Annual Review

Annual Review

Sakhalin Energy Investment Company Ltd.

Sakhalin Island (Head Office) 35, Dzerzhinskogo St., Yuzhno-Sakhalinsk, 693020, Russia

Moscow Branch 31, Novinskiy Boulevard, Moscow, 123242, Russia www.sakhalinenergy.com

Annual Review Contents

CONTENTS

Sakhalin II Project: Phase 1 and what is to be achieved in Phase 2 4 PHASE 1 5 PHASE 2 6

Highlights for 2007 8 GENERAL Shareholding structure change 9 Completion of the Offshore Pipelines 11 Start of drilling at the Lun-A Platform 12 Installation of the PA-B Platform 13 OPF: supplying power 14 Commissioning the LNG Plant 15 Oil Export Terminal: ready-for-operation 17 Establishment of the Port of Prigorodnoye 18 Trans-Sakhalin Onshore Pipeline System: river crossings completed 20 Personnel Development and Training 23 Workplace Safety 24

LNG marketing 25

Financial proceeds 25

2 Annual Review Contents

ENVIRONMENT AND PEOPLE

Environmental Protection 27

Environmental Action Plan 27

Independent environmental assessment 28

Western Gray Whales 28

Steller's Sea Eagle 29

Other rare birds 29

Sakhalin Taimen 30

Salmon 30

Biodiversity 31

Social Activities 32

Look ahead to 2008:

«project to production» 34

Molikpaq 34

Lun-A 34

PA-B 34

OPF 35

Trans-Sakhalin Onshore Pipeline System 35

LNG/OET 35

Annual Review 3 Sakhalin II Project Sakhalin II Project: Phase 1 and what is to be achieved in Phase 2

Sakhalin II was conceived as a proj- ect to produce oil and gas from the Pil- tun-Astokhskoye (PA) and Lunskoye fields in the Sea of Okhotsk offshore Sakhalin Island and sell it into the ra- pidly growing Asia Pacific market. An operating company — Sakhalin Energy Investment Company Ltd. — was estab- lished in 1994 to meet these objectives. Today the Company’s shareholders are (50% + 1 share), (27.5%), Mitsui (12.5%) and Mit- subishi (10%). The two fields are located some 15 km offshore North-East Sakhalin in water depths of 30 to 50 metres. The total hydrocarbon resource volumes in both fields are described in a table below:

Sakhalin II Hydrocarbon resource volumes (1 January 2008) Names Crude oil Dissolved gas Free gas Condensate of Fields (B + C1 + C2), (B + C1 + C2), and cap gas (C1 + C2), million tonnes billion cubic metres (C1 + C2), million tonnes billion cubic metres In place Recoverable In place Recoverable In place In place Recoverable Piltun- 461.421 116.875 58.734 15.22 103.391 12.341 8.301 Astokhoye Lunskoye 43.866 3.172 8.912 1.785 530.884 63.005 41.859

Total 505.287 120.047 67.646 17.005 634.275 75.346 50.160

Sakhalin Energy adopted a phased ap- proach to the project implementation.

4 Annual Review Sakhalin II Project

PHASE 1

Phase 1 was launched in 1996. The delivered to customers in Japan, Korea, development of the Astokh feature of and the USA. the PA field was selected as the starting The Molikpaq system for minimal point, with production from the Molik- flaring of associated gas is the first sy- paq (PA-A) platform. First oil from stem of this kind ever used in Russia. In Phase 1, achieved in July 1999, was a 2007, as in previous production sea- major milestone: for the first time, oil sons, the produced associated gas was was produced commercially from Rus- re-injected. sia’s offshore continental shelf. The At the close of 2007, due to harsh heart of the operation was the Molik- weather the Company chose to tempo- paq platform, the first offshore oil plat- rarily suspend production and discon- form in the Russian Federation. nected FSO Okha from the Single Since the waters of the Sea of Ok- Anchor Leg Mooring system (SALM). hotsk are covered with ice for six When the weather had improved and months a year, oil is produced only du- the crew was preparing to reconnect ring the ice-free period, i.e. approxima- the FSO, it was discovered that the tely six months a year. Nine production SALM was damaged. Due to the need for seasons (1999-2007) yielded a cumula- SALM repairs, a decision was made on tive total of some 13.2 million tonnes 25 November to close the ninth oil pro- of oil production (the Vityaz crude oil duction season earlier than planned. was a new brand introduced to the market by Sakhalin Energy). Since production commenced, crude oil has been exported to Japan, Korea, China, Taiwan, the Philippines, Thailand, Alaska and Hawaii. The Molikpaq’s ninth pro- duction season opened in 2007 in June at some 90 000 barrels of oil per day. In 2007 Sakhalin Energy produced 1.68 million tonnes (12.4 million barrels) of oil, 100 thousands tonnes (800 tho- usand barrels) more than in the previous year. This was

