24x7-Power For All

A joint initiative of

Government of & Government of

December 2014

1

2

Table of Contents

1. INTRODUCTION ...... 5 2. POWER SUPPLY POSITION ...... 7

2.1. POWER SUPPLY POSITION ...... 7

2.2. DEMAND PROJECTIONS ...... 8 3. GENERATION PLAN ...... 12

3.1. EXISTING GENERATION CAPACITY ...... 12

3.2. POWER PROCUREMENT COSTS ...... 14

3.3. ISSUES REGARDING COAL PROCUREMENT PLAN ...... 14

3.4. ACTION PLAN – STATE ...... 18

3.5. GOI INTERVENTION ...... 18

3.6. FUND REQUIREMENT ...... 19

3.7. RENEWABLE ENERGY PLAN ...... 19

3.8. GOI INTERVENTION ...... 20 4. TRANSMISSION PLAN ...... 21

4.1. INTER -STATE TRANSMISSION SYSTEM ...... 21

4.2. INTRA STATE TRANSMISSION SYSTEM ...... 27 5. DISTRIBUTION PLAN ...... 31

5.1. EXISTING DISTRIBUTION SYSTEM ...... 31

5.2. SCHEMES UNDER IMPLEMENTATION ...... 31

5.3. PROPOSED SCHEMES ...... 32

5.4. CONNECTING THE UNCONNECTED ...... 37

5.1. FUND REQUIREMENT ...... 38

5.2. ACTION POINT - STATE ...... 39

5.3. GOI INTERVENTION ...... 39

5.4. RENEWABLE ENERGY INITIATIVES OF GOVT OF RAJASTHAN AT CONSUMER LEVEL ...... 40

5.5. ACTION PLAN - STATE –RENEWABLE ENERGY ...... 41

5.6. GOI INTERVENTION ...... 41 6. ENERGY EFFICIENCY ...... 42 7. FINANCIAL VIABILITY OF DISTRIBUTION COMPANIES ...... 50

7.1. FINANCIAL POSITION OF DISTRIBUTION UTILITIES ...... 50

7.2. FINANCIAL RESTRUCTURING SCHEME OF GOI (O CTOBER 2012) ...... 50

7.1. LOSS REDUCTION, ENERGY MANAGEMENT &, ENERGY ACCOUNTING ...... 54

7.2. GOI INTERVENTION ...... 58

7.3. ACTION POINTS ( DISCOMS / STATE GOVT ) ...... 58

7.4. MANAGING THE RISKS ...... 59

7.5. INVESTMENT PLANNING AND MONITORING MECHANISM ...... 60

3

8. OTHER INITIATIVES ...... 62

8.1. COMMUNICATION ...... 62

8.2. INFORMATION TECHNOLOGY (IT) INITIATIVES ...... 62

8.3. INSTITUTIONAL ARRANGEMENT ...... 63

8.4. CAPACITY BUILDING ...... 64 9. YEAR WSIE ROLL OUT PLAN ...... 65 10. SECTOR WISE INVESTMENT PLAN AND FUND REQUIREMENT ...... 67 11. ANNEXURES ...... 70

4

breakdowns and Supply Code specifying the supply voltages & frequency etc, to be 1. INTRODUCTION followed by Discoms. SERCs also monitors the performance of distribution companies on the basis of notified Performance of Standards. Rajasthan is the largest state in geographical area in the country. It comprises of vast arid To supplement the efforts of State land and desert region. Agriculture is the main Government, Government of India and vocation of the people in the State. State has Government of Rajasthan have taken a joint very little surface water irrigation potential, initiative to provide 24 X 7 power in the state which has been almost fully exploited. Ground to all consumers (except agriculture water is main source of irrigation. consumers). Agriculture consumers will be provided 6.5 -7 Hrs. of supply daily. This The power sector in Rajasthan has witnessed initiatives aims at ensuring uninterrupted substantial improvement over the past decade supply of quality power to existing consumers due to increase in generation capacity and th by the end of 12 plan and providing access to strengthening of network infrastructure electricity to all unconnected consumers in the leading to an improvement in the overall next five years. power supply position of the state. Currently, most connected consumers in the state are An exercise has been carried out to assess the being provided with at least 21-22 hours of additional energy requirement for providing power supply. However, there are areas in the 24x7 power supply to all households in the state which experience unduly long state, financial implications on utilities for interruptions in power supply due to procuring additional energy and per unit inadequacies in the distribution infrastructure. implication on tariff for additional energy. Moreover, a large portion of non-agriculture Based on the exercise, the sensitivity analysis consumers in rural areas are supplied through has been carried out for cost of service and single phase only. Further, there is a large resulting Financial Gap under multiple section of households in the state i.e. about 29 scenarios on various parameters namely, tariff %, which is yet to be electrified. hike, reduction in power procurement cost, increase in interest and moratorium period,

AT&C loss reduction, etc. Electricity is a concurrent subject and distribution of electricity falls under the An assessment of the adequacy of availability purview of the respective State of power to the state from various sources i.e. Government/State Power Utility. As per from generating sources owned by the state Electricity Act 2003, it is the duty of a both existing and under construction, from distribution licensee to develop and maintain central sector stations both existing and under an efficient, co-ordinated and economical construction, Common projects, generating distribution system in his area of supply and to sources owned by private sector and PPAs supply electricity in accordance with the have been made. Inter State Transmission provisions contained in the Act. The State System (ISTS), Intra state Transmission Electricity Regulatory Commission (SERC) System and distribution infrastructure have shall specify or enforce standards with respect been reviewed to ensure their adequacy for to quality, continuity and reliability of service providing 24x7 power in the states. Works by licensees. Accordingly, State Electricity required for strengthening and augmentation Regulatory Commissions (SERCs) have of distribution infrastructure have been notified the Standards of Performance identified for supplying uninterrupted power specifying maximum allowable time for to the consumers. Central Government will restoration of supply due to forced supplement the efforts of the State

5

Government through schemes which are being 7. Measures such as energy mix finalised by Ministry of Power for funding of optimization, reduction in power works required for strengthening and procurement costs, improving operational augmentation of distribution infrastructure, efficiency of state generation plant(s) and feeder segregation and 100% metering. optimal fuel procurement costs including The initiatives for providing 24x7 power in the sources of supply. state mainly includes- 8. Introduce modern technologies to monitor 1. Reliable 24X7 supply to the consumers reliable supply like sub-station automation, (except agriculture) within a period of providing adequate communication three years of commencement of the infrastructure, GIS, Reliability, Centralised program. Agriculture consumers will be Network Analysis and Planning tools, SAP supplied power for 6.5-7 Hrs daily. driven ERP systems, DMS (Distribution Management Systems), OMS (Outage 2. All unconnected households to be Management System), etc. provided access to electricity in a time

bound manner in next five years i.e. by FY 9. Monitoring the timely commissioning of 2018-19. various generating plants, transmission and distribution infrastructure to meet the 3. To ensure adequate capacity addition expected growth in demand. planning & tie ups for power from various

sources at affordable price to meet the 10. To meet the performance standards of projected increase in power demand for supply of electricity as mandated by the future. Regulators. 4. Strengthen the Transmission and Distribution network to cater to the An Action plan has been drawn based on the expected growth in demand of existing as above covenants which will be executed by well as forthcoming consumers. the State Govt with the support of Govt of 5. Financial measures including optimizing India, wherever necessary, as per their investments and undertaking necessary approved plans, schemes and policies. This balance sheet restructuring measures to joint initiative of Government of India and ensure liquidity in the utility finances. Government of Rajasthan aims to enhance the satisfaction levels of the consumers, improve 6. To ensure reduction of AT & C losses as the quality of life of people, and increase the per the agreed loss reduction trajectory. economic activities resulting into inclusive development of the State.

6

2. POWER SUPPLY POSITION 2.1. POWER SUPPLY POSITION sector stations and 75 MW from Mundra UMPP. Maximum peak demand in Rajasthan attained so far was 10,047 MW during last year (2013- The state’s likely benefit from the power th 14) which was also met almost in full. stations planned to come up by the end of 12 Similarly, the energy availability was 58042 plan period would be about 4859 MW, which MUs against the requirement of 58202 MUs. includes 1307 MW from Central sector projects, 1260 MW from State sector projects and 2292 The gap between energy requirement and MW from Private Sector projects. All the State energy availability in Rajasthan is on the and Private sector power projects and a few decline since 2011-12 when it was 3.9% and it Central sector projects, which were planned to has now come down to less than 1%. come up during the 12 th plan period, already Similarly, demand-supply gap during peak stand commissioned providing a benefit of hours in the state has reduced from 7.1% in about 3,813 MW to the state. Additional benefit 2011-12 to almost Nil at present due to of about 1050 MW will be available to significant addition in generation capacity Rajasthan from the Central Sector projects, during the 11th Plan and the 12th Plan period which have to come up by the end of the 12 th so far. The table 2.1 shows the trends of power Plan. supply position in Rajasthan. The sizable benefit of about 6,150 MW from the Rajasthan got benefit of about 2339 MW power projects commissioned in Rajasthan and (Excluding RES) from the power projects th other parts of the country subsequent to the end commissioned during 11 Plan with 434 MW of 10 th Plan has helped Rajasthan become from Central sector stations, 1290 MW from almost self-reliant in meeting the demand of State Sector stations, 540 MW from private power in the state today.

Table 2.1: POWER SUPPLY POSITION IN RAJASTHAN SINCE 9 th PLAN END

PEAK PEAK ENERG ENERGY ENERGY ENERGY PEAK PEAK DEFICIT/ DEFICIT/ Y AVAIL- DEFICIT/ DEFICIT/ PERIOD DEMAND MET SURPLU SURPLU REQUI- ABILITY SURPLUS SURPLU (MW) (MW) S S RMENT (MU) (MU) S (MW) ( % ) (MU) (- / +) ( % ) (- / +) (- / +) (- / +) 9TH PLAN 3700 3657 -43 -1.2 24745 24495 -250 -1.0 END 10 TH PLAN 5794 4946 -848 -14.6 33236 31715 -1521 -4.6 END 2007-08 6374 5564 -810 -12.7 36738 35597 -1141 -3.1 2008-09 6303 6101 -202 -3.2 37797 37388 -409 -1.1 2009 -10 6,859 6,859 0 0.0 44,109 43,062 -1,047 -2.4 2010-11 7,729 7,442 -287 -3.7 45,261 44,836 -425 -0.9 2011-12 8,188 7,605 -583 -7.1 51,474 49,491 -1,983 -3.9 2012-13 8,940 8,515 -425 -4.8 55,538 53,868 -1,670 -3.0 2013-14 10,047 10,038 -9 -0.1 58,202 58,042 -160 -0.3

7

households in the State (Rural 93.05 lakhs and Urban 32.16 lakhs). Out of this 58.20 lakhs 2.2. DEMAND PROJECTIONS households in rural area and 30.26 lakhs households in urban area are electrified The present energy requirement of Rajasthan leaving a balance of 34.85 lakhs households in is of the order of 58.9 BU per year and the rural area and 1.9 lakhs households in urban introduction of 24X7 supply across the State is areas yet to be electrified. The total no of un- likely to increase the electricity consumption electrified households in the State of substantially in the State. The demand can be Rajasthan based on Census figures and as per classified in three broad categories. GoR are as under- (a) Demand on account of 24X 7 power Particulars As per As per GoR supply to already electrified households Census figures (b) Demand on account of 24X7 power Total Households 139,98,504 125,21,000 supply to already electrified other than Rural Households 105,21,699 93,05,000 domestic category Urban Households 34,76,805 32,16,000 (c) Demand from electrification of un- electrified households Total Electrified 88,47,763 H/H Rural Electrified 5,820,819 Estimation of demand considering the 24X7 H/H Urban Electrified 30,26,944 supply program H/H As per Census 2011 data, there were about Total Un-electrified 51,50,741 36,73,237 H/H 125.81 Lakhs households in the State and Urban Un- 4,49,861 1,89,056 67% households were using electricity as electrified H/H main source of lighting in the state. The Rural Un- 47,00,880 34,84,181 details of households as per census 2011 are electrified H/H as under: In urban area, only 15,000 applications are Census 2011 Data of Rajasthan pending for connections and remaining households may be utilizing electricity on No. of Households Households Balance in Rajasthan using Un-electrified share basis as a united family. Out of 34.85 Electricity Households lakhs un-electrified rural households in the as Main state, only about 25 lakhs households may be Source of Lighting considered as un-electrified as balance Total 1,25,81,303 84,30,040 41,51,263 households may be using the electricity on (67%) (33%) shared basis as a united family. Considering Urban 30,90,940 29,01,680 1,89,260 the fast growth in urban area and looking to (24.6%) (93.9%) (6.1%) the past trend, 5 lakhs connection are likely to be released in urban areas in next five years Rural 94,90,363 55,28,360 39,62,003 considering one lakh connections per year. (75.4%) (58.3%) (41.7%) (Source: Census of India ) To compute the demand from hitherto un- electrified households the following steps have The no of Households in the state in 2014 been adopted: based on census 2011 data and Compound (a) The number of electrified and un- Annual Growth Rate (CAGR) of 20 years electrified households in 2014 has been (census of 1991 & 2011) works out to be taken as per Govt of Rajasthan data. 139.99 Lakhs ( 105.22 Lakhs Rural & 34.77 Lakhs Urban). However, as per GoR, as on 01-Apr-2014 there are about 125 Lakhs

8

(b) The electrification of 30 Lakh un- (e) Demand projections for consumers other electrified households have been than domestic have been taken as per considered as per GoR data. Financial Restructuring Plan (FRP). (c) Based on the urban & rural consumption (f) Basis the above, the overall consumption data provided by GoR, present per for domestic & non domestic have been household consumption has been assessed. estimated for the state. (d) Energy requirement for rural & urban The overall energy requirement for state of households have been computed based on Rajasthan by 2018-19 based on the above is the latent demand and considering growth given in the tables below. of per household consumption from the

current levels of 1.96 units/day to 3 units/ day in rural areas by 2018-19 and from 5.5 units/day to 8 units /day in urban areas by 2018-19. (a) Demand from electrified households The improvement of supply as well as natural load growth will result in increase of the consumption levels in the hitherto electrified households. The overall consumption and the additional consumption have been estimated by projecting an increase in per household consumption from the current levels of 1.96 units/day to 3 units/ day in rural areas by 2018-19 and from 5.5 units/day to 8 units /day in urban areas by 2018-19 in the table below.

Table 2.2: ENERGY REQUIREMENT FOR ALREADY ELECTRIFIED HOUSEHOLDS

Rajasthan S. Particulars → Calculation 2014- 2015- 2016- No. ↓ steps 2017-18 2018-19 15 16 17 A DEMAND PROJECTIONS FOR ELECTRIFIED HOUSEHOLDS 1 Consumption of Rural Electrified Households 2 Consumption (units per Units 2.0 2.3 2.5 2.8 3.0 day per household) 3 Annual Energy MUs 4,249 4,905 5,592 6,312 7,066 Requirement for 58,20,819 Rural Household 4 Consumption of Urban Electrified Households 5 Consumption (units per Units 5.50 6.1 6.8 7.4 8.0 day per household) 6 Annual Energy MUs 6,077 6,969 7,910 8,901 9,944 Requirement for 30,26,944 Urban Household 7 Total Annual Energy (A3 + A6) MUs 10,326 11,875 13,503 15,213 17,010 Requirement due to existing electrified households(A3+A6) A1 ADDITIONAL ENERGY REQUIREMENTS FOR ELECTRIFIED DOMESTIC CONSUMERS 1 Additional Energy (A7-presnet MUs 1,316 2,865 4,493 6,203 8,000 Required for Electrified consumption Households i.e. 9010 MUs)

9

(b) Demand from un-electrified households

Table 2.3: ENERGY REQUIREMENTS ON ACCOUNT OF ELECTRIFICATION OF UN- ELECTRIFIED HOUSEHOLDS

ELECTRIFICATION OF UN-ELECTRIFIED HOUSEHOLDS ( 25 Lakh @5 L / year) 2014-15 2015-16 2016-17 2017-18 2018-19 B URBAN 1 Electrification of un- 500,000 Nos. 100,000 100,000 100,000 100,000 100,000 electrified Household 2 Cumulative Annual MUs 201 447 739 1,077 1,460 Energy Requirement for unelectrified Urban Household RURAL 3 Targeted Electrification 2500000 % 20% 20% 20% 20% 20% of unelectrified households 4 Electrification of Nos. 500,000 500,000 500,000 500,000 500,000 unelectrified Household 5 Cumulative Annual MUs 365 821 1,369 2,008 2,738 Energy Requirement for unelectrified Rural Households 6 Total households (B1 +B4) No. 600,000 600,000 600,000 600,000 600,000 electrified 7 Annual Energy (B2 +B5) MUs 566 1,268 2,108 3,084 4,198 Requirement due to Electrification of un- electrified Household

(c) Demand from other than domestic consumer categories The following are the estimates of energy demand from other than domestic consumer categories. The growth in energy requirement for other than domestic consumers has been as per Financial Restructuring Plan (FRP). The table also provides the overall energy demand from all categories including the electrified and to be electrified households.

10

Table 2.4: ENERGY REQUIREMENTS FOR OTHER THAN DOMESTIC CATEGORY CONSUMERS AND TOTAL ENERGY REQUIREMENT

C ANNUAL ENERGY 2014-15 2015-16 2016-17 2017-18 2018-19 REQUIREMENTS 1 Total Domestic Annual MUs 10,892 13,143 15,611 18,298 21,207 Energy Requirement (Current + Projection) 2 Current Energy Requirement 33,676 MUs - Other than Domestic 3 Annual Energy Requirement - MUs 36,563 39,721 43,178 46,963 51,108 Other than Domestic Consumers ( Growth as per FRP) 4 Total Energy Requirements C1+C3 MUs 47,454 52,864 58,789 65,261 72,316 for sale 5 Distribution losses % 21.75 20.00 18.50 17.25 16.00

6 Total Energy required at MU 60,645 66,080 72,133 78865 86090 Discom Periphery 7 Transmission losses % 4 4 4 4 4

8 Total Annual Energy MU 63171 68834 75138 82151 89677 Purchase Requirement 11268 9 Peak Demand (MW) MW 12278 13402 14653 15995 LF=64% ` The above figure of energy requirement is peak demand by around 800-1000 MW by also in line with the projections made in 18 th 2018-19. Further reduction in peak demand EPS by CEA for the state of Rajasthan. As per may also be achieved by adopting demand 18 th EPS of CEA, the projected energy side management initiatives like introduction requirement of Rajasthan is 89,792 MU by of Time of Day (TOD) tariff in the state 2018-19 and after assuming load factor of 64% for Rajasthan, the anticipated Peak Keeping in view the above requirement, an demand of the state would be around 16004 assessment of the adequacy of Generation, MW. Transmission and Distribution infrastructure has been done to meet the projected demand By using energy efficient irrigation pump-sets and the same are covered in the subsequent and energy efficient lighting (use of LEDs), chapters. the energy consumption of the state is expected to reduce by 7950 MUs during 2018-19. This would also help in reducing the

11

3. GENERATION PLAN construction projects. Out of which about 625 MW is from non-conventional energy sources 3.1. EXISTING GENERATION CAPACITY and 5520.15 MW from conventional sources. The total installed capacity as on June 2014 As such the total anticipated available (including allocated share in Joint & Central capacity by 2018-19 is expected to be Sector plants) was 15,201 MW including 56% 21346.14 MW. (17081 MW–Conventional & from coal based generation, 11 % from hydro 4265 MW–Renewable). Taking into based generation and 24 % from renewable consideration the 70% contribution from energy sources. The installed capacity has conventional installed capacity and 8% from grown from 10160 MW to 15201 MW which non-conventional installed capacity to meet is a growth of over 19.6 % per annum during the peak demand, the capacity available for the last two and a quarter year i.e. from meeting the peak demand of 16000 MW 31.03.2012 to 30.06.2014 - contributed from would be around 12298 MW. additions to coal based (3469 MW) and renewable based (1274 MW) generation Non Conventional Conventional Total capacity. The figure 1.1 and table 3.1 provide Existing the fuel-wise and sector-wise generation Capacity 11561 3640 15201 capacity mix respectively in Rajasthan, as on Capacity 30 th June, 2014. addition by 2018-19 5520 625 6145 Figure 1.1: Generation capacity Fuel Mix Total Capacity by 2018-19 17081 4265 21346 Capacity Available out of Total capacity to meet the peak demand by 2018-19 11957 341 12298 Additional Capacity required to meet the peak demand of 16000 MW by 2018-19 3702

Source: CEA Further, GoR has planned coal based projects of 4520 MW in the states which includes Rajasthan has met a peak demand of 10,038 projects of 2920 MW in state sector ( i.e MW during 2013-14 and it is expected that Kalisindh TPS Unit # 3 & 4 (2 X 660 MW) & the peak demand of Rajasthan would be TPS Unit #1 & 2 (2 X 800 MW)) around 16000 MW by 2018-19 considering and projects of 1600 MW (Banswara TPS the additional energy requirement for Unit # 1 & 2 (2 X 800 MW)) under case -2. providing 24X7 power supply to the State. Also 3600 MW of renewable energy is also The present energy requirement is of the order planned to be available for the state by 2018- of 58.29 BU per year and is likely to increase 19. Although, there are issues of coal linkage to 89.6 BU per year by 2018-19. for these project, however, these coal based projects are important to meet the expected To meet the expected demand of the state, peak demand of the state. The list of projects capacity addition of 6145.15 MW is expected under construction and future projects are in the state by 2018-19 from under provided in table no – 3.2 & 3.3

12

Table 3.1: Existing Installed capacity (MW) (June 2014) Thermal Sector Hydro Nuclear NES Total Coal Gas Total STATE 987.96 4715 603.80 5318.80 - 23.85 6330.61 PRIVATE 0.00 2,800 0.0 2800.00 - 3616.30 6416.30 CENTRAL 645.13 1014.72 221.23 1235.95 573.00 - 2454.08 TOTAL 1633.09 8529.72 825.03 9354.75 573.00 3640.15 15200.99 % 10.7% 56.1% 5.4% 61.5% 3.8% 23.9% 100% Source: CEA

