Initial Environmental Examination

Document Stage: Draft Project Number: 42486-016 April 2016

IND: Urban Services Improvement Program – Water Supply Improvement in Mauganj

Package No: MPUSIP-7A

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Initial Environmental Examination

Project No. 42486 April 2016

IND: Madhya Pradesh Urban Services Improvement Program – Mauganj -Water Supply Subproject

Prepared by: MaRS Planning and Engineering Services Pvt. Ltd.

CURRENCY EQUIVALENTS (as on 1 Feb 2016) Currency Unit - Conversion INR 1.00 = $ 0.015 $ 1.00 = INR 66.00

Abbreviations

AC – Asbestos Cement ADB – Asian Development Bank ASO – Assistant Safeguards Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB Central Pollution Control Board EA – Executing Agency EAC – Expert Appraisal Committee EC – Environmental Clearance EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; ESR – Elevated Service Reservoir GOI – Government of GOMP – Government of Madhya Pradesh IA – Implementing Agency IEE – Initial Environmental Examination; LPCD – Liters per Capita per Day MLD – Million Liters per Day MNP – Mauganj Nagar Parishad MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company MPUSIP – Madhya Pradesh Urban Service Improvement NOC – No Objection Certificate PDMC – Project Design and Management Consultant PE – Polyethylene PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMU – Project Management Unit PO – Project Officer PPTA – Project Preparatory Technical Assistance PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Right of Way SEIAA – State Environmental Impact Assessment Authority SPS – Safeguard Policy Statement, 2009 UDED – Urban Development & Environment Department ULB – Urban Local Body WTP – Water Treatment Plant

2 Initial Environmental Examination- Mauganj Water Supply Scheme

WEIGHTS AND MEASURES

˚C Degree Celsius km kilometre lpcd litres per capita per day mm milli meter m metre mld million litres per day mm millimetre Nos Numbers sq.km Square Kilometer MCM million cubic meter

3 Initial Environmental Examination- Mauganj Water Supply Scheme

TABLE OF CONTENTS

1. Executive Summary 6 2. Introduction 10 A. Background 10 B. Purpose of IEE report 10 C. Report Structure 12 3. Description of Subproject Area 13 A. Project Area 13 B. Existing Situation 13 C. Components of the Subproject 17 4. Policy, Legal and Administrative Framework 26 A. ADB Policy 26 B. National and State Laws 26 5. Description of the Environment 30 A. Methodology Used for Baseline Study 30 B. Physical Environment 30 C. Biological Resources 32 D. Socio-Economic Conditions 32 E. Subproject Site Environmental Features 35 6. Anticipated Environmental Impacts and Mitigation Measures 37 A. Pre- Construction Impacts 38 B. Construction Impacts 42 C. Operation and Maintenance Impacts 49 7. Information Disclosure and Public Consultation 51 A. Overview 51 B. Public Consultation 51 C. Information Disclosure 52 8. Grievance Redress Mechanism 53 A. Project Specific Grievance Redress Mechanism 53 9. Environmental Management Plan 54 A. Implementation Arrangements 54 B. Environmental Management Plan 54 C. EMP Compliance Responsibilities 75 D. Training 77 E. Monitoring and Reporting 78 F. EMP Implementation Cost 79 10. Conclusions and Recommendations 80

4 Initial Environmental Examination- Mauganj Water Supply Scheme

LIST OF TABLES

Table 1 Projected Population and Projected Water Demand 17 Table 2 Proposed Mauganj Water Supply Sub project Components 20 Table 3 Applicable Environmental Regulations for Subproject 27 Table 4 WHO Ambient Air and Noise Quality Standards 29 Table 5 Source Water Quality 31 Table 6 Silent Environmental Features 35 Table 7 Design Stage Environmental Management Plan 56 Table 8 Pre- Construction Stage Environmental Management Plan 58 Table 9 Construction Stage Environmental Management Plan 60 Table 10 Operation Stage Environmental Management Plan 70 Table 11 Construction stage Environmental Monitoring Plan 72 Table 12 Operation Environmental Monitoring Plan 73 Table 13 Outline Capacity Building Program on EMP Implementation 77 Table 14 Cost Estimates to Implement the EMP 79

LIST OF FIGURES

Figure 1 Location of Subproject Area 13 Figure 2 Existing Intake well at Nihayi River of Mauganj 13 Figure 3 Water Storage Facilities at Mauganj Town 14 Figure 4 Existing Pipe Line Map of Mauganj Town 16 Figure 5 Junction where river Nihayi joins Odda Nallah 18 Figure 6 Location of Proposed components on Google Map 19 Figure 7 Index Map of Proposed WSS 22 Figure 8 Cross Section of Proposed Intake Well 23 Figure 9 Proposed WTP Layout Plan 24 Figure 10 Proposed Weir Cross Section 25 Figure 11 Survey of India Toposheet showing Mauganj Town 33 Figure 12 Odda Nallah network and existing and proposed weirs 40

List of Appendices

Appendix 1: Stakeholder Consultation Appendix 2: REA Check list Appendix 3: Water Testing Report Appendix 4: Khasra Details and Map Appendix 5: National Ambient Air Quality Standards Appendix 6: National Ambient Air Quality Standards in Respect of Noise Appendix 7: Vehicle Exhaust Emission Norms Appendix 8: Drinking Water Standards Appendix 9 : Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works Appendix 10: Sample Outline Spoils (construction waste) Management Plan Appendix 11: Quarterly Reporting Format for Assistant Safeguards Officer Appendix 12: Sample Environmental Site Inspection Report Appendix 13: Sample Grievance Registration Form

5 Initial Environmental Examination- Mauganj Water Supply Scheme

I. EXECUTIVE SUMMARY

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as „the Project‟. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Environment Department (UDED) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns  Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and  Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening  Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;  Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and  Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. The subproject The subproject town Mauganj located in the in the South-east part of Madhya Pradesh state. Mauganj is a small town, and population as per 2011 census was 28948. The objective of the proposed improvements in town is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The project proposals envisage providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. This IEE has been prepared for the proposed Mauganj Water Supply subproject which includes: (i). two Weirs (4 m height), one across River Nihayi and second across Odda nala, (ii) intake well of 8.25 MLD capacity on odda nala on u/s side of existing stop dam, (iii) Raw water rising main of 8,140 m length, (iv) water treatment plant (WTP) of 8.30 MLD, (v) clear water sump for 400 KL capacity at WTP, (vi) clear water rising main of 5010 m

6 Initial Environmental Examination- Mauganj Water Supply Scheme

length, (vii) OHT of 1800 KL at zone 2, (viii) distribution network of 103.47 km length, and (ix). Bulk flow meters and household connections

5. Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank‟s operations, and the requirements for environmental assessment are described in ADB‟s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

6. The subproject is unlikely to cause significant adverse impacts because: (i) the water abstraction for the project is very minimal in comparison with the river water flow/availability, (ii) the components will involve straightforward construction and operation, so impacts will be mainly localized; (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements; and (iv) being located mainly in an existing built-up area, will not cause direct impact on terrestrial biodiversity values. Potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well- developed methods for mitigation of these impacts to acceptable levels.

7. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

8. Description of the Environment. The subproject components are located in Mauganj town and its surroundings. The Weirs will be constructed across the rivers of Nihayi and Odda, and intakes will be located close to the banks on government lands. WTP including clear water sumps will be also located close to the intakes where sufficient government land is available. These facilities are located outside the town, and are mostly surrounded by agricultural lands, and rivers/nallahs. There are no forest areas in the vicinity/ Rest of the components – water tanks, distribution lines, connections etc., will be located within the urban areas. The raw water transmission pipes, connecting intake and WTP, will be essentially outside the town, and clear water transmission pipes, from WTP to distribution reservoirs, will be partly outside and partly within the towns. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. While there is no natural habitat left within the town areas, the areas near river intakes are comparatively intact though most of the lands there too converted into agricultural use. There are no protected areas, like wildlife sanctuaries, national parks, nor there are any historically, archeologically protected areas in the vicinity. Towns are densely populated in the core/old town areas with narrow lanes, and small and closely built houses, while most of the areas are undeveloped and are still under agricultural use. Commercial areas are along the main roads, which are mostly congested with activities, pedestrians and traffic.

9. Potential environmental impacts. The subproject is unlikely to cause significant adverse impacts because: (i) relatively small scale as the population and water demand is minimal, (ii) the components will involve straightforward construction and operation, so impacts will be mainly localized; and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

7 Initial Environmental Examination- Mauganj Water Supply Scheme

10. Environmental impacts as being due to the project design or location are not significant. The proposed water supply scheme include design of new water sources with nearest surface water bodies. Considering good water availability and very small demand, it is assessed to be unlikely to have any significant issue of source sustainability. Given that proposed check dam cum weirs are small structures with limited height (4 m from river bed) and submergence confined to river course, the impacts on downstream and ecosystem are likely to be insignificant. Water quality is good and there are no notable pollution sources in the vicinity that could affect the water quality. Although none of the components are located within the forest, conduct of construction works and presence of workers, vehicles may damage /disturb the sensitive areas. Necessary precautionary measures are suggested to avoid any impacts.

11. During construction, potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels. Operation phase impacts are likely to be insignificant.

12. Environmental Management Plan. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels. Locations and siting of the proposed infrastructures were considered to further reduce impacts. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town.

13. The EMP includes design measures such as (i) discontinuation of groundwater source, and shifting to a sustainable surface water source (ii) wash water recovery for the WTP to reduce effluent to be discharged; (iii) beneficial use of treated sludge; and (iv) quick leak detection and rectification to save the resources, etc. During construction, the EMP includes mitigation measures such as (i) selection of appropriate construction methodology and scheduling for intake works in river; (ii) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts; (iii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iv) provision of walkways and planks over trenches to ensure access will not be impeded; (v) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (vi) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vii) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

14. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non- detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition

8 Initial Environmental Examination- Mauganj Water Supply Scheme

and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

15. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

16. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

17. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

18. Implementation Arrangements. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency. Implementing Agency will be Madhya Pradesh Urban Development Company (MPUDC), A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC) centrally located in PMU and with field teams, will support PMU & PIUs. Infrastructure will be designed, built, and operated (DBO) by contractor for 10 years, after which it will be transferred to the ULB. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by Environment Specialist of PMC Team. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

19. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

20. Conclusions and Recommendations. The proposed subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require following government permission/approvals: (i) permission of Water Resources Department (WRD), GoMP for water abstraction and construction of RPSs/intake; and (ii) consent for establishment and consent for operation for WTP from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to award of contracts.

21. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

9 Initial Environmental Examination- Mauganj Water Supply Scheme

II. INTRODUCTION

A. Background

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as „the Project‟. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Environment Department (UDED) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns  Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and  Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening  Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;  Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and  Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and

10 Initial Environmental Examination- Mauganj Water Supply Scheme

(vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are: (i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators:  Improved water supply capacity of 186ml/day installed in 64 towns;  4,000 km water supply networks installed in 64 towns;  350,000 households provided with metered house connections including 100 government schools;  8 MLD sewage or septage treatment plants constructed; and  Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management  23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated;  ULBs institute volumetric water charges for recovery of water service O&M costs  ULBs‟ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters‟ readings  100% operating cost recovery (excluding debt service) achieved;  GIS system established for effective O&M of water services

B. Purpose of IEE Report

5. ADB requires the consideration of environmental issues in all aspects of the Bank‟s operations, and the requirements for environmental assessment are described in ADB‟s Safeguards Policy Statement (2009). Accordingly, this Initial Environmental Examination (IEE) has been conducted to assess the environmental impacts and provide mitigation and monitoring measures to ensure that there are no significant impacts as a result of the subproject.

6. This IEE is prepared for Package 7A, Mauganj water supply improvement subproject. The subproject includes civil works, project implementation and management, and non-physical investments. A detailed description of the components is provided in Section III. The project area cover Mauganj town which comes under Rewa district. IEE is based on the detailed engineering report prepared by the Consultant team and will be finalized during bidding stage to reflect any changes and latest subproject designs.

7. The environmental impacts of Mauganj water supply subproject have been identified and assessed as part of the planning and design process. An environmental assessment using ADB‟s Rapid Environmental Assessment Checklist for Water Supply was conducted, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this IEE has been prepared in accordance with ADB SPS‟s requirements for environment category B projects.

8. The IEE was based mainly on secondary sources of information and field reconnaissance surveys; no field monitoring (environmental) survey was conducted. Stakeholder consultation was an integral part of the IEE.