Annual Review 5 Sakhalin II Project

PHASE 2

Sakhalin II Phase 2, sanctioned in • An onshore production facility 2003, is one of the largest integrated oil (OPF) located near the north-east and gas projects in the world. For the coast of Sakhalin, 7 km inshore from first time in its history Russia’s oil and the landfall point of the gas pipeline gas industry witnesses the simulta- from Lun-A platform. Its main purpose neous implementation of several large is to process gas and condensate pro- interconnected green field sub-projects duced at the Lunskoye gas field before in a remote region with hardly any in- pumping them into the pipeline sy- frastructure and in a harsh sub-arctic stem for transportation to the oil ex- environment. port terminal and LNG plant. Oil and The development is a multibillion- gas produced by the Piltun-Astokh- dollar project in a sensitive frontier skoye platforms will also be transpor- environment, requiring the simulta- ted to the OPF to be subsequently neous execution of several projects. transported by pipeline to an essen- These include: tially ice free location at Prigorodnoye in the south of the Island. In addition, the OPF supplies power to Lun-A. • Two new production platforms: • Trans-Sakhalin onshore pipeline sy- Lunskoye-A (Lun-A) platform at stem which will carry hydrocarbons the Lunskoye gas field, which will from the fields in the north of Sakhalin produce most of the gas for the LNG via the onshore processing facility plant. The platform production ca- (OPF) near the Lunskoye field to the pacity is more than 50 million m3 LNG plant and oil export terminal in of gas per day and some 50,000 bar- the south of the Island at Prigorod- rels of condensate per day (8,000 m3 noye. The oil and gas pipelines share a per day) and Piltun-Astokhskoye- single pipeline corridor (“Right Of B (PA-B) platform at the Piltun Way” or ROW) varying in width depen- feature of the Piltun-Astokhskoye ding on the terrain. The total length of Field, which will have the capacity the two pipelines is 1600 km. The on- to produce up to 70,000 barrels/day shore ROW crosses more than 1,000 (11,000 m3/day) of oil and 2.6 mil- water courses and 19 seismic faults. lion m3/day of associated gas. Halfway between the onshore proces- • 300 km of offshore pipelines, and sing facility in the north and the oil ex- tying in the existing Molikpaq plat- port terminal in the south, a booster form to the new Piltun-Astokhskoye station (Booster Station 2 / BS 2) is si- field offshore pipeline system, in tuated near the village of Gastello. It order to enable year-round hydro- comprises crude oil booster pumps, gas carbon production. compressors, and auxiliary equipment.

6 Annual Review Sakhalin II Project

• The first LNG plant and associated export facilities in Russia. The plant for production of (LNG) is located near Prigorodnoye on the south coast of Sakhalin. The plant is designed to produce 9.6 million ton- nes of LNG per annum (4.8 million tonnes of LNG per year from each of the two identical process trains). A Double Mixed Refrigerant (DMR) gas liquefaction process was develo- ped specifically for the Sakhalin plant. The DMR process, which currently is the most advanced liquefaction tech- nology, was fine-tuned for best perfor- mance in Sakhalin's cold climate and optimised for compressor efficiency. • A new crude oil export terminal (OET) is located at Prigordnoye in Aniva Bay on the same site as the LNG plant. The OET will be used to store oil in two oil storage tanks. The tanks have a total net operating capacity of 1.2 million barrels (190,000 m3) and can accommodate six days worth of the onshore pipeline’s throughput. reconstruction of roads, bridges, sea- Crude oil will be exported via a sub- ports and airports, telecommunications sea pipeline to the tanker loading and other public infrastructure facili- unit (TLU) located some 5 km of- ties. The Company has budgeted about fshore in Aniva Bay. $500 million for this purpose. LNG and oil export facilities are part This work scope required the efforts of the infrastructure of Russia’s first of some 25,000 people at peak activity, specialised seaport at Prigorodnoye. most of whom (about 70%) were Rus- The port’s loading terminal will sian nationals. Once fully launched, comply with the International Mari- the Sakhalin II Project will become a time Organisation’s standards. key new source of energy for the Asia Pacific region. Sakhalin Energy strives Such a huge development also requi- to achieve performance which meets red a significant upgrade of some of Sak- or exceeds its PSA commitments to the halin Island’s general infrastructure. The Russian Party, and to be acknowledged programme that Sakhalin Energy is by buyers and competitors as a world implementing covers construction and class, high performing energy supplier.

