04 NEDO-IC-00ER36

FeasibiIity Study

on

Rehabilitation at Fenchuganj Fertilizer Factory

March, 2001

New Energy and Industrial Technologies Development Organization (NEDO) Entrusted to KOBE STEEL, LTD.

► □20005066■2 FEASIBILITY STUDY ON REHABILITATION AT FENCHUGANJ FERTILIZER FACTORY Kobe Steel, Ltd., Japan March, 2001

Study purpose ; This study intends to realize higher energy conservation and reduction of greenhouse gas emissions in by rehabilitating and applying uptodate process for urea production plant, as the Fenchuganj fertilizer plant in old and low efficiency. This feasibility study was made for the materialization of the project in the scheme of Clean Development Mechanism (CDM). FeasibiIity Study

on

Rehabilitation at Fenchuganj Fertilizer Factory

March, 2001

New Energy and Industrial Technologies Development Organization (NEDO) Entrusted to KOBE STEEL, LTD. INTRODUCTION

This report has been compiled through collecting the results of basic research “Fenchugangi Fertilizer Plant Renovation Plan Investigation ” for promoting joint implementation, with which Kobe Steel, Ltd was entrusted from New Energy and Industrial Technology Development Organization (NEDO) as its research business in 2000.

In December, 1997, the third United Nations Framework Convention on Climate Change was held in Kyoto. For the purpose of preventing global warming attributable to greenhouse effect gas, such as CO2, “Kyoto Protocol”, in which advanced countries would aim at achieving an annual average emission volume reduction by at least 5 % during the period from 2008 through 2012, compared with the level in 1990, was adopted in the above Convention. In the case of Japan, reduction target was determined as 6 %. In Kyoto Protocol, “Joint Implementation ”, in which reduction volume of greenhouse effect gas would be shared each other among advanced nations internationally through actual implementation of the project, and “Clean Development Mechanism (CDM)”, which advanced nations were expected to implement jointly with developing countries, were decided as measures for obtaining flexibility in the process of achieving their target. Under the circumstances, Japan is anticipated to attain its target with application of such systems.

This investigation has been made for the purpose of contributing to energy saving and greenhouse effect gas reduction in the targeted county ’s industries and its fertilizer industry ’s modernization essentially required for continuous economic development, with introduction of Japan ’s energy saving technology, as well as realizing the renovation project of Fenchugangi Fertilizer Plant, the oldest and low efficient in Bangladesh, through its combination with implementation of future “Clean Development Mechanism (CDM)”.

The results of our investigation are herein reported.

March, 2001

Kobe Steel, Ltd List of staffs in charge of research

Name Belonging & Managerial Position Business in charge Yoshiro Tanaka General Manager, Chief in research business, Environment Plant Engineering responsible for overall business Company, Kobe Steel, Ltd. management & project Junichiro Nada General Manager, Environment Plant Assistant chief in research business, Engineering Company, Kobe Steel, Ltd. responsible for management of technical department & process Yoshio Yabunaka General Manager,Environment Plant Research business, responsible for Engineering Company,Kobe Steel, Ltd. marketing research Nobuyuki Masuda Manager, Environment Plant Research business, responsible for Engineering Company, Kobe Steel, Ltd. financial affairs Akihiko Jogu General Manager in charge of chemical Research business, responsible for plant, Environment Plant overall engineering business Engineering Company, Kobe Steel, Ltd. CONTENTS

INTRODUCTION OUTLINE

Chapter 1 BASIC COMPONENTS OF PROJECT...... -1-1 1. Situation of Bangladesh...... -I-1 1.1. Political, Economic, Social Conditions...... -1-1 1.2 Energy Conditions ...... -I-10 1.3 Needs for CDM Project...... -1-21 2. Necessity for Introduction of Energy Saving Technology in the Targeted Industry . -1-22 3. Significance, Needs of the Project and Spread of thePerformance to Peers Group -1-24 3.1. Significance, Needs in Implementation of the Project...... -1-24 3.2 Spread of its Performance to Peers Group...... -1-25

Chapter 2 SPECIFICATION OF THE PROJECT PLAN...... -II-1 1. Project Plan ...... -II-1 1.1 Summary on the Targeted District in the Project (NGFF Fertilizer Plant) ...... -II-1 1.2 Details of the Project...... -II-6 1.3 Greenhouse Effect Gas Targeted in the Project...... -II-7 2. Outline of NGFF Fenchuganj Fertilizer Plant ...... -II-8 2.1 Interest on the Side of Fenchuganj Fertilizer Plant ...... -II-9 2.2 Conditions of Relevant Equipment in Fenchuganj Fertilizer Plant ...... -II-10 2.3 Capacity for Performing the Project on the Side of NGFF Fenchuganj Fertilizer Plant ...... -11-48 (1) Technical capacity...... -11-48 (2) Management system...... -II-51 (3) Management foundation, management policy...... -11-53 (4) Capacity for financial burden ...... -11-54 (5) Capacity for provision of manpower ...... -11-55 (6) System for implementation ...... -11-55 2.4 Details of the Project and Specifications of Relevant Equipment after Renovation in NGFF Fertilizer Plant ...... -11-57 2.5 Scope of Funds, Machinery & Equipment and Services to be Provided Mutually in the Project Implementation ...... -11-74 2.6 Preconditions and Points at Issue in Project Implementation...... -11-76 2.7 The Project’s Implementation Schedule ...... -11-78 3. Materialization of Financial Plan ...... -11-82 3.1 Financial Plan for the Project’s Implementation (Amount of Necessary Fund, Fund Raising Method, etc.)...... -11-82 3.2 Prospect for Fund Raising...... -11-83 4. Matters Relating to Joint Implementation Conditions ...... -11-86 4.1 Adjustment Matters with the Targeted Country for Materialization of CDM, Including Provision of the Project’s Implementation Conditions and Share of Business Responsibility in View of Actual Situation in the Project’s Execution Site...... -11-86 4.2 Possibility of the Targeted Country ’s Consent on the Project’s Joint Implementation (Requirements for Obtaining the Targeted Country ’s Consent, Based on the Approach of the Targeted Country ’s Government Related Agencies and NGFF Fertilizer Plant) ...... -11-86

Chapter 3 PROJECT EFFECT...... -Ill-1 1. Energy Saving Effect...... -Ill-1 1.1 Technical Ground for Positive Energy Conservation Effects...... -Ill-1 1.2 Baseline for Energy Saving Effect Calculation Base...... -HI-4 1.3 Actual Volume, Period of Production and Accumulated Volume of Energy Saving Effect...... -HI-7 1.4 Actual Method for Ascertaining Energy Saving Effect...... -HI-9 2 Effect Due to Greenhouse Effect Gas Reduction ...... -Ill-11 2.1 Technical Base for Production Effect Due to Greenhouse Effect Gas Reduction ....-Ill-11 2.2 Baseline for Greenhouse Effect Gas Reduction Effect Calculation Base...... -Ill-11 2.3 Actual Volume, Period of Production and Accumulated Volume of Greenhouse Effect Gas Reduction Effect...... -Ill-12 2.4 Actual Method for Ascertaining Greenhouse Effect Gas Reduction Effect...... -Ill-13 3. Influence to Productivity ...... -Ill -15

Chapter 4 PROFITABILITY...... -IV-1 1. Economical Effect Due to Investments Payback...... -IV-1 1.1 Preconditions for Calculation and Financial Plan ...... -IV-1 1.2 Investment Amount and Effects...... -IV-2 1.3 IRR Calculation Results and Appraisal...... -IV-3 2. Cost Reduction Effect in this Project...... -IV-4 2.1 Energy-Saving Effect...... -IV-4 2.2 Effects of Greenhouse Gas Reductions ...... -IV-4 Chapter 5 CONFIRMATION OF DISSEMINATION EFFECT...... -IV-1 1. Possibility of Spread of the Technology Introduced in the Project...... -IV-1 2. Effects Reflecting the Diffusion of Technologies...... -IV-1 2.1 Energy Saving Effects...... -IV-1 2.2 Effects due to Greenhouse Gas Reduction ...... -IV-2

Chapter 6 INFLUENCE TO OTHER ASPECTS...... -VI-1 1. Environmental Aspect...... -VI-1 2. Economic Aspect...... -VI-1 2.1 Foreign Currency Saving...... -VI-1 2.2 Reduction of Production Cost...... -VI-2 2.3 Sales Price...... -VI-2 3. Social Aspect...... -VI-2 3.1 Guarantee for Livings of Employees and their Families...... -VI-2 3.2 Function as a Supply Base of Fertilizer in Fenchuganj Area...... -VI-3

CONCLUSION

APPENDIX 1. List of Source Books 2. Site Survey Schedule OUTLINE OUTLINE

This investigation has been made as a basic research, aiming at combination of energy saving measures of fertilizer plant at Fenchugangi, Bangladesh (hereinafter called as “NGFF Fertilizer Plant ”) with future “Clean Development Mechanism (CDM)”. For the purpose of making this investigation, experts were delegated there from Japan three times in the past. Such experts had opportunities to meet the persons concerned of the related Bangladesh Government Agencies, particularly those of Ministry of Environment and Forest and Ministry of Industry. Through these meetings, the Government ’s position for tackling CDM was inquired and ascertained clearly by Japanese delegates. When Japanese delegates visited NGFF Fertilizer Plant, main organization for implementation of the project on the side of Bangladesh, and Bangladesh Chemical Industries Corporation (BCIC), upper organization of NGFF Fertilizer Plant, they were able to ascertain mutual efforts to be made for materialization of NGFF Fertilizer Plant ’s renovation project. Also, its technical aspects, in the case of materialization, were examined by both of the parties. On the side of Japan, the results of local investigation were examined thoroughly and possible outcomes through implementation were well reviewed. The summaries of results of local investigation as well as those of reviews on possible outcomes through implementation are as follows.

With the greater part of territory being surrounded by India, the People’s Republic of Bangladesh is situated at the western part of India and adjacent to the border of Myanmar in a narrow area of its southern part. It has a country area of approximately 140,000 km2, about 2 times as large as Hokkaido. With a population of 130 million, almost same as that of Japan, it is well known as a distinguished over-populated land among developing countries.

As indicated by GDP per capita in Bangladesh, amounting to around US $ 360 (1997), most people seem to suffer extreme poverty. Under the background, there are losses of properties due to natural disasters, such as flood and cyclone, and increase of population attributable to the birthrate highly remained. To let the people get out of such poverty and better their living standards, the promotion of investments from overseas and activation of economic activities are essentially required.

Among limited natural resources in Bangladesh, natural gas is the most important natural resource, which is expected to develop the domestic industries. Around 75 % of natural gas production are used for power generation and chemical fertilizer manufacturing. While an estimated amount of workable deposits of natural gas in Bangladesh is regarded as approximately 10 trillion cubic feet (around 300 billion m3), its annual production is approximately 250 billion cubic feet (7 billion m3 in 1994/95). Thanks to annual increase of

(1) consumption volume of electricity consumption volume and that of natural gas at the same time, reflecting the development of domestic industries, natural gas resource in Bangladesh will be exhausted in next 20 ~30 years, judging from the present standard of natural gas consumption volume, unless increase of deposits through new development of natural gas become available. There are, therefore, urgent needs in Bangladesh to preserve valuable natural gas as much as possible by means of executing energy saving.

In Bangladesh, the Jamna River streaming via area of India runs through between its eastern part and western part, while the Padoma River (the Ganges River) and the Megna River flow into the Jamna River from its north-western area and north-eastern area, respectively. And the merged three rivers empty themselves into Bay of . With low grounds in the greater part of land, these rivers often flow over their banks and cause deluges in rainy season. This country is, therefore, apt to be influenced considerably by rise of sea-surface due to global warming.

The implementation of CDM is expected to contribute to economic development through promotion of investments from overseas, reduction of consumption volume of natural gas, valuable resource among limited domestic natural resources, by use of energy saving technology and prevention of global warming through emission volume reduction of greenhouse effect gas. In anticipation of much benefits to be produced by CDM, Bangladesh is eagerly desirous of such implementation.

NGFF Fertilizer Plant was constructed by Japanese Consortium, consisting of Kobe Steel, Ltd., a leading contractor, Mitsubishi Heavy Industries Ltd., Ishikawajima Shipbuilding Co., Ltd., Fuji Electric Co., Ltd and Meidensha Co., Ltd, under financial supports from JBIC (the former EXIM) in 1962. In 1978, its rehabilitation in mechanical fields was implemented by Kobe Steel, Ltd under financial aids from JBIC (the former Overseas Economic Cooperation Fund), and its operation has been managed up to now with NGFF’s best efforts. In 1986, Japan Consulting Institute made an investigation on this project’s rehabilitation and concluded that fresh equipment should be built up after scrap-down for reason of damages of the plant, which had been operated more than 25 years after its start-up. The construction of new plant was, however, not realized due to lack of necessary fund, and operation of the existing plant has been maintained up to now through NGFF’s efforts.

With a lapse of 23 years after rehabilitation in 1978, the machinery & equipment have naturally superannuated. As a result, decline in production capacity, rise in production cost due to increase of energy basic unit as well as environmental pollution attributable to leakage of gas and liquid in the process have been brought about. Although its operation is barely

(2) maintained with NGFF’s efforts, the operation ratio hovers around 78 %, owing to superannuation of the equipment and lack of spare parts. In addition, the basic unit of energy has exceeded the projected value by about 15 %.

Meanwhile, NGFF Fertilizer Plant is under control of Bangladesh Chemical Industries Corporation ( hereinafter called as “BCIC”). In view of the present situation of the above fertilizer plant, BCIC requested us to implement F/S relating to the following 4 items, such as recovery of production capacity, execution of energy saving, environmental betterment and measures for prolongment of the plant ’s life.

CD To improve the plant ’s production capacity up to the value originally projected (Measures forproduction increase) (2) To facilitate a minimum of 10 years plant operation (Measures for prolongment of the plant ’s life) (3) To reduce the basic unit of natural gas (Measures for energy saving) © To take environmental pollution into consideration (Measures for environment)

Through examination on renovation plan of this time, it has been confirmed that the production volume originally planned would be recoverable with rehabilitation of the superannuated machinery & equipment and supplies of spare parts, and that both of reduction of greenhouse effect gas generation volume and decrease in manufacturing cost of urea fertilizer would be achievable by reducing natural gas consumption volume down to the value originally planned. In other words, natural gas volume per ton of urea product will decrease by around 18.6 %, from the present 1,820 m3 (the mean value in 1999/2000) to 1,535 m3. Also, urea production volume is expected to increase by about 29 %, from the present 84,275 tons (actual value in 1999/2000) up to 108,625 tons on annual production base, as an effect of production increase.

With adoption of the manufacturing process technology prevailed 40 years ago, sufficient collection of energy was not designed in NGFF Fertilizer Plant. In the aspects of capacity and process technology, there are many differences in this plant, compared with those of latest energy-efficient fertilizer plants. Our check-up on NGFF’s fertilizer production plan has revealed that, within the permissible range due to economic examination results, more reduction of natural gas consumption volume would be attainable with adoption of latest process in available parts, by utilizing the existing equipment at the maximum and controlling additional capital expenditures as well as by increasing energy efficiency. With such improvement of the process, natural gas consumption will decrease furthermore by about 73 m3 per ton of urea product. Consequently, the total consumption volume of natural gas, as a

(3) result of rehabilitation and process improvement, will amount to 1,462 m3 per ton of urea product, and the total reduction is expected to be around 20 %. Production increase effect attributable to process improvement seems, however, to be less than that of the above rehabilitation, thanks to economical reasons, such as additional expenses for removals of many bottlenecks existed in the process.

Since additional energy required for production increase exceeds energy reduction volume obtained from energy saving effect, natural gas consumption volume in this project will increase, as a whole, by approximately 4,900,000 Nm3 (oil conversion 4,220 toe) on annual basis, although around 20 % reduction of energy basic unit and simultaneously about 29 % production increase are achievable as the energy saving effect mentioned above. In respect of greenhouse effect gas reduction effect, the project’s CO2 volume diffused in the air will decrease, as a whole, by 7,768 tons annually, as the volume of CO2, arisen from production increase and fixed in urea product, exceeds that of CO2, corresponding to production increase and generated from combustion of natural gas.

Our estimate has clarified that the total fund required for the above rehabilitation and process betterment in NGFF Fertilizer Plant would amount to approximately US$ 19,106,000. For examination on the project’s profitability, the following conditions have been assumed. Based on soft loans totally from overseas, borrowings conditions, such as interest: 1 %, repayment period: 25years, grace period: 7years, and other conditions, such as the present gas price: 1.93 Taka per m3, urea sales price per ton for production increase, reflecting the present import price, :US$ 120, have been presumed Consequently, 9.04 % of Internal Rate of Return (IRR) has been obtained.

As a result of calculating the reduction effect to greenhouse effect gas cost on the basis of the investment amount and greenhouse effect gas reduction, annual C02 generation volume per US$ 1 million of investment amount is estimated to decrease by 407 tons(=7,7698 -F 19,106).

In addition to the above energy saving effect and production increase effect, BCIC’s requirements for betterment of plant environment and more than 10 years prolongment of urea manufacturing equipment as well as maintenance of function as a fertilizer supply base in the area of Fenchugangi will be attainable, if this project is materialized. Under the circumstances, a great deal of enthusiasm for realization of the project are now displayed by NGFF and BCIC.

(4) Despite the fact that Bangladesh, as a recipient country of foreign aid, supports its domestic economy by foreign assistance fund and NGFF is a state-run enterprise, its investment for plant efficiency is restricted due to the country ’s difficult financial conditions, and NGFF is compelled to operate its plant at extremely low- efficient level.

From employment security viewpoint, this plant ’s significance for existing is of great importance in the area of Fenchugangi, although it is such fertilizer plant as having continued its operation for 40 years since its start-up. In this project, an effect of greenhouse effect gas reduction to expenses is relatively high and IRR comes up to the acceptable level of 9.04 %.

Also, implementation of this project, if combined with CDM project, will contribute to CO2 reduction in Japan. In the process of our investigation of this time, a great deal of enthusiasm for materialization of this project was shown on the side of Bangladesh. Since cooperation and maximum efforts to be made mutually by both parties were ascertained for such realization, our endeavors for realizing this project will be continuously made in the future. Such being the case, provision of ODA (Yen Credit) is strongly desired

(5) CHAPTER 1

BASIC COMPONENTS OF PROJECT CHAPTER 1 BASIC COMPONENTS OF PROJECT

1. Situation of Bangladesh

Area 147.000 Km2 (Approximately 2 times as large as Hokkaido) Population 126.900.000 people Population growth rate: 1.7 % (World Population White Paper/1999) Capital Dacca Race Mostly occupied by Language Bengali (National language) Adult literacy rate 44 % (Male 50 % /Female 27 %) (Bangladesh Bureau of Statistics) Religion Islam 88 %, Hindu 10.5 %, Buddhist 0.6 %, Christian 0.3 % (National census/ 1991) Japanese resident : 440 persons (As of October, 1999 )

1.1. Political, Economic, Social Conditions

(1) Political conditions Since the establishment of Government headed by Sheik Hashina in June 1996, a state of confusion caused by the friction between the party in power and non-government parties has continued. Bangladesh Nationalist Party, leading party among non-government parties, had developed consistently its movement to overthrow Awami League Government. Although National Party, 2nd party among non-government parties, overthrew the former Bangladesh Nationalist Government headed by Karena Jina in cooperation with Awami League and assisted the establishment of Awami League Government, it has joined the movement to overthrow Awami League Government with Bangladesh Nationalist Party. Meanwhile, the former President El Shado, head of National Party, has been put into prison for reason of corruption during the term of his service and now on trial.

From the first, there have not been much differences in the policies of Awami League, Bangladesh Nationalist Party and National Party. With Bangladesh political parties having no strong financial bases, concessions monopolized by party in power, including official post, subsidy and public works, often cause political friction. In addition, there have been many casualties, thanks to seriousness of boycott for Parliament discussion

— I— i — and Hartal (Political demonstration for producing general Conditions) in the street. It is, however, prominent that non-government parties have broken their steps. Some members of non-government parties stood as candidate and won the election, which relevant parties instructed to boycott. In National Party, there is such movement that some members support Awami League. Reflecting such movement, Awami League is successful in securing a stable majority. It is said that justification of the present regime has been lowered due to some members’ open participation in activities of terrorism or unfair practice in election. Disturbance of public order is worried about, in view of the fact that Islam extremists train coups for activity of terrorism with financial aids from international organization and East Bengal Communist Party, which acted as extreme terrorist party in the past, has changed itself as underground criminal organization and has committed crimes repeatedly.

As next general election is scheduled to be made in July 2001 when the tenure of the present regime expires, there are frequent occurrences of Hartal led by non-government parties.

1) Political system • Domestic administration

Form of government : Republicanism Head of state : President Shahhabudin Armedo Parliament : One house system (Total seats: 330) (30 are, however, reserved for women) Prime Minister : Sheik Hashina

2) Diplomacy & National Defense

Diplomatic policy Maintenance of friendly relations with neighborhood countries as well as reinforcement of cooperative relations with Western aid countries, including Japan. Non-alliance group, Member of Islamic Countries ’ Conference, Member of the British Commonwealth. From January 2000, the country has been inaugurated as a permanent member of United Nations Security Council with term of 2 years. In March 2000, the country ratified CTBT as the first country in South area. Military strength Budget-28.34 billion Taka. (Ratio to ordinary budget 17.8%)(1998/99) Military service Volunteer system

-1-2- Troop strength : Army-101,000 persons, Navy- 10,500 persons, Air Force-6,500 persons

3) History

13 th century : Muslims dominated Hindu ’s territory 18th century : British domination was maintained. 1947 : The country achieved independence as a part of Pakistan and became State 1970 : After the independence of Pakistan, Awami League, requesting state autonomy, became the leading party at the first general election. Confrontation with became crucial. 1971 : Civil war occurred. And it brought about the India-Pakistan War with military invention of India for the purpose of assisting East Pakistan. As a result of surrender made by Pakistan Government Army , the People’s Republic of Bangladesh was established. The first President was Sheik Mujibaru Raman. And the present Prime Minister is his eldest daughter. At the beginning of its independence, the Government took presidential system. Dissatisfied with the Government ’s line favorable to India and the President ’s action to make his son the Chief of the General Staff in army, a group of young commissioned officers carried out a coup d ’ etat and killed the President together with his family, except two daughters abroad. (6 years-old boy was included) After then, military regime continued for a period of time. 1979 : Bangladesh Nationalist Party (BNP) Government headed by Jauru Raman was established. 1981 Since Jauru Raman was killed by counter force in the military, Vice President Sattaru took over the Presidency. 1982 After the President Sattaru was overthrown through a bloodless coup d ’ etat by Elshad, the Chief of the General Staff in army, in March, the Constitution came to a standstill and military regime assumed the governmental position. 1986 Elshad formed his own party, “National Party” and managed to take a majority in the General Election held in May. 1988 While National Party headed by Elshad won an overwhelming victory over the General Election held in March, non-government parties boycotted the Election. 1990 More than 130,000 people were killed by a record sized cyclone. While anti-government protest action became active, President Elshad, who continued vigorous administration for about 9 years, resigned due to repeated corruption and bribery. (Now in prison) 1991 As a result of the General Election in March, BNP became a leading party, while National Party slid down to third party. Begum Kareda Jia, wife of the former President Jauru Raman, became the first woman prime minister. Prime Minister Kareda Jia filed a proposal to amend the Constitution for returning to Parliament Members’ Cabinet System from Presidential System and obtained its approval through a national referendum in September 1991. 1994 With disastrous defeat of the party in power in the Local Election held in January, political friction occurred among non-government parties, including Awami League, which gathered strength as a second party. Consequently, Parliament members of non-government parties resigned all at once, asking for early implementation of General Election in 1995. 1996 Although General Election was held at the time of completion of 2 years term, it was boycotted by major non-government parties. While anti-government protest action by non-government parties became active, politics and economy were at a complete standstill. In March, Prime Minister Jia resigned, and election administration cabinet started. As Awami League assumed its regime again with a lapse of 21 years as a result of the General Election held in June, Hashna Awami, eldest daughter of the first President Mujitaru Raman, became Prime Minister

— 1 — 4 — and has continued her service up to the present. Also, General Election is scheduled to take place in 2001.

(2) Economic conditions

1) Summary on economic aspects

Based on the fact that GNP per capita is less than 300 US$ in Bangladesh, it is said that most people suffer extreme poverty. Under the background, there are losses of properties due to natural disasters, such as flood and cyclone, and increase of population attributable to the birth rate highly remained. Bangladesh, aid recipient country, has supported its domestic economy with overseas aids funds provided for reason of its poverty.

Dacca, capital city, has recently attained a rapid development, and economic activities seem to have become active with a remarkable increase of traffic volume, including passenger cars and trucks.

As a result of BNP Government ’s tackling economic structural reform under the guidance of World Bank and IMF, a remarkable performance, such as reduction of financial deficit and improvement of International Balance of Payment, has been achieved. The growth rate of GDP remains, however, at low level. After establishment of Awami League regime in June 1996, comparatively stable economic growth has been attained. Thanks to deluge in 1998, slowdown of GDP growth in 1998/99 is now worried about. While gross production of food grain came up to the 20 million tons barrier for the first time in 1998/99, food self-support rate remains at around 90 %. Also, the industrial ratio to GDP, driving force of economic growth, still remains at a little more than 10 %. The continuous achievement of growth rate at the level of 7 % p.a. is required to overcome the .

Table I — 1 Table of economic summary

Agriculture, Weaving & Knitting Product Industry, Main industries Jute Processing Industry Main trade items (1997/98) Export Weaving & Knitting product, Frozen food, Jute product, Leather goods Import Capital goods, Textiles, Crude oil & oil product, Steel Main counterparts of trade (1996/97) Export United States, United Kingdom, Germany, France, Belgium, Netherlands Import India, China, Japan, Singapore, United States, Germany

(Source: Ministry of Foreign Affairs HP) 2) Economic Indicators (Unit: US$, Period: From July through June of each year)

Table I —2 Economic Indicators

Currency Taka (TK) Exchange rate 1 US $ =49.5 Taka (April, 1999) 55.5 Taka (2000) GDP 33,897 million (1997/98) Per capita GDP 268 (1997/98) Economic growth rate 5.6% (1997/98) Increase rate of commodity prices 7.0% Unemployment rate 26.0 % (1994, World Bank data) Gross trade amount (1997/98) Export 5,172 million, Import 7,524 million Debt service ration 8.6% (1997/98)

(Source: Ministry of Foreign Affairs HP) Sources of item 2~12 : Bangladesh Bureau of Statistics, Ministry of Finance, IMF data, etc. There is an agreement on structural reform plan with IMF and World Bank. 3) Economic cooperation

Table 1 — 3 Economic cooperation

Main aids countries (DJapan ©United Kingdom ©Netherlands (ODA White Paper 1996) ©Canada © Germany Actual results of aids from Total: 129.98 million US$ Japan (ODA White Paper) Onerous financial cooperation (Net disbursement, 1998) 50.14 million US$ Gratuitous financial cooperation ( » ) 216.35 million US$ Technical cooperation ( n ) 22.83 million US$ Bilateral relations: (Japan/Bangladesh) Political relations Based on economic & technical cooperation, friendly relationships have been developed. Pro-Japanese Economic relations Trade with Japan (Trade White Paper) Trade amount (1995) (1996) (1997) Export 146 million 143 million 130 million US$ US$ US$ Import 347million 345 million 317 million US$ US$ US$ Main item Export Shrimp, Textiles, Textile raw materials Machinery & equipment, Metal product, Import Chemical product Direct investment from Japan (Monthly Financial & Monetary 52 cases, 22,4 billion US$ Statistics Report, MOF)

(Source: Ministry of Foreign Affairs)

(3) Social conditions 1) Summary on social aspects In Bangladesh, economic gap between city district (Dacca) and rural districts tends to widen, due to recent economic development. In rural districts, there are many people who are unable to get out of poverty, thanks to losses of properties attributable to annual repeat of flood and cyclone and high birthrate. As most of these people gather in Dacca, large city, to seek for better living and occupy wetlands and side place of railroad track in the city, its living circumstances become worse. The number of street children and beggar keeps on rising.

-1-7 While rubbish in Dacca amounts to 9,000 tons/day, 300 tons out of the rubbish, including glass, steel and paper, are recycled by poor people, but 400 tons are left on road. Capacity of sewage disposal in Dacca is only 20 % and 40 % is individually disposed. The remaining portion is discharged as it is.

Rikisha-man is an easy job for people coming from rural districts. If a man hires such Rikisha from its owner by paying about 1 US$/day, he can earn income from that day. Under the circumstances, the downtown of Dacca is crowded with many Rikishas. And economic activities are hindered, due to traffic congestion caused by crowded-ness of Rikisha. When the authority concerned tried to shut Rikisha out from main street (Milple Street) in the city, Rikisha men started a riot for protesting such exclusion, resulting in more than 50 injured persons. As of January 2001, exclusive lines are set up partially in main streets of Dacca. (See Photograph I — 1 and I — 2)

Photograph I — 1 Rikisha Photograph I —2 Slum

In rural districts, repairs of roads are always required due to coverage of water attributable to flood. Since gravel needed for road works is insufficient in Bangladesh, pebbles in rivers are carried out from the neighborhood of national border with India and used for such works after cracking by hammer. Sometimes red bricks are used for road floor after cracking. Relied on jobs, such as carrying earth and sand for road works and cracking pebbles and red bricks, many people coming from rural districts make their livings. As introduction of construction machinery, including conveyor, takes their jobs, there are many resistances. In Bangladesh, continuation of such insufficient industrial • economic • social activities provide many people with working places. Unless population problem is resolved, labor saving and efficiency will not be achievable.

At present, households receiving electricity supply in Bangladesh account for only 15 % of the total. In rural districts, lamps burning kero sine are widely used for lighting. In respect of fuel for cooking, woods and cattle’s dung are used.

In Dacca, city gas is used in ordinary households. Gas rate is calculated under fixed amount system, due to difficulty in providing gas meter with each household by gas supply company. In case of portable cooking stove with 2 burning points, rate is 288 Taka per month. Spread of electricity contributes to betterment of standing position and living standard in rural districts.

1-9- State-run television broadcasting in Bangladesh televises many programs providing easily understandable information with viewers, including illiterates.

Cellular phone has recently started to spread, since many years were required to wait until set-up of fixed telephone at home by telephone company. There is, however, a fear that telephone companies facing with crisis will stop their connections with cable telephones.

With inclusion of arsenic in ground water, coming from tube well as drinking water, exceeding permissible range, it becomes a subject of discussion. Many countries, including Japan, have competitively provided Bangladesh with funds to set up tube wells, because surface water proved to be in-sanitary. Although outbreak of infectious disease has decreased considerably, the content of arsenic in ground water extremely exceeding the permissible range have been detected in around 90 % territories of the county. Despite of studies continued by the United Nations and other countries, prospect for resolving such problem is still far from certain.

2) Standard of reward (As of January, 2001, 1 Taka is equivalent to about 2 Yen) Road works laborer 100 Taka / day Rikisha man 150~200 Taka / day Ordinary laborer 150 Taka / day Office boy/ Cleaning man / Guard 5.000 Taka / month Driver 12.000 Taka / month Receptionist / Computer operator 15.000 Taka / month Clerk / Assistant programmer 15.00 Taka / month Accountant 25.000 Taka / month

1.2 Energy Conditions

In Bangladesh, energy production and distribution have been managed by state-run companies. Major natural resource in Bangladesh is natural gas. As of 1997, an estimated amount of workable deposits of natural gas is 300 billion m3 (Approximately 10 trillion scf) and annual supply volume comes up to around 7 billion m3. In respect of other energy source, such as oil, it depends on import, with availability of collecting minimum volume of condensate in natural gas field. Natural gas have been produced and sold by Petrobangla (Oil, Gas, Mineral Resources Corporation). Sales of imported oil are made by Bangladesh Oil Corporation. As for coal, there are coal-fields in Jamalganj, Peerganj and Brapukeria. Since coal seam in Jamalganj is such deep as 1,000 ms, it is not economical. In Brapukeria, 1 million tons of annual production is scheduled to start under guiadance of China from 2002. Although coal depends on import from India and is used mainly for baking bricks, it’s volume is very small.

