 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN28B 0+000 76+758 FRUMOS – BOTOSANI, KM 0+000 – 71.512 0% 0% DECEMBRIE 2023 DECEMBRIE 2023 267.31 MIL LEI FARA TVA AVIZAT PT CTE DRDP IASI - 09.06.2021 - AVIZAT DTAC DRDP IASI - 10.03.2021; AVIZAT DTAC CNAIR SA - 16.03.2021. AUTORIZATIE DE CONSTRUIRE NR. VAHOSTAV - SK A.S. - TRAMECO SA PENTRU ETAPA PROIECTARE KM 76+758 21/12.05.2021 EMISA DE MTIC.

IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI NERAMBURSABILE, ALOCALTE IN CADRUL POIM 2014 - 2020 MODERNIZARE DN29D BOTOSANI - 22.06.2020 - EMITERE ORDIN DE ASOCIEREA SC AUTOTEHNOROM SRL - SC OPR ASFALT SRL - OBRAS CONTRACT PROIECTARE SI EXECUTIE IN DERULARE 12 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN29D 2+800 48+146 STEFANESTI KM 2+800 – KM 18+500 45.046 0 0% INCEPERE PENTRU ETAPA DECEMBRIE 2023 208.44 MIL LEI FARA TVA PUBLICAS-Y REGADIOS SA - SC EVALCONS TECH SRL IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE SI KM 18+800 – KM 48+146 PROIECTARE TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021 PT - AVIZAT CNAIR SA NR. 5035/26.03.2021

04.11.2020 A AVUT LOC DEPUNEREA OFERTELOR PENTRU PROCEDURA DE ATRIBUIRE A CONTRACTULUI "PROIECTARE TI EXECUTIE LARGIRE LA 4 BENZI A DN 7, BALDANA-TITU, KM 30+950 – KM 52+350”. PANA LA TERMENUL LIMITA AU DEPUS OFERTE URMATORII AGENTI ECONOMICI: 1. ASOCIEREA CLAY WORK - DIMAKS TURIZM INSAAT ENERJI AKARYAKIT NAK. VE TAS. GIDA TEM. OTOM. OTO. KIR.ITH. IHR. SAN.VE.TIC.LTD.STI. ISTANBUL; 2. ASOCIEREA COSEDIL SPA – SC BIT INVEST SRL - CHIRULLI ANDREA IMPRESA INDIVIDUALE – SC TOTAL ROAD SRL; 3. ASOCIEREA SC G&M ROAD BUILDING ENGINEERING SRL – SC KIRLIC GROUP SRL – SC BUILDING DESIGN 2000 TOP SRL – SC IRIMAT CONS S.R.L. - D'AGOSTINO ANGELO ANTONIO COSTRUZIONI GENERALI S.R.L. – SC CONCORDIA CON. STRADE S.R.L – SC SERCONSTRUCT ROADS S.R.L.; ESTIMAT SEMNARE CONTRACT IN LARGIRE LA 4 BENZI A DN7, BALDANA- 4. ASOCIEREA SC MAVGO HOLDING S.R.L. – SC BDU MAXI CONSTRUCT S.R.L.; 13 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 30+950 52+350 21.4 IPOTEZA FARA CONTESTATIE: DECEMBRIE 2023 DECEMBRIE 2023 210.63 MIL. LEI FARA TVA TITU, KM 30+950-KM 52+350 5. OZALTIN INSAAT TICARET VE SANAYI A.S. MARTIE 2021 VALOAREA ESTIMATA A CONTRACTULUI ESTE CUPRINSA IN INTERVALUL 243.801.103,00 - 289.093.324,00 LEI FARA TVA. DURATA CONTRACTULUI ESTE DE 6 LUNI PERIOADA DE PROIECTARE TI 20 DE LUNI PENTRU EXECUTIA LUCRARILOR. COMISIA DE EVALUARE VA ANALIZA OFERTELE IN CONFORMITATE CU PREVEDERILE DOCUMENTATIILOR DE ATRIBUIRE TI CU LEGISLATIA IN VIGOARE IN DOMENIUL ACHIZITIILOR PUBLICE. ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 29.04.2021; COMUNICAREA REZULTATULUI PROCEDURII: 29.04.2021; TERMEN DEPUNERE CONTESTATII: 10.05.2021; ESTIMAT SEMNARE CONTRACT, IN IPOTEZA FARA CONTESTATII: 25.05.2021

CONTRACT REALIZARE EXPERTIZA TEHNICA SEMNAT IN DATA DE 06.06.2020 ORDINUL DE INCEPERE A FOST EMIS IN DATA DE 10.07.2020, CU O DURATA CONTRACTUALA DE 90 DE ZILE, TERMEN DE FINALIZARE 08.10.2020 REABILITARE DN 6, ALEXANDRIA - CALENDAR PROCEDURA DE LICITATIE LOTUL 2, KM 132+435 - 185+230 - RELICITARE CRAIOVA, KM 90+190 - KM 222+182 DEPUNERE OFERTE: 24.05.2021; 14 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN6 132+435 185+230 48.009 2021 2024 ANUL 2024 267.15 MIL. LEI FARA TVA LOT 2: KM 132+435 - KM 185+230 ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 26.07.2021; (RELICITARE) COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA: 26.07.2021; CONTESTATII: 05.08.2021 ESTIMARE SEMNARE CONTRACT: 20.08.2021 REABILITARE DN66 PRIN REAMENAJAREA SECTORULUI CONTRACT EXECUTIE LUCRARI SEMNAT IN DATA DE 02.11.2020 CUPRINS INTRE KM 105+000 – KM DURATA DE REALIZARE A INVESTITIEI: 12 LUNI (EXCLUSIV PERIOADA DE TIMP FRIGUROS, DE REGULA, CUPRINSA IN PERIOADA 15.11- 15.03 ), CU O 15 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN66 106+220 106+965 ASOCIEREA S.C. FREYROM S.A. - PROCONS GROUP S.R.L 105+580 IN VEDEREA CONSTRUIRII 1.325 10.00% 8.39% 12.11.2020 12.07.2022 ANUL 2022 19.85 MIL. LEI FARA TVA PERIOADA DE GARANTIE A LUCRARILOR ACORDATA DE EXECUTANT DE 96 LUNI (8 ANI). UNUI POD NOU PESTE JIU DE LA APROBATA SITUATIA DE LUCRARI NR. 1 IN VALOARE DE 673.083,63 LEI FARA TVA. IN CURS DE APROBARE SITUATIA DE LUCRARI NR. 2 IN VALOARE DE MERI LA KM 105+250, REAMENAJARE 991.685,77 LEI FARA TVA. SECTOR KM 106+220 – KM 106+965