Annual Review 7 Highlights for 2007 Highlights for 2007

8 Annual Review Highlights for 2007 GENERAL Shareholding structure change

On 18 April 2007 Shell, Mitsui and casions to discuss various issues. Gaz- Mitsubishi signed a Sale and Purchase prom specialists toured the Project agreement with OAO Gazprom, accor- sites to offer advice and expertise for ding to which Gazprom acquired a 50% future safe and efficient Project deve- plus one share stake in Sakhalin Energy lopment. for $7.45 billion. The current sharehol- Royal Dutch Shell remains Sakhalin ding structure of Sakhalin Energy is as Energy’s lead Technical Advisor. The follows: Gazprom holds 50% plus one agreements in place with Shell cover share, Royal Dutch Shell 27.5%, Mitsui advice and services related to explora- 12.5% and Mitsubishi 10%. tion, development, transportation and The entry of Gazprom as the majo- production of oil and natural gas, as rity shareholder in April 2007 was a well as advice and services in respect of landmark development. The vast expe- the design, engineering, construction, rience of the Russian shareholder put commissioning, start up and operation the Company in a position to more ef- of the LNG Facilities. fectively address many of the remai- In accordance with the amended ning challenges. With the entry of Shareholders Agreement, Gazprom no- Gazprom, Sakhalin II became de facto minees were appointed to the Commit- a Russian strategic project. tee of Executive Directors, the body In the autumn of 2007, Gazprom set responsible for the day-to-day manage- up a representative office in Yuzhno- ment and operations of the Company. Sakhalinsk with a range of aims, inclu- Four of Sakhalin Energy’s nine Execu- ding facilitating cooperation between tive Directors are currently nominated the main shareholder and the Com- by the lead shareholder, including the pany management. Managers and ex- Deputy CEO, the Director External Af- perts from the Russian gas giant visited fairs / Government Relations, and the Sakhalin and Japan on a number of oc- Commercial and HR Directors.

Annual Review 9 Highlights for 2007 The Committee of Executive Directors (CED) As of 1st March 2008

CEO Ian Craig

THE DEPUTY CEO Andrey Galaev

PHASE 2 PRODUCTION TECHNICAL COMMERCIAL PROJECT DIRECTOR DIRECTOR DIRECTOR DIRECTOR Jaap Huijskes Tim Hake Robert Ryan Viktor Snegir

GR/EA DIRECTOR FINANCE HR DIRECTOR GENERAL Igor Ignatiev DIRECTOR Vladimir Penkin COUNSEL Erwin Nijsse Ute Joas-Quinn

10 Annual Review Highlights for 2007

Completion of the Offshore Pipelines

The installation of the offshore pipe- Pressure testing of the TLU export lines was completed in 2006. 2007 saw pipeline at Aniva Bay was conducted the successful final connection of the in June, while pipeline pressure te- lines to the PA-B and Lun-A platform. sting at PA-B and Lun-A was succes- Diving operations for the connec- sfully completed in August 2007. tion of four offshore pipeline systems Thereafter the offshore pipelines were to the platforms at water depths of 30 dewatered and dried with nitrogen to 50 m commenced in June 2007 and and prepared for future testing and lasted two months. commissioning.

Annual Review 11 Highlights for 2007

Start of drilling at the Lun-A Platform

In 2007, to support Lun-A commis- missioned and tested. Drilling of the sioning, the accommodation support first well, a cuttings re-injection well, vessel Sanko Angel was deployed near commenced in August, upon issuance the platform. A ‘frog’ personnel trans- of a Rostekhnadzor permit. No waste fer unit and a crane were used to trans- was discharged into the sea during well fer workers between the platform and drilling. Solid wastes were placed in the accommodation vessel. containers at the platform and liquid In 2007, the new cyber drilling rig wastes were delivered to Molikpaq to unit on Lun-A was successfully com- be injected into a disposal well.

12 Annual Review Highlights for 2007

Installation of the PA-B Platform

In July 2007, Sakhalin Energy succes- The PA-B topsides, similar to Lun-A, sfully completed the installation of the were connected to their concrete gra- PA-B production platform topsides, vity base substructures via a cradle sy- manufactured in Korea. stem (friction pendulum bearings) that For transportation of the massive will allow the platforms to withstand, topsides a special barge (190x192 m) without any serious consequences, a was built. Upon arrival the barge was massive earthquake of the kind that carefully manoeuvred between the only occurs once in 3,000 years. four legs of the gravity base substruc- Soon after the topsides were instal- ture and the massive topsides were pre- led the PA-B hook-up and commissio- cisely ballasted and, with pinpoint ning process was initiated by Samsung accuracy, lowered onto the substruc- Heavy Industries, together with a 550- ture legs. By successfully ‘mating’ the strong, international group of specia- 28,000 tonne topsides to its gravity lists. This important project stage base, Sakhalin Energy broke its own could not have been achieved without world record set by the Lun-A topsides the Safe Bristolia flotel (floating installation operation the previous hotel), which accommodated many year. The entire operation was execu- more assembly and pre-commissio- ted to the highest safety standards, wit- ning personnel than the platform ever hin the Company’s established noise could. In November 2007 Safe Bristo- limits and with no discernable impact lia demobilised from the site. From on the Western Gray Whales, whose that time on the platform operated on feeding grounds are located just 7 km its own, with 140 commissioning per- from the platform. sonnel on board.

Annual Review 13 Highlights for 2007

OPF: supplying power

In January 2007 the OPF commen- were started at the OPF site. By this ced supplying power to the Lun-A plat- time, a permanent accommodation form. During the year the process and office building was built and put equipment was upgraded. In Septem- into operation, and the first group of ber 2007, commissioning activities OPF personnel moved in.