In “Asia Research Center World Trend, December, 1998,” Page 23-28, JETRO reported in detail on energy conditions in Bangladesh (See Figure I— 1). Under entrustment on “South Asia Area (Bangladesh) Energy Multi-consumption Industries Basic Research Business ” from New Energy and Industrial Technology Development Organization, Japan Consulting Institute presented its report relating to energy conditions in Bangladesh in March 1991.

Bangladesh Oil Petrobangla Corporation Gas 7,005,000,000 m3 Exploitation

Oil 2,414,000 tons supply 3,0433,000,000 m’ 2,278,000,000 m ’ 256,000 tons

2,149,000 tons Electricity Bangladesh Development Bureau Chemical Industry Corporation 10,806 GWH electricityy generation Chemical fertilizer production 4,612 GWH 1199 GWH 3,003 GWH

Dacca Electricity Rural District ,307,000,000 m3 Supply Corporation Electrification Bureau

2,913 GWH 1,018 GWH

Consumers

Figure I—1 Energy conditions in Bangladesh

(Source: JETRO Asia Economic Research Center HP)

Since electricity supply capacity was 2,500 MW in 1999 and 300 MW short, compared with 2,800 MW of demand, electricity was often cut off. Cut-off of electricity supply causes not only stoppage of water supply, resulting in inconvenience on living conditions of citizens, but also slump of industrial production as well as reduction of new investment. According to the trial calculation made by World Bank, such cut-off pushes down GDP growth by 5 %. Except the case that Power Station constructed by Wahtoshira Co, U.S. started its regular operation in October 1998, there has not been any construction of new power plant

I—11 — since 1994/95. While the existing equipment superannuated, actual electricity generation capacity were inclined to decrease with peak time in 1994/95. Simultaneously, electricity demand increased continuously in parallel with spread of electric appliances and industrial growth. And its demand exceeded supply in 1996/97.

Of 3,091 GWH of power generation equipment capacity in 1997/98, 76.5 % depends on natural gas and 16.0 % relies on oil. And the remaining portion is hydraulic power generation. While actual generation capacity is 2,445 GWH, operation rate remains at 79 %. At present, Petrobangla sells natural gas to Electricity Development Bureau at the price of 53 Taka per 1,000 SCF. The cost of electricity generation by use of gas in Electricity Development Bureau amounts to 1.5 Taka per unit, (at the time of KW), and electricity is sold to Dacca Electricity Supply Corporation at the price of 1.72 Taka. And Electricity Supply Corporation sells its electricity to end users at the price of 2.45 Taka per KW. Based on the fact that most of electricity supply volume are, however, treated as “system loss”, a sizable amount of accounts receivable are un-collectible. Most of losses are caused by pilferage of electricity. Even government agencies, such as state-run companies and local self-governments, are in arrears on a lot of electricity rate. According to data for 1994/95, Dacca Electricity Supply Corporation supplied 4,612 GHW in total, while rates for 2,913 GWH, equivalent to around 63 % of the total, were collected. Of 1,220 billion Taka of accumulated un-collected rates by Dacca Electricity Supply Corporation, 23 % were due to government agencies’ arrears. Since Electricity Supply Corporation suffers from deficit attributable to a huge amount of system loss, the Corporation is in arrears on electricity rates payable to Electricity Development Bureau in amount of 15.47 billion Taka. Consequently, Electricity Development Bureau is in arrears on gas rates payable to Petrobangla in amount of 2.58 billion Taka. As Electricity Development Bureau has to live on other financial sources for repaying loans relating to the existing equipment construction due to its deficit, it incurs un-availability of increase and repairs of generation equipment, reduction of equipment operation rate and frequent occurrence of electricity cut-off.

Electricity Development Bureau has concluded with a foreign company an agreement on construction of new generation equipment with 2,40 MW capacity at the time of completion of 5th five year plan. In October, 1998, Khulna Power Station constructed by Wahtoshira Co, U.S. started its operation. For the purpose of obtaining supply of natural gas required for newly installed generation equipment, introduction of foreign capital has been made by Gas Development . Pertobangla and Electricity Development Bureau decided to purchases gas and electricity in a lump from foreign companies, respectively. As the result of this method, Bangladesh Government is neither required to bear equipment construction cost, nor responsible for management. Since electricity and gas rates are politically lowered,

1-12- electricity and gas purchased from foreign companies are at high cost and their prices exceed sales prices of Electricity Development Bureau and Petrobangla. Petrogangla, which was unable endure back spread, raised gas rates by 15 % in December 1998 and by 15 % in September 2000, respectively. Meanwhile, Electricity Development Bureau raised electricity rates by 4.7 % in July 1999. Further to say, it has to pay electricity and gas rates in foreign currency to foreign companies. Since both of Electricity Development Bureau and Petrobangla have no capacity for raising foreign funds, Ministry of Finance is worried about their arrangement. As foreign companies are doubtful of the Government ’ capacity for raising foreign funds, they ask for permission to export natural gas. In view of the situation that gas consumption volume during the term of 5th five year plan is estimated to be 2 trillion cubic feet and its estimated deposits amounts to approximately 10 trillion cubic feet, the country cannot afford to export natural gas in large quantity. The policy for expanding electricity supply capacity in early stage through energy development by use of foreign funds seems to be reasonable in short term, but it entails much financial burden in long term.

Although Occidental Co.,US caused a large scale of explosion accident in gas working site of Megruchara, and such 6 trillion Taka of damage, as estimated by Ministry of Environment and Forest, was brought about, the company withdrew from Bangladesh without paying any compensation. The reinforcement of gas production capacity was projected in expectation of power station ’s expansion, but supply volume of natural gas exceeded its demand extremely, thanks to considerable delay of power station construction plan. It is a grave issue in energy division.

To avoid recurrence of such trouble in the future, Bangladesh Government concluded with U.S. Government in December 1998 an agreement, in which financial and technical aids as well as overall policy suggestion would be provided for the purpose of evaluating merits and demerits of projects to be promoted by foreign companies.

Data relating to energy program in Bangladesh are shown in Table 1—4 through 1—12. These are quoted from official HP of JETRO Asian Economic Research Center.

Table 1 — 4 Main gas wells in Bangladesh, their production volumes and estimated amounts of deposits are shown. Table 1 — 5 Power stations in Bangladesh and their generation capacities are indicated. Table 1-6 Energy supply and consumption in Bangladesh is set forth. Table 1-7 Equivalent energy conversion into standard oil is indicated. Table 1-8 Electricity generation equipment, actual electricity generation capacity and demand & supply are shown.

-1-13 Table 1-9 Future construction plan for new electricity generation equipment is set forth. Table I —10 Supply & demand trend forecast for electricity and gas (at the time of projection for 5th five year plan) is indicated. Table I-11 Mining areas allotted to foreign companies. Table I-12 Energy used ordinarily in and rural areas are set forth. Table I —4 Main gas wells, their production volumes and estimated amount of deposits

Natural gas (1 billion cubic feet) Oil & liquefied gas (1,000 barrel) Deposits Deposits Code Place name Workable Remainin Workable Remainin up to the up to thee deposits g deposits deposits g deposits present present Exploitation by Petrobangla BK Bakhrabad 867 549.8 317.2 2,130 763 1,367 FE Feni 80 39.5 40.5 243 87 156 HB 1,895 655.7 1,239.3 100 28 72 KT Kail ash Tila 2,529 151.5 2,377.5 27,560 1,208 26,352 MG Meghna 104 6.2 97.8 210 210 NR Narshingdi 126 13.6 112.4 310 8 302 RP Rashidpur 1,309 124.4 1,184.6 4,000 108 3,892 SN Shaldanadi 140 1.6 138.4 420 420 SY 266 161.3 104.7 890 551 339 TT Titas 2,100 1,513.3 586.7 3,020 1,890 1,130 Management by Petrobangla (Production is stopped at present) CH 1,140 26.5 1,113.5 80 80 KA Kamta 195 21.1 173.9 40 40 Exploitation by foreign companies SG Sangu 848 1.2 846.8 Future developments (led by foreign companies) BB Beani Bazar 167 167.0 1,820 1,820 BG Begumganj 15 15.0 10 10 FG Fenchuganj 210 210.0 520 520 JL Jalalabad 900 900.0 15,750 15,750 KB Kutubdia 468 468.0 SM Semutang 98 98.0 20 20 SB Shahbajpur 333 333.0 Total 13,790 3,265.7 10,524.3 57,123 4,643 52,480

(Source) Data of natural gas are quoted from data on August 1998 in Bangladesh Bureau of Statistics Pocketbook Bangladesh 98, p 239. Data of oil & liquefied gas are cited from data on February 1997 in Petrobangla, Exploration Opportunities in Bangladesh, p 26: Statistical Yearbook of Bangladesh 1997, p 262. Code and place names are cited from Petroleum Exploration Opportunities in Bangladesh pp 26-28, Natun Bhuchittrabalee, p 14. Note: Jalalabad gas well developed by Occidental Co.,U.S. started its regular operation from February 1999.

-1-15- Table 1 — 5 Power stations and their electricity generation capacities (Unit: MW)

Name Designed generation Actual generation Code Fuel (All of them are under control of capacity capacity Electricity Development Bureau) AS Ashuganj gas 724 550 BR Baghabari oil 71 71 BS oil 47 37 BH Bheramara oil 60 40 BL oil 6 2 BO oil 8 7 FG Fenchuganj gas 90 60 OH Ghorasal gas 740 680 HP Haripur gas 99 90 KT Kaptai hydraulic 230 230 KL Khulna oil 249 79 RJ oil 2 1 RG Rangpur oil 20 20 RZ Rauzan gas 420 360 SP Saidpur oil 28 18 SH Shahjibazar gas 96 80 SD gas 60 6 SK Sikalbaha gas 116 92 SY Sylhet gas 20 20 TG Thakurgaon oil 6 3 Total 3,091 2,445

(Source) Data on October 1998 quoted from NEDO’s report on “Local conditions of energy consumption efficiency” 1999, pi 57-158 and Natun Bhuchittrabalee, p 15. Table I — 6 Supply & consumption of energy (1994/95)

Crude oil & Natural gas Electricity petroleum product (1 million m3) (at the time of (1,000 tons) GW) Domestic production & 10 7,005 10,806 electricity generation Import 2,529 Supply Export -157 Stock adjustment 32 Total supply volume 2,414 7,005 10,806 Electricity generation 256 3,043 Loss in transportation & 9 372 3,232 transmission of electricity Own consumption 5 640 Ordinary household 434 515 2,688 Commerce & service 104 655 Consumption business Industry 151 688 2,859 Transport & traffic 1,140 Agriculture & others 424 732 Use as raw materials for 2,278 fertilizer Total consumption 2,414 7,005 10,806 volume

Note : At the time of 10,806 GW in domestic electricity generation, hydraulic generation at the time of 372 GW is included.

-1-17- Table 1 — 7 Equivalent energy conversion into standard oil (lOOOtons)

Crude oil & petroleum Natural gas Electricity product Domestic production & 10.19 6,456.51 929.32 electricity generation Import 2,578.83 Supply Export -160.10 Stock adjustment 32.63 Total supply volume 2,461.55 6,456.51 929.32 Electricity generation 261.04 2,804.73 Loss in transportation & 9.17 342.87 277.95 transmission of electricity Own consumption 4,61 55.04 Ordinary household 442.55 474.68 231.17 Commerce & service 95.86 56.33 Consumption business Industry 153.97 634.13 245.88 Transport & traffic 1,162.46 Agriculture & others 432.36 62.95 Use as raw materials for 2,099.63 fertilizer Total consumption 2,461.55 6,456.51 929.32 volume

Note: Conversion value of hydraulic generation volume comes up to 124,470 tons. (Source) Bangladesh Bureau of Statistics, Statistical yearbook of Bangladesh 1997, pp 251, 256

Table 1 — 8 Electricity generation equipment, actual electricity generation capacity, and demand & supply (Unit: MW) Electricity generation equipment Actual Electricity Gap electricity demanded between Year Thermal Thermal Hydraulic power power Total generation at peak demand by oil by gas capacity time and supply 1984/85 130 446 564 1,140 1,018 887 131 1989/90 230 444 1,678 2,352 1,834 1,509 325 1994/95 230 682 1,995 2,907 2,133 1,970 163 1995/96 230 682 1,995 2,907 2,105 2,087 18 1996/97 230 682 1,995 2,907 1,768 2,114 -346 1997/98 230 496 2,365 3,091 2,445 2,806 -361

Source : Statistical Yearbook of Bangladesh 1997, p 257; Planning Commission, The Fifth Year Plan 1997-2002, p 238; Ministry of Finance, Bangladesh Economic Review 1998, p 54; Artha Mantranalaye, Bangladesh Arthanaitik Shameekhha 1999, p 68 ; The Daily Star, 4 April 1998 Table 1 — 9 Future construction plan for new electricity generation equipment

Electricity generation Code Place name Fuel Remarks capacity (MW) Management by Electricity Development Bureau BP Bara Pukuria Coal 300 To be completed in June, 2002 GH 210 Operation was commenced in January, 1999, due to delay of Gas completion originally scheduled in March, 1998 HP Haripur Gas 109 To be completed in March, 2000 RZ Rauzan 210 Operation was commenced in Gas September, 1997 SH Shahjibazar Gas 60 To be completed in June, 2000 SD Siddhirganj Gas 210 To be completed in March SY Sylhet Gas 90 To be completed in June, 2001 (Site is undecided) Gas 200 To be completed in June, 2002 Total 1,389 Construction & management by foreign private companies BI Baghabari 100 The completion originally Oil/gas scheduled in June, 2000 has been changed and will be after 2001. HP Haripur 360 The completion originally Gas scheduled in June, 2001 will be delayed considerably. KL Khulna 110 Regular operation started from Oil/gas October2, 1998. KL Khulna Oil/gas 210 To be completed in June, 2002. ME Meghnaghat 450 The completion originally Gas scheduled in June, 2001 has been changed and will be after 2003. MY 60 The completions originally Gas scheduled in June, 1999 were delayed considerably. Power station on board 400 The completions originally (4 places) Oil/gas scheduled in June 1999 were delayed considerably. Overall development plan for 350 In respect of Uncol Co’s Western District proposal ,U.S. Government Gas supported , while World Bank is doubtful. Total 2,040

Source : The Fifth Five Year Plan 1997-2002, p 342; The Daily Star, 17 Jan. 1.Feb.5 20 May jul. 1999

-1-19- Table I —10 Supply & demand trend forecast for electricity and gas (At the time of projection for 5th five year plan)

Annual demand volume Actual electricity Electricity demanded at Year of natural gas generation capacity (MW) peak time (MW) (1 million cubic feet) 1997-98 2,813 2,806 365 1998-99 3,464 3,109 410 1999-00 4,342 3,447 438 2000/01 5,156 3,736 455 2001/02 5,739 4,051 495 Total 2,163

Source : The Fifth Five Year Plan 1997-2002, pp 342, 359

Table I — 11 Mining areas allocated to foreign companies

Mining area Company Remarks (1st allocation of mining area) 12 Occidental (US) Contracted on January 11, 1995 13 • 14 Occidental Contracted on January 1 1, 1995. Gas explosion accident on June 15, 1997. 15 Cairn (UK) Contracted on June 12, 1995. 16 Cairn Contracted on May5, 1994. On June 12, 1998, Shangu gas well started its regular operation. 17 • 18 Rexwood (US) • Contracted on January 18,1997. Oakland (US) 22 UMIC (US) Contracted on February 16,1997. (2nd allocation of mining area) Decided companies made bids on July 25,1998 3 • 6 Enron (US) • Oakland 5 Shell (Netherlands) • Cairn 7 Triton (US) • Unocal(US) • PTI (Malaysia) 8 Pangaea (Canada) • OMV (Austria) Mining area, where some companies made bids, but no order has been placed 9 Competed with Tullow (Ireland), Chevron (US) and Texaco (US) 10 Competed with Unocal, Shell and Cairn 11 Competed with Tullow, Mobil (US) and Petronas (Malaysia)

Source : Petroleum exploration Opportunities in Bangladesh , pp 4-6 ; The Daily Star ,20, January 1998,13 June,27 July 1998; Data presented from Uchida, special investigator, Japanese Embassy in Bangladesh

1-20 Table 1—12 Energy used ordinarily in cities and rural areas (%)

Households in Households in Whole country cities rural areas Kerosine lamp 36.73 90.47 84.73 Electric lamp 62.77 8.59 14.37 Lighting Others, 0.50 0.94 0.90 Total 100.00 100.00 100.00 Firewood 57.63 42.67 44.25 Kerosine burner 2.32 0.36 0.57

Fuel for Gas portable cooking stove 20.43 0.20 2.37 cooking Electric cooking utensils 5.12 0.38 0.88 Others 14.50 56.39 51.93 Total 100.00 100.00 100.00

(Source) Bangladesh Statistical Pocketbook 98, p 164

1.3 Needs for CDM Project

In Bangladesh, its economic development as well as reduction of influence attributable to global warming are expected through materialization of CDM project. Since it has a mechanism consistent with national interest, needs for CDM are extremely high in the country. It is understandable from the fact that Bangladesh Government made a great deal of effort in the United Nations Framework Convention on Climate Change. The reasons of strong needs for CDM in Bangladesh are able to summarize as follows.

CD As most of its territory are zero meter high above sea level, Bangladesh is troubled with natural disaster, such as flood and cyclone, in rainy season every year. And it is apt to be influenced badly by global warming due to localized torrential down sour, attributable to climate condition change, and estimated rise of sea surface. Reduction of greenhouse effect gas generation through implementation of CDM project is a matter of great concern in Bangladesh.

® Up to the present, Bangladesh has maintained its domestic economy with direct aids funds from overseas for reason of its poverty. Recently, Bangladesh Government and people pose questions on infinite continuation of such foreign aids. Such opinion that development of its domestic industries by themselves, activation of economic activities and betterment of people’s living standard should be made through introduction of investment from overseas becomes predominant. Activation of investment from overseas through implementation of CDM project is of great importance to development of Bangladesh as well as slough-off from aid receiver position.

(3) Natural gas is the most important natural resource in Bangladesh. At present, 3/4 of natural gas is consumed for electricity generation, basic industry, and production of chemical fertilizer. Although estimated deposits are regarded as 10 trillion SCF (Approximately 300 billion m3), there is a possibility of its drying in the future, owing to annual increase of necessary volume, although annual supply remains around 7 billion m3. Such being the case, materialization of energy saving in natural gas massive consumption basic industries and reduction of natural gas consumption through implementation of CDM is much significant to Bangladesh.

2. Necessity for Introduction of Energy Saving Technology in the Targeted Industry

With 7 plants of urea in Bangladesh shown in Table 1 — 13, they are divided into 2 types of equipment, including urea manufacturing equipment with old-fashioned process and large equipment with adoption of new process. NGFF and PUFF have the former typed equipment, while other plants have the latter equipment. Since the former equipment has old typed process, energy efficiency is extremely low. Meanwhile, as the latter is highly efficient equipment with application of new typed process, energy saving effect obtained from process change is not expected to be large. In a report on “South Asia Area (Bangladesh) Energy Massive Consumption Industries Basic Research Business ”, 1998, a trial calculation on energy saving effect through process change with application of collection of wasted heat and absorption typed refrigeration process is made, by taking advantage of CUFF Fertilizer Plant, as a model case. According to the above report, 1.8 % of energy saving effect is attainable, but only small merit is obtainable.

1-22- Table 1—13 Table for Urea Fertilizer Plants in Bangladesh

Location Production Production Plant name Process (Time of Unit name capacity capacity (Abbreviated title) Licensee completion) (Ton/year) (Ton/year) Natural Gas Fertilizer Co Fenchuganj Ammonium 203 65,000 Chemico (NGFF) (July, 1962) &, Urea 340 100,000 Chemico Urea Fertilizer Co (UFFL) Ghorasal Ammonium 824 272,000 Kellog, (September, &, Urea 1,422 470,000 Toatsuo 1972) Zia Fertilizer Co (ZFCL) Ashuganj Ammonium 930 307,000 Uhde, (July, 1983) &, Urea 1,600 528,000 Stami Polash Urea Co (PUFL) Ghorasal Ammonium 170 56,000 China (July, 1988) &, Urea 305 95,000 China Chittagong Urea Fertilizer Chittagong Ammonium 1,000 330,000 Kellog Co (CUFL) &, Urea 1,700 561,000 Toatsu Jamna Fertilizer Co. Jamna Ammonium 1,000 356,000 Tom, (JFCL) (July, 1992) &, Urea 1,700 561,000 Snam Karunafuri Fertilizer Co. Chittagong, Ammonium 1500 500,000 Tom, (Kfco) (April, 1995) &, Urea 1725 575,000 Stami

In these large-sized urea fertilizer plants with application of new process, production volumes have decreased due to super-annuation of equipment and imperfection of maintenance. Simultaneously, unit cost of natural gas per ton of urea has increased. Our recent investigation has revealed that actual production volumes in UFFL, ZFCL and JUFL declined to 71.7 % on the average in 1999/2000. In respect of energy consumption volume increase, 18 % up in ZFCL, 20 % up in UFFL and 22 % up in JUFL are estimated, compared with 18 % increase in CUFL Fertilizer Plant at the time of investigation released by the report on “South Asia Area (Bangladesh) Energy Massive Consumption Industries Basic Research”.

In the case that reliability on machinery & equipment is recovered through application of maintenance of these new processes in large-sized urea fertilizer plant as well as implementation of adequate maintenance for each machinery & equipment, a remarkable energy saving effect with increase of operation rate will be achievable, compared with the present level. Since these new typed plants have large capacities, energy saving effect and production increase effect will be extremely effective, compared with those of NGFF. Necessity for introducing energy saving technology in Bangladesh ’s targeted industry is, therefore, very significant.

1-23- 3. Significance, Needs of the Project and Spread of the Performance to Peers Group

3.1. Significance, Needs in Implementation of the Project

(1) Greenhouse effect gas reduction effect

With extreme super-annuation of the targeted plant and fuel basic unit being

approximately 2 times as much as the average fuel basic unit of other large-sized urea fertilizer plants, there are needs for its reduction through introduction of energy saving

technology on the side of Bangladesh. Since CO2 reduction equivalent to 76,450 tons oil conversion is achievable through implementation of the project and a great deal of contribution to prevention of global warming, including a partial contribution to CO? reduction volume in Japan, on thee basis of Kyoto Protocol through its combination with CDM is also available, implementation of the project is very significant.

(2) Foreign currency saving effect Production increase effect of around 24,800 tons of urea product is obtainable only through implementation of the project. The volume equivalent to the volume of urea being presently imported is reducible. Saving of foreign currency amounts to 3 million US$ annually, on the assumption that import price per ton per ton is 120 US$ Based on the possibility of spread of energy saving technology in the project, approximately 600,000 tons of production effect will be attainable in BCIC’s other large-sized urea plants on the basis of performance in 1999/2000, and it will, therefore, result in around 72 million US$ of foreign currency saving. Bangladesh has always maintained its domestic economy with aids funds from overseas for reason of most people ‘s suffering from poverty. In view of such situation, the possibility of saving foreign currency is very significant. Synergistic effect, obtainable from production increase effect and energy saving effect through implementation of the project, has the same effect as in case of export of wasted natural gas after its collection. Since reduction of external payment with foreign currency is achievable through implementation of the project, significance to Bangladesh ’s economy is extremely high.

(3) Environmental improvement effect

In NGFF Fertilizer Plant, neither introduction of new technology nor significant reduction renovation has been made, although some rehabilitation were executed, since its start-up in 1962. As Bangladesh maintains its domestic economy with aids funds from overseas and capital expenditures required nominally for environmental improvement are not practicable, the environmental conditions in neighborhood have become worse considerably due to increase of radiation of toxic substance in parallel with development of equipment’s super-annuation. Implementation of the project is expected to promote necessary modernization of production equipment, betterment of production, such as reduction of energy consumption volume and improvement of yield rate, and environmental improvement. Since NGFF’ s working environment for employees is of very poor quality due to contamination caused by copper liquid flowed from manufacturing process and bad smell attributable to leakage of ammonium gas and complains are often brought about from residents in neighborhood, needs for environmental improvement through implementation of the project are extremely high.

(4) Needs for maintenance of NGFF fertilizer Plant

With application of mixed gas refinery process by use of copper liquid in NGFF Fertilizer Plant, it has become super-annuated and inefficient plant. Judging from its depreciable life, it is not wrong, therefore, that it would be closed. Local investigation

clarified that more than 10 years operation would be endurable by repair of works of the existing old-fashioned equipment. Since employees of NGFF and residents in Fenchuganj area requested strongly for maintenance of the plant, Bangladesh Government had to withdraw its closing policy determined at once. Thanks to guarantee for employment and traders concerned and its function as a supply base for urea fertilizer to farmhouse and tea plantation, there are strong needs for implementation of the project on the local side.

3.2 Spread of its Performance to Peers Group

Among energy saving technologies to be introduced in the project, spread of its performance to peers group is not highly expected. As the performance coming from introduction of maintenance technology is very significant, its spread will be attainable. Maintenance technology is all-purpose technology. For example; How to select a targeted equipment among super-annuated and inefficient machinery & equipment? How to decide inspection method and inspection item? How to judge inspection results? Whether replace or repair? To what extent repair should be made? Is any repair method that doesn ’t influence production? Also, maintenance technology is comprehensive technology on the basis of experience accumulated in plant site for many years and applicable in other industry ’s plant, composing of similar type of machinery & equipment, except urea fertilizer plant. Although a lot of examination on betterment of operation rate and energy saving are always made in peers group or other plant, it is difficult for Bangladesh to make investment for nominal equipment improvement or modernization due to maintenance of its domestic economy heavily depending on aids funds from overseas. There is a possibility of the project’s performance being spread over in other plants of peers group, in which operation rate lowered and energy consumption increased.

-1-25- CHAPTER 2

SPECIFICATION OF THE PROJECT PLAN CHAPTER 2 SPECIFICATION OF THE PROJECT PLAN

1. Project Plan

1.1 Summary on the Targeted District in the Project (NGFF Fertilizer Plant)

(1) Climate Throughout the year, the climate in Bangladesh is divided into 2 seasons i.e. rainy season and dry season. Rainy season means the period from March through September, while dry season is the period from October to February. Dry season is in winter and its average lowest temperature is 15 °C during the period from December through January. Except the mention on general weather situation throughout the country in newspaper ’s weather information column, there is not enough information on weather in Bangladesh unfortunately and a bit of information is available in TV program. With low spread rate of TV in local areas, it appears difficult to keep citizen well informed of weather forecast. From the drawn through evening on October 28 when our investigation team stayed in Dacca, a storm came on suddenly, resulting in closing of air port and collapse of trees on the street. Due to lack of weather forecast for storm on the coast, many fishermen, who went fishing the night before, were reported as missing.

The weather trend and precipitation throughout the year in Dacca is shown in Table II —

1.

Table II — 1 Highest and lowest average temperature and precipitation in Dacca

Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Lowest 15 16 23 25 24 26 26 26 26 24 19 15 temperature (°C) Highest 26 29 34 34 32 32 31 32 32 33 30 28 temperature (°C) Precipitation (mm) - - 195 176 300 399 262 317 306 79 0 10

Fenchuganj, where NGFF is located, is situated at north-eastern point about 180 km away in direct distance from Dacca and the near national border with Magaraya District, India. Different from the other territories, most of which are less than 10 meters above sea level, Fenchuganj commands a view of mountains near the national border with India. These mountains lead to hilly country with more than 10 meters height. So its

-II-1 climate is slightly different from that of Dacca. Its neighborhood is a prominent rainfall territory and annual precipitation comes up to approximately 3,000 mm. In rainy season (summer), a lot of moisture-laden air generated in the Gulf of Bengal moves northward and produce up-drafts in mountains near the national border, resulting in a large quantity of rainfalls in neighboring plains. With a climate of high temperature and high humidity, Fenchuganj is hot and stuffy in summer. The progress of construction works in rainy season comes down to 60 % ~70 % of the progress in drying season. As most territories in Bangladesh are flooded in rainy season, rice farming is continued only in limited areas. As chemical fertilizer runs out after being dissolved in water due to flood, efficiency (fertilizer effect) declines. Since Fenchuganj is fortunately located at hilly country, it has rarely a flood in fields throughout the year. With low humidity, cleanness of air and coolness in drying season (winter), the climate during the period from October to February is very comfortable. Sometimes, lowest temperature declines below 10 °C. On January 14, 2001 when our investigation team stayed in Fenchuganj, the lowest temperature was reported to have come down to 5 °C. Although there is no long-term climate data in Fenchuganj, the data for the past 3 years is indicated in Table II-2.

Table II —2 Highest & lowest temperature and precipitation in Fenchuganj i

Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Highest 27.8 31.5 33.8 34.5 36.2 35.5 34.7 35.0 34.5 35.0 34.0 30.3 temperature (°C) Lowest 9.7 9.8 13.8 18.7 20.3 21.0 23.3 23.0 23.3 21.0 16.5 11.0 temperature (°C) Precipitation (mm) 32,7 1.7 174 250 489 448 523 371 315 96.1 53.5 0.3

(2) Geographical features

Fenchuganj, where NGFF Fertilizer plant is located, is situated at eastern longitude of 92 °C and northern latitude of 24”40’, which is nearly same as that of Taipei, and it lies at the southern point 20km away from Sylhet, principal city of State of Sylhet. Also, Fenchganj is situated at the northeastern point about 190 km away in direct distance from Dacca, and near the national border with Magaraya, India. In the country where most of the territories are less than 10 meters above sea level, Fenchuganj command a view of mountains near the national border with India, and neighborhood area is hilly country with many undulations. Most of hilly country is covered with tea plantations and a producing center for tea of good quality. In tea plantations, there are many rubber trees with certain intervals to avoid direct rays of the sun. Most of flat areas are paddy fields.

—II—2 — (3) Traffic

From Dacca, capital, to Fenchugannj, any of transport facilities, including railroad (train), road (car) and airplane, is available.

In case of railroad, 3 trains are available .in a day. Including waiting time for oncoming train due to single track operation, it takes, however, about 9 hours even by express train. In respect of class, there are 3 types, such as Shoven (Ordinary car), 1st class and A/C car. Their fares between Dacca and Fenchuganj are 180 Taka, 300 Taka and 700 Taka, respectively. Generally, the Japanese is reluctant to get on ordinary train. Since a ticket for A/C is not obtainable at once, it is necessary to purchase such ticket several days before boarding.

Meanwhile, it takes about 8 hours by car, owing to bad conditions of roads. Thanks to rough driving, there is a lot of risk of meeting traffic accident. Particularly, transfer during night is more risky due to lack of street- lamp. In Bangladesh, the number of death and serious injury accident occurrence comes up to 58 persons per 10,000 annually. It is more than 30 times higher, compared with 1.8 persons in Japan. In rainy season, streets are often blocked off due to coverage of water or much time is required for crossing river by ferryboat.

In case of airplane, it takes about 35 minutes from Dacca to Sylhet and additionally 1.5 hours from Sylhet to Fenchuganj by car. Prior arrangement for car from Sylhet to Fenchuganj is essentially needed. Between Sylhet and Fenchuganj, there is a crossing point over river by use of ferryboat, but a bridge is at present under construction. Since each of Bman and GMG runs 2 flights daily, it is recommendable to take use of them. While Bman is a state-run company which has Hokker’s jet-planes, GMG is a private company, which is aligned with British Airline (BA) and run Hokker’s propeller-plane with 2 engines. As GMG has a reputation for its punctuality to the minute, our investigation team takes always use of GMG’s plane. One way fare is 4,150 Taka.

(4) Communication Although NGFF Fertilizer Plant has an outside telephone, it often becomes inconvenient. Under the circumstances, it is rather impossible to communicate with NGFF Plant by use of direct telephone or fax from Dacca or Japan. NGFF is equipped with radio communication facilities for exchanging messages with BCIC’s Office, Dacca. NGFF ‘s communication with outside is usually made by use of telephone in NGFF’s Office located in the city of Dacca. The internal communication between NGFF Plant and Sylhet Office is made daily though messengers’ going back and forth. Sending a fax is the most certain method for communication with NGFF from Dacca or overseas. As there is an access point (9723701,09,10,11,17,27,30,35,43,45) of internet provider (Xirus Net) in Sylhet, it will be convenient if a communication method by e-mail is established in the future.