CONTRACT DE PROIECTARE SI EXECUTIE LUCRARI SEMNAT IN DATA DE 24.07.2020. VALOARE CONTRACT PROIECTARE + EXECUTIE LUCRARI: 126.778.219,70 LEI CU TVA, DIN CARE: PROIECTARE: 3.655.098,42 LEI CU TVA EXECUTIE LUCRARI: 123.123.121,28 LEI CU TVA ORDINUL DE INCEPERE PENTRU MODERNIZARE DN 2L, SOVEJA - AVIZAT DTAC CTE DRDP IASI 16918/ 10.05.2021; AVIZAT DTAC CTE CNAIR SA - 08.06.2021 16 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2L 60+165 76+277 16.112 PROIECTARE IN DERULARE PROIECTARE A FOST EMIS IN DATA DECEMBRIE 2023 DECEMBRIE 2023 106.54 MIL. LEI FARA TVA LEPSA, KM 60+165 - KM 76+277 DURATA CONTRACTULUI ESTE: 30 LUNI PERIOADA DE PROIECTARE SI EXECUTIE A LUCRARILOR: DE 22.09.2020 - 6 LUNI PROIECTARE; - 24 LUNI EXECUTIE LUCRARI; - 84 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. PTE IN CURS DE REVIZUIRE.

PROIECTARE SI EXECUTIE "REALIZARE 17 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 256+675 258+950 BANDA A TREIA DN 7 VALEA OLTULUI 2.274 8.46 MIL. LEI FARA TVA INTRE KM 256+675 – KM 258+950”

DRUM DE LEGATURA INTRE DN69 SI 18 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN69 0+000 10+000 TODINI COSTRUZIONI GENERALI S.P.A. 10 CTR SEMNAT IN DATA DE 29.01.2021 2021 2023 ANUL 2023 189.95 MIL. LEI FARA TVA CONTRACT SEMNAT IN DATA DE 29.01.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA) ȘI ARE O GARANȚIE DE 84 DE LUNI. AUTOSTRADA A1

STUDIUL DE FEZABILITATE IN VARIANTA DRAFT PREDAT DE CATRE PRESTATOR IN CURS DE ANALIZA. DRUM DE LEGATURA A1 - DN7 (TITU) S-AU EMIS OBSERVATII ASUPRA VARIANTEI DRAFT A STUDIUL DE FEZABILITATE SI SE ASTEAPTA VARIANTA FINALA. 19 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 0+000 14+300 (DJ 711A) - LARGIRE LA 4 BENZI DE 14.3 OCTOMBRIE 2019 Aug-21 73.33 MIL. LEI FARA TVA IN DATA DE 29.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE FEZABILITATE. STUDIUL DE FEZABILITATE SE AFLA IN ANALIZA LA BENEFICIAR. IN DATA CIRCULATIE DE 25.05.2021 AU FOST TRANSMISE OBSERVATIILE BENEFICIARULUI LA DOCUMENTATIA INAINTATA IN DATA DE 29.04.2021. PRESTATORUL IMPLEMENTEAZA OBSERVATIILE FORMULATE PENTRU SF.

CONTRACT SERVICII DE PROIECTARE STUDIU DE FEZABILITATE IN ELABORARE 20 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DRUM TRANSREGIO GILAU - APAHIDA 0+000 38+800 GILAU - APAHIDA 38.8 DERULAT IN BAZA UNUI PROTOCOL 2345.52 MIL. FARA TVA FINALIZARE SF - TRIM. IV 2021 DE CATRE UAT CLUJ NAPOCA

S.C. SEARCH CORPORATION S.R.L. - ELABORARE SF / S.C. BEST SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI 21 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN24C 106+650 142+250 MANOLEASA - RADAUTI PRUT 35.6 33.63% 0% 109.69 MIL. LEI FARA TVA CONSULTING & DESIGN S.R.L. BUCURESTI - REVIZUIRE S.F. LIPSA FINANTARE LUCRARI

POD PE DN13C PESTE RAUL TARNAVA MARE POD PE DN 13C PESTE RAUL 22 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 1+200 1+252 0.0521 5.45 MIL. LEI FARA TVA CONTRACT SEMNAT IN LUNA OCTOMBRIE 2020. LA VANATORI TARNAVA MARE LA VANATORI

REMEDIERE DEFECTIUNI PE DN1H KM 23 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN1H 6+000 12+000 SC MECANO BAU TRADING SRL 6 90.50% 47.88% 15.10.2020 31.08.2021 ANUL 2021 12.761 MIL. LEI FARA TVA ORDINUL DE INCEPERE A FOST EMIS INCEPAND CU DATA DE 15.10.2020 6+000 - KM 12+000

24 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN51 2+600 43+783 ZIMNICEA - ALEXANDRIA 41.183 0.1953 MIL. LEI FARA T.V.A. DOCUMENTATIE INTOCMITA IN VEDEREA PROMOVARII SPRE LICITATIE.

PASAJ SUPERIOR PE DN2, PESTE CF 25 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2 2 841.094 MIL. LEI FARA TVA LA ROMAN, KM 332+961

152+990 - 200+745 (ORAVITA - 26 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN57 152+990 200+745 47.755 1.638 MII LEI FARA TVA DOCUMENTATIE PREDATA LA DIRECTIA ACHIZITI MORAVITA)

S-A EMIS ORDINUL DE INCEPERE IN DATA DE 15.03.2021. DURATA DE EXECUTIE CONTRACT : DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL PROIECTARE SI EXECUTIE PASAJ 27 DN21 104+160 106+900 2.74 0% 0% 15.03.2021 01.09.2023 ANUL 2023 98.120 MIL LEI FARA TVA - 360 ZILE PERIOADA DE PROIECTARE SUPERIOR PE DN 21, KM105+500 - 540 ZILE PERIOADA DE EXECUTIE. STADIU:IN CURS DE ELABORARE/ PREDARE DECLARATIE DE PROIECTARE (TERMEN PREDARE -120 ZILE DE LA ORDINUL DE INCEPERE.) 4. VARIANTE OCOLITOARE