14 Annual Review Highlights for 2007

Commissioning the LNG Plant

In 2007, the Company started com- missioning purposes resulted in accele- missioning activities at the LNG plant rated preparation of plant production in parallel with the on-going con- systems for subsequent operation. struction. On 5 July 2007, the LNG carrier Gra- Due to its large size and complexity, nosa with approximately 135 tho- the plant cannot be handed over by usand cubic metres of LNG from CTSD, the general contractor, to Sakha- Bontang (Indonesia) moored alon- lin Energy, the future owner, as a single gside the LNG jetty. After the systems entity. To ensure smooth handover, all had cooled down, the natural gas was the facilities were divided into groups transferred from the carrier to two to be handed over in a phased manner. LNG storage tanks. The process of sto- The first facility handover ceremony rage cooling and LNG offloading took was held in January 2007. Facility han- 10 days. dovers continued throughout the year. The second LNG cargo (85 thousand A major milestone was the import of cubic metres) was imported to the LNG two large LNG cargoes to the construc- plant at Prigorodnoye from Alaska on tion site of the first Russian LNG plant. 10 October by the LNG carrier Arctic The decision to import LNG for com- Sun and offloaded in two days.

Annual Review 15 Highlights for 2007

The LNG delivered by the carriers was used for cooling of loading lines, equip- ment and LNG storage tanks. The low temperature will now be maintained until the first LNG export. The imported LNG was also used for commissioning of the flaring system, gas turbine genera- tors, boil off gas compressors and other major elements of the process trains. Gazprom, the majority shareholder of Sakhalin Energy, rendered considerable assistance. Specifically, the LNG import operation, the first ever in Russia, requi- red issuing a special executive order by the RF government and obtaining ap- provals from a number of authorities, in- cluding customs and the border service. In 2007, the state-of-the-art LNG/OET laboratory successfully passed certifica- tion tests to the requirements of Gos- standart and the international ISO17025 standard. Laboratory specialists are now analysing samples of oil, gas, chemicals and wastewater entering the LNG/OET site. In addition, the laboratory will be used to analyse, as required, samples bro- ught from the OPF.

16 Annual Review Highlights for 2007

Oil Export Terminal: ready-for-operation

In May 2007, representatives of Sak- halin Energy and CTSD, the general con- tractor, signed a ready-for-operation certificate for the oil export terminal (OET) and the tanker loading unit (TLU). The construction of these facili- ties is fully completed. The TLU is designed to operate in low temperatures, stormy seas, strong winds, seismicity and possible collision with vessels. The TLU is a tower-type outlet with a turning tanker mooring head on top and an oil loading arm with mooring lines. The TLU, designed by Sandwell Engineering, received in 2007 the most prestigious award gran- ted by Canadian Consult Engineers Jo- urnal for the world’s best engineering projects.

Annual Review 17 Highlights for 2007

Establishment of the Port of Prigorodnoye

Facilities for export of oil and LNG 100 Aframax oil tankers each year, form part of the infrastructure of a new which is approximately 4 to 5 vessels specialised sea port. In October by a spe- per week. The port facilities will allow cial decree of the Russian Government a tanker to be loaded within 16 hours the port was named “Prigorodnoye”. and turned around within 24 hours. Prigorodnoye Port will be operated 2007 has seen the commencement by a joint venture between Sakhalin of the site preparation for the con- Energy and Sovcomflot established by struction of the marine administration an appropriate agreement signed in building. The Marine Administration late 2007. The new company will pro- Building will accommodate Port Admi- vide expert pilots for LNG carriers and nistration staff, Pilot services, Marine oil tankers, and manage the port ope- and LNG Facilities coordination, OSR rations. At peak the new port will serve Team, State Port Authorities and the approximately 160 LNG carriers and Technical Services staff.

18 Annual Review Highlights for 2007

LNG carriers

Three LNG carriers were specially built in Japan for shipping Sakhalin II LNG to customers. The capacity of each of the tankers is over 145,000 m3 of LNG. Two new LNG carriers The Grand Elena and The Grand Aniva were built at Mitsubishi Heavy Industries shi- pyards (Nagasaki). Their christening ceremony was held in October 2007. The Grand Elena LNG carrier was named after Elena Anatolievna Zolota- reva, who headed the Moscow office of Sakhalin Energy for more than ten years. The Grand Aniva was named after the bay where the first Russian LNG plant being built by Sakhalin Energy is located. The Grand Elena was delivered to Sakhalin Energy at the close of October 2007. The two vessels are jointly owned by a Russian-Japanese consortium comprising OAO Sovcomflot and Nippon Yusen Kabushiki Kaisha (NYK). In July 2007, a third LNG carrier charted by the Company on a long-term basis was formally launched at the Mitsui Engineering and Shipbuilding shipyards in Tokyo. The carrier is owned by Primorsk Shipping Corporation and two Japanese companies, Mitsui O.S.K. Lines Ltd. and Kawasaki Kisen Kaisha Ltd.

