Ministry of Road Transport & Highways

Govt. of

Rehabilitation and Upgrading to 2 lanes / 2 lanes with paved

Public Disclosure Authorized shoulders configuration and strengthening of Lalsot –

km 0 – km 85 section of NH – 11B in the State of (Package No. SP/C/4)

Project Start

Public Disclosure Authorized Km. 0/00 Project End Km. 85/00

NH 11 B

SIA and TDP Public Disclosure Authorized

Social Impact Assessment (SIA) and Tribal Development Plan

Public Disclosure Authorized January 2014

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

SOCIAL IMPACT ASSESSMENT AND RESETTLEMENT ACTION PLAN CONTENTS Chapter Description Page No. No. List of Abbreviations 1-4 0.0 Executive summary 0/1 – 0/6 1.0 Project Identification 1/1 – 1/8

1.1 Introduction 1/1 – 1/3 1.2 Objective of the Project 1/3 – 1/3 1.3 Existing Road Conditions 1/4 – 1/6 1.4 Identification of Villages & Towns 1/7 – 1/8 2.0 Objectives and Study Methodology 2/1 – 2/3 2.1 Objectives 2/1 – 2/1 2.2 Collection of Right of Way (ROW) Data 2/1 – 2/1 2.3 Properties and Assets Affected 2/1 – 2/2 2.4 Census and Socio Economic Survey 2/2 – 2/2 2.5 Consultations 2/3 – 2/3

3.0 Socio-Economic Profile of Project influence area 3/1 – 3/7 3.1 Introduction 3/1 – 3/1 3.2 Overview of Rajasthan 3/1 – 3/2 3.3 Project influence Area (PIA) 3/2 - 3/5 3.4 Socio-Economic Profile of Direct Impact Zone (DIZ) 3/5 – 3/7

4.0 Proposed Improvements 4/1 – 4/4 4.1 Introduction 4/1-4/3 4.2 Carriageway configuration 4/3-4/4 4.3 Design Cross Sections and Road Widening and Improvement 4/4-4/4

5.0 Minimizing Adverse Impacts 5/1 – 5/5 5.1 Design Considerations 5/1 – 5/2 5.2 Analysis of Alternatives Alignment 5/2 – 5/4 5.3 Road Safety and Signage 5/5 – 5/5

6.0 Socio-Economic Profiling of Project Affected Households 6/1 – 6/7 6.1 Social and Cultural Profile 6/1 – 6/3 6.2 Economic Profile 6/3 – 6/7

7.0 Social Impact Assessment 7/1 – 7/6

8.0 Public Information & Consultations 8/1 – 8/6 8.1 Stakeholder Analysis 8/1 – 8/2 8.2 Community Consultations 8/2 – 8/5 8.3 Summary of Consultations 8/6 – 8/6

9.0 Resettlement Policy Framework 9/1 – 9/15 9.1 Introduction 9/1 – 9/1 9.2 Applicable Legal and Policy Framework 9/1 – 9/2 MORTH TCPL Index 1/1

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter Description Page No. No. 9.3 Objectives and Scope of Resettlement Policy Framework 9/2 – 9/3 9.4 Definitions 9/3 – 9/7 9.5 Resettlement Principals 9/7 – 9/8 9.6 Entitlement Matrix 9/8 – 9/13 9.7 Methods for Assessment of Replacement Cost 9/13 – 9/15 9.8 Direct Purchase of Land 9/15 – 9/15

10.0 Institutional arrangement for RAP implementation 10/1 – 10/8 10.1 Central level 10/2 – 10/3 10.2 State level 10/3 – 10/3 10.3 Sub-Project level 10/3 – 10/5 10.4 RAP Implementation Support Agency 10/5 – 10/7 10.5 Replacement Cost Committee at District Level 10/7 – 10/7 Mechanism for Implementation of RAP, Training and Capacity Building - at 10/8 – 10/8 10.6 Project and Sub-project Level

11.0 Disclosure & Consultation Plan 11/1 – 11/4 11.1 Consultation Plan 11/1 – 11/3 11.2 Suggestion and Complaint Handling Mechanism (SCHM) 11/3 – 11/4

12.0 Grievance Redressal Mechanism (GRM) 12/1 – 12/3 12.1 Grievance Redressal Committee GRC) 12/1 – 12/3

13.0 Monitoring & Evaluation (M&E) 13/1 – 13/6 13.1 Institutional Arrangement for M & E 13/1 – 13/2 13.2 Monitoring & Evaluation (M&E) at Project & Sub-project Level 13/2 – 13/3 13.3 Process & Performance Monitoring 13/3 – 13/4 13.4 Evaluation 13/4 – 13/6 13.5 Reporting 13/6 – 13/6

14.0 Implementation Arrangement & Schedule 14/1 – 14/11 14.1 Schedules for Resettlement Plan Implementation 14/4 – 14/4 14.2 Implementation Process 14/4 – 14/10 14.3 RAP Completion 14/10– 14/10 14.4 Awareness Creation about HIV/AIDS 14/10 – 14/11

15.0 Livelihood & Income Restoration Plan 15/1 – 15/5 15/1 – 15/1 15.1 Measures to Reduce Impacts on Livelihood 15/1 – 15/1 15.2 Income Restoration Measures under the Project 15/2 – 15/2 15.3 Income Restoration Strategy 15/2 – 15/3 15.4 Disruption of Livelihood of PAPs 15/3 – 15/4 15.5 Skill Mapping 15/4 – 15/5 15.6 Income Restoration

MORTH TCPL Index 1/2

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter Description Page No. No. 15/5 – 15/5 15.7 Training

16.0 Gender Plan 16/1 – 16/5 16/1 – 16/1 16.1 Introduction 16/1 – 16/2 16.2 Potential Project Impacts on Women 16/2 – 16/3 16.3 Women Involvement in Development Process 16/3 – 16/3 16.4 Involvement of Women in Construction Activities 16/3 – 16/5 16.5 Provisions for Women in Construction Camp 16/5 – 16/5 16.6 Women as Members of the Consultant Teams for RAP Evaluation

17.0 Tribal Development Plan 17/1 – 17/7 17/1 – 17/1 17.1 Tribal Scenario in the Project Area 17/1 – 17/1 17.2 Methodology used to Assess Tribal Issues 17/1 – 17/2 17.3 Impact Mitigation Measures 17/2 – 17/4 17.4 R&R Assistances Other Possible Impacts (Direct and Indirect) to Tribal Populations and 17/5 – 17/7 17.5 Management/ Mitigation Measures 18/1 – 18/4 18.0 Resettlement Budget

18.1 Land Rate 18/1 – 18/2 18.2 Replacement Value of Structure 18/2 – 18/2 18.3 Compensation for Trees & Standing Crops 18/2 – 18/2 18.4 Budget 18/2 – 18/4 18.5 R&R Assistance Disbursements 18/4 – 18/4

MORTH TCPL Index 1/3

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

List of Tables Table No. Description Page No Table 1.1 District wise road length (km) 1/3-1/3 Table 1.2 Existing configuration of the project road 1/5-1/6 Table 1.3 List of Villages and Towns 1/7-1/8 Table 3.1 An Overview of Rajasthan 3/2-3/2 Table 3.2 Districts at a Glance 3/3-3/4 Table 3.3 Summary of villages & towns 3/5-3/6 Table 4.1 Proposed improvements in open sections of the road 4/1-4/1 Table 4.2 Proposed improvements in habitation and built up sections 4/1-4/1 Table 4.3 Widening proposal of the project road 4/2-4/2 Table 4.4 Summary of Improvements Proposed 4/2-4/3 Table 4.5 Typical Cross Sections Length in Km 4/3-4/4 Table 5.1 A comparison statement of options considered for Gangapur bypass 5/3-5/3 Table 6.1 Distribution of PAHs as per Religion 6/1-6/1 Table 6.2 Distribution of PAHs as per Social Category 6/1-6/1 Table 6.3 PAPs likely to be affected 6/2-6/2 Table 6.4 Household Size 6/2-6/3 Table 6.5 Education Level of Head of Households 6/3-6/3 Table 6.6 Occupation of Head of Households 6/4-6/4 Table 6.7 Monthly Household Income 6/4-6/4 Table 6.8 Monthly Household Income by Social Category 6/5-6/5 Table 6.9 Vulnerable Households 6/6-6/6 Table 6.10 Livestock owned by Households 6/6-6/6 Table 6.11 Consumer items owned by Households 6/7-6/7 Table 7.1 Structures Affected by Ownership 7/1-7/1 Table 7.2 Status and Typology of Structures Affected 7/2-7/2 Table 7.3 Structures Affected by Usage 7/2-7/2 Table 7.4 Extent of impact on structures 7/3-7/3 Table 7.5 Area affected (structures) 7/3-7/3 Table 7.6 CPRs likely to be affected 7/4-7/4 Table 7.7 CPRs likely to be affected 7/4-7/4 Table 7.8 Additional Land required District-wise 7/5-7/5 Table 7.9 Additional Land Required 7/5-7/5 Table 8.1 Stakeholder’s Analysis 8/2-8/2 Table 9.1 Applicability of Acts, Notifications and Policies 9/1-9/2 Table 9.2 Entitlement Matrix 9/9-9/13 Table 13.1 Performance Monitoring for RAP Implementation 13/3-13/4 Table 13.2 Impact Indicators 13/6-13/6 Table 14.1 Road sections free from land acquisition 14/2-14/2 Table 14.2 Implementation of Activities 14/5-14/6 Table 14.3 Resettlement Activities vis-à-vis Agencies 14/7-14/8 Table 17.1 Management/ Mitigation Measures 17/5-17/7 Table 18.1 Estimated Budget for Resettlement and Rehabilitation 18/3-18/4 MORTH TCPL Index 1/4

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

List of Figures

Figure No. Description Page No. Fig 1 Index Map (Project Road) 1/2-1/2 Fig 10.1 Institutional Arrangement for RAP Implementation 10/1-10/1 Fig 12.1 Grievance Redressal Mechanism 12/2-12/2 List of Map

Map No. Description Page No. Map 3.1 Administrative Divisions Map of Rajasthan 3/1 – 3/1 Map 5.1 Gangapur bypass alignment options marked on Google 5/4 – 5/4 map

List of Photo

Photo No. Description Page No. Photo 1.1 Existing Road Condition Photographs 1/4-1/4 Photo 1.2 Existing Road Condition Photographs 1/4-1/4 Photo 1.3 Existing Road Condition Photographs 1/4-1/4 Photo 1.4 Existing Road Condition Photographs 1/4-1/4 Photo 1.5 Existing Road Condition Photographs 1/5-1/5 Photo 8.1 Public Consultation Photographs 8/3-8/3 Photo 8.2 Public Consultation Photographs 8/3-8/3 Photo 8.3 Public Consultation Photographs 8/4-8/4 Photo 8.4 Public Consultation Photographs 8/4-8/4 Photo 8.5 Public Consultation Photographs 8/4-8/4 Photo 8.6 Public Consultation Photographs 8/4-8/4 Photo 8.7 Public Consultation Photographs 8/4-8/4

List of Annexure

Annexure- 2.1 Census and Socio-economic survey questionnaire Project road marked on census maps Dausa and Annexure- 3.1 Sawai Madhopur Annexure- 3.2 Project road marked on census maps Karauli Annexure- 3.3 List of census Villages Annexure- 3.4 Village wise data as per Census 2001 Annexure- 4.1 Typical Cross Sections of the road Annexure- 4.2 Applicability of Cross Sections of the project road Annexure- 5.1 Safety Measures Annexure- 5.2 Traffic Management Plan Annexure- 6.1 List of PAPs Annexure- 7.1 List of CPRs Annexure- 7.2 List of Villages additional land to be acquired Annexure- 8.1 Documentation of consultations at various locations Annexure- 18.1 Government approved rate for land

MORTH TCPL Index 1/5

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP

LIST OF ABBREVIATIONS

SR ABBREVIATIONS PARTICULARS NO. 1 AIDS ACCQUIRED IMMUNO-DEFICIENCY SYNDROME 2 ANNEX ANNEXTURE 3 APL ABOVE POVERTY LINE 4 BPL BELOW POVERTY LINE 5 BRGF BACKWARD REGIONS GRANT FUND 6 BSR BASIC SCHEDULE OF RATES 7 CA COMPETENET AUTHORITY 8 CBO COMMUNITY BASED ORGANISATION 9 CD COMMUNITY DEVELOPMENT 10 CE CHIEF ENGINEER 11 CH. CHAINAGE 12 CL CENTRE LINE 13 COI CORRIDOR OF IMPACT 14 CPRs COMMON PROPERTY RESOURCES 15 DDDA DISTRICT DAIRY DEVELOPMENT AUTHORITY 16 DIC DISTRICT INDUSTRIES CENTRE 17 DIZ DIRECT IMPACT ZONE 18 DLC DISTRICT LEVEL COMMITTEE 19 DLRO DISTRICT LAND REVENUE OFFICER 20 DPR DETAILED PROJECT REPORT 21 DRDA DISTRICT RURAL DEVELOPMENT AGENCY 22 DWCRA DEVELOPMENT OF WOMEN & CHILDREN IN RURAL AREAS 23 EA EXECUTIVE AGENCY 24 EAP EXTERNALLY AIDED PROJECT 25 EC ENVIRONMENTAL CLEARENCE 26 EE EXECUTIVE ENGINEER 27 EIA ENVIORNMENTAL IMPACT ASSESSMENT 28 EPs ENTITLED PERSONS 29 GOR GOVERNMENT OF RAJASTHAN 30 GOI GOVERNMENT OF INDIA 31 GRC GRIEVANCE REDRESSAL COMMITTEE 32 GRM GRIEVANCE REDRESSAL MECHANISM 33 GSDP GROSS STATE DEMOSTIC PRODUCT 34 HA HACTARE 35 HDI HUMAN DEVELOPMENT INDEX 36 HFL HIGH FLOOD LEVEL 37 HH HOUSEHOLD

MORTH TCPL Abbre.-1

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP

SR ABBREVIATIONS PARTICULARS NO. 38 HIV HUMAN IMMUNODEFICIENCY VIRUS 39 IAY INDIRA AWAS YOJANA 40 ICDS INTEGRATE CHILD DEVELOPMENT SCHEME 41 IEC INFORMATION, EDUCATION AND COMMUNICATION 42 IL INTERMEDIATE LANE 43 IMR INFANT MORTALITY RATE 44 ITI INDUSTRIAL TRAINING INSTITUTE 45 JGSY JAWAHAR GRAM SAMRIDHI YOJANA 46 JNNURM JAWAHARLAL NEHRU NATIONAL URBAN RENEWABLE MISSION 47 KMPH KILO METER PER HOUR 48 KVIC KHADI and VILLAGE INDUTRIES COMMISSION 49 LA LAND ACQUISITION 50 LHS LEFT HAND SIDE 51 LPG LIQUID PETROLEUM GAS 52 M & E MONITORING AND EVALUATION 53 MCW MOTHER AND CHILD WELFARE 54 MDR MAJOR DISTRICT ROADS 55 MLA MEMBER OF LEGISLATIVE ASSEMBLY 56 MMR MATERNAL MORTALITY RATE 57 MNREGS MAHATAMA GANDHI RURAL EMPLOYMENT GUARANTEE SCHEME 58 MoEF MINISTRY OF ENVIRONMENT AND FOREST 59 MoM MINUTES OF MEETING 60 MORT&H MINISTRY OF ROAD TRANSPORT & HIGHWAYS 61 NABARD NATIONAL BANK FOR AGRICULTURE AND RURAL DEVELOPMENT 62 NH NATIONAL HIGHWAY 63 NHDP NATIONAL HIGHWAYS DEVELOPMENT PROGRAM 64 NHIIP NATIONAL HIGHWAYS INTER-CONNECTIVITY IMPROVEMENT PROGRAM 65 NO. NUMBERS 66 NREGA NATIONAL RURAL EMPLOYMENT GUARNTEE ACT 67 NRRP NATIONAL REHABILITATION AND RESETTLEMENT POLICY 68 NTHs NON-TITLEHOLDERS 69 OBC OTHER BACKWARD CASTE 70 OP OPERATIONAL POLICY 71 PA PROJECT AUTHORITY 72 PAF PRJECT AFFECTED FAMILY 73 PAHs PROJECT AFFECTED HOUSEHOLDS

MORTH TCPL Abbre.-2

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP

SR ABBREVIATIONS PARTICULARS NO. 74 PAPs PROJECT AFFECTED PERSONS 75 PBGs PROJECT BENEFICIARY GROUPS 76 PCI PER CAPITA INCOME 77 PCU PROJECT CORDINATION UNIT 78 PDPs PROJECT DISPLACED PERSONS 79 PDS PUBLIC DISTRIBUTION SYSTEM 80 PESA PANCHAYAT EXTENSION TO SCHEDULED ACT 81 PIA PROJECT INFLUENCE AREA 82 PIU PROJECT IMPLEMENTATION UNIT 83 PWD PUBLIC WORKS DEPARTMENT 84 R&R RESETTLEMENT AND REHABILITATION 85 RAP RESETTLEMENT ACTION PLAN 86 RAP IA RESETTLEMENT ACTION PLAN IMPLEMENTATION AGENCY 87 RHS RIGHT HAND SIDE 88 RIDF RURAL INFRASTRUCTURE DEVELOPMENT FUND 89 ROW RIGHT OF WAY 90 RPF RESETTLEMENT POLICY FRAMEWORK 91 RRO RESETTLEMENT AND REHABILITATION OFFICER 92 SACO STATE AIDS CONTROL ORGANISATION 93 SC SCHEDULE CASTE 94 SCHM SUGGESTION AND COMPLAINT HANDLING MECHANISM 95 SDM SUN-DIVISONAL MAGISTRATE 96 SDO SUB DIVISIONAL OFFICER 97 SDS SOCIAL DEVELOPMENT SPECIALIST 98 SGSY SWARNAJAYANTI GRAMEEN SWAROZGAR YOJANA 99 SH STATE HIGHWAY 100 SHGs SELF HELP GROUPS 101 SIA SOCIAL IMPACT ASSESSMENT 102 SL SINGLE LANE 103 SPIU STATE PROJECT IMPLEMENTATION UNIT 104 SQMT SQUARE METER 105 ST SCHEDULE TRIBE 106 STDs SEXUALLY TRANSMITTED DISEASES 107 TAM TELEVISION AUDIENCE MEASUREMENT 108 THs TITLE HOLDERS 109 TOR TERMS OF REFERENCE 110 TRYSEM TRAINING OF RURAL YOUTHS FOR SELF EMPLOYMENT 111 TV TELEVISION 112 VLWs VILLAGE LEVEL WORKERS

MORTH TCPL Abbre.-3

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP

SR ABBREVIATIONS PARTICULARS NO. 113 VO VOLUNTRY ORGANISATION 114 WB WORLD BANK 115 WHH WOMEN HEADED HOUSEHOLD 116 WPR WORK PARTICIPATION RATE 117 WRD WATER RESOURCES DEPARTMENT

MORTH TCPL Abbre.-4

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

Chapter – 0

EXECUTIVE SUMMARY

1. The Ministry of Road Transport & Highways (MoRTH), Government of India has decided to up-grade all the existing single lane/intermediate lane National Highways, which are not covered under National Highways Development Program (NHDP) to at least 2-lane standards through National Highways Inter-connectivity Improvement Program (NHIIP). The NHIIP comprises of 33 project roads of non-NHDP National Highways across 7 states and 1 Union Territory with total length of 3769 km. Of these, 11 sub-projects have been proposed by MoRTH for implementation with World Bank Assistance.