11 Initial Environmental Examination- Mauganj Water Supply Scheme

C. Report Structure

9. This report contains the following sections: (i) Introduction (ii) Description Of the Subproject (iii) Policy, Legal and Administrative framework (iv) Description of Environment (v) Potential Environmental Impact & Mitigation Measures (vi) Public Consultation and Information Disclosure (vii) Grievance Redress Mechanism (viii) Environmental Management Plan (ix) Conclusions and Recommendations

12 Initial Environmental Examination- Mauganj Water Supply Scheme

II DESCRIPTION OF THE SUBPROJECT

A. Description of Project Area 10. Mauganj is a Town in Mauganj Mandal in Rewa District in Madhya Pradesh State. It is located at a 65 km distance from the Main City Rewa in District. It is located at 601 km distance from its State Main City Bhopal. Mauganj has a good connectivity with the adjoining areas. Geographically, the city lies at 24° 41' North latitude and 81° 53' East longitude at an altitude of about 312 m above mean sea level in Region.

Figure 1: Location Map of Sub project Town.

B. Existing Situation 11. The sources of water to Mauganj Nagar Parishad are mainly through Tube wells power pumps with pump house and hand pumps. The major source of water in Mauganj Nagar Parishad is Nihayi River which flows in the north-eastern side of the town. For the filtration of water, town has a filtration plant which is 40 years old. It is 5 kilometer away from the town and in present, it is not working.

Figure 2: (a) Intake well at Nihayi river (b) Nihayi river

13 Initial Environmental Examination- Mauganj Water Supply Scheme

12. The town get majority of water supply directly from these tube wells located in various parts of the town without any treatment. The per capita supply of water is 50 liters per day is estimated under the existing supply system which is very low as compared to the prevalent national standards of 135 LPCD. One OHT of capacity 45000 Gallon is located near nagar parishad and it is in use. Second OHT is of capacity 2.7 LL (staging 15 m). It was constructed in year 1983 and it is not in use due to shortage of water.

Figure 3: Water storage facility in Mauganj town

OHT-1 (in use) OHT 2 (Not in use)

EXISTING DISTRIBUTION DETAILS 13. The present water distribution system includes water pipelines system which is not sufficient. The water distribution arrangement includes one OHT in the town. Town gets majority of water supply through the network pipelines laid down in different part of the town. These network lines are linked with main pipelines coming from the ten tube wells (located in various parts of the town). For the storage and supply of water, town has an overhead tank which is situated in ward no. 3. In the town, water pipeline system or network has mainly 100 mm dia. AC pipes. It is 40 Years old and it is filled twice in a day. Ward number 2, 3 and 4 get water supply from overhead tank. The distribution line network in length about 2500 m. is only exists and have leakage problem. Water during summer seasons or in emergencies and other occasions/functions are also supplied through Water Tankers. The per capita supply of water is 50 liters per day is estimated under the existing supply system which is very low as compared to the prevalent national standards of 135 LPCD. Thus, there is huge scarcity of water and the water supply system in the town requires augmentation schemes on top priority basis.

14. Existing system having Intake Well, W.T.P. based on source River Nihai is not in function since 2010. As the flow in River Nihai reduces in the month of February & ceases in the month of March. Existing Deh (water pool) is not capable to meet out requirement of summer season (February to June). Bunding on River Nihai D/S of existing Intake Well at a distance of 150 m from Intake Well was done by the U.L.B. every year. Now this practice has been stopped by U.L.B. This existing system is not in function due to lack of water. Quality of Raw Water is good.

15. Issues In Present Water Supply System  The water distribution system is very old and has leakage problem due to which pressure remain is low.  The distribution system has limited coverage.

14 Initial Environmental Examination- Mauganj Water Supply Scheme

 Pipelines were mainly laid along the major roads, was a major constraint in the distribution of water to the end user in internal areas.  Per capita water supply is low (approx 50 lpcd) against the standard norm of 135 lpcd.  There was lack of technical/skilled man power to handle the system.  15-25% of the water is lost in transmission due to leakage

15 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 4: Existing pipe line map of Mauganj town

16 Initial Environmental Examination- Mauganj Water Supply Scheme

C. Components of the Subproject

16. Water Demand: The current (2016) gross water demand of Mauganj is estimated as 4.66 MLD, while the base year (2018) and ultimate design year (2048) demands are projected at 54.90 MLD and 8.25 MLD respectively.

Table 1: Projected Population and Projected Water Demand

2016 2018 2033 2048

PROJECTED POPULATION (SOULS) Mauganj 28948 30390 44054 51143 En route 2041 2104 2664 3400 Villages Other 35 50 120 200 Hotels/(no of Bed) Total 31024 32544 46838 54743 Population PROJECTED WATER DEMAND (MLD)

Mauganj 4.49 4.72 6.84 7.94 En route 0.16 0.17 0.21 0.27 Villages Other Hotels 0.01 0.01 0.02 0.03 MLD Total MLD 4.66 4.90 7.07 8.25

SOURCE IDENTIFICATION 17. There are three possible sources identified for the Mauganj Town. One is Nihayi River and the other is Gorma Dam and Oda nala.

(1) Nihayi River: It is passing from the town. Flow ceases during summer season (April-May). At present there is sufficient flow (observation dated 7.11.2015) shown in photograph.

 There are 3 main tributary of River Nihai named Joki nala, Barghat Nala & Gora Nala. Catchment area of River Nihai D/s site of existing intake well is 143.36 Sq. Km.  There is one Deh near intake wells. As per area basin survey dead storage capacity is reported 0.040 MCM in length 1600 m and in depth varying from 0.3 m to 3 m.  As the flow of the river ceases during summer season in May. Hence it is proposed to construct weir at a distance of 150m d/s site of existing intake well which is in left bank of River. To avoid submergence on upstream site of proposed RPS height of RPS cannot be kept more than 4.00 m.  From area basin – survey it is clear that only 0.38 M.C.M. water can be stored which is insufficient even to meet demand of town for intermediate year 2033. Hence this proposed source alone will not fulfill our requirement of the town. It (Nihayi river) is tributary of Oda-Nala. As an additional arrangement, to meet out requirement, water will be drawn from Odda Nala itself D/s of Weir near village Khatkari constructed by W.R.D. Distance From Khatkari to Headwork site (intake well site) is about 8kms.

17 Initial Environmental Examination- Mauganj Water Supply Scheme

(A) Silar River:- Silar River is non-perennial & flows in south-west direction to touching boundary of the town. Flow of river ceases in mid of month March. Silar River has catchment area of 134.886 Sq. Km. Silar is also tributary of Oda-Nala. (Topo Sheet 63 H.) Silar cannot be considered as source of the town.

(B) Oda Nala: - Oda nala starts from hilly area (near to village Sitapur). Oda Nala is non-perennial. It crosses NH-7 near village Dagduwa which is about 8 Km. from Mauganj.

 There are two major tributary of Oda Nala named River Nihayi & River Silar. Silar meets Oda before of River Nihayi. Oda forms a fall at village Bahuti named as BAHUTI-FALLS. Falls depth is 465‟ (141.70 M.)Cumulative catchment area of all above mentioned sources (Nihayi, Silar, Oda) are under at village Khatkari.

River Catchment Area (1) Nihayi 150.860 Sq. Km. (From D.P.R. of P.H.E. & Totpo sheet) (2) Silar 134.886 Sq. Km. (From Topo Sheet 63 H.) (3) Oda 179.848 Sq. Km. (From Topo Sheet 63 H.)

 Combined Catchment area of Oda Nala at Village Khatkari = 465.594 Sq. Km. River Nihayi joins Oda Nala near Village Chamarhar no. 6 about 1 Km. from Paikan Tola of village Chamarhar. This junction is called as TIN-MOHAD.

Figure 5: Junction where River Nihayi Joins Odda Naala

 W.R.D. has constructed a RPS at village Khatkari on Oda Nala in year 2015. Length of RPS is 60 m & height is 2 m. During rainy season of year 2015 (July to October-2015) due to this RPS there is huge storage of water in upstream site of Oda Nala, in river Nihayi & Silar. Ultimate demand for year 2048 is 8.25 MLD. As the flow ceases in the month of February. Hence storage for the period (February to June) 5 months is required. Considering storage for 180 days. Storage required is as under.

8.25 MLD = 8.25 X106 lit/Day = 8250 cum/day For 180 days = 180 X 8250 cum = 14, 85,000 Considering evaporation & absorption as 50% of total cum = (1485000) X0.5 = 742500 Total Quantity = 14856000 + 742500 = 2227500 cum = 2.2275 MCM

18 Initial Environmental Examination- Mauganj Water Supply Scheme

(2) Gorma Dam: Gorma Dam owned by W.R.D. is located at a distance of 24 km from Mauganj PWD rest house. Due to less rainfall in the district, storage of water is insufficient. Due to long distance and O&M point of view, Gorma Dam may not be proposed as source of the town. Silent feature of Gorma Dam is as under.

Catchment area: - 140.64 Sq. Km. Length: - 3710 M. Height: - 23.02 M. D.B.L.: - 327 M. M.W.L.:- 326 M. L.S.L.:- 316 M. Total storage capacity:- 39.20 M.C.M. Live-storage:- 36.08 M.C.M. (1274.455 Mc. ft.) Dead Storage:- 03.12 M.C.M. (110.02 Mc. Ft.) Command area:- 91.15 Sq. Km. Modernization of the dam was done in year 2008. As the dam was constructed for the Irrigation Purpose is quite old. Moreover, storage capacity has reduced due to silting. Looking the storage capacity, distance from Mauganj town and Main route of Raw/Clear Water Rising Main from dam Site to town shall be a critical problem in future. Hence Gorma Dam cannot be considered as source for the Town Mauganj.

Figure 6: Location of proposed components on Google map

Hence Nihayi River and Odda Nala are proposed as source for the town.

18. It is proposed to develop a water supply based on Odda Nallah and Nihai River as source for Mauganj Town. This system consists of raw water abstraction from Odda Nallah and Nihai river, transmission, treatment, storage and distribution to consumers . Table 1 shows the nature and size of the various components of the subproject.

19 Initial Environmental Examination- Mauganj Water Supply Scheme

Table 2: Proposed Mauganj Water Supply Subproject Components Infrastructure Function Description Location Weirs and  Construction  Weir at Nihayi River of  Proposed one weir Intake wells of weirs to store 4 m height and 50 m length across River Nihayi near water to meet lean  Weir at Odda Nallah of Existing Intake Well flow demand Raw 4 m height and 60 m length  Second weir is water abstraction proposed across Odda from Odda Nallah nala in right bank at and Nihayi River and Village Khatkari US side supply to WTP of Existing Stop dam

Raw water Transmit raw water  Raw water Rising From Intake wells to WTP transmission from intake to main from Proposed Intake along the PWD road main treatment plant well to Proposed WTP, Dia: 400 mm. Length : 7850 m Type DI-K9  Raw water Rising Main From Existing intake well to Proposed WTP, Dia: 150 mm. Length : 150 m Type DI-K9

Water Treatment of raw 8.30 MLD capacity water Located in Mauganj town Treatment water to meet the treatment plant with in Chandrashekar ward, Plant (WTP) drinking water arrangements: Site is owned by Revenue and clear standards - Alum coagulation & Department, GoMP. water sump flocculation (CWS) - Sedimentation - Rapid gravity filtration - Disinfection with chlorine - Wash water recovery - Sludge drying beds - Miscellaneous infrastructure (compound wall, landscaping, lighting, rest rooms etc) - 400 KL Sump well Pumping To provide adequate  Raw water Pumping  At intake sites Stations pressure in the water Machinery At Proposed Intake supply system well , Discharge-322 cum/hr, . Head-44.0 m  At WTP sites  Raw Water Pumping Machinery At Existing Intake well , Discharge- 41 cum/hr, Head-19.0 m  Clear Water Pumping Machinery At CWS Discharge-322 cum/hr, Head- 50.0 m

Overhead Storage of water at 18 Lac liters capacity RCC One OHT is proposed of 18.0 Tanks (OHTs) higher elevation for tank Lac Lit capacity beside one supply to consumers Defunct existing OHT. It is and Compound wall Govt. land. There is no tree cutting involved during