Table 3.2: Projects under construction Capacity Commissioning Name of project (MW) Schedule State sector Chhabra TPS Stage-I Ph2 250 Unit-4 – Dec 14(COD) Kalisindh TPS Stage-I unit-2 (in state sector) 600 Unit-2 – Dec 14 (Comm) Dec 14 (COD) Ramgarh RGTPP Stage-IV 160 Jan-17 and Mar-17 subject to finalization of gas prices STPS Stage –V unit 7&8 1320 Sept – 16 and Dec – 16 Chhabra TPS Stage -II unit 5 660 Sept – 16 Sub-total (State Sector) 2990 Chhabra TPS Stage –II Unit 6 (State Sector) 660 Conditional EC received* (Expected commissioning June- 2018) Partnership projects BBMB uprating 13.65 2014-15 Central sector Allocation Barh STPP Stage-1 (3x660) 186 2016-17 to 2017-18 Kol Dam HEP (4x200) 86 2014-15 to 2016-17 Barh STPP Stage-2 (2x660) 132 2014-15 RAPP Unit # 7 & 8 (2 X 700 MW) 700 2018-19 Parbati II HEP 86 2016-17 Kishanganga HEP 36 2016-17 Tapovan Vishnugarh HEP 56 2016-17 Kameng HEP 28 2017-18 Lower Subansiri HEP 46.5 2018-19 Sub-total (Central Sector) 1356.5 Private Sector Projects (Case -1) 500 2016-17 Sub-total (Private Sector) 500 Total ( Conventional ) 5520.15 NES Projects Wind/Solar/Biomass for the state 625 2014-15 to 2016-17 Grand Total 6145.15

13

Table 3.3: Future Projects Name of Project Capacity Commissioning Schedule Kalisindh TPS Stage-2 Unit # 3 & 4 2 X 660 MW 2018-19 subject to coal linkage (in state sector) Banswara TPS Unit # 1 & 2 (in state 2 X 800 MW 2018-19 subject to coal linkage sector) Banswara TPS Unit # 1 & 2 2 X 800 MW 2018-19 subject to coal linkage (Case-2) Projected capacity expected to be Solar & Wind Projects 3600 MW developed under JNNSM, Rajasthan Solar & wind energy policy by 2018-19 Grand Total 8120 MW

3.2. POWER PROCUREMENT COSTS The power purchase cost accounts for ~ 66 % of the total expenditure of distribution 3.3. ISSUES REGARDING COAL companies in FY 2013-14. These can further PROCUREMENT PLAN increase due to dependency on the imported (a) Unit 6 of Chhabra SCTPS of 1X660 coal on account of shortages in supply of MW domestic coal. The breakup of power purchase cost from This unit is expected to be commissioned by various sources is shown below: June’18. However conditional environmental clearance (EC) has been received for this unit, Source Average Unit on the basis of which four old units of Kota Rate Thermal Power Stations Unit-I to Unit-IV aggregating to 640 MW would have to shut Procured from State plants Rs. 3.78 per down and coal allocated to these units be used (RVUN) during 2013-14 unit for 660 MW CTPP Unit#6. Retirement of Average rate procured from Rs. 3.33 per Kota units is not desirable as the units have allotted CGSs during 2013-14 unit been operating at good efficiency and plant availability levels. Procured from exchange for the Rs 3.47 per last 3 year unit The EC for Chhabra unit-6 should be delinked Procured through bilateral Rs 3.77 per from the KTPS Unit-I to Unit-IV. Though contracts in the last 3 years unit coal for Chhabra Unit # 6 has been linked from enhanced mining capacity of 10 to 15 Procured through IPP’s in the Rs 3.80 per MTPA of RVUN’s ‘Parsa East & Kanta last 3 years unit Basan’ coal blocks, yet it requires EC for 15 MTPA capacity which will take long time. Power purchase cost of Rajasthan Less than Rs 4 /unit and is RVUN has already awarded order for competitively execution of this unit in 2013 and work for priced. this unit could not commence at site for want of Environment Clearance.

Mining Plan has been approved in Nov 2013 and enhanced mining capacity will not require any additional land. In view of above, MOEF

14

to consider to grant EC for unit 6 based on 15 MTPA approved mining Plan or Ministry of (ii) Coal Requirement Based on Coal Coal to grant tapering linkage of coal (3.25 Blocks Allotted for on Going Projects MTPA) for this unit. Parsa East & Kanta Basan Coal Block (b) Coal Requirement: Parsa East and Kanta Basan(PEKB) (i) Coal Requirement Based on Linkage coal blocks in the state of Chhattisgarh with CIL have been allotted to Rajasthan(RVUN) in June 2007 by Letter of assurance (LOA) / linkage Ministry of Coal, Govt. of India for quantity of RVUN’s post 2009 meeting coal requirement of Chhabra commissioned units i.e. Suratgarh TPS TPS (Unit# 3&4-2X250MW) & Unit # 6 (250 MW), Kota TPS Unit # 7 Kalisindh (Unit#1&2 -2X600MW) and (195 MW) and Chhabra Unit #1 & 2 (2 part coal requirement for STTPP X 250 MW) is for 65% PLF which Unit#7& 8 and CTPP Unit# 5&6. need to be enhanced. Apart from this, Mining plan of Parsa East and Kanta in order to achieve higher efficiency of Basan coal blocks (10 MTPA) was the plants materialization of coal approved by MoC in July, 2009. supply need to be increased to 100 % of LOA. Ministry of Coal, GoI in Feb 2012 accorded ‘in principle’ approval to Further, a statement showing coal allow the use of coal mined from ‘Parsa requirement, availability, shortage and East & Kanta Basan’ coal blocks in the additional coal requirement in Million Super Critical Projects of 2x660 MW Tonnes Per Annum (MTPA) based on Chhabra (Unit#5&6) and 2x660 MW linkage with CIL is as under; Suratgarh (Unit # 7 & 8) after considering mining capacity FY14- FY15- FY FY17- FY18- Particulars enhancement from 10 MTPA to 15 15 16 16-17 18 19 MTPA and directed RVUN to furnish a Domestic revised mining plan of enhanced Raw Coal 19.7 19.7 19.7 19.7 19.7 Requirement capacity. Subsequently, Revised (A) Mining Plan of Parsa east and Kanta Basan (15MTPA) coal blocks was Coal 16.4 16.6 16.8 17.1 17.1 approved by Ministry of Coal in Nov Linkage (B) 2013. The requirement of coal for these super critical projects will be from July Materializati 14.7 14.9 15.2 15.3 15.3 2016. on 90% (C) GoR need to pursue for expediting Shortfall in Environment Clearance from MoEF for Raw coal as 3.16 2.95 2.72 2.50 2.50 per linkage enhanced mining capacity from 10 (E)=(A-B) MTPA to15 MTPA in respect of Parsa Additional East & Kanta Basan Coal Blocks. GoI coal to facilitate in expediting the requirement 3.16 2.95 2.72 2.50 2.50 based on environment clearance for 15 MTPA linkage with capacity. CIL

15

Crores with Railways in the month of Kente Extn. Coal Block March, 2011. The construction work of new rail line has commenced. Ministry of Coal, Govt. of India had allocated Kente Extn. Coal block to Rajasthan Vidyut Utpadan Nigam RVUN in August 2013 subject to certain (RVUN) had applied to MoC for grant of clarifications/ confirmations. The long term linkage of coal for Kalisindh required clarifications/confirmations on (Unit 3 & 4) & Banswara (Unit 1 & 2) above were furnished in Oct /Nov 2013. State sector projects on 19.01.2010 and The formal allotment letter in this regard subsequently applied for allocation of is still awaited and RVUN has not been coal blocks on 14.12.2012 & 30.01.2013 able to proceed further for obtaining for Kalisindh & Banswara State sector necessary clearances, licenses and Projects. MoP has already recommended approvals etc. from the concerned on 05.05.10 to MoC for allocation. authorities. The coal from this coal block Ministry of Coal has allocated a small shall be used in meeting balance captive Kente Ext coal bock on requirement of coal for Suratgarh Super 05.08.2013 against the above application Critical TPP Unit 7&8 (2x660 MW) and dated 30.01.2013 for meeting the coal Chhabra Super Critical TPP Unit 5&6 requirement of under construction (2x660 MW). projects only & not for these new

projects. GoR need to pursue for early issuance of formal allocation letter from Ministry of Coal in respect of Kente Extension Coal RVUN had also applied to MOC for grant Block. GoI to facilitate in expediting the of long term linkage of coal for IPP same. project on 16.04.2009 and for allocation of coal block on 30.01.2013. Ministry of (c) Allocation of Coal Linkage/Coal Blocks Power has already recommended for for Future Power Projects grant of coal linkage for IPP project to Ministry of Coal on 20.08.2010. Government of Rajasthan has sanctioned Environmental Clearance could not be Supercritical Power Project at Kalisindh granted by MOEF for want of assurance (2x660 MW Unit# 3&4) & Banswara of Long Term Linkage of Coal/allocation (2x800 MW Unit# 1&2) under State of Coal Block for these State sector & Sector on 24.06.2010 & one Supercritical IPP projects. Power Project at Banswara (2x800 MW) under Case-2 Tariff based Competitive GoR need to pursue for allocation of new Bidding Route (IPP) on 13.01.2009. coal block(s) / grant of Long Term Linkage of Coal for execution of these The Govt. of Rajasthan has entered into a power projects. GoI to facilitate in MoU with Ministry of Railways, Govt. of expediting the same. India in 2011 for construction of new broad gauge Rail Line between Ratlam (MP) and Dungarpur (Rajasthan) via Banswara. Rail Link project cost is Rs 2083 Crores out of which 50% cost of

project and 100 % cost of acquisition of land in Rajasthan & MP (approx. Rs. 1200 Crores) will be borne by GoR. RVUN has already deposited Rs. 200

16

S. PARTICULAR 2 X 660 MW KALISINDH 2 X 660 MW BANSWARA No. S (UNIT-1 & 2) (UNIT-3 & 4) 1 Land Sufficient 216 Ha land of stage-I is Total 462.52 Ha land has been available and some additional land will identified .Section-4, Section-6 and be acquired if needed Section-9 issued for acquisition of 238.05 Hectare private land. Award has been issued by land acquisition officer but land owners are not accepting cheques. 2 Water 1320 Mcft water has been allocated by 2000 Mcft water has been allocated WRD from Kalisindh Dam for which by WRD from Mahi Dam. height of the Kalisindh Dam to be raised from RL 316 M to RL 319 M.

3 Term of Term of Reference (ToR) granted by Term of Reference (ToR) granted by Reference (ToR) MOEF on 10.12.2013. MOEF 07.12.2011. 4 Rapid Completed REIA Could not be started/ carried Environment out due to resistance / agitation by Impact local people. Assessment (REIA) Studies 5 Public hearing – Conducted at site Jhalrapatan by Not yet scheduled Required for Rajasthan State Pollution Control Board grant of on 8.7.2014. Environment Clearance(EC) by MoEF

(d) RAMGARH GAS TPS EXTN. ST- IV subject to finalization of Gas prices by (110 MW GT + 50 MW STG) ;- MoP&NG, GoI.

RVUN has already awarded Boiler GoI is requested to finalize Gas price for Turbine Generator (BTG) contract to M/s. Ramgarh Stage-IV Gas based Power BHEL for 160 MW Ramgarh (Stage-IV) Project at discounted prices to be supplied in Sept, 2012 and material worth Rs. 185 from isolated gas fields in Jaisalmer Crs has been supplied to site up to Nov, (Rajasthan) and also not to increases gas 13. Order for Balance of Plant (BoP) is prices beyond USD 5 per MMBTU. under finalization and expected to be awarded by Oct, 2014. GAIL has confirmed the availability of 0.75 MMSCMD gas for Ramgarh Stage-IV but finalization of gas price is under consideration at Ministry of Petroleum & Natural Gas. Units are now scheduled to be commissioned by Jan, 17 and Mar , 17

17

3.4. ACTION PLAN – STATE b. To facilitate allocation of new coal block(s) / grant of Long Term Linkage of Coal for execution of the power 1. To complete the generating capacities of projects in the state for Kalisindh State and to monitor the Central Sector & (Unit 3 & 4) & Banswara (Unit 1 & 2) Private Sector projects as per following Roll out Plan- c. To facilitate Environment Clearance from MoEF for enhanced mining Power for FY FY FY FY FY capacity from 10 MTPA to15 MTPA all - Roll 2014 2015- 2016- 2017- 2018 Total out Plan -15 16 17 18 -19 in respect of Parsa East & Kanta Generation Basan Coal Blocks. (State 850 110 2030 660 3650 Sector d. To permanently delete the names of U/C) Power Stations of RVUN from the list Future Subject to State 2920 coal of Thermal Power Stations identified Projects linkage for import of coal and Ministry of Central 145. 746. 0 264 214 1370.15 Coal to allocate full Annual Sector 65 5 Private Contracted Quantity of coal to all 500 500 sector power stations of RVUN e. Ministry of Coal, Govt. of India had 2. To take up the matter of coal linkage / allocated Kente Extn. Coal block to environment clearance with Ministry of Coal RVUN in Aug-2013. Ministry of and MOEF for the ongoing and future Power, Govt. of India is requested to projects as per requirement. extend cooperation for early issuance of formal allocation letter from 3. To procure more power, if required, from Ministry of Coal. the market to meet the demand for providing f. To finalize Gas price for Ramgarh 24x7 power in the state. Stage-IV Gas based Power Project at discounted prices to be supplied from isolated gas fields in Jaisalmer 3.5. GOI INTERVENTION (Rajasthan). a. The Environment Clearance for Chhabra unit-6 should be delinked from the KTPS Unit-I to Unit-IV and Though, Govt of India would make all tapering linkage for coal need to be possible efforts within the framework/ provided for by Ministry of Coal or policies to assist the Govt of Rajasthan as grant Environment Clearance for requested above, but if, there is any CTPP unit 6 based on approved problem in meeting the above requests of mining Plan for 15 MTPA for Parsa the State Govt , a back up plan would be East and Kanta Basan. worked out by State Govt to procure adequate power to meet the projected requirement.

18

3.6. FUND REQUIREMENT 3.7. RENEWABLE ENERGY PLAN

Estimated fund requirement for under Rajasthan is endowed with abundant construction Projects of Capacity 3650 MW potential of renewable energy sources will be Rs. 28993.51 Crores with debt equity particularly wind and solar. State has ratio 80:20 and for Future Projects of Capacity already issued liberal policies for 2920 MW fund requirement will be Rs. promotion of renewable energy 18980.00 Crores with debt equity ratio 70:30. generation.

Till now RVUNL is operating its business on It is proposed to set up renewable NO PROFIT NO LOSS basis, and does not energy plants of about 10,240 MW claim Return on Equity. Thus no internal capacity in the state by 2018-19. Out of surplus is available for investment on this, 7500 MW would be from solar & construction projects. Now for under 2740 MW from wind. construction projects, the cost of the project is

financed by way of 30% Equity contribution by The solar capacity of 7500 MW would the State Government and the balance 70% is be developed as under- financed through LOAN from the Financial

Institutions. RUVNL is 100% Government of • Through VGF based competitive Rajasthan undertaking. bidding – 1000 MW The details of fund requirement are as under- 6500 MW Generat Total Expen FY FY FY FY FY • Open access scheme within state ion Cost diture 15 16 18

of up to 17 19 and other than state /captive use (RVUN) projec Mar - • REC (solar) mechanism ts 14 • Nation Solar Mission Ph-II, Batch I U/C 28994 13201 4717 5100 5024 837 113 & II Projects • Nation Solar Mission Ph-III, Batch I

Future 18980 - 500 5000 5000 5000 3480 Projects Out of 7500 MW Solar capacity, 1000 MW is planned to be set up for the state Total 47974 13201 5217 1010 10024 5837 3593 through competitive bidding on VGF base @ Rs 2.5 Crores / MW to make available solar power at a lower rate of Rs 5.5 / unit to ensure less burden on the state discoms. The other 6500 MW of solar projects will be developed by IPPs.

2740 MW from wind – These projects will be developed by IPPs as per Govt of Rajasthan wind Policy up to the RPO target set up by SERC. As such no funding from State or Central Govt would be required from these projects.

19

(Rs in crores) It is proposed that 4225 MW (625MW Renew able FY FY FY FY FY U/C +3600 MW) of renewable energy Total energy 14-15 15-16 16-17 17-18 18-19 will be available for the state for its own use. Wind 3000 3000 3000 3720 3720 16440

Table 3.4: Solar year-wise proposed capacity Solar 3500 7000 10500 14000 17500 52500 addition plan S. No. FY Capacity Addition (MW) Total 6500 10000 13500 17720 21220 68940 1 2014 -15 500 2 2015 -16 1000 3 2016 -17 1500 4 2017 -18 2000 5 2018 -19 2500 Action plan – State Total 7500 MW The state has to ensure the completion of renewable generating capacities in the state as Table 3.5: Wind year-wise proposed per following Roll out Plan- capacity addition plan

S. No. F.Y Capacity Addition (MW) Renewable FY FY FY FY FY 1. 2014-15 500 energy 14- 15- 16- 17- 18- Total 2. 2015-16 500 15 16 17 18 19 3. 2016-17 500 Solar 4. 2017-18 620 Capacity MW 500 1000 1500 2000 2500 7500 5. 2018-19 620 Addition Total 2,740 Wind Power MW 500 500 500 620 620 2740 Addition Fund requirement

For developing 6500 MW solar and 2740 MW 3.8. GOI INTERVENTION wind based renewable energy plants in the To consider sanctioning the Viability Gap state, no Grant / financial assistance is required Fund (VGF) @ Rs.2.5 Crores / MW for 1000 from central Govt as all these projects will be MW so that the solar bidding may be carried developed by private investors/ IPPs. out on VGF, fixing the tariff at Rs. 5.45 /KWh However, total fund required for these for developers following similar guidelines proposed projects are as under – that have been used for the JNNSM Phase –II Batch-1 procurement process.

GoR may submit their proposals to MNRE for VGF funding as per norms of prevailing schemes.

20

4. TRANSMISSION PLAN

4.1. INTER -STATE TRANSMISSION SYSTEM strong reliable ISTS network has been Presently about 8200 ckt km of transmission established. Major 400kV transmission lines lines & 9 nos. of 400/220 kV substations with connecting Rajasthan to other states is listed a total transformer capacity of about 6855 below: MVA are existing in Rajasthan under the Inter From Haryana: State transmission system. In Rajasthan, 3 Nos. of existing Central sector generating ‹ Bhiwadi – Hissar 400kV S/c stations (Anta CCGP, RAPP-B and RAPP-C) ‹ Gurgaon – Bhiwadi 400kV S/c with a cumulative generation capacity of ‹ Manesar – Neemarana 400kV D/c 1300MW is being evacuated by ISTS. The details of Inter State Transmission system, to From Uttar Pradesh: transfer power from these Inter-state ‹ Balia - Bhiwadi 2500 MW HVDC generating stations are listed below: Bipole Anta CCGP Generation: ‹ Agra - Bassi 400kV S/c ‹ Anta-RAPP-C – RAPP-B 220 kV S/c ‹ Agra - Jaipur 400kV D/c ‹ Anta - Bhilwara-I – 220 kV D/c ‹ Agra - Bhiwadi 400kV D/c ‹ Agra - Sikar 400kV D/c ‹ Anta – Sawaimadhopur - Dausa 220 kV D/c From Gujarat (WR) RAPP-B (2x220MW) Nuclear Generation: Zerda –Kankroli 400kV D/c (one ckt via ‹ Rapp-B - Anta 220 kV S/c Bhinmal) From Punjab ( NR) ‹ RAPP – Chittorgarh 220 kV D/c Moga- Bhiwadi 400 KV D/C

‹ RAPP – Udaipur 220 kV S/c RAPP-C (2x220MW) Nuclear Generation: Presently, 9 Nos of 400/220 KV Sub-stations with 6855 MVA Transformation Capacities ‹ Rapp-C - Kota 400kV S/c have been established under Inter State

Category in the State. ‹ RAPP-C – Kankroli 400kV D/c Table 4.1 shows the substation and their For import of Rajasthan’s share of power transformation capacity. from central sector generations outside Rajasthan, a Table 4.1: Substations and their transformation capacity

Sl. No Name of the S/S Voltage ratio No. of Trf. MVA Capacity Tot. trf Capacity

1 Bassi 400/220 2 315 630

2 Jaipur South 400/220 2 500 1000

3 Kota 400/220 2 315 630

21

4 Kotputli 400/220 2 315 630

5 Bhiwadi 400/220 3 315 945

6 Neemarana 400/220 1 315 + 500 815

7 Sikar 400/220 2 315 630

8 Bhinmal 400/220 2 315 630

9 Kankroli 400/220 3 315 945

Total MVA Capacity 6855

To facilitate drawl of power by Rajasthan and b) RAPP–Kota-Jaipur 400kV D/c– to meet projected peak load of 16000 MW by (480ckms) and RAPP-Shujalpur 400kV 2018-19 a robust Inter-state transmission D/c-(500ckm): system (ISTS) has been planned and is under To improve evacuation of power from RAPP construction. Further for evacuation of power generation complex to load centres of from state generating stations as well as for Rajasthan and to facilitate evacuation of transfer to various load centres within power from proposed RAPP-C (2x700MW) Rajasthan, a vast Intra State Transmission generation - a 400kV D/c from RAPP Network has been developed by Rajasthan generation complex to Jaipur with one circuit Rajya Vidyut Prasaran Nigam Ltd via Kota has been proposed and is to be taken (RRVPNL). ISTS projects under construction up by POWERGRID. are as below:

RAPP-Shujalpur 400kV D/c would connect 4.1.1. ISTS Projects under construction RAPP generation complex with Shujalpur in Madhya Pradesh, Western Region. The line a) Gwalior–Jaipur-Bhiwani 765kV 2xS/c would help Rajasthan to receive power from line – 1100 Ckm WR - as and when need arises. Further, when Rajasthan is surplus, the power can be Construction of 1100 circuit km of 765kV exported to WR. The line is being taken up line is under implementation as part of under Tariff Based competitive bidding and is various schemes. Gwalior – Jaipur 765 kV expected by November 2016. lines would facilitate import from the pit head coal based generating stations located in c) State-of-the-Art Static Var Eastern and Western regions. From these lines Compensator (SVC) at Kankroli power of the order of about 2000-3000 MW Kankroli is a major substation located in the can be transferred to Rajasthan. Similarly, south western part of Northern Grid. It is Jaipur – Bhiwani 765 kV lines would connected to RAPP-5&6 nuclear generations facilitate import of power from the various by a 400kV D/c line. Further, it is also hydro power stations located in the states of connected to Western Region via Kankroli- Himachal and J&K. During off peak period, it Zerda / Bhinmal 400kV D/c line. However the would facilitate export of power from Kankroli area faces voltage constraints. Rajasthan. Accordingly (+) 400 MVAR / (-300) MVAR Static Var Compensators has been proposed at Kankroli S/s. The Static Var compensator

22

shall help in controlling the voltage and Jodhpur & Bikaner) and Southern (Banswara providing reliable supply to the area. & Pratapgarh) parts of Rajasthan.