4.1. VARIANTE OCOLITOARE PROIECTE IN EXECUTIE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

15.01.2019 - PENTRU LUCRARILE CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017 AUTORIZATE PRIN AC 140/ AUTORIZATIA DE CONSTRUIRE NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020 20.12.2018 24 LUNI DE LA EMITEREA LUCRARI CE SE EXECUTA: GRINDA PARAPET SECTOR INEL CENTRAL CATRE DN 6, SUDARE ANTRETOAZA SI LONJERONI TABLIER METALIC - OBIECTELE ST2 STRACO GRUP SRL - SC COMNORD SRL - SPECIALIST CONSULTING PASAJ SUPRATERAN PE DJ 602 1 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE CENTURA BUCURESTI DOMNESTI - DJ 602 0.536 33.57% 32.27% 16.09.2019 PENTRU LUCRARILE AUTORIZATIEI DE CONSTRUIRE ANUL 2022 91.55 MIL. LEI FARA TVA SI ST3, MONTARE GRINZI PRINCIPALE TABLIER METALIC - OBIECT ST2, EPUISMENTE RETEA TRANSGAZ, CANALIZARE PLUVIALA, SAPATURA RAMPA SRL CENTURA BUCURESTI DOMNESTI AUTORIZATE PRIN AC 69/28.08.2019 (ESTIMAT LUNA 09.2022) COBORARE PRELUNGIREA GHENCEA, EXECUTIE STRAT DE FUNDATIE DIN BALAST PE LARGIRE DN CB SECTOR INEL CENTRAL CATRE A1, EXECUTIE STRAT DE 23.09.2020 - PENTRU LUCRARILE FUNDATIE DIN BALAST LA PUNTUL DE INTOARCERE PRELUNGIREA GHENCEA, ASTERNERE STRAT DE BAZA DIN MIXTURI ASFALTICE AB 31,5, STABILIZARE AUTORIZATE PRIN AC 54/23.09.2020 TEREN FUNDARE - RAMPA PAMANT ARMAT.

23.01.2019 - DATA DE INCEPERE PERIOADA DE PROIECTARE OBIECT 1: 0+000 -20+299, 08.03.2019 - DATA DE INCEPERE A DESCHIDERE TRAFIC 2 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BACAU 0+000 30+842 SPEDITION UMB SRL – TEHNOSTRADE SRL BACAU OBIECT 2: 0+000 - 3+177 30.842 91.42% 96.81% LUCRARILOR IN BAZA AC IANUARIE 2022 ANUL 2020 668.33 MIL. LEI FARA TVA 03.09.2020 - OBIECT 3 OBIECT 3: 0+000 -7+366 040/15.07.201503.07.2019 - DATA 02.12.2020 - OBIECT 1 DE INCEPERE A LUCRARILOR IN BAZA AC 051/28.06.2019

CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS. 05.12.2018 A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020 (DATA DE INCEPERE A ACTIVITATII 3 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BARLAD 0+000 11+281 ASOCIEREA SC TEHNIC ASIST SRL – SC TASS INFRA LOGISTIC SRL BARLAD 1 11.281 22.50% 13.62% ESTIMAT IUNIE 2022 132.051 MIL. LEI FARA TVA AUTORIZATIE DE CONSTRUIRE A FOST EMISA. DE PROIECTARE) 06.08.2020 - DATA ORDINULL DE INCEPERE A LUCRARILPR A FOST EMIS IN DATA DE 06.08.2020 DE INCEPERE A LUCARILOR) AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.

PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE: ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. – S.C. SPEDITION UMB 4 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE GALATI 0+000 33+600 GALATI 1 33.6 0% 0% IUNIE 2021 DECEMBRIE 2025 ANUL 2025 705.28 MIL. LEI FARA TVA • 12 LUNI PERIOADA DE PROIECTARE, S.R.L. – S.C. TEHNOSTRADE S.R.L. • 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR, • 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.

CONTRACT REZILIAT IN DATA DE 04.04.2019 DE CATRE CNAIR SA PENTRU NEINDEPLINIREA DE CATRE ANTREPRENOR A MAI MULTOR INSTIINTARI DE REMEDIERE. EXPERTIZA TEHNICA REALIZATA - 2019 IN DATA DE 23.12.2020 CNAIR A SEMNAT CONTRACTUL AVAND CA OBIECT “CONSTRUCTIA VARIANTEI DE OCOLIRE MIHAILESTI - FINALIZARE LUCRARI”, 31.94% - PROGRES IN CADRUL CU OFERTANTUL DECLARAT CASTIGATOR S.C. VIAROM CONSTRUCT S.R.L. 30.7% - PROGRES IN CADRUL CONTRACTULUI REZILIAT; FEBRUARIE 2021 - DEMARARE VALOAREA CONTRACTULUI ESTE DE 36.862.651,20 LEI FARA TVA. 5 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE MIHAILESTI 0+000 3+180 S.C. VIAROM CONSTRUCT S.R.L. MIHAILESTI RELICITARE 3.18 CONTRACTULUI REZILIAT; 2022 36.9 MIL. LEI FARA TVA 18.65% IN CADRUL NOULUI LUCRARI RAMASE DE EXECUTAT SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. 32% IN CADRUL NOULUI CONTRACT CONTRACT TRASEUL ARE O LUNGIME DE 3,18 KM. DURATA CONTRACTULUI ESTE DE 72 DE LUNI, DIN CARE: 12 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021. URMEAZA PREDAREA AMPLASAMENTULUI.