Many TV channels through satellite broadcasting are receivable. With set-up of parabolic antenna and decoder, NHK’s TV program for overseas broadcasting is receivable in Dacca. In addition to BBC and CNN, other programs in German, French, Bengali, Hindu, Urdu and Arabic are also receivable.

(5) Standard of living

In 1960, when NGFF was constructed and Bangladesh was called as East Pakistan, the population was approximately 50 million people. As the result of 2.6 times increase in the past 40 years, the present population is estimated as 130 million people.

The country area is around 140,000 km2, which is about 2 times as large as Hokkaido. The State of Sylhet, in which Fenchuganj is situated, occupies around 15 % of the

country area, with population of approximately 6 million people. While the Indian and the Pakistani in neighborhood countries come into Middle East and West European lineage in Aryan race, the Bangladeshi is an Oriental who lives on rice. It is said that GNP per capita amounts to around 300 US$ (1997) and many persons are troubled with poverty. On the background, there are losses of properties due to natural disaster, such as flood and cyclone, and increase of population attributable to highly remained birthrate.

The suburbs of Fenchuganj are interspersed with approximately 20 cottages, which run tea plantations, except NGFF Fertilizer Plant. Although these tea plantations were owned by British people, who lived there with their families, such plantations are now incorporated as companies and tea production is made by local people. See Photograph II-1.

—II—4 — Photograph II — 1 Vivid green-colored tea plantation

Most of residents in Fenchuganj are NGFF’s and tea plantations ’ employees and their families as well as cultivation farm families. Without particular industry in the neighborhood, there are only NGFF Fertilizer Plant, Fenchuganj, a power station with 90 MW, a cement plant, Chatak, and a pulp & paper mill, as a whole, in the State of Sylhet.

Most of people, who come from this part of the country and receive higher education in Dacca or overseas, don ’t come home due to lack of employment in this parts of the country. Many staffs of NGFF take up position without their families staying in Dacca. People of intelligent class don ’t like to reside permanently in this part of the country for reason of their sons ’ education. Bi-polarization between few people who received higher of education, such as university education or overseas education, and the greater part of people are widened considerably. Most of NGFF’s staffs are technical experts who received higher education. Their speeches and behaviors are logical, but they lack in practical actions. It is certainly due to the fact that caste system still remains.

Many people of more than lower-middle class are pyknic. There is a tendency that a pyknic is welcome, based on the reason that people have plenty of meals in wealthy family. In case of common people, many folks are lean due to undernourishment. They have, however, mild, good and humane personalities.

The Bangladeshi seems to feel inferior to Indian, and much interchange with India is not recognized in this part of the country near the national border. Since there are many ’ crossing the national border unlawfully, India has repeatedly asked Bangladesh to take appropriate steps.

—II —5 — (6 ) Language

Generally, Bengali is spoken in Bangladesh. At the time when Bangladesh was a part of Pakistan and called as East Pakistan, the Bangladeshi spoke in Bengali, while Urdu was spoken in Pakistan. Under the circumstances, English was used as official language in both countries for mutual communication. So there are at present many people who speak English in Bangladesh. The teaching English is quite popular and, in case of high school students, they can debate in English rapidly with strong accent. Almost all of the counterparts, who get in touch with our investigation team in business, have a talk with the team in English easily.

In the cities of Sylhet and Fenchuganj, common people ‘s literacy rate and education level are low. Most people speak Bengali only and cannot understand English.

(7) Religion

Most of Bangladeshis are Muslims. Together with Pakistan, Bangladesh had been under domination of Britain, as a state of India, for a long time since 1860s till the end of the war. In accordance with the commitment made during the 2nd World War, India became independent at first. And, for religious reason, Pakistan, mainly consisting of Muslims, gained independence from India, mainly consisting of Hindus. With distance of around 2,000km, Pakistan had consequently 2 territories, such as West Pakistan and East Pakistan, with India lying between both of the countries.

In Fenchuganj district near the national border with India, more than 90 % of people are

Muslims and about 6 % are Hindus. And the remaining people are Christians and Buddhists.

1.2 Details of the Project

With a lapse of 40 years after its start-up, machinery & equipment in NGFF have super-annuated. Repair works were implemented several times in the past. In the project, similar repair works with change of process will be executed, in view of environmental problem. As a concrete measure, various small works will be implemented accumulatively, and, with continuation of operation, points at issue will be resolved one by one. The results, which satisfy the following 4 items requested by BCIC, as mentioned in the “Summary”, and meet CDM ’s purpose, will be obtainable.

® To improve the Plant ’s production capacity up to the value originally projected (Measure for production increase)

— II —6 — (2) To facilitate a minimum of 10 years plant operation (Measure for prolongment of the Plant) (3) To reduce the basic unit of natural gas (Measure for energy saving) © To take environmental pollution into consideration (Measure for environment)

The project’s details for achieving its purpose are summarized as follows.

(1) Process improvement © Energy saving by means of preventing environmental pollution due to leakage of lean solution, with low temperature CO conversion and installation of metanator after abolition of synthesis washing equipment. (2) Energy saving through collection of hydrogen from purge gas in ammonia synthesis part. (3) Energy saving through collection of wasted heat, with installation of economizer in collectable heat circuit.

(2) Machinery & equipment improvement through maintenance © Supply of spare parts for emergency use and exchange & repair

(2) Exchange of machinery & equipment, which has become dangerous in continuous use, due to super-annuation (3) Supply of material for equipment (Steel plate, pipe, etc), by which repair or manufacturing at plant site become available. © Supply of machinery & instrument required to be installed for safe operation or operative efficiency © Supply of instrument & spare parts approved as necessary in machinery plant for maintenance, construction machine plant and analysis room

In parallel with the above, technology transfer, including improvement process technology and maintenance technology , will be made.

1.3 Greenhouse Effect Gas Targeted in the Project

Targeted gas is CO] in combusted gas discharged from natural reforming furnaces (2 units in regular operation) and electricity generation boilers (2 units out of 3 in regular operation). Although hydrocarbon (almost methane) in fuel and natural gas used at NGFF Fertilizer Plant is also greenhouse effect gas, it’s examination is out of target, since diffusion volume of methane leaked from relevant pipes and equipment is extremely small. Other greenhouse effect gas, such as fluorine gas, is not treated in the Plant.

II—7 The volume of CO2, diffused in the air, amounts to about 2,500 m3 / hour, coming from 2

units of natural gas reforming furnace, and around 10,000 m3, coming from 2 units of electricity generation boiler. The implementations of various energy saving measures in the Plant will bring about reduction of load in electricity generation equipment, resulting in decrease of load in electricity generation boiler and reduction of natural gas consumption volume. In addition, reduction of combusted gas and CO2 diffusion volume will be attainable.

2. Outline of NGFF Fenchuganj Fertilizer Plant

Although NGFF Plant was built up 40 years ago, its operation is still continuing with lessened efficiency, and annual production volume, exceeding more than 80 % of the projected volume, is maintained. The Fertilizer Plant must be the oldest urea plant in the world. 40 years operation has been continued, not only owing to accumulated operation & maintenance technology, but also due to comparatively strongly-made machinery. With un-development of compactness and flexibility technology seeking for economical efficiency at that time, structure, emphasizing sheer scale machinery & equipment with adoption of comparatively large factor of factor, appears to have been supplied. The machinery actually applied, particularly rolling mill, is large and strongly-made, compared with similar machinery prevailing at present.

Since the completion of its construction, the operation of NGFF Plant has been continued with own maintenance and inspection for 40 years. During the period, rehabilitation works were made by itself several times. Through Overseas Economic Cooperation Fund ’s financial support in the amount of 285.5 million Taka (Around 19 million US$), rehabilitation on relatively large scale was implemented during the period from 1978 to 1979 under technical assistance of Kobe Steel, Ltd. In 1987, rehabilitation on medium scale was executed with ODA’s fund in the amount of 95.9million Taka (About 3.2 million US$). Despite Bangladesh Government ’s decision to close NGFF in 1993, such decision was upset for reason of social conditions in this district of the country, and continuation of NGFF was determined. In 1995, overhaul was implemented with Bangladesh Government ’s fund amounting to 50.3 million Taka. By use of the Government ’s fund in the amount of 200 million Taka, rehabilitation works completing at the end of June, 2001 are in progress.

With production cost exceeding sales price, NGFF is continuing its operation in the red. It is due to the fact that NGFF’s basic unit of natural gas exceeds those of other fertilizer plants and urea product price is politically lowered. Although initial investment amount was amortized with a lapse of around 40 years after start-up, the outstanding balances of loan

—II —8 — provided for several rehabilitation works still remains. As annual maintenance budget is limited to 10 million Taka (20 million Yen) due to its operation in the red, implementation of sufficient repair works is unavailable every year and necessary works are carried over to following year one by one. The Government provides special fund with NGFF once in every several years for immediate completion of accumulated necessary works at the time when continuation of operation has become impossible. They are details of repair works.

Thanks to super-annuation and lack of maintenance & inspection and spare parts, the operation of NGFF Plant is often interrupted. Such interruption causes decrease of urea production volume as well as loss of energy (Natural gas) attributable to continuous operation of other equipment. It is due to the fact that excessive energy and time are required for shutdown and start up at the time of stoppage of all equipment. While production volume has been lowered to 80 % of projected volume, natural gas basic unit has inversely increased by around 12 %.

2.1 Interest on the Side of Fenchuganj Fertilizer Plant

Through the process of our local investigation implemented three times in the past, interest in this project on the side of NGFF and BCIC, its upper organization, has proved to be extremely high. The beginning of our investigation was based on NGFF’s written request dated December 20,1999,which Kobe Steel, Ltd. received from BCIC. After then, BCIC urged us repeatedly to visit NGFF Fertilizer Plant.

Based on the construction agreement between Kobe Steel, Ltd. and Pakistan Industry Development Corporation concluded in 1958 as an initiative export contract in Japan since the war, the targeted NGFF Urea Fertilizer Plant started its operation in 1962. At present, NGFF is a division of BCIC, which is under umbrella of Ministry of Chemistry & Industry, and 100 % state-owned enterprise. With a lapse of 40 years after start-up, NGFF has experienced rehabilitation several times up to the present. Owing to super-annuation, its operation rate has, however, declined to 78 % level. As applied process is also old-fashioned in addition to its super-annuation, energy consumption volume increases by around 16 %. Under the circumstances, BCIC requested Kobe Steel,Ltd. by letter to investigate the Plant without compensation and examine on improvement plan for resolving the following problems as well as to prepare and make a proposal in writing.

CD To recover production capacity ® To reduce energy consumption volume (3) To improve environmental pollution (4) To facilitate a minimum of 10 years plant operation After Kobe Steel, Ltd. applied its proposal on NGFF Plant Renovation Plan as a public target project in “Joint Implementation Promotion Basic Research”, it was entrusted with investigation on its Renovation Plan from NEDO, and such investigation was executed as scheduled. It is, therefore, natural that NGFF Plant has much interest in this project.

The positive and cooperative attitudes shown by general manager and all staffs at the time of our local investigation indicate clearly their interest in this project. With extraction of more than 200 points at issue in major equipment out of around 1,000 units of machinery & equipment, they accepted a long time discussion on measures. Although such discussion sometimes continued until very late at night, our projected investigation was implemented without delay. At the time of preparing this report, NGFF urged us to present a report written in English.

As NGFF and BCIC, its upper organization, as well as residents in the suburbs of Fenchuganj and a commissioner of labor union in Sylhet have their interest in the project, they inquired us about details of our discussion over and over again. Our discussion revealed that NGFF was afraid of determination, suggesting closure of its plant, and strongly desired to have an early decision on implementation of the project. NGFF felt, therefore, greatly relieved by our explanation that our investigation aimed at pursing energy saving efficiency through maintenance of NGFF.

As a basic issue in the project, NGFF Plant has much interest in fund-raising. While BCIC and Ministry of Industry are expected to make adjustments on their own initiatives among Bangladesh ’s authorities concerned, they are interested in combining this project with CDM. Such being the case, our investigation team has promised them to complete our report written in English and to cooperate with them in obtaining Bangladesh Government ’s approval with explanation on Overseas Development Aid System as well as to provide information on development of international discussion for CDM and to work together with them in its materialization

2.2 Conditions of Relevant Equipment in Fenchuganj Fertilizer Plant

(1) Summary of relevant equipment

1) Relevant equipment in Fenchuganj Fertilizer Plant Area of plant site : Battery limit-40 acres (162,000 m2) : Housing colony-364 acres (1,43,000 m2) : Related supplementary equipment-15 acres (60,700 m2) : Total: 419 acres (Around 1.7 million m2)

—II—10 — Plant equipment capacity

: Ammonia Plant 2 lines, Equipment capacity per unit 100 LT, Total-203 MT/D : Urea Plant 3 lines, Equipment capacity per unit 111 LT/D, Total-338 MT/D : Power Generation Plant 3 lines, Generation capacity per unit 12,000 KW, Total 36,000 KW : Ammonia Sulfate Plant I line, Equipment Capacity 40 MT/D : Sulfuric Acid Plant 1 line, Equipment Capacity 35 MT/D

Supplementary equipment : Water intake equipment: Capacity per hour 2,600 tons, Water is supplied through pipes lying under ground to plant : Service water treatment equipment: Capacity-350 tons per hour : Water purification equipment: 3 lines, Capacity per line-48tons per hour : Cooling water equipment: Capacity- 11,000 tons : Bulk urea product warehouse: 156m (L) x 24m (W) x 5.0m (H) : Bagged urea product warehouse & shipment equipment: 144m (M) x 36m (W) x 17.5m (H) : Machine processing & repair shop, Instrumentation parts repair shop, Spare parts warehouse : Others: Analysis room, Head office building, Office at plant site, School, Clinic, Mosque 2

2) Layout within battery limit Layout Drawing of plant site is shown in Figure II — 1. The area is rectangle in its shape with distance of 300 m between east and west and that of 580 m between south and north, and it has 16.5 hectares. Head office, school and clinic are located out of this area. By use of side track, loading of urea product (50 kg) from platform to freight car or truck is available.

— II—11 — Direction to Sylhet

—T

Directiorl to Dacca Figure II— 1 Layout Drawing of NGFF Fertilizer Plant Equipment

11-12- The equipment numbered in Figure II — 1 are as follows.

1. Reservoir 2. Warm water pool 3. Cooling water pump station 4. Cooling water tower 5. Bulk urea product warehouse 6. Bagged urea product warehouse 7. Bagging equipment 8. Urea production equipment (NH3-C02 separation part)

9. Urea production equipment (Compressor House) 10. Urea production equipment (Condensation part) 11. Urea production equipment (Carbamate decomposition part) 12. Urea production equipment (Pump shelter) 13. Urea production equipment (Rotary urea dryer) 14. Urea equipment (Grain production tower) 15. Parts warehouse 16. Machinery plant 17. Instrumental parts repair shop 18. C02 gas holder 19. Ammonia spherical tank 20. Compressor house 21. Analysis room & office at plant site 22. Office at plant site 23. Canteen 24. Ammonia production equipment (Compressor house) 25. Electricity room 26. Substation 27. Ammonia production equipment (Synthesis part) 28. Ammonia production equipment 29. Ammonia production equipment (C02 removal plant) 30. Ammonia production equipment (Natural gas reforming part) 31. Water treatment equipment 32. Power generation plant 33. Side track 34. Place for materials 35. Main gate

-11-13 (2) Ammonia production process

Ammonia production process consists of natural gas reforming equipment (701 section),

1st stage gas compression process, CO2 removal equipment (713 section), 2nd & 3rd stage gas compression process, Gas refinery equipment (715 section), 4th stage compressor, Ammonia synthesis equipment (718 section) and Ammonia refrigeration equipment. Summary of process is shown in Figure II —2. As indicated in Figure II -2, natural gas sent from outside of the Plant is supplied to natural gas reforming equipment and reformed through mixing with steam generated in the system. And, after

process of air breathing, it produces mixed gas, consisting of hydrogen, CO, CO2, nitrogen, a little quantity of unresponsive methane and excessively added steam. This is

called as reformed gas. The reformed gas generates CO2 and H2 in CO conversion equipment at next stage through reaction of CO contained in reformed gas with accompanied gas. This reformed gas is compressed and increased in its pressure in 1 st

stage compression process after cooling and sent to CO2 removal equipment (713

section), and most of accompanied CO2 is removed. All quantity of CO2 separated in

this stage is used for urea synthesis. Gas coming out from CO2 removal equipment is called as synthesis gas. In addition to hydrogen and nitrogen, synthesis gas includes a

little quantity of methane, argon, CO2 and CO. Since CO2 and CO become poison for ammonia synthesis catalyst, they are removed to the level of ppm in next synthesis gas refinery equipment (715 section) after compression and pressure increase in 2nd and 3rd

stage gas compression process. In synthesis gas refinery equipment, CO2 and CO are absorbed and removed through washing by use of copper ammonia acetic acid solution with low temperature. For cooling of copper ammonia acetic acid solution, cooled catalyst coming from refrigeration equipment (719) is used. Gas coming from synthesis gas equipment, consisting of hydrogen and nitrogen with mole rate of 3:1, includes a little quantity of methane slipped in reforming equipment and invaded argon, accompanied with the air. Such methane and argon are not only unresponsive against ammonia synthesis catalyst, but also harmless. After its pressure being increased highly in compression equipment 4th stage, synthesis gas is sent to ammonia synthesis equipment (718section). In ammonia synthesis equipment (718 section), ammonia is generated through reaction of hydrogen and nitrogen under condition of high pressure and high temperature. Together with unresponsive synthesis gas, generated gas is refrigerated by cooled catalyst coming from refrigeration equipment (719 section), and condensed and separated. Separated liquid ammonia is sent to urea synthesis equipment. Un-condensed gas separated from condensed ammonia is cycled to

ammonia synthesis equipment by compressor and re-used. Unresponsive H2 and are recycled to ammonia synthesis tower. In parallel with development of ammonia synthesis, unresponsive methane and argon are accumulated in the system and a part of gas coming from cycle system gas is always purged.

701 natural gas reforming equipment

701 High temperature CO conversion equipment Gas compressor 1 st stage 713 Carbon acid carbonic acid gas removal equipment Gas compressor 2nd & 3rd NH3 cooled catalyst 715 stage synthesis gas refining equipment

NH3 cooled catalyst Gas compressor ammonia ammonia 4th stage refrigeration synthesis equipment equipment

ammonia Urea synthesis storage equipment equipment

Ammonia

Figure II —2 Ammonia Production Equipment and Process Diagram

11-15- All reactions occurred in Ammonia Plant, in which methane is used as raw material, is summarized in the following.

CH4 + 1.391 (H2O) + 1.138 (Nz) +0.304 (Oz) ^ 2.261 (NH3) + CO2

2 moles of ammonia and 1 mole of CO2 are required for urea synthesis. In the case where all quantity of ammonia are used for urea synthesis as shown in the above chemical formula, approximately 13 % is short in the volume of CO2 generated from ammonia equipment. In NGFF, deficiency is, therefore, made up for with collection of

CO2 from ventilator gas in ammonia gas by means of MEA absorption method. Since ammonia is partially used for raw material of ammonia sulfate or sold outside, CO2 is not at all times in short supply. Only in case of CO2 being short, CO2 is collected from ventilation gas in electricity equipment boiler by use of MEA solution.

Details of each process unit in ammonia production process are as follows.

1) Natural gas reforming (701 section) Concept relating to natural gas refining process is shown in Figure FI—3. Natural gas introduced into the Plant from Sylhet through pipeline is lowered in its pressure and divided into natural gas for process (called as PNG) and natural gas for fuel (called as FNG). PNG contains a little quantity of organic sulfur. As sulfur becomes a poison for nickel related catalyst filled up in reforming furnace in next process, it is absorbed and removed by means of putting PNG into organic sulfur removal equipment filled with activated carbon. Mixed with 14 kg/cm2 of steam after preheating, PNG is supplied into catalyst tube in direct burning type heating furnace at 399 °C and 8.2 kg/cm2G via preheating process. In NGFF, mole rate of steam and carbon atom (S/C) is 5.5.

In 1st reforming furnace, methane reforming reaction (D and CO conversion reaction (2) occur simultaneously, and hydrogen, CO CO2 and mixed gas (Reformed gas), consisting of unresponsive CH4 and excessively added vapor, are obtainable.

CH4 + H2O <4 CO + 3H] (D

CO + H2O <4- CO2 + Hz ®

As both of the above (Band ® are reversible reactions, methane reforming reaction ® goes forward to right direction through absorbing reaction at high temperature and CO2 conversion reaction (2) steps forward to left direction through heating reaction. With 577 °C and 6.5 kg/cm2, at exit of 1st reforming furnace, the remaining methane is around 9 %. Reformed gas coming from 1st reforming furnace is supplied to 2nd reaction furnace, reaction vessel, filled with catalyst. In reaction vessel, the air sent from air compressor is breathed and temperature rises up to 930 °C by partial burning of reformed gas. And the remaining gas decreased to about 0.3 % throughthe above Q reaction of unresponsive methane. The volume of breathed air is finally adjusted as necessary nitrogen source on the condition that

rate of H2 to N2 in synthesis gas is 3 to 1. Reformed gas coming from 2nd reforming furnace is at 6.5 kg/cm2 and 785 °C and gas composition is indicated in Table II-3.

Table II — 3 2nd Reforming furnace exit gas composition

Composed material ch 4 CO CO2 h 2 n 2 Ar 02 % 0.3 7.4 12.2 58.6 21.3 0.2 0

Reformed gas, with high temperature, coming from 2nd reforming furnace enters into wasted gas collection boiler tube and is cooled down to 410 °C with generation

of 14.0 kg/cm2 G steam.

Burned gas CO2 into the air

Organic 1st 2nd Wasted reforming reforming gas Reformed Natural gas sulfur equipment equipment collection gas removal boiler equipment

Process air blower

Figure II — 3 Diagram of (701) Natural gas reforming equipment

-11-17 2) CO conversion and CO2 removal equipment (713 section)

Concept relating to CO conversion and CO2 removal process is shown in Figure II — 4. Reformed gas coming from wasted heat collection boiler is sent to CO

conversion equipment and produces hydrogen and CO2 on Fe/Cr related CO conversion catalyst through CO conversion reaction ® by steam accompanied with CO. Also, CO decreases to 2.0 %. As CO conversion is thermal reaction, reformed gas after CO conversion rises up to 438 °C in its temperature. This reformed gas is collectible for preheating of mixed gas, consisting of PNG supplied in 1st reforming furnace and steam, and thermal source for re-boiler. Reformed gas is increased up in its pressure to 19.3 kg/cm2G in synthesis gas compressor 1st

stage after washing and cooling and sent to CO2 removal equipment (713 section).

16.7 % of CO2 contained in reformed gas flows to upper direction over filled layer

in CO2 absorption tower and contacts with oncoming heated calcium carbonate water solution flowed down from the top of tower. And it is separated and removed from reformed gas selectively absorbed into water solution by reaction formula (3), and concentration decreases to 0.6 % at absorption tower exit.

CO2 + K2CO3 + HzO 2KHCO3 (3)

Rich solution with CO2 is reduced in its pressure nearly to pressure level of the atmosphere sent to the top of re-generation tower and contacts with oncoming steam rising in the tower while falling. After then, it is heated and re-generated with

diffusion of CO2. Heated lean solution with diffusion of CO2 is removed from

regeneration tower bottom and recycled to absorption top by pump. In CO2 removal process by use of heated calcium carbonate, absorption and regeneration of CO2 are made at around 100 °C. Process gas coming out of absorption tower top is cooled and, after separation of condensed water, is increased in its pressure in synthesis gas compression equipment 2nd & 3 rd stage. Finally, it is sent to

synthesis gas refining equipment. Meanwhile, CO2 coming from regeneration tower top is cooled and, after separation of condensed water, sent entirely to urea synthesis equipment, as material for urea.

11-18- C02 gas To gas compression equipment

Low pressure steam C02 refrigeration tower

To gas High Wasted Reformed CO2 compression temperature gas gas absorption equipment Reformed CO collection compression removal gas conversion boiler equipment equipment equipment

Figure II —4 (701) CO conversion & (713) CO2 removal equipment

Following high pressure CO conversion equipment (FITS), process for converting the portion of CO unconverted in FITS, with installation of low temperature CO conversion equipment (LTS), is recently applied. Although 2.0 % of CO remain at exit of HIS, its reduction to 0.12 % is achievable with application of LTS. As all

quantity of gas reduces due to removal of CO2 at C02 removal equipment exit, the rate of CO is 2.4 % at present. In case of LTS application, it comes up to 0.14 %.

In latest C02 removal equipment, improvement of CO2 absorption efficiency by use of thermal calcium carbonate solution and energy saving by adding activation catalyst, anti-corrosion agent and anti-foaming agent into thermal calcium carbonate

solution are designed. CO2 is now removed to the level of 0.6 % in CO2 removal equipment in NGFF, but reduction to below 0.2 % is attainable in latest improved

CO2 removal equipment.

3) Synthesis gas refining equipment (715 section) Concept relating to synthesis gas refinery process is indicated in Figure II-5 (715). Synthesis gas increased in its pressure up to 144 kg/cm2 in synthesis gas compression equipment 2nd & 3rd stage is washed by water solution, including low temperature ammonia copper acetate, in synthesis gas refinery equipment, and most of remaining CO is absorbed and removed. Since CO2 and CO become poison for ammonia synthesis catalyst, their removal to the level of ppm is required at this stage. By contact of synthesis gas introduced from lean solution washing tower bottom with oncoming ammonia lean solution, including a plenty of Cu+2, flowed from upper part, CO contained in synthesis gas is absorbed and removed to the level

of 5 ppm. In lean solution washing tower, CO2 is absorbed and removed to the level of 50^60 mm at the same time. Gas coming from lean solution washing tower top enters into final washing tower bottom and is washed through contact with

oncoming ammonia water flowing down. As a result of absorption of CO2,

synthesis gas, consisting of CO and CO2 in less than 5 ppm in each quantity, is obtainable in final washing tower top. In this synthesis gas, the ratio of hydrogen and nitrogen is 3 to 1. Although it includes a little quantity of remained methane

and argon entered into system with the air breathed in 2nd reforming furnace, it is used as raw material for ammonia synthesis, as both of remained methane and argon are unresponsive to ammonia synthesis reaction. Composition of synthesis gas at final washing tower exit is shown in Table II —4.

CO condensed gas To fuel

NH3 lean To low solution refrigeration pressure regeneration steam tower equipment

Synthesis CO NH3 - gas Synthesis Refined gas absorption washing gas synthesis gas Synthesis compression removal tower compression gas equipment equipment compression equipment equipment

Figure II 5 (715) Synthesis gas refinery equipment Table II —4 Synthesis gas composition mole at final washing tower exit %

Composed CH4 CO CO2 h 2 n2 Ar material % 0.4 5-10 ppm 0-5 ppm 74.5 24.8 0.3

This gas is sent to ammonia synthesis part after being increased in its pressure in synthesis gas compressor 4th stage.

As ammonia absorbed solution, coming from final washing tower bottom, includes carbonic acid ammonia, it is recycled to urea plant, after reduction of its pressure.

Rich solution extracted from lean solution washing tower bottom is reduced in its pressure to the level, ranging from 140 kg/cm2 to 2.8 kg/cm2, and sent to the top of lean solution regeneration tower. Lean solution regeneration tower consists of upper and lower sections. In upper section, rich solution, flowing down, contacts with oncoming rising steam and NH3 steam and is finally regenerated with diffusion of absorbed CO and CO2. As regenerated lean solution extracts metal copper from Cu + through CO reaction, oxidation is promoted at the bottom of lean solution regeneration tower by means of blowing the air to maintain ion density ratio of Cu ++ / Cu in lean solution at certain level. Regenerated lean solution coming from the bottom of lean solution regeneration tower is cooled to the level of 0 °C by ammonia after water cooling and is recycled to the top of lean solution washing tower after being increased in its pressure by high pressure pump. Off gas coming from the top of lean solution regeneration tower contains about 60 % of CO and used as fuel in 1st refinery furnace.

Synthesis gas refinery equipment is applied in the process for absorbing and removing CO and C02 in low temperature by using copper ammonia acetic acid at high temperature as rich solution. Thanks to the following reasons, it is not applicable at present.

- In addition to complicated-ness, its operation is difficult. - With various instrument, its maintenance is expensive. - Mixing off ammonia acetic acid is troublesome. - As it is high pressure equipment, leakage is always expected and environmental pollution by lean solution is worried about. - As it is applied in low temperature, a lot of energy is used for refrigeration - Except fuel, separated CO condensed gas is not usable.

11-21 As mentioned in the latter part of paragraph 2), LTS and the latest improved C02 removal process are recently applied. With application of new process, content of

CO and that of C02 at the entrance of synthesis gas refinery equipment decrease to 0.14 % and 0.21 %, respectively. CO and C02, poison for catalyst, are removed through their conversion to harmless methanation. Methanation is an adverse reaction of methane reforming reaction and indicated in thee following reaction formula.

CO + 3H2 -> CH4 + H20

C02 + 4 H20 -> CH4 + 2H20

Although around 1.26 % (0.14 X 3 +0.21 X 4) of hydrogen loss is caused at this time, it is less than 2.4 % of CO loss, and merits in application of new process, such as energy saving ,are widely expected.

4) Ammonia synthesis equipment (717 section)

Concept relating to ammonia synthesis and storage process is shown in Figure II— 6 . Synthesis gas coming from synthesis gas refinery equipment is increased to 365 kg/cm2 in its pressure in ammonia synthesis compressor 4th stage (final stage) and sent to ammonia synthesis equipment as makeup gas. Mixed with synthesis gas cycled from synthesis gas cycle machine, this makeup gas is cooled down to the level of 0 °C in ammonia refrigeration condensation equipment. Ammonia refrigeration equipment is applied for collection of cooled heat, separated from synthesis gas in ammonia 2nd separation equipment and kept at 0 °C, and has a function of refrigeration by use of cooled catalyst. Synthesis gas from cycling machine contains about 10 % of ammonia and also 7.8 % of ammonia even after its mixture with makeup gas. When synthesis gas is cooled down to 0 °C in this refrigeration equipment, most of ammonia is condensed. And it is divided into condensed ammonia and gas in next 2nd ammonia separation equipment. Through mixture of makeup gas with cycled gas, a partial pressure of ammonia in cycled gas decreases and impurities in makeup gas are removed by condensed ammonia with application of this method, although condensed separation efficiency is relatively small. And the purity in synthesis gas increases. The gas separated in ammonia 2nd separation equipment is kept at 0 °C and includes about 3 % of ammonia. After collection of its cooled heat in ammonia refrigeration equipment, this gas is supplied to ammonia synthesis tower. Ammonia synthesis reaction is heat generation reaction. Since the temperature of reaction generated gas exceeds that of entrance gas in catalyst layer, preheating of gas in supply side and cooling of

11-22 reaction generated gas are available in synthesis tower by means of internal heat exchange between gas at low temperature and reaction generated gas at high temperature. In respect of gas preheated up to a certain temperature by internal heat exchange, ammonia synthesis is promoted on Fe related ammonia synthesis catalyst by the following ammonia synthesis reaction®.

3H] + N] — 2 NH ®

While NH3 is 3 % at synthesis tower entrance and 15.9 % at exit, gas generation ration is 25 %. Reaction gas coming from synthesis tower is kept at 207 °C and cooled down to the level of 40 °C. And a part of generated ammonia is condensed and divided into condensed ammonia and gas in next ammonia 1st separation equipment. To keep the total of methane and argon, contained in synthesis gas and cycled in ammonia synthesis equipment, less than 10 %, a part of synthesis gas is purged to the outside of system and used as fuel in 1 st reforming furnace. After its cycling by synthesis gas cycle machine, the gas separated by ammonia 1st separation equipment is mixed with makeup gas and cycled by synthesis gas cycling machine. Consequently, synthesis gas completes its cycle.