Annual Review 19 Highlights for 2007 Trans-Sakhalin Onshore Pipeline System: river crossings completed

By late 2007, pipeline construction was substantially complete with only about 100 km remaining to be welded out of a total length of 1,600 km. In- stallation of oil and gas pipelines ac- ross some of the most difficult terrain of Sakhalin was the achievement of the year. The 2006-2007 season scope of work envisaged construction of 88 winter river crossings and was the se- cond season when the work was su- pervised by independent inspectors. The inspectors’ report showed consi- derable improvement in work quality compared to the previous season. Con- siderable difficulties had to be over- come and non-standard technologies had to be applied during the construc- tion. For example, a dry crossing met- hod (using flume pipes) was extensively used during the 2006-2007 winter sea- son and helped mitigate the impact on spawning rivers. All winter river cros- sings were successfully completed in April 2007. Construction of seismic fault cros- sings began in mid-2007, and by the end of the year, two out of 19 crossings were completed. Special shelters were built, tents put up and heating installed to allow operations to proceed in the winter season. An impressive scope of technical and biological remediation activities was completed in 2007. Technical restora- tion was completed on 404 km (51% of the Right Of Way (ROW) against 50%

20 Annual Review Highlights for 2007

planned), biological restoration — on 242 km (31% of the ROW against 30% planned). The banks of 502 rivers were reinforced and reinstated (62% of all the rivers crossed against 50% planned). During 2007, installation of block valve stations (47 on the gas pipeline and 104 on the oil pipeline, including 45 integrated and multi-phase sta- tions) took place. The stations are de- signed to minimise the impact from hydrocarbon leaks in case of pipeline damage. By the end of the year 127 block valve stations were assembled and pre-tested, and 107 were tied-in

Annual Review 21 Highlights for 2007

into the pipeline. The work programme used for storage of oil spill response also included the installation of five pig equipment. traps along the pipeline route, inten- The main 2007 milestone of the Bo- ded for pipeline pigging. oster Station 2 project was the succes- Russian contractors completed, on sful completion of the assembly, schedule, the construction of all five pi- operability testing and delivery of all peline maintenance depots (PMD) gas compression equipment for the along the length of the onshore pipeli- process line. By December 2007, both nes. These facilities will become hubs gas cooling plants, the first gas turbine for all types of onshore pipeline main- unit and first compressor were instal- tenance activities. They will also be led on the BS 2 site.

22 Annual Review Highlights for 2007

Personnel Development and Training

To assist with training offshore dril- already joined operations teams as ling technicians, the Company instal- technical specialists. led a Drilling Advanced Rig Training (or The Company’s management set a DART) simulator in Yuzhno-Sakha- goal of appointing Russian employees linsk. It uses 3-Dimensional graphics, to the Company's key management po- sound effects and real time simulations sitions as well as scaling down expa- to enable users to develop skills and triate personnel in favour of Russian test various drilling techniques. There nationals. In 2007, Sakhalin Energy do- are only five other simulators like this ubled the number of Russian nationals in the world. in senior and mid-level managerial po- Sakhalin Energy’s training centre in sitions. 260 new Russian staff were Yuzhno-Sakhalinsk runs training pro- hired, exceeding target numbers in all grammes that are structured to take functional divisions. into account an individual’s work The training plan objectives were place, role in the organisation, baseline also met with almost 36,000 man-days qualifications and the specific expe- of training achieved. In 2007, under the rience required for their job. 93 trai- Personnel Development Programme nees continued their training in the 1,867 Sakhalin Energy employees went Centre in 2007. Over 70 graduates have through various training courses.

Annual Review 23 Highlights for 2007

Workplace Safety

In 2007 the Company was able to re- In contrast to the vehicular traffic duce the total number of injuries at all performance there are a number of facilities, but the year was marred by a outstanding achievements in both number of road traffic related fatalities. project and operations. The most im- These sad events resulted in even pressive accomplishment was the 20 greater focus on road safety in the on- million manhours without a lost time shore pipelines construction project in injury at the LNG plant construction. particular. As a result, the Company The LNG/OET team won the presti- trained over 2,000 drivers in defensive gious annual Shell Chief Executive’s driving, inspected over 3,000 vehicles, HSE Award for this performance. installed 450 IVMS (In-Vehicle Moni- The onshore processing facility toring System) units in high risk vehi- (OPF) Team also scored highly with its cles, and trained over 800 supervisors achievement of just under 10 million in safety intervention techniques. man-hours without a lost time injury. An excellent job under very tough schedule and climate constraints was done on the pipeline maintenance de- pots project, which was completed safely with no LTIs (Lost Time Inci- dents) recorded after more than 2 mil- lion manhours of work. The Molikpaq platform crew also demonstrated sustained exemplary performance as they achieved more than three years with no lost time in- jury incidents. Many “frog” lifts were completed on the Lun-A platform during the summer campaign. More than 1600 lifts, both with 3-man Frog and 6-man Frog, transporting over 10,000 passengers to and from the accommodation vessel, were completed safely during a three month period, which is a world record.

24 Annual Review Highlights for 2007

LNG marketing

In 2007, Sakhalin Energy executed two new LNG sales agreements with Ja- panese buyers Osaka Gas and Chubu Electric Power Co., Inc. These deals ef- fectively complete the contracting out of the entire Sakhalin II LNG plant ca- pacity to 11 LNG buyers. The Sakhalin II overall long-term LNG contractual commitments now cover 98% of the future LNG plant trains 1 and 2 capa- city for 20 or more years ahead. The re- maining uncommitted 2% will be used to ensure operational flexibility.