30.06.2017 (SERVICII DE CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015 PROIECTARE) DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017. 6 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE SATU MARE 0+000 19+540 ASOCIEREA ITINERA SPA COLLINI LAVORI SPA - VIA DESIGN SRL SATU MARE 1 19.54 67.50% 58.66% ESTIMAT DECEMBRIE 2021 304.791 MIL. LEI FARA TVA 28.06.2018 DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I. (EXECUTIE LUCRARI) DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020

40% PROGRES INREGISTRAT IN 37.5% PROGRES INREGISTRAT IN CONTRACT REZILIAT DE CATRE "COLLINI LAVORI SPA - CONTRACT REZILIAT CADRUL CONTRACTULUI DE LUCRARI 14.10.2014 - CTR REZILIAT IN DATA DE 24.11.2020 A FOST SEMNAT CONTRACTUL NR 92/79265. CADRUL CONTRACTULUI DE LUCRARI ANTREPRENOR IN LUNA 05.2018. 7 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU JIU 0+000 19+987 CONTRACT RELICITAT - ASOCIEREA SECOL SOCIETA EDILE TARGU JIU RELICITARE 19.987 REZILIAT; NOV. 2020 - CONTRACT RELICITAT 207 MIL. LEI FARA TVA A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021. REZILIAT; CONFORM CONTRACT RELICITAT - COSTRUZIONI E LAVORI S.A." 9.00% -IN CADRUL NOULUI SEMNAT IN DATA DE 18.02.2021 A FOST PREDAT AMPLASAMENTUL. 0% IN CADRUL NOULUI CONTRACT AUGUST 2022 CONTRACT

VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE CONSTRUCTII DRUMURI SI AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA PARC S.R.L.) – S.C. BDU CONTRACT REZILIAT IN DATA DE MAXI CONSTRUCT S.R.L. – HYDROSTROY AD. 20.05.2019.CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA. 29.63% - PROGRES INREGISTRAT IN ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE 58% - PROGRES FIZIC INREGISTRAT OCOLIRE TECUCI - REST DE SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. CADRUL CONTRACTULUI DE LUCRARI 8 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TECUCI 0+000 6+945 CONSTRUCȚII DRUMURI ȘI AUTOSTRĂZI S.R.L. (FOSTA S.C. AQUA TECUCI (RELICITARE) RELICITARE 6.945 LA DATA REZILIERII 03.08.2015 EXECUTAT” A FOST SEMNAT IN 41.74 MIL. LEI FARA TVA VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6,945 KM. REZILIAT PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD 0% IN CADRUL NOULUI CONTRACT 16.04.2021. A FOST EMIS ORDINUL 0% IN CADRUL NOULUI CONTRACT DE INCEPE LUCRARI IN 20.05.2021.IN VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZĂ CU UN PASAJ SUPERIOR DN24 ȘI LINA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN 21.05.2021 A AVUT LOC PREDAREA ALINIAMENT PANA LA INTERSECTIA LA NIVEL CU DJ252H LA KM 2+490, TRAVERSEAZA CU PASAJ SUPERIOR LINIA CF FAUREI - TECUCI LA KM 6+416,29 SI AMPLASAMENTULUI SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU DN25.

PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.

29.01.2019 - DATA DE INCEPERE PROIECT TEHNIC FINALIZAT PERIOADA DE PROIECTARE 9 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA SUD 0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25.69 30.24% 29,59% ESTIMAT 2022 ANUL 2022 272.43 MIL. LEI FARA TVA AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020. 25.03.2020 - ORDIN - INCEPERE EXECUTIE LUCRARI IN DERULARE. EXECUTIE LUCRARI

ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6 LUNI (FINALIZARE 24.03.2021) SI 24 LUNI EXECUTIE LUCRARI (FINALIZARE 23.03.2023). ASOCIEREA SINOHYDRO CORPORATION LIMITED – SC GOOD ETAPA 2 - 7 KM INTRE DN 1F KM 5.535 KM (5 VIADUCTE, 2 PODURI, 2 DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020. 10 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE ZALAU 0+000 5+535 1 1% 15% 2020 2023 185.54 MIL. LEI FARA TVA PROOD S.R.L. 79+625 - DJ 191C INTERSECTII TIP GIRATIE) A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI. A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021. A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.

IN DATA DE 19.11.2019 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE AFERENT ACESTUI OBIECTIV. DRUM DE LEGATURA DN5 - SOSEAUA DE DRUM DE LEGATURA DN5 - SOSEAUA IN DATA DE 05.03.2020 A FOST SEMNAT CONTRACTUL DE SUPERVIZARE AFERENT LUCRARILOR. 11 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE 0+000 5+720 PORR CONSTRUCT S.R.L. 5.72 36.00% 24.29% APRILIE 2020 ESTIMAT 2022 ESTIMAT 2022 106.638 MIL. LEI FARA TVA CENTURA - POD PRIETENIEI DE CENTURA - POD PRIETENIEI IN DATA DE 15.04.2020 A FOST EMIS ORDINUL DE INCEPERE PENTRU PROIECTARE IN DATA DE 21.10.2020 A FOST EMIS ORDINUL DE INCEPRE PENTRU EXECUTIA LUCRARILOR 4.2. VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

2020 - FINALIZARE PROIECTARE, 1 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE VARIANTA OCOLITOARE SFANTU GHEORGHE 0+000 8+000 CONTRACT ELABORARE SF FINALIZAT SFANTU GHEORGHE 1 8 07.05.2018 41.47 MIL. LEI FARA TVA PROCEDURA DE ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE - IN DERULARE, ETAPA EVALUARE OFERTE. ETAPA STUDIU DE FEZABILITATE

http://www.cnadnr.ro/ LARGIRE LA 4 BENZI A CENTURII sites/default/files/DRU RUTIERE A MUNICIPIULUI BUCURESTI MURI_NA%C8%9AIONA 2 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE CENTURA BUCURESTI 35+600 55+465 18,68 SUD INTRE A1 (KM 55+520) SI DN 5 LE_%C8%98I_VARIANTE (KM 40+000) - LOT 1 SI LOT 2 _DE_OCOLIRE_CALEND AR.pdf

PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE SI 3 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE VARIANTA OCOLITOARE SIGHISOARA 0+000 13+057 SIGHISOARA 13.057 0.00% 0.00% 6/14/2021 ESTIMAT 23.11.2021 ESTIMAT 2021 293.084 MIL LEI fara TVA 14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE EXECUTIE IN DERULARE