Condensed gas separated in ammonia 1st separation equipment and 2nd separation equipment are reduced in its pressure and collected in let down tank. After then, it is sent to spherical tank for ammonia storage and becomes raw material for urea synthesis. Gas generated in let down tank is used as fuel in 1st reforming furnace.

Purge gas coming from ammonia synthesis system is kept at 1,180 NH3 / H per hour and contains about 60 % of hydrogen and 10 % of ammonia. Although it is used in

1st reforming furnace as fuel, energy saving is achievable with collection of these hydrogen and ammonia.

11-23- Synthesis gas Synthesis Synthesis Purge Gas From gas cycle compression machine equipment

NH3 NH3 2nd Ammonia Synthesis NH3 1st refrigeration separator synthesis gas separator condensation tower cooling equipment equipment

To fuel system

Ammonia

refrigeration down tank machine Ammonia NH3 storage To urea spherical synthesis tank equipment

Figure II — 6 (717) Ammonia synthesis & (718) Storage

(3) Recent operation conditions in Ammonia Plant NGFF’s operation record of Ammonia Plant for 3 years from July, 1997 through June, 2000 has been summarized. It is shown in Table II. With extraction of stoppage hours and their causes in the past 3 years from the Table, details of stoppage (July, 1997~June,

2000) in Ammonia Plant are indicated in Table II —6 . In Table II —5 and II —6 , stoppage hours indicate a half of the actual stoppage hours. Since Ammonia Plant,

consisting of 2 lines, continues its operation of another line even in case of 1 line being stopped, influence of stoppage hour to ammonia production is considered to a half. As indicated clearly in Table II —6 , the stoppage hours, attributable to troubles of synthesis gas compressor 716 KT and process air compressor 716 K2, are 2,178 hours in total and

account for 88.8 % of the total. To obtain reliabilities on synthesis gas compressor 716 K1 and process air compressor 716 K2 is needed for operation rate increase in Ammonia Plant. It is, therefore, understandable how adequate maintenance & repair are much significant.

11-24- 5,223 5,571 4.334 6,078 5.308 4,874 4,336 4,368 3.382 5,033 5,560 5,751 5.133 4.837 4,495 58,197 4.964 5.278 3,318 Tons/M Production

6,100 6,300 6,100 6.300 6,100 6,300 6,300 6,100 6.300 6,300 6,300 6,300 5,692 6,300 6,100 74,192 6,100 6,300 6,300 99/00 Tons/M Capacity ~ 1997/98 Time

nil nil Hrs. 64:45 36:20 99:00 80:00 10:00 95:00 40:00 26:00 104:00 47:00 160:05 233:00 662:00 112:00 189:00 186:00 117:00 Down

anc

......

in

line.

for

pump suction (S,C,N) leakage trouble

burst no.3

DS

gas

&

leak to (C) flange &

steaming

down coil line iransier

B-train

flange 3 to due top 3

NGFF

JGT liner

gland pump broken

shut

iin

NH carbamate to (B) low meter water

by troll

PNG

leak

to

tot forced feed

Hot inside

collar

3

low tube with

feed level (S.C.N) or

&

cover, pump

gland in Haripur NH (C) of

train

ran

trouble failure of 2)

A

run pump

pump suspension plunger

was leakage suction

Reformer

repaired. Absorber reactor

plant leakage was gas Other

to

feed plant, carbonate

feed

leak,

(C) packing 3

3 pri.

to to plant (B)

3 urea Hot NH Urea uue train NH

713 repaired leakage Due B One 11 NH in power Due maintenance 1) 1) 2) replacement. cover gland pump steaming. done done

down

boiler

steaming steaming shut

plant

steaming to

to

power

catalysts catalysts

of Record trouble

forced

train

reforming reforming bursting

B

Reformer to

train train

A A Due tubes,

Operation

and

main section

and

burnt. down burst gas

Plant

intake

burst coil leakage. shut

room)

main

to coil purification

water

tube

starter intake H.P

(switch

in (N) starter boiler trouble

out out. coil failure towards

water (N) Ammonia

plant line repaired.

black black trouble

Relay

power

Electrical to towards compressor

Power Total Total Aux.

1) 2) 1) 2) process line (715) compressor electrical gas replaced NGFF Due

-5

cooler

bearing Stage II

down Other

Stage bush 3rd. maintenance maintenance.

shut 3rd.

(N) (S) (N) (N)

to

Table changed.

done.

and

work

compressor compressor compressor compressor compressor

changed compressor

) air air air air air

damaged Air

side

Process repaired maintenance Process (GP Process Process piston Process

Met. Met.

Main

(3rd. stop (4th

cracked bot.

to

down

trip

ni/iui/ Stage

stage

shut top/bottom

ot

(N.S) maintenance. 3rd. 4th maintenance maintenance. maintenance maintenance

(S) (S) (N) (N) (S) (S) (S) vLUUUI

changed)

delivery

maintenance.

&

rod compressor (S)

baaoi

Compressor repaired

Main changed) suction

piston compressor compressor compressor

compressor Compressor compressor compressor tUIIIJI

changed Main

Main compressor Main Packing Main Main Stage line Main valves Main Main stage IVIdill Jul. Jun Nov. Oct. Dec. Sep. Apl. Aug. Mar. Jut. Jan. Feb. May. Oct. Nov. Dec. Sep. Aug. 97/98 Month 1998 1998 1997 Year

11-25 5.096 5.213 5.392 5.492 5.045 2,958 4,198 5,074 4,143 4.354 4,942 4.831 4.049 4.906 4.818 4.821 4.501 56,623 58.317 173,137 Tons/M Production 6,300 6.100 5.896 6,300 6.100 6,300 6.300 6.300 6.300 5.692 6.100 6.100 6.300 6.100 6.100 6.300 6,300 74.396 67,892 222.780 Tons/M Capacity Time

Mrs. 9:22 55:30 74:20 22:20 41:30 92:20 56:17 22:05 73:12 21:40 52:25 33:08 47:22 109:42 197:12 115:02 745:15 307:22 1045:33 2453:43 Down

2

C0 shut.

Stage of

717. cooler cooler

train

water in 3rd.

down

prill prill of one of

work.

failure) shortage enter for for shut

(B)

and

work to for

(B) (B)

gas

pump Cleaning (N)

changing supply

down (bad

down down

scrubber

trouble repairing intake

comp.

shut shut shut water

cleaning. carbon

urea air urea

water

trouble

of

Other

of of of (A) (water

plant leakage

Cleaning Total water Scheduled Scheduled cooler scrubber(B) cooler Process Tube Activated Trouble failure failure

2)

(B).

changing down

tube

for

shut reformer

to down

reformer

second shut

of

&

trouble

train

A train

prim.

change of A

of

steaming scheduled steaming

Reformer Gasket train train train

1) Steaming A catalyst Steaming A A

of

power ref.

(C)

during

of train

ref.

down failure A

air

of over start-up

shut circulator

problem

during to

to compressor to

problem.

exciter short change air

(C) due in

in

to to ampere

to

trouble

compressor (N) high Electrical (N) power

problem trouble trouble trouble of

over with From shortage

Electrical failure.

compressor Shortage station refrigeration Comp. Electrical Electrical Electrical change tripped Power Electrical tube

in

for

valve stage

for changing

down

compressor for down

3rd.

air shut

for

changing maintenance

shut maintenance

of

to

end) S) S) for for

bearing

stop

maintenance. maintenance maintenance.

& &

&

(big

stop (N) maintenance (N) (N (N) stop (N

changing rod

compressor

bearing head

compressor piston Air

change.

Air compressor compressor compressor compressor compressor compressor compressor compressor

maintenance Cylinder piston, Air changing Air Air Air Air (S). Air suction Air Air valve 4th

4th in twice. for for

S)

packing one

Main stage for

&

for valve

for (N down down 2nd new

down

gasket

valve

change

metallic and down for for stop

with shut shut

shut

check

Valve S) S)

oil bush maintenance maintenance. maintenance. stop stop maintenance shut stop

& &

&

etc. maintenance (S) (N) (S) (N (N) (S) (N) (N) (N (N)

changed

maintenance

Neck

and compressor valve

compressor rod

(N)

valve. valve.

Main Main

origin)

piston compressor compressor compressor compressor compressor compressor compressor compressor compressor compressor compressor

maintenance Main maintenance. Main stage (China Main Main leakage changing leakage. changing maintenance, Main Main compressor Main changing. Main maintenance. Main Main Main Jun Apl. Jul. Feb. Mar. Jun. Jan. Feb. Apr. Mar. Sep. Oct. Nov. Dec. Aug. May. May. 98/99 99/00 Month Total 1999 Year 1999 2000

11-26 Table II —6 details of stoppage (July, 1997^ June, 2000) in Ammonia Plant are indicated (1997.07—2000.06) Cause for stoppage Stoppage hour Ratio Trouble in synthesis gas compressor 410 Hr 16.7% Trouble in air compressor 692 Hr 28.2% Compound troubles in air compressor and synthesis gas 912 Hr 37.2% compressor Compound troubles in synthesis gas compressor and 164 Hr 6.7% relating to electricity Trouble relating to electricity 182 Hr 7.4% Trouble relating to reforming furnace 20 Hr 0.8% Others 74 Hr 3.0% Total 2,453Hr 100.0 %

With extraction of annual ammonia production volume, actual production volume and stoppage hour in each year from Table II-5, each ratio has been calculated and indicated in Table II - 7. NGFF’s plant is operated at around nominal equipment capacity of 200 LT during stable condition. The ratio of annual production volume to projected volume is such low as 77.3 % on the average in 3 years. It is due to the fact that NGFF’s production volume was projected on the basis of 365 days / Y standard, i.e. Annual production 203.2 MT/ Dx 365 D/Y=74,168 MT. On the condition that 320 days are counted for annual operation day as originally projected, annual production amounts to 65,024 MT/Y and the ratio of average production volume in 3 years to projected value comes up to approximately 89 % {173, 137/(65, 024x3)=0.89). Meanwhile, the average ratio of stoppage in 3 years is 9.43 %. In the case of calculating the number of days corresponding to annual operation days on the basis of this value, 330.6 days, which are longer than 320 days of projected annual days by 10.6 days, are obtainable.

Days corresponding to annual operation = 365x (100-9.43)/!00 = 330.6 days

Although actual operation days are 10.6 days longer, annual operation volume accounts for 89 % of production value. It is not consistent with the fact that the Plant has been operated at its nominal capacity during stable condition. On the assumption that a consecutive stoppage of operation of 45 days is required for regular repair once a year, 320 days of annual operation days are counted. Whenever accident occurs in NGFF, its operation is, however, immediately stopped and troubled part is repaired. NGFF completes its repair work skillfully in short time in case of accident, but annual production volume decreases due to influence of reduction volume caused by a lot of

-11-27 stoppage times, although days corresponding to total stoppage hours are comparatively short.

Table II —7 Ammonia production volume & Stoppage hours ratio (July, 1997^June, 200) Year 97/98 98/99 99/00 Total Projected production volume MT/Y 74,192 74,192 74,396 222,780 Production result MT/Y 58,197 58,317 56,623 173,137 Production volume ratio 78.44 % 78.60 % 76.11 % 77.72 % Operation stoppage hour 662:00 745:15 1045:33 2453:43 stoppage hour ratio 7.56% 8.51 % 11.94% 9.43%

(4) Urea production process

In Urea Plant, 333 LT/D (108,250 MT/Y on the basis of 315 days/Y) of urea in the state of grain are produced by use of liquid ammonia generated in Ammonia Plant and

carbonic acid gas collected in CO2 removal equipment through Chemico’s complete cycle method. While urea synthesis equipment consists of 3 complete lines, each of which has 111 LT/D capacity, each equipment of refrigeration, bagging, storage and shipment in the following process has 1 line, respectively. Urea production process is shown in Figure II—7 “Urea synthesis equipment process”. While unresponsive

carbamate is divided into ammonia and CO2 and cycled to separately to synthesis tower in NGFF, such carbamate is cycled without decomposition to synthesis tower in the latest energy saving process. Summary on urea production process in NGFF is set forth in the following. NH 3 (From NH3 equipment)

Shipment Urea Product NH3-CO2 separator Shipment equipment Liquid NH3 storage Wasted water

Urea in the state of grain Storage & bagging Carbamate Refrigeration Urea synthesis separation equipment tower equipment

Urea solution Re-dissolution system CO] compressor Urea in the state Urea grain Urea evaporation of grain condensation production equipment Refrigeration equipment CO] (From NH equipment) NH3 stripping

Wasted water

Fig. II —7 (400) Diagram of Urea synthesis equipment process

1) Urea synthesis equipment Makeup ammonia, raw material for urea, is supplied from Ammonia Plant and stored in liquid ammonia storage equipment together with collected ammonia, unresponsive in urea synthesis cycle. After then, it is increased up to 250 kg/cm2 in its pressure by ammonia supply pump and put into urea synthesis tower.

Makeup CO2, another raw material for urea, is sent from Ammonia Plant and

compressed up to 70 kg/cm2 by CO2 compressor together with collected CO2, unresponsive in urea synthesis cycle. After being liquefied through refrigeration and increased in its pressure up to 250 kg/cm2G, as liquid carbonic acid gas, by liquid carbonic acid supply pump, makeup gas is put into urea synthesis tower.

The mole ratio of ammonia, supplied to synthesis tower as raw material, to CO2 is

-11-29- 5.6 and exceeds considerably 2 of the equivalent rate. In urea synthesis tower, urea synthesis reaction attributable to the following reaction formula© and © occurs, but the temperature in synthesis tower is maintained at 185 °C,as this reaction causes a small quantity of heat generation reaction. Reaction © advances un-reversibly with heat generation reaction, while reaction © is reversible dehydration reaction, slowly going ahead by heat absorption reaction. The composition of urea and carbamate in urea synthesis tower are, therefore, always balanced.

2 NH] + CO] => (NH2)C02(NH4) Heat generation ©

(NH2)CO(NH4)2 <=> (NH2)2CO+H20 Heat absorption ©

Since there are a lot of corrosive C02 with high temperature in synthesis tower, carbon steel is corroded considerably. Its inside is, therefore, processed with stainless lining and surface is passivated for increase of anti-corrosiveness. So a small quantity of air is supplied into synthesis tower by high-pressure air compressor and measure for covering the surface of stainless lining with oxidized film is always taken.

Reactive generated materials at synthesis tower exit consist of 4 ingredients, such as urea, carbamate, excessive ammonia and water, and also a small quantity of hydrogen and nitrogen. Balance composition of reactive generated materials is shown in Table II — 8.

Table II — 8 Composition at urea synthesis tower exit (Mole %)

Composition nh 3 CO] Carbamate Urea h 2o Others materials % 43.9 0.0 14.0 32.1 9.7 0.3

Reactive generated materials, coming from the top of urea synthesis tower and being decreased in its pressure down to 20 kg/cm2 by pressure adjustment valve, is evaporated through heating of excessive ammonia by steam heater and separated from urea carbamate solution. Ammonia gas separated from excessive NH] separator is recycled to liquid ammonia storage equipment together with ammonia, raw material for synthesis, after cooling and condensation. Urea carbamate solution without excessive ammonia is sent to carbamate separation equipment after being reduced in its pressure to 1 kg/cm2 by pressure valve.

11-30- 2) Carbamate separation equipment

Urea carbamate water solution supplied to carbamate separation equipment is heated up to 100 °C and carbmate is divided into CO2 and NH3 through reaction toward opposite direction in reaction formula©, while water solution becomes basically such water solution as containing urea only. Since this reaction is absorption reaction, heat needed for reaction is supplied by steam with 10 kg/cm2. With this heat, separation of carbamate and condensation of urea through water vaporization occur simultaneously. Mixed gas of CO2 and ammonia with water, generated in

carbamate separation equipment, is sent to NH3 -CO2 separation equipment. Also, urea water solution coming from carbamate separation equipment is sent to urea evaporation condensation equipment.

3) NH3-CO2 separation equipment

In respect of ammonia and CO2 collected from carbamate separation equipment,

CO2 is selectively absorbed by MEA (Mono ethanol amine) solution and separated from ammonia. Separated ammonia is increased in its pressure up to 20 kg/cm2 by 3 stage ammonia compressor and, after being condensed by water cooling, sent to

urea synthesis tower from liquid NH3 storage equipment together with makeup

ammonia for their recycling. CO2, absorbed into MEA solution, is separated from MEA solution in regeneration tower by steam heating and sent to urea synthesis

tower by CO2 compressor together with makeup CO2 for their recycling.

4) Urea evaporation condensation equipment Urea water solution supplied from carbamate separation equipment is such solution as already condensed to the level of 80 %. With application of vacuum falling film evaporation method in vapor condensation equipment, urea solution runs down from the upper part of inside wall of interior rotary wing in the state of film, and water is condensed through evaporation after being heated with 10.5 kg/cm2 of steam from the outside of wall. In evaporation condensation equipment, urea, with temperature of 145 ~ 150 °C and including less than 0.5 % water, is obtainable in the state of melting. This melted urea is sent to urea grain production equipment by pump. For collection of a small quantity of ammonia contained in evaporated water, un-condensed gas, air (nitrogen and oxygen) breathed into synthesis tower, is separated after cooling and condensation, and ammonia is collected from condensed

water. This ammonia is sent to NH3 -CO2 separation equipment together with

mixed gas of ammonia and CO2, generated from carbamate separation equipment,

-11-31- for their recycling. Condensed wasted solution dried through ammonia stripping is drained.

5) Grain production, cooling and bagging

A series of equipment in the above consist of 3 lines, and there is a line in the process after grain production equipment. Melted urea with high temperature is splayed from tower nozzle at the top of grain production tower to downward and cooled for formation of urea grain through its contact with oncoming cooled air from the bottom of grain production tower, while its falling. Finally, it falls down to the bottom of the tower. This grain urea is cooled down to the level of normal temperature by rotary drum- type refrigerator and shipped as product after being bagged in 50 kg each. Sometimes, grain urea from rotary drum-type refrigerator is stored in storage warehouse on large-scale in bulky condition. It has 99.5 WT % of product purity and the remaining portion is water. Bullets, impurities, are less than

1.0%.

(5) Recent operation conditions in Urea Plant

The operation record of Urea Plant in NGFF for 3 years from July, 1997 through June, 2000 is summarized and shown in Table II —9. Stoppage hours and their causes are extracted from the above Table are indicated in Table II —10. Stoppage hours in Table II —9 and Table 11—10 represent 1/3 of actual stoppage hours. Since 2 lines are in

continuous operation even in case of 1 line being stopped, influence of stoppage hour to urea production is considered to be 1/3.

Out of total stoppage hours, stoppage hours due to top cover and inside lining of urea synthesis tower 401 are 2,342 hours and 395 hours, respectively, as shown in Table U — 10. And they come up to 2,737 hours totally and account for 51.7 % of the total stoppage hours. As complete stop of leakage from tower top cover of urea synthesis tower 401 HI is required for increasing operation rate of Urea Plant, adequate maintenance and inspection are essentially needed. With extraction of annual urea production projected volume, actual production volume and stoppage hour, each ratio is calculated and shown in Table II—10. Urea Plant is operated nearly at nominal capacity of 333 LT/D during stable operation condition.

-11-32- 7,552 7,732 5,079 6,518 7,016 8,787 7,453 8,141 7,573 7,170 8,582 7,899 4,534 86,304 Tons/M Production 8,525 8,250 8,250 8,525 8,525 8,525 7,700 8,250 8,525 8,250 8,525 8,525 8,525 100,375 Tons/M Capacity

Time

8.00 8.00 9.00 Mrs. 10.00 11.00 33.00 99.00 22.00 79.00 15.00 18.00 20.00 80.00 11.00 34.00 39.00 55.00 32.00 16.00 46.00 24.00 20.00 49.00 97.00 89.00 192.00 184.00 207.00 112.00 100.00 169.00 101.00 186.00 199.00 1846.00 Down

case down

failure

repair trouble repairing

shut repair crack

pump leak to

pump

pump pump

feed repair

tube

scheduled

trouble

reflux reflux transfer pump

line

3

2 3 bearing

Other NG NH3 NH & NH Reformer C0

down

leak

cracked shut

tube to

line

Record

boiler BFW

Trouble down)

Plant Plant

shut

Operation Electrical Power Power (full

&

down leak

boss boss Plant

shut liner

leak leak & repair leak to

leak UREA repair repair cover

cover cover

cover cover

Failure

top liner top top liner thermo-element liner thermo-element top top

leak leak

unit unit unit unit unit unit unit unit unit unit

NGFF Autoclave (C) repair (S) (N) (N) (C) (C) (C) flange (N) (C) (C) flange

9

main shut

— repair & Pump

head to

II gear

repair repair leak

&

guide guide Repairing

(C)

&

cross

Broken

Trouble & head (N)

Repairing Failure

gland head head guide

leak

Table

) Pump

&

break Pump cross Plunger Pump gland gland

head,

cross gland

cross repair

(S,C (C) (S) (?) repair (?) (S) N)

Feed unit unit unit

Repairing &

3

repairing bearing (C (C) (S) (S) guide Pump Pump Pump NH Pump Pump Repairing Pump (S) down

coil

shut

to

trouble Stator

compressor

elec, Trouble

gas comp.

gas comp. Plant

main

3 3 damaged Main Gas NH NH tripped Jul. Jun May Apr. Jul. Feb. Mar. Jan. Sep. Nov. Dec. Oct. Aug. 97/98 Month 1998 1997 Year

11-33 7,315 6,324 7,561 7,594 6,033 7,844 7,785 6,662 7,965 8,412 6,353 8,379 88,644 Tons/M Production 8,525 8,250 7,700 8,250 8,525 8,250 8,525 8,250 8,525 8,525 8,525 8,525 100,375 Tons/M Capacity Time

Mrs. 9.00 7.00 8.00 8.00 3.00 13.00 16.00 13.00 19.00 72.00 80.00 22.00 17.00 13.00 12.00 80.00 27.00 24.00 24.00 28.00 23.00 33.00 32.00 38.00 29.00 35.00 29.00 36.00 128.00 105.00 240.00 225.00 1438.00 Down

&

bush

down

line N) gland

motor gland

cross &

shut

(S suction (S)

to pump outlet

corroded leak pump

driving leak

pin pump feed

pump pump leak

feed

gland

box 3

trouble

& bush line feed C02 NH feed feed subcooler

repair

2 2 2 3

Other stuffing leak cover NH3 No.1(C)/belt C0 head C02 pin NH leak C0 C0 BFW

down

full

shut to

to

plant

blackout

Trouble

power

plant

Electrical shutdown Blackout Power

down

boss

leak

shut

leak

line leak to leak leak leak

repair

replacement replacement repair

cover circuit cover cover therm-element cover reducer

Failure

liner liner top liner top top thermo-element top top circuit

units

leak flange

unit unit unit unit unit unit unit unit unit top

Autoclave (S) (C) (C) (N) (N) (N) (C) (S) (N&C) boss (S) (N) tube shut

to

to

leak leak

noise

Trouble gland gland repairing

down leak

units units Pump

abnormal tie-rod repair checking N) N) gland

& & Feed

unit unit unit unit C C unit 3

NH (S) (C) (S, (S) (C) check (S, (?) down

panel shut

to trouble work

repair Repair Trouble 401-K1(N)

Trouble

process

train elec.

comp. Plant comp. plant A

3 3 3 3 NH NH Main NH board NH Jul. Jun Feb. Sep. Jan. Oct. Mar. Nov. Aug. Dec. Apr.. May. 98/99 Month 1999 1998 Year

11-34 7,921 7,298 7,179 7,698 8,001 7,416 7,489 6,494 5,926 4,508 77,245 252,193 Tons/M Tons/M Production Production 8,525 8,250 8,525 7,975 8,250 8,525 8,525 8,250 8,250 8,525 92,125 292,875 Tons/M Tons/M Capacity Capacity Time Time

4.00 Mrs. 5.00 9.00 Mrs. 8.00 11.00 22.00 14.00 12.00 27.00 66.00 74.00 41.00 28.00 86.00 20.00 87.00 121.00 109.00 103.00 131.00 177.00 248.00 370.00 5293.00 2009.00 Down Down

to

&

repair down down

gland gland

line shaft shaft tripped

shut shut

repair suction to to

pump

pump C/W

pump

driving driving

pump pump repair feed

feed

2 2 & trouble trouble

leak ground water

feed feed cooler cooler C0 C0

shutdown

2 2 3 3

Other Other C0 leak C0 cover NH Jetty leak Prill broken full NH Prill under

to

down down

leak

shut shut

tube to to

boiler

Trouble Trouble shutdown

Plant full

Electrical Electrical Power suffer down down

shut shut

to leak to leak leak leak leak

replacement replacement leak

cover cover cover cover cover

Failure Failure

liner liner liner top top top top top

unit unit unit unit unit unit unit unit

Autoclave Autoclave (N) (S) (C) (C) (C) (S) (S) (N) shut shut

to to

leak

Trouble Trouble

Cover leak

Pump Pump

suet. gland

Feed Feed unit

unit 3 3

NH NH (N) (?)

down down

catalyst shut shut

to to for work

repair problem problem

repair

Trouble Trouble comp,

train

shutdown A

train scrubber scrubber

Plant Plant Main A

3 3 3 3 NH NH NH change Water Water Planned NH Jun. Apr. Jan. Feb. May. Mar. Sep. Oct. Nov. Dec. 99/00 Total Month Month

d Gran 2000 1999 Year Year

11-35 Table II —10 Causes for stoppage of urea plant operation ______(July, 1997^June, 2000) Cause for stoppage Stoppage hour Ratio % Leakage at urea synthesis tower cover 2,342 44.25 Corrosion of urea synthesis tower inside 395 7.46 lining Leakage in Ammonia supply pump 816 15.42 Leakage in liquid C02 supply pump 440 8.31 Trouble relating to electricity system 269 5.08 Others 1,031 19.48 Total 5,293 100.00

In Table II — 10, the ratio of actual production volume to projected volume in NGFF is 86.01 % on the average for 3 years. This ratio exceeds 77.72 % of Ammonia Plant due to the reason that NGFF’s projected production value, estimated as 100,357 MT/Y, is lower than annual production volume, contrary to Ammonia Plant. With 320 days for annual operation days, annual production amounts to 108,265 MT/Y (=1,016 x 333 LT/D 320 D/Y). Since the ratio of average production volume for 3 years to projected value comes down to 0.795 {=259,223/(108,265 x 3)}, it decreases by around 80 %. While the ratio of stoppage hour is 21.63 % on the average for 3 years and annual operation days, corresponding to 287 days {=365 x (100-21.63)/l 00}, are shorter than 320days of projected annual operation days by 33 days. In Urea Plant, the ratio of annual operation days and the ratio of production volume to projected volume are almost consistent. It is due to the following reasons. Although stoppage of plant is mainly attributable to urea synthesis tower’s repair, which requires many days, the number of times of stoppage is relatively small, compared with operation rate. Also, compared with Ammonia Plant, influence by number of times of stoppage to production volume is comparatively small, since there are 3 production lines in Urea Plant.

Table II — 11 Urea production volume & stoppage hour ratio (July, 1997—June, 2000) Year 97/98 98/99 99/00 Total Projected production volume MY/Y 100,375 100,375 100,650 301,400 Actual production MT/Y 86,304 88,644 84,275 259,223 Ratio of production volume 85.98 % 88.31 % 83.73 % 86.01 % Operation stoppage hour 2,242:00 1,438:00 2,004:00 5,684:00 Ratio of stoppage hour 25.59% 16.42% 22.88 % 21.63%

-11-36 (6 ) Conditions in electricity power plant

Electricity power plant supplies electricity and steam. While Natural gas is used as fuel, heavy oil is usable for plant operation under the present structure. It consists of 3 units of boiler and 3 units of generator. And 1 unit of each machine is preparatory. Maximum 12,000 kw of electricity generation and generation of steam required for fertilizer plant are available from the above generators and boilers, respectively. Steam turbine is steam extraction turbine, and extraction of steam with middle and low pressure

is available. NGFF power plant operation data for 6 years from 1981/82 to 1996/97 is shown in Table 11—12. This power plant is in relatively smooth operation and one of equipment, which has no serious problem, thanks to one preparatory line. Although there has hardly been any problem affecting fertilizer production attributable to electricity supply capacity of power plant, complete power cut-off due to damage of boiler tube occurs once or twice a year, as indicated in Table II —5 and II —9.

Table II —12 NGFF power plant operation data (1981/82^1996/97)

Natural gas Total generation Electricity for Steam for Urea Basic unit of Year consumption volume Urea Plant Plant natural gas volume Unit NM3/Y KWH/Y KWH/Y MT/Y nmVkwh 81-82 102,427,535 163,875,700 147,376,360 552,677 0.625 82-83 99,575,597 156,031,500 139,650,490 528,303 0.638 83-84 92,420,421 142,724,600 117,124,120 459,427 0.648 84-85 102,268,051 163,838,600 146,900,290 515,664 0.624 85-86 84,471,890 141,718,800 126,950,222 437,352 0.596 86-87 97,902,474 172,111,900 155,022,598 541,337 0.569 87-88 95,990,642 164,860,900 148,232,819 547,662 0.582 88-89 96,146,257 167,324,100 150,816,813 508,403 0.575 89-90 93,947,551 164,330,300 148,729,841 454,264 0.572 90-91 97,619,662 166,651,000 150,687,272 475,414 0.586 91-92 101,116,977 169,397,900 153,189,674 493,930 0.597 92-93 93,958,143 156,739,360 141,438,726 477,141 0.599 93-94 92,045,820 159,535,680 144,013,543 448,377 0.577 94-95 90,318,454 157,311,200 141,764,277 455,352 0.574 95-96 83,731,150 150,239,601 134,900,443 429,522 0.557 96-97 92,404,582 160,845,500 145,589,994 485,528 0.574

In this power plant, a comparatively large of pressed steam is extracted for sending steam to Fertilizer Plant. Overall thermal efficiency in power plant comes up to approximately 60 %, and it seems to be a plant with relatively high thermal efficiency. Urea production volume versus electricity consumption volume

> 20.0 | 100 * 00.0 o § 90.0 E § 80.0 | 70.0 | 60.0 £ 50.0 | 40.0 5 30.0 90 100 110 120 130 140 150 160 Electricity consumption volume : million KWH/Y

Figuere II — 8 Relation between urea production and electricity consumption volume

Relation between electricity consumption and steam consumption in Fertilizer Plant

300 350 400 450 500 550 600 Steam consumption volume 1,000 MY/Y

Figure II — 9 Relation between electricity consumption volume and steam consumption volume in fertilizer equipment

— 11 — 38 Relation between urea production and electricity consumption volume for the past 38 years and relation between electricity consumption volume and steam consumption volume in Fertilizer plant for the same period are shown in Figure II —8 and Figure II —

9, respectively. In Figure II —8, relation of urea production volume and electricity consumption volume is nearly in direct proposition and also relation between electricity volume and steam consumption volume is almost in direct proposition. Since electricity and steam supplied to Fertilizer Plant are considered as integration, value of natural gas

basic unit NH3 in power generation is treated as including steam energy accompanied by electricity per KWH in this report. In case of electricity generation by medium term turbine, energy required for power generation is entropy attributable to difference of pressure, in consideration of extracted steam, and not consistent with actual conditions,

as power generation efficiency rate becomes 100 %.

(7) Present conditions of machinery & equipment in Fertilizer Plant There are plenty of various machinery & equipment in NGFF Fertilizer Plant. Main equipment are about 300 items and number of all machinery amounts to 1,000 units. Thanks to super-annuation, application of maintenance technology is required for all of equipment, which are targeted for examination in NGFF renovation project. The present conditions of main machinery & equipment needed for urgent repair and measures are summarized.

