The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

Power Sector Recovery Project (P146696)

AFRICA | Guinea | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 11 | ARCHIVED on 19-Jun-2020 | ISR42351 | Public Disclosure Authorized

Implementing Agencies: Ministry of Energy and Hydraulics, The Republic of Guinea, Electricite de Guinee (EDG), Unité de Gestion du PRSE/MEH, Unité de Gestion du Projet/EDG

Key Dates

Key Project Dates

Bank Approval Date: 16-Jun-2014 Effectiveness Date: 30-Jan-2015 Planned Mid Term Review Date: 16-Nov-2017 Actual Mid-Term Review Date: 30-Apr-2018 Original Closing Date: 31-Dec-2019 Revised Closing Date: 31-Dec-2020 pdoTable

Public Disclosure Authorized Project Development Objectives

Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve the technical and commercial performance of the national power utility.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

Components Table

Name Support the improvement of EDG s performance through a Management Services Contract:(Cost $16.00 M) Improvement of Distribution Network and Commercial Performance of EDG:(Cost $46.70 M) Public Disclosure Authorized Technical Assistance, Capacity building and Project Implementation Support:(Cost $12.30 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO €Moderately Satisfactory €Moderately Satisfactory Overall Implementation Progress (IP) €Moderately Satisfactory €Moderately Satisfactory Overall Risk Rating €High €Substantial

Implementation Status and Key Decisions

The detailed project progress by the components can be summarized as follows: The component 1 – Management service contract (MSC) of Electricité de Guinée (EDG): the four-year MSC has been fully implemented and ended on October 9, 2019 and the final technical contract audit by the MSC auditor (PWC) was submitted in Feb. 2020.

Public Disclosure Authorized The transition from MSC to a Management led by a team of competitively recruited Guineans, assisted by a management support operator (MSO) is not yet over. The Board of Directors appointed in August 2019 took over from the MSC Contractor and appointed an interim management team. Through a competitive selection by the Board of Directors assisted by a project financed HR firm, a Director General (DG) was hired and appointed in January 2020 and directors are hired. A Management MSO was selected, and its experts will be deployed as soon as restrictions imposed by COVID-19 are lifted.

6/19/2020 Page 1 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

The implementation of Component 2 (Improvement of Conakry Distribution Network and Commercial Performance of EDG) and Component 3 (Technical assistance, capacity building and support to project implementation) is Satisfactory. The Contracts for works of the initial project financing including the rehabilitation of distribution network in ; the regularization of illegal connections in Kaloum, and have been fully implemented. Component 3 mainly financed the MSC technical auditor, the electricity anti-fraud policy. The financial restructuring plan of EDG is 60% completed.

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance -- €High €Substantial Macroeconomic -- €Substantial €Moderate Sector Strategies and Policies -- €Substantial €Substantial Technical Design of Project or Program -- €Moderate €Low Institutional Capacity for Implementation and -- €Substantial €Moderate Sustainability Fiduciary -- €Substantial €Moderate Environment and Social -- €Substantial €Substantial Stakeholders -- €High €Substantial Other -- -- €Substantial Overall -- €High €Substantial

Results

PDO Indicators by Objectives / Outcomes

Improve the technical performance of the national power utility

IN00859060 ►Direct project beneficiaries (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 1,400,000.00 3,160,000.00 3,650,000.00 3,200,000.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859135 €Female beneficiaries (Percentage, Custom Supplement)

Baseline Actual (Previous) Actual (Current) End Target

6/19/2020 Page 2 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

Value 52.00 52.00 52.00 52.00

IN00859137 ►Electricity losses per year (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 42.00 29.90 23.00 23.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

Improve the commercial performance of the national power utility

IN00859131 ►Bill collection rate (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 77.00 83.00 83.00 96.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

Improve the technical performance of the national power utility

IN00859134 ►Average daily hours of service (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 12.00 19.00 20.00 18.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

Improve the technical performance of the national power utility

IN00859132 ►Average interruption frequency per year in the project area (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 942.00 350.00 450.00 350.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

People provided with new or improved electricity service

IN00859133 ►People provided with new or improved electricity service (Number, Corporate)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 220,726.00 274,433.00 318,000.00

6/19/2020 Page 3 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859136 €People provided with new or improved electricity service - Female (Number, Corporate Supplement)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 114,777.00 165,360.00 165,360.00

Intermediate Results Indicators by Components

Technical Assistance, Capacity building and Project Implementation Support

IN00859140 ►Average number of hours of training per staff per year (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 17.00 6.80 17.00

Date 25-Aug-2017 11-Dec-2019 18-Jun-2020 31-Dec-2020

Improvement of Conakry Distribution Network and Commercial Performance of EDG

IN00859139 ►People provided with access to electricity services under the project by household connections   rehabilitation and standardization of household connections in Kaloum Ratoma and Matoto (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 216,150.00 216,150.00 216,150.00

Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859142 ►Number of substations refurbished (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 55.00 61.00 67.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859143 ►People provided with access to electricity services under the project by household connections   Rehabilitation and extension of Distribution network in Dixinn (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 36,574.00 59,377.00 74,178.00

Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859144 ►Beneficiary satisfaction survey completed, published (Yes/No, Custom)

6/19/2020 Page 4 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

Baseline Actual (Previous) Actual (Current) End Target

Value No No No Yes

Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859145 ►Number of meters installed, of which large consumer smart meters (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 61,786.00 62,633.00 57,887.00

Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859146 ►Number of transformers installed (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 39.00 39.00 24.00

Date 25-Aug-2017 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859147 ►Distribution lines constructed or rehabilitated under the project (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 157.00 157.00 96.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859148 €Distribution lines rehabilitated under the project (Kilometers, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 157.00 157.00 96.00

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

Support the improvement of EDG€€s performance through a Management Services Contract

IN00859138 ►Operator appointed (Yes/No, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value No Yes Yes Yes

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

IN00859141 ►Technical auditor appointed (Yes/No, Custom)

6/19/2020 Page 5 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

Baseline Actual (Previous) Actual (Current) End Target

Value No Yes Yes Yes

Date 21-May-2014 11-Dec-2019 17-Jun-2020 31-Dec-2020

Performance-Based Conditions

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

P146696 IDA-54990 Effective USD 22.60 22.60 0.00 20.20 0.10 99%

P146696 IDA-61830 Effective USD 25.00 25.00 0.00 9.37 14.89 39%

P146696 IDA-H9690 Effective USD 27.40 27.40 0.00 24.79 0.00 100%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P146696 IDA-54990 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020 P146696 IDA-61830 Effective 16-Mar-2018 17-Apr-2018 09-Nov-2018 31-Dec-2020 31-Dec-2020 P146696 IDA-H9690 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020

Cumulative Disbursements

6/19/2020 Page 6 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)

PBC Disbursement

Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC

Restructuring History

There has been no restructuring to date.

Related Project(s)

P160771-Power Sector Recovery Project - Additional Financing