4.3. VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC -- IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

CONTRACT PRESTARI SERVICII DE PROIECTARE FAZELE SF+PT+DE+DATC+AT SEMNAT IN DATA DE 14.03.2018 IN DATA DE 26.03.2018 S-A EMIS ORDINUL DE INCEPERE NR.3B/4773/26.03.2018 PENTRU SERVICII DE PROIECTARE IN FAZA SF. SF FINALIZAT SI APROBAT PRIN HG INDICATORI TEHNICO-ECONOMICI NR. 58/24.02.2021. ORDIN DE INCEPERE PENTRU PT+DTAC SI AVIZE - NR. 3B/4773/26.03.2018 - INCEPAND CU 01.10.2020. PROIECTUL TEHNIC A FOST PREDAT IN 29.01.2021. MAI SUNT DE ELABORAT : DETALII DE EXECUTIE 1 LUNA, PREGATIRE DOCUMENTATIE DE ATRIBUIRE PENTRU ACHIZITIA LUCRARI DE EXECUTIE: 2 LUNI, DOCUMENTATIA CADASTRALA PENTRU HG DE EXPROPRIERI DE UTILITATE PUBLICA; 2021 - FINALIZARE ETAPA DE MAI SUNT DE OBTINUT: CTE CNAIR PENTRU PT+DTAC, AUTORIZATIA DE CONSTRUIRE SI HG DE EXPROPRIERI DE UTILITATE PUBLICA; PROIECTARE. DOCUMENTATIA PENTRU PROMOVAREA HG DE EXPROPRIERI SI DOCUMENTATIA PT + DTAC SUNT CONDIȚIONATE DE UN PUNCT DE VEDERE AFIR CU VALOARE PROIECT 1.6 MIL LEI FARA DURATA DE EXECUTIE A LUCRARILOR PRIVIRE LA SUPRAPUNEREA OBIECTIVULUI VO GIURGIU PESTE UN OBIECTIV PRIVAT FINANTAT PE FONDURI EUROPENE AFIR. 70% - SF FINALIZAT SI APROBAT PRIN TVA; CONTRACT ELABORARE FAZE DE PROIECTARE SF+PT+DE+DTAC+AT 12.068 CONFORM VARIANTEI DE : 36 DE LUNI DE LA ORDINUL DE IN DATA DE 25.05.2021 A AVUT LOC O SEDINTA DE LUCRU LA SEDIUL MINISTERULUI TRANSPORTURILOR LA CARE PROIECTANTUL VO GIURGIU A 1 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE GIURGIU 0+000 12+068 GIURGIU 1 HG INDICATORI TEHNICO - 57% 14.03.2018 ANUL 2020 VALOARE LUCRARI CF. SF - VARIANTA IN DERULARE TRASEU APROBATA INCEPERE, DUPA FINALIZAREA PREZENTAT O SOLUTIE DE PROIECTARE PRIN MODIFICAREA PROFILULUI TRANSVERSAL AL VO, PRIN CARE SE EVITA DEMOLAREA HALEI DE ECONOMICI NR. 58/24.02.2021 4 AVIZATA: TOTAL GENERAL - 343.36 SERVICIILOR DE PROIECTARE SI PROCESARE(SERA DE LEGUME), DAR CARE VA AFECTA BAZINUL DE RETENTIE IMPREJMUIREA SI DOUA CONSTRUCTII ANEXE. MIL LEI FARA TVA OBTINEREA AUTORIZATIEI DE IN DATA DE 02.06.2021 AFIR A TRANSMIS ACORDUL CA BENEFICIARUL PRIVAT S-A MODIFICE AMPLASAMENTUL AFECTAT DE EXPROPRIERE NECESARA CONSTRUCTIE REALIZARII VO GIURGIU CU CONDITIA MENTINERII CONDITIILOR DE ELIGIBILITATE SI SELECTIE INSCRISE IN CEREREA DE FINANTARE. IN DATA 04.06.2021 A FOST AVIZATA IN CTE DRDP BUCURESTI DOCUMENTATIE PT+DTAC. IN DATA DE 16.06.2021 A FOST INAINTATA LA CNAIR DOCUMENTATIA IN FAZA PT +DTAC PENTRU PROGRAMARE ANALIZA SI AVIZARE IN CTE CNAIR SI PENTRU APROBAREA MODIFICARILOR NECESARE FATA DE SOLUTIA APROBATA LA FAZA SF . IN DATA DE 25.06.2021 CA URMARE A SOLICITARII CNAIR - DEPARTAMENT OBTINERE FINANTARI PRIN ADRESA NR. 3B/ 2737/25.06.2021, DRDP BUCURESTI A INAINTAT DOCUMENTATIILE TEHNICE IN FAZELE SF - FINAL AVIZAT, PT + DTAC IN VARIANTA INAINTATA LA CTE CNAIR, PENTRU A FI PUSE LA DISPOZITIA CONSILIULUI JUDETEAN GIURGIU PENTRU INCHEIEREA UNUI PARTENERIAT PENTRU IMPLEMENTAREA OBIECTIVULUI IN TEMEIUL OUG NR. 101/2020.

CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI, ELABORARE PROIECT TEHNIC INCLUSIV DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA DE OCOLIRE RM. VALCEA NR. 148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE 16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL. VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA. DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU. CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARIEI ORASULUI CALIMANESTI. DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU 2 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE RAMNICU VALCEA 0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21.84 30% 0% 16.12.2019 2022 276.36 MIL. LEI FARA TVA RACORDAREA LA CENTURA CALIMANESTI. C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA DAESTI - ETAPA 5. DOCUMENTATIA TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM NR. 05/19899/26.01.2021 CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. S-A EMIS ORDIN DE SISTARE DIN DATA DE 29.01.2021. AU FOST INITIATE DEMERSURI IN VEDEREA ADRESARII INSTANTELOR JUDECATORESTI COMPETENTE PENTRU CHEMARE IN JUDECATA A C.J. VALCEA SI A REPREZENTANTULUI UAT DAESTI.