20 Initial Environmental Examination- Mauganj Water Supply Scheme

construction period. Clear water Treated water Clear water rising mains- These transmission Transmission transmission from  Rising Main From pipelines will be mostly Network WTP to OHTs CWS to Junction A, Dia: 400 laid along the main public mm. Length : 2800 m type DI- roads in the town, which K9 are wider. Pipes will be  Rising Main From laid underground. Junction A to Existing OHT-1 at Zone-1, Dia: 150 mm. Length : 50 m Type DI-K9  Rising Main From Junction A to Proposed OHT- 2 at Zone-2, Dia: 300 mm. Length : 2160 m Type DI-K9 Distribution To distribute water Distribution pipe line of total Pipes will be laid Network from service length 44 km ( HDPE Pipes): underground along the reservoirs to public roads; this work will consumers  Distribution pipe line cover entire area of the HDPE, Pipe - 90 to 315 mm towns; in narrow roads, dia,DI-K9- 315 mm for Zone where there is no place, 1(Length-20883) the pipeline will be laid in  Distribution pipe line the center of the road ; HDPE, Pipe - 90 to 315 mm where the roads are very dia,DI-K9- 350 to 600 mm for wide , the pipelines will be Zone 2A(Length-27360) laid in the road shoulder.  Distribution pipe line HDPE, Pipe - 90 to 315 mm Dia, DI -K9 350 to 400 mm Dia, for Zone 2B(Length- 15307)  Distribution pipe line HDPE, Pipe - 90 to 315 mm for Zone 2C(Length-19317)  Distribution pipe line HDPE, Pipe - 90 to 315 mm dia,DI-K9- 350 to 400 mm for Zone 2D(Length-20611) Bulk Water Monitor water flow Lum- sump Fixed at strategic Meters in the improved locations at source, WTP, network OHTs, DMA inlets etc., bulk meters will be fixed with the pipe section Consumer Provide water to 5,430 nos Water delivery pipe will be connection consumers and connected to distribution with flow measure water lines and meters will be meters usage attached to the delivery pipe at each house with a meter chamber

D. Implementation Schedule

19. After the approval of the detailed project report, bid will be prepared and tenders are likely to be invited by June 2016, and the contract will be awarded by December 2016. Construction is likely to start in January 2017, and will take about 24 months.

21 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 7: Index Map of Proposed WSS

22 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 8: Cross Section of Proposed Intake

23 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 9: Proposed WTP Layout Plan

24 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 10: Proposed Weir cross section

25 Initial Environmental Examination- Mauganj Water Supply Scheme

III POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

20. ADB requires the consideration of environmental issues in all aspects of ADB‟s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

21. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

22. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project‟s impact and risks.

23. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

24. Environmental assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

26 Initial Environmental Examination- Mauganj Water Supply Scheme

25. Applicable environmental regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 3.

Table 3: Applicable Environmental Regulations Law Description Requirement

Madhya Prepared in accordance with the National Permission of WRD, GoMP: Pradesh State Water Policy, it states that “for environmental Water Policy, balance, skillful and planned management of  Water abstraction from Nihai 2003 all types of developmental activities, economic & Odda Rivers and use on equitable basis and in view of the prime construction of RPS & Intake importance of water for all human and other well living beings, an effective and sound water policy is necessary”. (WRD permission has already been obtained. Intake locations Policy is detailed in 17 sections dealing with for Mauganj is finalized in different aspects of water resources. No. 7 discussion with the WRD) deals with Water Allocation Priorities, and according to which drinking water supply shall have the highest priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Water Act was enacted to provide for the prevention WTP require CTE (prior to start (Prevention and control of water pollution and the of constriction) and CFO (prior to and Control of maintaining or restoring of wholesomeness of start of operation) from MPPCB. Pollution) Act water, by Central and State Pollution Control of 1974, Rules Boards and for conferring and assigning to of 1975, and CPCB/SPCBs powers &functions relating to Application has to be submitted amendments water pollution control. online at http://www.mppcb.nic.in/xgn.html

Control of water pollution is achieved through administering conditions imposed in consent issued under to this Act. These conditions regulate the quantity and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) Environment Emissions and discharges from the facilities to Refer National Ambient Air (Protection) be created or refurbished or augmented shall

27 Initial Environmental Examination- Mauganj Water Supply Scheme

Law Description Requirement

Act, 1986 and comply with the notified standards Quality Standards. CPCB Environmental Standards.

Noise Pollution Rule 3 of the Act specifies ambient air quality Refer rule 3 :Noise Pollution (Regulation standards in respect of noise for different (Regulation and Control) Rules, and Control) areas/zones. 2000 amended up to 2010 (on Rules, 2000 CPCB site) amended up to 2010.

Municipal Solid Rules to manage municipal solid waste Solid waste generated at Wastes generated; provides rules for segregation, proposed facilities shall be Management storage, collection, processing and disposal. managed and disposed in Rules, 2016 accordance with the MSWM Rules

Construction & Rules to manage construction & to waste Construction & demolition waste Demolition resulting from construction, remodeling, repair generated from the project Waste and demolition of any civil structure. Rules construction shall be managed Management define C&D waste as waste comprising of and disposed as per the rules Rules, 2016 building materials, debris resulting from (Appendix 10 ) construction, re-modeling, repair and demolition of any civil structure.

Labor Laws The contractor shall not make employment Appendix 9 provides applicable decisions based upon personal characteristics labor laws including unrelated to job requirements. The contractor amendments issued from time to shall base the employment relationship upon time applicable to equal opportunity and fair treatment, and shall establishments engaged in not discriminate with respect to aspects of the construction of civil works. employment relationship, including recruitment and hiring, compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

26. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group‟s Environment, Health and Safety Guidelines. These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from

28 Initial Environmental Examination- Mauganj Water Supply Scheme

these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

Table 4: WHO Ambient Air& Noise Quality Guidelines

29 Initial Environmental Examination- Mauganj Water Supply Scheme

IV DESCRIPTION OF THE ENVIRONMENT (BASELINE DATA)

A. Methodology Used for Baseline Study

27. Data collection and stakeholder consultations: Data for this study has been primarily collected through comprehensive literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites. 28. The literature survey broadly covered the following: i. Project details, reports, maps, and other documents prepared by DPR consultant ii. Discussions with Technical experts, municipal authorities, relevant government agencies like WRD etc. iii. Secondary data from previous project reports and published articles, and iv. Literature on land use, soil, geology, hydrology, climate, socioeconomic profiles, and other planning documents collected from Government agencies and websites. 29. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Physical Environment 30. Mauganj is a Town in Mauganj Mandal in Rewa District in Madhya Pradesh State. Mauganj is the Main Town for the Mauganj Mandal. It is located at a 65 km distance from the Main City Rewa in District. It is located at 601 km distance from its State Main City Bhopal. Mauganj has a good connectivity with the adjoining areas. Geographically, the city lies at 24° 41' North latitude and 81° 53' East longitude at an altitude of about 312 m above mean sea level in Bagelkhand Region.

31. It has a total population of 28948 according to 2011 provisional population totals. The town constitutes a total area of about 46.3 Sq. Km. under the jurisdiction of Mauganj Nagar Parishad and is divided into 15 no. of wards for management of civil services and administration. In June 1973, Mauganj town was declared as Notified Area Committee and in 2011 the town got the status of Nagar Parishad. Mahadev temple which is in Devatalab, only 17 km far from Mauganj. Asht Bhuji temple is also situated nearby. Bahuti waterfall is a huge waterfall situated near to Mauganj having depth of 141.73 m.

32. Mauganj is in the south-eastern part of Rewa District near to the States Border of Madhya Pradesh and Uttar Pradesh, the Mauganj town is well connected to the rest of the towns of M.P. and U.P. by Road, Rail and Airways. Mauganj is 65 km far from Rewa, some villages Panni, Dhera, Barahata, Khatkhri, Padar, Nandanpur.

33. Roadways: National highway 7 (Now NH 35 four lane) passes through the town which connects to Allahabad in the North and Rewa in the west. The town is also well connected to rest of the towns of by State Highways and Major District Roads at regional level.

34. Railway Linkage: As town is not directly linked with Indian Railway System, the nearest railway station is Rewa in Madhya Pradesh at a distance of 65 km.

35. Geography Mauganj is one of the 11 Nagar Parishad of Rewa district of Madhya Pradesh. Mauganj is located at 24.68°N and 81.88°E. It has an average elevation of 313 m (1026 feet). The terrain of the region is typified as plain to gently sloping towards north. The

30 Initial Environmental Examination- Mauganj Water Supply Scheme

medium deep black soils are intensively cultivated and highly potential. The soil is deep clay to loamy, calcareous slightly alkaline and show swells and shrink properties. The soil is calerous, slightly alkaline and shows swell and shrink properties

36. Climate The climate of the area is relatively moderate. During the winter season the temperature falls down to as low as 5.5 degree Celsius. In summer, temperature rises to 42 to 44 degree during the month of May and June.

37. Municipal Area And Planing Area The municipal area is devided in to 15 wards.The City Development Plan will be formulated for Mauganj Nagar Parishad area which is 46.3 Sq. km.

38. Topography Mauganj has an average elevation of 313 metres (1026 feet). The terrain of the region is classified as plain to gently sloping towards north. The medium deep black soils are intensively cultivated and highly potential. The soil is deep clay to loamy, calcareous slightly alkaline and show swells and shrink properties.

39. Rainfall The monsoon season is during June to September with an approximately 90% of all rainfall in the region caused by the monsoon falling from June to October accounts for average annual rainfall of about 950-1100 mm. During monsoon months the relative humidity remains more than 60% normally. The rainfall distribution pattern is irregular but most of gets lost due to runoff. July and August are the months of maximum rainfall. May is the driest month of the year, the scant winter rainfall is useful for the cultivation of Rabi crops but it is usually inadequate without access to supplementary irrigation purpose.

40. Ambient Air and Ambient Noise :- There is no data on ambient air and noise quality in Mauganj town, which are not subject to monitoring by the Madhya Pradesh Pollution Control Board (MPPCB) as there are no major industries.

41. Water Quality: Water pollution includes both surface water pollution and ground water pollution. There is no data availability regarding surface water quality status and pH value variations in the existing lake. Also there is no data available for the ground water quality at the existing bore well. As mentioned earlier, Mauganj does not have an underground sewerage system. 42. Water quality of Nihai river and Odda nallah at the proposed intake location indicates that all the parameters are well within the limits, and suitable for domestic water supply.

Table 5: Source Water Quality Parameters Sample 1(Nihai River) Sample 2 (Odda Permissible Limit Nallah) Temperature, oC 28 27 pH 7.9 8 6.5-8.5 Color, Hazen units Colourless Colourless 5 Total dissolved solids 190 210 500 (mg/l) Total alkalinity (mg/l) 130 152 200 Chlorides (mg/l) 37 56 250 Fluoride (mg/l) Nil Nil 1.0 Total Coliform / 100ml Nil Nil Shall not be detectable in any 100 ml sample Sulphate mg/l Nil Nil 200 Nitrate mg/l Nil Nil 45 Source: Sampling Survey by DPR consultant

31 Initial Environmental Examination- Mauganj Water Supply Scheme

C. Biological Resources 43. The project area –municipal area of Mauganj Nagar Parishad, comprises the habitat areas of Mauganj town. There are no ecologically sensitive features in the project area. Streams are seasonal, so there is no noticeable aquatic life. Flora and fauna found in the area is of local species. Aquatic life in the project areas is not notable, given low rainfall semi-arid zone. Name and distance of the nearest protested area and Forest is as under.

Sr. Forest name Block Direction Distance from Remark No. w.r.to town the Town (1) Bhaishwai Mauganj (N-W) 15 Km. to 40 Nearest Forest Area Beat Forest Quadrant Km. starts just after Bahuti Fall and spread to Shivrajpur, Rehumda of Naigarhi Block (2) There are no archeologically, Historically Protected area and extend to Sohagi Sites with in or near the town is confirmed.

D. Socioeconomic Conditions 44. The decadal growth rate for the year 1991-2001 was registered as 33.47%. At present, as per the census 2011, MNP has registered a total population of 26,411 with a decadal growth rate of 14.71%. As per the census of 2011, the gross density of Mauganj town is 570 persons per sq km, which is increasing continuously since 1991.

YEAR POPULATION 1981 13242 1991 17252 2001 23024 2011 26420

45. Sex Ratio: The ratio between the number of males and the number of females is expressed in number of females per 1000 males. As per the census 2011, the sex ratio in the Mauganj has decreased at 938 females per 1000 males as compared to 2001 census figure of 940.

