SRIRAM EDUCATIONAL TRUST #49 , – 600 002.

GENERAL CONDITIONS:

1. Date of Commencement of work shall be within one week from the date of issue of work order (or) from the date of handing over the site.

2. Period of completion of work will be 30 days from the date of commencement.

3. RMD will be deducted at the rate of 5 % from each bill and released after one year from the date of completion of work.

4. Quantities in the schedule are tentative and may vary according to site conditions and during execution.

5. Payment will be made as per actual measurements and quantities (based on the levels taken before filling and after compaction).

6. No escalation of rate will be allowed under any circumstances.

7. First Aid box should be made available at work site with adequate medicines and dressing materials.

8. Contract assigned to the contractor shall be cancelled if child labour is engaged in executing the work.

9. Security of the contractor’s equipment and materials is his own responsibility.

10. Contractor should ensure that all the applicable labour laws especially safety and insurance of the labour are followed. This is basically the responsibility of the contractor. The client should be kept informed of any labour disputes.

11. For all payments TDS towards income tax will be deducted as per orders in force and as per the prescribed rates.

12. Contractor should be required to indicate registration number under General Sales Tax Act 1959 in the Tender form and produce sales tax clearance certificate issued by the commercial tax department. Sales tax will be deducted as per the orders is force and as per the prescribed rates.

2

13. It is total responsibility of the Contractor for getting all approvals of Local Body, Revenue and other required authority for quarrying and supplying of earth.

14. Filling of earth and its consolidation will be carried out as per clause 401 of MORTH specifications.

15. The Contractor is required to make his own arrangements for vibratory roller of capacity of 8 - 10 T for earth compaction complying with MORTH specifications.

16. The Contractor is required to arrange his own DG set for meeting power requirements for night work.

17. Interim payment will be made every week based on the 50% of the quantity supplied (for voids and compaction).

18. If any clarification is required, the Contractor can contact the Project Officer of the Trust during office hours. His Telephone Number is 28511011.

~~~~~~~

3

NAME OF WORK: FILLING AND CONSOLIDATION WITH EARTH FOR A TOTAL EXTENT OF 5.72 ACRES IN SRIRAM EDUCATIONAL TRUST LAND AT IN TALUK.

Bill of Quantities

S.No Description Qty Unit Rate Amount 1 Supplying and Filling in formed base level where ever necessary with Filling Earth. The earth should be brought from outside the premises including all lead and lift, leveling and consolidation etc. The earth should be compacted in layers not exceeding 300mm thick. (The compaction should be done by 8-10 tons power vibrator roller to achieve the required standard proctor density of 95% as per standard specification.(MORTH specification) The rates are including hire charges for roller, generator if required, for all approvals and local clearance for the supply of earth. (payment to be made for finished item of work after completion based on original and finished levels) a Part A area 4670.00 Cum

b Part B area 4554.00 Cum

SRIRAM EDUCATIONAL TRUST LAND AT VYASARPADI

4