Details of pocket wise wind and solar d) System strengthening capacity in Rajasthan for which the To meet the growing power demand of transmission system has been planned are Rajasthan - various augmentation and system provided in Table 4.3 strengthening activities are proposed to be Table 4.3: Pocket wise Wind Generation in carried out progressively such as Rajasthan augmentation of transformer capacity by 500 Existin MVA at Bassi 400/220 substation, Sikar – Additio g Total Jaipur 400 kV D/c- 340 ckm and Sikar – S.N n by Pocket (Mar’1 (MW Ratangarh 400 kV D/c-160 ckm lines are also o 4) (2018- ) under implementation. 19) (MW) e) Transmission System for integration of 1 Jaisalmer/Barmer 2254 2240 4494 Large Scale Renewable 2 Jodhpur/Bikaner 391 60 451 In Rajasthan, existing renewable energy Banswara/Pratapg capacity is about 3,524 MW (As on Mar’14). 3 141 604 745 The transmission system has been planned for arh 7333 MW out of the proposed capacity of Other parts of 4 12 129 141 10,240 MW renewable capacity by 2018-19 Rajasthan which is mainly through solar and wind generation. The additional evacuation system Total(MW) 2798 3033 5831 for balance RE capacity, if required, will be planned and implemented in due course of time in consultation with State Govt. Table 4.4: Pocket wise Solar Generation in Table 4.2: Details of Renewable capacity Rajasthan for which Tx system has been planned in Addition 2018-19 Existing by Total S.No Pocket (Mar’14) Total (2018- (MW) (MW) Wind Solar Renewable 19) Capacity* 1 Jaisalmer/Barmer 70 1444 1514 Existing RE capacity (MW) 2798 726 3524 2 Jodhpur/Bikaner 656 2856 3512 (As on Mar’14) Transmission Total (MW) 726 4300 5026 system planned for capacity 3033 4300 7333 Addition by Based on the capacity additions, it is expected (2018-19) that Rajasthan may have more RE capacity Total (MW) 5831 5026 10857 than required for meeting their Renewable Purchase Obligations (RPO). Further, *Excluding Biomass Rajasthan may not be able to absorb the entire RE energy locally - particularly during off- Renewable capacity in Rajasthan is mainly peak period - when renewable generation is at confined to Western (Jaisalmer, Barmer, its peak. In addition, the IEGC stipulates the renewable energy plants as “MUST RUN”

23

and not to be subjected to “merit order dispatch” principles. Figure 4.1Proposed ISTS Transmission To address above aspects and the Corridor for RE in Rajasthan intermittency nature of renewable energy generation, development of strong and reliable grid interconnections is important. There is a need to strengthen Interstate transmission which shall facilitate transfer of power outside the RE resource rich states.

In order to facilitate integration of large scale renewable generation capacity by 2018-19, a comprehensive transmission plan comprising of intra state and interstate transmission system strengthening has been evolved as a part of “Green Energy Corridors”. As part of this corridor, under ISTS four Nos. of 765/400kV substation would be established in Rajasthan i.e. at Chittorgarh, Bhadla, Ajmer & Suratgarh.

The corridor envisages high capacity 765kV D/c lines which would traverse across To facilitate pooling of power from various Rajasthan from Southern to Northern part of RE generations at various points of common Rajasthan as well as from Western to Central coupling (PCC), transfer to various load part. The corridor would connect major centres and interconnection with the ISTS renewable pockets in Rajasthan and would points - the intra state strengthening scheme facilitate export of power from Rajasthan. has been evolved by RVPN / PGCIL Further the corridor would be integrated with ISTS station at Moga. This would facilitate Summary of proposed Inter-state transmission Rajasthan to integrate with Hydro generation system strengthening schemes - for which complex of NR for facilitate balancing investment is to be made as a part of Green requirement. An additional ISTS Energy Corridor is as shown below: strengthening which includes establishment of Table 4.5: Summary of proposed Inter- new 400/220kV substation at Akal-II and its State Transmission System connectivity with 400 kV Jodhpur (new) and Bhadla (new) Substation is also proposed. As Length Substation part of this corridor 400kv Jodhpur is also S.No Item capacity proposed to be connected to high capacity (Ckm) (MVA) 765/400 kv Ajmer substation which would be connected to planned Green Energy 1 Inter State 3650 15000 Corridors.

The details of inter-state schemes (ISTS) for Rajasthan as a part of green energy corridor is

as under:

24

Interstate transmission scheme for * The system was discussed and approved in 32 nd Rajasthan for integration of renewable standing committee meeting of NR. However, it generation as part of Green Energy was decided that this system shall be taken up for Corridor implementation only after receipt of application for Connectivity and LTA for sufficient quantum from Solar/ wind generation developers a) Transmission scheme to be implemented around Bhadla area by POWERGRID • Ajmer (New)- Ajmer (RVPN) 400kV c) Additional Inter State Transmission D/c (Quad) Scheme proposed for renewable • Chittorgarh (New)- Chittorgarh generation projects during 2017-19 in (RVPN) 400kV D/c (Quad) Rajasthan – The System is yet to be • Chittorgarh – Ajmer(New) 765kV D/C approved • Establishment of 2x1500 MVA, • Establishment of 4x500 MVA, 765/400kV S/s at Chittorgarh 400/220kV S/s at Akal-II (new) • Establishment of 2x1500 MVA, • Akal - Bhadla (New) 400 kV D/c 765/400kV S/s at Ajmer (New) (Quad) • Akal (New) - Jodhpur (New) 400 kV Estimated cost (a): 1663 Crores D/c (Quad) • Jodhpur (New) - Ajmer (New) 400 kV D/c (Quad) b) Implementation agency is yet to be finalized Estimated cost (c): Rs 1700 Cr

• Ajmer(New) – Suratgarh (New) Total Estimated cost (a+b+c): Rs 8600 Cr 765kV D/c

• Suratgarh(New)-Moga(PG) 765kV f) Renewable Energy Management D/c Centres (REMC) • Suratgarh (New)- Suratgarh (existing) Renewable generation especially wind is 400kV D/c (Quad) characterized by its intermittent & variable • Bhadla (New)-Ajmer (New) 765 kV characteristics. Therefore other controlling D/c* infrastructure such as forecasting of renewable generation, balancing • Bhadla (New)-Bhadla (RVPN) 400 kV infrastructure, dynamic compensation, D/c (Quad)* establishment of Renewable Energy • Bhadla (New)-Pokhran New (RVPN) Management centres (REMC), at 400 kV D/c (Quad)* SLDC/RLDC/NLDC level, real time measurement/monitoring, Energy storage etc. • Establishment of 2x1500 MVA, have also been identified as part of the green 765/400kV S/s (AIS) at Suratgarh energy corridors. (New) • Establishment of Renewable Energy 765/400/220kV (765/400 kV-2x1500 Management Centres (REMC) has also been MVA & 400/220kV- 2x500MVA) proposed for the State of Rajasthan substation at Bhadla (New)* considering the high level of renewable Estimated cost (b): 5237 Crores penetration. REMC shall perform real time

25

monitoring of renewable generation as well as renewable generation forecasting exclusively ‹ Rs 1663 Cr (implemented by on different time scales. Integration of REMC POWERGRID with 70% loan with existing control centres would facilitate and 30% equity) scheduling & dispatch of RE power. Further, ‹ Rs 6937 Cr (Implementing in order to facilitate real time dynamic state agency yet to be tied up) measurement at RE pooling stations or point of common coupling, installation of PMU/PDC and associated Fibre optic The debt component (70%) of transmission communication links are considered to be system being developed by POWERGRID established in a unified manner. (Rs 1663 Cr) is funded through concessional loan from KfW, Germany. The implementing agency (ies) for balance transmission system g) Adequacy of ISTS (Rs 6937 Cr) is yet to be identified for which funding would be through own resources and external borrowing. However to rationalize • The planned ISTS system is sufficient the transmission tariff soft loan from to meet the power transfer requirement multilateral funding agencies is required. In of Rajasthan by 2018-19 to meet the such cases sovereign guarantee is required projected demand of about 16000MW. from GoI. • Interstate transmission system for integration of renewable generation is adequate for 7333MW capacity Action Points- CTU addition, however in case of for

increased quantum, additional • transmission system is required, and POWERGRID/Implementing agency the same would be planned after to ensure development of interstate discussion with the State Govt. transmission as indicated above Note: The proposed tr. system is evolved considering a progressively by 2018-19 particular load generation scenario and network configuration, which may change from time to time • State nodal agency shall ensure that depending upon actual load growth, generation Renewable generation developer apply capacity addition, network development etc. In case of any change in the above consideration, the proposed for connectivity/Long term access for transmission system needs to be reviewed. its integration in the ISTS.

• To plan and develop the additional h) Fund requirement : transmission system (if required) for Total estimated cost in Rajasthan for Inter evacuation of anticipated RE power State Transmission Network strengthening (ISTS) is Rs 12,216 Crs. The inter-state more than 7333 MW in the state. scheme of Rs 3616 Cr is under • In order to integrate large scale implementation, therefore balance (8600 Crs) variable generation and address its investment is required for ISTS strengthening. inherent characteristics of intermittency & variability, there is a ‹ Interstate: Rs 12,216 Cr need of addressing it through suitable • Rs 3616 Cr (for schemes listed under mitigating measures like balancing & 4.1.1(a) to (d)) [Under control infrastructure. Balancing implementation] infrastructure includes enlargement of • Rs 8600 Cr for Green energy corridor balancing area through strong grid i.e. integration of renewables interconnection, flexible generation

26

resources like Pumped storage plants 4.2. INTRA STATE TRANSMISSION (PSP), large scale battery storage etc. SYSTEM In addition control infrastructure like Renewable forecasting system, To meet with a projected load demand of Renewable Energy Management 16000 MW by 2018-19 a robust intrastate Centre (REMC), Dynamic reactive transmission system has been planned and compensation, Real time monitoring same is under various stages of etc. are also required to be provided. implementation . To address the issue, a technical consultancy on aspects like strategy & 4.2.1 Existing System road map for providing balancing infrastructure, assessment of balancing The transmission network that presently capacity of control areas & measures caters to the load across the State as on 31- to enhance it, technological roadmap March-2014 is as follows: etc. is being carried out as part of technical assistance (upto Eur 2 462 Nos. of EHV sub-stations having million grant) from GIZ, Germany to Capacity: 53248 MVA along with 31092 Ckt. be completed in 2014-15. kM of associated transmission lines consisting of - GOI Intervention ∑ 9 Nos of 400 kV grid substations GoI may identify implementing agency (Heerapura – Jaipur, Ratangarh, Bikaner, (ies) for development of balance ISTS Jodhpur, Jaisalmer, Barmer, Hindaun, (Rs 6937 Cr) for integration of Bhilwara & Merta City) with 6420 MVA renewable. capacity and 3278 ckt kM. of associated lines.

∑ 93 Nos of 220 kV grid substations with 22105 MVA capacity and 12236 ckt kM. of associated lines. ∑ 360 Nos of 132 kV grid substations with 24724 MVA capacity and 15153 ckt kM. of associated lines. 4.2.2 Under Construction/ Planned Intra State Transmission System:

∑ 2 Nos. of 765 kV grid substations at Anta and Phagi (Jaipur) with 7500 MVA capacity are under construction.

∑ 6 Nos. of 400 kV grid substations at Chittorgarh, Ajmer, Babai, Jodhpur (New), Ramgarh and Bhadla with 4965

MVA capacity are under construction/ implementation. 2 Nos. of 400kV grid substations at Banswara & Jaisalmer-2 with 2000 MVA capacity planned for implementation and 4 nos. of 400kV GSS with 4000 MVA capacity are being identified.

27

The details of proposed physical plan are as follows:

Table 4.6: Proposed physical plan 2014-15 to 2018-19

Voltage Project Unit 2014-15 2015-16 2016-17 2017-18 2018-19 Level No./ 2/3000 0/4500 0/0 0/0 0/0 765 KV MVA Ckm. 425 * 0 0 0 0 No./ 1/315 2/945 0/630 1/1000 2/2000 400 KV MVA Intra-State Ckm. 271 1618 0 150 300 Transmission No./ network 6/940 6/720 8/1240 7/1300 5/1160 220 KV MVA Ckm. 1219 334 594 321 273 No./ 20/725 16/475 4/100 13/400 13/425 132 KV MVA Ckm. 1016 659 289 325 325 No./ 0/0 0/0 0/0 0/0 0/0 765 KV MVA Ckm. 0 0 0 0 0 No./ 0/0 0/0 3/1315 1/2815 2/2000 400 KV MVA Green Energy Ckm. 0 820 520 1490 1570 Corridor No./ 2/260 2/260 0/0 1/160 3/640 220 KV MVA Ckm. 299 504 20 230 390 No./ 132 KV 0/0 0/0 6/150 7/150 7/200 MVA

Ckm. 10 32 300 364 640

* 425 kM of 765 kV lines already completed and charged on 400 kV voltage level which will be upgraded to 765 kV voltage level during 2014-15.

All the above schemes are approved except 4 Projects under Tariff Based Competitive nos. 400kV GSS, 4000 MVA with 600kM Bidding (TBCB): transmission lines, 1 no. 220kV GSS, 320 MVA with 100 CkM transmission lines and In addition to the planned transmission system 18 nos. 132kV GSS, 450 MVA with 625 cKM mentioned above, the following projects are transmission lines. These schemes will be proposed to be implemented through Private approved & constructed in phased manner for participation wherein the entire investment is evacuation of power from generating stations to be made by the private parties/developers: (RE and conventional sources), for system strengthening and normal development works. (a) There are 3 projects which are under advanced stage of implementation under TBCB mode as per following details:

28

Table 4.7: Projects under Tariff Based Crores has also been identified which is likely Competitive Bidding (TBCB) under to be implemented through TBCB or through advanced stage of implementation TBCB with VGF support. S Name of GSS with Devel sched Est . associated lines oper uled Cost 4.2.3 Investment for intra state N com ( Rs in o missi transmission network: crores) . oning Total investment of Rs 11,530 Crs: 400kV GSS at Deedwana GMR 2014- 284.12 1 . with following lines: 15 • Rs 6,848 Crs for intra state system i. 400kV S/C Bikaner- (incl. cost of Augmentations, Deedwana line SCADA, IT items, establishment of ii. 400kV S/C Ajmer- metering , communication & data Deedwana line iii. 220 kV D/C control centres, ERP, RMU, PLCC Sujangarh-Deedwana equipment etc.) line • Rs 4,682 Crs for Green energy 400kV GSS at with GMR 2014- 188.31 corridor (incl. Rs 1018.31 Crs 2 scheme proposed under KFW . 400kV S/C Hindaun- 15 Alwar line funding) 220kV GSS at Nawalgarh EMC 2015- 36.27 3 . with following lines: O 16 i. 220kV S/C Sikar- The funding for the above investment will be Nawalgarh line arranged by borrowing from financial ii. 220kV Nawalgarh- institutions with required equity support Jhunjhunu line from GoR. The recovery of the above investment will be done through wheeling charges which will be factored in the tariff. (b) The following three projects have also

been identified and proposed to be implemented through TBCB with VGF Details of above investment for intrastate support upto 2018-19: transmission network are given at Annexure – Table 4.8: Projects identified and proposed IV to be implemented through TBCB through 4.2.4. Adequacy of State Transmission VGF funding upto 2018-19 system - Rajasthan Transco

Est Cost The above proposed transmission S. Name of GSS with associated lines (Rs in system will be capable of meeting No. crores) projected peak load of 16000 MW 400kV GSS at Jaipur (North) with 1 upto 2018-19 and RE power of about 400kV D/C Babai-Jaipur (North) 221.81 . 10800 MW (3524 MW existing and line. 2 400kV D/C Bikaner-Sikar(PGCIL) 7333 MW addition by 2018-19). The 265.00 . line. additional transmission system (if 3 400kV S/C Suratgarh (STPS) - required) for evacuation of anticipated 157.79 . Bikaner line. RE power more than 10800 MW shall also be identified, approved and (c) Apart from the above, one more project implemented as per system of 400kV D/C Udaipur-Jodhpur line (490 requirement matching with the RE ckM) with 400/220kV, 630 MVA GSS at generation. Udaipur having estimated cost of Rs. 379.53

29

of transmission charges in the State, grant from Govt. of India is required from National Clean Energy Fund 4.2.5 Action Points - Rajasthan Transco (NCEF) and Clean Technology Fund (CTF).

GoR may submit their proposals to 1. The proposed transmission system MNRE for funding as per norms of upto 2018-19 needs to be implemented prevailing schemes. as per schedule for ensuring 24x7

power supply in the State. 2. To overcome the operational practical difficulties in injection of RE power 2. The funding for implementation of due to intermittency and variability, Intra State transmission system suitable balancing mechanisms are amounting to Rs. 6848 Crores shall be required to be installed. A Policy in timely arranged/tied up wherein 30% this regard would be formulated in equity support shall be provided by consultation with CEA/CERC. Govt. of Rajasthan.

3. The funding for implementation of transmission system for Green Energy Corridor (Rs 4,682 Crs with 30% equity support from Govt. of Rajasthan) shall also be arranged by Rajasthan Transco wherein 40% Grant/Aid (Rs. 1874 Crores) has been proposed to be provided by MoP from National Clean Energy Fund (NCEF) and Clean Technology Fund (CTF).

4.2.6 GOI intervention 1. The transmission company of the State (i.e. RVPN) has developed transmission system through its own resources for evacuation of RE generation by incurring huge investment. Due to low Capacity Utilization Factor (CUF) of the order of (18-22%) of RE generators. the incidence of transmission charges is very high on consumers/generators. Therefore, there is need to provide support for developing evacuation system for promoting RE generation. For implementation of transmission system for Green Energy Corridor Projects and to avoid high incidence

30

5. DISTRIBUTION PLAN

5.1. EXISTING DISTRIBUTION SYSTEM 5.2. SCHEMES UNDER

IMPLEMENTATION At the end of March 2014, the distribution network of Rajasthan consists of 2,40,203 ckt km low tension lines, 3,56,641 ckt km 11 kV RAPDRP lines and 47,293 ckt km 33 kV lines with a Government of India has launched 1,63,017 Km network of AB cables. Restructured-Accelerated Power There are 4585 No of 33 kV substations and Development and Reforms Programme (R- 11, 79,684 Nos of 11/0.4 kV distribution APDRP) as a central sector scheme to transformers. The total transformer capacity is encourage energy audit and accounting 20,763 MVA at 33 kV level and 34,937 MVA through IT intervention and to reduce the at 11 kV level. HT to LT ratio has increased AT&C losses upto 15%. The focus of R- substantially from 0.92 in FY 05 to 1.68 at the APDRP Scheme is on actual demonstrable end of FY 14. performance by utilities in terms of sustained In Rajasthan, at present, there are about 1.14 AT&C loss reduction. Projects under the Crores of electricity consumers including scheme are being taken up in two Parts. Part- about 12.0 lacs under agriculture category. A includes the projects for IT applications for The category wise break up of consumers, per energy accounting / auditing, GIS, consumer unit tariff, Billing & collections in the state is indexing, SCADA & IT based consumer given at Annex-V service centres etc. and Part-B includes regular distribution strengthening projects All categories of consumers in the state are including separation of agricultural feeders given supply without load shedding. After from domestic and industrial ones and High executing virtual feeder separation in rural Voltage Distribution System (HVDS) etc. areas in the year 2008, the State has been supplying 24x7 power to the rural domestic Under Part-A of R-APDRP, 87 projects at an consumer. For agriculture consumers, the estimated cost of Rs 315.95 Crores have been power supply is being given 6.5 hours in day approved for the state of Rajasthan and Rs block and 7 hours at night block. 130.25 Crores have been disbursed till date. Part-A SCADA projects for 5 towns for the However, during the preceding 4-5 years, the states have also been sanctioned at an distribution system has suffered due to lack of estimated cost of Rs 150.90 Crores and Rs maintenance and lack of supervision resulting 45.28 Crores have been disbursed into increase in frequent unscheduled breakdowns and tripping in the system. To Under Part-B of R-APDRP, 81 projects at an provide quality 24x7 power supply to rural estimated cost of Rs 1540 Crores have been areas, there is an urgent need to augment/ approved for the State and Rs 548 Crores strengthen the rural 11KV feeders which are have been disbursed and the work would be 16,397 in numbers as well as to improve the completed within next 2 years. For these infrastructure on the 33 KV sub-stations works, 50% funding of around Rs. 770 crores which are 3991 in number. has to be arranged by the State.