Financial proceeds

Russian Content

The Company continues to provide assistance to po- tential vendors in Russia and Sakhalin by raising Rus- Sakhalin II main facilities are still to sian companies’ awareness of the Project’s future be brought online, however, despite the and current requirements for contracted work/ser- ongoing construction and seasonal oil vices and materials/equipment. A list of future Sak- production, Russia and Sakhalin cur- halin II tenders (for 2007-2011) was developed and rently receive significant financial be- published on Sakhalin Energy’s public website. In nefits from the Project. 2007 the Company held 11 workshops that were at- In 1996 — 2007, the total revenues to tended by around 40 Russian companies, and two the Russian Government from the proj- trade fairs which attracted more than 80 partici- ect development had exceeded $800 pants representing various Sakhalin companies. million, including $100 million in pro- The Project's Russian content measured as manho- fit tax paid in Q1 2008. urs of services provided and as the volume of material and equipment delivered, exceeded 80% in 2007. The value of new contracts together with the 2007 change orders, awarded to Russian companies added up to 68% of the overall value of 2007 contracts.

Annual Review 25 Highlights for 2007

ENVIRONMENT AND PEOPLE

26 Annual Review Highlights for 2007

Environmental Protection Environmental Action Plan

In 2006 the RosPrirodNadzor (RPN, mentation, provided it is further detai- the Russian environmental authori- led and updated in view of the results ties) required that Sakhalin Energy of our joint effort». A new revision of should pay more attention to environ- the Plan and a progress report were ment safety in respect of the Sakhalin submitted to the RPN in October 2007. II Project pipelines system construc- On 26 October 2007, Ian Craig, Sak- tion. Sakhalin Energy acknowledged halin Energy's CEO, reported to Yuri the findings of environmental comp- Trutnev, the RF Minister of Natural Re- liance inspections in 2006 and used sources, on the response to RPN fin- them to develop and implement re- dings and on EAP progress. The Minister spective corrective plans. expressed satisfaction with the results A revised version of the Environmen- of the Company's efforts and noted tal Action Plan (EAP) was submitted to with confidence that the Project should RPN in March 2007 and was officially become an example of the highest re- endorsed as a «basis for future imple- spect for Russia’s natural environment.

Annual Review 27 Highlights for 2007

Independent environmental assessment

In October 2007, AEA, in its capacity the Project’s facilities/assets”, and as an independent consultant to po- that “there are examples of laudable tential lenders of the Sakhalin II Phase best practices”. “Where non-confor- 2 Project, produced a final report on mances with requirements have been the project’s commitments as laid out identified in the documentation these in the publicly available Health, Safety, are either minor in nature or else Sak- Environmental and Social Action Plan, halin Energy has plans in place for and assessed Sakhalin Energy Invest- their correction”. ment Company Ltd. against a compre- The report renders full support to hensive set of standards, guidelines, Sakhalin Energy’s philosophy of mee- legislative requirements and interna- ting the challenges it is facing. The re- tional treaties and conventions. port contains recommendations for The AEA report states that “there is a improvement in certain areas, and yet high level of compliance for most of its conclusions are essentially positive.

Western Gray Whales

Sakhalin Energy’s programme of mi- tigating potential negative impacts on western grey whales engages highly skilled experts in marine mammals and acoustics from leading Russian re- search institutes. The Company works closely with the Western Gray Whale Advisory Panel established by the In- ternational Union for Conservation of Nature (IUCN) at the initiative of Sak- halin Energy. In 2007, as in previous years, Sakhalin Energy continued to monitor noise le- vels, throughout the entire period of ma- rine activities, with acoustic buoys along the perimeter of the whale feeding area. The noise monitoring data obtained du- ring installation of the PA-B topsides in 2007 showed that the Company’s thres-

28 Annual Review Highlights for 2007

hold noise standards were not exceeded. with low-noise machinery and engines, When installation was completed, the mandates speed limits for vessels and whales were observed in the part of the establishes special navigation corridors. feeding area closest to the platform. Sakhalin II operations have been con- Noise monitoring was only one of a sy- ducted in the area adjoining the gray stem of measures designed to minimise whale feed zone for nearly 10 years with impacts on whales. Other mitigation no visible signs of impact on gray wha- measures included reduced vessel num- les. According to independent scientific bers and optimised timing of operations estimates, the whale population increa- and distance to the whales. In addition, sed within the observation period from the Company operates vessels equipped 100 to 123 animals.

Steller's Sea Eagle

Several dozens of Steller's sea eagles’ the Steller’s sea eagle breeding success. (classified by IUCN as a vulnerable spe- 13 nesting places within the construc- cies) nests fall within the project impact tion area produced 11 nestlings hatc- area — in the vicinity of the OPF and the hed by September. The population northern pipeline segments. productivity therefore increased by 35% In 2007 surveys were made in April on a year-to-year basis. The breeding su- (early nesting period) and in August and ccess is a testimony to the effectiveness then again in September (late nesting of the construction period). The resulting information was impact mitigation used to develop and implement impact programme and mitigation measures for all nests that other measures to fall within the project impact zone. protect the sea eag- The data collected during the spring les’ nests from preda- and summer surveys were used to assess tion by brown bears.