2. National Highway 11B lies in eastern part of Rajasthan. Total length of NH11B from Lalsot to Dhoulpur is 186 km. The project road (sub-project) starts at Lalsot (km 0+000) which is the junction point with NH 11A and terminates near Karauli (km 85). The present report pertains to Lalsot to Karauli section (km 0+000 to km 85) of NH-11B. Total length of the existing road is 85 km. The length of project road including the proposed Gangapur City Bypass is 86.62 km. It lies in the administrative boundaries of three districts viz., Dausa, Sawai Madhopur, and Karauli. The Project Influence Area (PIA) has been considered as the administrative boundaries of the districts (Dausa, Sawai Madhopur and Karauli) through which the project road traverses. The Direct Impact Zone (DIZ) are the boundaries of villages and towns in which upgrading of project road is likely to affect land, structure and other properties.

3. The objective of the NHIIP is to provide better connectivity of various existing National Highways in the country and induce socio-economic development in the project area. The proposed improvements include widening to 2-lanes/2-lane with paved shoulders, strengthening, geometry corrections, realignments, bypass, junction improvements, provision of drains in habitations and semi-urban/urban area, safety measures, etc.

4. The project would affect 172 households comprising 1208 persons. Socio-economic profile of the project affected households has been worked out on the basis of Census & Socio-economic survey conducted for structures and other properties likely to be affected. Project affected households comprise Hindus, Muslims and Jains. Hindus constitute 89.5% of the total PAHs. Social category of PAHs include Other Backward Castes (48.8%) closely followed by general category households (45.9%). ST and SC together constitute less than 5% of the total project affected households.

MORTH TCPL -0/1

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

5. As per the findings of the survey 19.8% of the head of the households are illiterate. Those who have completed primary schooling and upper primary schooling comprise about 31%. Though 43.5% of the head of the households may be termed as literate by definition but majority of them have completed low level of education. The average size of the project affected households work out to be 7 persons.

6. Occupational profile indicates that 45% of the project affected households are engaged in agriculture and allied agricultural activities. Business occupation has been indicated by 16.3% of the head of households followed by daily wage labour and service. The sources of livelihood of majority of the households are limited and low income economic activities.

7. Households having monthly income of less than Rs. 2500 per month constitute less than 1.0% of the total PAHs whereas 14.5% of the PAHs have indicated monthly income in the range of Rs. 2501 to 6000. The income level of about 59% of the households is more than Rs. 6000 per month.

8. Efforts have been made to minimize the adverse impacts of the project by (i) utilising available ROW as much as possible, (ii) limiting the land width requirement at critical locations the design has been fit in 14/15 m of land width, (iii) proposing concentric widening in 93.71% of the project stretch, (iv) adopting the principle of actual land requirements in open sections of project stretch instead of having a uniform land width throughout the road stretch, and (vi) provision of bypass for Gangapur city.

9. Additional land area is required for improving sharp curves, reconstruction of major (2) and minor (5) bridges, major junction improvements (12) and one bypass. Requirements of additional land area have been worked out by superimposing the alignment on the revenue maps followed by ground verification. 15.380 ha of additional land area including 3.159 ha of government land will be required for widening and upgrading the project road. Approximately 6.82 ha of land area i.e., 44.34% of the total land area required for providing Gangapur City Bypass. One of the existing roads has been utilized for about 1.41 km length out of the total proposed length of the Gangapur City Bypass (3.620km). The land required for the project road will be acquired as per the provisions of the NH Act 1956 and government land will be transferred by standard inter-governmental procedure.

10. A total of 101 structures and 25 CPRs have been identified which are likely to be affected. 79.3% of total structures including CPRs (126) likely to be affected are title holders. One structure likely to be affected has been categorised as encroacher.

MORTH TCPL -0/2

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

Community, religious and government structures altogether constitute less than 20% of the total structures likely to be affected within the proposed right of way.

11. Extent of impacts on structures/ properties has been assessed by taking measurements with respect to widening proposals. There are 6 semi-pucca and 2 kutcha structures which would be impacted more than 50%. These structures would require relocation. Besides, there are 20 structures comprising 8 each pucca and semi-pucca structures and 4 kutcha structures which would be impacted substantially (26 to 50%). The actual position of these structures (20) would be known at the time of implementation by taking into consideration the viability of the structure

12. Structures likely to be affected have been categorized by its present use and 52.48% of them are used for residential purpose. This is followed by structures used for commercial (27.72%) and residential cum commercial (19.80%) purposes respectively.

13. Structures likely have been categorized as pucca, semi-pucca, and temporary. Semi- pucca structures constitute 50.50% of the total structures (used for residential, commercial and residential cum commercial structures) followed by pucca (26.73%) and kutcha (22.77%) structures.

14. Public information and consultations were held during the social screening and census and socio-economic survey stages which covered individual consultations, public meeting, focus group discussion, in-depth interviews, etc. It ensured participation of potential project affected persons (PAPs), local community and other stakeholders. People were informed in advance, and allowed to participate in free and fair manner. This resulted in active participation by the people in making meaningful contribution during project preparation stage.

15. During consultations brief description about the project, road development agency, involvement of the funding agency, likely adverse impacts and positive impacts, employment generation, etc were discussed and initial opinion of people were solicited. Hand drawn sketches were used to explain broadly the proposed improvement plan and likely adverse impacts. Concerns, views and suggestions expressed by the participants during these consultations have been shared with design team for minimizing the impacts wherever possible.

16. Concerns and apprehensions expressed by the community covered compensation amount for land, structure and other assets, impacts on structures, impact on religious structures, impacts on sources of earning, likely hood of being displaced, road accidents,

MORTH TCPL -0/3

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

etc. Overall, people in general and other stakeholders are in favour of the proposed project. Likely project affected persons were also found in favour of the proposed project. The community perceives that the project will help development in the area and also generate employment opportunities.

17. A Resettlement Policy Framework has been prepared by the Ministry of Road Transport & Highways, Government of India for National Highways Inter-Connectivity Improvement Project (NHIIP). This RPF includes resettlement and rehabilitation principles and approach to be followed in minimizing and mitigating adverse impacts likely to be caused by the project implementation, entitlement matrix, census and socio-economic survey, preparation of SIA and RAP, institutional arrangements at Central, State and Sub-project levels. Institutional arrangements for RAP implementation include engagement of RAP Implementation Agency (NGO/ Consultancy Firm), designated R&R Officer at sub-project level, formation of District Level Replacement Cost Committee and Grievance Redressal Committee, appointed and or designated Land Acquisition cum Social Development Officer at State Level, and engagement of PMC and M&E agencies at Central Level. The resettlement and rehabilitation assistance to project affected persons shall be provided in accordance with the entitlement matrix contained in the RPF.

18. Besides, capacity building plan have been proposed for all staffs involved in the implementation of RAP at all three levels. Training to implementation agency staff will be provided from time to time as part of capacity building plan.

19. Draft Resettlement Action Plan (RAP) and Executive Summary of the Draft RAP in local language () have been disclosed on MoRTH website as well at the World Bank Infoshop/ Public Information Centre. Feedback, if any would be incorporated into the final RAP document, following which the final RAP will be re-disclosed. Further to enhance transparency in implementation, the list of PAPs for disbursement of benefits shall be separately disclosed at the concerned Panchayat Offices/ Urban Local Bodies,, District Collector Offices, Block development Offices, District Public Relations Offices (at the state and district levels), Project office, and any other relevant offices, etc. The Resettlement Policy Framework, Executive Summary of the SIA and RAP will be placed in vernacular language in the District Collector’s Office.

20. The GRC will be constituted by the Project Authority with the aim to settle as many disputes as possible on LA and R&R through consultations and negotiation. There will be one GRC for each PIU/PST. The GRC will comprise five members headed by a retired

MORTH TCPL -0/4

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

Magistrate not below the rank of SDM. Other members of the GRC will include a retired PWD Officer (not below the rank of Executive Engineer), RRO, representative of PAPs and Sarpanch (Elected Head of Village) of the concerned village. Grievances of PAPs in writing will be brought to GRC for redressal by the RAP implementation agency. The RAP implementation agency will provide all necessary help to PAPs in presenting his/her case before the GRC. The GRC will respond to the grievance within 15 days. The GRC will normally meet once in a month but may meet more frequently, if the situation so demands. A time period of 45 days will be available for redressing the grievance of PAPs.

21. Internal monitoring will be carried out by the LA cum-Social Development Officer of Project Coordination Unit (PCU) with assistance from R&R officer and Resettlement Action Plan Implementation Agency (RAP) IA i.e. NGO/Consultancy firm whereas external monitoring and evaluation will be carried by the third party engaged for the purpose.

22. Given the area of land acquisition and extent of impacts on structures and kiosks, it is recommended that RAP IA is mobilized at site at least six months in advance before the mobilization of contractor. It is estimated that resettlement assistance to kiosks and temporary structures in government land can be disbursed by 9-10 months and hence a few more project road sections can be handed over to the contractor. The work on bypass should be taken up towards the end of second year as R&R activities for land owners can’t be completed due to nature of land acquisition process. It is estimated that a time period of 24 months will be required for the implementation of RAP.

23. Information and education campaign on HIV/AIDS and other sexually transmitted diseases (STDs) will be conducted by the RAP IA during the RAP implementation period. The campaign will target the construction workers at labour camps, truckers at parking places, general people near markets/haats and other strategic locations along the road. The RAP IA will develop network with State AIDS Control Society and other relevant agencies working for the prevention of HIV/AIDS. Hand bills, brochures, leaflets meant to create awareness about HIV/AIDS and risk/danger involved shall be printed in local language and distributed to target groups. Posters, hoardings indicating prevention from HIV/AIDs shall be displayed at suitable locations for the benefit of general people.

24. The project will provide income restoration opportunities by way of skill development training and linkage with the on-ongoing government schemes. RAP IA with support from

MORTH TCPL -0/5

SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli SIA &RAP section of NH – 11B in the State of Rajasthan

PIU will assist PAPs in making a choice for feasible income generation activities. Market feasibility study and training need assessment shall be undertaken by the RAP IA to enable the PAPs to choose the most viable and promising income restoration programs . The RAP IA will play a proactive role to mobilize various government schemes in the concerned districts for the benefit to PAPs, particularly BPL, WHH and other vulnerable groups through self-help groups (SHGs) and project beneficiary groups (PBGs) or individually.

25. During RAP implementation all project affected women would be consulted on a bi- monthly basis by the women members of the RAP IA. Compensation for land and assets lost being same for all the affected or displaced families, women headed households would be provided adequate attention and counseling by the RAP IA during RAP implementation. Women's participation should be initiated through Self-Help Group formation in each of the villages affected by the project. These groups would then be linked to special development schemes of the Government, like Swarnajayanti Gram Swarozgar Yojana (SGSY). There will be involvement of local women also in the local labour force. Foreseeing the involvement of women both directly and indirectly in the construction activities, certain provisions such as Temporary Housing, Health facilities, Day Crèche Facilities, exemption from night shift in construction Works, Education Facilities would be made available for the welfare of women and children, in particular during the road construction work.

26. The estimated resettlement budget is Rs. 10.97 crores which covers compensation for land, structure, and other assets and resettlement and rehabilitation assistances, institutional cost, awareness programme and training, etc.

MORTH TCPL -0/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 1

SOCIAL IMPACT ASSESSMENT & RESETTLEMENT ACTION PLAN

1.0 PROJECT IDENTIFICATION 1.1 Introduction The Ministry of Road Transport & Highways (MoRTH), Government of India has decided to up-grade all the existing single lane/intermediate lane National Highways, which are not covered under National Highways Development Program (NHDP) to at least 2-lane standards through National Highways Inter-connectivity Improvement Program (NHIIP). The NHIIP comprises of 33 project roads of non-NHDP National Highways across 7 states and 1 Union Territory with total length of 3769 km. Of these, 11 sub-projects have been proposed by MoRTH for implementation with World Bank Assistance. National Highway-11B (NH-11B) connects NH – 11A and NH-3 in Rajasthan. It covers a total distance of 186km. NH-11B starts at Lalsot and passes through towns such as Lalsot, Gangapur, Karauli, Bari and Dholpur and terminate at Dholpur on NH -3. The present report pertains to Lalsot to Karauli Section (Km 0 to Km 85) of NH-11B in the State of Rajasthan. The MoRTH intends to rehabilitate and up-grade the existing intermediate lane/2 lane between Lalsot to Karauli of NH–11B to 2-lane/2-lane with paved shoulders configuration. The implementation of rehabilitation and up-gradation of this corridor is likely to be taken up with World Bank assistance. The World Bank has agreed to support this sub-project in-principle provided the implementation conforms to environmental and social safeguard policies of the World Bank and the legal framework of the country. The project road starts at Lalsot (Km 0.000) in Dausa District and ends at Karauli (km 85.000) in on NH-11B in Rajasthan State. Total length of the existing road is 85.000 kms. It passes through Dausa, Sawai–Madhopur and Karauli districts of Rajasthan State. The main settlements along the project road are Lalsot, Rajoli, Shyonanda, Nagariyawas, Toda Ganga Bheruvas, Toda tehkla, Suratpura, Mandavari Khanpur ,Dabar, Nagarheda, Khedli, Piplai, Sitod, Koyala, Thali, Badhkala, Jalokhara, Hingotiya, Mahanandpura, Mirzapur, Dibsya, Khanpur Baroda, Jat Baroda, Toksi, Salempur, Kudgaon, Mahamadpur, Bijalpur, Manch, Dhungad, Gunesara, Gopalpur sai, Rampur, Barkheda and Karauli. The length of project road including one proposed bypass would be 87 km. The project road for most of its length passes through plain terrain. Project road is not passing through reserved and protected forest area. Lalsot, Piplai Salempur, Mahamadpur are congested stretch on the project road. The project location map of the project road is presented below (Fig. 1.1).

MORTH TCPL CH - 1/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Project Start Km. 0/00 Project End Km. 85/00

NH 11 B

Fig 1.1 - Map of Rajasthan State

MORTH TCPL CH - 1/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

The project requires World Bank, Government of India (GoI) and the State Government of Rajasthan (GoR) clearances and approvals before the construction work can proceed. The project road is not located in a legally defined eco-sensitive area, there is no wildlife sanctuary and national park within 10 km from the project road. However, land acquisition for bypass and realignments is more than 20 mtrs, environmental clearance is required to be sought from the MoEF.

The MoRTH has appointed the Technogem Consultants Pvt. Ltd., as project consultant to assist all aspects of project preparation and implementation in accordance with the objectives as detailed in the Terms of Reference (ToR). These tasks are linked to the engineering, environment and social aspects of the project preparation that will be undertaken throughout the period of Consultancy agreement.

1.2 Objective of the Project

The objective the project is to provide better connectivity of various existing National Highways in the country and thereby help induce socio-economic development in the project area. Improvements of these selected national highways would improve connectivity, facilitate speedy and smooth transportation of bulk goods with less interruption at a lesser transport cost and in less time, induce economic development of existing growth centres, provide impetus for the development of new growth centres, employment generation and as a consequence poverty alleviation in the project areas.

Project road length falling in respective districts is presented Table 1.1

Table 1.1 – District wise road length (km)

Road section From To (km) Length District (km) Kms % Lalsot – Sirsali 0.000 17.230 17.230 20.27 Dausa Sirsali – Salempur 17.230 55.000 37.77 44.44 Sawai Madhopur Salempur – Karauli 55.000 85.000 30.00 35.29 Karauli Total 85.000 100.0 . Source:-Road Inventory Survey

MORTH TCPL CH - 1/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

1.3 Existing Road Conditions

A view of a few locations of the project sections is shown in photographs. The carriageway width varies from 4.5 m to 7.0 m with soft shoulders of 1.5 m to 2.5 m. The carriageway width is 1½ lane (5.5 metres) in 49 km of the length and 2 lanes

(7.0 metres) in 36 km of the project road Photo 1.1 length. Existing configuration of project road is given in Table 1.2.

The existing road has more or less straight alignment except some locations where geometric corrections/improvements would be required.

The project road traverses through plain area from the starting point to the end Photo 1.2 point. Land use pattern abutting the project road is predominantly agricultural and barren. Built-up locations comprise residential and commercial structures. Overall the land use pattern along the road is agriculture. The main crops are wheat, Jowar, Bajara, Rice, Oil seeds etc. The business establishment includes Photo 1.3 petty shops, grocery shops, vegetable shops, hotels, ddhabas, tea stalls, petrol pumps, automobile work-shops etc. There are no industrial establishments along the project road. Besides, there are schools, colleges, hospitals, statues and religious structures along the project road.

Pavement condition is fair to very poor. At many places existing BT surfaces are Photo 1.4

MORTH TCPL CH - 1/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

completely denuded. Cross drainage are not adequate along the project road.

Various types of utility services such as electric lines, water supply lines, optical fiber cables, telephone cables etc. are running parallel or crossing the project road at various places. It is also observed that a number of very deep open wells as well as Photo 1.5 tube wells with hand pumps are abutting the road.

There are no boundary stones demarcating the Right of Way (RoW) in the entire length. Existing RoW details are also not available with PWD. The RoW from village map / revenue records maps have been worked out. The Right of Way (RoW) on an average varies between 15 to 25.6 metres, except a few locations where it ranges between 9 to 12 metres. Salempur (km 56.000 to 57.600) is congested place where available RoW is 9 to 12 metres.

Near settlements, road side markets and cross roads, the project road is congested because market places, Petty shops close to the project road near settlements and urban areas. There are also some locations where religious structures are either on the edge of/ or close to the carriageway. Existing configuration of project road and abutting land use are presented in Table1. 2.