31

RGGVY connections of around 0.15 lakh BPL - amounting to Rs.19.9 Crores is expected to be At present, the un-electrified households are completed by December 2014. The state share being electrified under RGGVY scheme of required for meeting this obligation would be Govt of India. Under this scheme electricity around 2.0 Crores. connections are being provided for the rural households in the habitations with population of more than 100 only. The status of these RGGVY 12 th Plan : The 12 th plan RGGVY plans is as under: scheme for providing access to all the remaining rural households in the habitations RGGVY 10 th & 11 th Plan : with population more than 100 for the state of The scheme was approved at an estimated Rajasthan was approved with 28 schemes cost of Rs. 1331 crores covering electricity covering 27 districts at an estimated cost of connection to 11.84 lakhs BPL households. Rs. 1453.19 Crores covering electricity Out of which electricity connection of around connection to 13.36 lakhs households 11.69 lakh BPL households has already been including 4.43 lakhs BPL households. released. The remaining electricity

Table 5.1: GoI Schemes Sanctioned and Under Implementation GoI Schemes already Sanctioned and under implementation 2014 - 2015-16 2016-17 2017-18 2018-19 Total Remarks 15 RGGVY 12 th plan (sanctioned 28 150 450 450 403.19 0 1453.19 Sanctioned schemes) RAPDRP- Part- A for IT enablement under Sanctioned RAPDRP – Part A 185 0 0 0 0 185 Rs 315.95 Cr and (For towns with Rs 130 Cr disbursed population more than 30,000)

RAPDRP Part A – Sanctioned Rs SCADA projects for 5 50 61.83 - - - 111.83 157.11 cr and Rs big towns 45.28 cr disbursed

Sanctioned Rs 1540 Cr, and Rs. 548 cr. RAPDRP- Part-B – 500 492 992 Disbursed from 81 towns GoI/Counter Funding Total Sanctioned GoI 885 1003.83 450 403.19 0 2742.02 Schemes

5.3. PROPOSED SCHEMES (a) Feeder Improvement Programme To eliminate the frequent occurrence of Activities involved for improvement of 16397 shutdowns and number of tripping, feeder and Nos. 11 kV feeders requiring an investment of substation improvement programs are Rs. 1500 Cr. Anre provided below:- proposed to be implemented in the State 1. Replacement of 3, 35,246 numbers comprising the following activities: damaged M&P boxes of 3 phase transformers.

32

2. Replacement of 1,02,724 numbers identified for laying 3 phase feeder damaged protection boxes of 1 phase under feeder improvement programme transformers situated nearer to the existing 33 kV 3. Replacement of 40,003 kms single Sub-stations. Cost of the above work phase and 15,142 Kms 3 phase has been included in Feeder obsolete AB cables. Improvement Programme. 4. Augmentation of capacity of 53,181 numbers single phase transformers in (c) Providing three phase supply to big Abadi areas and Dhanies. villages :- 5. Drawing 3 phase system for 1,756 number of villages near to the 33 KV To ensure 24 hours supply to the substations. domestic, commercial, industrial and 6. Providing 8, 93,009 insulated other loads (other than agriculture connectors to eliminate direct tapping loads) in the villages, Discoms have of AB cables. already laid 3phase feeder to around 7. Replacement of 3, 43,787 number 2000 villages of population more than agricultural, 23,591 other categories 4000. To enhance the benefit of 24 x 7 three phase and 6, 94,054 single phase to more villages, it is proposed as defective meters. under :- 8. Providing earthing of 1, 15,441 numbers single phase transformers. i. Separate 3 phase feeder is proposed 9. Augmentation of existing capacity of to be laid in villages having 41,750 kms conductor population more than 2000. There 10. Drawing of 73,278 kms neutral wire are 3338 villages in Rajasthan and 4, 21,239 intermediate pole. having population more than 2000 and less than 4000. Meter Qty FY' FY' FY' FY' FY'19 ii. The estimated cost to execute the Installation / 15 16 17 18 Replacemen Target above work is Rs.1007 crs. t Agricultural Consumers iii. The works are proposed to be implemented in phased manner Metering for 141K 50K 50K 30K 11K - unmetered during F.Y. 2015-16 to 2018-19 agricultural consumers Replacemen 343K 75K 75K 75K 75K 43K (d) Substation Improvement Programme t of existing defective Activities to improve 3991 numbers 33-KV Meters Single Phase Consumers Rural substations requiring an investment of Replacemen 694K 150 150 150 150 94K Rs. 400 cr are provided below:- t of existing K K K K defective 1. Replacement of 679 non operative Meters Roster switches on 11KV Feeders. 2. Installation of 10,102 new Roster switches on 11 KV Feeders. (b) Providing three phase supply to 3. Repair/replacement of non- villages near to the existing 33/11 kV operative circuit breakers on 2022 substations: To ensure 24 hrs. supply Nos 11KV feeders. to the domestic, commercial, Industrial 4. Installation of new circuit breakers and other loads (other than Agriculture on 6843 nos 11 kV feeders. loads) in the villages, Discoms have 5. Replacement of non-functional already laid 3-phase feeder to around 2986 feeder meters 2000 villages of population more than 6. Installation of 4672 new feeder 4000 and 1756 villages have been meters

33

7. Improvement of earthing required As per the sanctioned scheme for 87 at 1976 nos, 33 kV substations. towns, State Data Centre is to be established at Jaipur City and all the Work is expected to be completed by requisite software viz. application March 2015. It is proposed to undertake software, Data Base software and the the above initiatives which are essential requisite hardware will be installed steps for providing reliable, affordable through RAPDRP funding. It is & quality 24x7 power for all the pertinent to mention that sizing of the consumers Software and Hardwares were considered taken into account that the consumers and sub divisions of entire (e) Requirement of additional 33/11 KV state will be served through the state S/S in rural area for 24x7 supply Data Centre, if the entire scheme is The 24x7 power supply for all to rural implemented in entire Rajasthan. areas including electrification of un- Discoms has to bear only the cost of electrified households in rural area will field activities like GIS based network cause additional demand (over and and asset mapping, sub station metering above the existing/usual) and it is etc. for the remaining areas which are necessary to create additional 33/11 kV not covered under RAPDRP to achieve substation (other than State plan) for the following objectives:

providing reliable power supply 1. IT enablement of entire Discom.

satisfactorily in rural areas. 2. Parity in business Process in entire Discom. Even in some cases only To achieve the 24x7 supply, it is part of subdivision has been therefore proposed to create 2 Nos. 5 covered under R-APDRP under MVA 33/11 kV sub-station per year in such circumstances it would be each District during next four years i.e. difficult to maintain the parity in F.Y. 2015-16 to 2018-19. The estimated business process within one sub- cost of the above will be Rs.444 crores division if scheme is not and the works will be executed in a implemented entirely. phased manner in next four years. 3. Facilitate all the consumers of all Discom with the benefits of RAPDRP scheme. (f) IT enabled services to the towns with 4. Avoid future fragmentation, which less than 30 thousand population and may take place if the scheme is not in rural areas under RAPDRP- Part-A implemented in entire Discom. 5. Adoption of common technology Under RAPDRP Part –A, 87 towns of with Integration of entire System. Rajasthan were covered with population 6. To take the benefit of huge of more than 30,000 for IT enabled investment made for Data center. services. In order to implement RAPDRP scheme in the entire state GoI is requested to provide assistance of Rs. irrespective of the coverage of Sub 235 Cr. so that IT enabled services to the Division / Town of more than 30,000 consumers may also be provided to the rural population in RAPDRP, it was areas and towns less than 30 thousand considered that all modules under Part population at par with the RAPDRP towns of A of RAPDRP would also be urban areas and to monitor 24x7 supply with implemented in the towns of population authentic energy audit by utilising the DATA of less than 30 thousand and in rural centre, software & IT applications with other areas. infrastructure being laid for RAPDRP part-A.

34

consumers installations. AT & C losses State of Rajasthan was the first one to launch during 2013 -14 were 26.74 %. The details of R-APDRP program Part- A, inviting IT energy availability, sales and AT&C Loss Implementation Agency and ambitiously from FY 10 to FY 14 are given at Annexure covering both R-APDRP towns and non- R- VI APDRP towns. However, the Implementation progress has been very slow and project is yet The State Govt. has initiated measures for to go-live. making 100% metering, billing, and revenue collection a requisite. Only about 1.42 lakh Since five years that the IT Implementation agriculture consumers (out of total of 12 lakh Agencies (ITIA) was selected to build in agriculture consumer) are yet to be metered. critical components of the IT infrastructure State Govt proposes to undertake the like Customer Relationship Module, Billing following works for reduction of AT&C System, Automatic Meter Reading, Web Self losses - Service, Security, MIS, Centralized Call Centre, etc. is not being implemented i. Providing metering equipments successfully. with all 11 KV feeders for reliable energy audit. Other critical diagnostic tool such as energy ii. Provide metering equipment for audit, Inventory management system, unmetered flat rate 1.41 lakhs Geographical Information System are yet to agriculture connections out of total be implemented. of 12 lakhs Ag. Consumers. To ensure proper & reliable energy Infact there has not been any process to accounting. capture data changes post Consumer iii. Replace 3.43 lac defective Indexation that was carried out few years /damaged metering equipment of back and suspect that the data captured might Agriculture consumers out of the not be put to use. total 10.6 lakhs metered agriculture consumers, under For taking benefits of the huge investment Feeder Improvement Programme. already made under RAPDRP and meeting iv. Replace all defective meters by the program objective, GoR should focus on March 15 as identified in feeder addressing the critical gaps in the existing improvement programme. Apart system and ensure for an early from one time meter replacement implementation for both RAPDRP & NON- there should be periodic drive for RAPDRP towns else the infrastructure such as testing of meters and the hardware, servers may soon be out of replacement of defective meter as warranty. per SOP guidelines issued by RERC. (g) Reduction of AT&C losses for non v. Augment capacity of conductor as RAPDRP towns : per load requirement

Substantial reduction in AT&C losses has vi. Augment distribution transformers been achieved after introduction of High capacity as per connected load Voltage Distribution System (HVDS) in rural growth. areas during FY 06 (41.21%) to FY 10 vii. Organize intensive vigilance (28.03%) through feeder renovation program checking’s to curb the theft of by doing virtual segregation of single phase energy. Government of Rajasthan load from three phase agricultural load and can help the Distribution putting distribution transformers with Companies by setting up Special metering equipment nearer to agriculture Police Station, Special court for

35

speedy resolution of the Electricity Customer segmentation in terms of cases. differentiated service delivery can also be viii. Maximize the collection payment prescribed by state regulator in the next avenues thereby maintaining more phase. than 99.5% collection efficiency ix. Install prepaid meters to the (i) Revamping Maintenance Philosophy: Government connections x. Use IT enabling tools to identify Presently DISCOMS are only engaged in the high loss areas to take Break Down repair work of the various measures for loss reduction. equipments. In order to increase reliability of xi. Capturing of actual energy the system DISCOM should look for consumption by utilizing IT implementing system driven preventive interface. maintenance system. Power Transformers, xii. Most state DISCOM’s Grids are Distribution Transformers, Circuit Breakers manned on 24x7 basis and duty can be checked periodically for identification registers/log sheets are maintained of any faults and correction thereof. Further, in the grid for recording the Discom should have defined roadmap to adapt Predictive Maintenance as well. voltage, current and other data with respect to all the feeders. The data are recorded in register by the (j) Performance Monitoring Mechanism: shift people by manually reading the data from the meters. However, In order to implement appropriate reform with R-APDRP roll-out both in R- measures and meet the objective, baseline APDRP and non-APDRP towns, , parameters needs to be verified and it is expected that the electronic established, and hence it is proposed that a meters with downloading facilities Third Party Audit should be carried out for are been installed and hence establishing the baseline parameters for the DISCOM may enforce the practice KPI indicated below and thereafter following of data downloading through performance parameters needs to be CMRI for feeder meter data and monitored at the DISCOM Corporate level carry out data analysis/ energy audit on such data Corporate KPI UOM (h) Improving Consumer Convenience: Strategic Objectives Improving consumer convenience should be Maximize PAT Rs Crs the focus of any distribution utility. For Rate of No of households Nos in improving consumer convenience in Return Rajasthan Standard of Performance to be electrified Lakhs guidelines has been recently issued by the CAPEX Rs. Crs Regulator. Sustain AT&C Losses % AT&C loss Collection % DISCOM should submit the compliance on level & Efficiency SOP in the time period as prescribed by the achieve Billing Efficiency % regulator. For improving further and make the further process more transparent state regulator can reduction undertake Customer Satisfaction Survey Monitoring Establishment Rs. Crs through some independent agency. Distribution Cost Cost R&M Cost Rs. Crs

36

Corporate KPI UOM urban, target of release of connection of 1 Strategic lakh per year has been estimated as per trend Objectives of last five years. A&G Cost Rs. Crs Power Purchase Rs./unit 5.4.2 Rural Area Cost Out of 34.85 lakhs un-electrified rural Enhancing CSI Overall Index households in the state, only about 25 lakhs Customer households may be considered as un- Satisfaction Total Consumer Nos. electrified which would be provided Complaints/ '000 electricity through grid and balance consumers households may be located in remote places New initiatives to Nos. or using the electricity on shared basis as a enhance customer united family. Out of the balance 9.85 Lakhs convenience un electrified rural households, about 1.5 lakh Addition in Nos. household have already been provided solar regards to Payment domestic lighting system and 1.1 lakh Avenues households will be provided Solar Domestic PA Compliance Index Lighting System (SDLS) in next five years. Index Balance 7.25 lakh households are located in Operational No. of customers Ratio agriculture fields or using electricity on Efficiency served /employee sharing basis as united families, living in System SAIDI Hrs carvan, forest areas, remote far flung areas Reliability SAIFI nos. etc. The details of the above are as under- DTR Failure Rate % PADCI Months Rural uneletrified Households No in lakhs (Project Av. Duration Closure Total 34.85 Index) To be electrified under RGGVY 18.80 No of Accidents Nos (Fatal/ Non Fatal) Dhanies with population less than 2.12 100

5.4. CONNECTING THE To be electrified from existing 4.08 UNCONNECTED grid in already electrified villages & Dhanies As per GoR, there are about 36.75 lakhs un- electrified households in the state including Already provided solar domestic 1.50 34.85 lakhs in the rural areas and 1.9 lakhs in lighting system urban areas. Solar domestic lighting system to 1.10 be provide in next 5 years 5.4.1 Urban Area H/Hs located in Ag fields, forest 7.25 As per GoR, in urban areas, at present only 15 areas, carvans, remote far flung thousand applications are pending for areas etc connections and it is expected that remaining urban households are using electricity on sharing basis as a united family. Keeping in view of the fast growth of households in the urban areas due to migration from rural to

37

Dhanis may be electrified by extending 5.4.2.1 Electrification of 18.80 Lakhs supply from the grid at an estimated cost of Households under RGGVY Rs. 1839 Crores.

• About 15000 households would be 5.4.2.3 Out of the remaining 13.25 Lakh un- electrified under the already approved 10 th th electrified households in the state, Govt of & 11 Plan RGGVY Rajasthan may identify such households • 13.36 lakhs households have already been th which can not be electrified by extending sanctioned under 12 plan RGGVY. supply from the existing grid in next 3 • 6 more schemes at an estimated cost of months. A detailed plan will thereafter be Rs. 813 Crores covering 5.44 lakhs formulated in next 3 months to see which households in six districts have been households are economically feasible to be th submitted to REC for sanction under 12 connected with the grid and which would plan RGGVY. need off grid solutions. The plan would be implemented in the time frame indicated 5.4.2.2 Electrification of 2.12 lakhs earlier. The details of various off grid Households located in Dhanies with solutions of MNRE are at Annexure –VII. population less than 100 :

Around 2.12 lakhs households are estimated to be located in about 30 thousand un- 5.1. FUND REQUIREMENT electrified /partially electrified Dhanis households in the state which are not eligible to be covered under RGGVY. As per GoR, majority of the households located in these

The summary of total fund required for these proposed distribution works are as under– Table 5.2: Details of Investment Planned (Rs in crores) Distribution FY 14- FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks 15 No central assistance is State Plan 1513 1437.00 1372.00 1549.74 1595.17 7466.91 required Centrally sponsored Schemes already 885 1003.83 450 403.19 0 2742.02 Approved by GOI approved (RGGVY & RAPDRP) Electrification of 6 lakh un-electrified 0 450 450 450 489 1839 As indicated in 5.4.2.3 H/h located in Dhanies Earlier sanction of RGGVY submitted 63 250 250 250 813 RGGVY schemes schemes submitted to REC May be covered under GOI new schemes which Other development 2532 754.23 417 372 394.94 4470.17 are being finalised by distribution schemes MOP as per the norms of the schemes / policies

Details of investment plan for next five years for state funding & fund requirement from GoI are given at Annexure –VIII & IX

38

5.2. ACTION POINT - STATE (DDUGJY) for funding for strengthening & augmentation of sub transmission and distribution works, 100% metering, 1. To complete all the distribution works capacity building, ERP and feeder necessary for providing 24x7 quality segregation have been launched by supply to all the connected consumers. MoP. As RAPDRP scheme has been 2. To take necessary steps to meet the subsumed in a newly launched scheme of agreed trajectory for reduction of Integrated Power Development scheme AT&C losses (IPDS) GoR may seek funding for the 3. To identify such un-electrified above works under this scheme. households which can not be electrified by extending supply from 2. Six(6) schemes at estimated cost of the existing grid in next 3 months and Rs.813 Crore have been submitted by to formulate a detailed plan in next 3 GoR to REC for sanction under 12 th months to finalise the economical Plan RGGVY and requested for early feasible for connection with the grid sanction of the same. and off grid solutions. Accordingly, take necessary steps to provide access As RGGVY scheme has been subsumed in a to electricity to all unconnected newly launched scheme of DDUGJY, GoR households in a time bound manner in may seek assistance under this new scheme. next five years i.e. by FY 2018-19.

4. To introduce modern technologies to

monitor reliable supply like sub-

station automation, providing adequate

communication infrastructure, GIS,

Reliability, Centralised Network

Analysis and Planning tools, SAP

driven ERP systems, DMS

(Distribution Management Systems),

OMS (Outage Management System),

etc.

5.3. GOI INTERVENTION

1. GoR has requested assistance form GoI for an amount of Rs. 4470.17 Crores for strengthening of distribution network for providing 24x7 supply like feeder improvement, substation improvement, creation of new 33 kV sub-stations, separation & providing three phase system to the electrified villages of population more than 2000 and system augmentation in non RAPDRP towns etc.

Two Schemes i.e. Integrated Power Development scheme (IPDS) and Deen Dayal Upadhyaya Gram Jyoti Yojna

39

5.4. RENEWABLE ENERGY Year No of Pumps 2010 -11 34 INITIATIVES OF GOVT OF 2011 -12 1675 RAJASTHAN AT CONSUMER 2012 -13 4280 LEVEL 2013 -14 6900

• Grid connected Roof Top Scheme It is proposed that around 5,000 pumps/ year would be installed in the state if the During the year 2013-14, an approval of 5 above subsidy pattern is continued. MW capacity for grid connected roof top system had been received from MNRE to • Solar Off-Grid Systems

RRECL which is state nodal agency for It is an ongoing scheme of MNRE in the promotion & development of which domestic lighting system (DLS) / renewable energy in the state. This home lighting system (HLS) are being scheme is having a provision of 30% provided to the beneficiaries in rural and subsidy from MNRE and 70% has to be urban areas having one solar module of 37 borne by the beneficiary. The scheme is W, 2 CFLs each of 9 W and one battery of proposed to be taken during 2014-15 40 Ah capacity. This scheme is having a subject to finalisation of Net Metering provision of 30% subsidy from MNRE Regulations by Regulatory Commission. and 70% has to be borne by the The petition is pending in this regard with beneficiary. So far more than 1.5 Lakhs SERC. systems have been installed in the state.

• Solar water Pumping Scheme The Government buildings, hospitals,

This is a scheme by MNRE. Presently the Public Health Centres (PHCs) in rural and scheme is being implemented by state semi-urban areas are proposed to be Horticulture Deptt. Since 2010-11. Total provided with Solar Off-Grid Systems subsidy provided is 86 %( 30% from with battery support. MNRE & 56% from Rastriya Krishi Vikas Yojana) of the bench mark cost of DPRs for above schemes would be the pump Balance 14% is to be borne by prepared and submitted to MNRE for the beneficiary. The details of the pumps approval on yearly basis. The projected installed during last 4 years is as follows- figures of above scheme are mentioned in the given below table:

Table 5.3: Details of Renewable Energy initiatives ( Physical & Investement)

Sl. Particulars Unit FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total No. Grid connected 3.5MW 10MW 10MW 10MW 10MW 43.5MW A No. Solar Rooftops 100 no’s 300 no’s 300 no’s 300 no’s 300 no’s 1300 no’s Investment Rs. 25 70 70 70 70 305 required Cr. Assistance req % 30% 30% 30% 30% 30% 30% under NCEF Solar off-grid 2 MW 5 MW 5 MW 5 MW 5 MW 22 MW B No. systems (10000) (25000) (25000) (25000) (25000) (110000) Investment Rs. 37 92.5 92.5 92.5 92.5 407 required Cr. Assistance req % 30% 30% 30% 30% 30% 30% under NCEF

40

Solar pump C No. 5000 5000 5000 5000 5000 25000 systems Investment Rs. 360 360 360 360 360 1800 required Cr. Assistance req. % 30% 30% 30% 30% 30% 30% under NCEF Assistance % 56% 56% 56% 56% 56% 56% discontinued under Rashtriya Krishi Vikas Yojana, which may be continued by GOI

5.5. ACTION PLAN - STATE –RENEWABLE ENERGY

DPRs for above schemes would be prepared and submitted to MNRE for approval on yearly basis.