46. Literacy Rate: Literacy, being an important indicator of social development, affects the demographic characteristics and participation in laour. As per the census 2011, the average literacy rate of Mauganj town has been increased to 61.43% from 51.9% in census 2001.

47. Heritage and Tourism: Mauganj falls under - Rewa- Allahabad tourist circuit. At town level, Mauganj does not have tourist destination and heritage buildings. Bahuti water falls, on Odda Nala, about 60 km from Mauganj is a famous water fall in the state of Madhya Pradesh.

32 Initial Environmental Examination- Mauganj Water Supply Scheme

Figure 11: Survey of India Toposheet Showing Mauganj Town

33 Initial Environmental Examination- Mauganj Water Supply Scheme

34 Initial Environmental Examination- Mauganj Water Supply Scheme

E. Subproject Site Environmental Features

Table 6: Site Environmental Features of proposed components of WSS

Infrastructure Location & Environmental Features Site Photograph Water Intake well will be built in Odda Nallah intake and right bank at Village Khatkari U/S side of River Existing Stop dam under the control of Ponding Water Resources Department, GoMP. structure Capacity of Intake well is 8.3 MLD. Facilities To enhance source reliability and sustainability, one Weir is also proposed of about 4 m height from Bed level at D/S side of Intake well. There will be no submergence or involvement of private land and asset due to construction of this work. Aquatic life of water pool to be taken care during construction activities in the river. One Weir is also proposed at Nihayi

river D/S side of existing intake well of about 4 m height from Bed level.

Water Proposed WTP site is located in the Treatment Dubgawa Village near Existing Intake Plant well site. It is Govt. land. There is no involvement of Forest land.

Water service One OHT is proposed of 18.0 Lac Lit Reservoirs capacity beside one Defunct existing OHT. It is Govt. land. There is no tree cutting involved during construction period.

35 Initial Environmental Examination- Mauganj Water Supply Scheme

Transmission Transmission pipelines will be mostly & laid along the main roads. Pipes will be distribution laid network Underground. The transmission main (400 mm dia) leading to Intake well to WTP, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. Water from this pipeline will also be provided to ULB premises. There is no forest land within the prescribed limit of the town. Hence there is no involvement of Forest land or required any permission for

Transmission network alignment photographs

36 Initial Environmental Examination- Mauganj Water Supply Scheme

V ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

48. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

49. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

50. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

51. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project‟s area of influence.

52. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.asp is used to screen project for environmental impacts and to determine the scope of the IEE.

53. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant; (ii) proposed water abstraction from the sources is very small compared to overall water availability, and the proposed stop dams are so shallow that the submergence is confined to river course itself; (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur.

37 Initial Environmental Examination- Mauganj Water Supply Scheme

A. Pre-Construction Impacts – Design & Location

54. Design of the Proposed Components. Technical design of the (i) intake facilities, including stop dams, (ii) water treatment plant; (iii) raw water and clear water mains, (iv) storage reservoirs, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i) Discontinuation of current unsustainable groundwater source and creating a new water supply system based on nearest surface water sources (ii) Limiting the height of barrage/dam across rivers to create river ponding structure within the river course, to avoid additional submergence (iii) Recovering backwash water from treatment process (iv) Treatment and reuse of sludge from treatment process (v) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (HDPE pipes up to 150 mm dia joined by electro fusion couplers using on-site electro fusion welding, and all higher dia pipes by on site butt welding) (vi) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (vii) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (viii) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (ix) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (x) Using low-noise and energy efficient pumping systems

Alternative Water Source Analysis:

55. The Project water demand for the ultimate year 2048 has been estimated as 8.25 MLD. There are three possible sources identified for the Mauganj Town: Nihayi River, Gorma Dam and Oda nala.

(1) Nihayi River: It is passing from the town. There are 3 main tributaries of River Nihai named Joki nala, Barghat Nala & Gora Nala. This is the existing source. Catchment area of River Nihai D/s site of existing intake well is 143.36 Sq. Km. River is non- perennial and the flow is very high during monsoon, but reduces considerably from the month of February, and completely ceases in March, and up to the arrival of monsoon in mid to late June. Due to this the existing intake is non-operation for half of the year.

(2) Silar River:- Silar River is non-perennial & flows in south-west direction to touching boundary of the town. Flow of river ceases in mid of month March. Silar River has catchment area of 134.886 Sq. Km. Silar is also tributary of Oda-Nala. Silar cannot be considered as source of the town.

(3) Oda Nala: - Oda nala starts from hilly area (near to village Sitapur). Oda Nala is non- perennial. It crosses NH-7 near village Dagduwa which is about 8 Km. from Mauganj. There are two stop dams on Oda Nala downstream of Junction of River Nihai & Oda Nala known as TIN MOHAD. (1) Karahi Weir (Left Bank – Karahi Village and on the right bank – Village Khatkari) and (2) Sumeda Weir. Sumeda weir is on downstream

38 Initial Environmental Examination- Mauganj Water Supply Scheme

side of Karahi Weir at a distance of about 4.5 Km. Both the stop dams have been constructed by the W.R.D. in the year 2015. There are two major tributary of Oda Nala named River Nihayi & River Silar. Silar meets Oda before of River Nihayi. Oda forms a fall at village Bahuti named as BAHUTI FALLS and with a depth of 465 feet (141.70 m) it is the highest water fall in the state of Madhya Pradesh. Oda flows down further and joins Bihad River, which in turn is a tributary of Tons River.

56. Water availability. There are no flow gauging stations on any of these rivers, and therefore no flow records available. Discussion with the WRD and municipal staff managing water supply, and the local people, indicate that all the rivers are seasonal, and flow for about 7-8 months a year, with very high flows during monsoon. Rivers almost run dry during the months of March – May. The flow record available for the year 1969, January to April indicate a negligible flow (range of 0.0014 – 0.0102 cumec (cubic meter per second), which is much less than the demand of 0.1167 cumec (2.97 MCM per year or 8.4 MLD with 20 hour pumping from river intake).

57. Although the above 3 are separate rivers, but are all interconnected, and forms part of Oda nala network, which in turn is a tributary of Bihad River. Nihai, and Silar feed into Oda, and in addition, Oda has its separate catchment. Cumulative catchment area of all above mentioned sources (Nihayi, Silar, Oda) at village Khatkari is given below. Combined Catchment area of Oda Nala at Village Khatkari is 465.594 sq km. River Nihayi joins Oda Nala near Village Chamarhar. This junction is called as TIN-MOHAD.

o Nihayi 150.860 Sq. Km. (From D.P.R. of P.H.E. & Topo sheet) o Silar 134.886 Sq. Km. (From Topo Sheet 63 H.) o Oda 179.848 Sq. Km. (From Topo Sheet 63 H.)

58. With an average of 900- 1000 m annual rainfall, the above catchment can generate significant quantities of runoff every year. The flow is considerable during the monsoon and post monsoon period of June-December/January, and therefore will be able to meet the demand. As the flow started to reduce from February, and up to the next monsoon season, raw water storage is required to meet the demand of this lean flow season. Hence it is proposed to create a storage in the river by constructing a small stop dam across the river. The period for storage has been taken from January to June i.e. Six Month (180) days, and the storage requirement is estimated as 1.485 MCM.

Requirement of water for 180 days i.e. = 180 * 8.25 ML 1st January to 30th June (6 months) = 1485 ML = 1.485 MCM

59. It is proposed to construct a weir across River Nihai, on the downstream side of the existing intake to create a river ponding structure. It is also considered that the dam height should be as low as possible so that the submergence is limited to the river course, and it is found that there shall be no any submergence when the height of Weir(stop dam) is kept at 4 m at proposed site on River Nihai. On the basis of area basin survey, it is estimated that this dam will have a storage capacity of 0.38 MCM, which can meet only 25% of the above lean period demand, and will be sufficient for about 45 days only. Therefore additional storage is required to meet the rest of the demand.

39 Initial Environmental Examination- Mauganj Water Supply Scheme

60. It is therefore proposed to construction another Weir (stop dam) across Odda Nala. WRD already construction 2 stop dams on Odda nala, on the downstream of its junction with Nihai. With a dam height of 1.5 m, both the WRD dams have created a storage of about 0.48 MCM each in Oda Nala. It is proposed to construction a dam with a height of 4 m, which will ensure that the submergence is limited to river course, and will also be adequate to meet the rest of the demand. This dam will be constructed on Oda nala, downstream of its confluence with Nihai and Silar rivers, but upstream of existing WRD stop dams. Bahut Wall will be 10 km downstream of the proposed dam location.

61. As pointed out all the dams are interlinked. (Line diagram of Rivers, Nala map showing their Junction, flow, direction – existing stop dam & proposed stop dam has been shown in the below.

Figure 12: Odda River Network and Existing & Proposed Dams

40 Initial Environmental Examination- Mauganj Water Supply Scheme

62. Source water sustainability and environmental considerations. In Mauganj, water is proposed to be sourced from the nearest river and Nallah, Nihai and Odda, respectively. Water will be abstracted from a gravel packed well, to be constructed in the river bed that will convey water to the intake well at the bank of the river. To ensure water availability during the no-flow period, weirs are proposed.

63. These are small dams, with a height of just 4 m above the river bed level (same as depth of river banks), thus confining the submergence to river course itself. This will ensure adequate water availability to meet the demand of no-flow period. Dam will consists of 2.5 solid structure (built in RCC) and 1.5 m curry shutters. During the monsoon high flows shutters will be open to allow free flow over 2.5 m RCC dam. Given very small storage, dam will be filled at the first monsoon flow itself, and the water coming from the upstream will overflow freely. Therefore the change in flow regime due to this small dam will be negligible on downstream users and river eco system. The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life. Water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. No negative impacts thus envisaged.

64. Weir across River Nihai: - After construction of stop dam, surplus water will flow and shall meet with Oda Nala as it is tributary of Oda at TIN MOHAD and shall feed to Oda Nala. There are no notable water abstraction points on the downstream side of proposed stop dam site on River Nihai. Both the sides of the river is covered with agriculture lands. There is no any forest in this reach. As the river is seasonal, and the proposed dam is very small and therefore there will be no significant change in the downstream flow regime. No impacts on river ecology anticipated. River flows downstream and joins Oda nala, which again carries considerable flow, therefore impact of flow reduction will be negligible.

65. Weir across Oda Nala: -There are two existing stop dams known (Karahi Weir & Sumeda Weir) of WRD on the downstream of the proposed dam site on Odda nala. Oda Nala forms Bahuti Falls of 465ft. (141.70 m) at Bahuti village about 10 km downstream of proposed dam site. Both the sides of Oda Nala are covered with agricultural lands. Deep hilly valley starts from Bahuti fall. There is forest on both side of valley after the fall. After this fall (Oda) this is known as Nahala Nala, which finally, meets with River Belan (Uttar Pradesh). There is no any adverse effect on downstream users as they will get water for irrigation purpose as per provision kept by the W.R.D. As the water will flow freely once the dam is full (and the dam will get full with first monsoon flow itself given very small storage), there will not be any impact on both the downstream dams of WRD. Also impact on Bahut water falls or its related tourism is anticipated as the proposed dam will not change the flow regime considerably, given the limited height and small storage. Water falls is seasonal, and attractive mostly during the monsoon flows of July to December.

66. Water quality. Existing water quality of Nihai and Odda is good, and is suitable for domestic supply after conventional treatment and disinfection. There are no notable pollution sources in the vicinity. Therefore no impacts envisaged.

67. Use of Chlorine as disinfectant. It is proposed to use chlorine at WTP to disinfect the water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Although facilities are not located close to habitations, safety precautions are necessary to

41 Initial Environmental Examination- Mauganj Water Supply Scheme

ensure the safety of workers and citizens. To avoid any risk, chlorination facility will be provided with following safety provisions:

o Chlorine neutralization pit with a lime slurry feeder o Proper ventilation, lighting, entry and exit facilities o Facility for isolation in the event of major chlorine leakage o Personal protection and safety equipment for the operators in the chlorine plant o Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier o Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

68. Similarly proposed works in the river bed (for dam and intake) may damage the river bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Measures are included in the EMP to avoid, minimize these impacts Removal of trees and vegetation will be minimize by best alignment and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of compensatory tree plantation is included in the EMP.

69. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP.

70. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, etc.,

71. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor‟s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

C. Construction Impacts

72. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of all the towns are very narrow and congested with pedestrians

42 Initial Environmental Examination- Mauganj Water Supply Scheme

and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

73. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excel soil shall be used for construction.

74. Other civil works in the subproject include construction of stop dam across river Oda and Nihai, intake cum pump house on the river bank including a gravel packed wells in the river that will connect to intake well, raw water pumping station including laying of water intake pipes, water treatment plant, water tanks (ground level / overhead), pumping station at identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc.

75. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. These anticipated impacts are temporary.

76. Sources of Materials. Significant amount of sand and coarse aggregate will be required for this project. The construction contractor will be required to:

o Use material sources permitted by government; o Verify suitability of all material sources and obtain approval of PIU; and o Submit to PIU on a monthly basis documentation of sources of materials.

77. Air Quality. Emissions from construction vehicles, equipment, and machinery used for excavation and construction will induce impacts on the air quality in the construction sites. Anticipated impacts include dusts and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons. These however will be temporary, limiting to construction activities only. To mitigate the impacts, construction contractors will be required to: o Damp down exposed soil and any stockpiled material on site by water sprinkling; o Use tarpaulins to cover sand and other loose material when transported by trucks; o Clean wheels and undercarriage of haul trucks prior to leaving construction site o Disallow access in the work area except workers to limit soil disturbance and prevent access by barricading and security personnel o Fit all heavy equipment and machinery with air pollution control devices which are operating correctly

78. Surface Water Quality. Run-off from stockpiled materials and chemical contamination from fuels and lubricants during construction works can contaminate downstream surface water quality of the streams. As the rainfall in the project areas is mostly confined to monsoon,

43 Initial Environmental Examination- Mauganj Water Supply Scheme

these potential impacts are short-term and temporary. However, to ensure that these are mitigated, construction contractor will be required to:

o All earthworks be conducted during the dry season to prevent the problem of soil run- off during monsoon season; o Avoid stockpiling of earth fill especially during the monsoon season unless covered by tarpaulins or plastic sheets; o Prioritize re-use of excess spoils and materials in the construction works. If spoils will be disposed, only designated disposal areas shall be used; o Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies; o Place storage areas for fuels and lubricants away from any drainage leading to water bodies; o Dispose any wastes generated by construction activities in designated sites; and o Conduct surface quality inspection according to the Environmental Management Plan (EMP).

79. Construction of dam in the river may lead to degradation of water quality due to increase in turbidity and chemical contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life, silting/chocking of spill ways/ canals etc., Though there are no notable aquatic life, to ensure that any negative impacts are mitigation, the contractor will be required to: o Select a construction methodology that is least disturbing, and appropriate for the in- situ soil condition, and able to complete the construction work prior to onset of monsoon o Schedule the construction works during low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with dam authorities on release of water; avoid scheduling the works during water release period. o Erect temporary barriers to form enclosed construction area with least disturbance o Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond o Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage

80. Generation of Construction Wastes. Solid wastes generated from the construction activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers‟ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:

o Prepare and implement a Construction Waste Management Plan o Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies; o Avoid stockpiling any excess spoils. Excess excavated soils should be dispose to approved designated areas; o Domestic solid wastes should be properly segregated in biodegradable and non-

44 Initial Environmental Examination- Mauganj Water Supply Scheme

biodegradable for collection and disposal to designated solid waste disposal site; o Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed in disposal sites approved by local authorities; o Prohibit burning of construction and domestic waste; o Ensure that wastes are not haphazardly dumped within the project site and adjacent areas. o Get approval of PIU in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

81. Noise and Vibration Levels. Except water intake and WTP, all the construction works will be conducted at selected sites and along the roads in Mauganj urban area and surroundings, where there are houses, schools and hospitals, religious & historical places and small-scale businesses. The sensitive receptors are the general population in these areas. Increase in noise level may be caused by excavation, particularly breaking of cement concrete or bitumen roads, operation of construction equipment like concrete mixers, and the transportation of equipment, materials, and people. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings and monuments. This impact is negative but short-term, and reversible by mitigation measures. The construction contractor will be required to:

o Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance; o Horns should not be used unless it is necessary to warn other road users or animals of the vehicle‟s approach; o Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimise sound impact to surrounding sensitive receptor; and o Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. o Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;

82. Surface and Groundwater Quality. Another physical impact that is often associated with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In Mauganj groundwater is deeper than the proposed excavation depths, and rains are limited to short duration during monsoon. However, to ensure that water will not pond in pits and voids near project location, the construction contractor will be required to conduct excavation works in non-monsoon season to the maximum extent possible.

83. Accessibility. Excavation along the roads, hauling of construction materials and operation of equipment on-site can cause traffic problems. Roads in the core/old town area is very narrow. However, most of the roads are used by pedestrians and two wheelers, and four wheelers vehicles are very limited. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:

o Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in

45 Initial Environmental Examination- Mauganj Water Supply Scheme

congested areas – immediately removed from site/ or brought to the as and when required o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; o Schedule transport and hauling activities during non-peak hours; o Locate entry and exit points in areas where there is low potential for traffic congestion; o Keep the site free from all unnecessary obstructions; o Drive vehicles in a considerate manner; o Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours o Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. 84. Wherever road width is minimal, there will be temporary loss of access to pedestrians and vehicular traffic including 2 wheelers during the laying of pipes. Under those circumstances, contractor shall adopt following measures:

o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access.

85. Socio-Economic – Income. The project components will be located in government land and there is no requirement for land acquisition or any resettlement. Construction works will impede the access of residents to specific site in limited cases. The potential impacts are negative and moderate but short-term and temporary. The construction contractor will be required to:

o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; o Consult businesses and institutions regarding operating hours and factoring this in work schedules; and o Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints. o Notify community/ water users in advance about likely interruptions in water supply. o Provide alternate sources of clean water until water supply is restored.

86. Socio-Economic – Employment. Manpower will be required during the 24-months construction stage. This can result in generation of temporary employment and increase in

46 Initial Environmental Examination- Mauganj Water Supply Scheme

local revenue. Thus potential impact is positive and long-term. The construction contractor will be required to:

o Employ at least 50% of the labour force, or to the maximum extent; and

87. Occupational Health and Safety. Workers need to be mindful of the occupational hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:

o Comply with all national, state and local labour laws (see Appendix 9); o Develop and implement site-specific occupational health and safety (OH&S) Plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal protective equipment; (c) OH&S Training1 for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; o Ensure that qualified first-aid is provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; o Provide medical insurance coverage for workers; o Secure all installations from unauthorized intrusion and accident risks; o Provide supplies of potable drinking water; o Provide clean eating areas where workers are not exposed to hazardous or noxious substances; o Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; o Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; o Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; o Ensure moving equipment is outfitted with audible back-up alarms; o Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general

1 Some of the key areas that may be covered during training as they relate to the primary causes of accidents include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to assess staff competence to ensure that the training provided is relevant and effective. Supervision and monitoring arrangements shall be in place to ensure that training has been effective and the worker is competent at their job. The level of supervision and monitoring required is a management decision that shall be based on the risks associated with the job, the level of competence required, the experience of the individual and whether the worker works as part of a team or is a lone worker.

47 Initial Environmental Examination- Mauganj Water Supply Scheme

public as appropriate; and o Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

88. Asbestos Materials. Existing water distribution network is mostly asbestos cement (AC) pipes, and because of the health risks these will be left in situ and replaced by new pipes. Plan pipeline alignments carefully to avoid any conflict or damage.

89. Community Health and Safety. Hazards posed to the public, specifically in high-pedestrian areas may include traffic accidents and vehicle collision with pedestrians. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Plan routes to avoid times of peak-pedestrian activities. o Liaise with PIU in identifying risk areas on route cards/maps. o Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. o Provide road signs and flag persons to warn of on-going trenching activities.

90. Work Camps. Operation of work camps can cause temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants. Potential impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Consult PIU before locating project offices, sheds, and construction plants; o Minimize removal of vegetation and disallow cutting of trees; o Provide drinking water, water for other uses, and sanitation facilities for employees; o Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; o Prohibit employees from poaching wildlife and cutting of trees for firewood; o Train employees in the storage and handling of materials which can potentially cause soil contamination; o Recover used oil and lubricants and reuse or remove from the site; o Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; o Remove all wreckage, rubbish, or temporary structures which are no longer required; and o Confirm to PMU report in writing that the camp has been vacated and restored to pre-project conditions before acceptance of work.

91. Debris disposal. Prior to the commencement of works, contractor shall identify a debris disposal site in consultation with the PIU and adhering to following criteria:

o The site shall be selected preferably from barren, infertile lands. In case

48 Initial Environmental Examination- Mauganj Water Supply Scheme

agricultural land needs to be selected, top-soil stripping, stacking and preservation should be undertaken prior to initiation of any activities. o Debris disposal site shall be at least 200 m away from surface water bodies2. o No residential areas shall be located within 100 m downwind side of the site. o The site is minimum 250 m. away from sensitive locations like hospitals, religious places, ponds/lakes or other water bodies. o The local governing body and community shall be consulted while selecting the site.

D. Operation and Maintenance Impacts

92. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components), it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

93. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

94. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable

E. Project benefits

95. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

96. The citizens of Mauganj will be the major beneficiaries of the improved water supply system,

2 In the absence of site meeting the stipulated criteria, an alternate site can be selected specifying the reasons. In such a case, the construction camp management plan should incorporate additional measures specific to the site as suggested by the Construction Manager.

49 Initial Environmental Examination- Mauganj Water Supply Scheme

as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

VI. INFORMATION DISCLOSURE AND PUBLIC CONSULTATION

A. Overview

97. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

98. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in Mauganj PWD, WRD and Madhya Pradesh Pollution Control Board. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, ULB and PIUs), Government of India and the ADB.

B. Public Consultation

99. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

100. Institutional consultations were conducted with the Governmental Departments such as PMU, Pollution Control Board, Public Health Engineering Department, Water Resourced Department, and ULB. The project proposal is formulated in consultation with Mauganj Nagar Parishad and suits the requirements of the ULBs.

101. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites.

102. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to enhance the infrastructure service levels and the living standard of the public.

50 Initial Environmental Examination- Mauganj Water Supply Scheme

2. Consultation during construction

103. Prior to start of construction, ULB and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

104. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

105. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the UADD, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

106. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

107. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

VII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

108. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP‟s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

109. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons‟ grievances related to the program. The multi- tier GRM for the project is outlined below, each tier having time- bound schedules and with responsible persons identified to address grievances and seek appropriate persons‟ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

110. Who can complain: A complaint may be brought by persons who are, or could be, “directly, indirectly, materially, and adversely” affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf.

111. What the Grievance/Complain should contain: Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem.

112. Where to file a Complaint: Complainants will have the flexibility of conveying grievances/suggestions by dropping grievance redress/suggestion forms in complaints/suggestion boxes to be installed by project at Mauganj Nagar Parishad offices, PIU offices or by e-mail or by writing in a complaints register in the PIU offices or at construction site offices.

113. How to file a Complaint: The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 13.

(i) Offline System - The application can be made on the application form available at all accessible places (NPs/ Office of PIUs/ construction site offices). The application should have the name and complete postal address of the applicant.

(ii) Online System - Grievances pertaining to the implementation of the project can also be filed online at the website of MPUDC/PMU or by e-mails.

114. Documentation: Documentation of the complaints is important and must contain name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the 52 Initial Environmental Examination- Mauganj Water Supply Scheme

community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

115. Grievance/Problem Redress through Participatory Process: Efforts must be made by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

116. Following process will be followed:

(i) 1st level grievance. In case of grievances that are immediate and urgent in the perception of the complainant, PMC supervising staff will direct the contractor to and ensures that it is resolved. If the grievance is not under the contractor scope, but under the program, PMC (field office) will resolve this issue. All the grievances should be resolved within 3 days of receipt of a complaint/grievance.

(ii) 2nd level grievance. All grievances that cannot be redressed at first level within 3 days will be brought to the notice of PIU and PMC Assistant Environmental Specialist. PIU will review the grievance and act appropriately to resolve it within 10 days of receipt.

(iii) 3rd level grievance. All the grievances that are not addressed at 2nd level by PIU within in 10 days of receipt will be brought to the notice of notice of the Grievance Redressal Committee (GRC)3. GRC will meet twice a month and determine the merit of each grievance brought to the committee. The GRC will resolve the grievance within 1 month of receiving the complaint. All decisions taken by the GRC will be communicated to complainant by the Nodal Officer.