CONTRACT PRESTARI SERVICII COMPLETARE STUDIU DE FEZABILITATE SEMNAT LA DATA DE 05.12.2019, IN DERULARE. 3 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE REGHIN 0+000 10+440 SC TPF INGINERIE SRL REGHIN 1 10.44 05.12.2019 2021 108.11 MIL. LEI FARA TVA CONTRACT COMPLETARE SF IN DERULARE

RELICITAREA LUCRARILOR RAMASE COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT DE EXECUTAT SE VA REALIZA IN 2 09.10.2014 (ORDIN DE INCEPERE LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE EXECUTAT, CU TERMEN DEPUNERE OFERTE: 26.08.2020 ETAPE: PENTRU CONTRACTUL REZILIAT) 34.26% -PROGRES INREGISTRAT IN CONTRACT 1 INCETAT PE CALE PROCEDURA ANULATA ADMINISTRATIV PENTRU NEDEPUNERE DE OFERTE ETAPA 1: REVIZUIRE PROIECT TEHNIC 37.55% - PROGRES FINANCIAR ORDIN DE INCEPERE A LUCRARILOR - 4 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU MURES 0+000 11+643 TARGU MURES 11.643 CADRUL CONTRACTULUI DE LUCRARI AMIABILA IN 29.12.2017 ANUL 2023 134.80 MIL. LEI FARA TVA DEMERSURILE IN VEDEREA ACTUALIZARII PROIECTULUI TEHNIC SUNT DEMARATE DE CATRE DRDP BRASOV. ETAPA 2: LICITATIE LUCRARI RAMASE INREGISTRAT LA DATA REZILIERII PENTRU CONTRACTUL RELICITAT - VA REZILIAT IN DATA DE 23.02.2021, A FOST PUBLICAT IN SEAP ANUNTUL NR. CN1029446 CU PRIVIRE LA ACHIZITIA PUBLICA CARE VA AVEA CA SCOP ACTUALIZAREA DE EXECUTAT, CORELATE CU FI SPECIFICAT ULTERIOR SEMNARII DOCUMENTATIEI TEHNICE PT+DDE VARIANTA DE OCOLIRE TARGU MURES. PROIECTUL TEHNIC REVIZUIT ACESTUIA PROCEDURA DE LICITATIE IN DERULARE LA NIVELUL DRDP BRASOV

"CONTRACTUL PENTRU ELABORARE SF, PT SI DTAC A FOST SEMNAT IN DATA DE 26.07.2019 . ORDINUL DE INCEPERE A FOST EMIS IN LUNA FEBRUARIE 2020. SC CONSITRANS SRL - CONTRACT PROIECTARE ELABORARE SF, PT SI STUDIU DE FEZABILITATE FINALIZAT, URMEAZA PARCURGEREA PROCEDURII PRIVIND APROBAREA INDICATORILOR TEHNICO-ECONOMICI (AVIZ CTE 5 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE ALTERNATIVA TECHIRGHIOL 0+000 28+833 TECHIRGHIOL 1 28.833 30% 0% FEBRUARIE 2020 DECEMBRIE 2021 DECEMBRIE 2021 5.372 MIL. LEI FARA TVA DTAC CNAIR, AVIZ MT, AVIZ CI SI HG). DUPA EMITEREA HG, TERMENUL CONTRACTUAL PENTRU EMITERE PT ESTE 3 LUNI. AMC 1+2 A FOST AVIZAT IN CADRUL CTE CNAIR SA. IN CURS DE FINALIZARE INVESTIGATIILE GEOTEHNICE DE TEREN."

SF - 2006 (AVIZ MT 36/27/19.03.2007). CONTRACT REVIZUIRE SF SI ELABORARE PT + DTAC SEMNAT IN LUNA MAI 2019 - IN DERULARE, CU TERMEN DECALAT FINALIZARE SEPTEMBRIE 2021 6 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE VASLUI 0+000 14+940 CONTRACT REVIZUIRE SF IN DERULARE VASLUI 1 14.94 2019 2021 142.8 MIL. LEI FARA TVA DURATA REVIZUIRE SF – 8 LUNI AVIZ CTE DRDP IASI NR. 16891/19.04.2021 DURATA ELABORARE PT – 6 LUNI VALOARE CONTRACT PROIECTARE: 1.478.500 LEI

CONTRACT IN DERULARE. A AVUT LOC SEDINTA NR. 1 DE PROGRES IN DATA DE 25.03.2021. 7 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE PITESTI VEST 0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0% IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIE STUDIUL DE PREFEZABILITATE. PRESTATORUL A TRANSMIS SPF-ul REVIZUIT. A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. IN CURS DE ANALIZA LA BENEFICIAR (TRANSMIS LA CESTRIN) 8 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE DOROHOI 0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13.9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI

CONTRACT IN DERULARE. 9 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA VEST 0+000 22+000 SEARCH CORPORATION SRL TIMISOARA 22 18.01.2021 18.04.2022 3.66 MIL. LEI FARA TVA IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2

4.4. VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

PROCEDURA DE ACHIZITIE PUBLICA PENTRU CONTRACTUL DE SERVICII DE „ELABORARE STUDIU DE FEZABILITATE PENTRU VARIANTA DE OCOLIRE BISTRITA”, A FOST ANULATA. 2.33 MIL LEI FARA TVA (VALOARE 1 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BISTRITA 0+000 15+000 BISTRITA 1 15 OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE- ESTIMATA CONTRACT S.F.) SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI LOT 2 BISTRITA-VATRA DORNEI, VA INDEPLINI SI FUNCTIA DE VARIANTA DE OCOLIRE PENTRU LOCALITATILE INTERSECTATE DE ACESTA.

CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: "ELABORARE STUDIU DE FEZABILITATE, PROIECT TEHNIC DE EXECUȚIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI TEHNICE PE PARCURSUL EXECUȚIEI DE LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU OBIECTIVUL DE INVESTIȚIE: DRUM DE LEGATURA PENTRU SPORIREA CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA – PITESTI (TRONSONUL 1)".

DRUM DE LEGATURA DN6 - DRUM EXPRES INITIERE PROCEDURA DE ACHIZITIE ATRIBUIRE CONTRACT DE DRDP CRAIOVA A INTOCMIT CAIETUL DE SARCINI PENTRU ACHIZITIA SERVICIILOR DE PROIECTARE AFERENTE PROIECTULUI, PRECUM SI REFERATUL DE 2 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE - - - - 10 km - - CRAIOVA-PITEȘTI (TRONSONUL 1) PRESTARI SERVICII DE PROIECTARE NECESITATE PENTRU INTRODUCEREA IN PAAP 2021 A PROCEDURII DE ACHIZITIE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI INCLUSIV TVA. OBIECTIVUL A FOST INCLUS IN PAAP PENTRU ANUL 2021 AL DRDP CRAIOVA.

DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI; 2 LUNI – ELABORARE PT INCLUSIV DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR; 60 LUNI – ASISTENTA TEHNICA IN PERIOADA DE GARANTIE A LUCRARILOR).