1) Rotary machine a. Actual operation of rotary machines, such as pump, blower, and fan, are generally maintained with repair works, including repair and exchange of spare parts.

b. Since axis sealed portion of all pumps are made by grand packing method, a large quantity of liquid leakage are recognized (Discharging volume exceeding standard volume). Process liquid and utility (Cooling water, etc) are, therefore, wasted and such environmental deterioration that gas contained in liquid gives off bad smell, is brought about.

c. As a whole, screw joint is damaged and a lot of liquid discharge are found in the contact portions of auxiliary pipe (cooling water) fitted with rotary machine body.

d. 715 J1 (High pressure lean solution pump) & 715 J2 (Low pressure lean solution pump)

-11-39- Lean solution is considerably leaked from main axis portion and its solution is solidified, attached and piled in a large quantity.

e. 402 J3 (Ammonia return pump) Thanks to damages of crankcase and axis in the past, auxiliary works on large scale were implemented.

f. 402 J1 (Grain production tower supply pump) Casing pump with jacket was renovated at plant site.

g. 402 J1 (Liquid carbonic acid supply pump) Type: Vertical triplex plunger, variable stroke, High pressure service, Discharge pressure: 250 kg/cm2. Adjustment equipment for process flow volume is workable only for stroke function adjustment of this pump, but function in stroke adjustment mechanism becomes worse. As flow meter is not installed in discharge line, exact volume is not countable.

h. 402 J2 (Stable supply pump) Type: Vertical triplex plunger, Constant stroke, High pressure service. Discharge pressure: 250 kg/cm2

Owing to a number of leakage troubles in its body, exchange of packing and repair works were executed. As packing material used at present is V type packing made of synthesis rubber, its life is such short as 3 months - As examples of troubles in the past, accidents, such as cutting loss of crankshaft, connecting rod and plunger, and bearing damage occurred. In these accidents, temporary measures, including procurement of parts from local suppliers, were taken.

i. Steam turbine for power generator

In 1 unit out of 3 units, inconvenience occurred. So dismantling and inspection were made after its stoppage of operation. Wears at entrance of steam wing (3 units) were recognized. Exchange with new parts is required. j. Spare parts of seal ring for power generator’s steam turbine are short.

11-40 k. Due to corrosion of blower for gas extraction in water purification equipment, it was in poor operation. Blower made of anti-corrosive material (stainless or vinyl chloride) is required.

l. 3311 (Cooling tower supply pump) The height of cooling tower is 23 meters and short in its head, while 5.000 M3/H and 16 meters (head) are designed in the present specifications. The change to 3,000 M3/H and 24 meters (head) is needed.

m. Mixer in clarifier (Water supply equipment for product collection) is in poor operation. Inspection & repair are needed.

n. Mixer in flash mixer (product collection equipment) is in poor operation. Inspection & repair are required.

o. Water supply pump in water supply station is often stopped due to trouble or alien substances in bearing and shaft portions. As substitute for bearing type, application of non-oil supply type with hard driver is needed.

2) Machinery a. With auxiliary works, such as execution of welding and exchange of parts, actual operation of machinery is maintained. As a whole, any exterior measures for corrosion attachment to external surface, maintenance of temperature and looseness of keeping cool cover are not taken.

b. 715 F2 (Refinery tower) Owing to occurrence of inconvenience, such as development of corrosion and decrease of function in bubbling stage, repair works were executed.

c. 717 HI (Ammonia synthesis tower) As development of corrosion and reduction of catalyst’s efficiency occurred, repair works on large scale are required (The structure doesn ’t facilitate exchange works for inside basket and catalyst). Steps for Improvement are needed.

d. 718 HI (Ammonia spherical tank) Leakage of gas in connecting part of top gas exit nozzle is recognized and repair is needed. Complete extraction of liquid remaining inside the tank and re-filling method are problems to be resolved.

— II—41 — e. 402 HI (Urea synthesis tower) Specifications: Shell-multi-layer carbon steel, sus316Lx 15 mm lining, Internal temperature (°C) x pressure (kg/cm2) =185x250

- Thanks to corrosion of internal lining and gasket at top cover under severe operation conditions, operation is often stopped. f. 403 E2 (Evaporation equipment) Since the inside and outside circle parts of wing are worn down, clearance with shell’s diameter widens and efficiency declines. Troubles, such as damage of bearing relating to revolving rotor, leakage from sealed axis part and vibration inducement due to unbalance of revolving rotor, occurred. In repair shop, a lot of time is spent for auxiliary work, such as repair of bearing, increase of wing’s thickness by welding and change of balance. g. 402 FI (Excessive ammonia condenser) Owing to corrosion and frictional wear, this machine becomes risky and continuous use is unavailable. Steps for betterment are needed. h. 401 E6 (CO2 3 rd 1st separation cooler) Since efficiency decreases with excessive damage due to corrosion, measures for improvement are needed. i. 403 E4 (Evaporation equipment middle condenser) As efficiency decreases with excessive damage due to corrosion, steps for improvement are required. j. 403 G4 (Surge tank) This equipment is made of aluminum, and repair is often executed, owing to corrosion. Change of aluminum material to stainless material is under study. k. 405 E10 (Regeneration tower) As excessive damage is recognized, measures for betterment are needed. l. 405 FI (Absorber Stripper) As considerable damage is found, measures for improvement are required. m. 403 El (Decomposition equipment) Thanks to attachment and piling of scale inside of tube, efficiency of this equipment decreases.

— II — 42 — n. 40402 (Prill cooler) The outside circle surface ring is worn down considerably. The dent, due to frictional wear and scratch on outside circle surface in raider ring, is recognized.

o. 403 E5 (Evaporator after cooker) Tube was damaged due to corrosion and frictional wear. It was exchanged with new tube.

p. 404 FI (Grain production tower) Since corrosion of composition materials for grain production tower (Tower, frame, brace and stage, etc) is very severe, this tower is in danger. Execution of reinforcement works by use of supporting materials is required. Checking on volume of fine particles contained in exhaust gas coming from top of tower is needed.

q. As hand-hammering is made on outside surface of grain urea hopper to quicken contents ’ falling, serious uneven shape is recognized. Fitting of air knocker, useful for transport of powdered material, is needed.

r. High pressure water supply heater in power plant is damaged due to corrosion and frictional wear. Measures for betterment are required.

s. Thanks to considerable super-annuation of cooling tower in power plant, repair works on large scale are needed. Improvement and repair of composition materials, such as structure, framework, filling material and hood, as well as reinforcement of supporting materials are required. A half of fans are not workable, due to damage of blade and inducement of vibration.

t. As damages in cooling tower for fertilizer plant, structure for composition materials, framework, louver, lantern, filling material and hood are severe, repair and reinforcement of supporting materials are required.

3) Compressors a. The operation of each compressor is somehow maintained with repair works, such as repair and exchange of spare parts.

b. In compressor room of ammonia plant, 10 units of reciprocating gas compressor are installed. Among leaked gas from all compressors in the room, bad smell,

arising from NH3, particularly causes worst environment.

-11-43- c. In urea compressor room, 9 units of reciprocating compressor are installed. Although leaked gas from all compressors are afloat in this room, its quantity is relatively small, compared with compressor room in ammonia plant and environmental problem is not brought about.

d. As the quantity of gas leakage from 716 K1 (Synthesis gas compressor) and 717 K1 (Circular) is particularly large, measures for improvement are required. At present, leakage gas is discharged to outside of the room through exhaust dust installed at distance piece, sealed axis part, in 717 K.

e. Due to reduction in treatment capacity of 719 K1 (Ammonia refrigeration compressor), exchange works of cylinder liner and piston ring with new parts have been executed. (Any repair was not made for more than 20 years in the past). Our inspection on inside of cylinder revealed that clearance between piston ring /liner ring and interface of cylinder liner was 1.3 mm. (Standard value of this machine = 0.5~0.75 mm)

f. 16 K2 (Process air compressor) In common with all compressors, their efficiencies have decreased. As efficiency decline in 716 K2 (Process air compressor) is considerable, it is taken up as an important matter in process operation. g. 149 K1 (Ammonia refrigeration compressor) Although operation was re-started after exchanges of parts for cylinder liner,

piston ring and metallic packing, piston rod cutting accident occurred within 2 days operation. This machine was operated continuously for more than 20 years without any repair work. Until repair of this time, this compressor has been operated in such condition that load of piston rod exceeded its designed value. The transformed point in axis diameter at cross head fitting part was cut off due to effect of long-term and repeated function of load. h. 402 K1 (Air compressor) This compressor is plunger & tandem typed compressor with small quantity of flow volume capacity and usable for high pressure (350 kg/cm2). Also, it is reciprocating 5 stage compressor. With 30 mm and 16 mm diameter size in 4 absorption/5 class piston and plunger installed at high pressure part respectively, it has function and structure designed under severe conditions. As examples of trouble in the past, damage of 4 absorption and 5 class cylinder and piston ring, installed at high pressure part, often occurred. In case of comparing loss in

-11-44 shutdown period for repair works with product cost, purchase of new compressor is more advantageous.

4) Piping system a. As a whole, actual operation is maintained with repair works for pipes, such as execution of welding and exchange of spare parts. There are, however, such pipes as their thickness being reduced due to corrosion and frictional wear. Red corrosion on outside surface and exfoliation in keeping warm & cool materials are recognized. Also, liquid leakage and gas leakage from the connection of piping are found in many points.

b. Thanks to corrosion in Pipe (Size: 70/40) of exit line in 402 J1 CO2 supply pump and 40212 ammonia supply pump, its thickness decreased to 70/20. So it is in danger.

c. In execution of cooling water pipe works, there are several errors. Since the size of down stream pipe installed after junction of plural lines is smaller in its diameter than those of feeder pipes, reconsideration is required.

5) Electricity equipment a. Actual operation of electricity equipment and parts in electricity room, motor for driving rotary machine at plant site and a set of other electricity equipment are maintained with repair works, such as repair and exchange of spare parts. Due to super-annuation of electricity equipment as a whole, such operation is under severe conditions.

b. In respect of 716 K1 (Synthesis gas compressor) and high pressure motor for other compressors, several short circuit accidents occurred in the past due to poor insulation.

c. Various spare parts relating to electric parts are short. Since some of old-typed parts are not produced at present for certain reasons on the side of manufacturers, these spare parts are not obtainable.

d. Although spare parts for the existing high pressure oil circuit breaker are needed, they are not produced at present. Recently, vacuum circuit breaker is generally used. In case of low pressure breaker, mold case circuit breaker is at present popular. So procurement of spare parts for the existing oil circuit breaker becomes difficult.

11-45- e. Thanks to poor insulation in high pressure motor (400 Kw) for 410 K1 (Ammonia refrigeration compressor), troubles occurred. NGFF has chosen its course in procuring starter coil and executing fitting works by itself. (NGFF has similar experience in motor for compressor of ammonia plant)

f. Spare parts for contactor of VCM are short.

g. Spare parts for high pressure compensator are insufficient.

h. Power generator for emergency use is in poor operation, due to poor function of exciter. Exchange of exciter is needed.

6) Instrumentation Poor function and operation as well as the state, where nothing remains as the result of removal of necessary instrument, are recognized as a whole. It is due to super-annuation, frictional wear and corrosion in instruments. Instruments required for necessary process points are operated and controlled at minimum number. While repair works, such as repair and exchange of parts, are executed, actual operation is maintained. Owing to super-annuation, instrumentation is under severe conditions. Except the above, points at issue as follows.

a. It is doubtful whether adequate calibration is executed.

b. Leakage gas and liquid in high pressure parts (including pipes) are recognized.

c. Paining of whole instruments, repairs of keeping warm & cool instruments and environmental cleaning are needed.

d. As the following analyzers required in process operation are poor in their functions, they are not usable. Measures for urgent improvement are needed.

- h/N2 analyzer (717 sect) (Specific gravity measure method) - Natural gas detector (701 sect)

- CO & CO2 measure - AE-AR-701-2

- NH3 measure - Smoke route oxygen measure

-11-46- e. Instrumentation at issue in process operation

- Installation of flow volume record warning equipment is required for measuring discharged liquid volume of 402 K1 (Air compressor) (FIT-402-4, FRA-402-4)

- Adjustment of liquid volume of CO2 entering into urea synthesis tower is

available. Installation of CO2 flow volume record adjustment equipment is required. (FIT-402-2, FRCA-402-2) - Adjustment of entrance pressure in urea synthesis tower (402 HI) is available. Pressure record adjustment instrument is needed. (PCV-402-14)

f. Due to troubles in analyzer for boiler water supply and PH meter, hey are not usable.

g. The following in water supply equipment are in extremely difficult conditions, due to their poor functions. Since they are essentially required for process operation, urgent measures are needed.

- Automatic operation is not available due to poor functions of all JCV air function valve. Because of many points, where manual operation is executed, smooth operation is not expected. Procurement of new air typed automatic valve is required. - Exchange of PH meter is needed. - Exchange of silica analyzer is required.

7) Present situation relating to machinery plant equipment and construction machine

a. Repair shop equipment Thanks to super-annuation in machinery processing equipment, the following machinery processing equipment are not usable.

-Universal grinding machine: Length of bed: 10-6 ”, swing: 15”, motor: 7.5 kw -Bench type grinding machine:, motor: 3 kw -Screw cutter (Screw: BS standard) -Radial drill machine:

Inconvenience in fixed supporter and inducement of vibration often occur, due to damage of working structure. Although repair and exchange of parts are necessary, repair is unavailable as these parts are not produced at present.

-Air hammer, falling weight: 250 kg, motor: 22 kw

11-47- -Driving part of 5 tonsof ceiling- run crane is unworkable.

b. Welding & manufacturing instrument

- For reinforcement of repair works through execution of welding, provision of DC & AC welding materials is newly required. - NGFF has its own welding experts. In respect of inspection after welding execution, NGFF asks at present Atomic Energy Center in Bangladesh to delegate experts for such inspection.

c. Construction machine

Thanks to super-annuation and excessive damages, some of crane ,pay-loader, and folk-lift are unworkable in their operation. Management of plant operation relies on newly procured heavy machines.

- Reinforcement for maintenance of each machine and management of spare parts as well as prolongment of their lives are required. - 20 tons crane: Provision of spare parts is needed. - 40 tons P & H crane :Spare parts are required. - Folk-lift (3 tons): New folk-lift is needed. - Truck crane (10 tons): Provision of spare parts ids required. - Pay loader: Provision of spare parts is needed.

2.3 Capacity for Performing the Project on the Side of NGFF Fenchuganj Fertilizer Plant

(1) Technical capacity

Judging from NGFF’s technical capacity in the aspect of plant engineering, divided into engineering, procurement, construction and operation (E, P, C and O), it seems that both of NGFF and BCIC don ’t have capacities for performing the project. NGFF has, however, continued its operation and maintenance of the plant for 40 years after start-up. In respect of plant operation and maintenance technology, it has, therefore, plenty of experience and technical capacity.

Since procurement of necessary machinery & materials for maintenance was made by itself, it is not overestimation to say that NGFF has sufficient capacity in this field, including overseas procurement. In rehabilitation work made in 1978, NGFF implemented all local works by itself under support of several supervisors delegated from

-11-48- Japan. In regard to local works, there is a pile of technology accumulated in many years. So its technical capacity come up to our expectation.

1) Capacity for engineering

BCIC and NGFF don ’t have capacity for engineering. Among plants under the umbrella of BCIC, personnel change is often carried out and many technical staffs in NGFF have their working experience of working in BCIC’ s other plants. They have, therefore, know-how on chemical fertilizer process and operation & maintenance of equipment. These technologies are, however, individually held and not accumulated in organization as a whole. And they are not good at numbers and drawings.

All of 7 fertilizer plants under the umbrella of BCIC were constructed with finance or fund from overseas and all of their construction contracts were concluded with foreign engineering companies as package deal. Under the circumstances, there are historical details that BCIC entrusted engineering with contractors, which made their basic & detail designs in foreign countries, and any technical transfer of practical method for project was not received by BCIC.

With collection of technical information from BCIC ’ s fertilizer plants and unified management of such technical information, BCIC appears to be able to accumulate sufficient engineering know-how easily. In case that establishment of engineering method is made, implementation of engineering required for repair work or maintenance & conservation in all of BCIC ’s fertilizer plant becomes attainable.

2) Procurement of machinery & materials NGFF has its capacity for procurement of machinery & materials needed for plant maintenance & conservation, including overseas procurement. All procurement of machinery & materials by the Government and public corporations are regulated to be made by open tender in accordance with domestic rule in Bangladesh. NGFF’s procurement of machinery & materials is made in compliance with such rule accordingly.

In domestic newspapers, there are public notices of invitation to tender everyday (See Photograph II — 2). In such public notice, international procurement and domestic procurement are itemized. In regard to L/C opening relating to overseas procurement and quality compensation method, including inspection at plant site, BCIC has plenty of experience. Since BCIC has agents for forwarder business in

— II — 49 — Chittagong Port in respect of transport of overseas procurement machinery & materials, it applies itself to receive cargoes and transport such cargoes to plants on behalf of NGFF.

Photograph II —2 There are at all times a lot of public notices for tender in newspapers

3) Local works It is our judgement that NGFF has sufficient technical capacity of implementing installation work required for renovation work. Since completion of construction work, NGFF has continued plant operation & maintained relevant equipment by itself. Also, it has experience in rehabilitation works several times in the past.

During the period from 1978 through 1979, NGFF implemented rehabilitation on relatively large scale under technical assistance of Kobe Steel Ltd. with Overseas Economic Fund’ s financial aid amounting to 28.55 Kurore. In 1987, rehabilitation work was executed under ODA’s fund in the amount of 95.9 million Taka. Although Bangladesh Government made its decision to close NGFF in 1993, it determined NGFF ‘s continuation due to social reason in this district, with reversion of the above decision, and in 1995 NGFF made its overhaul under financial aid in the amount of 50.3 million Taka from Bangladesh Government. At present, rehabilitation work with the Government ’s ADP (Annual Development Program) in the amount of 2 billion Taka is under progress. NGFF’s maintenance division has many years experience in doing daily works, such as removal of machinery, repair and installation, without stopping operation in other lines. NGFF ’s experience and capacity in repair work appear to be superior to those of unaccustomed outside constructors. With some construction machines and machinery plant, NGFF ’s maintenance division is able to perform repair works of this time through supply and provision of necessary spare parts. Meanwhile, BCIC is in a position to lend construction machines owned by other fertilizer plants to NGFF, if necessary.

(2) Management system As in BCIC ’s other plants, there is hardly any delegation of management power, including technical division ’s operation, maintenance and inspection of whole plant, from general manager to responsible persons in each special division of NGFF. With full responsibility of general manager, top-down management system is complete in the plant. In case of implementation of the project, general manager is expected to hold additional post of project manager on NGFF side, and any staff of NGFF is not assigned to such position.

NGFF ’s organization is shown in Figure II— 10. The number of NGFF ’s employees is at present about 1,15o persons. Owing to recent personnel cut, the number of employees has decreased. It’s organization is subdivided and office duties ranging from engineer to technical staff are clearly distinguished.

11-51 1150 Figure!! —10 Organization Chart of NGFF

lx DCE/DCC lx DCE(Civil) f) 2x Motor Cycle lx ME/Chem 1x Office Assist (Mosbbirul Islam) 2, Office Equipment 4x Ag/AC/AS 1 x MUSS 1x Engineer (C) a) 1 x Plain Paper Copier 26x MO 'MT/ HS07 HST 1x Sweeper b) IxDuplicating Machine lOx SO-I/SO-II/ 2xHO/HST 1 x Office Assist, c) 60 x Typewriter ST-l/ST-II 1x ST-I/ST-D lx Typist d) 1 x Fax Machine 4x SSO/SST lx SSO/SST lx MLSS e) 14 x Calculator 4x MT/MST f) lx Air Conditioner 2x ST-I/ST-H 2x SST

a) A.C.M. (Gen. Adm. Protocol) Additional Chief Manger a) Aya Female Assist to Nurse for Attending the b) MLSS (Many Places) Member of Lower Subordinate Staff Patients in Medical Labo c) A.C.M.0. (Medical) Additional Chief Medical Officer b) Imam Mosque Guide d) D.C.M.O. (Medical) Dupty Chief Medical Officer c)Moazzin Mosque Guide e) M.O. (Medical) Medical Officer d) Khadim Helper in Mosque f) A.H.M. (School) Assistant Head Master g) A.C.A. (Finance) Additional Chief Accountant h) D.C.A (Finance) Dupty Chief Accountant i ) A.O. (Finance) Accuntant Officer j ) D.C.A. (Bill, Pay) Dupty Chief Accountant k) D.C.E/D.C.C. (Ammonia) Dupty Chief Engineer/Dupty Chief Chemist 1) S.A.E./Forman (Ammonia) Sub Assistant Engineer/Forman m) M.O./H.S.O. (Ammonia) Master Operator/Highly Skilled Operator n) SO-I/SO-II (Ammonia) Skilled Operator-I/Skilled Operator-II o) SSO/SST (Ammonia) Semi Skilled Operator/Semi Skilled Technician p) MO/HSO (Ammonia) Master Operator/Highly Skilled Operator q) D.C.C./D.C.E. (Urea) Dupty Chief Chemist/Dupty Chief Engineer r) AE/AC/AS (Urea) Assistant Engineer/Assistant Chemist/Assistant Superintendent s) MO/HST (Urea) Master Operator/Highly Skilled Technician t) ST-I/ST-II (Urea) Skilled Techinician-I/Skilled Technician-!! u) D O E (Sylhet Gas Pipe) Dupty Chief Engineer v) MO/MT (Water Pump Supply) Master Operator/Master Technician w) M E.. (Mechanical) Mechanical Engineer x) DOE (Civil) (Civil) Dupty Chief Engineer y) AE (Civil) Assistant Engineer z) MT/HST (Civil) Master Technician/Highly Skilled Technician aa) DOE (Training & Tech.) Dupty Chief Engineer bb) Sr. S.F.O. (Fire & Safety) Senior Safety and Fire Officer cc) F.S.L. (Fire & Safety) Fire and Safety Leader dd) MPIC Material Planning and Inventory Control ee) SGPL Syhlet Gas Pipe Line (3) Management foundation, management policy

NGFF is compelled to manage itself under weak financial foundation and severe management policy. NGFF ’s own planning and implementation of future management problems, such as sales and income program required for company management, is in difficult condition. Thanks to deficiency of supply, domestic fertilizer market in Bangladesh relies on import for making up for the shortage of around 50,000 tons annually. In each fertilizer plant of BCIC, its necessary production volume is decreasing due to super-annuation and shortage of fund. Based on the tendency, such as demand increase and production volume reduction, import volume of urea is likely to increase in the future.

With domestic demand of urea exceeding its production volume extremely, a seller’s market is formed in Bangladesh. Since urea product prices are determined by the Government and bagged urea has been fixed as 4,800 Taka per ton for several years, market principle is, however, not applicable. Such being the case, management effort in operation appears unnecessary. In 2000, the Government introduced territorial allocation system in production, distribution and consumption of fertilizer. As a result, trading of NGFF ’s fertilizer was limited to 4 traders in the suburbs of Sylhet. Reflecting poor capacities of these traders, 35,000 tons of urea is stored in NGFF ’s fertilizer warehouse and 150 million Taka of inventories are posted in NGFF.

Meanwhile, natural gas price was raised twice by 15 % each in December, 1998 and September, 2000, respectively. At present, price per 11 m3 is 1.93 Taka and total payment amounts to 30 million Taka monthly. With posting red figures every year, NGFF has accumulated deficiency amounting to 300 million Taka. Such accumulated capital deficiency is almost equivalent to arrears to Jalalabad Gas Supply Co, natural gas supplier. Such being the case, the gas supply company gives a warning of stopping gas supply, unless gas rates in arrears are settled. Without introduction of fund from Bangladesh Government, NGFF is not in a position to solve this problem only by its management effort. Under such limited circumstance that the Government decided continuation of NGFF ’s operation and urea product ’s official price is fixed below production cost and distribution has to rely on traders designated by the Government, management responsibility is restricted to product cost reduction, attainable by reasonable management through restructuring of organization as well as increase of production volume and basic unit reduction effect.

In the process of organization ’s restructuring, a considerable number of employees ’ cut was made. Because of request to shorten stoppage time of operation for production

-11-53- increase, there is a possibility that maintenance method becomes sloppy. Under the limited time and budget, procurement of pure spare parts or parts, consistent with specifications, become difficult and available materials, kept by side, are used after adequate machine processing. And it results in increase of the number of operation interruption as well as production volume reduction.

(4) Capacity for financial burden

BCIC has neither intention nor capacity to bear funds required for NGFF ’ s rehabilitation through implementation of COM. BCIC asks Japan for providing all funds needed in the project, including fund for local works. Ex work price of urea product has been fixed domestically for several years by the Government as 4,800 Taka per ton in respect of 50kg bagged product. Although natural gas basic units are relatively low in BCIC ’s other latest large size urea plants, payback of initial investment are not yet finished in some of these plants. With gradual increase in material natural gas price, back spreads are recorded in many plants. In BCIC ’s fertilizer plants, around 6,000 Taka of production cost on the average exceeds its sales price. Despite BCIC ‘s request for urgent increase of urea price by 1,000 Taka per ton at the minimum against the Government, it has no chance of raising such price, since general election of Parliament members in next year is near at hand. Under such difficult financial condition, BCIC refuses to undertake its finance for NGFF ’s renovation work.

Although initial investment was amortized with a lapse of 40 years since Start-up of operation in NGFF, its basic unit is 2 times as much as those of other latest plants. In continuation of red book closing, NGFF has to maintain its operation and present capital deficiency comes up to approximately 300 million Taka with gradual exhaustion of working capital. As annual budget for maintenance works amounts to 10 million Taka (20 million Yen) only, such works required for maintenance of operation are postponed accumulatively and its operation is put in danger.

Under thee circumstances, Bangladesh Government decided to implement rehabilitation required for maintenance of safe operation in NGFF with introduction of fund, amounting to 450 million Taka totally, in 2 phases and 1st phase rehabilitation with budget of 200 million Taka is in progress. Following up 1st phase rehabilitation to be completed in June, 2001, 2nd phase rehabilitation with budget of 250 million Taka (about 500 million Yen) is now under preparation with its implementation schedule in July, 2001. Also, NGFF has no capacity for bearing financial burden.

-11-54- Although BCIC insists on its inability for financial burden, budgetary measure for 2nd phase rehabilitation in NGFF has been taken. With regard to use of 250 million Taka of budget planned for 2nd phase rehabilitation work as Bangladesh ‘s financial part, more consideration is needed.

In addition, NGFF has necessary equipment and technology, including man power and construction machines, required for plant maintenance, since it continued its operation while maintaining urea production equipment for the past 40 years. Also, BCIC ’ s other urea plants have capacities for maintenance & inspection of their own equipment. Meanwhile, adjustment of resources, including construction machines owned by BCIC ’ s plants, is needed for their maximum use in NGFF ’ s renovation work. NGFF has also machinery plant equipment, construction materials for its own maintenance. It is conceivable that the value, obtainable from making use of these resources in local works of CDM energy saving project, is counted as part of Bangladesh ’ s financial provision.

(5) Capacity for provision of manpower NGFF ’ s maintenance division organizes its line-up, consisting of 359 persons. Out of the total members, there are 106 persons in power generation division, 102 persons in electricity & instrumentation division and 15 persons in civil engineering & construction division and other divisions. Completion of local works is achievable by making use of these members effectively in parallel with usual maintenance works.

In addition, support from operation division is obtainable, if necessary, since such division has 404 employees. Although BCIC has not any person suitable to NGFF ’ s renovation work among its members, taking main positions, delegation of one or two technical staffs is conceivable but it is limited to technical experts of machinery and civil engineering. Any technical expert in instrumentation field is unavailable.

(6) System for implementation BCIC has its understanding of lump sum turn key form being unsuitable to renovation project in NGFF and doesn ’t stick to open tender method particularly. Although a contractor is decided in principle through open tender method, there are many previous instances of contracts on private base. For example, there are capacity betterment projects, such as renovation works in Ghorasal and CUPL. Also, Bangladesh Government has its understanding of private contract to be concluded with original contractor without tendering in the case of China ’s renovation agreement in PUFL. It is, therefore, probable that implementation of NGFF renovation work is made exceptionally by Japanese alliance, since construction of NGFF Fertilizer Plant was built up by Japanese alliance. Reasonable contract amount is, however, required as precondition.

As scale and details of CDM renovation work are similar to those of previous rehabilitation work executed in 1978, it doesn ’t raise a question as far as responsibilities are shared in same way. In previous rehabilitation work, engineering and main machinery & materials were provided by Japanese side and implementation scope of construction works were shared by NGFF, for reason of plant performance responsibility being taken by Japanese side.

NGFF ’ s consent on project implementation through similar sharing of responsibility has been obtained. Project team for implementation of basic design and procurement business is formed outside Bangladesh (Probably in Japan). It is ideal that detail design is executed by domestic design company in Bangladesh and installation work is implemented by NGFF ’ s members, headed by responsible persons in charge of such works. With continuation of maintenance for 40 years, NGFF Plant has know-how on such maintenance. Since execution of such work is needed without making sacrifice of production volume, coordination, among production division, maintenance division, and local work contractor, is essentially required. Also, project manager’s ability for adjustment with general manager in each division is needed. In view of these conditions, managing director of NGFF Plant appears to be most suitable person for project manager at execution site. Project manager is scheduled to appoint a coordinator for project adjustment, who fulfills his duty on behalf of project manager, among NGFF ’s staffs. From Japan, delegation of several supervisors is expected. Thanks to difficulty in completing all construction works in short period only by NGFF members, local companies are to be appointed. Main business of these local companies is provision of technical experts and laborers, but their provision of construction machines and materials for works appears to be difficult. It is, therefore, necessary to make use of NGFF ’ s machinery & materials at the maximum and use insufficient items borrowed from BCIC ’ s other plants.

-11-56 2.4 Details of the Project and Specifications of Relevant Equipment after Renovation in NGFF Fertilizer Plant

(1) Details of the project in Fenchuganj Fertilizer Plant

1) Process improvement Process improvement is limited to energy massive consumption typed ammonia process, while betterment works in urea production process are not planned due to relatively low economical effect obtainable from energy saving through change to latest carbamate cycle method, compared with investment amount. Improvement part of ammonia process is shown in Figure II — 11 “Process flow after improvement of ammonia equipment”. The part, indicated by heavy line in Figure II — 11, is process laying- pipes in improvement part.

a. Improvement of ammonia synthesis gas refinery method (Plan - A)

With installation of low temperature converter and methanator after abolition of synthesis gas washing equipment, using lean solution, prevention of environmental pollution due to leakage of lean solution and energy saving are achievable. The change parts of process are as follows.

- By means of installing low temperature converter (8) between the existing CO] removal regeneration tower re-boiler (713E4) and gas scrapper cooler (701E4), reduction of CO, remained in process gas, from the present level of

2.0 % to 0.12 % is attainable.

- Reduction of thermal volume required for regeneration of solution is achievable, by mixing absorption activation catalyst, anti-corrosion agent and anti-foaming agent with thermal lean solution in CO] removal equipment and reducing volume of CO] remained in the gas from the present level of 0.6 % to 0.2 %. For the purpose of increasing absorption efficiency in CO] absorption tower (713F1) and regeneration efficiency in regeneration tower (713F2), internally filled materials are changed.

- After being divided at absorption side of gas compressor 2nd stage (17), process gas coming from C02 removal equipment is successively introduced into newly installed methanator pre-heater (12), methanator thermal exchanger (13), mathanator (14), final cooler (15) and drain separator (16), and synthesis gas is refined by means of converting remained CO and C02 into methane through methanator reaction. Refined gas is returned to absorption side of gas compressor 2nd stage together with process gas.

11-57- - Compressed synthesis gas in gas compressor 2nd and 3rd stage is supplied directly to absorption side of gas compressor 4th stage by skipping copper acetic acid gas refinery equipment. In this process, such copper acetic acid gas refinery equipment is not used.