Table 1.2 - Existing configuration of the project road Name of Existing the road Single / Existing Sr. section intermediate / Chainage km Abutting land use No (Project 2 lane Road) From To ROW (m) 1 NH 11B Intermediate 0/000 0/300 15 2 NH 11B Intermediate 0/300 1/300 20 to 25.6 Urban commercial 3 NH 11B Intermediate 1/300 2/400 25.6 4 NH 11B Intermediate 2/400 3/500 15 5 NH 11B Intermediate 3/500 4/000 15 Urban residential 6 NH 11B Intermediate 4/000 12/600 25.6 Agriculture 7 NH 11B Intermediate 12/600 14/400 25.6 Residential 8 NH 11B Intermediate 14/400 19/000 25.6 Agriculture 9 NH 11B Two lane 19/000 24/200 25.6 Agriculture 10 NH 11B Two lane 24/200 25/200 15 Residential

MORTH TCPL CH - 1/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Name of Existing the road Single / Existing Sr. section intermediate / Chainage km Abutting land use No (Project 2 lane Road) From To ROW (m) 11 NH 11B Two lane 25/200 31/000 25.6 Agriculture 12 NH 11B Two lane 31/000 31/500 20 Agriculture 13 NH 11B Intermediate 31/500 32/000 25.6 Residential 14 NH 11B Intermediate 32/000 33/000 20 Agriculture 15 NH 11B Intermediate 33/000 37/000 25.6 Agriculture 16 NH 11B Two lane 37/000 38/400 20 Agriculture 17 NH 11B Two lane 38/400 40/400 25.6 Residential Residential on one 18 NH 11B Two lane 40/400 42/400 25.6 side, open land on other side 19 NH 11B Two lane 42/400 43/800 25.6 Agriculture 20 NH 11B Two lane 43/800 45/600 25.6 Barren land 21 NH 11B Two lane 45/600 48/000 25.6 Agriculture Open land on one side, 22 NH 11B Two lane 48/000 49/200 25.6 residential on other side Open land on one side, 23 NH 11B Intermediate 49/200 49/800 15-20 residential, commercial on other side Proposed 24 Gangapur Intermediate 49/800 50/800 15-20 Urban commercial bypass Partly residential, partly 25 NH 11B Intermediate 50/800 53/400 25.6 open land 26 NH 11B Intermediate 53/400 54/000 20 Agriculture 27 NH 11B Intermediate 54/000 55/000 25.6 Agriculture 28 NH 11B Intermediate 55/000 56/000 20 Agriculture 29 NH 11B Intermediate 56/000 57/600 9 to 12 Residential 30 NH 11B Intermediate 57/600 59/000 20 Agriculture 31 NH 11B Intermediate 59/000 61/800 25.6 Agriculture 32 NH 11B Intermediate 61/800 62/800 25.6 Residential 33 NH 11B Intermediate 62/800 63/600 25.6 Agriculture 34 NH 11B Intermediate 63/600 64/500 12 Residential 35 NH 11B Intermediate 64/500 66/200 25.6 Agriculture 36 NH 11B Intermediate 66/200 66/800 25.6 Residential Agriculture & Open 37 NH 11B Intermediate 66/800 71/200 25.6 land 38 NH 11B Intermediate 71/200 72/600 25.6 Residential Agriculture & Open 39 NH 11B Intermediate 72/600 74/500 20 land

MORTH TCPL CH - 1/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Name of the road Single / Sr. Existing section intermediate / Existing Abutting land use No Chainage km (Project 2 lane Road) 40 NH 11B Two lane 74/500 77/000 25.6 Agriculture & open land

41 NH 11B Two lane 77/00 78/500 20 Agriculture & open land 42 NH 11B Two lane 78/500 84/500 15 to 18 Residential 43 NH 11B Intermediate 84/500 85/000 20 Residential Source:-Road Inventory Survey 1.4 Identification of Villages and Towns

As part of project preparation, Social Screening Survey was conducted of the project road. Along the project road section there are many settlements including a few towns namely, Lalsot, Karauli and Gangapur City. The survey identified census villages1 and towns through which the project road traverses. A total of 55 census villages and 2 towns have been identified through which the project road passes details of which are covered under socio-economic profiling of the area. List of villages and towns likely to be impacted by the proposed upgrading is provided in Table 1.3. These villages and towns are falling within the direct impact zone of the project road.

Table 1.3 – List of Villages and Towns Sr. No. Name Village/Towns District 1 Lalsot (M) Urban Dausa 2 Rajauli Rural 3 Shyonanda Rural 4 Nagariyavas Rural 5 Toda Ganga Chak no. 1 Rural 6 Bheruwas Rural 7 Mukundpura Rural 8 Todadhama Rural 9 Khemvas Rural 10 Shahapura Rural 11 Toda thekala Rural 12 Binori Rural

13 Suratpura Rural

14 Mandavari Rural

15 Khanpur Rural

1 A village is a statutory recognised unit having a definite boundary and separate land records as per Census of India.

MORTH TCPL CH - 1/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. No. Name Village/Towns District 16 Sirsali Rural Sawai - Madhopur 17 Sitarampura Rural 18 Dabar Rural 19 Nagarheda Rural 20 Kheadli Rural 21 Pipalai Rural 22 Sitod Rural 23 Badh Sitod Rural 24 Badh Ghanoli Chak No.1 Rural 25 Koyla Rural 26 Badh Koyla Rural 27 Badh Bidarka Rural 28 Thali Rural 29 Ahamadpur Rural 30 Badh Bichala Rural 31 Badh Khurd Rural 32 Badh Kalan Rural 33 Jalokhara Rural 34 Hingotiya Rural 35 Mahanandpura Rural 36 Mirjapur Rural 37 Brahmwad Rural 38 Udaikalan Rural 39 Saloda Rural 40 Dibsya Rural 41 Khanpur Baroda Rural 42 Jat Baroda Rural 43 Toksi Rural 44 Salempur Rural Karauli 45 Govindpura Rural 46 Kudgaon Rural 47 Mahmadpur Rural 48 Bhadkya Rural 49 Bijalpur Rural 50 Manch Rural 51 Dhugadh Rural 52 Gunesara Rural 53 Taroli Rural 54 Gopalpursay Rural 55 Rampur Rural 56 Barkheda Rural 57 Karauli (M) Urban Source:-Road Inventory Survey

MORTH TCPL CH - 1/8

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 2

OBJECTIVES AND STUDY METHODOLOGY

2.1 Objectives

The overall objective of the study is to assess the adverse impacts of the project road on property and life of people and also prepare a time bound resettlement action plan to assist the project affected persons (PAPs) in getting their entitlements (compensation - for affected land, structure and other properties and assets and R&R assistances) to enable them in improving or at least restoring their living standards and income earning capacity.

The specific objectives of the study are as under:

• Collect information using suitable tools regarding project impacts;

• Differentiate the properties and assets likely to be affected by type of ownership and construction, etc;

• Assess the extent of loss of properties (land, structure and others) of individual as well as that of community and loss of livelihood;

• Conduct meaningful consultations with likely PAPs, community and other stakeholders;

• Establish a baseline profile of population, social structure, employment, sources of income, access to social services and facilities, etc.

The various activities that have been carried out as part of the study are summarized as under:

2.2 Collection of Right of Way (ROW) Data

There are no boundary stone demarking the ROW. ROW details are not available with PWD. ROW details are worked out from village maps. On an average 15 to 25.6 metres of Right of Way is available, except a few locations where it varies between 9 to 12 metres.

2.3 Properties and Assets Affected

Structures and other properties likely to be affected within the corridor of impact (keeping in view the minimum land width requirement i.e., 15 to 20.0 m in settlement and market sections and 20 m in open sections of the existing carriageway) were identified by measuring the distance of structures from the centre line of the existing carriageway MORTH TCPL CH - 2/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

and also by following the proposed alignment plan. Any structure (residential, commercial, small business units, etc) and CPRs that fell within the proposed ROW (corridor of impact) either partially or fully were considered as likely affected structures. Approximate dimension of structures falling within the limits (COI) were measured. Simultaneously, names of owners + possessors of structures, tenants associated with the likely affected structures and properties were also noted. The information on likely affected structures and other properties were recorded in a format. Data generated from this activity have been used to assess the project impacts.

2.4 Census and Socio Economic Survey

Census and socio-economic survey was conducted for each structures and properties covering owners and tenants. The survey was carried out by using a Census and Socio- economic survey questionnaire (Annexure-2.1) provided by the Project Authority. This survey was conducted to generate baseline information on socio-economic conditions of the PAPs and also to assess the extent of impacts due to proposed upgrading of project road.

Census and socio-economic survey was conducted by engaging a team of surveyors recruited locally. The survey was conducted under the overall supervision of R&R expert. It was conducted amongst all the project affected households and business units within the corridor of impact. The survey was administered to head of the household; preferably otherwise an adult member of the household was requested to provide the response.

The socio-economic questionnaire was developed keeping in view the aims and objectives and baseline data needed for assessing the socio-economic conditions of project affected persons with specific concern to vulnerable sections of the society (SC, ST, Women Headed Household, Disabled, Elderly Persons, etc) for monitoring the status of project affected persons during and after the implementation of project. The socio-economic questionnaire covered data generation on demography, education, occupation, sources of income, land holding, ownership of dwelling and other properties, consumer durables and consumer assets owned by the households, livestock holding, availability of basic facilities (drinking water, toilet, bath room, electricity, etc) and their views on the project and option for resettlement and rehabilitation.

MORTH TCPL CH - 2/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

2.5 Consultations

Consultations with potential project affected persons and local people were conducted at Lalsot, Gangapur city and Salempur to inform people about the proposed upgrading and strengthening of the project and also to understand know their issues, concerns and perceptions. Consultations at these places were conducted in view of exploring the possibility of alternatives because of congested nature of the place. To disseminate information about the project and also to involve larger participation in consultation meetings people were informed by the members of the survey team in advance specifying date, venue and time. In addition, spot consultations in groups and individual consultations were also held at several places during the field survey work. Outcome of the consultations was shared with the design team of the consultant for integrating the social concerns wherever feasible. The main objective of consultations were to promote public understanding and find out meaningful solutions of developmental problems such as local needs and problems, loss of livelihoods, impact on religious structures, alternatives, resettlement issues, etc.

MORTH TCPL CH - 2/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 3

SOCIO-ECONOMIC PROFILE OF PROJECT INFLUENCE AREA

3.1 Introduction

The following sections provide briefly the socio-economic profile of the state (Rajasthan), Project Influence Area (PIA) and Direct Impact Zone (DIZ). The project influence area has been considered as the administrative boundaries of the districts through which the project road traverses. They are Dausa, Sawai Madhopur and Karauli. The Direct Impact Zone are the census villages and towns in which upgrading of project road is likely to affect land, structure and other properties. The list of villages and towns through which the project road traverses is marked on the census maps, Annexure 3.1, 3.2, & 3.3.

3.2 Overview of Rajasthan

Map 3.1 Rajasthan is located in the north-western part of the country, between 69°30’E to 78°13’E longitudes and 23°30’N to 30°12’N latitudes. In terms of area it is the largest state in India and covers an area of about 3,42,239 sq. km, which accounts for 11 percent of the total area and about five per cent of the population of the country. Presenting a rhomboid shape, the State has a maximum length of 869 km from west to east and 826 km from north to south. The State is bound on the west by Pakistan, in the north by and Punjab, in the east by Uttar Pradesh and , and in the south by Gujarat. The State has 33 administrative districts. More than three-fourth proportion of the total population is resides in rural areas. An overview of the State is presented below in Table 3.1: MORTH TCPL CH - 3/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 3.1 – An Overview of Rajasthan Indicators As of March 2011 Area (Sq. km) 342239 Population 68621012 Rural population (%) 75.00 Urban population (%) 25.00 SC population (%) 17.16 ST population (%) 12.56 Sex ratio (females+ 1000 males) 926 Overall literacy (%) 67.06 Female literacy (%) 52.66 Contribution to Gross State Domestic Product Agriculture (%) 26.37 Industry (%) 27.10 Services (%) 46.53 Roads density+100 sq. km 55.09 Annual rainfall (average mm) 575 Per capita income (at current prices)- Rs. 39967 p.a. or 3330 p.m. Source: Rajasthan Micro-Finance Report, 2011 The economy of the state is characterized by high incidence of poverty, low literacy rate, unemployment and low per capita income. The share of agriculture has been declining even then even then agriculture continues to play an integral part of the development process in the state as 75% of the population still live in villages and continue to depend on agriculture and allied activities as a prime source of their livelihood.

3.3 Project Influence Area (PIA)

The project influence area covers Dausa, Sawai madhopur and Karauli districts. These districts lie in the eastern part of the State bordering Guna, Sheopuri districts of Madhya Pradesh on the east. The area with its sub-tropical climate has three very well defined seasons - summers, winters and monsoons. On the basis of climatic conditions and prevailing agricultural practices, Rajasthan has been divided into ten agro-climatic zones, each one having special characteristics of its own. Dausa district forms part of the Semi-Arid Eastern Plain (IIIA) whereas Sawai Madhpour District and Karauli Districts forms part of Flood Prone Eastern Plain (IIIB). Average size of the land holding in Zone III A ranges between 2.14 to 3.06 ha whereas it ranges from 1.4 to 1.7 ha, with the exception of Sawai Madhopur where it is 2.12 ha1. Summary of project area is given in Table 3.2.

MORTH TCPL CH - 3/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 3.2 – Districts at a Glance

Census 2001 Indicators Dausa Sawai Madhopur Karauli Latitude 26o 53’ 19.00’’ 26o 01’ 05.49’’ 26o 29’ 48.53’’ Longitude 76o 20’ 09.30’’ 76o 21’ 22.26’’ 77o 01’ 39.39’’ Area (sq. km) 2950 10527 5530 Households (No.) 193498 176738 180512 Population (No.) 1317063 1117057 1209665 Male (%) 52.7 52.9 53.9 Female (%) 47.3 47.1 46.1 Urban population (%) 10.4 19.4 14.2 Rural population (%) 89.6 80.9 85.8 SC (%) 21.2 20.0 23.2 ST (%) 26.8 21.6 22.4 Population growth rate (%) 23.75 19.79 20.94 Population density (per sq. km.) 446 106 219 Sex Ratio (females+ 1000 males) 899 889 855 Child sex ratio (females+ 1000 males) 906 902 881 Literacy (7+) Overall (Combined) - % 61.8 56.7 63.4 Males - % 41.8 40.2 43.0 Females - % 20.0 16.5 20.4 Overall (Rural) - % 60.1 52.6 62.4 Males (Rural) - % 41.2 38.8 42.8 Females (Rural) - % 18.9 13.9 19.6 Overall (Urban) - % 76.0 73.3 69.2 Males (Urban) - % 47.0 45.9 44.2 Females (Urban) - % 29.0 27.4 25.1 Work Participation Rate (WPR) 41.2 42.0 39.9 WPR (Male) - % 58.5 60.2 60.5 WPR (Female) - % 41.5 39.8 39.5 Main Workers 76.9 78.2 73.6 Main workers (Male) - % 68.6 68.5 73.0 Main workers (Female) - % 31.4 31.5 27.0 Cultivation - % 67.6 66.5 66.5 Agriculture - % 2.7 4.0 4.0 Main Workers (%) Household - % 2.7 2.7 2.7 Others - % 27.0 26.8 26.8 Marginal workers 23.1 21.8 26.4 Marginal workers (Male) - % 24.7 30.4 25.7 69.6 Marginal workers (Female) - % 75.3 74.3

MORTH TCPL CH - 3/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Census 2001 Indicators Dausa Sawai Madhopur Karauli Cultivation - % 64.1 54.8 55.0 Agriculture - % 19.8 24.2 27.4 Marginal Workers- % Household - % 3.3 3.7 3.2 Others - % 12.8 17.3 14.2 Non-Workers - % 58.8 58.0 60.1 Male - % 48.6 47.7 49.5 Female - % 51.4 52.3 50.5 1 Rajasthan Agriculture Competitiveness Project, Department of Agriculture, Govt. of Rajasthan, page 28- 29. One of the significant concerns of these districts population is the adverse sex ratio. Female sex ratio in the districts is amongst the lowest whereas the child sex ratio is higher than the overall sex ratio. As regards the distribution of social groups in total population, scheduled caste in the districts have a share of 20 to 23 per cent while the share of scheduled tribe, on the other hand, is 22 to 27 per cent in 2001. Approximately 45 to 50% of the total population is SC and ST (considered vulnerable) based on the social category. Overall literacy rate in Dausa, Sawai Madhopur and Karauli districts (census 2001) was 61.8%, 56.7% and 63.4% respectively. The gap between male and female literacy rate is of the order of more than 20% across all the districts.

As per Human Development Report Update, Rajasthan 2008, Sawai Madhopur and Karauli districts are among the least developed two districts of the state. When arranged in descending order of the composite index (considering education, health, income) of Human Development Index (HDI), Sawai Madhopur rank 28th, Karauli 23rd and Dausa 12th out of total 33 districts. Sawai Madhopur, Karauli and Dausa observe a value of 0.561, 0.566 and 0.576 respectively of the Human Development Index as against the highest value of 0.809 in Ganganagar and the lowest value of 0.409 in Dungarpur.

All the districts Dausa, Sawai Madhopur and Karauli represent a typical rural economy with more than 80% of their population living in rural areas in 2001. Employment structure of an economy is defined in terms of (a) Work Participation Rate and (b) The Sectoral distribution of workforce. The Work participation rate (WPR) shows the proportion of population actively engaged in productive work+services and includes work done for monetary gains. It may be observed that more than 70% of the main workers and 80% of the marginal workers are engaged in agricultural activities indicating very high level of dependency on rural economy. These districts indicate a high level of females work participation rate ranging from 27 to 31%. Thus is because women, particularly of the lower income range take up paid employment outside the household in

MORTH TCPL CH - 3/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

the event of crop failure and or to contribute to the income of the households be it through working in NREGA, SHG activities or participating as entrepreneurs and workers in other economic activities.

Climatic conditions and topography influence agricultural practices significantly. Rainfall, temperature, humidity, wind velocity and duration of sunshine are climatic factors that affect cropping pattern in an area in a significant manner. Economy of the project area is primarily an agrarian based economy. Scarcity of water is a major drawback in agricultural production in the area. Crops that are grown are those requiring less of water, and are therefore hardy and resistant. Kharif (summer) crops are bajara, sorghum, jowar, maize and pulses, groundnut, til, guwar, vegetables and the rabi (winter) crops are mainly wheat, barley, gram, rapeseed, mustard, and taramira. Cash crops include cotton, sugarcane, tomato, vegetables, onion and chilli.

3.4 Socio-Economic Profile of Direct Impact Zone (DIZ)

As mentioned earlier, the project road passes through the boundaries of 55 census villages and 2 towns (Lalsot and Karauli). The following sections provide brief information about these villages and towns as per census 2001. Summary of relevant data of these villages and towns is presented in Table 3.3. Village & town wise data as per Census 2001 is given in Annexure 3.4.

Table 3.3 – Summary of villages & towns Indicators Villages Towns Population 73520 191333 Male (%) 52.80 52.98 Female (%) 47.20 47.02 Sex Ratio (females+ 1000 males) 894 888 Child Sex Ratio 923 893 Literacy Rate (excluding age group of 0-6) Overall (%) 59.9 69.2 Male literates (%) 69.7 63.4 Female literates (%) 30.3 36.6 SC population (%) 21.6 14.3 ST Population (%) 15.6 3.2 Workers (%) 38.1 26.6 Male workers (%) 61.8 84.7 Female workers (%) 38.2 15.3 Main workers (%) 79.2 82.8 Workers engaged in cultivation & agriculture to total workers (%) 68.0 7.8 Workers engaged in HH work to total workers (%) 2.4 6.2 Workers engaged other work to total workers (%) 29.6 86.0 Marginal workers (%) 20.8 17.2

MORTH TCPL CH - 3/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Indicators Villages Towns Workers engaged in cultivation & agriculture to total workers (%) 83.4 17.6 Workers engaged in HH work to total workers (%) 3.4 13.6 Workers engaged other work to total workers (%) 13.2 68.8 Source:-Census Survey2001 As per Census 2001, the total population of all the villages and three towns are 73520 and 191333 respectively. Composition of male and female populations in both rural and urban is almost same. Female constitutes 47% of the total population. The overall sex ratio works out to be 894 in rural areas and 888 in urban areas which indicate low sex ratio. Child sex ratio is quite high as compared to overall sex ratio in the rural areas whereas the same is marginally high in urban areas.