117. The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation4, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

118. Record-keeping. PIU will keep records of grievances received, corrective actions taken and the final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

53 Initial Environmental Examination- Mauganj Water Supply Scheme

IX ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

119. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with a flexibility to redeployment depending upon the implementation requirements.

120. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

121. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno-economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

122. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build-operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

123. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

124. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

125. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

126. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) 54 Initial Environmental Examination- Mauganj Water Supply Scheme

ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

127. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

128. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

129. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

130. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

55 Initial Environmental Examination- Mauganj Water Supply Scheme

56

Table 7: Design Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds Design of Unsustainable  Discontinuation of current unsustainable groundwater source and These measures Part of water supply source; creating new water supply system based on a nearest surface are already project system resource & water source included in the costs energy use  Appropriate location of river intake to ensure water availability preliminary throughout the year, thereby avoiding the need to construct a designs. dam/barrage to create storage  Recovering wash water from treatment process DBO Contractor  Treatment and reuse of sludge from treatment process (DBOC) to  Minimizing water losses from pipelines by perfect jointing and follow, enhance alignments using appropriate techniques (HDPE pipes up to 150 where possible. mm dia joined by electro fusion couplers using on-site electro fusion welding, and all higher dia pipes by on site butt welding) PMU to ensure  Designing the entire system to maintain optimal flow and terminal compliance. pressure, and optimising the overall energy usage  Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies  Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor  Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections  Using low-noise and energy efficient pumping systems Water Project  Obtain permission from Water resources department, GoMP for PMU & Mauganj No costs; abstraction sustainability construction of dam (RPS) and Intake well Nagar Parishad, scope of & water use Permission IA conflicts already obtained Waste Environmental  Obtain consent from MPPCB for WTPs at Mauganj prior to start of PMU / Nagar No costs; generation pollution construction Parishad; DBOC scope of from WTP to prepare IA & DBO

57

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds operations application, and assist as required Chlorine Chlorine  Provide the following measure at the chlorine application unit: These measures Project usage as handling & o Chlorine neutralization pit with a lime slurry feeder are already Costs disinfectant application o Proper ventilation, lighting, entry and exit facilities included in the at WTP risk – health o Facility for isolation in the event of major chlorine leakage (if preliminary &safety risk to needed) designs. workers and o Personal protection and safety equipment for the operators in general public the chlorine plant DBOC to follow, o Provide training to the staff in safe handling and application of enhance where chlorine; this shall be included in the contract of Chlorinator possible. supplier o Supplier of Chlorinator equipment shall provide standard PMU to ensure operating manual for safe operation and as well as compliance. maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

57 58

Table 8: Pre-Construction Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds EMP Unsatisfactory  Appoint EHS supervisor and designate 1 EHS DBO contractor Cost for Implementation compliance to coordinator (among the technical staff) in each town implementation & reporting EMP  Ensure that all pre-construction activities are of mitigation complete prior to start of construction work measures  Ensure timely submission of monitoring reports responsibility of contractor. Utilities Damage/  Identify and include locations of utilities in the DBOC with PIU Project costs – disturbance to detailed designs/drawings to prevent unnecessary collaboration. general telephone lines, disruption of services PMU to ensure construction electric lines, water  Prepare a contingency plan to include actions to be compliance practice lines in project taken in case of unintentional interruption of services. area Construction Degradation of  Schedule the works on river bed during summer low- DBOC to follow Project costs – works on river river course and flow period general bed (intake) pollution  Do not disturb river bed except the actual work area; PIU/ PMU to construction no equipment, machinery shall be operated outside ensure practice the work area compliance  Avoid use of fuels, chemicals & lubricants; ensure no spillage  Clean up the area after the completion & prior to the onset of monsoon flow Construction Conflicts with local  Prioritize barren, waste, infertile, vacant lands within DBOC to identify Part of project work camps, community; the area, locations costs stockpile disruption to traffic  Shall not be located in productive agricultural lands, following the areas, storage flow and sensitive water bodies, natural drainage channels, flood plains criteria areas and receptors & groundwater recharge areas, forests, vegetative waste disposal lands, etc. PIU to ensure areas  Locate at sites that will not promote instability, compliance and flooding and result in destruction of natural drainage, approve vegetation, irrigation, & drinking water supply;  For private lands, obtain land owner‟s (not lessees) written consent; indicate the requirement for

58 59

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds reinstatement to original  Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,)  Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community.  Document site‟s pre-project conditions Sources of Extraction of  Obtain material only existing borrow sites/quarries DBOC to identify Part of project Materials materials can already permitted by the Department of Mines and sources that costs disrupt natural land Geology; have all permits, contours and  If new quarries sites/quarries are necessary, if required, vegetation contractor shall be obtain all necessary permissions obtain permits, resulting in as per the law in force. and submit to accelerated  Contractor to obtain construction materials only after PIU erosion, written permission / approval of PIU for respective disturbance in sources PIU to check natural drainage  Maintain a construction material register at the site and approve patterns, ponding and water logging, and water pollution. Consents, Failure to obtain  Obtain all necessary consents, permits, clearance, PMU / PIU to Part of project permits, necessary NOCs, etc required for the project prior to award of obtain project costs clearances, consents, permits, contact or start of civil works, as necessary. clearances; NOCs, etc. NOCs, etc. can  Include in detailed designs, drawings and documents DBOC to provide result to design all regulatory conditions and provisions, where necessary revisions and/or required assistance stoppage of works  Contractor to identify & obtain all necessary approvals, including in compliance with labour laws, DBOC to obtain before start of construction; construction  Contractor to acknowledge in writing to PIU and permits &

59 60

Field Anticipated Mitigation Measures Responsible for Cost and Impact Implementation Source of Funds provide copies of all obtained permits, clearance, PIU to ensure NOCs, etc. Asbestos Health risk due to  Obtain details from PHED/NPs on location of DBOC in Part of project Cement Pipes exposure to underground AC pipes coordination with costs asbestos materials  Locate the new piper carefully to avoid encountering PIU and ULB AC pipes  Leave the AC pipes undisturbed in the ground.

Table 9: Construction Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds EMP Irreversible impact  Project manager and all key workers DBOC Cost of EMP Implementation to the will be required to undergo training PMC Implementation Training environment, on EMP implementation including Construction and Orientation Training to workers, and spoils/waste management, Standard Environmental contractor is community operating procedures (SOP) for Specialists to responsibility of PMU. construction works; occupational conduct the Other costs responsibility health and safety (OH&S), core labor training of contractor. laws, applicable environmental laws, etc. Air Quality Emissions from  Control dust by water sprinkling on DBO Contractor Cost for implementation construction exposed soil, stock stockpiled of mitigation measures vehicles, material on site responsibility of equipment, and  Barricade area, provide wind sheets contractor. machinery used  Use tarpaulins to cover sand and for installation of other loose material when Air quality monitoring pipelines resulting transported by trucks; costs are included in the to dusts and  Clean wheels and undercarriage of EMP costs of project increase in haul trucks prior to leaving concentration of construction site vehicle-related  Prevent entry of traffic, public in pollutants such as construction area

60 61

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds carbon monoxide,  Fit all heavy equipment, and sulfur oxides, machinery with air pollution control particulate matter, devices which are operating nitrous oxides, and correctly; all the vehicle shall meet hydrocarbons. the emission norms and shall have valid pollution under control (PUC) certificate (Appendix 7)  Conduct air quality monitoring as per the monitoring plan Surface water Mobilization of  Avoid earthworks during the rainy DBO Contractor Cost for implementation quality settled silt season of mitigation measures materials, and  Avoid stockpiling of earth fill responsibility of chemical especially during the monsoon contractor. contamination season unless covered by tarpaulins from fuels and or plastic sheets; Water quality monitoring lubricants during  Reuse excess spoils & materials in costs are included in the installation of the construction as far a possible EMP costs of project pipelines can  Identify disposal sites prior to contaminate construction & dispose construction nearby surface waste only at designated areas water quality.  Install temporary silt traps basins along the drainage leading to the water bodies;  Place storage areas for fuels and lubricants away from any drainage leading to water bodies;  Conduct surface quality inspection according to the Environmental Management Plan (EMP). Noise Levels Increase in noise  Conduct noise generating activities DBO Contractor Cost for implementation level due to earth- (eg, cc road cutting) during day time of mitigation measures moving and  Minimize noise from construction responsibility of excavation equipment (by using vehicle contractor. equipment, and silencers, fitting jackhammers with

61 62

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds the transportation noise-reducing mufflers, and use of equipment, portable street barriers to minimise materials, and sound impact to surrounding people sensitive receptor;  Maintain maximum sound level not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s.  Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;  Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape and Impacts due to  Prepare and implement a DBO Contractor Cost for implementation aesthetics excess excavated Construction Waste Management of mitigation measures earth, excess Plan responsibility of construction  Stockpiles, lubricants, fuels, and contractor. materials, and other materials should be located solid waste such away from steep slopes and water as removed bodies; concrete, wood,  Avoid stockpiling any excess spoils; packaging dispose immediately to designated materials, empty areas containers, spoils,  Domestic solid waste generated at oils, lubricants, construction camps and work sites and other similar shall be properly managed (collected, items. segregated, disposed properly); waste should not burned  Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed through approved recyclers

62 63

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds  Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Loss of vegetation  Avoid removal of vegetation / tree DBO Contractor Cost for implementation Resources – and tree cover cutting of mitigation measures Terrestrial  If unavoidable, minimize as far as responsibility of possible, and obtain tree-cutting contractor. permit  Plant 10 trees for every one cut Land use Environmental  The impact due to change in land Not applicable Not applicable Issues due to land use will be negligible due to this use change project. Accessibility Traffic problems  Confine work areas along the roads DBO Contractor Cost for implementation and conflicts near to the minimum possible extent; all of mitigation measures project locations the activities, including material & responsibility of and haul road waste/surplus soil stocking should be contractor. confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required  Leave spaces for access between mounds of soil;  Provide walkways and metal sheets where required to maintain access across for people and vehicles;  Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites;  Schedule transport and hauling activities during non-peak hours;

63 64

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds  Keep the site free from all unnecessary obstructions;  Drive vehicles in a considerate manner;  Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids  Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.  For works in very narrow roads o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access  Do not obstruct access; provide DBO Contractor Cost for implementation Income. of residents and temporary access, by leaving spaces of mitigation measures customers to in excavation, provide walkways and responsibility of nearby shops metal sheets for people and vehicles contractor. where necessary to continue business  Increase workforce in the areas with

64 65

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds predominantly institutions, place of worship, business establishment, hospitals, and schools;  Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio-Economic – Generate  Employ local persons in construction DBO Contractor Cost for implementation Employment temporary work if manpower is available of mitigation measures employment and responsibility of increase in local contractor. revenue Occupational Health Occupational  Comply with all national, state and DBO Contractor Cost for implementation and Safety hazards which can local core labor laws (see Appendix 7 of mitigation measures arise during work of this IEE) responsibility of  Implement site-specific occupational contractor. health and safety (OH&S) measures, such as the following  Provided personal protective equipment (PPE) to workers (like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used  Conduct OH&S training workers/staff  Do no employ ad-hoc work procedures, follow best & acceptable work practices  Document work-related accidents  Provide qualified & easily accessible first-aid facilities all times at all sites  Secure all installations from unauthorized intrusion and accident risks;  Provide potable drinking water;  Provide clean eating areas where

65 66

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds workers are not exposed to hazardous or noxious substances;  Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers;  Ensure that visitor/s do not enter hazard areas unescorted  Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;  Ensure moving equipment is outfitted with audible back-up alarms;  Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and  Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively. Community Health Traffic accidents  Plan routes to avoid times of peak- DBO Contractor Cost for implementation

66 67

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds and Safety. and vehicle pedestrian activities and high risk of mitigation measures collision with areas. responsibility of pedestrians during  Prevent public entry in to work areas contractor. material and waste through barricading and security transportation guards  Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure.  Provide road signs and flag persons to warn of on-going trenching activities.  In very narrow streets, conduct work section-wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and  Establish camps only after site DBO Contractor Cost for implementation worksites noise pollution approval of mitigation measures from machine  Do not location camps near water responsibility of operation, water bodies (maintain atleast 1 km buffer) contractor. pollution from  Avoid cutting of trees/ clearing storage and use of bushes fuels, oils,  Provide adequate drinking water, solvents, and water for other uses, and sanitation lubricants facilities  Ensure conditions of livability at work Unsanitary and camps are maintained at the highest poor living standards possible at all times; conditions for  Prohibit employees from poaching workers wildlife and cutting of trees for firewood;  Train employees in the storage and handling of materials which can