5.6. GOI INTERVENTION 1. To facilitate the earlier approval of DPRs for the above schemes under National Clean Energy Fund (NCEF) 2. Continuation of 56% assistance under Rashtriya Krishi Vikas Yojana for Solar Pump system

41

6. ENERGY EFFICIENCY

With increasing importance being given to low carbon growth these days, the cheapest and more affordable option to overcome the energy deficit is Demand Side Management and implementation of energy efficiency measures in various sectors such as agriculture, municipalities, buildings, domestic, industries etc. In this chapter, the demand side energy savings potential that exist in Rajasthan, interventions and timelines are discussed. A. SAVINGS POTENTIAL & INVESTMENT

Table 6.1 summarizes the sector specific demand side energy savings potential vis-à-vis the investments required in the state of Rajasthan. Table 6.1 Investment Savings Percentage of to achieve S. Consumption Potential Techniques to be Sector energy potential No (MU) per annum incorporated consumption savings (MU) (INR crores) Replacement with 1. Agriculture 41 % 17839 4770 7200 energy efficient pump sets Replacement of 2. Domestic 21% 9009.6 2100 1604 ICLs with LED bulbs Retrofitting of Commercial 3. 7% 3226.5 480* 720* energy efficient Buildings equipments Replacement with Public Water 4. 4% 1541.5 400 250 energy efficient Works pump sets Municipal Replacement of 5. Street 1% 389.1 200 400 existing street lights lighting with LED. Total 32004 7950** 10174**

* For commercial buildings sector only 50% (i.e. 1613 MU) having connected load greater than 100 kW or with contract demand of 120 kVA or more are considered. **Around 7950 MU of energy savings annually can be achieved at an investment of Rs. 10174 crores.

42

60,000 will be of Rs. 7200 crores with an B. INTERVENTIONS estimated savings of around 4.77 BU per The agricultural sector accounted for about annum. Apart from the 41% of the state’s energy consumption i.e. 17.8 BU during 2013-14 and the subsidy energy savings, this would result in annual burden of the State for the year 2014-15 is subsidy savings of Rs. 1200 crores to the state estimated at Rs. 6000 crores for about 1.2 Based on the estimated subsidy reduction, the million pump sets. simple payback on investment is around 6 Two successful pilots in Agricultural Demand years. Farmers have little financial obligation Side Management have proved that to pay electricity bills, therefore apart from investment in agricultural pump sets monetary savings on account of electricity efficiency can payback in a short time, refer Table 6.2 below: bills, the reduced maintenance cost of farmers is the biggest incentive in such interventions. Table – 6.2 No. Parameters Solapur Hubli Doemstic sector accounted for an energy consumption of 9.1 BU which is nearly 21% 1. No. of pumpset 2209 590 replaced of the total consumption in 2013-14. In order 2. Annual energy savings 6.1 2.9 to stimulate investments in energy efficient achieved (MUs) lighting projects, high quality LED lamps are 3. Energy Savings (%) 25 37 proposed to be given to households at the cost 4. Investment (INR crores) 8 2.6 of incandescent lamps (ICLs) to encourage 5. Annual Reduction of 1.2 1.01 them to invest in energy efficiency under the subsidy (INR crores) DSM based Efficient Lighting Program (DELP). There are about 12 lakhs agricultural pump The main features of DELP includes sets which are eligible to receive subsidy from replacement of 60 W ICL with 8 W LED with the state government. The State Govt. is 5-6 years free replacement warrantee on providing subsidy of Rs 3.03 per unit of lamps against technical defects, distribution of energy consumption in Agriculture sector. As 3 LEDs to each household on getting back the per the DRP prepared by BEE in JVVNL for working ICLs and monitoring of projects as 1800 pump sets, the energy saving potential is per international standard methodology around 45%. Taking the average energy approved by CDM Executive Board for BLY. savings outcome of the two pilots, a 30% There are an estimated 12.6 million reduction in energy consumption and subsidy households in the state as per 2011 Census is possible by replacing all existing pumps data. Thus, the total energy savings from with star rated energy efficient pump sets. replacement of ICLs to DISCOMs will be The average pump sizes in JVVNL & 2100 MU annually at an investment of Rs. AVVNL are 6.5 KW, while in JDVVNL it is 1604 crores. Puducherry has become the first 16 KW. The estimated investment in state to undertake implementation of DELP replacement of 12 lakhs pump sets, taking an on a large scale. average cost of efficient pump sets to Rs.

43

In 2013-14, the commercial sector in the state existing lights with LEDs can lead to an of Rajasthan accounted for nearly 7% of the energy savings between 55-60%. In addition total energy consumption, i.e., 3226 MU of to energy savings, LED street lights also reduce maintenance costs as they come with which the targeted baseline for energy 5-7 years free replacement warranties enhance conservation is around 50% (i.e. 1613 MU) in the light output and meet national lighting the organized sector in buildings having standards, allow automatic controls to connected load greater than 100 kW or with enhance savings by remote switching, contract demand of 120 kVA or more. daylight savings and dimming. In addition, Techno-commercial analysis for energy LED lamps improve the power factor of the efficiency project implementation at Vidyut system and enhance the savings to DISCOMs. Replacement of all street lights with LEDs in Bhawan and Rajasthan Secretariat in Jaipur Rajasthan with an investment of around Rs. shows energy savings of 0.13 MU and 0.85 400 crores can lead to energy savings of 200 MU per annum with estimated investments of million units annually. Rs. 0.42 crores and Rs. 2.4 crores C. APPROACH / STRATEGY respectively. As per details available, energy savings to the tune of 30% are achievable in All the above interventions involve replacement of inefficient equipment / the end use functional areas of lighting, appliances with energy efficient ones for the cooling & ventilation, refrigeration, etc., agriculture, domestic, commercial buildings which can help the state alleviate 480 MU, and municipalities. These can be undertaken with an estimated investment requirement of by the State Govt. at no upfront cost by Rs. 720 Crores. In addition to these, Rajasthan using the Energy Service Company Government has already adopted Energy (ESCO) model. The model is based on the concept of promoting Performance Contract Conservation Building Code (ECBC) for new mode where the company invests in any commercial buildings, the effective project by entering into a contract agreement implementation of which will also result is with the facility owner which is recovered significant energy savings. through the savings accrued due to reduced electricity bills. The municipal sector accounted for 5% of the energy consumption, with public water works comprising 4% (1540 MU) and street lighting D. TIMELINES constituting of around 1% (389 MU). Various Agriculture Sector: energy audit studies have revealed a savings Under AgDSM, a plan to cover the entire 12 potential of 25% - 30% through replacement lakh pump sets is indicated below in Table 6. of inefficient drinking and sewage water 3. The year wise investment required, savings pumping systems with energy efficient ones. to be achieved and reduction of subsidy Thus, it can be estimated with an investment burden is also indicated. The project will also of around Rs. 250 crores all the drinking and evolve standard operating processes as well as sewage water pumping systems can be made robust payment security mechanisms so as to energy efficient and savings of around 400 replicate the same in an accelerated manner. MU annually can be achieved. Assuming the state government is paying subsidy of Rs 2.50/ per unit of energy consumption in agriculture sector. The In Rajasthan, almost the entire public lighting estimated simple payback period is around 6 is based on conventional lights and it has been years. demonstrated that replacement of these

44

Table 6.3

2014-15 2015-16 2016-17 2017-18 2018- Total 19 Total pumps to be replaced 50000 250000 300000 300000 300000 1200000 Amount of energy savings (MU) 198.75 993.75 1192.5 1192.5 1192.5 4770 Investment (INR crores) 300 1500 1800 1800 1800 7200

Domestic Sector: A plan to cover the entire state having 12.6 million households has been prepared which is in Table 6.4 below. The year wise investment required and savings to be achieved is also indicated. Table -6.4 Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total No. of Households 600000 3000000 3000000 3000000 3000000 12600000 No. of LED replaced 1800000 9000000 9000000 9000000 9000000 37800000 Annual Energy Saved (MU) 100 500 500 500 500 2100 Investment (INR crores) 76 382 382 382 382 1604 Assuming electricity price in the domestic sector to be Rs. 4/kWh, the simple payback period is around 2 years.

Commercial buildings: The plan to cover the commercial buildings in Rajasthan is at Table 6.5 below: Table 6. 5 Parameter 2014-15 2015-17 2016-17 2017-18 2018-19 Total Coverage of Government Government Government 30% of 40% of 100% retrofitting in buildings buildings buildings (40%) Private Private Govt. + commercial buildings (20%) (40%) + 10% + 20% of buildings buildings Private of Private Private buildings buildings Buildings Annual Energy Saved 19.2 76.8 115.2 115.2 153.6 480 (MU) Investment (INR 28.8 115.2 172.8 172.8 230.4 720 crores)

Assuming electricity price in the non - domestic sector to be Rs. 4 / kWh, the simple payback period is around 4 years. In addition to above, the following activities to promote the efficient use of energy and its conservation in commercial buildings (refer Table – 6.6 ) may be undertaken:

45

Table – 6.6 S. Activity Timelines No. 1 Amendment in Schedule of Rates and Plinth Area rates of PWD 2014-15 2 Amendment of standard design template of public buildings On going 3 Training and capacity building of compliance officials and design professional On going through Institutional framework

Municipal Sector (Public Water Works & Street Lights): A plan to cover the entire municipal sector (public water works and street lights) of the state is given below in Table – 6.7 and Table -6.8 .

Public Water Works: Table -6.7 Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total % of water pumping systems to 12.5 12.5 25 25 25 100 be covered Annual Energy Saved (MU) 80 80 80 80 80 400 Investment (INR crores) 50 50 50 50 50 250 Assuming electricity price in the public water works to be Rs. 4/kWh, the simple payback period is around 1.5 years.

Street Lights: Table – 6.8 Parameters 2014-15 2015-16 2016-17 2017-18 2018-19 Total % of street lights to be covered 12.5 12.5 25 25 25 100 Annual Energy Saved (MU) 25 25 50 50 50 200 Investment (INR crores) 50 50 100 100 100 400 Assuming electricity price in street lighting to be Rs. 4/kWh, the simple payback period is around 5 years. Sector-wise investments to achieve the savings potential through various energy efficiency measures for 5 years are given below at Table -6. 9 : Table – 6.9 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Investmen Saving Investmen Saving Investmen Saving Investmen Saving Investmen Saving Sectors t s t s t s t s t s (INR cr) (MU) (INR cr) (MU) (INR cr) (MU) (INR cr) (MU) (INR cr) (MU) Agricultur 300 198.75 1500 993.75 1800 1192.5 1800 1192.5 1800 1192.5 e Domestic 76 100 382 500 382 500 382 500 382 500 Commerci al 28.8 19.2 115.2 76.8 172.8 115.2 172.8 115.2 230.4 153.6 Buildings

46

Public Water 50 80 50 80 50 80 50 80 50 80 Works Street 50 25 50 25 100 50 100 50 100 50 Lights 1675.5 504.8 422.95 2097.2 2504.8 1937.7 2504.8 1937.7 2562.4 1976.1 Total 5

Cumulativ 2098.5 e 422.95 4036.2 5973.9 7950 saving(MU 0 )

E. ACTIONS POINTS

The sector-wise Central Government and distributed to utility and consumer State Government actions envisaged to optimally. facilitate implementation of energy efficiency • State may issue mandatory notification for measures as mentioned above are detailed use of energy efficient pump set for new below: agriculture connections. Also encourage Agriculture Sector and continue the schemes for promoting EEPS like the present scheme of providing financial assistance of Rs. 500/- • Funds Required: Rs. 7200 crores per HP for up gradation of existing pump • Savings: 4770 MU sets or procurement of new EEPS. • Ensure formulation of a detailed time line Central Government : in consultation with concerned departments like Distribution Companies • M/o Agriculture may amend the for implementation of energy efficiency guidelines of various schemes like measures in agriculture. Rashtriya Kisan Vikas Yojana (RKVY) to • promote use of star rated energy efficient Ensure establishment of a payment pump sets (EEPS) under these schemes security mechanism so that the company making investments under the ESCO • BEE may expand its star labelling mode recovers the same through the programs to cover higher size pump sets. savings accrued due to reduced electricity • Energy Efficiency Services Limited bills. (EESL) to take up project design and project development. Domestic Sector State Government : • Funds Required: Rs. 1600 crores • Distribution Companies / Utilities may • Savings: 2028 MU file DSM petition with Rajasthan Central Government: Electricity Regulatory Commission for getting sanction of the proposed DSM • BEE may consider formulation of plan. specification for LED bulbs and introducing star label scheme for LED • Rationalization of agricultural tariff so bulbs. that benefit of energy efficiency is

47

• Energy Efficiency Services Limited enforcement of ECBC compliance and (EESL) to take up project design and mandating retrofitting in energy-audited project development. buildings may result in reduction of electrical consumption from commercial State Government : sector. Government of Rajasthan may • Distribution Companies / Utilities may consider mandatory retrofitting in file DSM petition with Rajasthan Government buildings with an objective Electricity Regulatory Commission for of reduction of electricity bills, which getting sanction of the proposed DSM state government is paying against plan. electricity bill of these buildings. This would also demonstrate impact of ESCO • Ensure formulation of a detailed time line based retrofitting projects to private in consultation with concerned building owners to adopt the same. departments like Distribution Companies for implementation of energy efficiency • As per the Planning Commission’s measures in municipalities. projection; residential building are becoming one of the larger consumers of • Ensure establishment of a payment electricity in the county by 2030. BEE is security mechanism so that the company introducing design guidelines for energy making investments under the ESCO efficient multi storey residential mode recovers the same through the apartments including in the composite and savings accrued due to reduced electricity hot & dry climatic zone. State bills. Government may mandate compliance of Commercial buildings these guidelines through institutional framework in the state. • Funds Required: Rs. 720 crores • Ensure formulation of a detailed time line • Savings: 480 MU in consultation with concerned departments like Public Works Central Government : Department, for implementation of energy • BEE may provide technical support for efficiency measures in municipalities. effective enforcement of ECBC and • Ensure establishment of a payment promotion of ESCO based retrofitting security mechanism so that the company works in Government buildings. BEE can making investments under the ESCO provide support for capacity building of mode recovers the same through the state department through establishment of savings accrued due to reduced electricity ECBC cells for compliance of ECBC and bills. retrofitting in Government buildings. • For residential buildings, the state could • Energy Efficiency Services Limited adopt the star labelling scheme for multi- (EESL) to take up project design and storey residential apartment buildings, project development for retrofitting in being prepared by BEE. commercial buildings.

Municipal Sector (Public Water Works & State Government : Street Lights) • Government of Rajasthan has adopted (i) Public Water Works ECBC Directives for new commercial building design and mandated energy Funds Required: Rs. 250 crores audit of existing commercial building Savings: 400 MU once in a three-year period. Effective

48

(ii) Street Lights implementation of energy efficiency Funds Required: Rs. 400 crore measures in municipalities. • Savings: 200 MU Ensure establishment of a payment security mechanism so that the company making investments under the ESCO Central Government: mode recovers the same through the savings accrued due to reduced electricity • BEE may consider formulation of bills specification for LED street lights and provide some financial assistance for one In addition to the above, Rajasthan Electricity pilot project under MuDSM program. Regulatory Commission (RERC) may be requested to issue directives for creation of • Energy Efficiency Services Limited DSM funds by DISCOMs / Utilities of the (EESL) to take up project design and State so that DSM activities can get extra project development. emphasis. Such funds can be utilized for State Government: meeting incremental cost of efficiency improvement. • Ensure formulation of a detailed time line in consultation with concerned departments like Public Health & Engineering Department and Urban Development Department for

49

7. FINANCIAL VIABILITY OF DISTRIBUTION COMPANIES disturbing the cost economics of Discoms so adversely that in case the interest and finance 7.1. FINANCIAL POSITION OF charges are excluded from the total cost, then DISTRIBUTION UTILITIES the above stated cost recovery would stand as 82% in FY 2013-14, leaving a gap of 18% After unbundling of the erstwhile Rajasthan only which can be addressed by suitable tariff State Electricity Board (RSEB) in July 2000, hikes and internal operational efficiencies. In Rajasthan Discoms commenced their case the liability of the short term outstanding operations with a loss of Rs. 680.00 cr. in FY loans is fully taken out from the Discoms’ 2001, which increased to Rs. 3908 cr. in FY books, the Discoms shall not only manage 2003-04 and thereafter touched to Rs. 15,643 their cost of power supply but also will not cr. in FY 2008-09. The primary reasons for require working capital support on one hand increasing the loss level from FY 2003-04 to and on the other they would also not be in FY 2008-09 were one tariff hike only during need of steep tariff hikes again and again . the period in Jan. 2005 that too 10.15% and higher quantum of power purchase at comparatively higher cost due to state In the beginning of FY 2011-12, the banks had generation projects lagging behind their stopped funding to the Discoms, resulting in schedules. over delay in various payment obligations to During this period Feeder Renovation power generators/ suppliers and others, Programme was aggressively implemented leading to likely disruption of power supply as which resulted in drastic reduction in the various power generators/suppliers started distribution loss level from 42.62% in FY cautioning to stop the power supply including 2003-04 to 26.59 % in FY 2008-09. Had this serving of regulation notices, invocation of ambitious programme not been there, the Letter of Credits (LCs) established in their above accumulated financial loss level would favor. Repayments along with interest have been phenomenally on much higher side. servicing to banks/FIs had to be stopped The accumulated financial loss further resulting in accruing of penal interest as well ballooned to Rs. 74,280 cr. (Prov.) in FY as turning of various loan accounts on the 2013-14 despite three consecutive tariff hikes verge of Non-Performing Assets (NPA). after 2008-09. Moreover, the distribution loss Likewise, over delayed payment to various also stood at 24.38 % (AT&C losses 26.74%) power generators attracted late payment in FY 2013-14. surcharge which in turn further deteriorated liquidity crisis already looming over. The recovery of total cost of power supply Moreover, other suppliers/contractors denied from revenue stood at 85 % during FY 2003- to further supply and execute the contracts 04, which remained 60% in FY 2008-09 and resulting in various capital projects and 62% in FY 2013-14 (Prov.). Despite three maintenance works held up. tariff hikes in a row during the period, there was only a marginal improvement in recovery of cost in FY 2013-14. This also indicates that 7.2. FINANCIAL RESTRUCTURING the expenditure during the period also increased commensurately with the SCHEME OF GOI (O CTOBER incremental revenue, chiefly on account of 2012) ever rising interest and finance charges, Taking a serious view over the ever increasing trend in power purchase cost and deteriorating financial condition of the state almost static distribution loss levels amongst owned Discoms across the country, the others. The interest and finance charges are

50

Planning Commission set-up a Committee • On the cut- off date 31 st March 2012 the headed by Sh. B.K. Chaturvedi, Member, accumulated losses of the Discoms were to Planning Commission to come out with a the tune of Rs.40, 942 cr. against which sustainable and viable scheme for long term the outstanding short term loans were viability of the distribution utilities Rs.31, 906 cr. and power purchase particularly in the most critical States, referred payables outstanding for more than 60 as the focused states including Tamil Nadu, days Rs. 4132 cr making a total of Rs. UP, Haryana and Rajasthan. Based on the 36,038 cr. recommendations of the said Committee, the • As such Discoms were eligible for full Ministry of Power, Govt. of India notified a outstanding liabilities as on 31 st March Scheme on 5.10.2012 for long term 2012 of Rs. 36038 cr. Out of this, bonds sustainability of the Discoms in the country. worth Rs. 18019 cr were to be issued by Rajasthan was one of the early movers for the Discoms and to be taken over by the providing consent to participate in the above State Govt. over a period of time in a Scheme. phased manner. The remaining short term loans were to be restructured by banks.

Some of the key commitments on the part of various stakeholders as envisaged in the Scheme vies- a-vies their compliances as of now are given as under:-

Sr. No. Commitments Compliances

1. Financial Restructuring Plan (FRP) is to be Has been prepared and finalized after approval chalked out by the Discoms and to be of all the required stakeholders. approved by the state govt. state regulatory commission and by the banks/FIs.

2. Bonds against 50 % short term liabilities Bonds amounting to Rs. 17961 Cr. have been (including power purchase payables ) issued to the various banks at a coupon rate of outstanding as on 31 st March 2012 are to 9.95% p.a. on 18 th October 2013; be initially issued by Discoms; 3. Remaining 50% short term loans Outstanding short term loans amounting to Rs. outstanding as on 31 st March 2012 are to 15,928 Cr. have been restructured by the be restructured for a period of 10 years banks. with a moratorium on principal of 3 years;

4. The bonds issued by the Discoms are to GoR has committed to take over the bonds be taken over by GoR through special worth Rs. 3,000 Cr. in FY 2013-14, Rs. 4,500 Govt. securities in a phased manner Cr. in FY 2014-15 Rs. 5700 Cr. in FY 2015-16 within next 2 to 5 years and the balance Rs. 4,761 cr. in 2016-17; During previous FY 2013-14 bonds amounting to Rs. 3,340 cr. instead of committed Rs. 3000 cr. have already been taken over by GoR.

5.. Banks/FIs to provide loan against Banks have provided fresh working capital operational funding during next three loans amounting to Rs. 10,952 Cr. in FY years starting from FY 2013 on a 2012-13, Rs. 9016 Cr. in FY 2013-14, and diminishing scale; have sanctioned Rs. 1101.01 cr. (up to July 14) against the committed of Rs. 2878 cr. for current FY 2014-15 and the remaining is in process of sanctioning at the end of the banks.

51

6. Filing of tariff petitions regularly. Being done regularly.

7. Pass through of adjustment of fuel cost to Being done regularly. offset power purchase cost.

8. Constitution of monitoring committees State Level Monitoring Committee (SLMC) constituted by the GoR vide order dated 11.12.2012, three meetings already held, last one held on 4 th June 2014.