4.5. VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA. LUCRARI IN EXECUTIE: LA DRUM - EXCAVATII PE DN CB SI PE BRETELE TRANSPORT AGABARITIC AG 1 SI AG2, EXECUTIE STRAT DE FORMA PE DN 4, PE AG1 LARGIRE LA 4 BENZI A CENTURII SI AG2 SI PE DNCB. RUTIERE A MUNICIPIULUI BUCURESTI AMENAJARE NOD RUTIER LOT 1: 31.07.2019 - DATA DE INCEPERE LA PASAJ - ARMARE SI COFRARE RIGLE P3B, P4B SI P4B1, ARMARE SI COFRARE RADIERE P5A, P4A SI SP1A, ARMARE SI COFRARE ELEVATII PILE P3A1, P2A 1 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA 3.69 22.00% 32.00% ESTIMAT 2022 SEPTEMBRIE 2022 169.5 MIL. LEI FARA TVA SUD INTRE A2 KM 23+600 SI A1 KM OLTENITA - DN 4 PERIOADA DE PROIECTARE SI P2A1. 55+520 RELOCARE UTILITATI - RELOCARE DE RETELE ELECTRICE SI RETEA GAZ, CONTINUARE MONTARE CONDUCTA NOUA GAZ PE DNCB, TELECOM - INTREGIRE TRASEU FIBRA OPTICA RELOCATA PE DNCB SI RELOCARE RETELE ELECTRICE PE AG2 SI MONTARE CABLU JT, CONTINUARE EXECUTIE CANALIZARE PE DN 4 CU PVC SI PE DNCB CU PAFSIN.

MODERNIZAREA CENTURII RUTIERE A 1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA. 2 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A MUNICIPIULUI BUCURESTI INTRE A1 - SECTIUNEA DN 2 - A2 11.524 7.59% 17.61% 04.05.2020 ESTIMAT AUGUST 2021 ANUL 2022 235.75 MIL. LEI FARA TVA LUCRARI IN EXECUTIE: DEMONTARE ESAFODAJ PILA P12, DECOFRARE CUZINETI SI OPRITOR ANTISEISMIC PILA Pila P12, DECOFRARE CUZINETI SI DN7 SI DN2 - A2 OPRITOR ANTISEISMIC PILA P11, MONTARE ESAFODAJ PILA P1, EVACUARE APE DIN ZONA RADIERE CULEE C1, PILA P8 SI PILA P9

LARGIRE LA 4 BENZI A CENTURII CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ BERCENI A FOST SEMNAT IN DATA DE 19.03.2019. ASOCIEREA S.C. TRAMECO S.A. - VAHOSTAV -SK, RUTIERE A MUNICIPIULUI BUCURESTI AMENAJARE NOD RUTIER LOT 2: LUCRARI CE SE EXECUTA: CANALIZARE PLUVIALA, STRAT DE FUNDATIE DIN BALAST, STRAT SUPERIOR DE FUNDATIE DIN BALAST STABILIZAT, RELOCARI 3 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 33+190 35+600 A.S. - CONSTRUCTII ERBASU S.A. - GRAFIC TENDS S.R.L. S.C. (LIDER 2.41 20.21% 13.87% 06.05.2019 ESTIMAT 2022 IUNIE 2022 146 MIL. LEI FARA TVA SUD INTRE A2 KM 23+600 SI A1 KM BERCENI - DJ 401 FIBRA OPTICA PE ZONA SOSEAUA BERCENI, MONTARE IZOLATORI SEISMICI, UMPLUTURI DIN PAMANT LA TERSAMENTE SI UMPLUTURI ARMATE DIN DE ASOCIERE TRAMECO S.A.) 55+520 BALAST LA RAMPE PASAJ, ASTERNERE STRAT DE BAZA AB31,5.

http://www.cnadnr.ro/ MODERNIZAREA CENTURII RUTIERE A sites/default/files/DRU A FOST DEMARATA PROCEDURA DE ACHIZITIE PUBLICA PENTRU LUCRARI DE REMEDIERE SI FINALIZARE LUCRARI - REST DE EXECUTAT. ASOCIEREA S.C. DELTA A.C.M. 93 SRL & AZVIRT LLC & S.C. MUNICIPIULUI BUCURESTI INTRE A1 - SECTIUNEA A1 KM 55+465 - DN7 KM 86.5% - PROGRES FIZIC LA DATA 77.73% - PROGRES FINANCIAR LA MURI_NA%C8%9AIONA 4 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 55+465 64+160 8.695 2021 TRIM IV 2022 106.6 MIL. LEI FARA TVA A FOST PUBLICAT ANUNTUL DE PARTICIPARE. MAXIDESIGN S.R.L. - CONTRACT REZILIAT DN 7 SI DN 2-A2:SECTIUNEA A1 (KM 64+160 REZILIERII DATA REZILIERII LE_%C8%98I_VARIANTE DETALII IN LINK-UL DE MAI JOS: 55+465) - DN 7 (KM 64+160) _DE_OCOLIRE_CALEND AR.pdf

CONTRACT SEMNAT IN DATA DE 23.10.2018. AUTORIZATIA DE CONSTRUIRE NR. 13 DIN DATA DE 16.03.2020. PROIECTARE SI EXECUTIE PASAJ 04.12.2018 - PROIECTARE; 2021- CONFORM ASUMARI ANUL 2022 CONFORM GRAFIC ORDINUL DE INCEPERE PENTRU PROIECTARE A FOST DAT IN DATA DE 04.12.2018. 5 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI SC STRABAG SRL MOGOSOAIA PE CENTURA MOGOSOAIA/ DN 1A 0.8 49.63% 37.29% 32.26 MIL. LEI FARA TVA 02.04.2020 - EXECUTIE ANTREPRENOR CONTRACT ORDINUL DE INCEPERE PENTRU LUCRARI A FOST EMIS IN DATA DE 02.04.2020 BUCURESTI PESTE DN 1A LUCRARI CE SE EXECUTA: ARMARE GRINDA CORONAMENT RAMPA OTOPENI, ARMARE ANANTRETOAZA PILA P1, ARMARE PLACA DE SUPRABETONARE INTRE PILA P3 SI CULEEA OTOPENI, UMPLUTURA RAMPA CHITILA, MONTARE ELEMENTE PREFABRICATE RAMPA CHITILA