With installation of ammonia equipment in each of 2 lines, independent operation of each line is available. Methanation reaction is a kind of large heat generation reaction occurred at 190 °C on nickel related catalyst. Although total content of CO and C02 at entrance of

methanator amounts to 0.35 % only, there is an increase of temperature up to 21 °C. In methanator pre-heater (12), process gas to be sent to methanator is preheated by high temperature reformed gas coming from HIT (6). Such methanator pre-heater is usable only at the beginning of raising temperature in methanator , but only heat exchanger for heat generation in methanator is used after normal operation condition. As H2Q is generated by methanation reaction, refined gas is divided, after condensed water being separated by drain separator (16), and returned to absorption side of the existing gas compressor 4th stage for its movement to ammonia synthesis gas equipment. b. Addition of HD S

Since natural gas received by NGFF contains a small quantity of sulfur, it is absorbed and removed in organic sulfur removal tank(l) by activation carbon for preventing poisoning of nickel related reformed catalyst. As Cu-Zn related low temperature CO conversion catalyst, extremely sensitive to sulfur, is used in reforming process, reduction of sulfur contained in process gas to the level below ppm is needed. With installation of HDS (4), filling CO-Mo catalyst and ZnO, in addition to organic sulfur removal tank before the process of natural gas supply to reforming equipment, a small quantity of remained sulfur is removed. Although HDS (4) is newly installed for 1 line, it treats 2 lines’ volume of process natural gas collectively. After then, such collected gas is divided into 2 parts and supplied to each of the lines. HDS consists of 2 catalyst filling layers, such as upper and lower layer. C02-Mo and ZnO are filled in entrance of upper part and exit of lower part, respectively. After going through the existing organic sulfur removal tank (701 Gl) in the state of normal temperature, process natural gas absorbs and removes organic sulfur by activation carbon. And, after being preheated up to 350 °C at first by steam in the existing process gas pre-heater (701E7) and secondly by HTS exit gas in newly installed process gas pre-heater (3), it is supplied to HDS (4), adding a small quantity of purge gas (191 Nm3/H) coming from ammonia synthesis part. In HDS, organic sulfur is at first

converted into sulfuric hydrogen through water addition reaction by Co-Mo catalyst. Generated sulfuric hydrogen is absorbed into ZnO in lower layer and separated from process natural gas. Sulfur remained in process gas is reduced to the level below comma

-11-58- ppm. Process steam and process gas are mixed after water addition desulfurization process, because of occurrence of H20 + ZnO = Zn (OH)2 reaction. Completely desulfurized process natural gas is sent to reforming equipment, after being mixed with steam, heated up to 400 °C by process gas from HTS, in the existing process steam super-heater(701E3).

-11-59-

Unit

Ammonia Synthesis Synthesis Aqueous Ammonia Water Cooling Delete piping

Water Cooling Process

Flow

Steam Established

=

Newly Process

Notes:STM Ammonia

Synthesis

Potash Removal

Urea

Hot COo To Improved

, 2 Gas

C0 Natural Reformer 11

II

Figure Drain Gas

Process Natural Water Coolin;

11-60 The name and number of machinery & equipment in process flow after ammonia equipment renovation in Figure II — 11 are as follows.

1. Activation carbon organic sulfur removal tank (701G1) 2. Process gas pre-heater (701E) 3. Process gas pre-heater (701E) 4. Water addition desulfurization tank (newly installed) 5. Process steam super heater (newly installed) 6. High temperature CO converter (701H1) 7. CO] removal regeneration re-boiler (713E4) 8. Low temperature CO converter (newly installed) 9. Gas scrapper cooler (701E) 10. Drain separator (701G2) 11. Gas compressor 1 st stage (716K 1) 12. Methanator pre-heater (newly installed) 13. Methanator heat exchanger (newly installed) 14. Methanator (newly installed) 15. Final cooler (newly installed) 16. Drain separator (newly installed) 17. Gas compressor 2nd & 3 rd stage (716K) 18. Gas compressor 4th stage (716K1) 19. Ammonia scrapper (newly installed) 20. Filter (newly installed) 21. Purge gas raising temperature instrument (newly installed) 22. Diffusion film typed hydrogen separator (newly installed) c. Collection of hydrogen from synthesis purge gas (Plan - B)

At present, purge gas discharged from ammonia synthesis gas is as follows.

H : 59.3 %, N : 19.7 %, NH3 : 10.0 %, Ar : 4.6 %, Ch4 : 6.4 % Flow volume:590 Nm3/h, Total : l,180Nm3/h, Temperature: 40 °C,

Pressure : 350 kg/cm2

Purge gas is now used as fuel in natural gas 1st reforming furnace. In this collection work, energy saving is attainable by means of collecting ammonia and hydrogen from this purge. Collected gas from 2 lines is collectively treated in 1 line of hydrogen collection equipment. Purge gas, discharged from ammonia synthesis part, is supplied to newly installed ammonia scrapper (19)

-11-61 and washed with water cycled by pump. And then, ammonia out of purge gas is washed and removed. By sending water to urea equipment, ammonia is collectable. Hydrogen is also separated and collected by diffusion film method. As diffusion film is, however, affected by liquid drip accompanied from ammonia scrapper (19) in the process of separation & collection, such

liquid drip is completely removed from gas by filter (20), before hydrogen being supplied to diffusion film type hydrogen separator (22). In addition, liquid drip, incompletely separated in filter, is completely evaporated by means of increasing its temperature up to 50 °C with steam in purge gas raising temperature equipment (21). In case of temperature being relatively higher, diffusion coefficient becomes larger and good efficiency is obtainable. Diffusion film typed hydrogen separator (21) has such structure as bundling hollow string. In diffusion film typed hydrogen separator (21), hydrogen penetrates selectively as a main component and other gas components rarely penetrate. Components of penetrated gas are as follows.

Hz: 92.8 %, Nz : 4.7 %, NH3: 0.0 %, Ar : 11.7 %,% : 0.8 % Flow volume: 528Nm3/h totally in 2 lines, Temperature: 40 °C, Pressure: 18

kg/cm2

While collection rate of ammonia is almost 100 %, that of hydrogen exceeds 90 %. Collected hydrogen is returned to absorption side of gas compressor (17) 2nd stage and recycled. Non-penetrated gas, including nitrogen mainly and more than 30 % of hydrogen and methane totally, is sent to 1st reforming furnace and used as fuel gas.

2) Improvement of machinery & equipment through maintenance

In NGFF Fertilizer Plant, there are about 300 units of main machinery and the number of all machinery comes up to nearly 1,000 units. Thanks to super-annuation, application of maintenance technology is required for all the machinery, which is targeted for examination in NGFF renovation project. With extraction of items affecting urea production considerably and items urgently needed in NGFF Plant, around 200 items were studied carefully together with NGFF ’s technical staffs. Consequently, such maintenance as mentioned in the following paragraph (2) 2): Specifications after repair of machinery & equipment has been determined.

-11-62 (2) Specifications after renovation of relevant equipment in Fenchuganj Fertilizer Plant

1) Specifications of new machinery relating to process improvement

Specifications of new machinery relating to process improvement are shown in specifications list of the following Table 11—13 Plan A (Abolition of lean solution washing equipment) and Table 11—14 Plan B (Purge gas hydrogen collection). Although specifications of civil engineering foundation, steel framework construction work, electricity, instrumentation, laying pipes, and keeping warm & painting works are actually needed, they are omitted in this report.

— 11 — 63 — a. Improvement of ammonia synthesis gas refinery method (Plan —A)

Table II —13 Specifications list of new machinery in Plan-A (Abolition of lean solution washing equipment)

Number of Name of Quality of Quantity Specifications machinery machinery material

3 Process natural 1 body side: multi-pipe cylinder type heat exchanger, TEM-C, BEM, (body gas pre-heater SB, condition) : liquid FITS exit gas, pressure : 6.4 kg, entrance temperature : 438 °C, exit temperature : 234 °C, (pipe side pipe side: STB condition) : natural gas, pressure : 12 kg, entrance temperature: 185 °C, exit temperature : 400 °C, heat transfer pipe : 150 pieces, 3/4", OD : 150 pieces, body : 400 D x 6,000 L

4 Water addition 1 SB legged vertical type cylinder compression vessel, designed reactor pressure : 8.6 kg, designed temperature : 350 °C, body diameter; 1940, T-T 6100, upper part Co-Mo catalyst: 6.8 m3, lower part ZnO catalyst : 4 m3, catalyst layer with support, catalyst entrance & exit manhole: 4 points, TE : 4 pieces, P : 11 pieces

8 Low 2 SB41B independent vertical cylinder pressure vessel, designed pressure: temperature 8 kg, designed temperature : 211 °C, body size : 3000 reactor Dx5000T-T, total height : 8100, catalyst upper part : ZnO, catalyst bottom part: Cu-Zn related LTS catalyst

713F1 C02 absorption 2 existing exchange of fillings, addition of absorption activation agent tower 713F2 C02 2 existing exchange of fillings, addition of anti-corrosion agent and regeneration anti-foaming agent tower

12 Methanator 2 SB/STP multi cylinder type heat exchanger, TEM-C, (body side pre-heater condition): liquid FITS exit gas, pressure: 6.4 kg, entrance temperature : 438 °C, exit temperature : 243 °C, (pipe side condition) liquid C02 removal exit gas, pressure : 19.4 kg, entrance temperature : 40°C, exit temperature : 190 °C

13 Methanator heat 2 SB multi cylinder type heat exchanger, type: TEM-C, BEM, (body exchanger side condition) liquid methanator exit gas, pressure : 18.5 kg, entrance temperature : 211 °C, exit temperature : 60 °C, (pipe side condition) liquid C02 removal exit, pressure : 19.4 kg, entrance temperature: 40 °C, exit temperature : 190 °C, body size : 318.5 x 6,690 L, 4 units

15 Final ccooler 2 SB/STP multi cylinder type heat exchanger, type: TEM-C, BEM, (body side condition) liquid methanator exit gas, pressure : 18.5 kg, entrance temperature : 60 °C, exit temperature: 40 °C, (pipe side condition) cooling water, pressure: 5 kg, entrance temperature : 30 °C, exit temperature : 40 °C, body size : 318.5 D x 6,130 L

14 Methanator 2 SB(Alloy) Type : vertical cylinder, fillings : Ni related methanator catalyst, size : 1,200 D x 5,270 H

16 Drain separator 2 C/S Type : vertical cylinder with wire mist caatcher, size : 318.5 D x 2,650 H, temperature: 40 °C, pressure : 19 kg

— II — 64 — b. Collection of hydrogen and ammonia from ammonia synthesis purge gas (Plan-B)

Generally, equipment for collection of hydrogen and ammonia from ammonia synthesis purge gas, is supplied by vendor as a package, including all of the following equipment on skid, after completion of laying pipes and painting works. Local works are, therefore, limited to their connections with the existing pipes.

Table 11 — 14 Specifications list of new machinery in Plan-B (Purge gas hydrogen collection)

Number of Name of Quality of Quantity Specifications machinery machinery material 19 Ammonia 1 SB/STPC Capacity : entrance gas volume : 1,180 nm3/H, ammonia synthesis scrapper gas ccomposition : H2 : 59.3 %, N2 : 19.9 %, NH2, 10.0 %, Ar:4.6 %, CH4 : 6.4 %, pressuree : 110 kg/cmG, entrance temperature : 33 °C, equipment : ammonia removal by pressure reduction and washing, auxiliary equipment: water cycle pump and water surge pump are included.

20 Filter 1 SB(C/S) disposal gas volume : 1.180 Nm3/H, Temperature : 33 °C, pressure .110 kg, temperature : 33 °C, pressure .110 kg, Mist from ammonia scrapper is separated and removed.

21 Purge gas 1 SB/STP multi cylinder type heat exchanger, type : TEM-C, BEM, (body raising side condition) liquid steam, pressure : 2 kg/cm2G, entrance temperature temperature : 120 °C, (pipe side condition) : purge gas, pressure instrument 110 kg/cm2G, entrance temperature : 33 °C, exit temperature : 50 t

22 Diffusion type 1 body BS entrance gas volume: 1,062 Nm3/h, entrance pressure : 110 hydrogen hollow kg/cm2G, temperature : 50 °C, hydrogen collection rate : more separator string than 90 %, collected hydrogen pressure : exceeding 18 kg/cm2G diffusion film filling, capacity

2) Specifications of machinery & equipment relating to maintenance

a. Repair specifications of machinery & instruments relating to Ammonia Plant

1. 716K.1 Synthesis eas compressor (snare parts & equipment) required quantity : for 2 units Spare parts - Piston ring 2 sets - Piston rod 1 set - Piston 1 set - Cylinder liner 1 set - Valve plate 200 - Valve spring 1,000 - White metal bearing 2 sets - Metallic packing 2 sets

-11-65- 2. 716 K2 Process air compressor (spare parts & equipment) required quantity : for 2 units - Installation of new oil filter in exit side process line - Installation of 1st and 2nd filter for removal of mist in lubricating oil - Set-up of elements in each filter as spare parts 3. Cooling water pump (manufacturing & exchange) required unit: 1 unit pump specifications - Type : centrifugal pump, - Disposal liquid : cooling water, - Capacity : 500 m3/h, - Pressure : absorption pressure =11.0 kg/cm2G, discharge pressure = discharge 2.0 kg/cm2 - Temperature :25 - Seal type : grand packing method, - Quality of material : body-cast iron, shaft-carbon steel, Motor : motor 18.5 KW x 6 P x 400 V 4. 716K2 Process air compressor (manufacturing & addition) required unit: 1 unit A. Compressor type centrifugal type compressor B. Summarized specifications compressor : 4 stages disposal wind volume : 6,000 Nm3/ discharge pressure : 8.5 ATG axis driving force : 675 KW

electromotor : 750 KW x 2P x 3,300 V x 3 4> x 50 Hz, C. Accessories inter-cooler, after-cooler lubricating oil equipment, laying pipes, a set of instrumentation, common holder D. Spare parts (for 2 years operation) bearing, axis seal, filter-element, O ring, gasket 5. 717H 1 Ammonia synthesis basket (manufacturing & exchange of catalyst and others) required unit: 1 unit As its efficiency decreased and maintenance became difficult, due to its structure, in which exchange of catalyst is unavailable, a new basket (filled with catalyst) is manufactured. 6. Non-activated gas generator (Installation of new equipment) Required unit: 1 unit specifications - N2 gas generation flow volume 200 Nnr/h - Product N2 gas ccompsition N2+ Ar = 99.9 vol % - Operation time 8 h/day - Composition method air compressor + air dyer + N2 gas generation equipment - Composition equipment Except the above, receiver tank (about 1 m3), laying pipes electricity, a set of new product - Motor for compressor 100 Kw x 400 V x 3 0 x 50 H Fitting area : About 12 m Lx3mWx4mH

11—66 — b. Repair specifications of machinery and instruments relating to Urea Plant

1. 402 K1 A. B. C air compressor (manufacture & exchange) exchange quantity : for 2 units Design specifications: -Type : multi stage piston type - capacity : 40Nm3 /h air - absorption pressure : 1 kg/cm2, discharge pressure : 325 kg/cm2 - design temperature : 0-35 U Machinery specifications : -type : horizontal, 5 stages, oil lubricating method - number of rotation : around 360 rpm - driving force transmission : V-belt driving - base : common base - quality of material : gas contact part-steel, piston-aluminum, piston rod-steel - motor : 22 kw x 400v x 50HZ Accessories: - heat exchanger - oil separator, measure (thermometer, cooling water flow volume controller, oil flow volume meter, etc) - absorption filter : spare instrument: 4 sets each 2. 401E6 CO? 3 stage 1st discharge cooler (manufacturing & exchange) 1 set This machine is considerably damaged due to corrosion. Its exchange for newly manufactured machine is needed. 3. 402J 1 A. B. C liquid ammonia sunolv oumn (snare Darts & equipment) Required quantity : 13 units Machinery specifications : - Type : fixed speed stroke, plunger type - temperature : entraance-16—38 °C - prressure : entrance-18—20 kg/cm2, exit: 250 kg/cm2G Spare parts : - packing: type : V type, material-Teflon, quantity: 1000 size : 3-3/8” OD x 2-3/8” ID - spacer Quality of material: SUS-304 quantity: 30 pieces - adapter : (male, female) Quality of material : SUS-304 quantity : 30 pieces each 4. 402H1 A. B. C urea synthesis tower (spare parts & equipment) Machinery specifications : - size : 1,000 $ x 12,000 h x 150 t, - type : multi layer vertical cylinder type, inside surface: SUS 316 L lining - entrance temperature : 100 °C, exit temperature : 185 °C, entrance pressure: 250 kg/cm2G Spare parts : - quality of material : upper part lining, size: 2,000 W x 4,000 L x lOt,quality off material : SUS 316L, quantity : 16 pieces, (Cleaning and treatment for anti-transmission are needed.) -spare parts for AL-gasket -4 sets - manufacturing of new top cover, quality of material : SUS 316L, quantity : 1 set - 2-1/2” stud bold, quality of material SUS-316 : quantity : 32 pieces - 4” corn liner, quality of material : 1 set -reducer : quantity : 3 sets 5. 402 FI Excessive ammonia condenser (procurement of materials & repair at plant site) It is in danger, owing to reduction of thickness caused by corrosion. Procurement of new lining material and welding work at plant site are required. Procurement of materials : quality of material : SUS 316L, size: 1,000 W x 3,500L x 44 t, quantity : 27 pieces 6. 403E4 Evaporator middle condenser (manufacturing & exchange) 3 units It is in danger, due to damage attributable to corrosion. Manufacturing of new shell and tube bundle and their exchange for the existing equipment are needed. 7. 403G4 Urea surge tank (procurement of material and manufacturing at plant site) 3 units Repair is required frequently due to corrosion of body, made of AL material. Procurement of stainless material and repair at plant site are needed. Procurement of material: Size : 1,000 W x 3,000 L x 10 t, quality of material: SUS-304, quantity : 20 pieces 8. 405E Regeneration tower boiler (manufacturing & exchange) 1 unit It is damaged considerably due to corrosion. Shell is newly manufactured by use of clad steel. (Stainless material lining was originally planned, but application of clad steel has been decided, in view of accuracy in execution work) 9. 405 FI Absorption tower stopper (procurement of material & works at plant site) It is damaged considerably owing to corrosion. Procurement of material and lining work at plant site are needed. Procurement of material: Size : 1,000 W x 3,200 L x 3 t, quality of material : SUS-318L, quantity : 15 pieces per units, 30 pieces in total for 2 units c. Repair specifications of machinery & instruments relating to power plant and other equipment

1. Steam turbine for power plant (spare parts & equipment) 3 units A. Specifications of turbine : - type : double automatic air extraction/ condensation method - capacity : 12,000 KW - number of rotation : 3,000 rpm B. Spare parts for sealing material (for 2 units) - For ground of governor side - For inter-ground of high, middle, low temperature sides - For ground of motor side - For close-off plate C. Spare parts for blade (for 3 units) - High pressure curtis stage (2 sets) - Shroud (2 sets) - coking piece, stripper pin (1 set) 2. Blade for cooling water tower (manufacturing & exchange) 1 unit Specifications of cooling tower : - Capacity : 3 x 3,350 m3/Hr (3 compartment) - Fan : absorption type - driving force : 55 KW x 4 P Procurement of spare parts : procurement o new fan (with boss), quality of material : 4 units corresponding to FRP , quantity : 4units of fan with 4 pieces of blade 3. High pressure water supply pre-heater (manufacturing & exchange) 3 units It is damaged due to corrosion and frictional wear. Manufacturing of tube bundle and its exchange are needed. Specifications of tube bundle : - Type : horizontal cylinder type, U-typed pipe - heating tube : 5/8” x 18 BWG x 3,450L x 65m 2, quality of material : maritime use (BFTF3) - stay rod, tube support, body, flange ( made of copper), A set of channel inside accessories are included. 4. Pure water equipment blower (procurement & exchange) 3 units Its operation is unavailable due to corrosion. Manufacturing of new anti-corrosive blower is needed. Specifications of equipment: Capacity : 42 NmVmin. x 60 mm Ag x 1.5 KW, quality o material: FRP 5. Warm water pump (renovation) The existing pump is poor in its capacity. Although design capacity is 5,000 m3/h x 16 (H) m x 300 KW, 25 m of capacity increase is required. By its renovation, increase of capacity up to 3,000 m3/Hr x 21 (H) m is achievable. Points of renovation: - The existing casing is re-used. - Increase of capacity is attainable by means of manufacturing new rotary body (main axis and fan caster). - As accessories, liner- ring and wear- ring are also manufactured.

— II — 69 — d. Repair specifications of instrumentation and analyzer

1. (715) CO & CO? analvsis meter (procurement & exchange) 2 sets 2. AE-AR-702-2 Sulfuric hvdrogen analvzer (procurement & installation) 2 sets gas extraction equipment, H2S detector 3. NH? gas record analvsis meter (procurement & installation) A. AIT-717-4 (instruction/transmitter) 2 sets Type : ER131, 1 P, NH3 graduations : 0-20 % B. AR-717-4 (record/receiver) 2 sets NH3 graduations : 0^20 % C. AIT-717-3 (instruction/transmitter) 2 sets ER131 1 P, NH3 graduations, : 0~10 % D. AR-717-3 (record/receiver) 2 sets, NH3 graduations : 0"-10 % 4. Smoke channel oxygen analyzer (procurement & installation) 1 set After extracting smoke channel gas from smoke channel by use of absorber and passing it through drain separator, oxygen analysis and measurement are made. 5. (717) Svnthesis gas H?/N? ratio measure (procurement & installation) Type: gas specific gravity measurement method - Non-anti-explosion type gas density measurement converter 2x2 sets - Anti-explosion type gas density measurement converter 2x2 sets - Flow volume set-up instrument 2 x2 sets - CDW cable, etc 2x2 sets - Pressure reduction valve for bombe 4x2 sets 6. (713) Procurement of new CO? analvzer 1 set 7. (402K1) Air compressor discharge volume record/ alarm device (procurement & installation) 3 sets A. FIT-402-4, output: 0.2"-1.0 kg/cm2 B. FRA-402-4, recorder, pressure switch 8. (402141) CO? flow volume record adjustment equipment for CO2 sent to urea svnthesis tower (procurement & installation) 3 sets A. FIT-402-2, output: 0.2~1.0 kg/cm2 B. FRA-402-2 recorder, adjuster, operation instrument pressure switch 9. (402H1) Urea svnthesis entrance pressure record adjustment equipment (procurement & Installation) 2 sets PCV-402-14, diaphragm adjustment valve (air operation), positioner for the above valve, 3 sides electromagnetic valve, pressure switch 0. JCV for pure water equipment (procurement & exchange) Type : butterfly valve, quality of material: cast iron (rubber lining) 45 sets, diaphragm valve 60 sets, manually-operated valve(material quality: cast iron + rubber lining) 66 sets 11. Procurement of PH meter lset 12. Silicon analvzer (procurement) lset e. Repair specifications of spare parts & machinery for electricity equipment

1. Compensator (equipment & exchange) 1 set Specifications : 1st voltage : 3.3 kw x 50 Hz 2nd voltage : 2.474-2.15- 1.815 kv x 50 Hz

2. Compensator (equipment & exchange) 1 set Specifications : 1st voltage : 3.3 kv x 50 Hz x 3 (p 2nd voltage : 19.5 kv x 50 Hz x 3 0 capacity : 6,500 KVA 3. Compensator (equipment & exchange) lset Specifications : 1st voltage : 3.3 kv x 50 Hz x 3 2nd voltage : 19.5 kv x 50 Hz x 3 0 capacity : 1,700 KVA Vacuum circuit breaker (equipment & exchange) 3 sets Specifications : electric current = 1,200 A x 3.6 kw capacity : 250 MVA x 50 Hz, with base 5. Vacuum circuit breaker (equipment & exchange) 1 set Specifications : electric current = 600 A x 3.6 Kv Capacity : 250 MVA x 50 Hz, with base 5. (716K1) Substitutable reactor for synthesis gas compressor (equipment & exchange) 1 set Specifications : 82 KVA x 87 A x3 , 3,500 kw x 3,300 V x 50 Hz 7. (716K2) Substitutable reactor for air compressor (equipment & exchange) 1 set 19.5 KVA x 21.6 A x 3 0,820 kw x 3,300 V x 50 Hz 8. Motor for ammonia refrigeration compressor: 1 set High- pressure motor (400 kw) is unworkable due to insulation trouble. Procurement and exchange of starter coil are required. Quantity of coil: Fitting to 12 units of machine is made by NGFF. ?. Motor for energy use (manufacture & exchange) 1 set Based on manufacturer’s opinion that fitting of exciter for this motor is unavailable at plant site, manufacture of new motor is needed. Specifications of motor: -capacity : 1,250 KVA x 3.5 KV x 50 Hz x 1,000 rpm -exciter : RHEO statistic automatic voltage adjuster -accessories : AVR single body (automatic voltage adjuster) -manufacture quantity : 1 unit f. Repair specifications of other off-site equipment

Construction machine & machinery plant equipment 1. Radical drill machine (Darts manufacture & eaumment) 1 unit Thanks to poor drill support, poor connection and vibration, repair is required. Since manufacturer stopped production of this typed machine, there is not any division of design, manufacture and services. Examination, such as analysis, inspection and sketch, by expert delegated to plant site is needed. 2. Tools for milling machine (procurement) 1 set endmill : 1 mm $ ~30 mm (1 mm pitch) with milling chuck, drill: 1 mm $ ~32 mm(l mm pitch), micrometer : outsside-50~75 mm, inside-50^75 mm 3. Folk-lift (procurement) 1 unit Specifications of machine : Type : diesel engine car (48 kw), capacity: 3 tons, double mist: 3 m, folk : standard type Pipe vendor (procurement) 1 unit pipe 70 OD x 40 ID processing is available. Type : reciprocating oil pressure cylinder (by motor type pump) stroke-350 mm, manually-operated exchange valve method, vendor diameter : 1.5 m x 1 set, 2.5 m x 1 set 5. Welding cutting machine (procurement) A. DC/ARC welding machine 2 sets Regular electric current 300 A, (input: V x Hz = 400 V x 50 Hz), welding cable 20 m with hand-holding torch B. AC/ARC welding machine 5 sets Regular electric current 300 A (input: VxHz = 400 V x 50 H z) welding cable 20 m with hand-holding torch C. TIG welding machine 1 set Regular electric current 300 A welding cable 8 m, gas regulator D. Plasma cutter (air compressor, without accessories) 1 set Regular current 70 A, cutting torch Cable 10 m

-11-72- g. Analyzer and other instruments for laboratory

(Note : Voltage of all electric instruments: 110V/220V, 50/60 Hz AC) 1. Weighing scale: A. digital scale (Max.200 gr.) 2 sets B. upper balance (Max.3,000 gr.) 1 set 2. pH meter (digital type) 1 set 3. Transmission meter (digital type) 1 set 4. Spectro-photometer (digital type) 1 set (Silica, steel, sulfide, hydrazine, ammonia, bullet, others) 5. Frame-photometer (for natural gas) lset 6. Gas chromatograph A. Gas chromatography (with TCD) 1 set (Process gas, For measurement of H2,N2,CO ,C02,CH4~C6 Hi4, etc) B. Gas chromatography (with FID) 1 set (Process gas, For measurement of CO, C02, methanol and others in condensed water at the level of ppm) 7. Karlfisher water drip measure (measurement for water in urea) 1 set 8. Jar tester (with 6 paddle mixer) 1 set (For measurement of optical medicine additive in flocklation) 9. Electric dry oven (by 350 °C) 1 set (Temperature adjuster is needed.) 10. Low temperature incubator 1 set (temperature range:-10 °C to 50 °C) 11. Vibrating sifter machine 1 set (with different size of sifters) 12. Muffle electric furnace (Max. temperature : 1,100 °C) 1 set (with temperature adjuster) 13. Coefficient of viscosity group (For moving coefficient of viscosity and red wood) 1 set each 14. Flash point tester (For lubricating oil) 1 set 15. Yellow sulfur analyzer 1 set (Measurement for H2S, COS and mercaptan in natural gas at the level of ppm) 16. Bombe calorie meter 1 set (For measurement of sulfuric compound) 17. De-ionization meter (For highly purified water) 1 set 18. Distilled water production equipment 1 set 19. Mixer (For crushed solid matter) 1 set 20. Electromagnetic mixer & hot plate 1 set 21. Vacuum pump 1 set 22. Portable air compressor 1 set

11-73- 2.5 Scope of Funds, Machinery & Equipment and Services to be Provided Mutually in the Project Implementation

For thee purpose of materializing the project for energy saving and environmental measures in NGFF Fertilizer Plant at the earliest convenience through its combination with COM, joint execution of necessary business was ascertained among BCIC, NGFF and our investigation team. Partial responsibility of each party was determined as follows.

(1) Scope of machinery & services to be provided on the side of Bangladesh

1) Working stage for materialization of thee project Bangladeshi parties are expected to take steps to ask for the Government ’s approval on project implementation and obtain its agreement. In respect of funds required for project implementation, the parties are anticipated to ask for Japanese Government for finance by means of combining the project with COM and take necessary steps to obtain such funds. Itemized descriptions areas follows.

0 Communication, negotiation and adjustment business with Bangladesh Government for project implementation as well as acquisition of the Government ’s approval.

(2) Acquisition of Bangladesh Government ’s approval for their approach to Japan in respect of finance required in the project.

(3) Provision of technical data on equipment and operation in NGFF Fertilizer Plant to cooperate with Japan in their preparation of technical data required for various application procedures in Bangladesh. 0 All procedures required in the companies, Bangladesh Government related agencies’ procedures and applications relating to the project @ A series of procedures and conclusion of loan agreement, relating to borrowing.

2) Execution stage for the project

0 Application and acquisition of approval for tax exemption or tax breaks of import duties and VAT relating to goods imported from overseas.

(2) Provision of cooperation and different kinds of services required for obtaining Bangladesh ’s visa or cooperate qualification needed in domestic activities in respect of project implementation. (3) Provision of technical documents of basic design data and the existing machinery & equipment. ® Procurements of machinery, materials and various works, and also those of machinery and materials manufactured domestically in Bangladesh in respect of project implementation.

(2) Scope of machinery & services to be provided on the side of Japan Japanese party (principal executor for this investigation) cooperates with Bangladesh in preparing technical data required for Bangladeshi parties’ obtaining their Government approval and providing such data with them. Also, Japanese party prepares technical data needed for Bangladesh ’s steps of financial application to Japanese Government and provides different kinds of support services required until determination of Japanese loan. With paying attention to development of international discussion on realization of CDM in the future, under the present situation that actual implementation method of CDM is still unclear, Japanese party is under preparation for providing Bangladesh successively with information acquired by Japanese side. Itemized descriptions are as follows.

1) Working stage for materialization of the project

Japanese party provides with the following services.

CD Communication, negotiation and adjustment business with Ministry of Industry BC1C and NGFF Fertilizer Plant in respect of project implementation.

(2 Communication and adjustment business with Japanese Government reiatec agencies in respect of this basic investigation and project implementation.

(3) Systematic support work in Bangladesh ’s structuring for raising funds fron Japan in respect of project implementation. © Cooperation in preparing technical data required for Bangladesh ’s various application procedures. (5) Provision of information acquired by Japanese side through international discussion on realization of CDM.

11 — 75 — 2) Execution stage for the project

Japanese party provides the following matters. (D Detail plan and detail design of machine & equipment to be planned, based on the project and Japanese technology.

(2) Design support for other machinery & materials relating to the project.

(3) Technical support for other machinery & materials to bee procured outside Bangladesh. © Technical guidance for certain period after completion of the project.

© Support for CO2 reduction volume monitoring.

2.6 Preconditions and Points at Issue in Project Implementation

(1) Funding

Both of BCIC and NGFF don ’t have capacities for bearing funds required for project implementation. It is, therefore, precondition that such funds are provided from Japan. In addition, BCIC and NGFF are desirous of receiving funds as grant. In case of soft loan except grant, it depends on financial conditions, such as interest rate and repayment period. The values for services provided by BCIC and NGFF in local works are to be counted as a part of principal builder ’s financial burden, if provision of funds on the side of principal builder is required. Also, adjustment on diversion of a part of ADP fund provided for NGFF ’s rehabilitation work Phase II to principal builder ’s financial burden is needed

(2) Effectuation of CDM and its procedures

As for the purpose of CDM agreed in COP3 held at Kyoto in 1997, its definite

implementation method was not consented in COP6 conference held at Hague, Netherlands in October 2000. Japanese Government decided, however, to contribute another one billion of fund to “Global Environment Facility”, consisting of 9 advanced countries, such as Japan and the United States. Necessary procedures for project

targeted in CDM and trade conditions for CO2 reduction volume after project implementation are to be immediately clarified. NGFF is in urgent need of

implementing rehabilitation for energy saving and CO2 reduction effect as well as prolong-ment of equipment’s life.

