Gympie Regional Council crews have a busy fortnight ahead with a number of major project construction and road maintenance activities.

Please find the full list of activities below.

Construction projects

Project What’s happening What we are doing in the next two weeks

Wadell Road, The works include the widening - Site establishment of Wadell Road and improvements to the existing - Provision for traffic pavement. Works also include constructing new stormwater - Installation of new drainage and upgrading the stormwater pipes and

existing. pits

Project forecast completion early February 2020

Mary Street, Construction of new - Excavation of drainage stormwater infrastructure alignment including pipes and drainage pits. Associated rehabilitation - Installation of new landscape works will also be stormwater pipes included. - Construction of drainage pits

- Rehabilitation works to footpath and road infrastructure

- Project forecast completion date 23/12/2019 Project What’s happening What we are doing in the next two weeks

Feros Road, Road widening and pavement - Works to commence in Mothar construction including sealed the next fortnight Mountain formation providing additional road width. New traffic furniture - Site establishment and improved drainage - infrastructure. Stripping material

- Correction formation on full with section

- Project forecast completion date 06/12/2019

Scottish Mine The works include construction - Site establishment No.1 of a gravel access track in the Scottish Mine Site. Works also - Topsoil, spread and includes drainage earthbound shape earthbound wall wall, gravel walking track and access track, concrete driveway - Gravel walking track and

and installation of a fence. access track

- Concrete pour driveway

- Project forecast completion date 29/11/2019

Power Road – The works include construction - Excavation and pathway of a concrete pathway from construction of concrete Katrina Court and continuing footpath from Katrina along Power Road to Woolgar Court to Power Road Road. Project forecast completion date 22/11/2019 Project What’s happening What we are doing in the next two weeks

Noosa Road – Road pavement construction - New road pavement to road and sealed formation providing be constructed construction full road width traffic furniture and improved drainage - Kerb and channel infrastructure. - Vegetation rehabilitation and associated landscape works to be completed

- New traffic furniture to be installed

- Project forecast completion date 23/12/2019

Maintenance activities

Road Name Where it is What we are doing Fisher Lane Gympie Wheel stop repair Myall Street Gympie Kerb and channel Beresford Crescent Gympie Kerb and channel Rafter Road Glanmire Kerb and channel Duke Street Gympie Kerb and channel Fisherman’s Pocket Road Fisherman’s Pocket Gravel re-sheeting Brewery Road Gympie Maintenance grading Sykes Road Maintenance grading Petersen Road Bells Bridge Maintenance grading Meadows Lane Chatsworth Maintenance grading Albrecht Road Corella Maintenance grading Melbern Road Chatsworth Maintenance grading Glen Echo Road Maintenance grading Brooweena Woolooga Woolooga Heavy formation grading Road (Main Roads) Crossing Road Widgee Crossing North Shoulder grading Parson Road Service Road Gympie Verge repairs and sealing Mahaffey Road Table drain repair Neuendorf Road Langshaw Drainage Road Name Where it is What we are doing Heathcote Road Langshaw Drainage Eel Creek Road Langshaw Drainage Upper Eel Creek Road Langshaw Drainage Herron Road Drainage Mary’s Creek Road Mary’s Creek Drainage Booinbah Road Tansey Culvert repair Planted Creek Road Tansey Drainage Goonuloom Road Tansey Drainage Sexton Road Sexton Drainage Cooloola Drive Rainbow Beach Line marking Parkland Drive Chatsworth Reseal preparations Kiaka Road Reseal preparations Power Road Widgee Reseal preparations Road Wilsons Pocket Reseal preparations Isis Court Cooloola Cove Reseal preparations Melawondi Road Melawondi Reseal preparations Blackgate Road Amamoor Reseal preparations Crossing Road Kybong Reseal preparations Edina Court Cooloola Cove Reseal preparations Maryborough Cooloola Toolara Forest Asphalt pavement repairs Road (Main Roads)