9. Conversion into equity/ deferment of Following the condition of the Scheme, GoR repayment of outstanding state govt. loans. is not insisting the repayment of interest free loans provided to Discoms.

10. Central Govt. would provide incentive by To be complied with in due course. way of grant

(i) equal to the value of the additional energy saved by way of accelerated AT&C loss reduction i.e. reduction beyond 1.5% annually; and (ii) 25% of reimbursement to the state Govt. of bonds taken over by the latter.

11. 100% consumer metering. Consumer metering is complete. There are only 1.41 lacs flat rate agriculture consumers being not billed on metered energy basis. However, meters have also been installed to these consumers to ensure recording of actual consumption.

12. Outstanding dues of State Govt. Done. departments to be paid off till 30 th Nov. 2012.

st March 2012 have been taken Besides the above, the other conditions on 31 over by the State Government w.e.f. relating to installation of prepaid meters and 18.10.2013(date of issue of bonds) involvement of private participation etc. are in resulting in a relief of around 810 cr. process of implementation. during FY 2013-14;

3. Moratorium on repayment of remaining The implementation of the above mandatory 50% short term loans outstanding as on conditions has cushioned the distribution 31 st March 2012 stands extended till 31 st companies to partially mitigate the issues March 2015 to tide over the prevailing being faced to the extent as briefed below: liquidity crisis to this extent. 1. Filing of tariff petitions annually from 4. Annual accounts of the companies are FY 2011-12 and onwards and roll over being audited and finalized in time. of tariff orders and pass through of fuel

cost adjustment have improved the revenue streams; Though the Discoms have partially been eased out on account of the 2. Repayment and interest servicing on implementation of the Scheme, yet the 50% outstanding short term liabilities as following compelling factors have

52

necessitated updating of the existing FRP losses in the financial year 2013-14 so as to effectively garner the envisaged was got conducted. As per findings of benefits of the GoI Scheme. the energy audit agency, the • Bonds were to be issued effective from distribution losses are at the level of 1.4.2012 but delay in notifying the 24.38 % in the FY 2013-14, much guidelines on issuance of bonds and much higher than the loss level of 16.3 subsequent frequent discussions with % projected in the FRP. This factor Banks to evolve a consensus on alone has made the present FRP coupon rate and cut-off date, the document unworkable. bonds could be issued only on 18 th • Due to increase in cost of coal and Oct. 2013. This has resulted in burden freight etc., the average power of interest liability on the bonds purchase cost of Rs. 3.79 per unit as portion shouldered by Discoms from envisaged in FRP has actually stood as 1st April 2012 to 17 th Oct 2013; Rs. 4.10 per unit (Prov.) in FY 2013- • The benefit of tariff hike during FY 14. 2011-12, 2012-13 and 2013-14 could In view of above mentioned significant not be available for the full year as the deviations in the key parameters of the tariff orders were made effective from present FRP document, the State Level the date mentioned against each as Monitoring Committee (SLMC) has directed under: to update the FRP, subject to acceptance by all concerned with consequential amendments Financial Year Effective month in obligations. Accordingly the updating work 2011-12 September 2011 is already in process in consultation with M/s 2012-13 August 2012 PWC, the Discoms’ consultant. This work is 2013-14 June 2013 likely to be completed within next 3-4 weeks. The revision/updation of the existing FRP is For current Financial Year 2014-15 being carried out in anticipation of tariff petitions could be filed only on consideration by GoI of the following 6th June 2014 as the finalization of the requests made by the Discoms: MYT regulations by the regulator was done only in the first quarter of the current Financial Year. The tariff order • The cut-off date of the Scheme be for the FY 2014-15 is expected soon considered as 1.04.2014 in place of but the benefit may not be available 01.04.2012. for more than six months . • Moratorium on repayment of loans to • The regulatory assets during the last Banks/FIs outstanding as on 31st four years have been building up March 2014 be kept upto March 2018 substantially for two reasons. One, the in place of March 2015; regulator did not allow the proposed • Full Operational Funding Requirement ARR in the tariff petitions to avoid to be provided by the Banks/FIs for tariff shocks. The other, benefit of FY 2015-16, 2016-17 and 2017-18 tariff order was not available for full also. financial year. After the above revision/updation of the • Independent energy audit by a central existing FRP, Discoms expect their agency in respect of the distribution turnaround in FY 2017-18 mainly due to gradual reduction in AT&C losses from the

53

level of 26.78% in FY 2013-14 to 15% in FY Energy accounting and energy management 2019-20. Such reduction in AT&C loss level have proved to be the biggest challenges in is expected to yield a saving of approximately most Indian states. Till date there is no 10,000 cr. during the above period, giving credible mechanism for identifying the true much needed reprieve to the Discoms’ levels of distribution losses in the states. The financials. Gradual tariff hike till the full available data has mostly lacked in credibility recovery of total cost of power supply from and have been often restated to the extent that revenue will augment the revenue stream of it changes the loss picture completely. This is the Discoms ultimately paving the way for true in Rajasthan as well where the their scheduled turnaround. Operational distribution losses have climbed up from less efficiency is also expected to take place up to than 20% in 2011-12 and 2012-13 to about the expected levels. 25% in 2013-14. 7.1. LOSS REDUCTION, ENERGY The Targets for Distribution losses for FY 15 MANAGEMENT &, ENERGY onwards is given in table titled “ DISCOM- ACCOUNTING WISE DISTRIBUTION LOSS TRAJECTORY ”. The Targets for FY 15 & FY 16 are The high AT&C loss levels in the Discoms aggressive and since only few months are left remains a concern and all efforts shall be in FY 15, it will require extraordinary efforts. made to reduce the distribution losses to Efforts will be made to make up for any short improve the financial health of the Discoms. fall in a year in subsequent years. To manage this effectively a concrete plan for energy management, energy accounting and loss reduction shall be put in place. REPORTED T&D LOSS TRENDS* Year FY 08 FY 09 FY 10 FY11 FY 12 FY 13 FY 14

T&D Loss 35.5% 31.5% 31.0% 26.8% 24.3% 23.8% 27.5%

Transmission 6.0% 6.7% 6.6% 5.8% 5.8% 5.6% 4.1% Loss

Distribution 31.4% 26.6% 26.1% 22.3% 19.6% 19.2% 24.4% Loss

*The losses in transmission and distribution are not simple addition since the basis of measurement is at different points in the network DISCOM-WISE DISTRIBUTION LOSS TRAJECTORY

Year FY 15 FY 16 FY 17 FY18 FY 19 FY 20 FY 21

Jaipur Discom 24.50% 22.50% 20.50% 19.00% 17.50% 16.00% 15.00%

Ajmer Discom 19.60% 18.50% 17.50% 16.50% 15.50% 14.50% 14.25%

Jodhpur 21.14% 19.22% 17.30% 16.00% 15.00% 14.50% 14.25% Discom

All Discoms 21.75% 20.00% 18.50% 17.25% 16.00% 15.00% 14.50%

Proposed Improvement trajectory (including Loss Reduction, Billing & Collection efficiencies) subjected to adjustments in baseline data

54

55

Before embarking on the journey of loss To achieve its real potential accuracy reduction, baseline AT&C losses should be and regular updations of asset & re-established for the each of the DISCOMs. consumer mapping needs to be carried This will help in removing the ambiguity in out both for the existing and new set terms of loss level. Baseline AT&C losses can be fixed by following the method as of asset and consumer. It is also prescribed for TPIA by PFC. Baseline AT&C important for the utility to identify and losses will also help in resolving other regularly update the incremental important matter such as level of subsidy changes that is happening in the requirement, category wise billing details etc. network. Currently, in Rajasthan DISCOM, GIS has not been The R-APDRP has already initiated a number implemented successfully due to of measures in this regard including energy various reasons. audit and accounting with IT intervention. These initiatives now need to be strengthened 2. As per RAPDRP plan, Government and expanded in other areas. To meet this has thought of installation of meter for objective, the backbone infrastructure for in all the distribution transformer & improving measurement and visualization will feeder in the urban areas in the state. be created across the state and would include: As the scheme has not progressed 1. Implementation of Geographic successfully, a comprehensive feeder Information Systems (GIS) to map the and distribution transformer metering network assets and consumers programme needs to be rolled out that comprehensively and always updated would cover all feeders and for operational purposes. Activities transformers in the State. Measures in that would be supported by the GIS this regard have been continuing in the capabilities would include fault state over the past several years. This detection and restoration, new service will be made more comprehensive, connection issuance, connection – and will be backed by an expeditious disconnection, network expansion, etc.

56

restoration plan in case the meters turn the vital components of AMI are new defective or damaged; generation of meters which are capable to simultaneously perform 3. Metering standards and standard basic functionality of core metering installation guidelines needs to be and advance functionalities like formulated before procurement & sending meter data via Head End installation of meter. System (HES) using two-way remote 4. Consumer metering would be put in communication network, giving access place to ensure 100% metering of all to utility to execute remote commands supplies including agriculture in the like load connect/ disconnect, ability next 3 years. This will be implemented to inform consumer about real time by the support of the State pricing/ time of usage and performing Government and Government of India. periodic meter maintenance via over the air firmware upgrades. Data 5. A properly devised pricing policy can collected from meters are processed create incentives for the consumers to for various applications like billing, shift load from peak hours to off peak consumption analysis, outage hours. Time of use (TOU) Time of management, address customer day(TOD) pricing is one of the options grievances etc.Govt. of Rajasthan may of Demand Side Management in draw a roadmap for implementation of which the consumer pays more for AMI in a phased manner starting with energy used during peak hours and big cities and towns in the State. less during off-peak hours. This encourages consumers to shift load 7. Network analysis of the system to base during cheaper time periods of the day on power flows and network status to which helps in reducing the peak ensure that the losses and line outages demand thereby flattening out the load can be predicted or identified in a curve. Rajasthan Discoms may timely manner; As per RAPDRP approach Rajasthan Electricity program Network analysis application Regulatory Commission for would have been supplied to introduction of TOD pricing in their DISCOM. However one can assume next tariff notification. that without a credible GIS database the same has not been utilized fully in 6. Advanced Metering Infrastructure the DISCOM. Through change in (AMI) is a system which allows the process management, DISCOMS have utilities to remotely measure, collect, to ensure that the entire new capital and analyze the consumption data. The investment program are routed foundation blocks of AMI includes through network analysis module smart meters, associated hardware, rather than existing stopgap approach. software, data management, programming and communications 8. Loss measurement and verification devices that collect time-differentiated methodology implemented through energy usage from smart meters. external agencies to be implemented Smart Meters which constitute one of

57

9. To carry out independent feeder-wise energy measurements of the utilities and rate energy audits that would be carried out them on various parameters to ensure that the by the independent energy audit loss measurements and supply parameters for agency at the corporate office and the 24X7 supply are transparent and credible. reporting directly to the management.

10. To arrest the high AT&C losses, 7.2. GOI INTERVENTION involvement of private participation

by way of PPP/franchising will be GoI is being requested to approve the recast FRP covering the following basic features promoted. Towns with loss levels of therein at the earliest to ensure the projected more than 20% shall be identified for turnaround in FY 2017-18: PPP/ distribution franchisee, Urban

areas needing high reliability should a. The cut-off date as stipulated in Scheme be an ideal choice for PPP model. be extended from 1.4.2012 to 1.4.2014; Rajasthan has already moved forward in identifying Jaipur, Udaipur, Jodhpur b. The moratorium period be extended by & Bikaner as target areas for PPP Banks/FIs by 3 years- accordingly the model and should be then extended to repayments would commence from April 2018 in place of April 2015; other urban towns like Ajmer, Kota,

Chittorgarh, Bhilwara, etc. Also, a C. Full Operational Funding Requirement be provision would be useful to be build provided by the Banks/FIs for further 3 up in the RFP to include concentric years also i.e. in FY 2015-16, 2016-17 and areas of the towns selected over period 2017-18. of time. For their other areas different d. To provide capital reimbursement support models such as Input based urban upfront against the TFM to ease out the franchise / Collection based / rural State Government financials due to franchise with Self Help Group accepting the Scheme. (SHG), can be thought of e. Banks/FIs be persuaded to reduce their prevailing rate of interest on working 11. Aggressive vigilance checking shall be capital loans at least by 5 per cent, intensified. facilitating the Discoms to use the savings accrued on account of this less outgo of 12. Incentive scheme would be introduced interest to honour the scheduled for each circle, which is at all district repayments. headquarters and headed by a The above request of Govt of Rajasthan Superintending Engineer. Such would be considered by Govt of India as per incentives could be distributed its policies or otherwise Govt of Rajasthan amongst concerning Discoms officials, would make arrangements for funding from police personnel, district officials etc. other sources.

For this purpose, external verification through competent accredited certification agencies shall be taken up. Such agencies 7.3. ACTION POINTS ( DISCOMS / shall carry out an annual verification of the STATE GOVT ) energy accounting and audit facilities, the Discoms

58

i. Implementation of FRP including compliances of the mandatory conditions; ii. Regular tariff filing and rolling over of tariff orders ; iii. Regular pass through of fuel cost adjustment; iv. Reduction in AT&C losses as per 7.4. MANAGING THE RISKS projections v. Timely preparation and finalization of Time-bound and successful implementation of annual accounts the 24X7 Power Supply Scheme is dependent on the some key parameters that are critical to GoR the financial health of the distribution i. Timely release of subsidy to the segment. For providing 24x7 power supply to Discoms all households in the state, financial ii. Timely adherence to FRP implications on utilities for procuring implementation liabilities additional energy and per unit implication on tariff for additional energy has also been carried out and the details are at Annex- X.

Based on the exercise, a sensitivity analysis has been performed to understand the impact of various factors on the financial health of the

utilities. The sensitivity of various factors is shown as under:

Sensitivity Analysis Sl. No. Measure Degree of Sensitivity

1 T&D Loss Reduction Trajectory Highly sensitive 2 Tariff changes Highly sensitive (especially to initial years) 3 Power procurement optimization Highly sensitive 4 Extension of Interest Moratorium by Low sensitivity 2 years 5 Reduction of interest rates Highly sensitive 6 Higher feeder improvement investments Low sensitivity 7 More energy efficient consumption Low sensitivity* 8 Lower Agriculture Consumption Highly sensitive *This is because of lack of differentiation in AT&C loss and ABR in the domestic category. If these are considered, then sensitivity would be significant and in reverse direction. The details of sensitivity analysis are at Annex-XI

59

The performance of the utilities is sensitive to role of the PMU shall be to ensure the the risks, which must be handled consciously following: and mitigated accordingly. • Develop, compile and update (or require the same to be done) detailed project 1. The burden of short term liabilities needs plans for all capex related to 24X7 to be addressed for the sector to turn supply and related aspects (including around for providing reliable 24X7 supply; the renewable energy related infrastructure and monitoring 2. Investments needs to be efficiently and investments); rigorously planned and adequately • Monitor progress against the plans, financed through cost efficient means. analyse and advise the utilities on Wherever possible, private financing any delays and bottlenecks on should be promoted. critical measures to promote 24X7 3. Energy accounts and AT&C losses needs supply and also ensure broader to be monitored through a comprehensive financial viability by tracking program; measures on loss reduction, 4. Energy efficiency will be promoted at the investments, etc. and prepare end use consumption levels financial/physical progress of the 5. Power procurement and associated risks projects as per defined periodicity; (including fuel risks) needs to be managed • efficiently Timely availability of information 6. Release of timely subsidy by the State about various projects, their Government to the Discoms sources of the finance, the terms 7. Timely filing of tariff petitions by state and conditions that govern the utilities to rationalize the tariff so as to projects (including the externally reduce the gap between ACS & ARR aided projects and those supported by Government of India and Government of Rajasthan). The above measurers would require strong • implementation planning, project monitoring Identify the issues to where and Information Technology (IT) backbone. intervention of GoI is required The progress against the FRP and the and take up these issues with measures taken to manage the risks of concerned ministries under repeated slippage against the FRP objectives intimation to MoP shall be monitored independently through the • Arrange initial dialogue/interaction institutional mechanism. with the external agencies. Support negotiation arranged by the 7.5. INVESTMENT PLANNING AND concerned entity/department for MONITORING MECHANISM project assistance.

• Maintain data base records of The investments required for 24X7 power projects under its purview in a supply have already been articulated in the structured manner and ensure previous chapters. However it is important to timely availability when required ensure that the investments is made on time as • To organise the monthly/quarterly per plans and to deliver the desired results. review meetings chaired by Chief For effective implementation, a Project Secretary/Energy Secretary & Monitoring Unit (PMU) is proposed to be Director, PMC. established by government of Rajasthan. The

60

The PMU shall use state of the art IT tools to concerned entities. The PMU shall be ensure that the information on projects manned by an independent external agency tracked is always updated and available in the that shall be responsible for reviewing and manner required for decision making by reporting progress on a monthly basis. Government of Rajasthan and other

61

8. OTHER INITIATIVES

8.1. COMMUNICATION Successful implementation of 24X7 Power Supply Scheme requires clear communication among all the stakeholders across the value chain, including the consumers. In order to avoid potential roadblocks in implementation due to poor communication and flow of information, the following table lists the primary responsibility of each stakeholder and the corresponding method in which it will be carried out. A centralized corporate communication team can be formed at headquarters of the DISCOM for looking at activities of overall communication strategy. The financial situation in Rajasthan makes it imperative to raise tariffs while other initiatives including 24X7 supply are implemented. Such tariff increases would inevitably impact consumers and meet with resistance. To address this, the utilities would clearly communicate their plans on implementing the reliable 24X7 supply scheme along with the other reliability and efficiency improvement measures that they are implementing. A high level of involvement of the Government of Rajasthan will also be required. Table: Proposed communication responsibilities

Communication Objective Responsibility Frequency

“ Power for all” - Roll Out Plan Energy Secretary Quarterly

Power Supply Position CMD Transco Daily

CEO, State Energy Efficiency Energy Savings & Conservation Monthly Deptt

Planned Outages & Disruption CMD, Discom Daily

Real time feeder-wise Information CMD, Discom Daily

Status update on Deliverables Secretary, Energy Quarterly

CEO, State Renewable Energy Renewable Power Quarterly Deptt

Generation- Projects, PLF & Fuel MD, State Genco Monthly

Transmission Projects – Physical Progress and CMD, Transco Monthly Achievements

Distribution – Progress ,Achievements, Losses, CMD, Monthly Consumer Initiatives etc. Discom

62

and response capabilities. Technologies for sub-station automation, GIS, SCADA, 8.2. INFORMATION TECHNOLOGY DMS, OMS, etc., shall be adopted. For the (IT) INITIATIVES urban areas SCADA is quite useful for improving reliability and reduction of The need to adopt IT in every sphere of utility network downtime. operation is pervasive. Power is a complex product that must be consumed on a real time ‹ Regional Distribution Control Centres basis. The overall value involved in the (RDCC) within the State are proposed to process is very high. Even more importantly be established. These will initially cater to it touches all citizens. Yet, the information the principal load centres, but would systems that drive the operations of the sector thereafter be expanded to all load centres are generally very basic and information of the state. This will be a key initiative, transparency and consistency is poor. While not only for effectively managing 24X7 sporadic efforts have been made in the past to supply, but also thereafter for other improve this, quantum changes are required to functions like forecasting. increase IT adoption in all spheres of power ‹ Renewable Energy Management centres sector operation. shall be established and equipped with In Rajasthan, IT adoption on a massive scale adequate capabilities through financing will be pursued in the following areas: availed from KfW and ADB. ‹ At the corporate level, the operations need ‹ Smart Cities will be implemented to inter- to be integrated through implementation alia, reduce the intensity of electricity of Enterprise Resource Planning Systems consumption in the cities while (ERP). This would cover critical aspects simultaneously improving supply quality, like Finance and Accounts, Asset reliability and integration of renewable Management, Inventory Management, energy resources Human Resource Management, Project ‹ Power procurement optimization tools Management, Personal information will be implemented to reduce the power System (PIS). ERP will help in timely procurement costs and improve supply capitalization of asset, deriving better reliability. This shall be achieved through business value of investment etc. the institution of technically robust ‹ At the commercial operations level there forecasting, scheduling and dispatch (Unit is a need to comprehensively implement Commitment) and settlement tools. The Customer Management Systems (CMS) tools shall be used to ensure that the for undertaking customer related control room operators have the ability to processes including billing and take real time decisions to ensure cost collections, customer complaint reduction. management, new connection provision ‹ Project monitoring tools shall be etc.; incorporated in the PMU to ensure that ‹ Centralized Information & Monitoring progress on the investments in the state System for operational , enforcement & are monitored rigorously and bottlenecks litigation, vigilance activities and analysis identified. ‹ Power management would require the ‹ Standards of service specified under institution of technically capable Section 57 of the EA 2003 shall be controlling facilities equipped with tools monitored. The utilities shall use IT tools like SCADA and Distribution to gather the information with regards to Management Systems (DMS) that allow service standards with minimal manual for adequate visualization of the networks