SC constitutes 21.6 and 14.3 % of the total population in rural and urban areas respectively. It is less than 1% of the total population of corresponding villages in 25% of the villages. In 3 villages, the entire population belongs to SC whereas in another 4 villages it is more than 55% of the total population. The ST population in these districts ranges from 22.4% to 26.8%. The project road does not pass through any notified schedule area of the State. ST population is less than 5% of the total population of the corresponding villages in 26 villages. In 17 villages, ST population however, constitutes more than 25% of the total population of the corresponding village. Of these 17 villages, in four villages almost the entire population belongs to ST. Overall ST population constitutes 15.6% of the total population in rural areas and 3.2% of the total population in the urban areas, see Annex 3.4

ST comprises 3.5% of the project affected households as per census and socio- economic survey. The survey identified 6 schedule tribe titleholder households (4 land owners & 2 structure owners) along the project road.

Literacy is one of the important indicators of measurement of development. Understanding of literacy level of likely project affected persons is important from rehabilitation point of view. People likely to be affected are mostly native of these villages and therefore socio-economic conditions of villagers are reflection of likely project affected persons. From the data provided in Table 3.3, it may be seen that overall literacy rate (excluding the population of 0-6 years) is 59.9% in rural areas and 69.2% in urban areas. Females comprise only 30.3% and 36.6% of the total literates in rural and urban areas respectively. Literacy rate in 22 (45%) of the villages is less than the average literacy rate (59.9%) of the rural areas. Overall literacy rate in urban areas is not very high as compared to rural areas. Similar trend is observed in female literacy rates in urban and rural areas, a difference of 6%.

MORTH TCPL CH - 3/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Percentage of workers engaged in different activities indicates the nature of employment available in the area. As per Census 2001, 38.1% of the total population are workers which comprise 79.2% main workers and 20.8% marginal workers in rural areas. Non workers constitute about 62% of the total population indicating high dependency ratio. In urban areas however, workers comprise 26.6% of the total population i.e. less than rural areas but main workers constitute 82.8% of the total workers, higher than rural areas. In rural areas, majority of workers (68% main workers and 83% marginal workers) are engaged in agricultural activities. In urban areas, a large majority of workers (86% main workers and 69% marginal workers) are engaged other works.

High literacy rate, engagement in non-agricultural work and high sex ratio are indicators of development status. Overall the development status of the project area is low.

MORTH TCPL CH - 3/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 4

PROPOSED IMPROVEMENTS 4.1 Introduction

The project stretch is proposed to be strengthened and upgraded under Phase 1 of NHIIP with the World Bank assistance. It includes widening, strengthening, geometry corrections, provision of realignments and bypasses, junction improvements, provision of drains in habitations and semi-urban and urban area, paved shoulders, etc.

The typical configuration for upgrading the existing road to 2-lane/ 2 lane with paved shoulders is summarized in Tables 4.1 & 4.2.

Table 4.1 – Proposed improvements in open sections of the road

Element Characteristics Design Value Cross section 1A,1B,1C & 4 Carriageway width 7 m Shoulder Paved - Earthen 2.5 m either side Slope of embankment, if applicable 1:2 Road way width 12 m Footpath - Drain width 1.5m Minimum land width required including 18m safety zone and working space Design Speed A design speed in rural areas has been adopted as 30-80 kmph, Source:-DPR

Table 4.2 - Proposed improvements in habitation and built up sections Element Characteristics Design Value Cross section 2A, 2A1 & 2B Carriageway width 7 m Shoulder Paved 1.50 m Paved area 0 to 4.30 m as per availability of space Earthen shoulder Slope of embankment, if applicable Not Applicable Road way width 10 m Element Characteristices Design Value Footpath 1.50 m Drain width 1.50 m Minimum land width required including 13.0 m safety zone and working space Design Speed A design speed in built-up areas has been adopted as 30 to 50 kmph. Source:-DPR

MORTH TCPL CH - 4/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

The improvement design has been prepared considering the design speed of 30-80 kmph in open sections and 30-50 kmph in habitations & market sections in view of limited ROW and safety aspects. Bypass have been provided at one location Gangapur . Length of Gangapur is 3.620 km. A land width of 30 m has been considered for the bypass.

Proposed widening options of the project road are given in Table 4.3. It may be observed that concentric+ both side widening has been proposed in 93.71% of the project road length in order to minimize the impacts. One bypass and 5 realignments comprise length 6.29 % (5.0 km) of the project length. A land width of 30 m has been considered for bypass. Curve improvements and approaches to Minor Bridge proposed for reconstructions are proposed more than 2% of the project road length.

Table 4.3 – Widening proposal of the project road

Widening options Length % of total length of Reason for widening (km) the project road One side widening Left Nil Nil Rigth 1.83 2.11% Curve Improvement Both side widening 81.17 93.71% To minimize land width New construction 2.21 2.55% (Bypass) ROB including approaches 1.41 1.63% under construction by RSRDC Source:-DPR

Summary of proposed features for upgrading the project road is provided in Table 4.4 Raising the height of existing road has been proposed in 42.63% (37.09 km) of the project road length. 1 No. of truck parking, 37bus shelters at Bus stops and junction improvement at 60 locations have been proposed in the improvement plan.

Table 4.4 - Summary of Improvements Proposed

Sr. Project Features Quantity Proposal under Improvement No. Plan 1. Total Project Length 85.00 86.620 Km including one bypass (existing) 2. Geometric Improvement and 2.810 km Improvements and horizontal realignment for approaches of realignment for approaches of minor bridges proposed for bridges. reconstruction. 3. Provision of Paved Shoulder 27.32 km

MORTH TCPL CH - 4/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Project Features Quantity Proposal under Improvement No. Plan 4. Proposed By-Pass 1 nos. Gangapur bypass: 3.625 km including 1.51 Km ROB with approaches under construction by RSRDC 5. Raising of Highway Formation 37.96 km Reasons for raising to maintain HFL

6. Major Bridges 2 nos. One minor bridge at km 35/800 is proposed for reconstruction for inadequate waterway and converted into Major bridge. 7. Minor Bridges 5Nos. 8. Culverts 82 nos. 9. ROB Nil 10. Fly Over Nil 11. Grade Separated Structures Nil 12. Service Roads - Not Proposed 13. Road Side Covered RCC Drains 26.45 km In built-up section. 14. Major Junctions 12Nos. At Grade Improvement proposed for all the Major Intersection. 15. Truck Parking 1 Nos. 16. Bus Stops 37 Nos. At 37 locations 17. Toll Plaza - Not Proposed 18. Footpath and Pedestrian Guard 27.31 km. Total 26.45 km length proposed in Rails in Built-up sections built-up section. Source:-DPR

4.2 Carriageway configuration Table: 4.5 Typical Cross Sections Length in Km

Cross Sr. Length in section Description No km Type 1 1A 2 lane road in rural area with raising and with full crust 19.36 2 1B 2 lane road in rural area with widening carriageway to 21.32 2 lane and strengthening existing carriageway 3 1C 2 lane road in rural area strengthening with overlays 11.37 4 2A 2 lane road in built up area with full crust, 1.5m wide 14.79 paved shoulders and paved area upto drain. 5 2A1 2 lane road in built up area with full crust, 1.5m wide 3.80 paved shoulders and paved area upto drain.

MORTH TCPL CH - 4/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Cross Sr. Length in section Description No km Type 6 2B 2 lane road in built up area with overlay on existing 8.72 carriageway 1.5m paved shoulder and paved area upto drain. 7 3 2 lane approaches to ROB with RES 1.60 8 4 2 lane road for bypass / Realignments 4.25 9 4 2 lane road for bypass / Realignments by Railway 1.41 Source:-DPR

4.3 Design Cross Sections and Road Widening and Improvement

The project road is proposed for up-gradation to 2-lane/2-lane with paved shoulders configuration. All concerned IRC guidelines will be followed for widening and up-gradation of road. Design standard for improvement of geometrics and design of pavement and structures have been adopted as set out in IRC SP 73:2007 ‘Manual of Standards and Specifications for 2-laning of State Highways on BOT basis. The typical cross sections considered are summarized below;

For typical cross sections refer Fig 4.1 to Fig. 4.8 are attached in Annexure 4.1

Fig.4.1 Typical Cross section Type TCS-1A Fig.4.2 Typical Cross section Type TCS-1B Fig.4.3 Typical Cross section Type TCS -1C Fig.4.4 Typical Cross section Type TCS-2A Fig.4.5 Typical Cross section Type TCS-2A1 Fig.4.6 Typical Cross section Type TCS-2B Fig.4.7 Typical Cross section Type TCS-3( To be constructed by Railway) Fig.4.8 Typical Cross section Type TCS-4

Applicability of cross sections to the project road is attached in Annexure 4.2

MORTH TCPL CH - 4/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 5

MINIMIZING ADVERSE IMPACTS

5.1 Design Considerations

The overall design considerations adopted by MoRTH to minimize the adverse impacts (on land, structure, livelihood, etc) in the project are as below:

• The proposed right of way for bypass will be 30 meters if the projected traffic is less than 15,000 Passenger Car equivalent Units (PCUs) in 2030 and 45 meters if the traffic is more than 15,000 PCUs in 2030.

• The corridor of impact (CoI)+proposed cross-section would be restricted within the existing right of way . The corridor of impact (CoI) for the project would broadly range between 15 m to 18 m to fit the typical cross sections, space for drains, roadside furniture and utilities. However, in specific locations, CoI of less than 15m would also be considered to minimize the impact on properties and environmental features. Whereas, in urban areas, if the available lands width is found more than the required to fit the cross section, entire available space may be paved from building line to building line to facilitate pedestrian movements, parking etc.

• Decision on bypasses and realignments will be taken based on a comparison of options with or without the proposed change in design on a case-to-case basis.

Alternatives were explored to minimize the adverse impacts of the proposed intervention as far as possible. Some of the specific measures adopted for minimizing the adverse impact are as under:

• Adverse impacts on structures in congested sections or habitations and market sections were minimized by limiting the land width requirement to 14 to 15 m.

• Concentric widening has been proposed in as far as possible 93.71% (81.17 km) of the project road length. Impacts on land in open sections of project road MORTH TCPL CH - 5/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

were minimized by adopting the principle of actual land requirements from one point to another point to fit in the requisite cross section instead of having a uniform land width throughout the road stretch.

• Bypass have been provided at one locations namely Gangapur City to avoid impacts on a substantial number of structures and acquisition of costly land. The land width for bypass has been considered 30m. Length of Gangapur City bypass is 3.620 km. This includes 1.41Km length of ROB including approaches under construction by RSRDC on Gangapur City road at the crossing of Dehli Mumbai main railway line.

5.2 Analysis of Alternatives Alignment

After having examined the feasibility of the road-improvement in the existing alignment, it is concluded that some of the project segment (mainly thickly built-up stretches) may have technical, social and environmental constrains during construction because these critical stretches are experiencing congestion, encroachment of ROW and poor geometry. Therefore, it is pertinent to develop alternative alignment to these critical stretches. These alternatives have been analyzed keeping in view social, environmental and technical parameters and thus the best alternative has been finalized

5.2.1 Alternative Alignment to Gangapur bypass

The existing alignment of project road passes through dense populated area of Gangapur city town which is sub division Headquarter of . Existing ROW 15 to 20mtr in market area is not sufficient for proposed improvement and widening. In addition, the geometry of road is very poor. If existing road is widened, number of structures will need to be removed and R&R will be an issue. To avoid large number of destruction in dense populated area of Gangapur town, a bypass has been proposed. Total length of bypass is 3.620 km alignment of bypass is proposed by using the alignment of ROB and its approaches length 1.410 km under construction by RSRDC on Gangapur-Hindaun state highway at the crossing of main railway line Mumbai-. Hence length of bypass proposed for construction in this project is 2.210 km. Two options for Gangapur bypass were considered as per Table -5.1 and option-2 is found most feasible. Please See in Map No-5.1 MORTH TCPL CH - 5/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 5.1: A comparison statement of options considered for Gangapur bypass Sr.N Description Existing Stuctures Option-2 Option - 3 o & Option-1 1 Length (km.) 2.350 3.620 2.700 2 Existing ROW (meter) 12.80 Nil Nil 3 Proposed ROW (meter) 25.6 30 30 4 Land acquisition (ha) 2.5 6.82 8.00 Res/ Res/ 5 Type of Land Res/ commercial Agriculture Agriculture 6 Tree felling (Number) 52 27 60 No. of built-up structures to 7 41 8 10 be dismantled (Number) No. of CD structures to be 8 Nil 3 5 established (Number) No. of families to be affected 9 42 8 10 (Nos.) Water bodies to be affected 10 Nil 1 nil (Nos.) 11 ROBs 2* 1** 1*** 12 Vehicular subway 0 0 1 13 Cost (Indian Rupees) 45 Crore 9 Crore 24 Crore Source:- DPR

** Using One ROB by RSRDC (Under construction). Option I is present NH11B plus 2 new proposed ROB’s * One ROB on Gangapur – Dausa (proposed) Railway line & one on Mumbai – Delhi Railway line. *** One ROB on Mumbai- Delhi Railway line

MORTH TCPL CH - 5/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

Map 5.1: Gangapur bypass alignment options marked on Google map

MORTH TCPL CH - 5/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

5.3 Road Safety and Signage

In assessment of the impacts of the project, safety of the road users and road side communities has been found to be major concern. Speedy travel on the proposed road in operation phase will make the possibility of increases the degree of loss of life in case of an accident. Road safety measures will be taken as per guidelines of IRC: SP:88- 2010, IRC: 67-2001, IRC: 35-1997, IRC: 79-1981, IRC: 41-1994, IRC: 103-1988, IRC: SP:44- 1994, IRC: SP:55-2001, IRC: SP: 31-1992 during road construction. A number of measures have been proposed to reduce the risk of traffic accidents. Please see Annexure 5.1 for safety provisions locations.

Traffic management plan is attached as Annexure 5.2

MORTH TCPL CH - 5/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 6

6. SOCIO-ECONOMIC PROFILING OF THE PROJECT AFFECTED HOUSEHOLDS

The following sections present socio-economic profile of the households likely to be affected by the proposed upgrading. The baseline information collected through household survey provides the socio-economic conditions of affected households. A wide range of data including religion, social category, loss of land and structures, present usage of structures, education, occupation, sources of income, ownership of fixed assets and consumer items, choice of resettlement etc have been collected by conducting census and socio-economic survey among likely project affected households. Households likely to lose land, land, structures and other properties were visited by the surveyors for conducting survey.

The data base provides broad understanding of social and economic conditions of project affected households and the likely impacts that people would experience due to proposed upgrading. A selected set of socio-economic information is discussed in the following sections to establish the profile of the project affected persons. The data base generated through household socio-economic survey would be used by the monitoring and evaluation consultant (to be hired under the project) for evaluating the resettlement plan objectives.

6.1 Social and Cultural Profile

The distribution of households on the basis of religious category (Table 6.1) indicates presence of three religious groups. Hindus comprise 89.5% of the total households f) of Hindus. Muslims comprise 8.7% and Jains less than 2%. List of PAHs is provided as Annex -6.1.

Table 6.1 - Distribution of PAHs as per Religion

Land Structure Total Religion Owner Owner Tenant No. % No. % No. % Nos. %age Hindu 62 87.3 92 92.0 0 0.0 154 89.5 Muslim 9 12.7 6 6.0 0 0.0 15 8.7 Jain 0 0.0 2 2.0 1 100.0 3 1.7 Total 71 100.0 100 100.0 1 100.0 172 100.0 Source: Socio-economic survey 2011-2012

Households likely to be affected as per social category have been presented in Table 6.2. Other backward castes comprise 48.81% of the total households likely to be affected. It may be noted that OBC constitutes the majority in the overall social profile of the state of Rajasthan. Other backward castes include socially and economically backward castes declared by the State. This is closely followed by the general castes. ST and SC together constitute less than 5% of the total project affected households.

MORTH TCPL CH - 6/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 6.2 - Distribution of PAHs as per Social Category Land Structure Social Total Owner Owner Tenant Category No. % No. % No. % No. % General 17 23.9 61 61.0 1 100.0 79 45.9 OBC 48 67.6 37 37.0 0 0.0 84 48.8 SC 2 2.8 0 0.0 0 0.0 2 1.2 ST 4 5.6 2 2.0 0 0.0 6 3.5 Total 71 100.0 100 100.0 1 100.0 172 100.0 Source: Socio-economic survey 2011-2012

Distribution of project affected persons (PAPs) is given in Table 6.3. The impacts are distributed all along the project road. A total of 1208 persons are likely to be affected by the proposed project road widening and upgrading. The composition of the PAPs likely to be affected is in favour of males at 55.3% as compared to 44.7% females. There are 506 females for 668 males i.e., the sex ratio of project affected persons works out to be 808 females per thousand males. The sex composition in any place has its demographic implications which are extremely vital for any meaningful demographic analysis.

Table 6.3 – PAPs likely to be affected Land Structure Total PAPs Owner Owner Tenant No. % No. % No. % No. % Male 297 52.9 370 57.28 1 100.0 668 55.3 Female 264 47.1 276 42.72 0 0.0 540 44.7 Total 561 100.0 646 100.00 1 100.0 1208 100.0 Source: Socio-economic survey 2011-2012

Distribution of households based on the size of the households is presented in Table 6.4. As such four categories have been made for analysis purpose. Some of the respondents did not provide response to queries relating to occupation, income, literacy levels, etc. About 45% of the households are of large size having more than six members. The household size comprising upto four members and 4 to 6 members constitute 18.6% and 18.0% of the total households respectively. The average size of the household works out to be 7. Table 6.4 – Household Size Household surveyed Household members No. % Upto 4 32 18.6 5 to 6 31 18.0 7 to 10 35 20.4 > 10 38 22.1 No Response 36 20.9 Total 172 100.0 Source: Socio-economic survey 2011-2012

MORTH TCPL CH - 6/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

As per the findings of the survey 19.8% of the head of the households are illiterate. Those who have completed primary schooling and upper primary schooling comprise about 31%, Table 6.5 Though 43.5% of the head of the households may be termed as literate but a large percentage of them have completed low level of education i.e., primary and upper primary. Out of the total literates, 70.7% comprise those who have completed primary and upper primary schooling. This indicates the importance of skill enhancement programmes for those who may lose livelihood due to proposed project upgrading. Head of the households having technical and post graduate qualifications constitute 7.5%. Overall, it may be summarized that literacy level of head of the household is good.