-11-76- (3) Bangladesh Government ’s attitude

Bangladesh Government ’s preparation of implementation organization in CDM project is urgently required. Despite Ministry of Environment and Forest ’s positive effort for CDM ’s effectuation through participating in CDM externally, there is not a complete understanding on the purpose of CDM and collective view in Bangladesh Government. Bangladesh has not reached, therefore, its final stage to ratify Kyoto protocol of COPS. According to Ministry of Environment & Forest, it is expected to organize task team in the Government immediately for ratification of protocol and establishment of organization, receiving CDM project. Based on our explanation with Ministry of Industry, business promoter, in respect of CDM ’s purpose, the Ministry deepened its understanding. Both of BCIC and NGFF promised us for taking necessary actions to obtain consents on project implementation in combination with CDM from relevant departments in the Government. Meanwhile, Japanese investigation team pledged themselves to cooperate fully with Bangladesh in provision of soft loan, such as Yen Credit, from Japan.

(4) Production cost and sales price of urea Bangladesh Government is required to solve NGFF ’s management in the red by reducing politically price of natural gas supplied to NGFF or adopting free price system for sales price of urea product. In thee case that NGFF is maintained politically under deficit management, introduction of suitable amount of fund is needed. Such deficiency is due to increase in fuel natural gas price and low price of urea product pegged by the Government for the past several years. Compared with international price, 6,000 Taka of urea production cost per ton in respect of 50 kg bagged product is not costly. If urea product is salable at import price, NGFF is able to gain sufficient income.

Depending on low cost aid fund from overseas in natural gas development, the Government was successful in lowering gas price politically. Thanks to shortage of electricity caused by increase of its demand, additional construction of power station and development of natural gas to be supplied to such power station become necessary. Reflecting the Government ’s introduction of foreign fund under product & sharing contract, natural gas price began to rise up to the level of international price. Since urea product price is of importance for lowering rice price, the Government decided 4,000 Taka of urea price per ton in respect of 50 kg bagged product as control price which has been kept for the past several years. With the above measure, rice price is stable in such low price as around 15~20 Taka (30—40Yen) per kg. NGFF ’s payment to gas supply company is in arrears due to accumulated deficiency, and gas supply company gives a warning of stopping gas supply, unless gas rates in arrears are settled.

11-77- (5) Operation guarantee for minimum 10 years

According to Bangladesh Government ’s policy, NGFF ’s operation is expected to continue for at least 10 years after completion of the project. Payback of investment

fund for the project and total CO2 reduction volume in 10 years are, therefore, attainable. With regard to economic calculation on investment fund for the project, its economic efficiency has been ascertained in each item of implementation, such as process improvement and rehabilitation, on the assumption that the project’s life comes up to 15 years.

(6 ) Technical problem

From technical viewpoint, there is not any particular question. Close attention and security are required to maintain usual operation during the period of local works. To minimize opportunity loss, such device as adjusting the process of connecting work for process improved parts in parallel with other works in short term is needed.

2.7 The Project’s Implementation Schedule

Details of business and schedule until materialization of the project (See Figure 11—12)

The project’s implementation is projected in 3 phases.

1) 1st Phase: Until adoption of the project 0 Procedures required mutually in the offices for the project’s materialization and preparation of basic memorandum. ® Negotiation and conclusion of the above basic memorandum. (3) Preparation of basic plan for CDM project.

® Application for the project to Bangladesh Government related agencies. (5) Application for finance ,such as ODA Environment Special Yen Credit, to Japan. © Technical support relating to the above application.

© Communication, negotiation and adjustment business with Bangladesh Government (Ministry of Industry and Ministry of Environment & Forest, etc) in respect of the project. ® Communication and adjustment business with Japanese Government related agencies.

11-78- (9) Application for tax exemption or tax breaks of import duties and VAT in Bangladesh.

2) 2nd Phase: Until completion of commissioning after adoption of the project ’s implementation The period of 16 months is required until completion of commissioning after adoption of the project’s implementation.

(D Conclusion of loan agreement.

(2) Conclusion of construction contract. (3) Detail plan and design for machinery & materials.

@ Procurement business for machinery & materials. © Loading & transport business (marine transport, custom clearance in Bangladesh, domestic ). © Construction works at plant site(concrete foundation work, machinery installation work, spare parts exchange work and repair & inspection). © Construction commissioning. ® Guidance on maintenance & inspection method for machinery & equipment.

3) 3 rd Phase: After completion of construction commissioning in the project

© Monitoring and evaluation on CO2 reduction volume. © Monitoring and evaluation on energy saving volume.

® Implementation of environmental assessment.

Based on the above businesses, the whole schedule in the project ’s implementation is shown in Figure 11—12.

Since definite implementation method of CDM for greenhouse gas reduction is not agreed internationally and the policies of both of Japanese and Bangladesh Governments are not yet decided, it is not good timing at present to set up implementation schedule, based on calendar year. Particularly, conditions, timing, and period required for lender ’s review and examination on the project ’s F/S are not clarified at all. On the condition that 14 months are needed for the period from commencement of procedures in the offices through effectuation of the project ’s construction contract, the process for the period until commissioning completion after effectuation of the project’s construction contract is drawn up accordingly.

Until completion of renovation work, 16 months from effectuation of contract and commencement of design work and 9 months from commencement of local works, such as inspection on the existing machinery & equipment, exchange of spare parts and preparation & repair, to completion of new process machinery installation are required, respectively. In respect of training, teaching on maintenance & inspection method for machinery & equipment is made at plant site under guidance of instructors to be delegated from Japan.

Monitoring and evaluation for CO2 reduction volume and energy reduction volume as well as implementation method of environmental assessment are clarified at the stage of final conclusion of international agreement. This project is promoted in accordance with agreed method and 2 months are required for the project’s completion after finishing of local works.

-11-80 32 31 30 29 28 27 ..... rare 26 25 24 project.

this 23

for

22 21 executor

20 | 19 principal

18 is of

month

17 KSL

16 schedule f

Effectuation

1 15 Conclusion of Necessary 7 \

14 Meanwhile, the

s

of Cn

13

, Am, \ 12 project Adoption 11 organization. 7

\ implementation

10 s ’ upper

9 its

8 project

7 Industry,

of

6 The 5

Ministry m

4 m and 11-12

m

3 m 2 BCIC

of

1 Figure

of /

work

inclusive

is KSL the Japan

Japan

NGFF NGFF NGFF NGFF NGFF NGFF NGFF Partial (Japan) of Bangladesh

KSL/NGFF Japan/NGFF Japan/NGFF KSL/NGFF KSL/NGFF Japan/NGFF and KSL/NGFF Japan/NGFF Japan/NGFF responsibilit Gavament

y

&

&

& plant

2

tax

above the

ODA,

repair C0 energy of

basic (marine (Ministry

in

as the work.

joint

custom

eouioment of contract on on business

and

to

to machinery

Bangladesh foundation Fertilizer

related

& for machinery

such in

Government for

basic of

business required adjustment

plan

agreement exemption works environmental project of

relating transport,

installation Item

Government duties

of evaluation evaluation and

conclusion

design project adjustment tax

the finance,

loan construction basic

machinery

maintenance Japanese Fenchuganj commissioning

business

Government for and Communication and for for and of of of and and

transport

mutually

on

for support volume import (marine

&

with

Preparation volume

means plan

machinery construction of

Bangladesh

Japan

Implementation inspection Monitoring reduction Monitoring saving assessment Local Guidance Procurement work, Construction materials Loading Detail materials transport Conclusion Application Conclusion business breaks

Communication application. NGFF with implementation Bangladesh Application negotiation Application to Technical Procedures Preparation offices. Negotiation memorandum

3 Phase 2 Phase 1 Phase Phase (Note)

11-81 3. Materialization of Financial Plan

3.1 Financial Plan for the Project’s Implementation (Amount of Necessary Fund, Fund Raising Method, etc.)

(1) Amount of necessary fund

The fund required in thee project amounts to approximately 2 billion Yen (19 mullion US $ ). Detail a and preconditions are indicated below.

The results of summarizing capital expenditures in this renovation project are shown in Table II —15. In this summary, the following matters are taken into account.

(D In view of situation that NGFF is a government body and this project is materialized on the basis of aid fund from overseas, exemption of import duties for materials imported from overseas appears available and they are not posted in our estimation. ® The following exchange rate is adopted.

1 US$= llOYen =54 Taka

(3) Since delegation of consultants from Japan is strongly desired by our customer, expenses for delegation of consultants are posted. ® Expenses for domestic transport, domestic engineering and installation are estimated, by targeting NGFF and local companies. © As necessary fund for the project, addition of interest payable for construction period in accordance with borrowing condition is needed. Also, expenses before startup of operation and working capital at the beginning of operation startup are required in usual project. As the project aims at renovating the existing plant, raw materials, fuel and utilities are not posted particularly, assuming that they are prepared sufficiently for daily operation.

11-82- Table 11—15 Summarized budget unit yen Marine & domestic No. Section Amount Packing FOB cost Installation Total transport cost

1 Ammonia section 693,460,170 20,803,805 3,467,301 70,732,937 138,692,034 927,156,247

2 Urea 106,537,700 3,196,131 532,689 10,866,845 21,307,540 142,440,905 3 Power plant 169,304,150 5,079,125 846,521 17,269,023 33,860,830 226,359,649 4 Demi-section 22,155,000 664,650 110,775 2,259,810 4,431,000 29,621,235

5 Water preparation 16,569,000 497,070 82,845 1,690,038 3,313,800 22,152,753

6 Repair shop 54,248,280 1,627,448 271,241 5,533,325 10,849,656 72,529,950

7 Repair shop 95,025,000 2,850,750 475,125 9,692,550 19,005,000 127,048,425

8 Electricity equipment 123,690,000 3,710,700 618,450 12,616,380 24,738,000 165,373,530

9 Heavy machine 2,625,000 78,750 13,125 267,750 525,000 3,509,625

10 Laboratory 26,513,550 795,407 132,568 2,704,382 5,302,710 35,448,616 11 Local engineering 50,000,000 0 0 0 0 1950,000,000

12 Consultant 300,000,000 0 0 0 0 300,000,000

1,660,127,850 39,303,836 6,550,639 133,633,041 262,025,570 2,101,640,935 us$ 19105827

(2) Method of fund raising Since Bangladesh has not internal reserves for the project’s construction fund particularly, the total amount of required fund is raised through BCIC’ s head office. BCIC’ s head office is desirous of raising fund on most favorable conditions in volume and borrowing cost. While BCIC has to rely aid fund from borrowing from overseas for foreign fund, borrowing from the Government (Ministry of Finance) is available for domestic fund portion.

3.2 Prospect for Fund Raising

(1) Possibility of fund raising As the result of discussion with BCIC and JBIC, thee following 3 cases are considered at present.

(D Yen Credit to be provided by Japan (2) Gratuitous fund for remedy of financial obligation (3) Fund on the former EXIM base

-11-83- According to opinions of persons concerned in JBIG and others, ® and (2) are appear to be most practical, and details are mentioned below.

CD Yen Credit to be provided from Japan

With regard to loan commitment, made by Prime Minister Mori last year, including Lupsha bridge construction project in the amount of 80 million US$, Haripur rural district infrastructure development project in the amount of 40 million US$, Kaputa hydraulic power plant expansion project in the amount of 20 million US$ and Rural District Electrification Bureau’s 13 billion US$ project, relevant loan agreements are in progress. Although Bangladesh is not treated as annual recipient country, there is a possibility of receiving aid fund from Japan once in every 2 or 3 years.

The financial conditions of these loans were as follows. Interest : 1 %, Grace period : 7 years, Repayment period : 25 years,

In case of Special Yen Credit and Environment Yen Credit to be provided specially as Yen Credit, such favorable conditions as Interest: 1%, Grace period: 10 years. Repayment period: 40 years, are applied. Since application of such favorable conditions for this project is not foreseeable, calculation on returns in this investigation is made on the basis of common Yen Credit

® Gratuitous fund for remedy of financial obligations

As such gratuitous fund is now on hand in Bangladesh, it seems to be suitable for this type of small size project, in which machinery & equipment account for project’s major element. The parties are required to do their best, since there is an order of priority in Bangladesh. According to Bangladesh Government ’s document delivered to relevant agencies (Public Corporation, etc), the borrowing conditions are as follows.

A borrowing institution is needed to deposit cash, equivalent to 25 % of loan, and the remaining 75 % is loaned at 0.25 % of interest rate.

(3) JBIG fund (the former EXIM fund)

In 2 types of credit, such as suppliers credit and buyers credit, the followings are usual conditions.

-11-84- Down payment : 5 %, Repayment period : 7^10 years (Max.) on deferred payment method.

Interest : Yen denominated loan-CIRR (1.9 %) + premium, Dollar denominated loan-CIRR (6.2 %) + premium

Since solution of question how to arrange down payment portion as well as bank guarantee required for borrowing is needed in this fund, its utilization seems to be difficult.

(2) BCIC’s attitude BCIC’ s responsible person expressed the following opinion at the time when JBIG’ intention was reported by us.

He had a strong interest in this project and, in consideration of the following matters, intended to ask Japanese Government for provision of Yen Credit by advancing order of priority in Bangladesh immediately after completion of this report.

- This report would be in line with CDM’s purpose and also acceptable to NEDO. - Credit line set forth in loan would remain within 2 billion Yen.

Meanwhile, gratuitous fund, another choice, would be studied as domestic matter in Bangladesh.

(3) Principal executor’s (Kobe Steel, Ltd.) attitude In the case that details of CDM’ s rule is determined and value assessment becomes available after ratification of international agreement, Kobe Steel, Ltd is able to materialize its plan for making investment of fund and technology and bearing expenses on the basis of CDM scheme as a principal executor. Under the present circumstances, it is, however, impossible.

11-85- 4. Matters Relating to Joint Implementation Conditions

4.1 Adjustment Matters with the Targeted Country for Materialization of CDM, Including Provision of the Project’s Implementation Conditions and Share of Business Responsibility in View of Actual Situation in the Project’s Execution Sight.

As conclusion of Chapter 2-6 “Preconditions and points at issue” is considered as precondition for implementation of CDM and adjustment is needed in parallel with development of international agreement on CDM, including establishment of monitoring system, provision of relevant information is required at all times. The indication of conditions from the counterpart country has not been made.

Although Ministry of Environment & Forest and NGFF Fertilizer Plant at execution site are extremely positive for environmental measures through the project’s implementation and energy efficiency improvement, the following main points are to be clarified as execution conditions.

® In respect of CDM implementation, Japanese Government ’s direct official contact in the future as well as establishment of definite approach and agreement on CO] sharing (2) Establishment of liaison office in Bangladesh Government in connection with CDM project (either in Ministry of Industry or in Ministry of Environment & Forest)

(3) Availability of soft loan provision from Japan to promote joint implementation project

® Adjustment matters with counterpart country for materialization of CDM, including business sharing.

4.2 Possibility of the Targeted Countries Consent on the Project’ s Joint Implementation (Requirements for Obtaining the Targeted Countries Consent, Based on the Approach of the Targeted Country’ s Government Related Agencies and NGFF Fertilizer Plant)

In this CDM project, requirements made by Bangladesh Government and NGFF Fertilizer Plant are included at the maximum. By minimizing operation stoppage period attributable to execution of works and by concentrating on investment with economic effect, total investment amount is controlled to the utmost. Bangladesh Government and NGFF Fertilizer Plant have strong intention of materializing this project.

-11-86 Bangladesh and the targeted company have not proper understanding on CDM, while Ministry of Environment & Forest understands it rightly. As realization of this CDM project is a very attractive step for country and companies, which don ’t have money enough to make investment for modernization, they have strong intention to materialize this project without fail. CHAPTER 3

PROJECT EFFECT CHAPTER 3 PROJECT EFFECT

1. Energy Saving Effect

1.1 Technical Ground for Positive Energy Conservation Effects

(1) Energy saving effect due to improvement of operation rate

With a lapse of 40 years after start-up, NGFF has often to stop its operation due to different kinds of troubles caused mainly by super-annuation in various places of equipment. The present operation rate (on 1999 / 2000 year base) has come, therefore, down to about 78%, while energy basic unit of urea product has increased by around 16%. Even if breakdown of a part of machinery result in such situation that shutdown of plant is needed, NGFF continues usually a partial operation of equipment, such as reforming furnace. In case of a large size heat engine, such as reforming furnace, being stopped once, it entails plenty of time for restart of operation and a large quantity of thermal loss in the process of cooling and re-heating. Such being the case, it is difficult to stop supplies of fuel for warm air operation, process steam and process natural gas, and they are successively emitted into the atmosphere with generation of excessive energy loss. Thanks to difficulty in following immediately load change of electricity and steam on the process side at the time of stoppage in emergency, restart of power generation equipment, or during operation for reducing production volume and shutdown, excessive energy is generated and removed, while natural gas being burned. Provided that stoppage gains in its number and stoppage time becomes longer, production volume decreases and energy loss increases accordingly. Sometimes, much time is required in each repair, even if stoppage decreases in its number. For example, much time is needed for repair, in case of operation being stopped due to occurrence of relatively large size trouble. Although operation rate, or production volume, decreases considerably in such condition, energy loss, or increase of energy basic unit, is relatively small in its quantity. Since energy loss occurs mainly at the time of shutdown, restart or operation of warming machine under repair, such loss is comparatively small, because of warning machine operation being stopped in the case of long-term shutdown, as far as operation is not stopped so often.

NGFF suffers, however, from production volume reduction and energy loss due to repeated shutdown caused by different kind of troubles in super-anuated machinery & equipment and repeated conditions that several hours or days are required for repair during continuation of warming machine operation.

— Ill— 1 — With recovery of function by means of inspecting the whole equipment and making adequate preparation & examination through implementation of this project, long-term and successive operation is attainable. In respect of energy saving effect obtainable by operation rate improvement, energy basic unit is expected to decrease by 14.3% (285 Nm3/ MT) from 1,820 Nm3/MT of actual value in 1999/2000 to 1,525 Nm3/MT.

A graphic chart for relation between operation rate % (production record/ equipment capacity) and natural gas basic unit (annual average Nm3) for 15 years from 1985/1986 ^ 1999/2000 is shown in Diagram III-1. When operation rate comes up to 100%, natural gas basic unit of urea decreases to 1,535 Nm3/MT, as indicated in the graph. (See asterisk)

♦ 2 85

1400 1500 1600 1700 1800 1900 Natural gas basic unit Nm3/MT

Figure III-1: Relation between operation rate and urea natural gas basic unit

(2) Energy saving effect due to process improvement in Ammonia Plant

1) Synthesis gas refinery process improvement (Plan A)

Energy saving is achievable through the following steps. As energy consumption volume is extremely large in the existing synthesis gas reforming equipment, in

which CO and CO2, poison for catalyst, is removed by means of washing synthesis gas with lean solution, installation of new synthesis gas refinery equipment, consisting of low temperature CO converter and methanator, is scheduled.. In

addition, in the process of CO2 removal, catalyst is added to thermal carbonic acid potassium solution. Through this process improvement, natural gas basic unit in urea product decreases by 54 Nm3 per ton, and technical ground for production of energy saving is as follows.

(D As cooling of lean solution down to 0°C in ammonia refrigerator is needed for increasing absorption efficiency, energy for refrigerator is usually required. Since such process becomes unnecessary in improved process, energy for refrigerator is not required.

(2) Since , in comparison of moving power of absorbed liquid cycling pumps, absorption capacity for CO in lean solution is relatively low, compared with

absorption capacity for CO2 in thermal carbonic acid potassium solution, and liquid cycling volume is comparatively large, a larger moving power of pump is needed. Strictly speaking, 7 times larger moving power is required, as 140 kg/cm2 in operation pressure is extremely high, compared with 20 kg/cm2 in

absorption & removal process of CO2 contained in thermal carbonic acid potassium solution.

(3) At present, rich gas, absorbed and removed by lean solution, is used as fuel. In improved process, 2.0% of CO remained in process gas is reduced to the level

of 0.12% by low temperature CO conversion reaction (CO + H2O = CO2 + H2)

and it generates additionally H2, usable as raw material for ammonia. Necessary volume of process natural gas, equivalent to hydrogen generated in this stage, becomes reducible and necessary volume of process steam and thermal load in 1st reforming furnace decrease proportionately. Although necessary volume of natural gas increases due to lack of CO rich gas, usually used as fuel, overall effect attributable to energy volume reduction becomes comparatively larger.

© Since steam required for regeneration of lean solution becomes unnecessary and catalyst is added to thermal carbonic acid potassium solution, reduction of steam needed for regeneration of solution is achievable.

2) Collection of hydrogen from synthesis purge gas (Plan B) As synthesis gas, which is used as fuel for 1 st reforming furnace after being reduced in its process, contains a large quantity of hydrogen, such hydrogen is collectable through installation of hydrogen separator with diffusion film method. Hydrogen collected in this stage is returned to absorption side of synthesis gas compressor 2nd stage and recycled. Necessary volume of process natural gas, equivalent to

-III-3- collected hydrogen, becomes reducible, and necessary volume of process steam and thermal load in 1st reforming furnace decrease proportionately. Although necessary volume of natural gas increases due to lack of CO rich gas, usually used as fuel, overall effect attributable to energy volume reduction becomes comparatively larger. With collection of hydrogen from synthesis purge gas, natural gas basic unit in urea product decreases by 19 Nm3 per ton.

1.2 Baseline for Energy Saving Effect Calculation Base

The values in NGFF’s operation result data for one year from July, 1999 to June, 2000 are used as baseline for energy saving calculation base.

(1) The idea of adopting one year operation result data as baseline (D Although production volume and energy consumption volume are kept nearly at the level of the value originally established during NGFF Fertilizer Plant ’ s operation, reduction of operation rate and increase of energy basic unit in recent years are caused by frequent stoppages attributable to equipment troubles and mainly due to production decrease during the period of startup, shutdown and repair as well as useless burning of fuel. Although at least 1 week or 10 days are required as shutdown period for repair, it is hard to say that mean values in short term, for example 1 month, reflect actual condition in determining numeral values for ground of baseline. Such being the case, mean value of data, which is not affected by short- term operation stoppage due to trouble and measured in relatively long-term period, should be established as a standard.

(2) In parallel with progress of super-annuation in NGFF Fertilizer Plant, reduction of operation rate and increase of energy basic unit make their rapid progress year by year. Such trend of changes in past years is, therefore, not reflected exactly, if relatively long-term operation data is adopted.

For reason of the above conditions, adoption of data for 1 year operation result is appropriate. 2

(2) The idea of adopting data in 1999/2000 CD Sometimes exceptional trouble, in which 1 month or longer term period exceeding 1 month is required for its repair, occurs. As production volume and energy consumption volume are kept nearly at the values originally established during NGFF Fertilizer Plant ‘s regular operation, production rate is considerably deteriorated by such trouble, but influence to basic unit is relatively small. In the graph (Diagram III-1) indicating relation between operation rate and energy basic unit, there is a scatter, reflecting the above situation. Since no long-term and successive shutdown attributable to unexpected trouble occurred in 1999/2000, adoption of data for that year is decided, as it seems to reflect actual condition.

(2) With reduction of operation rate and increase of energy basic unit advancing annually in parallel with progress of super-annuation in NGFF Fertilizer Plant, results of 1999/2000 year have become worst in the past 10 years. Judging from the data up to now, results of 2000/2001 is estimated to become much worse than those of the previous year and such trend is expected to continue in the future, too.

Based on such situation, it is appropriate to adopt data for 1999/2000.

(3) The idea of adjusting the period, such as July, 1999 ~ June, 2000, to fiscal year in Bangladesh With introduction of maintenance fund into super-annuated plant, adequate improvements of its operation rate and energy basic unit are attainable. In NGFF, a maximum maintenance is continued within the limit of its budget allocated in each fiscal year. It is suitable, therefore, to set up baseline, based on operation results in the period corresponding to such allocated fund.

(4) Actual figures in operation results of 1999/2000, obtained from NGFF Fertilizer Plant and established as baseline, are as follows. -Ammonia production volume : : 56,623 MT/Y

-Ammonia as raw material for ammonia sulfate : (D :2,112MT/Y

-For process and refrigeration :® : 532 MT/Y -For outdoor sale of liquid ammonia :© : 212MT/Y

-Ammonia as raw material for urea :© : 53,765 MT/Y

-Natural gas consumption volume in ammonia equipment :© : 57,8655,000 Nm3/Y

-Electricity consumption volume in ammonia equipment :© : 72,805,000 KWH

-Basic unit of natural gas for power generation :® : 0.577 Nm3/KWH

-Natural gas consumption volume in the whole fertilizer plant :® : 158,423,000 Nm3/Y

-Urea production volume :® : 84,275 MT/Y

—III—5 — In NGFF Fertilizer Plant, around 5% of ammonia intermediate product for ASP raw material & makeup of cooled catalyst in refrigerator and a minimum quantity of liquid ammonia are used for outdoor sales, respectively. Under the circumstances, some revisions are needed for determining figures as baseline of energy basic unit.

As revision method, the volume of natural gas ©, required for production of ammonia, excluding ammonia used for raw material of urea, is calculated at first and, after then, net natural gas consumption volume in urea production © is found by deducting © from consumption volume of all natural gas in the Fertilizer Plant. Finally, natural gas basic unit in urea ® is obtainable by means of dividing © by urea production volume. The above calculation for revision is summarized and shown below.

Total of ammonia, excluding ammonia used for raw material of urea: ©=®+®+®:2,858 MT/Y

Ammonia electricity basic unit HD/(D: 1,286 KWH/MT

Ammonia electricity basic unit (natural gas conversion) :742 Nm /MT

Ammonia natural gas basic unit : 1,022 NnT/MT Total ammonia natural gas basic unit 1,764 Nm7MT

Consumption volume of ammonia, excluding ammonia for raw material of urea : 5,042 Nm3/Y

Natural gas required for urea production ©=©-©: 1533,381,000 Nrtr’/Y

Natural gas basic unit in urea 1,820 Nm3/MT

Steam used in fertilizer plant is divided into 2 kinds of steam, such as steam generated in plant and steam supplied from power generation plant. All quantity of natural gas supplied to NGFF Fertilizer Plant(including natural gas for power generation) becomes energy source and is included in (9). Since steam supplied from power generation plant is included in basic unit of natural gas for power generation® required for calculation of ammonia basic unit, it is unnecessary to consider energy for steam separately.

Consequently, baseline (the idea of estimating energy consumption volume, in case of the project being not executed), required as ground for energy saving effect calculation, is fixed by values calculated from NGFF Fertilizer Plant ’s operation results data and shown below.

—Ill — 6 Urea natural gas basic unit : 1,820 Nm3/MT@

Product urea production volume : 84,275 MT/Y©

The composition of natural gas for calculation of energy saving effect is as follows.

CO2: 1.0%, CH4: 97.0%, C2H6:2.0%,Total: 100.0%

Heat generation volume of natural gas value calculated from the above gas composition:8,612 Kcal/Nm3 ©

1.3 Actual Volume, Period of Pro and Accumulated Volume of Energy Saving Effect

(1) Actual volume of energy saving effect With operation rate increasing from 78% of present level up to 100% through implementation of NGFF renovation work, 84,275 M/T of urea production rises up to 108,265 MT/Y© of equipment capacity and natural gas basic unit in urea product decreases by 285 Nm3/ MT from 1,820 Nm3/MT of present level to 1,535 Nm3 /MT of originally projected value, as mentioned in paragraghl.l.(l) of this chapter “ Energy saving effect due to improvement of operation rate”. 108,265 M/T of equipment capacity © is the figure obtained on the condition that 320days are counted as operation days in a year under production capacity of 111 LT/D in each line of 3 in total.

As mentioned in the preceding paragraph (2) “ Energy saving effect due to process improvement in Ammonia Plant ”, natural gas basic units decrease by 54Nm3/MT and 19 Nm3/MT respectively, through implementation of Plan A and Plan B for process improvement, and 73 Nm3/MT is reducible in total. Consequently, total 358 Nm3 /MT (=285+73) of reduction is achievable as a whole. Natural gas basic unit in urea product, including energy saving effect, comes up, therefore, to 1,462 Nm3/MT (=1,820 - 358).

Estimated energy saving effect with implementation of NGFF renovation project is as follows.

1) Urea production volume & energy consumption volume (standard value) at present.

Annual urea fertilizer production volume : © 84,275 MT/Y

-III-7- Annual natural gas consumption volume : @84,275 x @1,820=153,380,000 Nm3/Y

Heat volume conversion: 153.380.000 x ©8,612= 1,320.9 G Kcal (5,526,700 GJ/Y)

Crude oil conversion: 1.320.900.000. 000 4-10,000 = 132,090,000 kg/ Y (132,090toe/Y)

2) Energy saving after renovation work

Production increase effect(annual base): ®=84,275 MT/Y

Annual natural gas consumption volume: @84,275 MT/Yx 1,462= 123,210,050 /Y

Heat volume conversion: 123,210,050 x © 8,612 = 1,061.1 G Kcal / Y(4,439,600 GJ/Y)

Crude oil conversion: 1.061.1100.000. 000 -r-10,000 = 1,061,110,000 kg( 106,110 toee/)

Energy saving effect (annual natural gas conversion): 123.210.000 - 153,380,000 = A30,170,000 Nm3 /Y(up)

Energy saving effect (heat volume conversion): 1,061.1 = 1,320.9 = A259.8 G K cal/Y(l,078.00 GJ /Y) Energy saving effect (crude oil conversion): 106.110 - 132,090 = A25,980 toe /Y

The above calculation results are shown in Table III-1

Table III-l: Table on the total of energy consumption volume, energy saving effect and greenhouse effect gas:

Energy consumption volume Annual urea heat volume crude oil production natural gas conversion conversion T/Y lO^NmVY G Kcal/Y toe/Y Present standard value 84, 275 153, 380 1,320.9 132, 090

In case production After completion of work 84,275 123,210 1,061. 1 106, 110 increase is not considered Effect (difference) 0 ▲ 30, 170 ▲ 259. 8 ▲ 25, 980

III—8 — Although 23,990 MT of annual urea production increase effect is achievable as a result of around 28% increase in production volume through NGFF renovation work, additional energy consumption volume, required for production increase portion, exceeds slightly credit obtainable from energy saving effect, and rises by 4,903,000 Nm3 annually, compared with present consumption level.

(2) Energy saving production period NGFF’s fertilizer production equipment is such equipment as super-annuated considerably in nearly 40 years after start-up of operation. BCIC is desirous of continuing NGFF’s operation with at least 10 years of prolongment in its equipment life. Our proposal of this time takes results of examination into account to meet BCIC ’s requirements. So at least 10 years of energy saving effect production period after completion of renovation work is, therefore, estimated.

(3) Accumulated volume of energy saving effect In 10 years of energy saving effect production period after completion of renovation work, it is possible to maintain present energy saving with establishment of system, in which adequate spare parts are supplied without delay. As mentioned below, accumulated energy saving volume in 10 years is expected to become 10 times as much as present annual energy saving production volume.

Energy saving effect (natural gas): 49,030,00 Nm3/10 years (up)

Energy saving effect (heat volume conversion): 422 G Kcal/10 years (1,765,000 GJ/ ©years) (up)

Energy saving effect (crude oil conversion): 42,200 toe/ 10 years (up)

1.4 Actual Method for Ascertaining Energy Saving Effect

It is possible to ascertain energy saving effect only by comparing measured value of flow volume of all natural gas supplied to fertilizer plant and baseline numerical value of urea production. In the case that ammonia is extracted for ammonia sulfate production or outdoor sales of liquid ammonia according to the circumstances, such revision as mentioned in paragraph 1.2.of this chapter “Baseline for energy saving effect calculation base” is required. Energy saving effect is, therefore, ascertained with acquisition of operation data, including operation date needed for such revision, through the following method.

Ill-9 (1) Timing & period: By targeting 3 periods, such as 3 successive days, 2 months and 1 year, accumulated volume in each period is measured.

(2) Measurement method: Record keeping is made as operation record (daily report, monthly report and annual report) by applying measurement place and numerical value, usually executed by NGFF.