62

intervention to ensure transparency and ‹ Department Level Committee : It is credibility. proposed that the Department level The above need to be implemented urgently, committee headed by the Energy and also need to be integrated with each other Secretary will be formed and shall to ensure that the systems are inter-operable undertake steps required to ensure (i.e., they can talk to each other). For this the the projects are progressing as per utilities shall evolve a detailed IT plan to the action plan. This 9999committee implement the above in a well-coordinated will undertake progress reviews on a manner. monthly basis. The committee will be constituted with the following members –Secretary (Energy), CMD 8.3. INSTITUTIONAL ARRANGEMENT RVPNL, MD of Discoms and RRECL. A strong monitoring framework is essential to ‹ District Level Committee – It is ensure the success of the “Power for all” proposed to constitute a district level scheme. The following structure is being committee headed by the District proposed to undertake regular monitoring of Collector to take action that is the progress of all initiatives being under- necessary to ensure the projects are taken in this scheme. completed in a timely manner and ‹ Government of India (GOI) Level address any issues pertaining to land Committee : It is proposed that this or other relevant approvals. The committee will review the overall committee will be constituted with progress of the scheme on a the following members – District quarterly basis and provide Collector, S.E RVPNL, S.E Discom necessary support to ensure a and RRECL representatives. coordinated response from the ‹ Project Monitoring Unit (PMU) – Central Govt. - where necessary. A project monitoring unit shall be The committee may be constituted set to up for monitoring the progress with the following members – PFC, of the works being undertaken under REC, CEA, SECI, EESL, Ministry this scheme. The PMU will operate of Power Ministry of Coal, and under the Secretary, Energy and MNRE. shall be operated by an external ‹ State Government Level independent agency. The PMU shall Committee : It is proposed that a be responsible for undertaking State level committee headed by the coordination, preparing the action Chief Secretary will be formed to plans and monitoring progress of all review the progress of the scheme works under the “Power for all” on a quarterly basis. This committee scheme. The PMU would also help will monitor the progress of the facilitate in tracking the action steps works undertaken as part of the and providing feedback to the scheme and issue directions to various committee that are proposed enable faster execution. This to be set up under the scheme. committee will be constituted with Government of India shall provide the following Principal Secretaries/ grants for the PMU operations. Secretaries of the Power, Finance, Urban Development, Agriculture The committees that are being proposed and other relevant departments along above are required to be set up at the earliest with the CMD/Chairman/MD of to kick start the whole scheme. It is RVUNL, RVPNL and the Discoms important that the committees keep meeting and RRECL. on a regular basis as per the frequency/ timelines mentioned above – to ensure that

63

the objectives set out under the “Power for satisfaction. The capacity building may also all” scheme are achieved. include consumer grievance system, awareness regarding importance of working 8.4. CAPACITY BUILDING with safety, outage management system, demand side management etc. It is also With the increase of IT in the Generation, imperative to state that for serving the Transmission & Distribution system and to consumers in a different way change of meet the expectations of 24 X 7 power supply mindset of the employees would be required. for the consumers in the state, it is important It is critical that Change Management to focus on capacity building of the initiatives are roll out and institutionalize employees for enhancement of technical through out the DISCOM for achieving better know-how for latest technological results. The details of the present employee in developments and to increase the consumer the Rajasthan Discoms is as under: Table 10.1: Employee base of Discoms Jaipur Discom Ajmer Discom Jodhpur Discom Total Regular 1 Technical a Officers 432 364 317 1113 b Junior engineers 739 723 764 2226 c subordinates 15268 12571 12041 39880 Total-1 16439 13658 13122 43219 2 Non-Technical a Officers 88 76 67 231 b Ministerial staff 2077 2095 1720 5892 c Fourth class 785 582 414 1781 Total -2 2950 2753 2201 7904 Total (1 + 2) 19389 16411 15323 51123

In view of the importance of the training on 25 Crores would be required for the same. new technologies, there is a requirement for Also at each district headquarters, training development and implementation of Human schools needs to be opened for training of Resource training programme so as to realize subordinate technical staff for which the dream of 24 X 7 power supply system in approximately Rs. 50 Crores will be required the state in its true sense. by considering Rs. 1.5 Crores for each district There is already a provision for Demand headquarter. Following training programmes Side Management (DMS) trainings under are proposed to be implemented for Discoms: various programmes of Bureau of energy 1. Two Weeks trainings for technical Efficiency (BEE) and the same should be staff including officers & engineers implemented to achieve the goal of 24 X 7 once in every two years. power for goal. The training for the class C & D employees are also being provided under 2. One week training for non-technical RAPDRP Part C scheme. officers every two years. A state level officers training institute may be 3. One week training for subordinate required to be opened in the state to fulfil the technical staff at each district ongoing training requirement for employees headquarters every year. of Discoms. A provision of approximately Rs.

64

9. YEAR WSIE ROLL OUT PLAN Year wise deliverables are given in the table below- Table : Summary of deliverables Deliverables Power for all - Roll out Units FY FY FY FY FY Total Plan 2014-15 2015-16 2016-17 2017-18 2018-19 Generation

State Sector U/C MW 850 0 2140 0 660 3650

Subject to Future State Projects MW 2920 coal linkage

Central Sector MW 145.65 0 264 214 746.5 1370.15 Private sector MW 500 500 Transmission Inter State Substation Nos - - - - - 0 Lines ckt kM 1310 600 290 380 - 2580 Green energy Corridor Substation - - - 3 2 5 Lines - - - 1680 1970 3650 Intra-state Substation Nos 29 24 12 21 20 106 Lines ckt KM 2,506 2,611 883 796 898 14,448 Green energy Corridor Substation Nos. 2 2 9 9 12 34 Lines ckt KM 309 536 320 594 1,030 2,789 Distribution AT&C Losses % 21.75% 20.00% 18.50% 17.25% 16.00% 15.00% 33/11kV S/s – As per Nos. 220 200 200 200 200 1020 state Plan 33/11kV S/s – Additional Nos. 0 66 66 66 66 264 required for 24x7 supply Separate Three phase system for 24x7 supply Nos 0 800 800 800 938 3338 to 2000-4000 population villages No of households to be Lakhs 4.5 6 6.5 6.5 6.5 30 electrified Nos. Renewable Energy Solar Capacity Addition MW 500 1000 1500 2000 2500 7500 Wind Power Addition MW 500 500 500 620 620 2740 Solar rooftop grid - MW 3.5 10 10 10 10 43.5 connected MW / 2 MW 5 MW 5 MW 5 MW 5 MW 22 MW Solar off-grid Nos (10000) (25000) (25000) (25000) (25000) 110000 Solar Agl pump-sets Nos. 5000 5000 5000 5000 5000 25000

65

Energy Efficiency LED Distribution - Lakhs Households Nos. 1800000 9000000 9000000 9000000 9000000 37800000 Ag Pump sets No 50000 250000 300000 300000 300000 12 Lakhs replacement Street lighting - %age Municipalities 12.5 12.5 25 25 25 100 Consumer care centres districts 5 7 8 10 3

66

10. SECTOR WISE INVESTMENT PLAN AND FUND REQUIREMENT (Rs in Crores)

FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks

15792.19 Funds have been Generation Under Construction 4717.34 5100.00 5024.26 837.18 113.41 (Out of total cost tied up on 80:20 (RVUN) (3650 MW) of Rs 28993.51 ration Crores)

Future projects 500.00 5000.00 5000.00 5000.00 3480.00 18980.00 (2920MW)

34772.19 Total ( Generation) 5217.34 10100 10024.26 5837.18 3593.41 (6570 MW) ( Out of total req of 47973.51 Crores)

1922 (Expenditure of RS ISTS 888 628 321 85 0 PGCIL 1694 Crores till 31 Inter March 2014) state PGCIL/Any other Green energy (PGCIL) 456 1178 2166 2875 1925 8,600 agency selected corridor by GOI

Inter state 1344 1806 2487 2960 1925 12216 PGCIL total

System 1133.55 957.6 481.5 912 1345 4829.65 State Plan strengthening

Green energy Support required Intra 293.5 970 1461 1102 855 4681.5 corridor under NCEF Transmission state Others 383 452 438 372 373 2018 State plan Intra state 1810.05 2379.6 2380.5 2386 2573 11529.15 total State plan Base capex 728 615 638 641 641 3263 State plan Rural electrification including release of new 785 822 734 908.74 954.17 4203.91 State Plan agriculture connections Total (state Plan) 1513.00 1437.00 1372.00 1549.74 1595.17 7466.91 Schemes for which GoI assistance is required

RGGVY 12 th plan (5 Schemes have schemes under sanction, 0 63 250 250 250 813 been submitted to one is under preparation REC for sanction ) GoR may identify the H/H which can be grid Electrification of un connected or req. electrified / partially off grid solutions electrified Dhanis / 0 450 450 450 489 1839 in next 3 months Distribution Habitations having and a detailed population less than 100 plan may be prepared in this regard RAPDRP- Part- A Addl. Funding for IT 0 117 117 0 0 234 enablement under RAPDRP – Part A (For

67

towns with population less than 30,000) RAPDRP- Part- B Addl. 300 153 0 0 0 453 Funding under R- APDRP Part-B due to increase in ordered Prices (JVVNL 293 Cr. & Jd.VVNL:160 Cr.) Investment under 90 57.23 0 0 0 147.23 RAPDRP part B for enabling SCADA in Jaipur city RAPDRP total 390 327.23 117 0 0 834.23 May be covered Feeder improvement 300 800 400 0 0 1,500 under GOI new program schemes which Substation improvement 300 100 0 0 0 400 are being program finalised by MOP Additional 33 kV sub- 0 111 111 111 111 444 as per rules of station for 24x7 supply the schemes / in rural areas policies Separate 3 Phase system 0 241 241 241 284 1007 for villages of population 2000 to 4000 Technology 20 50 40 0 0 110 improvements DDG (Solar) 20 80 0 0 0 100

Capacity building 5 25 25 20 0 75 Total GOI Assistance required 1035 2247.23 1634 1072 1134 7122.23 GoI Schemes already Sanctioned and under implementation GoI Schemes RGGVY 12 th plan 150 450 450 403.19 0 1453.19 Sanctioned already (sanctioned 28 schemes) sanctioned & RAPDRP- Part- A for IT 185 0 0 0 0 185 Sanctioned under enablement under Rs 315.95 Cr implementation RAPDRP – Part A (For from above Rs towns with population 130 Cr disbursed less than 30,000) RAPDRP Part -A 50 61.83 0 0 0 111.83 Sanctioned SCADA projects for 5 Rs. 157.11 Cr. big Towns and Rs. 45.28 Cr. disbursed RAPDRP- Part-B – 81 500 492 992 Sanctioned Rs towns 1540 Cr, from above Rs. 548 cr. Disbursed from GoI/Counter Funding Total of sanctioned 885 1003.83 450 403.19 0 2742.02 GoI Schemes

Renewable Wind 3000 3000 3000 3720 3720 16440 IPP energy Solar 3500 70 00 105 00 140 00 17 500 525 00 IPP (including support required under NCEF for Rs 2500 Crores for VGF funding of

68

1000 MW @ 2.5 Crore/ MW) Grid connected solar 25 70 70 70 70 305 Support required rooftops under NCEF Solar off-grid systems 37 92.5 92.5 92.5 92.5 407

Solar pump systems 360 360 360 360 360 1800 Renewable total 6922 10522.5 14022.5 18242.5 21742.5 71452

Energy Efficiency 504.8 2097.2 2504.8 2504.8 2562.4 10174 EESL/BEE

69

ANNEXURES

Annexure-I Circle-wise AT&C loss trajectory

FY 2013-14 FY 15 FY 16 FY 17 FY 18 FY 19 FY 20 FY 21 FY 22 S Name of % % N Circle / Distrib Realisati ATC ATC ATC ATC ATC ATC ATC ATC ATC o Discom ution on 1 2 Loss3 4 5 6 7 8 9 10 1 1 12 1 3 1 Alwar 28.82 97.40 30.67 25.00 22.00 21.00 19.75 18.50 17.00 16.00 15.00

2 Bharatpur 41.12 91.14 46.33 35.00 30.00 26.00 22.00 20.00 19.00 18.00 17.50

3 Dholpur 49.23 90.59 54.01 40.00 35.00 30.00 25.00 21.00 19.00 18.00 17.00

4 Dausa 40.72 96.61 42.73 33.00 29.00 25.00 22.00 20.00 18.00 17.00 16.00

5 Karauli 44.00 88.85 50.25 35.00 30.00 26.00 22.00 20.00 19.00 18.00 17.00

6 JCC 9.83 99.74 10.06 9.70 9.60 9.50 9.25 9.00 8.75 8.50 8.25

7 JPDC 29.89 97.21 31.84 25.00 22.00 20.00 19.00 18.00 16.75 15.25 14.50 Sawaimadh 8 31.24 93.85 35.46 24.85 22.00 20.00 18.00 16.67 15.68 16.00 15.00 opur 9 Tonk 26.33 97.76 27.98 23.00 21.00 19.00 18.00 17.00 16.00 15.50 15.00

10 Jhalawar 41.09 83.60 50.76 35.00 30.00 26.00 23.00 20.00 18.00 17.00 16.00

11 Baran 31.27 81.42 44.04 28.00 24.00 31.00 20.00 19.00 18.00 17.00 16.00

12 Kota 24.74 93.34 29.75 19.00 17.86 18.00 17.00 16.00 15.50 15.00 14.50

13 Bundi 26.48 98.05 27.92 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

Total 27.85 96.07 30.69 24.50 22.50 20.50 19.00 17.50 16.00 15.00 14.39 Ajmer Discom 1 Ajmer City 17.1 98.9 18.0 16.00 15.00 14.00 13.00 12.00 11.00 10.00 9.00

2 Ajmer Distt 10.8 99.4 11.4 11.00 10.90 10.80 10.70 10.60 10.40 10.30 10.00

3 Bhilwara 14.29 99.51 14.71 14.00 13.00 12.50 12.00 11.75 11.50 11.25 11.00

4 Nagaur 30.34 97.84 31.85 26.50 23.50 21.50 20.50 18.50 16.00 17.00 16.00

5 Banswara 24.80 96.90 27.13 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

6 Dungarpur 16.74 98.13 18.29 16.75 16.25 16.00 15.90 15.65 15.35 15.25 15.00

7 Chitrgrh 23.13 98.05 24.63 22.00 21.00 20.00 19.00 18.00 17.00 16.50 16.00

8 Prtapgrh 16.01 95.65 19.66 18.00 17.75 17.50 17.25 17.00 16.90 16.50 16.00

9 Rajsamnd 13.94 99.80 14.11 13.00 12.50 12.00 11.50 11.00 10.50 10.75 10.00

10 Udaipur 17.80 99.47 18.23 17.00 16.00 15.50 15.00 14.75 14.50 14.25 14.00

11 Jhunjhunu 24.87 97.64 26.65 23.00 21.00 20.00 19.00 18.00 17.00 16.00 15.00

12 Sikar 21.92 98.43 23.14 21.00 20.00 19.00 17.75 17.00 16.75 16.50 16.00

Total 20.69 98.63 21.77 19.60 18.50 17.50 16.50 15.50 14.50 14.25 13.51 Jodhpur Discom 1 Barmer 19.1 98.5 20.2 19.00 18.50 18.25 18.00 17.50 17.00 16.50 16.00

2 Jaiselmer 20.5 97.4 22.6 19.50 19.00 18.50 18.00 17.50 17.00 16.50 16.00 Jodhpur 3 9.78 94.94 14.34 9.50 9.10 9.20 9.20 9.10 9.00 8.90 8.80 City Jodhpur 4 29.71 97.17 31.70 26.00 24.00 22.00 21.00 20.00 19.00 18.00 16.00 Distt 5 Jalore 14.14 98.21 15.67 14.00 13.50 13.00 12.50 12.00 11.50 11.00 10.50 6 Pali 9.4 97.3 11.8 10.50 10.00 9.90 9.75 9.50 9.35 9.25 9.00

7 Sirohi 11.0 93.6 16.8 13.50 12.90 12.75 11.50 11.25 10.90 10.80 10.00

8 Bikaner 27.44 93.58 32.10 24.00 22.00 21.00 20.00 19.00 18.00 17.00 16.00

9 Churu 29.83 95.98 32.66 25.00 22.00 21.00 20.00 19.00 18.00 17.00 16.00

10 HNGr 14.69 96.99 17.26 15.50 14.25 13.50 13.25 12.90 12.50 12.25 12.00

11 SNGr 16.22 98.67 17.33 15.00 14.75 14.25 13.90 13.30 12.90 12.50 12.00

Total 23.43 96.35 26.22 21.14 19.22 17.30 16.00 15.00 14.50 14.25 13.84 G.Total 24.38 96.91 26.71 21.75 20.00 18.50 17.25 16.00 15.00 14.50 13.96

70

Annexure-II Li st of Discom wise District wise town getting 24 Hrs. Supply

JAIPUR DISCOM Sr. No. Distt. / MTs Sr. No. Distt. / MTs 1 DHQ Alwar 33 KOTPUTLI 2 Behror 34 VIRAT 3 Khairthal 35 SHAHPURA 4 Tijara 36 DHQ-JHALAWAR 5 Kherli 37 J.PATAN 6 Rajgarh 38 AKLERA 7 DHQ-BTP 39 B.MANDI 8 NADBAI 40 SUNEL 9 Bayana 41 DHQ-BARAN 10 Weir 42 ANTA 11 Bhusawar 43 MANGROL 12 Deeg 44 CHHABRA 13 Kaman 45 DHQ- BUNDI 14 Nagar 46 K.PATAN 15 Kumher 47 KAPREN 16 DHQ-Dholpur 48 LAKHERI 17 Bari 49 INDERGARG 18 Rajakhera 50 NAINWA 19 DHQ-Dausa 51 DHQ- KOTA 20 Lalsot 52 KAITHOON 21 Bandikui 53 SANGOD 22 Hindaun 54 RMG 23 Todabhim 55 DHQ- SWM 24 DHQ-Karauli 56 GGC 25 DHQ-Jaipur 57 DHQ- Tonk 26 CHOMU 58 Malpura 27 BAGRU 59 Uniara 28 CHAKSU 60 Newai 29 PHULERA 61 Deoli 30 SAMBHAR 62 Toda 31 RENWAL 32 JOBNER

71

AJMER DISCOM Sr. No. Distt. / MTs Sr. No. Distt. / MTs 1 DHQ- Ajmer 36 DHQ- Pratapgarh 2 Pushkar 37 Choti Sadri 3 Beawar 38 DHQ- Rajasmand 4 39 Kankroli 5 Nasirabad 40 Nathdwara 6 Kekri 41 Amet 7 Sarwar 42 Deogarh 8 Bijainagar 43 DHQ- Udaipur 9 DHQ- Bhilwara 44 Kanore 10 Gangapur 45 Bhinder 11 Asind 46 Fatehnagar 12 Mandalgarh 47 Salumber 13 Bijoliya 48 DHQ- Jhunjunu 14 Shahapura 49 Pilani + Vidha Vihar 15 Jahazpur 50 Surajgarh 16 Gulabpura 51 Bagar 17 Mertacity 52 Chirawa 18 DHQ- Nagaur 53 Mandawa 19 Mundwa 54 Bissau 20 Kuchera 55 Mukandgarh 21 Kuchaman 56 Nawalgarh 22 Nawa City 57 Udaipurwati 23 Deedwana 58 Khetri 24 Parbatsar 59 DHQ- Sikar 25 Makrana 60 Laxmangarh 26 DHQ- Banswara 61 Fatehpur 27 Kusalgarh 62 Ramgarh Shekhawati 28 DHQ- Dungarpur 63 Losal 29 Sagwara 64 Srimadhopur 30 DHQ- Chittorgarh 65 Reengus 31 Begun 66 Neemkathana 32 Rawat Bhata 67 Khandela 33 Kapasan 34 Nimbahera 35 Badi Sadri

72

JODHPUR DISCOM Sr. No. Distt. / MTs Sr. No. Distt. / MTs 1 DHQ-Jodhpur 30 DHQ- Sri Ganganagar 2 Phalodi 31 Sadulshahar 3 Bilara 32 Kesrisinghpur 4 Pipar City 33 Raisinghnagar 5 DHQ-Pali 34 Gajsinghpur 6 Sojat City 35 Padampur 7 Jaitaran 36 Sri Karanpur 8 Falna 37 Suratgarh 9 Bali 38 Sri Bijaynagar 10 Sadari 39 Anoopgarh 11 Sumerpur 40 DHQ- Hanumangarh Jn. 12 Takhagarh 41 Hanumangarh Town 13 Rani 42 Pilibanga 14 DHQ- Sirohi 43 Bhadra 15 Sheoganj 44 Nohar 16 Pindwara 45 Rawatsar 17 Abu Road 46 Sangaria 18 MT.Abu 47 DHQ- Churu 19 DHQ-Jalore 48 Ratannagar 20 Bhinmal 49 Rajgarh 21 Sanchore 50 Taranagar 22 DHQ- Barmer 51 Ratangarh 23 Balotra 52 Rajeldesar 24 DHQ- Jaisalmer 53 Sardarsahar 25 Pokran 54 Sujangarh 26 DHQ- Bikaner 55 Bidasar 27 Nokha 56 Chhapar 28 Deshnoke+GSR 57 Ladanu 29 Dungargarh Town

73

Annexure-III Status of households electrification in the No. of Villages S.No. Name of Discom Households Electrification in the No. of villages Total

0% 0%> to =>10%to =>20% to 30% and <10% <20% <30% More

1 2 3 4 5 6 7 8 1 Jaipur 887 480 609 779 11677 14432 2 Ajmer 1127 1051 776 776 11235 14965 3 Jodhpur 1678 1172 1074 1067 8818 13809 Sector as whole 3692 2703 2459 2622 31730 43206

74

Annexure IV : The Intra State Abstract of Transmission Investment Plan upto 2018-19 is as under:

75

Annexure-V Consumer category breakup (as on 31 March 2014)

Domestic Domestic Agriculture Industrial Commercial Others Total rural urban Number of 58,20,819 30,26,944 12,01,073 2,89,615 10,98,651 47,823 1,14,84,925 Consumers Connected 3,729 3586 10,547 3,299 2606 433 24,200 Load (In MW) Energy 3578 5432 17,839 11,824 3,226 786 42,686 consumption (In MU) Per unit Tariff 4.32 5.65 3.37 5.94 7.28 7.04 4.81 (Rs/unit)

Billing 1547 3071 6,010 7,024 2,348 553 20,553 (Rs. in Crores)

Collection (Rs. 1439 2967 5,087 6,902 2,326 493 20,014 in Crores)

76

Annexure VI

Key energy input and related figures

S.No. 2010-11 2011-12 2012-13 2013-14 A Energy Availability at MU 47,154.78 50,068.92 55,342.53 59,156.17 Generator Point

B Energy sold through MU 103.56 15.16 31.05 276.63 exchange

C Net Energy Availability MU 47,051.22 50,053.76 55,311.48 58,879.54 (=A-B) for the state

D Transmission Loss MU 2713.79 (5.76) 2907.03 3111.84 2432.67 % (5.80) (5.62) (4.13)

E Net Energy Availability MU 44,337.43 47,146.73 52,199.64 56,446.87 (=C-D) at Discom Periphery

F Sales MU 34,448.92 37,903.78 42,160.22 42,686.35

G Distribution Loss MU 9,888.51 9,242.95 10,039.42 13,760.52 (=E-F) H % Distribution loss % 22.30 19.60 19.23 24.38

I Collection efficiency % 99.45 99.43 98.80 96.88

J AT&C loss of Discoms % 22.72 20.06 20.20 26.74

77

Annex-VII

MNRE Schemes/options for electrification of remote households

OPTION I: • System proposed: ∑ 100 Wp Solar system will be provided to each household ∑ This system would include: ‹ 5 Nos. of D.C. operated LED lights (2 Luminaires of 5 watts each and 3 Luminaires of 8 watts each) for 4 hours operation each day. ‹ One D. C. Fan of 12 watts for 10 hours operation each day. ‹ One D.C. B&W TV 12 watts for 4 hours operation each day can be attached or any other appliance can be powered ‹ One Mobile Charger

• Load Estimation:

S. No. Load Description Nos. Unit Load Total Hours of use per Energy Consumption (W) Load day (Wh)/day [DC] (W) 1 D.C. operated LED 5 8WX3 34 4 hours 136 Lights 5WX2 2 D.C. Fan 1 12Wx1 12 10 hours 120 3. D.C. B&W TV 1 12 12 4 hours 48 4. Mobile Charger 1 5 5 3 hours 15 Total 319 Say 0.3units/day

• System requirement to meet consumer demand for above consumption profiles i.e. 0.3 units per day is estimated with autonomy for two(2) non sunshine day is as under:

S. No. System Consumption Profile (with Two day Autonomy) 1 Solar PV Module 100 Wp 2 Battery Storage (Tu bular type) 12V, 75 AH

• Estimated Project Cost: Broad estimated cost for system for typical household is : Rs. 25,000/-

OPTION II:

• SYSTEM PROPOSED: a. 200 Wp Solar system will be provided to each household b. This system would include: ‹ 5 Nos. of D.C. operated LED lights (2 Luminaires of 5 watts each and 3 Luminaires of 8 watts each) for 6 hours operation each day. ‹ One D. C. Fan of 24watts (or 2 fans of 12 watts each) for 12 hours operation each day.