Table 6.5 – Education Level of Head of Households

Land Structure Total Education Owner Owner Tenant No. % No. % No. % No. % Illiterate 16 22.5 18 18.0 0 0.0 34 19.8 Primary School 10 14.1 7 7.0 0 0.0 17 9.9 Upper Primary School 15 21.1 20 20.0 1 100.0 36 20.9 High School 3 4.2 6 6.0 0 0.0 9 5.2 Graduate 3 4.2 7 7.0 0 0.0 10 5.8 Post Graduate 0 0.0 3 3.0 0 0.0 3 1.7 Not Known 24 33.8 39 39.0 0 0.0 63 36.6 Total 71 100.0 100 100.0 1 100.0 172 100.0 Source: Socio-economic survey 2011-2012

6.2 Economic Profile

Occupational profile of the head of the household is presented in Table 6.6. It may be observed that cultivation and agricultural labour are the occupation of 45% of the head of households followed by business activities (low scale enterprise) and daily wage labour. Wage labours are those who normally work on someone else’s land as agriculture labour. Salaried and others together comprise 5.3% of the total households. 28 households earn their livelihood by providing services to road users and people from surrounding areas. The sources of income are limited. Overall the economy of the area is largely dependent on agriculture, allied agricultural activities, trade and business, etc are all low income activities.

MORTH TCPL CH - 6/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 6.6 – Occupation of Head of Households Land Structure Total Occupation Owner Owner Tenant No. % No. % No. % No. % Cultivator 33 46.5 42 42.0 0 0.0 75 43.6 Business 6 8.5 22 22.0 0 0.0 28 16.3 Daily Wage Earner 7 9.9 3 3.0 0 0.0 10 5.8 Salaried 1 1.4 6 6.0 1 100.0 8 4.7 Agricultural Labourer 0 0.0 2 2.0 0 0.0 2 1.2 Others 0 0.0 1 1.0 0 0.0 1 0.6 Not Known 24 33.8 24 24.0 0 0.0 48 27.9 Total 71 100.0 100 100.0 1 100.0 172 100.0 Source: Socio-economic survey 2011-2012

Respondents were asked to provide indicative household’s monthly income against each earning members. For the purpose of analysis the income groups to which the households belong to are discussed below. The households have been grouped into following categories. They are - households having an income of less than and equal to Rs. 2500/- per month, Rs. 2501 to 6000 per month, Rs. 6000 to 10000/- per month and more than Rs. 10000/- per month. Data collected have been complied as above are presented in Table 6.7 along with analysis.

Overall households having monthly income of less than equal to Rs. 2500/- per month comprise less than 1% of the total households surveyed. There are no households likely to lose land in this income category. There is only one household likely to lose structure in this income category. 30.2% of the total households likely to be affected belong to the income category of more than Rs. 10000/- per month. This is followed by those households whose income varies between Rs. 6001/- to Rs. 10000/- per month. 28.5%of the households in this income range are likely to be affected by impacts on land and structures

Table 6.7 – Monthly Household Income Land Structure Total Occupation Owner Owner Tenant No. % No. % No. % No. % ≤2500 0 0.0 1 1.0 0 0.0 1 0.6 2501 to 6000 9 12.7 16 16.0 0 0.0 25 14.5 6001 to 10000 27 38.0 22 22.0 0 0.0 49 28.5 > 10000 11 15.5 40 40.0 1 100.0 52 30.2 No Response 24 33.8 21 21.0 0 0.0 45 26.2 Total 71 100.0 100 100.0 1 100.0 172 100.0 Source: Socio-economic survey 2011-2012

Households having monthly income in the range of Rs. 2501/- to Rs. 6000/- comprise about 8.5% of the total households surveyed. Out of the 25 households those who indicated their monthly income in the range of Rs. 2501/- to Rs. 6000/- comprise 76% OBC and 24% general category, Table 6.8. However, general category households are more in respective income category i.e., Rs. 6001 to Rs. 10000/- and above Rs. 10000/- respectively.

MORTH TCPL CH - 6/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 6.8 – Monthly Household Income by Social Category

Income Range (Rs.) Social 2501 to 6001 to No <2500 > 10000 Total category 6000 10000 Response No. % No. % No. % No. % No. % No. % General 0 0.0 6 24.0 16 32.7 37 71.2 21 46.7 80 46.5 OBC 1 100.0 19 76.0 32 65.3 14 26.9 17 37.8 83 48.3 SC 0 0.0 0 0.0 1 2.0 0 0.0 1 2.2 2 1.2 ST 0 0.0 0 0.0 0 0.0 1 1.9 5 11.1 6 3.5 No 0 0.0 0 0.0 0 0.0 0 0.0 1 2.2 1 0.6 Response Total 1 100.0 25 100.0 49 100.0 52 100.0 45 100.0 172 100.0 % 0.6 14.5 28.5 30.2 26.2 100 Source: Socio-economic survey 2011-2012

Households likely to be affected have been identified as vulnerable based on certain criterion which has been presented in Table 6.9. A total of 105 households have been identified as vulnerable. Head of the household who is 60 years & above in age have been considered as vulnerable and they comprise 27.32% of the total vulnerable households. Households covered under Below Poverty Line (BPL)1, Antyoday and Annapurna2 and other poverty alleviation schemes comprise 16.86% of the total vulnerable households identified. SC and ST are considered vulnerable based on social categorisation. These households constitute 4.65% of the total vulnerable households. There are two women headed households (1.16%), one likely to lose land and another one likely to lose structure. Overall, vulnerable households comprise 61.05% of the total households likely to be affected (172). As only 6 tribal households are affected which are scattered along the project corridor a Tribal Development Plan has been provided as Chapter 17.

1 According to the Press Note on Poverty Estimates 2009-10, by Planning Commission, Government of India, March 2012, based on Tendulkar methodology the BPL population is 26.4% percent of rural households and 19.9 percent of urban households are below poverty line in Rajasthan. This implies an overall poverty ratio of 24.8 percent. These poverty ratios are much higher than in India as a whole, the ratios stand at 33..8 percent (rural), 20.9 percent (urban) and 29.8 percent (overall)..

2 The consumers are divided into Above Poverty Line (APL) and Below Poverty Line (BPL) categories based on the correction to the state government’s original survey carried out in 2006. The PDS runs three schemes: (1) BPL – to provide BPL families with 35 kgs of food grains per month (25 kgs of rice and 10 kgs of wheat), (2) Antyoday, to provide extremely poor BPL families with 35 kgs of food grains per month — 21 kgs of rice at the rate of Rs 2 per kg and 14 kgs of wheat at the rate of Rs. 3 per kg., and (3) Annapurna to provide homeless senior citizens with 6 kgs of wheat and 4 kgs of rice free of cost.

MORTH TCPL CH - 6/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 6.9 – Vulnerable Households

Land Structure Total Vulnerable HH Owner Owner Tenant No. % No. % No. % No. % 60 & Above 27 38.03 20 20.00 0 0.0 47 27.32 Below 60 13 18.31 53 53.00 1 100 67 38.95 BPL 14 19.72 15 15.00 0 0.0 29 16.86 PH 10 14.08 9 9.00 0 0.0 19 11.05 SC 2 2.82 0 0.00 0 0.0 2 1.16 ST 4 5.63 2 2.00 0 0.0 6 3.49 WHH 1 1.41 1 1.00 0 0.0 2 1.16 Total 71 100 100 100.0 1 100 172 100.0 Source: Socio-economic survey 2011-2012

Number of livestock owned by the people used to be an indicator of wealth in the rural areas till a few decades ago. Size of livestock in a way also indicated the land holding size of the household. The situation however has changed over the years substantially because of repeated division of land, increased use of mechanized agriculture implements and non- availability of labours for agriculture purpose because of migration of labour to other states. Nevertheless, livestock continues to be a source of livelihood to many households as milk and milk products are always in demand in both rural and urban areas. Sheep, Goats and poultry are mainly reared by poor families for livelihood purposes whereas cows and buffaloes are owned by mainly land owners. Number of livestock owned by the project affected households is presented in Table 6.10. It may be seen that the average number of cows, buffaloes, sheep, goats and poultry per household works out to be 0.18, 1.14,0.04, 0.25 and 0.01 respectively.

Table 6.10 – Livestock owned by Households

No. of livestock owned by Livestock Structure Average/HH Land owner Total Owner Tenant Cows 8 23 0 31 0.18 Buffaloes 137 110 0 247 1.44 Sheep 0 6 0 6 0.04 Goats 30 12 0 42 0.25 Poultry 0 2 0 2 0.01 Others 0 0 0 0 0.00 Total 175 153 0 328 Source: Socio-economic survey 2011-2012

Possession of number and type of consumer items indicate economic condition of households. Possession of TV, mobile phone, landline phone, electric fan, radio, tape recorder are now common, while possession of two/three/four wheelers, availability of LPG connection, fridge, etc indicate better economic conditions. Average number of consumer items per household is presented in Table 6.11. It may be observed that there are 1.15 mobile phones per households. In other words, there are many households which have more than one mobile phone. One of the main reasons for high density of mobiles is low cost of communication and means to remain in touch with family members. TV now a days is one of the major sources of entertainment and are considered basic necessity Approximately half of all Indian households own a television as per Television Audience Measurement (TAM) Annual Universe Update - 2010, In case of MORTH TCPL CH - 6/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

households surveyed, availability of TV per household works out to be very less (0.16) i.e., 16 households per 100 households, much less than the national average. Commuting is primarily by cycle followed by scooter/motorcycle. Possession of these items indicates that a large majority of households are poor. Data collected on various consumer items from households shall be used to compare the economic changes among affected households after the implementation of the project by the monitoring and evaluation agency to be engaged by the project.

Table 6.11 – Consumer items owned by Households

Ownership of No. of items owned by consumer Structure Average/ Land Owner Total items Owner Tenant HH Mobile 5 32 1 38 0.22 Television 18 49 1 68 0.40 Tape Recorder 2 1 0 3 0.02 Radio 2 13 0 15 0.09 Refrigerator 9 28 1 38 0.22 Bicycles 10 26 1 37 0.22 Three Wheeler 1 0 0 1 0.01 Four Wheeler 4 12 0 16 0.09 Cooking Gas 19 38 0 57 0.33 Bus/Truck 0 2 0 2 0.01 Two Wheeler 22 41 1 64 0.37 Others 0 1 0 1 0.01 Total 92 243 5 340 Source: Socio-economic survey 2011-2012

MORTH TCPL CH - 6/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 7

7. SOCIAL IMPACT ASSESSMENT

Development projects generate not only positive impact/benefits but also cause adverse social impacts in terms of loss of land assets, non-land assets, loss of livelihood etc especially on vulnerable sections of the society who are susceptible to socio-economic risks. Identification of such anticipated adverse impacts and developing appropriate mitigation measures during project planning, design and implementation is essential for achieving social sustainability of any project.

Census and socio-economic survey started on 8 October 2011. The cut-off date therefore is the start date of the survey i.e., 8 October 2011. Structures and other properties likely to be affected within the corridor of impact (varying from point to point i.e., keeping in view the maximum land width requirement for widening as per the design) were identified and then distance of structures from the centre line of the existing road was noted. Further, measurements of structure and other physical details were noted down in the format. Any structure (residential, commercial, residential cum commercial and other properties that fell within the corridor of impact i.e., proposed RoW), either partially or fully was taken as likely affected structures. Name of owner of the structure/ property and associated persons with the likely affected structures were noted down. Thereafter, census and socio-economic survey format was administered to the head of the household or adult member of the household for collect the requisite data. Data collected from survey were entered into excel sheet for production of outputs. The extent of impacts due to the proposed intervention (upgrading and improvements) is discussed in the following sections.

A total of 126 structures including common property resources and government structures have been identified which are likely to be affected by the proposed works. Of the total structures likely to be affected (126), 79.37% is privately owned structures. There is only one encroacher (structure existing within the private land but have extended into right of way) likely to be affected. No squatters have been identified in the project road. Community, religious and government structures together constitute about 20% of the total structures likely to be affected within the proposed right of way. Distribution of structures likely to be affected is presented Table 7.1.

Table 7.1 – Structures Affected by Ownership

Structures affected Type of structures by ownership No. % Owner (TH) 100 79.37 Encroacher 1 0.79 Squatter 0 0.00 Community 5 3.97 Religious 6 4.76 Trust (Boundary wall - health facility) 2 1.59 Government 12 9.52 Total 126 100.0 Source: Census & Socio-economic survey 2011-12

MORTH TCPL CH - 7/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Structures likely to be affected have been categorized as pucca, semi-pucca and kutcha. Distribution of structures by ownership status vis-à-vis type of construction is presented in Table 7.2. Semi-pucca structures constitute 51.49% of the total structures likely to be affected (100) excluding community, religious and government structures. Pucca and kutcha structures likely to be affected comprise 26.73% and 22.77% respectively.

Table 7.2 – Status and Typology of Structures Affected

Structures by type of construction Total Status of structure Semi- by ownership Pucca Kutcha No. % pucca Titleholder 27 50 23 100 99.01 Encroacher 0 1 0 1 0.99 Squatter 0 0 0 0 0.00 Total 27 51 23 101 100 % 26.73 51.49 22.77 Source: Census & Socio-economic survey 2011-12

Structures likely to be affected have also been categorized by its present use and are presented in Table 7.3. It may be observed that a little more than 50% of the structures likely to be affected (101) are used for residential purpose. This is followed by structures used for commercial purpose. Majority of commercial structures are small business units and residential cum commercial units (mixed). Based on the information generated with regard to construction materials used for the construction of structures, it may be inferred that a majority of structures likely to be affected indicate poor economic conditions.

Table 7.3 – Structures Affected by Usage

Use of structures Typology of Mixed Total structure Residential Commercial Others (R&C)* No. % Pucca 9 9 9 0 27 26.73 Semi-pucca 27 15 9 0 51 50.50 Kutcha 17 4 2 0 23 22.77 Total 53 28 20 0 101 100 % 52.48 27.72 19.80 Source: Census & Socio-economic survey 2011-12 *R&C – Residential cum commercial

Extent of impacts on structures has been assessed by taking measurements of the structures with respect to widening proposals, Table7.4. It has been categorised into four groups viz., less than equal to 10, 11 to 25%, 26 to 50% and more than 50%. All the structures falling in the last two categories i.e., > 26 to 50% and >50% would require relocation. There are 6 semi-pucca and 2 kutcha structures which would be impacted the most. Besides, there are 20 structures comprising 8 each pucca and semi-pucca structures and 4 kutcha structures which would be impacted substantially. The actual position of these 20 structures would be known at the time of implementation by taking into consideration the viability of the structure. MORTH TCPL CH - 7/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 7.4 – Extent of impact on structures

Extent of impacts (%) Total Typology of ≤10 11 to 25 26 to 50 > 50 structures No. % No. % No. % No. % No. % Pucca 6 21.43 13 28.89 8 40.00 0 0.00 27 26.73 Semi-pucca 11 39.29 26 57.78 8 40.00 6 75.00 51 50.50 Kutcha 11 39.29 6 13.33 4 20.00 2 25.00 23 22.77 Total 28 100 45 100 20 100 8 100 100 100 % 27.72 44.55 19.80 7.92 Source: Census & Socio-economic survey 2011-12

Approximate area likely to be affected by types of structures is given in Table 7.5. Majority of the affected area (60%) is from semi-pucca category followed by kutcha and pucca structures categories. Table 7.5 – Area affected (structures)

Area affected (sqm) Type of structures Area % Pucca 502.59 18.64 Semi-Pucca 1605.69 59.55 Kutcha 588.03 21.81 Total 2696.31 100.0 Source: Census & Socio-economic survey 2011-12

The settlement/habitation along the road is also linked with the establishment of common properties. Efforts have been made to minimise impact on religious and community structures/places as far as possible. Nonetheless, a total of 25 common property resources (government structures, community, religious and trust) would be affected by the project. Distribution of CPRs affected as per ownership is given in Table 7.6 & 7.7. There are about 25% of the religious structures out of the total CPRs (25) likely to be affected. Religious structures include temples; Kabarsthan land, church compound wall, and Pir baba There are two structures which belong to trusts. Government structures meant for community comprise almost 50% of the total common property resources likely to be affected. Government structures likely to be affected include Gram Panchyat and patwari office, Primary health Kendra, schools, etc. Community structures include well, hand pump, Dharamshala etc.

MORTH TCPL CH - 7/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 7.6 - CPRs likely to be affected

Ownership CPRs Private land Encroacher Squatter Total % Community 5 0 0 05 20.00 Govt. 12 0 0 12 48.00 Religious 6 0 0 06 24.00 Trust 2 0 0 02 8.00 Total 25 0 0 25 100.00 % 100 0 0 Source: Census & Socio-economic survey 2011-12

Extent of impacts on CPRS has also been assessed. It may be seen that 40% of the CPRs would require relocation as major part of the structures would require dismantling and all of them are pucca structures. People have agreed to co-operate and provide assistance for relocation of CPRs, wherever required. List of CPRs likely to be affected is given in Annexure 7.1.

Table 7.7 – CPRs likely to be affected

Typology of Extent of impact (in % ) structure Upto 25 26-50 > 50 Total % Permanent 3 9 9 21 84.00 Semi permanent 2 0 0 2 8.00 Kutcha 2 0 0 2 8.00 Total 7 9 9 25 100.00 % 28 36 36 100 Source: Census & Socio-economic survey 2011-12

7.1 Impacts on Land

All possible efforts have been made to design the project road by utilizing the maximum available RoW. Even then additional land acquisition could not be avoided. Additional land area would be required at several locations where existing RoW is limited and also where alignment shifts from one side to another side. Additional land area required for the project road widening and strengthening, improvement of junctions, bypass, etc has been worked out by superimposing the alignment on the revenue maps. 15.380 ha of additional land area from 46 revenue villages (see Annexure 7.2) would be required for upgrading the project road. Additional land required for the project, present use and ownership are presented in Table 7.8 & 7.9 respectively. Private land comprises 79.46% of the total additional land requirements and is presently used for agricultural purposes.

MORTH TCPL CH - 7/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 7.8 – Additional Land required District-wise

Category of land required in ha District Residential Agriculture Commercial Government Total Dausa 0 0 0 0 0 Swai 0 9.064 0 2.233 11.297 Madhopur Karauli 0 3.171 0 0.912 4.083 Total 0 12.235 0 3.145 15.380 Source: Census & Socio-economic survey 2011-12

Table 7.9 – Additional Land Required

Area Present use & ownership Ha % Residential 0 0 Private Commercial 0 0 Agriculture 12.235 79.55 Government 3.145 20.44 Total 15.380 100.00 Source: Census & Socio-economic survey 2011-12

Additional land width is needed throughout the project road stretch project road sections viz., km. 27+400 to 27+800, 35+540 to 36+130, 46+400 to 47+000, 49+200 to 49+400 , 50+700 to 52+975, 63+500 to 64/000 ,72+900 to 73+300 ,74+000 to 74+275 , 74+275 to 74+555 ,77+955 to 78+250, and 78+250 to 78+505

Land required for different purposes and their corresponding length has been indicated in table 7.10. Land is needed for widening of project road, approaches to bridges, rising of project road in submergence section, bypass, realignment, etc. Maximum land acquisition (44.34%) is for Gangapur City bypass. Acquisition of 30 meter of land width has been proposed for the bypass. Other purposes for which most land is needed are realignment and widening of existing road.