67 68

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds potentially cause soil contamination;  Recover used oil and lubricants and reuse or remove from the site;  Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas;  Ensure unauthorized persons specially children are not allowed in any worksite Post-construction Damage due to  Remove all spoils wreckage, rubbish, DBO Contractor Cost for implementation clean-up debris, spoils, or temporary structures (such as of mitigation measures excess buildings, shelters, and latrines) responsibility of construction which are no longer required contractor. materials  All excavated roads shall be reinstated to original condition.  All disrupted utilities restored  All affected structures rehabilitated/ compensated  The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up.  All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regrassed  The contractor must arrange the cancellation of all temporary services.  Restore the work sites to pre-project conditions; PIU to approve in writing

68 69

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Mitigation Funds that site is restored

69 70

Table 10: Operation Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Monitoring of Cost and Impact Mitigation Mitigation Source of Funds

Check for Loss of water,  Effective leak detection and water DBO Contractor PIU and Operating blockage and increased demand auditing to reduce the water losses Mauganj Nagar costs leakage and inconvenience Parishad problems to consumers & reducing the general public water losses

Water Impacts on public  Ensure protection of water source Mauganj Nagar PMU in Operating contamination – health quality (Nihai River & Oda Nala), any Parishad coordination costs raw water entry of wastewater into the river with WRD contamination upstream of stop dam sites should be prevented. at source and  Contamination of treated water during DBO Contractor treated water transmission and distribution should PIU and during be prevented by quickly identifying, Mauganj Nagar transmission isolating and repairing the leak Parishad section. Develop a system of leak detection and rectification.  Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 8) Discharge the Pollution of  Backwash water will be recirculate so DBO Contractor PIU and Operating impurities and streams /drains no wastewater generated from WTPs Mauganj Nagar costs other solids  Maintain the mechanical parts as per Parishad collected due to the maintenance plan to avoid any hazards filtration and back wash

70 71

Field Anticipated Mitigation Measures Responsible for Monitoring of Cost and Impact Mitigation Mitigation Source of Funds

Sludge Land and water  Collect the sludge from WTP units, DBO Contractor PIU and Operating generation pollution, impacts dry in sludge drying beds, and reuse / Mauganj Nagar costs on health & dispose safely as per the design Parishad environment

Increased in Water pollution,  Sanitation facilities needs to be Mauganj Nagar PMU To be sewage and impacts on improved at community level and at Parishad identified generation public health and the town level to meet the increased - environment sewage demand respective NPs

Generation of Impacts on public  Collect solid wastes and dispose to DBO Contractor PIU and Operating waste materials health and approved disposal yards Mauganj Nagar costs environment Parishad

Occupational Health, social and  Provide appropriate PPE to workers & DBO Contractor PIU and Operating health and economic impacts training on its proper use Mauganj Nagar costs safety on the workers  Use fall protection equipment when Parishad working at heights.  Maintain work areas to minimize slipping and tripping hazards.  Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures.  Prepare escape plans from areas where there might be a chlorine emission.  Install safety showers and eye wash stations near the chlorine equipment

71 72

Field Anticipated Mitigation Measures Responsible for Monitoring of Cost and Impact Mitigation Mitigation Source of Funds

and other areas where hazardous chemicals are stored or used.  Prohibit eating, smoking, and drinking except in designated areas.

Table 11: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & Source of location Funds Construction All work sites Implementation of dust Regularly as required Supervising Part of TOR of PIU, disturbances, control, noise control, during construction; staff and PMC and PMU nuisances, public traffic management, & checklist to be filled safeguards & worker safety, safety measures. monthly once specialists Site inspection checklist to review implementation is appended at Appendix 11. Ambient air 2 locations  PM10, PM2.5 NO2, Once before start of DBO Cost for quality (one in the town, SO2, CO construction Contractor implementation of and outside the Quarterly (yearly 4- monitoring town – to be times) during measures identified during construction (2 year responsibility of implementation) period considered) contractor (18 samples x 5000 per sample = 90,000) Ambient noise 2 locations  Day time and night Once before start of DBO Cost for (one in the town, time noise levels (24 construction Contractor implementation of and outside the hours) Quarterly (yearly 4- monitoring town – to be times) during measures identified during construction (2 year responsibility of implementation) period considered) contractor

72 73

(18 samples x 1500 per sample = 27,000) Surface water 2 locations (down  pH, Oil & grease, Cl, Once before start of DBO Cost for quality stream of work F, NO3, TC, FC, construction & Contractor implementation of sites in Nihai and Hardness, Turbidity monthly during monitoring Odda nala) BOD, COD, DO, construction in river measures Total Alkalnity responsibility of contractor (18 samples x 4000 per sample = 72,000)

Table 12: Operation Stage Environmental Monitoring Plan Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & location Source of Funds

Source water Near intake pH, Cl, F, NO3, TC, FC, Hardness, Yearly DBO O&M costs quality points in Nihai Turbidity BOD, COD, DO, Total Alkalnity twice (pre & Contractor and Oda heavy metals & pesticides post monsoon)

Monitoring of Consumer end- pH, Nitrite, Nitrate, Turbidity BOD, Total Monthly DBO O&M costs quality of water random sampling Alkalnity, Total coliform and Feacal once Contractor supplied to in all zones coliform consumers

Sludge quality and WTP Analysis for concentration of heavy Yearly once DBO O&M costs suitability as metals and confirm that value are within Contractor manure the following limits (all units are in mg/kg dry, except pH)

73 74

Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & location Source of Funds

 Arsenic - 10.00,  Cadmium - 5.00  Chromium - 50.00  Copper - 300.00  Lead - 100.00  Mercury - 0.15  Nickel - 50.00  Zinc - 1000.00  PH - 5.5-8.5

74

C. EMP Compliance Responsibilities

131. PMU Responsibilities. PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project tinclude the following:

Bidding stage:

(i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water and to construct dams (RPS) and intake cum pump house b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction (ii) Ensure that EMP is included in bidding documents and civil works contracts (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labor laws and core labor standards including: a. Labour welfare measures and provision of amenities b. prohibition of child labor as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labor; e. the requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP (EHS officer) is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor‟s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

75 Initial Environmental Examination- Mauganj Water Supply Scheme

Operation stage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

132. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following:

(i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

133. Contractor’s responsibilities.

Bidding stage:

(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Construction stage:

(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work. (ii) Mobilize EHS officer and Archaeological supervisor prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit:

76 Initial Environmental Examination- Mauganj Water Supply Scheme

a. Construction waste management (CWM) plan b. Traffic management (TM) plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

134. The following Table 13 presents the outline of capacity building program to ensure EMP implementation. The detailed and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PMC.

Table 13: Outline Capacity Building Program on EMP Implementation Description Target Participants& Cost and Source of Venue Funds 1. Introduction and Sensitization to All staff and consultants Included in the Environmental Issues (1 day) involved in the project overall program cost - ADB Safeguards Policy Statement - Government of India and Madhya Pradesh At PMU, Bhopal applicable safeguard laws, regulations and (combined program for policies including but not limited to core labor all subprojects) standards, OH&S, etc. - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning

77 Initial Environmental Examination- Mauganj Water Supply Scheme

Description Target Participants& Cost and Source of Venue Funds 2. EMP implementation (1/2 day) All PIU staff, contractor Part of overall - EMP mitigation & monitoring measures staff and consultants program costs – -Roles and responsibilities involved in the Mauganj PMC will conduct at - Public relations, - Consultations subproject PIU office - Grievance redress - Monitoring and corrective action planning At PIU Part of scope of work - Reporting and disclosure of PMU, PIU, PMC & - Construction site standard operating DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers (1/2 day) Once before start of Contractors cost - Environment, health and safety in project work, and thereafter construction regular briefing every month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. Monitoring and Reporting

135. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs.

136. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works.

137. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 12). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

138. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi- annual (6-monthly) Environmental Monitoring Reports (EMR).Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites.

139. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB‟s monitoring and supervision activities will be commensurate with the project‟s risks and impacts. Monitoring and supervising of social and

78 Initial Environmental Examination- Mauganj Water Supply Scheme

environmental safeguards will be integrated into the project performance management system

F. EMP Implementation Cost

140. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 1.66 million, which are to be covered by contractor costs.

Table 14: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covered er By A. Implementation staff 1 Environmental Design & pre Per 0.5 150,00 75,000 DBO Specialist construction month 0 Contract 1 EHS Supervisor Construction per 24 50,000 1,200,000 DBO month contract Subtotal (A) 1,275,000

B. Mitigation Measures 1 Consent for Pre Lump 50,000 Project establishments & construction sum costs consent for operation from MPPCB 2 Provision for tree Construction Per tree 100 1,000 50,000 DBO cutting & contract compensatory plantation measures 3 Traffic management at Construction Lump - - 100,000 DBO work sites sum – 3 contract (Pavement Markings, towns Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 200,000 C. Monitoring Measures 1 Air quality monitoring Construction / sample 18 5,000 90,000 DBOC 2 Noise levels Construction / sample 18 1,500 27,000 DBOC monitoring 3 Surface water Construction / sample 18 4,000 72,000 DBOC monitoring Subtotal (C) 189,000 Subtotal (D) - Total (A+B+C) INR 1,664,000

79 Initial Environmental Examination- Mauganj Water Supply Scheme

X CONCLUSIONS AND RECOMMENDATIONS

141. The process described in this document has assessed the environmental impacts of all elements of the Mauganj water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

142. There are two important location and design aspects. First, the proposed water supply schemes include design of new water sources, that include construction of 2 weirs on Odda nallah and Nihai river. Secondly both the weirs are located in a small stretch of 8-9 km distance, and Nihai river is a tributary of Odda Nallah.

143. No flow data available for these river and nallah as they are not gauged by WRD. Considering the low water requirement of town with very high flows during monsoon, (as gathered from local information), it is assessed to be unlikely to have any issue of source sustainability. To cater to the low and no-flow period (~6 months),two small stop dams are proposed, one across Nihai river, and second across Oda Nala. These are small dams, with a height of just 4 m above the river bed level (same as depth of river banks), thus confining the submergence to river course itself. Storage is small and therefor the dam will be filled at the first monsoon flow itself, and the water coming from the upstream will overflow freely. Therefore the change in flow regime due to these small dams will be negligible on downstream users and on river eco system. The proposed impoundment in fact is likely to benefit the environment through groundwater recharge and propagation of aquatic life. Water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. No negative impacts thus envisaged.

144. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in rive, there is a risk of water contamination, river bed damage, etc.. Appropriate measures are suggested.

145. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period.

146. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

147. The project‟s grievance redress mechanism will provide the citizens with a platform to redress

80 Initial Environmental Examination- Mauganj Water Supply Scheme

of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

148. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

149. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

150. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community livability in Jaithari, Khand and Chandia .

151. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction and for construction of RPSs and intakes and (iii) Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs from MPPCB. These permissions/approvals shall be obtained.

152. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

81 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 1: Stakeholder Consultation

82 Initial Environmental Examination- Mauganj Water Supply Scheme

List of Participants (community consultation)

83 Initial Environmental Examination- Mauganj Water Supply Scheme

84 Initial Environmental Examination- Mauganj Water Supply Scheme

85 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 2: ADB rapid environmental assessment (REA) checklist

Country/Project: India/Madhya Pradesh Urban Services Improvement program-Mauganj- Water Supply project Sector/Division: Urban Development & Environment Department/MPUDC

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area…  Densely populated?  Mauganj is having average density of 716/Sq.km.The Project covers entire town including the densely population areas. There are no major negative impacts envisaged because pipeline will be located in unused Government lands alongside the existing roads and can be constructed without causing disturbance to houses and commercial establishments. In narrow streets disruption to road users is likely and measures like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. The location of WTP is sin less densely populated area of town so no negative impact envisaged.  Heavy with development activities?  No  Adjacent to or within any  No environmentally sensitive areas?  Cultural heritage site  No  Protected Area  No  Wetland  No  Mangrove  No  ine  No   No   No biodiversity   No B. Potential Environmental Impacts

Will the Project cause…  There are no significant water upstream wastewater discharge from pollution sources in the catchment. Communities, industries, agriculture, Raw water quality is tested and and soil erosion runoff? found that it is suitable for Domestic

86 Initial Environmental Examination- Mauganj Water Supply Scheme

use.  No monuments /areas and loss/damage to these sites?  Not applicable, subproject does not by excessive ground water pumping? involve groundwater abstraction  Project does not involve land displacement of communities? acquisition /displacement. No social conflicts envisaged  No, the water will be abstracted for water supply with other beneficial with due permission of Water water uses Resource Department. for surface and ground waters?  Raw water Quality is tested and (e.g. excessive pathogens or mineral found that it is suitable for Domestic constituents)? use. . Delivery of unsafe water to  Water will be treated and distribution system? disinfected prior to supply.  Water is abstracted from a existing works or wells, leading to pollution of Annicut on Nihayi river as there water supply? are no major polluting sources in the catchment  No Ground water pumping is leading to salinization and ground required as Surface water source is subsidence? selected for the project  Regular cleaning of storage tanks reservoir? will be conducted during operation.  As per CPHEEO manual the rate of beyond capabilities of community water supply is 70lpcd for the town facilities? where sewerage scheme is not anticipated sludge from  Appropriate provision for sludge water treatment plants? drying and disposal is included in the project  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  No transmission lines and access roads?  Measures for safe handling of inadequate design of facilities for Chlorine are included receiving, storing, and handling of chlorine and other hazardous chemicals.  Measures for safe handling of workers from the management of Chlorine are included chlorine used for disinfection and other contaminants?

87 Initial Environmental Examination- Mauganj Water Supply Scheme

 There is no resettlement of people resettlement of people for project implementation.  The contractor will be utilizing the construction workers from other local labour forces as far as areas and community possible; in case if it is workers? unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged.  Dust suppression measures such activities? as water sprinkling will be employed  Excavation & Laying pipelines interference of construction along public road will interfere with activities? the traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference.  Construction work during monsoon from construction operations? shall be carried out with due care so that silt run off due to construction operation is prevented.  No, appropriate O&M will be O&M treatment processes (especially conducted mudaccumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems?  Not envisaged system, which is corrosive due to inadequate attention to feeding of corrective chemicals?  Measures for safe handling of chlorine are included.  Water abstraction will be limited to affecting downstream water users? allocate quantity for Mauganj.  Water abstraction will be limited to allocate quantity for Mauganj. e flow due to  As per CPHEEO manual the rate of increased water supply water supply is 70lpcd for the town where sewerage scheme is not anticipated  No (wastewater from cooking and washing) and sludgefrom wastewater

88 Initial Environmental Examination- Mauganj Water Supply Scheme

treatment plant . Large population influx during project  Minimum influx of population during construction and operation that the construction and operation causes increased burden on period. socialinfrastructure and services (such as water supply and sanitation systems)? . Risks to community health and safety  No such materials are used in due to the transport, storage, and use project so no risk to community and/or disposal of materials such as health & safety explosives, fuel, and other chemicals during operation and construction? . Community safety risks due to both  Proper safety measures would be accidental and natural hazards, ensured during the construction & especially where the structural operation and decommissioning. elements or components of the projectare accessible to members of the affectedcommunity or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

89 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 3: Water Testing Report

90 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix-4: location of Weir on Google map and Strip map of proposed scheme

91 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 5: National Ambient Air Quality Standards

SL Pollutants Time Concentration in ambient air Method of NO: weighte measureme nt d Industrial, Ecologically average Residential Sensitive , Rural & Areas Other 1 Sulphur Dioxide Areas Improved West and (SO2) Annual 50 20 Geake- Ultraviolet µg/m3 24 hours 80 80 fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob 3 &Hochheiser (Na- (NO2) µg/m 24 hours 80 80 Arsenite) 3 Particulate GravimeChemilumtricin escence Matter Annual 60 60 -TOEM (Size less than 24 hours 100 100 -Beta attenuation 4 10Pa rticulate Annual 40 40 Gravimetric Matter -TOEM (Size less than 24 hours 60 60 -Beta attenuation 2.5 5 Carbon 8 hours 02 02 Non Dispersive Infra Monoxide 1 hours 04 04 Red (CO) mg/m3 (NDIR) Spectroscopy

Appendix 6: National Ambient Air Quality Standards in Respect of Noise

Area code Category of area/zone Limit in dB (A) Day Night time time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

92 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 7: Vehicle Exhaust Emission Norms

Norms CO( g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10 Bharat Stage-IV 1.5 0.96 3.5 0.02

Appendix 8: Drinking Water Standards

No. Substance or Requireme Undesirable effect Permissib Remarks characteristic nt outside the desirable le limit in Desirable the limit absence of Essential Characteristic alternate 1. Colour Hazen 5 Above 5, 25 Extended to 25 Units, Max consumer only if toxic acceptance Substance are not decreases suspect in absence of alternate sources 2. Odour Unobjectio - - a) test cold and na ble when heated b) test are several 3. Taste Agreeable - - diluTesttio tons be conducted only after safely has been established 4. Turbidity 5 Above 5, 10 - (NTU) Max consumer 5. pH value 6.5 to 8.5 acBeycepontad ncthise range the No relaxation - water will after the mucous membrane and/or water supply system 6. Total 300 Encrustation in 600 - Hardness water supply (mg/L) structure and CaCO3 adverse effects on domestic use

93 Initial Environmental Examination- Mauganj Water Supply Scheme

7. Iron (mg/L, 0.3 Beyond this limit 1.0 - Fe) Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria

8. Chlorides 250 250 Beyond effects 1000 - (mg/L, Cl) outside the desirable Max limit 9. Residual free 0.2 - - To be applicable Chlorine only when water (mg/L), Max is chlorinated. Tested at customer end. When protection against viral infection is Desirable Characteristics required, it should 10. Dissolved 500 Beyond this, 2000 - solids mg/L. palatability decreases Max and may cause gastrointestinal 11. Calcium 75 Eirrncitatirustaton. ion in water 200 - (mg/L, Ca) supply structure and Max. adverse effects on domestic use. 12. Magnesium 30 Encrustation in water 100 - (mg/L, Mg) Max supply structure and adverse effects on domestic use. 13. Copper (mg/L, 0.05 Astringent taste dis 1.5 - Cu) Max coloration and corrosion of pipes fittings and utensils will be caused 14. Manganese 0.1 Beybeyonondd tthishis. limit 0.3 - (mg/L, Mn) Max taste/appearance are affected, has advers effect on domestic use and water supply structure 15. Sulphate 200 Beyond this causes 400 May be extended (mg/L, SO4) Max. gastro intestinal upto irritation when 400 provided magnesium or magnesium (as 16. Nitrate 45 Beysodiumond arethis present 100 Mg- ) does not (mg/L, NO3) methaemoglobinemia Max. takes place. 17. Fluoride (mg/L, 1.0 Fluoride may be kept 1.5 - F) Max. as low as possible. High fluoride may cause 18. Phenolic 0.001 fBeyluorosis.ond th is, it may 0.002 - Compounds cause objectionable (mg/L C6H5OH) taste and odour 19. MerMax.cu ry (mg/L 0.001 Beyond this the water No To be tested Hg) Max becomes toxic Relaxation. when pollution is suspected

94 Initial Environmental Examination- Mauganj Water Supply Scheme

20 Cadmium 0.01 Beyond this the water No To be tested (mg/L, Cd) Max becomes toxic Relaxation. when pollution is suspected 21. Selenium 0.01 Beyond this the water No To be tested (mg/L, Se) Max becomes toxic. Relaxation. when pollution is suspected 22. Arsenic 0.05 Beyond this the water No Relaxation To be tested (mg/L, As) Max. becomes toxic when pollution is suspected 23. Cyanide 0.05 Beyond this the water No Relaxation To be tested becomes toxic when pollution is suspected 24. Lead (mg/L 0.05 Beyond this the water No Relaxation To be tested Pb) Max. becomes toxic when pollution is suspected 25. Zinc (mg/L, 5 Beyond this limit it 15 To be tested Zn) Max. can cause astringent when pollution is taste and an suspected 26. Anionic detergents 0.2 opBeyondalescence this limit in water it 1.0 To be tested (mg/L, can cause a light froth when pollution is MBAS) Max in water suspected 27. Chromium 0.05 May be carcinogenic - - (mg/L, Cr6+ above this limit 28. Polynuclear - May be carcinogenic - - Aromatic Hydrocarbons (mg/l, PAH) Max 29. Mineral oil 0.01 Beyond this limit, 0.03 To be tested (mg/L) undesirable taste and when pollution is odour after suspected chlorination takes 30. Pesticides (mg/L) Absent Toxicplace 0.001 - max Radioactive materials 31. Alpha emitters - - 0.1 - Bq/L Max 32. Beta emitters - - 1.0 - Pci/L Max 33. Alkalinity 200 Beyond this limit, 600 - (mg/L,) Max taste becomes 34. Aluminum 0.03 Cumulativeunpleasant effect is 0.2 (mg/L, Al) Max reported to cause dementia 35. Boron (mg/L) Max 1.0 - 5.0 -

95 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 9: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years‟ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees‟ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and

96 Initial Environmental Examination- Mauganj Water Supply Scheme

what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50).

The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

97 Initial Environmental Examination- Mauganj Water Supply Scheme

Appendix 10: Sample Outline Spoils (construction waste) Management Plan

The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan. The contractor, in consultation with the PMU, has to find out appropriate location/s for the Further precautions need to be taken in case of the contaminated spoils The vehicle carrying the spoil should be covered properly. The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc.

II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, e) Suggested reuse of disposal of the spoil

III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

98

Appendix 11: Quarterly Reporting Format for Assistant Safeguards Officer

1. Introduction

Overall project description and objectives Description of sub-projects Environmental category of the sub-projects Details of site personnel and/or consultants responsible for environmental monitoring Overall project and sub-project progress and status

Status of Sub-Project No. Sub- Design Pre- Construction Operational List of Progres Project Constructio Phase Works s of Name Works

2. Compliance status with National/ State/ Local statutory environmental requirements

No. Sub-Project Name Statutory Status of Action Environmental Complianc Required Requirement

3. Compliance status with environmental loan covenants

No. (List Covenant Status of Action Required schedule Compliance and paragraph number of

4. Compliance status with the environmental manageme nt and monitoring plan

Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on

99

site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

100

Summary Monitoring Table

Impacts Mitigation Parameters Monitored (As a Method of Location of Date of Name of Person (List Measures minimum those identified Monitoring Monitoring Monitoring Who from IEE) (List from in the IEE should be Conducte Conducted Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP

No. Sub-Project EMP/ CEMP Part CEMP/ EMP Status of Action Proposed Name of Being Implementation and Contract Implemente (Excellent/ Satisfactory/ Additional

101

5. Approach and methodology for environmental monitoring of the project

Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels)

Brief discussion on the basis for monitoring Indicate type and location of environmental parameters to be monitored Indicate the method of monitoring and equipment to be used Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 µg/m3 SO2 µg/m3 NO2 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 µg/m3 SO2 µg/m3 NO2 µg/m3

Water Quality Results Parameters (Government Standards) Site No. Date of Sampling Site Location pH Conductivit BOD TSS TN TP y mg/L mg/L mg/L mg/L µS/cm

Parameters (Monitoring Results) Site No. Date of Sampling Site Location pH Conductivit BOD TSS TN TP y mg/L mg/L mg/L mg/L µS/cm

Noise Quality Results LAeq (dBA) (Government Standard) Site No. Date of Testing Site Location Day Time Night Time

LA (dBA) (Monitoring Results) Site No. Date of Testing Site Location eq Day Time Night Time

7. Summary of key issues and remedial actions

Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes

Photos Summary of consultations Copies of environmental clearances and permits Sample of environmental site inspection report Other

APPENDIX 12: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT Project Name Contract Number

NAME: DATE: TITLE: DMA: LOCATION: GROUP:

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Compliance Items Compliance marked as Yes / No / Not applicable (NA) / Partially EImHSplement superviedsor (P appointedI) by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required Tarpaulins used to cover sand & other loose material when transported by After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is Road is closed; alternative route provided & public informed, information board Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures

104

Monitoring Items Compliance First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky Buildings

Signature

Sign off

Name Name Position Position

105

Appendix 13: Sample Grievance Registration Form (To be available in Hindi and English)

The _Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No

106

Means of disclosure:

107

108

109