78

‹ One D.C. colour TV 30 watts for 4 hours operation each day can be attached or any other ppliance cane be powered. ‹ One Mobile Charger

• Load Estimation:

S. No. Load Description Nos. Unit Load Total Hours of use per Energy Consumption (W) Load day (Wh)/day [DC] (W) 1 D.C. operated LED 5 8WX3 34 6 hours 204 Lights 5WX2 2 D.C. Fan* 1 24W X1 24 12 hours 288 or 12Wx2 3. D.C. Color TV 1 30 30 4 hours 120 4. Mobile Charger 1 5 5 3 hours 15 Total 627 Say 0.6 units/day

• System requirement to meet consumer demand for above consumption profiles i.e. 0.6 units per day is estimated with autonomy for two (2) non sunshine day is as under:

S. No. System Consumption Profile (with Two day Autonomy) 1 Solar PV Module 200 Wp 2 Battery Storage (Tubular type) 12V, 150 AH

• Estimated Project Cost: Broad estimated cost for system for typical household is: Rs. 50,000/-

OPTION III

∑ TARGET GROUP : Village with a cluster of 15 “House Holds”, which cannot be connected to the Grid ∑ Proposed Solution : Through Solar PV Mini Grid And Central Control Room • Load Estimation:

S. No. Load Description Nos. Unit Load Total Hours of use per Energy Consumption (W) Load day (Wh /day) [AC] (W) 1 Power for A.C. 5 8WX3 34 6hours 204 LED Lights 5WX2 2 Power for A.C. Fan 1 50W 50 6hours 300 and or Power for A.C. Loads like Color TV, Set top box / PC and Mobile Charger etc. Total 504 say 0.5 unit/day

79

i. Proposed Load for each house hold: each house hold = 500 Whrs. ii. Total Load for 15 households = 7500 Whrs.

iii. Solar System Specs. for the above Load: iv. Solar PV Panel = 2.5 KWp v. Battery = 48V, 600AH vi. Off Grid PCU (Inverter and Charge controller) =48 V , 2.5 KW

vii. A central control room for batteries and PCU viii. Other balance of System Components

ix. Budgeted cost of the System is Rs. 7.5 Lakhs OPTION IV:

• TARGET GROUP : Villages with 50 “House Holds”, which cannot be connected to the Grid • Proposed Solution : Through Solar PV Mini Grid And Central Control Room

• Load Estimation:

S. No. Load Description Nos. Unit Load Total Hours of use per Energy Consumption (W) Load day (Wh /day) [AC] (W) 1 Power for A.C. 5 8WX3 34 6hours 204 LED Lights 5WX2 2 Power for A.C. Fan 1 50W 50 10hours 500 and or Power for A.C. Loads like Color TV, Set top box / PC and Mobile Charger etc. Total 704 say 0.7 unit/day

(i) Proposed Load for each house hold: each house hold =700 Whrs. (ii) Total Load for 50 households = 35000 Whrs.

(iii) Solar System Specs. for the above Load: (iv) Solar PV Panel =12.5 KWp (v) Battery = 240V, 600AH (vi) Off Grid PCU (Inverter and Charge controller) =240 V , 12.5 KW

(vii) A central control room for batteries and PCU (viii) Other balance of System Components

80

(ix) Budgeted cost of the System is Rs. 30 Lakh

PROPOSED SCHEME:

• MNRE may provide subsidy at the rate of 40%.through NCEF

• A network of local technicians will have to be created for service and repair. • Some local agencies / NGO’s will have to be involved to ensure upkeep and proper use through awareness and training of users. • The beneficiary may be asked to keep some fixed amount as “Reserves” like for battery replacement in future

81

Annexure VIII

Details of Distribution Investment Planned: Schemes covered under State Plan.

Sl. Particulars Unit FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total No. Sub Transmission & A Distribution programme. SS Addition No. 220 200 200 200 200 1020 PTR Addition in SS No. 30 30 30 30 30 150 Feeder Addition Km 11910 9070 9900 10000 10000 50880 DTR Unit Addition No. 14000 13000 13000 13000 13000 66000 SS Addition Rs. Cr 369.06 335.46 335.46 335.46 335.46 1711 PTR Addition in SS Rs. Cr 14.91 14.91 14.91 14.91 14.91 75 Feeder Addition Rs. Cr 328.716 250.332 273.24 276 276 1404 DTR Unit Addition Rs. Cr 15.4 14.3 14.3 14.3 14.3 73 Total Base Capex Rs. Cr 728 615 638 641 641 3263 requirement

B Rural Electrification including release of Ag. Connection New Consumers Capex Rs. Cr 748.00 785.40 699.77 865.90 909.20 4133.17

Civil Infrastructure Rs. Cr 27.00 28.35 25.23 31.26 32.82 149.19 development cost

Miscellaneous Capex Rs. Cr 10.0 0 8.25 9.00 11.58 12.16 55.26 Total –B Rs. Cr 785.00 822.00 734.00 908.74 954.17 4203.91 Total I= A+B 1513.00 1437.00 1372.00 1549.74 1595.17 7466.91

82

Annex-IX Details of Investment Planned for which assistance is required from Central Govt (in Cr. Rs.) FY14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 Total Remarks

RAPDRP RAPDRP- Part- A Addl. 117 117 0 0 0 234 May be Funding for IT covered enablement under under GOI RAPDRP – Part A (For new towns with population schemes less than 30,000) which are being finalised by MOP .

RAPDRP - Part - B Addl. 300 153 0 0 0 453 Revised cost Funding under R-APDRP estimates Part-B due to increase in may be ordered Prices submitted (JVVNL 293 Cr. & to PFC for Jd.VVNL:160 Cr.) approval of Investment under 90 57.23 0 0 0 147.23 Steering RAPDRP part B for Commtt. enabling SCADA in Jaipur city RAPDRP total 507 327.23 0 0 0 834.23 Under RGGVY 12 th plan (5 0 63 250 250 250 813 Submitted RGGVY schemes under sanction, to REC for one is under preparation sanction ) under RGGVY Investment for 0 450 450 450 489 1839 May be electrification of un covered electrified / partially under under electrified Dhanis / various Habitations having schemes of population less than 100 MNRE. Feeder improvement 300 800 400 0 0 1,500 24x7 Supply May be program covered Substation improvement 300 100 0 0 0 400 under GOI program new Additional 33 kV sub- 0 111 111 111 111 444 schemes station for 24x7 supply in which are rural areas being Separate 3 Phase system 0 241 241 241 284 1007 finalised by for villages of population MOP. 2000 to 4000 Technology 20 50 40 0 0 110 improvements DDG (Solar) 20 80 0 0 0 100

Capacity building 5 25 25 20 0 75 Total GOI Assistance 1152 2247.23 1517 1072 1134 7122.23 required

83

Annexure X

IMPLICATION ON TARIFF of 24x7 PFA

Item Unit 2014-15 2015-16 2016-17 2017-18 2018-19 1 Additional Energy available MUs 4,768 10,178 14,475 22,574 29,630 for billing 2 Procurement of Additional MUs 6,422 13,392 18,677 28,665 37,038 Energy for supply 3 Cost of Power Purchase @ Rs. Rs. 2,890 6,026 8,405 12,899 16,667 4.50/kWh Crores 4 Annual T&D Infrastructure Rs. - - 1, 244 2,022 2,373 Cost (Rs. Crores) Crores 5 Total cost of additional energy Rs. 2,890 6,026 9,649 14,921 19,040 Crores 6 Average Revenue on Subsidy Rs./ 4.84 4.84 4.84 4.84 4.84 received basis kWh

7 Average Revenue received Rs. 2,308 4,926 7,006 10,926 14,341 from sale of additional energy Crores 8 Additional Cost Rs. 582 1,100 2,643 3,996 4,699 Crores 9 Total Energy Sale (Existing + MUs 47,454 52,864 58,789 65,261 72,316 Additional Energy) 10 Impact on Tariff Rs./ 0.12 0.21 0.45 0.61 0.65 kWh

84

Annexure XI

Sensitivity Analysis and Results

The table below lists the parameters for which sensitivity analysis has been conducted.

Sensitivity Analysis S no. Sensitivity Analysis 1 Faster AT&C Loss reduction 2 Slower AT&C Loss reduction 3 Lower tariff increases 4 Higher tariff increases (doubled) in first two years 5 Power purchase costs optimized (rates reduced by average of 5%) 6 Interest pay-outs on past STL capitalized for 2 additional years - till FY 17, instead of FY 15 7 Interest rate reduction of 2 percent fo r STL for FY 15 and FY 16 8 Higher Rural supply/associated investment costs 9 Lower/more efficient consumption in households 10 Lower Agricultural Sales Growth

i. Sensitivity to AT&C Loss Reduction

High and Low reduction in AT&C losses, relative to the base case reduction, has been considered in this analysis

Base Case and Sensitivity Scenario (AT & C losses)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 21.75% 20.00% 18.50% 17.25% 16.00% Base Case Loss Trajectory 24.40% Sensitivity: High Reduction Case Loss Trajectory 22.06% 19.72% 17.38% 15.04% (2.34% / year) to reach ~ 15 % by FY 2018-19 25.74% Sensitivity: Low Reduction Case Loss Trajectory (1 % / Year) 24.74% 23.74% 22.74% 21.74%

Base Case and Sensitivity Scenario (Percentage Change Per Year)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 5.0% Base Case Loss Trajectory 1.8% 1.5% 1.3% 1.3%

Sensitivity: High Reduction Case Loss 2.34% 2.34% 2.34% 2.34% 2.34% Trajectory (2.34% / year) to reach ~ 15 % by FY 2018-19 Sensitivity: Low Reduction Case Loss Trajectory (1 % / Year) 1.00% 1.00% 1.00% 1.00% 1.00%

85

Result: The table below shows the impact on Financial Gap under the three scenarios listed above. Clearly, higher AT&C loss reduction has a significant impact on the Financial Gap. Without the past liabilities impact, the state can return to profitability by 2016-17 even with low AT&C loss reduction. Impact of AT&C Loss Reduction - Rs./Kwh

With Past Liability Impact 2013- 2014- 2015- 2016 2017 2018- 14 15 16 -17 -18 19 Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: High Reduction Case Loss Trajectory (2.02) (1.76) (1.22) (0.74) (0.51) (0.28) Sensitivity: Low Reduction Case Loss Trajectory (2.02) (1.86) (1.42) (1.06) (0.95) (0.85) Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: High Reduction Case (1.33) (1.03) (0.14) 0.58 0.74 0.90 Loss Trajectory Sensitivity: Low Reduction Case Loss Trajectory (1.33) (1.12) (0.32) 0.31 0.39 0.47

ii. Sensitivities to Tariff Increase

Low tariff increase (4% per year) and higher increase in first 3 years (16% per year) has been assumed to analyze the sensitivity of financial Gap to extent of tariff revisions. Base Case and Sensitivity Scenario (Percentage) Scenario Assumptions 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Average Tariff: Base Case 10.0% 18.0% 10.0% 8.0% 4.0% (as per GoR inputs) Sensitivity: L ow Tariff Increase 4.38% 4.38% 4.31% 4.29% 4.18% (~ 4% / year) Sensitivity: Higher Tariff Increase (first 3 years) - 16.00% 16.00% 16.00% 8.30% 8.19% 16% / year for year 1,2 and 3, followed by ~ 8%/year Base Case and Sensitivity Scenario (Rs. / Unit)

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 Average Tariff: Base Case (as per GoR inputs) 5.33 6.29 6.92 7.47 7.77

Sensitivity: Low Tariff Increase (~ 4%/year) 5.06 5.28 5.51 5.74 5.98

Sensitivity: Higher Tariff Increase (first 3 years) - 5.62 6.52 7.56 8.19 8.86 16%/year for year 1,2 and 3, followed by 8%/year

86

Result: The table below shows the impact on Financial Gap in the tariff hike scenarios listed above. As seen in the table below, a high tariff increase in the first 3 years leads to considerable impact on Financial Gap. Including past liabilities, the state is expected to eliminate its losses by 2016-17. Impact of Tariff Increase - Rs./Kwh With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29)

Sensitivity: Low Tariff Increase (2.02) (1.87) (2.17) (2.29) (2.64) (2.76)

Sensitivity: Higher Tariff Increase (first 3 (2.02) (1.27) (0.77) 0.14 0.46 1.11 years) Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84

Sensitivity: Low Tariff Increase (1.33) (1.13) (1.02) (0.77) (0.99) (0.96)

Sensitivity: Higher Tariff Increase (first 3 (1.33) (0.56) 0.23 1.30 1.48 1.94 years)

iii. Sensitivity to Cost of Power Procurement

A 5% average reduction in power purchase costs over the base case has been assumed.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case Power Purchase Cost (Rs. Cr.) 22341 25511 28472 34960 40773

Sensitivity: 5% Lower Power Purchase Cost (Rs. Cr.) 21113 24108 26906 33037 38530

Result: The table below shows the impact on Financial Gap. Clearly, the lowering of procurement costs, which make up close to 70% of the total costs of Discoms, has a significant impact on the existing Financial Gap levels. Impact of Power Purchase Cost Reduction - Rs./Kwh With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19

Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: Lower PP Cost (2.02) (1.30) (0.74) (0.27) (0.04) 0.17 Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: Lower PP Cost (1.33) (0.60) 0.26 0.92 1.05 1.15

87

iv. Sensitivity to Interest Payments

To analyse the sensitivity to interest payment, interest on past STL is assumed to be capitalized for additional 2 years, beyond FY15. Also, another case in which Interest on Loans for first two years (FY 15 and FY 16) has been assumed to be reduced to 10% has been considered. Result:

The table below shows the impact on Financial Gap.

Impact of Additional Interest Capitalization/Reduction - Rs. /Kwh With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: Additional 2 year capitalization of (2.02) (1.58) (0.78) (0.10) (0.20) (0.28) interest on STL Sensitivity: STL Interest Reduced to 10% (FY (2.02) (1.45) (0.86) (0.36) (0.39) (0.23) 15 to 17) Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: Additional 2 year capitalization of (1.33) (0.86) (0.00) 0.65 0.75 0.84 interest on STL Sensitivity: STL Interest Reduced to 10% (FY (1.33) (0.86) (0.00) 0.65 0.75 0.84 15 to 17)

v. Sensitivity to Investment Costs

To analyze the sensitivity to investment costs, Higher Investment Costs (Rural Electrification and Feeder Improvement Costs increased by 50%) have been assumed. Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case RE & Feeder Segregation Capex 2650 950 - - -

Sensitivity: High Capex 2650 1700 750

Result: The table below shows the impact on Financial Gap. Considering that other parameters improve as per the base case, Higher Capex has a negligible impact on the Financial Gap.

88

Impact of Higher Investment Costs - Rs./Kwh With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: High Capex (2.50) (1.89) (1.23) (0.78) (0.61) (0.41) Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: High Capex (1.79) (0.92) (0.13) 0.48 0.62 0.71

vi. Sensitivity to Consumption

For more energy efficient consumption, Urban and rural household consumption is assumed to reduce by 10%, 2016-17 onwards. Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case Urban and Rural Consumption - kwh p er HH 5.5 & 2 6.1 & 2.3 6.8 & 2.5 7.4 & 8 & 3 2.75 Sensitivity: 10% Lower Consumption from FY 18 5.5 & 2 6.1 & 2.3 6.1 & 2.3 6.6 & 2.5 7.2 & 2.7

Result: The table below shows the impact on Financial Gap. The CoS increases because lesser units are sold for the same infrastructure/O&M costs. However, if the higher AT&C losses and lower ABR for small customers are taken into account, Energy Efficiency would increase gains and reduce subsidy burden. Impact of Efficient Energy Consumption - - Rs./Kwh With P ast Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: Energy Efficient (2.02) (1.58) (1.06) (0.69) (0.55) (0.40) Consumption Without Past Liability Impact

Ba se Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: Energy Efficient (1.33) (0.86) (0.00) 0.62 0.70 0.78 Consumption

89

vii. Sensitivity to Agriculture Sales Growth

Sensitivity has been analyzed by reducing the growth rate of agricultural sales in the future years.

Base Case and Sensitivity Scenario

Scenario Assumptions 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case: 9.5% p.a 9.50% 9.50% 9.50% 9.50% 9.50% Sensitivity: 4% p.a 4% 4% 4% 4% 4%

Result: The table below shows the impact on Financial Gap. Lower agricultural growth rate has a significant impact on the financial gap. Impact of Agri. Growth Rate With Past Liability Impact 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 Base Case (2.02) (1.58) (1.06) (0.62) (0.45) (0.29) Sensitivity: Low Growth (2.02) (1.62) (1.17) (0.80) (0.73) (0.66) Without Past Liability Impact

Base Case (1.33) (0.86) (0.00) 0.65 0.75 0.84 Sensitivity: Low Growth (1.33) (0.89) (0.07) 0.55 0.59 0.63

90

Abbreviations

AVVNL Ajmer Vidyut Vitran Nigam Limited ALDC Area Load Dispatch Center APTEL Appellate Tribunal for Electricity AT&C Aggregate Technical and Commercial BPL Below Poverty Line BU Billion Units CAGR Compound Annual Growth Rate CEA Central Electricity Authority ckt kms cir cuit kilometers CMS Customer Management Systems Cr. Crores DC Direct Current Discom Power Distribution Company DMS Distribution Management Systems EA Electricity Act of 2003 EESL Energy Efficient Street Lighting EHV Extra High Voltage ERP Enterprise Resource Planning Systems ESCO Energy Services Companies FIP Feeder Improvement Programme FIs Financial Institutions FRP Financial Restructuring Plan FY Financial Year Genco Power Generation Company GIS Geographic Information Systems GoI Government of India GoR Government of Rajasthan InSTS Intra state transmission system IPP Independent Power Producer ISTS Interstate transmission system IT Information Technology JVVNL Jaipur Vidyut Vitran Nigam Limited JdVVNL Jodhpur Vidyut Vit ran Nigam Limited kV Kilovolts LED Light-Emitting Diode M&V Measurement and Verification MD Managing Director MNRE Ministry of New and Renewable Energy MoC Ministry of Coal MoEF Ministry of Environment and Forests MoP Ministry of Power

91

Mtpa Metr ic tonnes per annum MU Million Units MVA Megavolt ampere MW Megawatt NCEF National Clean Energy Fund NLDC National Load Despatch Centre PFC Power Finance Corporation PGCIL Power Grid Corporation of India PMC Project Management Cell PMU Project M onitoring Unit POC Pont of Connection PPA Power Purchase Agreement RAPDRP Restructured Accelerated Power Development and Reforms Programme RDCC Regional Distribution Control Centre RE Renewable REC Rural Electrification Corporation REMC Renewable Energy Management Center RERC Rajasthan Electricity Regulatory Commission RGGVY Rajiv Gandhi Grameen Vidyutikaran Yojana RLDC Regional Load Despatch Center RRECL Rajasthan Renewable Energy Corporation Limited RPPC Rajasthan Power Procurement Cell RRVPNL Rajasthan Rajya Vidyut Prasaran Nigam Limited SCADA Supervisory Control and Data Acquisition Systems SECI Solar Energy Corporation of India SIP Sub -station Improvement Programme SLDC State Load Despatch Centre STU State Transmission Utility T&D Transmission and Distribution TBCB tariff based competitive bidding TPS Thermal Power Station Transco Power Transmission Company ULB Urban Local Body VGF Viability gap funding

92