Table 7.10 – Land Required for the Project Road Existing Chainage (km) Area Sr. Name of proposed to Tehsil District No. Village be acquired From To in (Ha)

Sawai- 1 27+400 27+800 Sitod Bamanvas 0.47 Madhopur

35+540 36+130 Sawai- 2 Thali Gangapur 2.50 36+600 37+000 Madhopur

Sawai- 3 46+400 47+000 Udaikala Gangapur 1.18 Madhopur

MORTH TCPL CH - 7/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

49+400 Sawai- 4 49+200 New Saloda Gangapur 0.36 New Madhopur

Existing Chainage (km) Area Sr. Name of proposed to Tehsil District No. Village be acquired From To in (Ha)

50+750 Sawai- 5 50+700 new Dipsya Gangapur 0.08 new Madhopur 52+950 51+550 Ex. Ex. Khanpur Sawai- 6 Gangapur 6.74 50+750 New 52+975 Badauda Madhopur New

7 63+500 64+000 Mohammadpur Sapotara Karauli 0.30

72+900 73+300 8 Gopalpur Karauli Karauli 2.49 74+000 74+275 9 74+275 74+555 Rampur Karauli Karauli 0.44 10 77+955 78+250 Barkheda Karauli Karauli 0.65 11 78+250 78+505 Karauli Karauli Karauli 0.18 Total 15.38 Source:-R & R Survey 2011

MORTH TCPL CH - 7/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter - 8

PUBLIC INFORMATION AND CONSULTATIONS Public information and consultation is an important method of involving various stakeholders particularly, local community with reference to the proposed development initiatives. It provides a platform to participants to express their views, concerns and apprehensions that might affect them positively or negatively. Through participation and consultation stakeholders influence development initiatives, and decision making process. The effectiveness of participation and consultation is directly related to the degree of involvement by the likely project affected persons and the local community and integration of outcome of consultations wherever feasible in the proposed development initiatives. Detailed planning is required to ensure that likely project affected persons, local community, interested groups, non-governmental organizations, civil society organizations; local government, line departments, etc are consulted regularly, frequently and purposefully during different stages of the project including project preparation.

The purpose of consultations was to inform people about the project, take note of their issues, concerns and preferences, and allow them to make meaningful choices. Consultations were held during the project preparation which covered group consultations, public meetings, and individual meetings, etc. It ensured participation of potential project affected persons (PAPs), local community and other stakeholders. People in general were informed in advance, and allowed to participate in free and fair manner. Consultations provided meaningful contributions with regard to reducing adverse impacts, provision of bypass, safety, etc. Concerns, views and suggestions expressed by the participants during these consultations were integrated into the design aspects wherever feasible. The following sections provide description of the consultations.

8.1 Stakeholder Analysis Analyses revealed that stakeholders are supportive and showed positive interest in the project and promised to ensure good support during execution of the project. The stakeholder analysis for the project is presented in Table 8.1

MORTH TCPL CH - 8/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 8.1 - Stakeholder’s Analysis

Stakeholder’s Interests, support Influence Relevant Stakeholder Location Category & Opposition (H+M+L)# Government Engineer(MoRTH), New Delhi, Supportive H PWD Engineers, GoR Stakeholder’s Interests, support Influence Relevant Stakeholder Location Category & Opposition (H+M+L)# Other concerned DLRO (Revenue, Dausa, Sawai Supportive M Department GoR, EE electrical Madhopur & Karauli Intended Villagers Project affected Supportive H Beneficiaries villages Adversely Affected PAPs commercial, Project affected Supportive H Persons residential villages Organized Interest Bussines groups, trade Project affected Not known L Groups unions towns Civil society RAP IA, representatives Project affected Supportive L of VO and CBOs villages Other stakeholder Not known Not known Not known Not known

# H-High, M-Midium & L-Low Consultations with district officials confirmed that the project area+ districts do not fall under Schedule V of the Constitution of India and hence PESA is not applicable.

8.2 Community Consultations

One of the prime objectives of the public information and consultations has been to involve local people in project planning. While undertaking the social screening survey and some technical surveys such as inventory of road side utilities and structures, census and socio-economic survey of PAPs, information dissemination focused on the proposed road improvements. PAPs were informed about the proposed road improvement program, likely impacts on individual and common properties resources and resultants likely benefits. Later group of people were requested to gather at a common place for exchange of information. During these consultations brief description about the project, road development agency, involvement of the funding agency, likely adverse impacts and positive impacts, employment generation, etc were discussed and initial opinion of people were solicited. Consultations were held at 4 locations – Mandawari, Khanpur, Piplai, Salempur on a pre-decided date, time and venue in consultation with local people and government officials. These consultations provided suitable platform to people to express their concerns and also provide suggestions with regard to proposed improvements. Descriptions of consultations held at different locations are provided in the following section:

MORTH TCPL CH - 8/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Venue : Description Photographs Venue- Mandawari

Tehsildar, Krishi Mandi Member, Patwari, Gram Panchayat Secretary, Byapar mandal Participants addhaksh, Project Preparation Team: Social expert of the consultant, Villagers, and field workers. • RoW details as per revenue map and plan the widening accordingly. • Provision of underpass Photo 8.1 Issues • Drainage system Discussed • Location of Bus Stop • Large no. of business loss will accrue. • Compensation of structure and other properties. • Follow centre line as in revenue map and then take minimum required land for road widening. • Make necessary change in alignment to save these common properties. • Provide underpass at the way to Diwachali & Khurra. Suggestions • Street lights at divider • Before start the construction Photo 8.2 activities please ensure to rehabilitate first and relocate common properties. • Suitable assistance should be provided. • No need of bypass otherwise we will loss our commercial activities. • Follow the existing centre line marked in village revenue maps. • To provide drainage system Important Findings

MORTH TCPL CH - 8/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Venue : Description Photographs Venue- Khanpur Baroda Nayab Tehsildar, Patwari, Gramsevak, Project Preparation Participants Team: Social expert of the consultant, Villagers, Sarpanch etc. Photo 8.3 • Provision of bypass Issues • Compensation of structure and Discussed other properties. • Provide bypass. • Before starting the construction activities ensure giving sufficient Suggestions time for resettling the houses. • Suitable assistance should be provided. Photo 8.4

• People are interested in project. Photo 8.5 Important Finding

Venue: Piplai NTDR-Bananwas, Land Record Inspector, Patwari, villagers, Social Participants Expert, Project preparation team and field enumerators. • Provision of Bypass • Two curves are here. Issues • Villagers safety Discussed Photo 8.6

• Provide bypass from Dawar to Gas Agency Bamanwas. • Make necessary provisions for Suggestions safety • Provide drainage along both sides of the road. Photo 8.7

MORTH TCPL CH - 8/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• Villagers are very happy with Important road widening proposal. Finding

Issues raised, demands & suggestions Mandawari • Street light at divider inside Mandawari (District Dausa) • Drainage on both side of project road Kailash Chardra Meena • Underpass at way to Khurra from project road Vijendra Kumar Meena • Bus stop at ½ km away from dense populated area Braj Mohan Meena • Speed breaker at both sides of crossing Shyam Lal Sharma • High mask light at Mandawari Chauraha Lalit Mohan Bhagwan Sahai Sharma

Khanpur Baroda (District • Requirement of bypass Khanpur Baroda) • Drains on both sides of the project road Vijendra Kumar Meena • Adequate compensation to PAPs+ Displaced people Mitto Singh • Pucca drain on both side of the NH-11B Laxmi Narayan Singh • Need of Fly over bridge to evade after the construction Jagdish of NH-11B the traffic jam Bharat Lal etc. Piplai (District- Sawai • Construction of bypass Madhopur) • Compensation as per the quality of land and crops Harimohan Meena consideration Mithleshkumar Sharma • Adequate and timely compensation to the acquired land Punam Chandra and compensation as per the current market rate Girij Prasad Patel • Provision of Construction of Yatri shed and public toilet. Vinod Kumar Joshi Shankar Vohra Pokhraj Gurjar Ram Prasad Mali etc.

Village-Salempur • Construction of bypass at Salempur (District- Karauli) • Road widening lead to development and provision of Surgyani Lal Meena side drain. Jyotish Gupta • Timely and adequate compensation should be given to Rajendra Kr. Sharma the affected people. Hasan Khan • Construction of residence for landless laborers Usama Khan • Construction of drain Niranjan Sharma

MORTH TCPL CH - 8/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Mitigation measures provided in response to concerns and suggestions made are provided in the table below:

Venue & Participants Issues Suggestions given Responses given/ dates Discussed Mitigation measures incorporated Mandawari Tehsildar, Krishi • RoW details • Follow centre line • Approach to road 12.10.2012 Mandi Member, as per as in revenue design has been Patwari, Gram revenue map map and then taken to minimize Panchayat and plan the take minimum land take and Secretary, Byapar widening required land for impacts on mandal addhaksh, accordingly. road widening. structures. Project Preparation • Provision of Concentric widening Team: Social expert underpass is planned in nearly of the consultant, • Drainage • Make necessary 93% of the stretch Villagers, and field system change in • Impacts on CPRs workers. • Location of alignment to save have been minimized Bus Stop these common and where not • Large no. of properties. possible, their business loss relocation shall be will accrue. • Provide carefully planned and • Compensatio underpass at the executed n of structure way to Diwachali and other & Khurra. properties. • Street lights at • Bus stops have been divider, Bus stop provided at ½ km away from dense populated area • speed breakers have • Speed breaker at been provided at both sides of critical locations crossing across the entire • High mask light at project stretch Mandawari • Construction Chauraha activities will commence only after • Before start the compensation and construction eligible assistances activities please have been paid as ensure to per the policy rehabilitate first framework and and relocate relocation of PAPs, common business units and properties. CPRs • Assistances shall be provided as per • Suitable policy framework assistance should • Only one bypass is be provided. Gangapur is proposed • No need of bypass otherwise we will loss our commercial activities Khanpur Nayab Tehsildar, • Provision of • Provide bypass. • alignment has been Baroda Patwari, bypass designed to avoid 13.10.2012 Gramsevak, Project • Compensatio • Before starting need for a new Preparation Team: n of structure the construction bypass MORTH TCPL CH - 8/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Venue & Participants Issues Suggestions given Responses given/ dates Discussed Mitigation measures incorporated Social expert of the and other activities ensure • construction consultant, Villagers, properties. giving sufficient activities will Sarpanch etc. time for resettling commence only after the houses. compensation and eligible assistances have been paid as • Suitable per the policy assistance should framework and be provided. relocation of PAPs, business units and • Pucca drain on CPRs both side of the • Assistances shall be NH-11B provided as per policy framework • Provisions for drains are incorporated in design Piplai, NTDR-Bananwas, • Provision of • Provide bypass • alignment has been 12.10.2012 Land Record Bypass from Dawar to designed and hence Inspector, Patwari, • road safety Gas Agency no bypass is villagers, Social Bamanwas. required Expert, Project • Make necessary • Safety measures preparation team provisions for (signages, rumble and field safety strips, speed limits) enumerators. • Provide drainage are provided for in along both sides the design of the road. • Compensation for • Compensation as land shall be as per per the quality of applicable rates land and crops • Compensation and consideration eligible assistances • Adequate and will be paid as per timely the policy framework compensation to • Provision has been the acquired land made for such and community works in compensation as the budget. The per the current implementing agency market rate will discuss such • Provision of measures and decide Construction of accordingly Yatri shed and public toilet. Salempur Tehsildar, Village • Construction of • Salempur bypass has village Sarpanch bypass at been dropped and in 13.10.2012 (Headman,Salempur Salempur agreement with the village and Ministry it has been Mohammadpur) dropped Assistant Engineer • Road widening • Provision of Drains villagers, Social lead to (1.5 meters) is Expert, Project development and incorporated across preparation team provision of side the entire stretch and field drain. • Compensation and enumerators. • Timely and assistances shall be adequate as per the policy compensation framework should be given • Temporary shelters

MORTH TCPL CH - 8/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Venue & Participants Issues Suggestions given Responses given/ dates Discussed Mitigation measures incorporated to the affected shall be provided for people. construction labor • Construction of residence for landless laborers

Documentation of consultations is provided as Annexure 8.1.

8.3 Summary of Consultations Participants expressed their opinion, concern and suggestions in a free and frank manner. In general all stakeholders including likely project affected persons were in favour of the proposed project. However, participants expressed concerns with regard to compensation, provision of drainage, safety, provision of bypass, etc.

People opined that proposed project will improve connectivity to various places and save time and money. Issues and concerns raised by participants were mostly common which includes compensation as per prevailing market rate, provision of drains, likelihood of increased number of accidents, provision of speed breakers, etc. Women were found concerned about the widening of the existing road, especially the high speed vehicles and likely accidents. They also felt that crossing to the other side of the road for various purposes including taking animals to the grazing land and accessibility to agricultural land is difficult.

MORTH TCPL CH - 8/8

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 9

RESETTLEMENT POLICY FRAMEWORK

9.1 Introduction

A Resettlement Policy Framework has been prepared by the Ministry of Road Transport & Highways, Government of India for National Highways Inter-Connectivity Improvement Project (NHIIP). This RPF includes resettlement and rehabilitation principles and approach to be followed in minimizing and mitigating adverse impacts likely to be caused by the project implementation, entitlement matrix, census and socio-economic survey, preparation of SIA and RAP, institutional arrangement for RAP implementation, etc. The compensation and resettlement and rehabilitation assistance to project affected persons shall be provided in accordance with this RPF in letter and spirit.

9.2 Applicable Legal and Policy Framework

Applicable acts, notifications and policies relevant in the context of this project are discussed below in Table 9.1. The Project Authority (MoRTH) will ensure that project activities implemented are consistent with the national, state, local regulatory and legal

framework.

Table 9.1 – Applicability of Acts, Notifications and Policies

Sr. Acts, Notifications Relevance to this project Applicability No. and policies 1 National Highways Land required for the project shall be acquired as per Applicable Act, 1956 the provisions of this act. 2 National Provides limited benefits to affected family (an ex- Applicable Rehabilitation and gratia payment of not less than Rs. 20,000+- and in Resettlement Policy case land-holder becoming landless or small or (NRRP), 2007 marginal farmer in such cases other rehabilitation benefits as applicable. 3 World Bank OP 4.12 The project entails land acquisition though, at a low Applicable – Involuntary scale for widening, realignments, junction Resettlement improvements, bypass etc. It would also adversely affect structures used for various purposes, livelihood of people (mainly earning their livelihood by means of petty shops and providing various services). Many of them have been operating from the government land. Thus both title holders and non-title holders alike would be affected as a consequence of the project. 4 The Right to The Act provides for setting out the practical regime of Applicable Information Act, right to information for citizens to secure access to 2005 information under the control of public authorities, in order to promote transparency and accountability in the MORTH TCPL CH - 9/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Acts, Notifications Relevance to this project Applicability No. and policies working of every public authority, the constitution of a Central Information Commission and State Information Commissions and for matters connected therewith or incidental thereto. 5 Environmental The Act provides for mandatory public consultation for Applicable protection Act, 1986 all listed projects and activities requiring prior and subsequent Environmental Clearance (EC) and includes road and amendments highways requiring further land acquisition. The Public Consultation shall ordinarily have two components comprising of:- (a) a public hearing at the site or in its close proximity- district wise, to be carried out in the manner prescribed, for ascertaining concerns of local affected persons; (b) obtain responses in writing from other concerned persons having a plausible stake in the environmental aspects of the project or activity.

9.3 Objectives and Scope of Resettlement Policy Framework

This Framework has been formulated to lay down the principles and procedures for management of social impacts caused by the project and guide the social impact assessment and preparation of mitigation plans including Resettlement Action Plans and Tribal Development Plans for the project. This Framework shall apply to all project roads under NHIIP whether partly or fully funded by World Bank during the entire period of loan assistance. Overall objective of this Framework is to guide the preparation and implementation of NHIIP based on the following principles:

 Take due precautions to minimize disturbance to human habitations, tribal areas and places of cultural significance.

 Ensure that the Project Affected Persons (PAPs) are not negatively affected by the project.

 Involve affected people from inception stage to operation and maintenance.

 Consult affected people in issues of ROWs, land acquisition or loss of livelihood

 Encourage consultation with communities in identifying environmental and social implications of projects.

 Pay special attention to marginalized and vulnerable groups and secure their inclusion in overall public participation.

MORTH TCPL CH - 9/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

 Provide compensation and assistance to PAPs prior to any displacement or start of civil works.

 Guarantee entitlements and compensation to affected people as per the R&R policy as established in this document. This would ensure compensation and assistance sufficient to improve or at least restore livelihoods to levels experienced before the project.

 Share information with local communities about environmental and social implications.

 Broad community support is ascertained based on free, prior and informed consultation.

Revision/Modification of the RPF: This RPF will be an “up-to-date” or a “live document” enabling revision, when and where necessary. Unexpected situations and/or changes in the project or sub-component design would therefore be assessed and appropriate management measures will be incorporated by updating the Resettlement Policy Framework to meet the requirements of country’s legislations and Bank safeguards policies. Such revisions will also cover and update any changes/modifications introduced in the legal/regulatory regime of the country/state. Also, based on the experience of application and implementation of this framework, the provisions and procedures would be updated, as appropriate in consultation with the World Bank and the implementing agencies/departments.

9.4 Definitions

Following definitions that will be applicable unless otherwise stated specifically.

• Agricultural labourer: means a person primarily resident in the affected area for a period of not less than five years immediately before the declaration of the affected area, who does not hold any land in the affected area but who earns his livelihood mainly by manual labour on agricultural land therein immediately before such declaration and who has been deprived of his livelihood;

♦ Agricultural land: Denotes land used or capable of being used for the purpose of agriculture or horticulture, dairy farming, poultry farming, pisciculture, sericulture, breeding of livestock or nursery growing medicinal herbs, raising of crops, grass or garden produce and land used by an agriculturist for the grazing of cattle, but does not include land used for cutting of wood only;

MORTH TCPL CH - 9/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

♦ Below poverty line (BPL) or BPL family: means below poverty line families as defined by the Planning Commission of India, from time to time and those included in the BPL list for the time-being in force.

♦ Corridor of impact (COI): Refers to the minimum land width required for construction including embankments, facilities and features such as approach roads, drains, utility ducts and lines, fences, green belts, safety zone, working spaces etc. Additional land width would be acquired+purchased or taken on temporary lease if the Corridor of Impact extends beyond the available Right of Way.

♦ Cut-off date: Refers to the date on which the census survey of PAPs starts in that road section+stretch. For entitlement purpose, the PAPs would be those who have been in possession of the immovable or movable property within the affected area+zone on or prior to cut off date. However, the cut-off date for land acquisition purpose is the date on which the notification under section 3A will be issued under the NH Act, 1956.

♦ Encroacher: A person who has extended their building, agricultural lands, business premises or work places into public+government land without authority.

♦ Entitled person (EP): A person who is adversely impacted by the project and is entitled to assistance as per the project entitlement framework is considered to be an Entitled Person.