(3) Measurement item: With simultaneous acquisition of data required for revision, including temperature, pressure and others relating to each measure, the following items are measured and necessary revisions are made.

a. Flow volume measurement

- Receiving volume of natural gas in NGFF, natural gas use volume in ammonia plant (process & refining furnace fuel) and natural gas use volume in power generation plant

- Ammonia ‘s urea makeup volume - Urea production volume - Supply volume of steam turbine evaporated steam - Supply volume of steam supplied to fertilizer plant, except steam for ammonia sulfate plant

b. Electricity volume measurement - Total electricity generation volume in power generation plant - Electricity use volume in electricity generation equipment

- Volume of electricity transmission to fertilizer plant, except ammonia sulfate plant

- Operation time in ammonia plant (record of operation stoppage and its reason)

- Operation time in urea plant (record of operation stoppage and its reason)

c. Analysis of natural gas

Analysis of natural gas composition is made more than one time in a day. Mean value in one analysis made on 3 samples is determined as value of that day. Gas composition in long-term period, exceeding one day, is found from weighted average of daily natural gas use volume and gas analysis value in that day. Natural gas heat volume is obtainable from calculation of gas analysis value. Since a part

III-10- of ammonia intermediate product is extracted for other uses in the Fertilizer Plant, treatment of such intermediate product is made carefully during the period of energy saving effect ascertainment, and energy saving effect volume is ascertained by making revision of measured values through the method mentioned in the above paragraph 1.2.of this chapter.

2 Effect due to Greenhouse Effect Gas Reduction

2.1 Technical Base for Production Effect Due to Greenhouse Effect Gas Reduction

Except CO2 produced by natural gas burning, there is not any other product of greenhouse effect gas in this project. Technical base for production of effect due to greenhouse effect gas reduction is the same to paragraph 1.1. of this chapter “Technical base for production of energy saving effect “. The reason is as follows.

Although only natural gas is supplied to NGFF Fertilizer Plant as energy source, all necessary energy is covered by necessary electricity and steam generated by means of burning heat of natural gas sent to this Plant. Meanwhile, natural gas used in ammonia plant is divided into process gas (PNG) for raw material of ammonia & urea and fuel gas (FNG) required in reforming furnace. Carbon atom, contained in natural gas used in the process, is collected in the state of CO2 as raw material for urea synthesis and all quantity of such CO2 is fixed inside urea molecular. A small quantity of CO2, generated from natural gas used as fuel, is collected for covering shortage of CO2 coming from Ammonia Plant and also used for urea synthesis. The remaining portion of CO2 is diffused into the atmosphere.

With regard to volume of CO2 emitted as greenhouse effect gas from the Fertilizer Plant, the remaining portion after deducting volume of CO2 fixed by urea from volume of CO2, obtained by burning of all carbon atom contained in natural gas supplied to the Plant, is emitted in the air.

2.2 Baseline for Greenhouse Effect Gas Reduction Effect Calculation Base

As mentioned in the above paragraph 2.1, data required for calculation of greenhouse effect gas reduction effect is the same to data needed for calculation of energy saving effect. It is, therefore, the same to data for baseline mentioned in paragraph 1.2. of this chapter “Baseline for energy saving effect calculation ” as the idea of estimating energy consumption volume , in case of the project being not implemented and it is also indicated below.

-Ill-11 Urea natural gas basic unit 1,820 NnrVMT ©

Product urea production volume 84,275 MT/Y ©

Composition of natural gas required for calculation of energy saving effect is as follows.

CO2: 1.0%, CH4: 97.0%, C2H6 : 2.0%, Total: 100% Heat generation volume of natural gas : 8, 612Kcal/Nm 3 @

2.3 Actual Volume, Period of Production and Accumulated Volume of Greenhouse EffectGas Reduction Effect

(1) Actual volume of greenhouse effect gas reduction effect

In this report, composition of natural gas supplied to NGFF is as follows.

CO2:1.0%, CH4: 97.0%, C2He:2.0%, Total: 100.0%

Greenhouse effect gas is produced by air diffusion of CO2 generated through burning of hydrocarbon in natural gas. As a result of burning methane and ethane, 1 mole and 2

moles of CO2 are produced through the following reaction formula, respectively.

CH4 +202 = CO2 + 2HzO C2H6 + 3.500% = 2CO2 + 3H2O

Since 1% of CO2 is contained in natural gas, 1.02 mole {=(0.97 x 1) + (0.02x2) + (0.01)} is finally produced by burning 1 mole of natural gas. Greenhouse effect gas generated in NGFF Fertilizer Plant is produced only by the above 2 kinds of burning reaction. Actual volume of greenhouse effect gas reduction effect is obtainable by calculation made through the following method.

On the precondition that actual volume of greenhouse effect gas reduction effect is

equivalent to the volume obtained by deducting volume of CO2, fixed to urea due to

production increase effect, from volume of greenhouse effect gas (CO2), generated at the time of burning the reduced volume of natural gas due to energy saving effect, such actual volume is calculable. As volume of natural gas required for production increase exceeds volume of natural gas reduced through energy saving, 4,903,000 Nm3 /Y increases inversely, as shown in Table III-1. It is 4,220 Toe/Y increase on crude oil

conversion basis. Accordingly, production volume of greenhouse effect gas CO2 increases seemingly by 9,824 M/Y(= 1.02 x 44 x 4,903,000/22.4/1,000). With annual increase of 23,990 MT/Y of urea production volume due to production increase effect,

volume of CO2 fixed to increased portion of urea comes up to 17,592 MT/Y (=23,990 x 44/60). Such being the case, annual reduction volume of greenhouse effect gas amounts to -7,768 MT/Y (= 9,824 MT/Y - 17,592 MT/Y) and 7,768 MT/Y of reduction is attainable.

(2) Production period of greenhouse effect gas reduction effect

NGFF’ s fertilizer production equipment is such equipment as super-annuated considerably in the past nearly 40 years after start up of operation. BCIC is desirous of continuing NGFF’s operation with at least 10 years of prolongment in its equipment life. Our proposal of this time for renovation takes results of examination into account to meet BCIC’s requirements. In 10 years of energy saving generation period after completion of NGFF ‘ s renovation work, maintenance of the present greenhouse effect gas reduction effect is achievable with establishment of system, in which adequate spare parts are supplied without delay.

(3) Accumulated volume of greenhouse effect gas reduction effect From (1) actual volume of greenhouse effect gas reduction effect and (2) generation period of greenhouse effect gas reduction effect, annual greenhouse effect gas reduction effect is calculable and indicated below.

Net annual reduction volume of greenhouse effect gas CO2, calculated from natural gas: 7,768 MT/Y

Meanwhile, accumulated volume of energy saving in 10 years comes up to 10 times as much as present annual energy saving production volume and is shown below.

In the case of natural gas: 7,768 MT/Y x 10 = 77,680 MT/ 10 years.

2.4 Actual Method for Ascertaining Greenhouse Effect Gas Reduction Effect

(1) Greenhouse effect gas reduction volume

Except CO2 produced by natural gas burning, there is not any other production of greenhouse effect gas in this project. It is, therefore, difficult to measure exactly

absolute volume of CO2 diffused into air through smoke dust. In actual method for ascertainment, the remaining volume obtained by deducting volume of carbon, fixed by

-III-13 urea, from total volume of carbon atom contained in all quantity of natural gas is estimated to be equivalent to volume of gas diffused into the air in the state of

greenhouse effect gas (CO2), as mentioned in paragraph 2.3 of this chapter “Actual volume of greenhouse effect gas reduction effect”.

Natural gas reduction volume, ascertained by measurement method mentioned in paragraph 1.4 of this chapter ” Actual method for ascertaining energy saving effect” and reduction volume of greenhouse effect gas, calculated from its composition, are as follows.

(2) Data collection

Data to be collected is the same to data required for ascertaining natural gas reduction volume attributable to energy saving effect. With measurement method and measurement items, mentioned in paragraph 1.4 of this chapter “ Actual method for ascertaining energy saving effect”, effect of greenhouse effect gas is, therefore, actually confirmed. Such data collection is made by NGFF by use of instrument and method mutually agreed by both of Japanese and Bangladesh parties. NGFF is expected to provide such data in the form mutually agreed with BCIC and Ministry of Industry.

(3) Communication in respect of data collection Data is submitted monthly to Ministry of Industry and quarterly to Japan by NGFF. Ministry of Industry makes data-check monthly and notifies Japan quarterly of results of comparison with greenhouse effect reduction target value. Also, details of unaccomplished volume due to trouble, such as equipment trouble, are notified to Japan.

(4) Ascertaining method

In view of international character of CDM, it is necessary to turn to related agencies of both governments for their guidance at the time when ascertainment of greenhouse effect gas reduction effect is required. Since in Bangladesh there are Ministry of Industry and Ministry of Environment & Forest, both of which have such function as corresponding to that of Ministry of Economy, Trade and Industry in Japan, formation of new organization appears unnecessary.

The existing organizations of both countries are indicated in the following Diagram III-2. In this Diagram, NGFF and Japanese promoter (company) surrounded by heavy lines are principal promoters in the project and lines connecting each department mean transmission route of information or instruction. To ascertain greenhouse effect gas reduction effect by means of transmitting such information, guidance of related agencies of both governments is required.

Organization on the side of Bangladesh Organization on the side of Japan

Ministry of Ministry of Ministry of Industry Environment & Economy confirmation Forest confirmation

Environment BCIC Trade & Industry Department

Resources & Energy Agency

support support Department in Energy Efficiency NGFF charge of new Office energy

Japanese promoter (company), report

Figure III-2 Monitoring system

3. Influence to Productivity

With increase of operation rate, production increase effect is attainable. Thanks to shutdown of operation, caused frequently by equipment trouble due to super-annuation of equipment, inadequate preparation and lack of spare parts as well as by accumulated time of stoppage, following successive shutdown, operation rate has decreased. In NGFF’ s renovation plan, reduction of shutdown time, curtailment of total down time and recovery of production up to full capacity of equipment are proposed, on the condition that provision of emergency spare parts & adequate preparation and renewal of considerably super-annuated equipment are executed. On the basis of present production volume, production increase effect, due to betterment of operation rate after NGFF renovation work, rises up by about 28% to 23,990 MT of annual urea production.

In respect of ammonia production equipment, more than 5% of production increase is achievable, compared with usual equipment capacity, through process change (Plan A & B) in gas generation part. Despite more than 5% increase effect at the part of front end, there are a

III-15- lot of bottlenecks for capacity -up in down stream equipment, particularly synthesis gas compressor and compressor for cooler. Although a large amount of additional investment is required for increasing equipment capacity with removal of such bottlenecks, additional new investment is considered to be restricted in economic aspect, on the assumption that only 10 years of equipment life remains.

In NGFF Fertilizer Plant, ammonia intermediate product is used for ASP and outdoor sales. At present, such volume amounts to approximately 5%. Since ammonia, used for other than urea production, is covered by surplus production capacity, exceeding the existing equipment capacity, a lot of benefits are brought about to NGFF. In addition to production increase effect, energy saving and environmental betterment effect, synergy effect, such as simplification of operation management & maintenance, is obtainable, through partial process change in ammonia equipment.

— Ill —16 — CHAPTER 4

PROFITABILITY CHAPTER 4 PROFITABILITY

1. Economical Effect Due to Investments Payback

1.1 Preconditions for Calculation and Financial Plan

(1) Premise of Financial Analysis Foreign Exchange Rate : 1 US$ = 54 TK= ¥ 110 Construction Cost : US$ 19,106,000 (2,102 Million Yen)

Annual Increase of Production : Urea 23,990 T/Y(Increase of production from 84,275 T/Yto 108,265 T/Y)

Sales Price of Urea : Government regulated domestic price at 1998-99 is 4,800 TK (88.89 $/Ton) N This is intentional low price to protect farmers. For your reference, present international price of Urea (CIF )seems to be $110^120 per ton. Therefore, for diversified analysis Economical Financial Analysis is made on the following four cases. CASE-1 : 88.89 $/T (Actual Government price of fiscal year of 1998-99)

CASE-2 : 100.00 $/T CASE-3 : 110.00 $/T CASE-4 : 120.00 $/T

Variable Cost : Actual Unit Cost of Natural Gas at 1998-99 is 1.93 TK/Nm3

Method of Depreciation : Straight-line method, Depreciation period 1 Oyears

Salvage value : 0

Project Life 15 years (2) Financial Plan

The sources for the required funds have not been fixed yet at present time. However, if we take the situation of financial possibility in Bangladesh, they shall depend all construction cost on the soft finance from foreign countries. Possible finance conditions from Japan (Yen Credit) is chosen for calculation purpose as below-mentioned ; Coverage: 100% of construction cost including local portion Interest: 1% per annum Grace period: 7 years Repayment period: 25 years Local Finance: Interest 10% if finance short occures during operation period

1.2 Investment Amount and Effects

(1) Total Investment Cost and Total Fund required Captioned Cost and Fund is mentioned in table IV — 1

IV — 1 Total Investment Cost and Funds

(Unit:US$ 1,000) CASE-1 CASE-2 CASE 3 CASE-4 Construction Cost 19,106 19,106 19,106 19,106 Pre-Operating Cost 105 105 105 105 Interest during Construction 109 109 109 109 Total Investment Cost 19,320 19,320 19,320 19,320 Cash 44 50 55 60 Total Fund Required 19,364 19,370 19,375 19,380

(2) Energy Saving and Production Increase Effect 1) Energy Saving Effect Present annual consumption of natural gas is 153,380,000 Nm3 (for Urea Plant)

By energy saving modification^ unit consumption for Urea production decreases from 1820 Nm3/T to 1462/ Nm3 by 358 Nm3/T. Therefore total decreased volume is calculated as below;

358 Nm3 X 84,275 T/Y=30,170,000 Nm3/Y =>Amount 1,077,000 $/Y(30, 170,000 Nm3/Y X 1.93 TK/Nm3 / 54 TK/$)

— IV —2 — 2) Production Increase Effect The production increase from 84275T/Y to 108265T/Y will be 23990T/Y.Marginal profit will be 590,000$/Y on (CASE I base)

1.3 IRR Calculation Results and Appraisal

Based on Premise, Total Investment Cost, Effect of energy saving and Production Increase, IRR figures are calculated as shown in Table IV-2

TablelV — 2 IRR on each case

Construction Cost Sales Price of IRR(%) (1000$) Urea CASE-1 19,106 88.89 $/T 3.43 CASE-2 19,106 100.00 $/T 5.55 CASE-3 19,106 110.00 $/T 7.34 CASE-4 19,106 120.00 $/T 9.04

Following is summary;

IRR on CASE I (88.89 $/T) is 3. 43 %. This case, even if small profit due to regulated price by government, is judged “feasible”. IRR on case 11(100 $/T) is 5. 55 %. Both case are feasible due to be over interest rate 1%. In case of 110 $/T, CASE-3 or!20 $/T , CASE-4, IRR sharply upward to7.34%, 9.04% respectively. From the point of profitability, depreciation cost factor occupies very high rate, so 1-10 years is not profitable but cash flow is plus. After depreciation is 100% done, considerable profit can be got starting from 11 years to 15 years even in CASE-1 „ 2. In all cases there will be no big shortage of finance.

Profitability of this project and status of cash flow is described on the out-put from computer enclosed.

For your refrence, IRR for the project is calculated as discount rate, by which the present value of cash out flow and that of cash flow in the following concept become equal value.

Outflow : Plant construction cost + Pre-operation expense + Working capital + Interest during construction

Inflow : Profit after tax + Interest + Depreciation + Differed assets + Amortization cost.

IV —3 2. Cost Reduction Effect in this Project

2.1 Energy-saving Effect

As mentioned in Chapter 3, the energy saving effect in this project is indicated in the following table.

Table IV —3 Annual enrgy saving item Natural gas Annual reduction in volume 30,170,000 Nm3/Y Annual reduction $ 1,077,000 amouunt in US$ Annual reduction in calorie 259. 8 Gkcal Annual reduction 25,980 toe/Y on crude oil equivalent

(Note) Annual reduction volume indicated in the form of sum of money (Natural gas 30,170,000 Nm3/Y X 1.93 TK/54= 1,077 K$)

Followings are evaluation on annual energy saving per investment cost.

Energy saving in crude oil equivalent : 25,980 toe/y(toe; ton oil equivalent) Total Investment Cost : US$ 19,106,000(2,102 million yen) Annual energy saving per investment cost : 1,360 toe-y/million-$ (12. 36 toe-ymillion yen)

Annual cost saving per investment cost : 0. 564 $ (1,077,000 -Tl9,106,000)

2.2 Effects of Greenhouse Gas Reductions

The evaluation of green house gas reduction is indicated as follows;

Annual Reduction volume of Greenhouse Gas : 80,388 t- COz/y Total Investment : US$ 19,106,000(2,102 million yen)

— IV —4 — Annual CO2 reduction per total investment cost : 4,207 t-C02-y/million-$ (38. 25 t-C02-y/milIion yen)

Annual CO2 reduction equivalent crude oil considering production Increase

: 10,3580 t -CO2/ y

Annual reduction CO2 per total investment

: 544 t- CO2 /y/million-$(4.92 t-C02-y/million yen) CHAPTER 5

CONFIRMATION OF DISSEMINATION EFFECT CHAPTER 5 CONFIRMATION OF DISSEMINATION EFFECT

1. Possibility of Spread of the Technology Introduced in the Project

The technology adopted in this project i.e. “cryogenic co conversion process advanced CO2 removal process,synthesis gas refining process by methanater (Plan A)”, have been already been introduced in the other big capacity fertilizer plants of BCIC in Bangladesh. Therefore, they are already proven process in Bangladesh. But, hydrogen removing process(Plan B) is having high possibility to be introduced in the fertilizer plants without using this process so far.

Maintenance technology adopted in this project must spread to fertilizer plants of BCIC with low rate operation and high unit consumption

2. Effects Reflecting the Diffusion of Technologies

2.1 Energy Saving Effects

Annual urea production by four big size fertilizer plants in 1999 is 1,520,000 ton. This is 600,000 ton less than designed capacity. Those for each plant are CUFL: 82%, ZFCL: 68%, UFFL: 68%, JFCL: 67%.

Unit consumption of the natural gas for each fertilizer plant in Bangladesh is 918N3, 90% operating rate at highest level and 1121N3 60% operating rate at lowest level.(This figure is weight-averaged by picking up highest figure and lowest figure for each plant of last five years) According to the data in 1992,they are 1021N3 at 71.7% operating rate in average.

Provided that maintenance technology described in this project is introduced in the big size major 4 plants, as a result, unit consumption can be revived to 918N3 at 90% operating rate (highest figure in last five years) from 1021N3 at 71.7% operation rate(average in 1999),following energy saving will be achieved;

(1021 Nm3-918 Nm3) *1,520,000 MT/Y= 156,560,000 Nm3/Y

In other word, 156,560,000 Nm3/Y will be saved. This figure can be converted to 1350 G Kcal/Y and (1,350)/( 10,000 Kcal/kg) = 135,000,000 kg (135,000 toe/Y) in crude oil equivalent.

-V-l- 2.2 Effects Due to Greenhouse Gas Reduction

Based on 1.02 mol green house gas is generated when burning of 1 mol green house gas,and 156,560,000N 3/Y gas is saved as per 2.1 section, following green house gas will be reduced;

156.560.000 (Nm3/Y)X 1.02 = 159,691,000 Nm3/Y

159.691.000 (Nm3/Y)X44/22.4 = 313,679,000 kg/Y equivalent, 313,679 MT/Y. CHAPTER 6

INFLUENCE TO OTHER ASPECTS CHAPTER 6 INFLUENCE TO OTHER ASPECTS

1. Environmental Aspect

Thanks to super-annuation in NGFF’s equipment, the surrounding area is badly affected by a large quantity of leakage of environmental pollution matters. Lean solution, ammonia gas and ammonia water solution are mainly included in these matters. Also, leakage of product urea solution from equipment, falling of grained product during handling and flow of dissolved product into side ditch are often recognized. With air for cooling, urea grain is diffused like smoke into the atmosphere from the top of grain production tower. In addition, there are K2CO2 solution and MEA solution, absorption solution in CO2 removal equipment as well as Sox and Nox from power generation boiler and reforming furnace. Among these environmental pollution matters, lean solution and ammonia come into question particularly. In respect of environmental pollution caused by lean solution, it is possible to solve such question through implementation of this renovation work by application of low temperature CO conversion and methanator method after synthesis gas refinement being stopped for reason of process change. Also, environmental pollution due to leakage of ammonia can be prevented by adequate preparation of machinery & equipment. There is not any other matter, which becomes a subject of discussion due to bad influence to environment. With implementation of NGFF renovation work, a substantial reduction of environmental pollution matter leakage is attainable, as relevant machinery & equipment are adequately prepared.

2. Economic Aspect

2.1 Foreign Currency Saving

In Bangladesh, around 500,000 tons of urea is imported annually. In case of production volume reduction attributable to super-annuation of other fertilizer plants in the future, increase of increase of import volume will become necessary. In NGFF, around 12,000 tons of ammonia sulfate is also produced annually. In the case that NGFF ‘ s operation is stopped, import of around 100,000 tons of urea and about 12,000 tons of ammonia sulfate, equivalent to NGFF’ s production volume, is needed for their coverage. In the event that 120 USS/t of import urea price and 100 US$/t of import ammonia sulfate price are assumed respectively, Bangladesh Government is expected to suffer from around 13.2 million US$ of foreign currency loss yearly, and Bangladesh will be badly damaged by such loss.

-VI-1 2.2 Reduction of Production Cost

With implementation of NGFF renovation work, production cost of urea product is anticipated to decrease from around 6,000 Taka of present cost to 3,572 Taka, owing to energy saving effect and production increase effect. As a result of economic calculation, approximately 169,398,000 Taka (3,137,000 US$) of accumulated income increase is estimated in 15 years. Up to the present, NGFF has recorded losses and continued deficit operation, due to back spread between production cost and sales price, every year. With implementation of this renovation work, a remarkable improvement of such deficit structure is attainable.

2.3 Sales Price

Supply price of 50kg bagged urea product amounts to 4,800 Taka/ton on ex-factory basis. In sales price to customer, freight is added to the above supply price. In neighborhood area, fertilizer is, therefore, obtainable at relatively low price. NGFFs urea product freight comes up to around 700 Taka/ton. So sales price of urea, delivered to farm houses and managers of tea plantation in the neighborhood of , amounts to around 5,500 Taka/ton. Thanks to Bangladeshi road conditions, particularly worst in rainy season, plenty of time and expenses are required for transport. In case of NGFF s operation stoppage, fertilizer could be delivered from ZFCL in Ashuganj, locating at nearest point to customers in Sylhet district. In this case, sales price of urea in Sylhet district is expected to rise up to around 6,000 Taka//ton.

3. Social Aspect

3.1 Guarantee for Livings of Employees and their Families

Until the time when NGFF Plant was built up 40 years ago, Fenchuganj had been a deserted village, having some tea plantations. In such place, a fertilizer plant, deemed as large sized plant at that time, appeared unexpectedly. Since then, Fenchuganj has prospered as business castle town for about 40 years. More than 10,000 people, including about 1,150 employees of NGFF, trade-men who come regularly to NGFF and their families, are now living in Fenchuganj. In case of NGFF being closed by Bangladesh Government, compensations for these people’s livelihoods are required. As NGFF ‘s labor union has a strong consciousness of rights, it is obvious that conflict between party in power and non-government parties will become serious.

-VI-2 In Fenchuganj, construction plan of a new plant adjacent to NGFF, called as Shahjarar Fertilizer Plant, is in progress. Bangladesh Government is desirous of continuing NGFF ‘s operation until completion of this new plant construction. Under the circumstances, measures for 10 years prolongment of NGFF ‘s life were asked for by the Government. Unfortunately, F/S for construction of a new fertilizer plant has, however, come to a negative conclusion, due to transport problem of products. If such situation hasn ’t changed even after 10 years, the Government will ask certainly for prolongment of NGFF ‘s life again.

3.2 Function as a Supply Base of Fertilizer in Fenchuganj Area

Tea plantations and farmhouses in the suburbs of Fenchuganj, mainly using urea fertilizer, depend on NGFF as supplier of such fertilizer. In rice farming and tea plantation, ammonia sulfate is needed, since sulfur increases fertilizer effectiveness. Except urea, NGFF has around 12,000 tons production of annual ammonia sulfate, mainly supplied to tea plantations. In Bangladesh, NGFF is only a plant where ammonia sulfate is produced. Such being the case, NGFF is an important supplier of fertilizer to rice farming and tea plantation houses in Sylhet district. In case of NGFFs operation being stopped, a serious influence to local agriculture is inevitable.

-VI-3- CONCLUSION CONCLUSION

With NEDO’s entrustment for “Investigation on Renovation Project of Fenchuganj Fertilizer Plant, Bangladesh ”, Kobe Steel, Ltd investigated energy saving and its resultant greenhouse effect gas reduction volume through local investigations executed 3 times since September, 2000 and implemented investigations on the possibility of COM (Clean Development Mechanism) and F/S for the purpose of combining this project with future CDM project in Japan.

Consequently, our investigation has revealed that reductions of consumption energy and greenhouse effect gas would be achievable, as assumed in original proposal, by means of implementing NGFF Fertilizer Plant ’s renovation project as CDM project. In addition, NGFF Fertilizer Plant at execution site, BCIC, its upper organization, Ministry of Industry and Ministry of Environment & Forest have strong intentions for promoting this project as CDM project and continuing their activities for materialization of this project in cooperation with us. Also, the above matters have been confirmed mutually by the parties in both countries.

Major technical points on the basis of investigation results are as follows.

CD Construction cost of NGFF Fertilizer Plant renovation project amounts to 19,106,000 US$. This amount is expected to be fully covered by soft loan with terms of 1.1% interest rate, 25 years repayment period and 7 years grace period, under such construction conditions as 2 years construction period, 10 years amortization period and 10 years installment payment. Also, coverage of insufficient fund is made by domestic short-term borrowings (10% interest rate). As a result of financial calculation, this project has proved to be profitable, since 3.43% of income, in case of 4,800 Taka (equivalent to 88.9 US$) of domestic urea official price, and 9.04% of income, in case of 120 US$ of sales price (equivalent to import price), are estimated respectively.

(2) Energy reduction volume increases yearly by 4,220 toe on crude oil basis with 4,903,000 Nm3 of annual natural gas consumption increase, as natural gas required for urea production increase exceeds the reduced volume of natural gas due to energy saving effect.

(3) In respect of greenhouse effect gas in the state of CO2 as a whole, its reduction effect comes up to 7,768 MT(CO]) annually.

-1 Bangladesh has supported its domestic economy by means of receiving foreign aids as aid recipient country. Thanks to financial difficulty under such conditions, NGFF Fertilizer Plant, a state-run company, is severely restricted in its capital expenditures required for plant modernization and maintenance & inspection. Since sales price of urea product is extremely lowered by the Government for protection of farmers, NGFF suffers from back spread between production cost and sales price. With implementation of this project, contribution to CO2 reduction in Japan as well as favorable effects, such as adequate correspondence to environmental standards, betterment of equipment productivity, foreign currency saving and guarantee for livings of local residents, and economic effect in Bangladesh are attainable. It is, therefore, appraised as excellent project.

The parties in Japan and Bangladesh intend to tackle the problem of materializing the project positively. Since provision of ODA (Yen Credit) is eagerly desired, the parties are expected to continue their activities for its realization.

2 APPENDIX-1

LIST OF SOURCE BOOKS APPENDIX-1

List of source books

1) JETRO Asia Economic Research Center HP

http: //www.. ne .j p / asahi/bhalo/ne wa/

2) Ministry of Foreign Affairs, Japan http://www.mofa. go.in/mofa/ area/bangladesh/data/html

3) NEDO

South Asia Area(Bangladesh) Energy Massive Consumption Industries Basic Research Business

Research Report for 1999, entrusted with Japan Consulting Institute

— A— 1 — APPENDIX-2

SITE SURVEY SCHEDULE 1st Site Survey

Sept 3rd to September 14th Members: Y.Tanaka ,Leader J. Nada, Process Engineer Y.Yabunaka, Marketing Manger T.Yoshikawa, Mechanical Engineer

Content of schedule day date Lodge AM PM 1 9/3 Sun Leave Narita Arriv. Dacca Dacca 2 4 Mon Visit JBIG Japanese Embassy Dacca Meeting with Ministry of Environment Meeting with Ministry of 3 5 Tue Dacca and Forest Indsutry/BCIC Arriving Fenchuganj 4 6 Wed Leave Dacca Fench Make up schedule with NGFF 5 7 Thu Survey facility and plant operation Survey facility and plant operation Fench 6 8 Fri holiday holiday Fench 7 9 Sat Survey Power Plant of NGFF Survey NGFF facility and operation Fench 8 10 Sun Survey NGFF facility and operation Finnl Meeting withNGFF Fench Arriving Dacca 9 11 Mon Leave Fench Dacca Collect Information Visit Polash Fertilizer 10 12 Tue Visit Polash Fertilizer Dacca

Visit JETRO Office to collect Visit and report to BCIC survery 11 13 Wed - information report, Leave Dacca 12 14 Thu Arrive Ja;pan -

-A-3 2nd Site Survey

Members: Mr. Y. Tanaka Leader J. Nada Process engineer T. Yoshikawa Mechanical engineer

Content of schedule day date Lodge AM PM 1 10/22 Sun Leave Japan Arriv. Dacca Dacca 2 10/23 Mon Ministry of Environment and Forest BCIC Dacca Mr. Nada/Yoshikawa leave Dacca Arriv. Silhet and visit NGFF Fenchu 3 10/24 Tue Mr. Tanaka visit BCIC BCIC Dcca Mr.Nada/Yoshikawa inspect operation NGFF Fenchu 4 10/25 Wed at NGFF Mr. Tanaka leave Dacca visit ZFCL Dcca

5 10/26 Thu Mr.Nada/Yoshikawa at NGFF NGFF Fenchu Mr. Tanaka leave Dacca visit JFCL Dcca 6 10/27 Fri Mr. Nada/YoshikawaHoliday Holiday Fenchu MR. Tanaka Holiday Holiday Dcca 7 10/28 Sat Mr.Nada/Yoshikawa NGFF NGFF Fenchu Mr. Tanaka collect information Nissho Iwai Dacca Ofice Dacca 8 10/29 Sun Mr.Nada/Yoshikawa NGFF NGFF Fenchu Mr. Tanaka collect information Leave Dacca , Arriv. Fenchuganj 9 10/30 Mon NGFF NGFF Fenchu 10 10/31 Tue NGFF NGFF Fenchu Final Meeting with NGFF including Final Meeting with NGFF including 11 11/1 Wed Fenchu GM GM Final Meeting with NGFF including Final Meeting with NGFF including 12 11/2 Thu Fenchu GM.confirm repairing items GM.confirm repairing items 13 11/3 Fri Leave Silhet Arriv. Dacca Dacca 14 11/4 Sat Nissho Iwai Dacca Visit BCIC Dacca 15 11/5 Sun Leave Dacca, 16 11/6 Mon Arriv.Japan 3rd Site Survey

January 10 to January 18th Members: Y.Tanaka ,Leader J.Nda Process Engineer Y. Yabunaka Markting Manager

Content of schedule day date Lodge AM PM 1 1/10 Wed Leave Japan Arriv Dacca Dacca Meeting with JETRO Dacca and JBIC 2 1/11 Thu Ministry of eEnvironment and Forest Dacca DACCA 3 1/12 Fri Leave Dacca Arriv Fenchuganj Fenchu 4 1/13 Sat Confirm Modification Items at NGFF Confirm Modification Items at NGFF Fenchu 5 1/14 Sun Confirm Modification Items at NGFF Confirm Modification Items at NGFF Fenchu Final Meeting with NGFF Top people 6 1/15 Mon Final Meeting with NGFF Top people Fenchu including MD Visit BC1C and Report to Planning 7 1/16 Tue Leave Fenchuganj Dacca Director BCIC 8 1/17 Wed Nissho Iwai Leave Dacca (23:55) 9 1/18 Thu Arriv. Japan Any part or a whole of the report shall not be disclosed without prior consent of International Cooperation Center, NEDO.

Phone +8 1- 3- 398 7- 9466 Fax +81-3-3987-5103