The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Power Sector Recovery Project (P146696)
AFRICA | Guinea | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 11 | ARCHIVED on 19-Jun-2020 | ISR42351 | Public Disclosure Authorized
Implementing Agencies: Ministry of Energy and Hydraulics, The Republic of Guinea, Electricite de Guinee (EDG), Unité de Gestion du PRSE/MEH, Unité de Gestion du Projet/EDG
Key Dates
Key Project Dates
Bank Approval Date: 16-Jun-2014 Effectiveness Date: 30-Jan-2015 Planned Mid Term Review Date: 16-Nov-2017 Actual Mid-Term Review Date: 30-Apr-2018 Original Closing Date: 31-Dec-2019 Revised Closing Date: 31-Dec-2020 pdoTable
Public Disclosure Authorized Project Development Objectives
Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve the technical and commercial performance of the national power utility.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
Components Table
Name Support the improvement of EDGâs performance through a Management Services Contract:(Cost $16.00 M) Improvement of Conakry Distribution Network and Commercial Performance of EDG:(Cost $46.70 M) Public Disclosure Authorized Technical Assistance, Capacity building and Project Implementation Support:(Cost $12.30 M)
Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating High Substantial
Implementation Status and Key Decisions
The detailed project progress by the components can be summarized as follows: The component 1 – Management service contract (MSC) of Electricité de Guinée (EDG): the four-year MSC has been fully implemented and ended on October 9, 2019 and the final technical contract audit by the MSC auditor (PWC) was submitted in Feb. 2020.
Public Disclosure Authorized The transition from MSC to a Management led by a team of competitively recruited Guineans, assisted by a management support operator (MSO) is not yet over. The Board of Directors appointed in August 2019 took over from the MSC Contractor and appointed an interim management team. Through a competitive selection by the Board of Directors assisted by a project financed HR firm, a Director General (DG) was hired and appointed in January 2020 and directors are hired. A Management MSO was selected, and its experts will be deployed as soon as restrictions imposed by COVID-19 are lifted.
6/19/2020 Page 1 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
The implementation of Component 2 (Improvement of Conakry Distribution Network and Commercial Performance of EDG) and Component 3 (Technical assistance, capacity building and support to project implementation) is Satisfactory. The Contracts for works of the initial project financing including the rehabilitation of distribution network in Dixinn; the regularization of illegal connections in Kaloum, Ratoma and Matoto have been fully implemented. Component 3 mainly financed the MSC technical auditor, the electricity anti-fraud policy. The financial restructuring plan of EDG is 60% completed.
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance -- High Substantial Macroeconomic -- Substantial Moderate Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Low Institutional Capacity for Implementation and -- Substantial Moderate Sustainability Fiduciary -- Substantial Moderate Environment and Social -- Substantial Substantial Stakeholders -- High Substantial Other -- -- Substantial Overall -- High Substantial
Results
PDO Indicators by Objectives / Outcomes
Improve the technical performance of the national power utility
IN00859060 ►Direct project beneficiaries (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 1,400,000.00 3,160,000.00 3,650,000.00 3,200,000.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859135 Female beneficiaries (Percentage, Custom Supplement)
Baseline Actual (Previous) Actual (Current) End Target
6/19/2020 Page 2 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Value 52.00 52.00 52.00 52.00
IN00859137 ►Electricity losses per year (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 42.00 29.90 23.00 23.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
Improve the commercial performance of the national power utility
IN00859131 ►Bill collection rate (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 77.00 83.00 83.00 96.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
Improve the technical performance of the national power utility
IN00859134 ►Average daily hours of service (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 12.00 19.00 20.00 18.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
Improve the technical performance of the national power utility
IN00859132 ►Average interruption frequency per year in the project area (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 942.00 350.00 450.00 350.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
People provided with new or improved electricity service
IN00859133 ►People provided with new or improved electricity service (Number, Corporate)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 220,726.00 274,433.00 318,000.00
6/19/2020 Page 3 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859136 People provided with new or improved electricity service - Female (Number, Corporate Supplement)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 114,777.00 165,360.00 165,360.00
Intermediate Results Indicators by Components
Technical Assistance, Capacity building and Project Implementation Support
IN00859140 ►Average number of hours of training per staff per year (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 17.00 6.80 17.00
Date 25-Aug-2017 11-Dec-2019 18-Jun-2020 31-Dec-2020
Improvement of Conakry Distribution Network and Commercial Performance of EDG
IN00859139 ►People provided with access to electricity services under the project by household connections â rehabilitation and standardization of household connections in Kaloum Ratoma and Matoto (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 216,150.00 216,150.00 216,150.00
Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859142 ►Number of substations refurbished (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 55.00 61.00 67.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859143 ►People provided with access to electricity services under the project by household connections â Rehabilitation and extension of Distribution network in Dixinn (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 36,574.00 59,377.00 74,178.00
Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859144 ►Beneficiary satisfaction survey completed, published (Yes/No, Custom)
6/19/2020 Page 4 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Baseline Actual (Previous) Actual (Current) End Target
Value No No No Yes
Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859145 ►Number of meters installed, of which large consumer smart meters (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 61,786.00 62,633.00 57,887.00
Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859146 ►Number of transformers installed (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 39.00 39.00 24.00
Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859147 ►Distribution lines constructed or rehabilitated under the project (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 157.00 157.00 96.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859148 Distribution lines rehabilitated under the project (Kilometers, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 157.00 157.00 96.00
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
Support the improvement of EDGs performance through a Management Services Contract
IN00859138 ►Operator appointed (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No Yes Yes Yes
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
IN00859141 ►Technical auditor appointed (Yes/No, Custom)
6/19/2020 Page 5 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Baseline Actual (Previous) Actual (Current) End Target
Value No Yes Yes Yes
Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020
Performance-Based Conditions
Data on Financial Performance
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed
P146696 IDA-54990 Effective USD 22.60 22.60 0.00 20.20 0.10 99%
P146696 IDA-61830 Effective USD 25.00 25.00 0.00 9.37 14.89 39%
P146696 IDA-H9690 Effective USD 27.40 27.40 0.00 24.79 0.00 100%
Key Dates (by loan)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P146696 IDA-54990 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020 P146696 IDA-61830 Effective 16-Mar-2018 17-Apr-2018 09-Nov-2018 31-Dec-2020 31-Dec-2020 P146696 IDA-H9690 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020
Cumulative Disbursements
6/19/2020 Page 6 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
PBC Disbursement
Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC
Restructuring History
There has been no restructuring to date.
Related Project(s)
P160771-Power Sector Recovery Project - Additional Financing
6/19/2020 Page 7 of 7