♦ Holding: means the total land held by a person as an occupant or tenant or as both;

♦ Kiosk: A kiosk is a booth+stall+cabin+cubicle made of wood or iron or any other building material which could be shifted to another location as a single unit without much damage and is used for carrying out petty business+ commercial activities and has been in operation+existence prior to cut off date.

♦ Land acquisition" or "acquisition of land": means acquisition of land under the NH Act, 1956 for the time being in force;

♦ Landowner: A person who is an allottee or a grantee of any land under any scheme of the Government under which such allotment or grant is to mature into ownership, who has mortgaged his land (or any portion thereof) or who has permanent rights and interest in land.

MORTH TCPL CH - 9/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

♦ Marginal farmer: Refers to a cultivator with an un-irrigated land holding upto one hectare or irrigated land holding upto half hectare.

♦ Non-agricultural labourer: means a person who is not an agricultural labourer but is primarily residing in the affected area for a period of not less than five years immediately before the declaration of the affected area and who does not hold any land under the affected area but who earns his livelihood mainly by manual labour or as a rural artisan immediately before such declaration and who has been deprived of earning his livelihood mainly by manual labour or as such artisan in the affected area;

♦ Non-titleholder: Affected persons+families+ households with no legal title to the land, structures and other assets adversely affected by the project. Non-titleholders include encroachers, squatters, etc.

♦ Notification: means a notification published in the Gazette of India.

♦ Occupier: means a member of a Scheduled Tribes community in possession of forest land prior to the 13th day of December, 2005;

♦ Project: Refers to the National Highways Interconnectivity Improvement Project (NHIIP).

♦ Project affected area: Refers to the area of village or locality under a project for which land will be acquired under NH Act 1956 through declaration by Notification in the Official Gazette by the appropriate Government or for which land belonging to the Government will be cleared from obstructions.

♦ Project affected family: includes a person, his or her spouse, minor sons, unmarried daughters, minor brothers, unmarried sisters, father, mother and other relatives residing with him or her and dependent on him or her for their livelihood; and includes "nuclear family" consisting of a person, his or her spouse and minor children;

♦ Project affected person (PAP): Any tenure holder, tenant, Government lessee or owner of other property, or non-titleholder who on account of the project has been affected from such land including plot in the abadi or other property in the affected area will be considered as PAP.

♦ Project displaced person (PDP): Any tenure holder, tenant, Government lessee or owner of other property, or non-titleholder who on account of the project has been involuntarily displaced from such land including plot in the abadi or other MORTH TCPL CH - 9/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

property will be considered as PDP. A displaced will always be a PAP but all PAP may not be PDP.

♦ Project affected household (PAH): A social unit consisting of a family and+or non-family members living together, and is affected by the project negatively and+or positively.

♦ Replacement cost: A replacement cost+value of any land or other asset is the cost+value equivalent to or sufficient to replace+purchase the same land or other asset.

♦ Small farmer: Refers to a cultivator with an un-irrigated land holding up to two (2) hectares or with an irrigated land holding up to one (1) hectare.

♦ Squatter: A person who has settled on public+government land, land belonging to institutions, trust, etc and or someone else’s land illegally for residential, business and or other purposes and+or has been occupying land and building+asset without authority.

♦ Tenant: A person who holds+occupies land-+structure of another person and (but for a special contract) would be liable to pay rent for that land+structure. This arrangement includes the predecessor and successor-in-interest of the tenant but does not include mortgage of the rights of a landowner or a person to whom holding has been transferred; or an estate+holding has been let in farm for the recovery of an arrear of land revenue; or of a sum recoverable as such an arrear or a person who takes from Government a lease of unoccupied land for the purpose of subletting it.

♦ Titleholder: A PAP+PAF+PAH who has legal title to land, structures and other assets in the affected zone.

♦ Vulnerable group: This includes Scheduled Caste. ST, family+household headed by women+female, disabled, handicapped, orphans, destitute, BPL, abandoned woman; unmarried girls; widows; and persons above the age of 65 years irrespective of their status of title (ownership). Vulnerable groups would also include those farmers who (after acquisition of land) become small and marginal farmers and also qualify for inclusion in BPL. For such cases, total land holding of the landowner in that particular revenue village will be considered in which land has been acquired.

MORTH TCPL CH - 9/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

♦ Wage earner: Wage earners are those whose livelihood would be affected due to the displacement of the employer. The person must be in continuous employment for at least six months prior to the cut-off date with the said employer and must have reliable documentary evidence to prove his/her employment.

9.5 Resettlement Principles

The broad resettlement principles adopted are as under:

Upgrading of project road will mostly take place within the existing Right of Way (RoW) except at some of the congested villages/settlements where bypass are proposed and at locations where minor improvements are required for accommodating road safety measures.

• Adverse impacts of the project on land, structure, livelihood and other assets will be avoided or minimized as much as possible exploring all viable alternatives;

• Where adverse impacts can’t be avoided, resettlement and rehabilitation assistance shall be provided to persons and also enable the persons to share the project benefits;

• Efforts shall be made to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-project level;

• PAPs and local community shall be meaningfully consulted and encouraged to participate in project implementation particularly, RAP;

• Replacement land shall be an option for compensation in the case of loss of land. In case of unavailability of replacement land, cash-for-land with compensation on replacement cost option will be made available to the PAPs;

• Compensation for loss of land, structures and other assets will be based on full replacement cost;

• In the event of necessary relocation, PAPs shall be assisted to integrate into host communities;

• Land acquisition for the project will be as per the National Highways Act, 1956;

• Cut-off date for titleholders will be the date of publication of notification under Section 3A of the National Highways Act, 1956. For non-titleholders who has not any legal holding of the occupied land such as squatters and encroachers the date of project census survey or a similar designated date declared by the executing agency will be considered as cut-off date; MORTH TCPL CH - 9/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• An entitlement matrix for different categories of people affected by the project has been prepared and provisions will be kept in the budget for those who were not present at the time of census survey. However, people moving in the project area after the cut-off date will not be entitled to any compensation or assistance;

• Vulnerable groups will be identified and provided additional support and assistance under the project;

• All common property resources (CPR) lost due to the project will be reconstructed or compensated by the project;

• Disseminate and update information to PAPs, local communities and other stakeholders on regular basis;

• Ensure disbursement of compensation and R&R assistance to PAPs as per the entitlements and prior to taking possession of the property affected;

• Establish suitable institutional arrangements for the implementation of RAP and its monitoring;

9.6 Entitlement Matrix

Under this resettlement and rehabilitation Policy adopted for the project, several categories of project affected persons are recognised with varying eligibility for the compensation and assistance packages in the entitlement matrix below in Table 9.2. This entitlement matrix has been developed in accordance with the basic principles adopted in the RPF and analysis of initial identification of project impacts.

In case where a State Government through any Act or Gazette Notification or as approved by any authority of State Government (duly authorized for the purpose) as per their approved procedure has fixed a rate for compensation of land and is higher than the provisions under the project, the same may be adopted by the Competent Authority in determining the compensation for land.

Similarly, in case where a State Government through any Act or Gazette Notification or as approved by any authority of State Government (duly authorized for the purpose) as per their approved procedure has fixed a rate for resettlement and rehabilitation assistance and is higher than the provisions under the project, the same may be adopted by the Executing Authority.

MORTH TCPL CH - 9/8

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 9.2 – Entitlement Matrix

Sr. Application Definition of Entitlement Details No. Entitled Unit A. Loss of Private Agricultural, Home-Stead & Commercial Land 1 Land within Titleholder Compensation a) Land for land, if available. Or, Cash the Corridor family and at compensation for the land at replacement of Impact families with replacement cost, which will be determined as (COI) traditional land cost, mentioned in Note (A). Right Resettlement b) If the compensation amount determined by and the Competent Authority is less than the Rehabilitation replacement cost mentioned in Note A, the difference amount will be paid as replacement assistance. c) In case of land for land is not provided, additional ex-gratia amount of Rs 20,000/- for those losing land up to 250 sqmts of land. The affected person will get Rs.80 per sqmt for any area acquired above 250 sqmt. (para 7.19 NRRP 2007) d) If as a result of land acquisition, the land holder becomes landless or is reduced to the status of a “small” or “marginal” farmer, rehabilitation allowance equivalent to 750 days of minimum agricultural wages would also be given. (para 7.14, NRRP-2007). e) Policy for acquisition/ compensation for residual land will be as per note B. f) In case of allotment of land, one time financial assistance of minimum Rs. 15000/- per hectare for land development. (para 7.9.1 of NRRP-2007) g) Refund of stamp duty and registration charges incurred for replacement land to be paid by the project; replacement land must be bought within a year from the date of payment of compensation to project affected persons. B. Loss of Private Structures (Residential/Commercial) 2 Structure Title Holder/ Compensation a) Cash compensation for the structure at within the Owner at replacement cost which would be Corridor of replacement determined as per Note (C). Impact (CoI) rate, b) Right to salvage material from the Resettlement demolished structures. & c) Three months’ notice to vacate structures. Rehabilitation d) Refund of stamp duty and registration Assistance charges for purchase of new alternative houses/shops at prevailing rates on the market value as determined in (a) above. Alternative houses/shops must be bought within a year from the date of payment of compensation. e) In case of partially affected structures and the remaining structure continues to be viable additional 25% of compensation amount as restoration grant. f) Monthly subsistence/transitional allowance

MORTH TCPL CH - 9/9

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Application Definition of Entitlement Details No. Entitled Unit equivalent to twenty-five days minimum agricultural wages per month for a period of one year from the date of displacement (para 7.16 of NRRP-2007). g) Each affected family getting displaced shall get a one-time financial assistance of Rs 10,000 as shifting allowance (para 7.10 NRRP 2007). h) Each affected family that is displaced and has cattle, shall get financial assistance of Rs 15,000/- for construction of cattle shed (para 7.10 NRRP 2007). i) Each affected person who is a rural artisan, small trader or self-employed person and who has been displaced (in this project owner of any residential–cum commercial structure) shall get a one-time financial assistance of Rs 25,000/- for construction of working shed or shop (para 7.12 NRRP 2007). j) House construction assistance of Rs. 10,000 for families belonging to vulnerable group will be provided. 3 Structure Tenants/ Resettlement a) Registered lessees will be entitled to an within the Lease Holders & apportionment of the compensation Corridor of Rehabilitation payable to structure owner as per Impact (CoI) Assistance applicable local laws. b) In case of tenants, three months written notice will be provided along with Rs 10,000 towards shifting allowance (NRRP 7.11). c) In case three months’ notice to vacate structures is not provided, then three months’ rental allowance will be provided in lieu of notice.

C. Loss of Trees and Crops 4 Standing Owners and Compensation a) Three months advance notice to project Trees, beneficiaries at market affected persons to harvest fruits, standing Crops within (Registered/ value crops and removal of trees. the Corridor Un-registered b) Compensation to be paid at the rate of Impact tenants, estimated by: (CoI) contract i) The Forest Department for timber trees cultivators, ii) The State Agriculture Extension leaseholders Department for crops & iii) The Horticulture Department for sharecroppers fruit/flower bearing trees.

c) Registered tenants, contract cultivators & leaseholders & sharecroppers will be eligible for compensation for trees and crops as per the agreement document between the owner and the beneficiaries.

d) Un-registered tenants, contract cultivators, leaseholders & sharecroppers will be eligible for compensation for trees and crops as per MORTH TCPL CH - 9/10

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Application Definition of Entitlement Details No. Entitled Unit mutual understanding between the owner and the beneficiaries.

D. Loss of Residential/ Commercial Structures to Non-Titled Holders 5 Structures Owners of Resettlement a) Encroachers shall be given three months’ within the Structures or & notice to vacate occupied land or cash Corridor of Occupants of Rehabilitation assistance at replacement cost for loss of Impact (CoI) structures Assistance structures. or Govt. land identified as b) Any encroacher identified as vulnerable per Project shall be paid replacement cost of affected Census structure to be determined as per Note C. Survey c) Any encroacher identified as non- vulnerable but more than 25% of structure used for residential purposes is affected be paid cash assistance at replacement cost for loss of structures to be determined as per Note C. d) All squatters to be paid cash assistance for their structures at replacement costs which will be determined as mentioned in Note C. e) Resettlement & Rehabilitation assistance to the squatters as under: (i) Monthly subsistence/transitional allowance equivalent to twenty-five days minimum agricultural wages per month for a period of one year from the date of displacement (para 7.16 of NRRP-2007). (ii) Shifting allowance of Rs 10,000 per family (para 7.11 NRRP 2007). (iii) Assistance of Rs 15,000/- for loss of cattle shed (para 7.10 NRRP 2007). (iv) Each affected person who is a rural artisan, small trader or self-employed person assistance of Rs 25,000/- for construction of working shed or shop (para 7.12 NRRP 2007). (v) House construction assistance of Rs. 10000/- for those belonging to vulnerable groups. E. Loss of Livelihood 6 Families Title Holders/ Resettlement a) Monthly subsistence/transitional living within Non-Title & allowance equivalent to twenty-five days the Corridor holders/ Rehabilitation minimum agricultural wages per month of Impact sharecroppers, Assistance for a period of one year from the date of (CoI) agricultural displacement (para 7.16 of NRRP- labourers and 2007). (PAPs covered under 1(f), 2 (f) employees and 5 (e)(i) above would not be eligible for this assistance). b) Training Assistance of Rs 10,000/- for income generation per family. c) Temporary employment in the project construction work to project affected persons with particular attention to vulnerable groups by the project

MORTH TCPL CH - 9/11

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Application Definition of Entitlement Details No. Entitled Unit contractor during construction, to the extent possible.

F. Additional Support to Vulnerable Group 7 Families Vulnerable Resettlement One time additional financial assistance within the families & equivalent to 300 days of minimum wages to Corridor of Rehabilitation all vulnerable including STs as Economic Impact (CoI) Assistance Rehabilitation Grant.

G. Additional Assistance to Scheduled Tribe Families Scheduled Family Resettlement a) Each ST affected family shall get an 8 Tribe families & additional one time financial assistance within the Rehabilitation equivalent to two hundred days of Corridor of Assistance minimum agricultural wages for loss of Impact (CoI) customary rights or usage of forest produce (para 7.21.5 NRRP 2007). Customary rights on land and usage of forest will have to be certified by the Gram Sabha or such appropriate authority. b) Each Scheduled Tribe family affected families resettled out of the district will get twenty-five per cent higher rehabilitation and resettlement benefits. H. Loss of Community Infrastructure/Common Property Resources Structures & Affected Reconstruction Reconstruction of community structure and 9 other communities of community Common property resources in consultation resources and structure and with the community. (e.g. land, groups common water, property access to resources structures etc.) within the Corridor of Impact (CoI)

I. Temporary Impact During Construction 10 Land & Owners of Compensation Compensation to be paid by the contractor for assets land & for temporary loss of assets, crops and any other damage as temporarily Assets impact during per prior agreement between the ‘Contractor’ impacted construction and the ‘Affected Party’. during e.g. diversion construction of normal traffic, damage to adjacent parcel of land / assets due to movement of heavy machinery and plant site. J. Resettlement Site 11 Loss of Displaced Provision of Resettlement sites will be developed as part of residential titleholders resettlement the project, if a minimum of 25 project displaced and and non- site/ vendor families opt for assisted resettlement.

MORTH TCPL CH - 9/12

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Application Definition of Entitlement Details No. Entitled Unit commercial titleholders market Vulnerable PAPs will be given preference in structures allotment of plots/flats at the resettlement site. Plot size will be equivalent to size lost subject to a maximum of 250 sqmt in rural area and 150 sqmt in urban areas (7.2 of NRRP 2007). Similarly, if at least 25 displaced commercial establishments (small business enterprises) opt for shopping units, the Project Authority will develop the vendor market at suitable location in the nearby area in consultation with displaced persons. Shopping unit size will be equivalent to size lost subject to a maximum of 100 in urban and 150 sq.ft. in rural areas. Vulnerable PAPs will be given preference in allotment of shops in vendor market. One displaced family will be eligible for only one land plot at resettlement site or shop in the vendor market. Basic facilities such as approach road, electricity connection, water and sanitation facility, etc shall be provided at resettlement site and in vendor market, as applicable by the Project Authority at project cost. Any other basic facilities shall be provided at the time of implementation in consultation with displaced persons depending on the requirements. Budget for the development of resettlement sites and vendor markets will be included in the overall project cost. In case of self-relocation, PAPs will be eligible for additional support for the construction of structure@ 15% of the financial assistance provided for new construction of house under IAY and JNNURM, subject to the condition that the PAP uses the assistance money for construction only within a period of one year from the date full payment of compensation and assistance amount in the concerned state. The PAP will be required to provide documentary evidence to that effect. Self-relocating displaced PAPs will not be eligible for land plots at resettlement site or shop in the vendor market.

9.7 Methods for Assessment of Replacement Cost

The methods for assessment of replacement cost and determination of compensation for loss of land, structure, and other assets are discussed in the notes provided below:

Note A

MORTH TCPL CH - 9/13

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

1. Compensation would be determined by Competent Authority:

(i) Calculate the base cost by adding 50% of the latest guideline value/circle rate for the indented use of the land;

(ii) Add 60% solatium to the base cost of land.

Or

2. Engage/Hire an Independent Valuer registered with Government, who can assist to assess the replacement cost of land as follows and provide inputs to the competent authority by:

(i) Appraising recent sales and transfer of title deeds and registration certificates for similar type of land in the village or urban area and vicinity

(ii) Appraising circle rate in urban and rural areas of the district

(iii) Appraising agricultural productivity rate for land – 20 years yield.

Or

3. Compensation as per the state approved procedure.

Replacement cost of land shall be the highest of the above three options.

Note B - Compensation for unviable residual land

If the residual plot(s) is (are) not economically viable, the SPIU will follow the rules and regulations applicable in the state and compensate accordingly; if there are no state specific rules and regulations available regarding residual land and the residual land is less than average land holding of the district after acquisition, then the SPIU in agreement with the project affected person will follow one of the following:

(i) The SPIU will buy the residual land for the project following the entitlements listed in the entitlement matrix; or

(ii) The SPIU will pay the project affected person 25% of the base cost of land as hardship compensation for that portion of land (residual) without its acquisition.

MORTH TCPL CH - 9/14

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Note C - Replacement cost of houses, buildings and other structures

The replacement cost of houses, buildings and other immovable properties will be determined on the basis of replacement cost by referring to relevant Basic Schedule of Rates (BSR) as on date without depreciation. In case of partial impact, if the residual structure is rendered structurally unsafe or unviable the entire structure to be considered affected and compensated accordingly. In case of displacement and the valuation amount is less than the amount provided under IAY/JNNURM as applicable, compensation equivalent to provisions under IAY/JNNURM shall be provided.

Note D - Compensation for Trees/Crops

Compensation for trees will be based on their market value. Loss of timber trees will be compensated at their replacement cost while the compensation for the loss of fruit bearing trees will be calculated as annual produce value calculated for the number of years (as per standard procedure followed by concerned department) depending on the nature of trees/crops.