Other rare birds

Siberian spruce grouse numbers were established their abundance and iden- monitored from 2006 till the spring of tified flyways between the near shore 2007 to establish the population of feed zones and inland nesting areas. these rare and vulnerable birds and The survey results were used to deve- their settlement areas around the OPF. lop mitigation measures to reduce di- In June and July, 2007 long-beaked sturbance of this species during the murrelet were also surveyed. The survey construction period.

Annual Review 29 Highlights for 2007

Sakhalin Taimen

Sakhalin taimen is a rare protected to make certain that our activities do species of the salmon family. not endanger the species. In 2007 Sakhalin Energy launched a In the summer and autumn of 2007 research programme to identify river top-level taimen specialists together systems along the pipeline route with ichthyologists and students of where the taimen dwell. The Com- Sakhalin State University mounted a pany sponsored the project to learn large-scale study of taimen in eight more about the species occurrence model river basins — from Aniva Bay pattern and the abundance of taimen to the northern part of the Nogliki di- in rivers with pipeline crossings, and strict.

Salmon

To support conservation and prudent commercial use of the wild salmon and its sustaining ecosystems, Sakhalin Energy, the international NGO Wild Sal- mon Centre and the Sakhalin Oblast Administration jointly launched the Sakhalin Salmon Initiative. In 2007, the Sakhalin Salmon Ini- tiative embarked on implementation of plans drawn by an international conference in the autumn of 2006. The strategic priorities of this public- private partnership headed by the Sakhalin Salmon Initiative — an protection programme with a budget NGO specially set up for this purpose of $8.8 million. — include salmon monitoring, estab- The 2007 fishing season was a re- lishment of protected natural terri- cord year on Sakhalin and according tories and support of educational to official statistics Sakhalin fisher- environmental programmes. In Fe- men caught some 147,000 tonnes of bruary 2008, Sakhalin Energy and the Pacific salmon. This indicates that oil Wild Salmon Centre signed a land- and gas development on the Island mark strategic agreement to co-fi- can take place alongside a continuing nance a three-year wild salmon and successful fishing industry.

30 Annual Review Highlights for 2007

Biodiversity

In 2007 the Company made conside- main objective is to deliver professio- rable progress in developing the Sakha- nal advice to the Company in BAP de- lin II Project Biodiversity Action Plan velopment. Furthermore, the biology (BAP). This plan includes data acquisi- experts included in the group will be tion and consolidation, development monitoring rehabilitation of the ani- of a biodiversity database, monitoring mal and bird habitats previously expo- and the involvement of many stake- sed to any kind of impact from holders. Sakhalin II construction activities. The In August 2007, Sakhalin Energy initial meeting of the group, which in- came together with the Environmental cluded representatives of regional en- Council of Sakhalin Oblast to establish vironmental entities, researchers and a biodiversity expert working group. Its ecologists, was held in December 2007.

Annual Review 31 Highlights for 2007

Social

In 2007 Sakhalin Energy invested $6.5 formally recognised by both the Sakha- million into socially important pro- lin Oblast Administration and the city grammes. The Company’s efforts were government of Yuzhno-Sakhalinsk.

32 Annual Review Highlights for 2007

Social activities undertaken by the company in 2007 included: • Nevelsk earthquake emergency relief efforts. SEIC staff also made a signifi- cant contribution to this worthy cause. • Investment of $3.3 m in the con- struction of a children’s dental clinic in Yuzhno-Sakhalinsk. • The continuation of the successful Senya TV cartoon programmes which teach children how to behave in emergency situations. • Supporting the opening of Informa- tion Resource Centres which con- centrate on drug abuse and the prevention of HIV/AIDS. • Donating medical equipment to the Regional Central Hospital in Korsakov. educational initiatives of local com- • Implementing a partnership project munities. with Kidsave NGO (USA) supporting • Organising master-classes for young foster care development. Sakhalin hockey players taught by • Supporting Sakhalin’s Indigenous Mi- Russia’s Hockey Legends team mem- norities through the Sakhalin Indige- bers. nous Minorities Development Plan • Awarding 21 higher education grants (SIMDP). In 2007 equipment was to Sakhalin high school graduates. purchased for remote medical sta- tions and a new mobile dental clinic was established. The Company also provided support for Uilta reindeer herders and a programme for the re- newal of Nivkh dog breeding. • Cooperating with the Sustainable Development Department of Sakha- lin State University in implementing sustainable development program- mes on the Island and raising aware- ness of Sakhalin communities about sustainable development issues. • Implementing Small Grants — Great Deeds programme in all Sakhalin di- stricts. The programme is aimed at su- pporting social, cultural and

Annual Review 33 Look ahead to 2008 Look ahead to 2008: «project to production»

2008 will be the most critical year for The Project construction phase is the Company, covering the completion, nearing completion and migration to testing and commissioning of our major the full-scale operational phase is un- assets, including the commissioning and derway. Below are some of the main start up of the LNG plant by the end of 2008 activities with a view to moving to the year. Accordingly, the Company’s key full year round hydrocarbons produc- objective is ‘Safe, reliable delivery of LNG’ . tion and the manufacture of LNG.