PENETRATIE PRELUNGIREA GHENCEA – DOMNESTI SI SUPRALARGIRE BULEVARDUL GHENCEA INTRE 139.255 MII lei FARA TVA - VALOARE 6 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI STRADA BRASOV SI TERMINAL 1.1 PROIECTARE TRAMVAI 41” CU PROIECTUL “PASAJ SUPRATERAN PE DJ 602, CENTURA BUCURESTI - DOMNESTI 4.6. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS 1 VARIANTA OCOLITOARE VARIANTA OCOLITOARE ALESD 0+000 16+840 ALESD 16.84 LOCALE IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE. IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE IUNIE 2021- URMEAZA AVIZAREA IN CADRUL CTE IM SI PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE 19+690 26+460 ETAPA I – VARIANTA SUD OBIECT 3 – 126.88 MIL. LEI FARA TVA (VALOARE 2 VARIANTA OCOLITOARE VARIANTA OCOLITOARE IASI 6.77 IMPOSIBILITATII PASTRARII TRASEULUI PE BULEVARDUL POITIERS SI STRADA TREI FANTANI (KM 19+690 - KM 26+460). LOCALE (SELGROS) (DN28) VARIANTA TRAFIC GREU ESTIMATA) PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA PREVEDERILOR OUG 101/2020. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE 3 VARIANTA OCOLITOARE VARIANTA OCOLITOARE MEDIAS 0+000 8+500 MEDIAS 1 8.5 2022 2024 OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS. LOCALE A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021. A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 - TERMEN PENTRU EMITEREA RAPORTULUI DE INCEPUT- 31.07.2021

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE 101/2020. 4 VARIANTA OCOLITOARE VARIANTA OCOLITOARE STEI 0+000 27+230 LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE STEI 1 27.23 0% 0% 257.413 MIL. LEI FARA TVA LOCALE ANTREPRENOR ANTREPRENOR ANTREPRENOR A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS. EXECUTAT, CU TERMEN DEPUNERE OFERTE : 22.06.2020 CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - ESTIMAT FINALIZARE TRIM. III 2021 4.7. VARIANTE OCOLITOARE IN FOLOSINTA - IUNIE 2021

NR. DE LA PANA LA STADIUL FINANCIAR DETALII CATEGORIE DRUM RANG DRUM INDICATIV DRUM ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII CRT. (km) (km) ACTUAL PROCEDURA

LUCRARI FINALIZATE - 20.11.2020 PENTRU ACEST PROIECT A FOST FINALIZAT PROCESUL DE ACCESARE A FINANTARII NERAMBURSABILE ALOCATE IN CADRUL POIM 2014-2020, FIIND 1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE RADAUTI 0+000 16+580 SPEDITION UMB - SC TEHNOSTRADE SRL RADAUTI 1 16.58 08.10.2018 20.11.2020 ANUL 2020 97.44 MIL. LEI FARA TVA EMISA NOTA DE APROBARE A FINANTARII ACESTUIA DIN FONDURI NERAMBURSABILE IN LUNA DEC. 2020. CONTRACT DE FINANTARE A LUCRARILOR EXECUTATE IN CADRUL POIM 2014-2020 SEMNAT IN LUNA IANUARIE 2021

LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020. MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, FIIND REALIZATA INSPECTIA PRELIMINARA (10.06.2021) IN URMA 2 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SACUENI 0+000 7+620 SC ANTREPRIZA DE REPARATII SI LUCRARI ARL CLUJ SA SACUENI 7.62 10.09.2019 12.08.2020 DECEMBRIE 2020 42.83 MIL. LEI FARA TVA CAREIA ANTREPRENORUL ARE LA DISPOZITIE 30 ZILE PENTRU REMEDIEREA DEFECTIUNILOR CONSTATATE DE COMISIE. SE ESTIMEAZA CA R.T.L. SE VA REALIZA IN LUNA IULIE 2021.

ASOCIEREA S.C. AUTOTEHNOROM S.R.L. (LIDER) – S.C. IUNIE 2021 - RECEPTIE LA OPERATIONAL AUTOLEASING S.R.L. – S.C. OPR ASFALT S.R.L. – DESCHISA TRAFICULUI - IN DATA DE IUNIE 2021 - FINALIZARE LUCRARI 3 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SUCEAVA 0+000 7+285 SUCEAVA 1 7.285 77% 01.10.2018 TERMINAREA LUCRARILOR 63.85 MIL. LEI FARA TVA OBRAS PUBLICAS Y REGADIOS S.A. – S.C. FLORCONSTRUCT S.R.L. – 27 SEPT. 2019 AUXILIARE IUNIE 2028 - RECEPTIE FINALA S.C. CALCARUL S.A.

VARIANTA OCOLITOARE CARACAL - 24.05.2018 - A FOST REALIZATA RTL 4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE 0+000 10+345 ASOCIEREA SECOL S.A. - S.E.C.O.L S.P.A. CARACAL 10.345 100% 97.05% 16.10.2014 RTL: 24.05.2018 41.69 MIL. LEI FARA TVA RELICITARE IN DATA DE 10.11.2020 A FOST REALIZATA RECEPTIA FINALA

IN DATA DE 29.11.2016 A AVUT LOC RECEPTIA LA TERMINAREA LUCRARILOR. LA DATA PREZENTEI CONTRACTUL SE AFLA IN PERIOADA DE NOTIFICARE A ASOCIEREA CHIRULLI ANDREA IMPRESA INDIVIDUALE - ALEANDRI RTL: 28.11.2016; 5 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 7+292 TRONSON I, DN1 - DN 11 LOT 1 - RELICITARE 100% 90.18% 16.12.2014 59.56 MIL. LEI FARA TVA DEFECTIUNILOR. SPA - SMART BUILDING PROJECT- PASQUALE ALO' SRL RF:19.12.2019 IN DATA DE 19.12.2019 A FOST APROBAT PROCESUL VERBAL DE RECEPTIE FINALA.

ASOCIEREA SC VIAROM CONSTRUCT SA - SC BETA COPS SRL - SC RECEPTIE LA TERMINAREA 6 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 4+924 TRONSON II, DN11 - DN13 LOT 3 4.924 100% 98.77% 07.08.2014 64.42 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 29.11.2019. MAXIDESIGN SRL LUCRARILOR: 29.11.2019