MOLIKPAQ

• The summer season will see the reinstallation of the SALM and start up of production of oil from the Molikpaq. The final acceptance and commissioning LUN-A tests of the oil and gas processing modules • The CRI well — the first well to be will be conducted in drilled from Lun-A – will be comp- 2008, and with that behind us, we will move to the leted by April 2008. next stage of year-round Molikpaq operation. • Drilling operations on the first gas Production will initially be through the SALM but well from Lun-A will then com- later in 2008 oil will flow to Prigorodnoye. mence. A total of three gas wells • Associated gas is planned to be transported via out of the planned total of 11 will the offshore pipeline system to OPF where it can be drilled in 2008. The first two of be used to switch the OPF generators from diesel these wells will be used to commis- fuelled power generation to gas powered. sion the 1st LNG train.

PA-B

• Following completion of commissioning, it is planned to start drilling the CRI well on PA-B platform in early 2008. • Drilling of the first oil well will commence in mid-year.

34 Annual Review Look ahead to 2008

OPF LNG/OET

• Construction of the third line for • Train 1 will be comple- MEG (mono-ethylene-glycol) will ted and handed over continue. to operations staff. The • All process systems inside the OPF third importation of a fence will be commissioned. cargo of commissioning • Construction teams will complete LNG will take place the Waste Transit and chemical early in summer. Train 2 storage area. final construction follo- • Construction teams will start de- wed by commissioning later in 2008. mobilisation. • Start-up of the LNG plant using feed gas from the • Gas from PA-A then LUN-A gas will north is expected by 2008 year end. be introduced to Train 1. • The permanent accommodation unit in Korsakov is planned to be completed and operations staff to move in. • The Marine Administration Building will be comp- leted. • Following TLU commissioning, crude oil will be offlo- aded at the rate of about 50,000 barrels per hour (8,000 m3 / hr).

The oil tanker The Governor Farkhutdinov will be joi- ned by her sister ship The Sakhalin Island to commence crude oil operations from Prigorodnoye.

TRANS-SAKHALIN ONSHORE PIPELINE SYSTEM

• The remaining fault crossings will be completed and final wel- ding will take place. • The pipelines will be pigged, gauged, hydrotested, and clea- ned and dried in readiness to receive hydrocarbons. • The fibre optic communications cable will be completed, then tested and commissioned. • The remaining block valve stations will be tied in and commissioned.

Final reinstatement of the river banks, the ROW and other sites will be substantially complete. Construction of Booster Station 2 will continue in 2008, followed by commissioning in 2009.

Annual Review 35 Look ahead to 2008

As the phase 2 construction nears com- count of construction completion and the pletion in the first half of 2008 the Produc- offshore drilling program. Final contracts tion directorate will interface closely with for the production phase will be let and the Project to ensure a smooth transition checks and reviews will be carried out to and handover for the hydrocarbon start up ensure materials and spares inventories phase. The final training of the operations are in place. Implementation of manage- and maintenance personnel will take place ment systems covering HSE, maintenance, to ensure full familiarity with their facilities plant integrity, product quality and fiscal and their roles in the start up and post start metering will be finalised for the production up periods. Great emphasis is placed on phase. The Sakhalin Energy corporate sys- adherence to start up procedures and in tems to ensure effective management of preparing and carrying out drills for emer- the company post start up will also be em- gency situations. To ensure compliance, bedded in the system. The customer inter- structured pre-start up audits and inspec- face is also being carefully managed and the tions involving the Company, shareholders, final arrangements for the Port at Prig- government agencies and lenders will take orodnoye and the shipping will come into place. Additional commissioning and start place during 2008. up specialists from vendors and technical service providers will also be brought on A busy year ahead, but Sakhalin Energy will board to support the start up. build on its achievements, meeting challenges Final implementation of processes cov- associated with the transition from project ering communication protocols and com- to production, with safety and reliability, as mand and control structures will be carried always, the main priorities. out. The hydrocarbon start up will take place After the years of design and construc- over several months in the second half of tion, the aspiration of the Company to become 2008 beginning with the Northern gas sys- a leading energy provider for the Asia Pacific tems. The integrated start up logic, covering region is coming ever closer. 2008 will in- parallel and sequential steps, has been de- deed be a pivotal year for Sakhalin Energy in veloped to optimize the schedule taking ac- making this a reality!

36 Annual Review

Annual Review

Annual Review

Sakhalin Energy Investment Company Ltd.

Sakhalin Island (Head Office) 35, Dzerzhinskogo St., Yuzhno-Sakhalinsk, 693020, Russia

Moscow Branch 31, Novinskiy Boulevard, Moscow, 123242, Russia www.sakhalinenergy.com