9.8 Direct Purchase of Land

Provision of direct purchase of land from land owners in case of sub-project where additional land requirement is very less (minimal) may also be considered. However, resettlement and rehabilitation benefits available to affected persons whose land would be acquired under the statute shall also be available to those affected persons whose land would be acquired through direct purchase.

MORTH TCPL CH - 9/15

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 10

INSTITUTIONAL ARRANGEMENT FOR RAP IMPLEMENTATION

Institutional arrangements for the implementation of RAP have been made fixed by making it part of the RPF. The Institutional Arrangements will be set up at three levels viz., MoRT&H (Central Govt.)., State Level and Sub-Project Level on partnership model wherein concerned agencies at different levels supplement and complement each other efforts. The key elements of institutional arrangements are co-operation/ support, collaboration and sharing of responsibilities with clearly defined roles, involvement of key stakeholders and vertical and horizontal linkages amongst different agencies. The institutional arrangement is discussed below and depicted in Figure 10.1.

Figure -10.1: Institutional Arrangement for RAP Implementation

Project Authority Social Development CE (EAP), MoRTH Specialist (SDS)

SE (Designated Social Officer), MoRTH

Regional Officer, MoRTH

SCHM (CE) PCU (State PWD, headed by CE NH (general wing and designated Nodal Officer) M&E Agency project Supported by Land Acquisition cum (Third party) related Social Development Officer

GRC at PIU -- SDE/AE (Designated as District Level District Level Replacement Cost (RPF related R&R Officer) Committee issues)

NGO / Consultancy Firm

MORTH TCPL CH - 10/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

10.1 Central Level

At Central Level, the Chief Engineer (EAP), MoRTH, Govt. of India will be overall responsible for the implementation of RAP. Chief Engineer (EAP) will have all delegated administrative and financial decisions with regard to implementation of the project as well as land acquisition, RAP implementation.

Institutional arrangement at Central Level will include augmenting the capacity of MoRTH with regard to resettlement and rehabilitation. A team comprising Superintending Engineer designated as Social Development Specialist (SDS) and a suitable number of Technical and Secretarial Staff will assist CE (EAP). The designated SDS will be directly involved in the implementation of RAP. The SDS will ensure that all resettlement and rehabilitation issues are complied with as per the RPF. The roles and responsibilities of the SDS would broadly include the following:

♦ Ensure preparation and disclosure of SIA, RAP and Land Acquisition Plan for sub projects as per RPF.

♦ Ensure adequate staffing at state and sup project level to ensure timely implementation of RAP.

♦ Guide and supervise in matters related to resettlement and rehabilitation to state and sub-project level offices.

♦ Compile data related to resettlement and rehabilitation activities received from field offices and update Chief Engineer (CE) and suggest suitable measures to be taken.

♦ Interact with implementation agencies at state and sup project level on a regular basis.

♦ Undertake field visits as and when required.

♦ Facilitate necessary help needed at site with regard to LA and R&R issues.

♦ Co-ordinate with state government department in matters related to implementation of R&R.

♦ Ensure budgetary provision for resettlement and rehabilitation of PAPs and relocation, rehabilitation and reconstruction of common property resources (CPRs).

♦ Ensure timely release of budget for implementation of RAP.

♦ Monitor implementation of RAP carried out by the agency through RRO.

♦ Perform other roles and responsibilities related to implementation of RAP as

MORTH TCPL CH - 10/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

assigned by the CE (EAP) from time to time.

♦ Ensure free, prior and informed consultation with vulnerable groups along the project and also ensure that sufficient supporting documentation is maintained.

♦ Ensure third party audit of RPF implementation.

10.2 State Level

At State Level, a Land Acquisition cum Social Development Officer will be appointed to provide assistance to the designated Nodal Officer of PIU, Road Construction Department, Govt. of Bihar. The roles and responsibilities of the LA cum SDO would broadly include the following:

♦ Facilitate preparation and implementation of land acquisition and RAP in compliance with RPF,

♦ Ensure consultation and stakeholder participation in finalisation of RAP,

♦ Guide and supervise RAP implementation at sub-project level,

♦ Interact with RAP implementation support agencies and undertake field visits for first-hand information,

♦ Guide and supervise the RAP implementing agency to roll out HIV prevention activities,

♦ Compile data on LA progress and RAP implementation activities received from field offices and update SE (Designated Social Officer), MoRTH and suggest suitable measures to be taken,

♦ Co-ordinate with various government departments in matters related to implementation of RAP,

♦ Check implementation of RAP carried out by the agency from time to time by undertaking site visits and consultations with PAPs,

♦ Perform other roles and responsibilities related to implementation of RAP as assigned by the SE (Designated Social Officer), MoRTH from time to time,

♦ Facilitate and cooperate in Third party Audit of RPF implementation.

10.3 Sub-Project Level

A Project Implementation Unit (PIU) comprising officials of State PWD will be constituted at sub- project level headed by the Superintending Engineer/ Executive Engineer

MORTH TCPL CH - 10/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

designated as Project Director. The PIU will be responsible for the project execution including RAP implementation. There will be a designated or appointed Resettlement & Rehabilitation Officer (RRO) at respective PIUs who will be responsible only for the implementation of RAP at site. No other roles and responsibilities will be assigned to RRO other than resettlement and rehabilitation. RRO will assist Project Director at PIU and SDS at Central Level in all matters related to resettlement and rehabilitation.

The roles and responsibilities of the Resettlement and Rehabilitation Officer are as under:

♦ Ensure RAP implementation with assistance from implementation agency as per the time line agreed upon.

♦ Interact with RAP implementation agency on a regular basis.

♦ Undertake field visits with implementation agency from time to time.

♦ Facilitate necessary help needed at site with regard to LA and R&R, HIV issues to implementation agency.

♦ Co-ordinate with district administration and other departments in matters related to implementation of R&R.

♦ Ensure distribution of Resettlement and Rehabilitation Policy and entitlement matrix for the project to PAPs.

♦ Ensure preparation and distribution of photo identity cards.

♦ Ensure and attend meetings organised by implementation agency on thematic areas related to resettlement and rehabilitation policy and entitlements and awareness generation.

♦ Ensure inclusion of PAPs who could not be enumerated during census but have documentary evidence to be included in the list of PAPs.

♦ Ensure preparation of identity cards, and approval from the Head Office and distribution of the same to PAPs.

♦ Ensure timely preparation of micro-plan from RAP implementation agency and approval from Head Office.

♦ Ensure disbursement of resettlement and rehabilitation assistance in a transparent manner.

♦ Participate in meetings related to resettlement and rehabilitation issues.

MORTH TCPL CH - 10/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

♦ Facilitate in opening of joint account of PAPs.

♦ Prepare monthly progress report related to physical and financial progress of implementation of RAP & submit to Head Office.

♦ Ensure release of compensation and assistance before taking over the possession of land for start of construction work.

♦ Ensure relocation, rehabilitation and reconstruction of CPRs before dismantling through proper mechanism.

♦ Attend and participate in Grievance Redress Committee meetings for redressal of grievances of PAPs and other committees involving R&R matters,

♦ Liaison with government and other agencies for inclusion of PAPs in employment and income generation programme/scheme.

♦ Carry out any other work related to resettlement and rehabilitation that may be entrusted from time to time by the PCU for compliance of R&R.

♦ Provide all necessary information and data related to R&R on monthly basis to Designated Social Officer at Central Level through Project Director.

♦ Ensure that vulnerable families get equal opportunity to participate during implementation and become overall beneficiaries in the project.

Besides, other institutional arrangements required for the implementation of RAP include engagement of RAP IA for the implementation of RAP, formation of District level committee to fix the replacement cost of affected properties, Grievance redressal mechanism, Suggestion and Complaint handling mechanism, engagement of monitoring and evaluation agency, etc. Roles and responsibilities of each agency are discussed below.

10.4 RAP Implementation Support Agency

To implement RAP, the Project Authority [CE (EAP), MoRTH] will engage the services of one or multiple agencies having experience in resettlement and rehabilitation issues through standard bidding process. The implementation agency will work in close co- ordination with RRO and report to PIU. Financial matters related to services of the RAP implementation agency will be dealt by Project Authority. Broad roles and responsibilities of implementation agency would be as:

MORTH TCPL CH - 10/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

♦ The RAP implementation agency will be the main link between the Project Authority and PAPs,

♦ Shall be responsible for verification of PAPs as prepared by the DPR consultants,

♦ Undertake public information campaign along with RRO at the commencement of the RAP,

♦ Develop rapport with PAPs,

♦ Distribute pamphlets of R&R Policy to PAPs, Panchayat Raj Institutions, and concerned Govt. Offices in the project area, etc.

♦ Include PAPs who could not be enumerated during census cum socio-economic survey and certification from R&R Officer,

♦ Distribute identity cards for PAPs,

♦ Preparation of micro-plan,

♦ Submission of micro-plan to RRO for approval from Head Office,

♦ Organize consultations at regular interval with PAPs with regard to resettlement and rehabilitation,

♦ Organize training program for skill up gradation of the PAPs,

♦ Assist PAPs in all matters related to compensation and R&R,

♦ Assist and facilitate aggrieved PAPs (for compensation and assistance) by bringing their cases to GRC,

♦ Facilitate in opening of joint account of PAPs,

♦ Generate awareness about the alternative economic livelihood and enable PAPs to make informed choice,

♦ Consultations with PAPs regarding the choice of resettlement (i.e. self or assisted), development of resettlement site, participation of women, etc.

♦ Identify training needs of PAPs for income generation and institutions for imparting training,

♦ Undertake outreach activities for HIV prevention for awareness and behaviour change as per RAP

♦ Consultations with local people and Panchayat Raj Institutions with regard to relocation, rehabilitation, reconstruction of affected CPRs as well as provision of new MORTH TCPL CH - 10/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

facilities under the project,

♦ Participate in various meetings,

♦ Submit monthly progress report, and

♦ Any other activities that may be required for the implementation of RAP, etc.

10.5 Replacement Cost Committee at District Level

A committee at district level will be constituted to fix the replacement cost of land, structures and other properties (trees, crops and other assets, tube well, hand pump, etc). The committee may comprise seven (7) members chaired by the District Collector/ Dy. Commissioner or his designated representative (not below the rank of SDM), Executive Engineer of the concerned District, District Agriculture Officer, Range Officer (Forest Department), an independent certified valuer and elected representative (MLA) of the concerned area and Team Leader of RAP implementation agency.

The highest value of land obtained by the three methods mentioned in Section 9.7 will be presented by the Project Authority approved by the committee as the replacement cost. Similarly, latest schedule of rates of the concerned districts shall be used for obtaining replacement cost of structures. For items not available in the schedule of rates for those items market rates shall be collected from three different sources and then replacement cost shall be fixed by the committee. For replacement costs of crops, trees and other such items similar methods will be followed.

For titleholders the difference of replacement amount and the compensation paid by the Competent Authority (CA) as per the NH Act shall be paid by the Project Authority to the entitled persons as assistance. The differential amount will be included in the micro plan to be prepared by the RAP IA.

The committee will be constituted through an executive order and or other suitable instrument within one month (30 days) from the date of mobilization of RAP implementation agency at site.

10.6 Mechanism for Implementation of RAP, Training and Capacity Building – at Project and Sub-project Level

Training and development of project staff is an integral part for implementation NHIIP. A training needs identification shall carried out at Central, Regional and Site level, based on which focused training modules will be developed in the first six months of project implementation;

MORTH TCPL CH - 10/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

 Strengthening in house capacity to implement the provisions of RPF/RAP,

 Creating Awareness, providing the tools for implementation of RAP, and accompanying set of management procedures to all departments,

 Developing competence within key officials to provide training in their respective level.

Based on skill requirement/improvement at all levels for proper implementation of RPF, a training programme focusing project implementing partners at Centre, State and field PIUs has been developed which will be implemented by the Project Authority (MoRTH) in the next two years. These training programs, which will be zeroed down after a quick training needs assessment, are to be conducted with the help of local and national training institutions and experts in various aspects of social management. MoRTH will also identify courses offered by the premier institutions in India and abroad on social management and inter-phase these with identified programme.

Provision for separate budget has been made for this activity. The budget reported under “institutional” head includes the cost estimates of training programs discussed above.

MORTH TCPL CH - 10/8

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 11

DISCLOSURE AND CONSULTATION PLAN

Information Disclosure: The Right to Information Act, 2005 provides for setting out the practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, the constitution of a Central Information Commission and State Information Commissions and for matters connected therewith or incidental thereto. The process for obtaining information and details of designated officials is posted on the MoRTH website http://www.morth.nic.in.

The Resettlement Policy Framework, Draft Resettlement Action Plan (RAP) and Executive Summary of the Draft RAP in local language (Hindi) have been disclosed on MoRTH website as well at the World Bank Infoshop/ Public Information Centre. Feedback, if any would be incorporated into the final RAP document, following which the final RAP will be re-disclosed. Further to enhance transparency in implementation, the list of PAPs for disbursement of benefits shall be separately disclosed at the concerned Panchayat Offices/ Urban Local Bodies,, District Collector Offices, Block development Offices, District Public Relations Offices (at the state and district levels), Project office, and any other relevant offices, etc. The Resettlement Policy Framework, Executive Summary of the SIA and RAP will be placed in vernacular language in the District Collector’s Office.

11.1 Consultation & Participation Plan

To ensure peoples’ continued participation in the implementation phase and aiming at promotion of public understanding and fruitful solutions of developmental problems such as local needs of road users and problem and prospects of resettlement, various sections of PAPs and other stakeholders will be engaged in implementation. Key actions would be as follows:

• Communicating and informing PAPs and beneficiary households in the project area of resettlement policy provisions and grievance redress mechanism through village level public meetings;

• Holding one to one meeting with the PAPs to explain their eligibility;

• Placing of micro plan in affected villages for review and minimize grievances;

MORTH TCPL CH - 11/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• Payment of R&R assistance to PAPs during public meetings to maintain transparency; and

• Household consultation to identify skill improvement training needs, counseling for usage of assistance amount and other activities towards livelihood restoration.

Information dissemination would be carried out through printed leaflets/ information booklets that would be prepared by the RAP Implementation Support Agency in local language. These would be distributed not only to PAPs but also to people (residents, businessmen and others) within the immediate project influence area and the local community in advance so that people discuss issues among themselves and prepare themselves for the meeting. On the day of public meeting, once again leaflets would be distributed among the people present for dissemination of information so as to ensure that all present at the meeting, get to know about the project in case they did not get the leaflet/ information booklet.

The leaflet/ information booklet would provide the following:

 brief description of the project and its objectives;

 a summary of adverse impacts (including land acquisition, and impacts on common property resources, etc);

 act under which land has been acquired;

 resettlement & rehabilitation provisions of the project and specific benefits available to vulnerable communities;

 ways and means of involving local communities;

 expectations from local communities;

 role of RAP IA and RRO; and

 Grievance redress mechanisms, suggestion and complain handling mechanism, etc.

Information dissemination would be carried out at least once in a month by organising public meetings at suitable locations involving PAPs, local communities, institutions and line departments at people’s door step on a pre-decided date and time. Wide publicity for the meeting would be carried out by beating of drums and announcement through loud speakers in the adjoining areas. The LA cum Social Development Officer & RRO

MORTH TCPL CH - 11/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

with assistance from RAP implementation agency would describe all aspects of the project, importance of consultations and also seek their participation and co-operation in the project. In these public meetings various aspects of the project would be explained and also the status of the project (technical, social & environmental) would be revealed. People in general and PAPs in particular, would be given opportunity to provide suggestions and raise issues which concern them and as a consequence maintain good rapport with local community. Land Acquisition cum Social Development Officer (State level), RRO, RAP Implementation Support Agency shall be present in these meetings.

After the public meeting, Minutes of Meeting (MoM)/ resolution would be prepared and read out to people present in the meeting. The MoM would be signed by the officials and participants present at the meeting. The MoM would be kept in project file for documentation purpose.

11.2 Suggestion and Complaint Handling Mechanism (SCHM)

The MoRTH recognizes the importance of this and hence intends to establish a SCHM for the NHIIP. The communication channels to report project related complaints/concerns will be disclosed at all levels of institutions - MoRTH, State, Project/site level.

Though the Right to Information Act, 2005 an Act of the Parliament of India provides for setting out the practical regime of right to information for citizens. The Act applies to all States and Union Territories of India except the State of Jammu and Kashmir. Under the provisions of the Act, any citizen may request information from a "public authority" (a body of Government or "instrumentality of State") which is required to reply expeditiously or within thirty days. The Act also requires every public authority to computerize their records for wide dissemination and to pro-actively publish certain categories of information so that the citizens need minimum recourse to request for information formally. In other words under the act, citizens have right to seek information from concerned agencies by following the set procedures. However, it is quite likely that many people may not use the provisions of this Act, only in limited cases covering serious concerns.

SCHM Users: The users of SCHM could be anyone from the project stakeholders, including civil servants (from MORTH, State PWDs, or from other State Departments) contractors, consultants, project affected people (communities), road users, CSOs/NGOs, any other public, who realizes either impact from or relation to the concerned project.

MORTH TCPL CH - 11/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Management of SCHM: The overall responsibility for the operation and management of NHIIP’s SCHM will rest with the PIC MoRT&H. The NHIIP’s SCHM will be handled at two levels: at the State and MoRT&H’s level.

Since all pre-construction and civil works will be implemented and managed by the States, all enquiries, suggestions and complaints related to a specific road will be submitted to the concerned implementing agency at the State Level. Each PIU at the State level is to set up a toll free number and/or email account for the project stakeholders and general public to submit their enquiries, suggestions and complaints. The toll free number and email account are to be displayed at the sign boards at the start and end of each project road. The bidding documents will have a requirement for the contractor to put in place signs at the start and end of the project road which will display the toll free number and email account to submit enquiries, suggestions and complaints to the concerned implementing government agency.

The EAP head will be in charge of assigning the responsible person/entity to address and handle enquiry, suggestion or complaint submitted at the M/oRT&H’s level. However, within his team he will assign an officer (engineer) who will be responsible for coordinating inquiries/comments and complaints/ concerns/grievances. His responsibilities will include:

• To respond to as many inquiries/comments as possible • To receive and sort concerns/grievances • To forward them to appropriate team members for resolution as per recommendation of the PIC Head • To track/monitor complaint/grievance acknowledgement and resolution • To review and report on complaint/grievance data and trends to the MORTH PIC Head, who in turn will report to MoRT&H CVO, NHIIP Project Oversight Committee, and WB. After receiving complaints, the complainants will be informed within three weeks about the status of the complaints and what action will be taken further. Channels: The following channels should be established to receive inquiries/comments and concerns /grievances: • Toll free phone • Email

MORTH TCPL CH - 11/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• On-line form • Regular post/mail • Suggestion box/Walk-ins

It is critical to assign a specific e-mail ID and a phone/fax number, and to set up an easy-to-access suggestion box and walk-in office. The project website will have a permanent sub-window that will contain an on-line form and facilitates grievance/complaint collection.

On-line Form for Suggestions and Complaints

The on-line form for suggestions and complaints will be provided on the NHIIP website. The form will contain only three entries as outlined below.

Subject : NHIIP Road : Content : Your email :

Suggestions/complaints submitted through this on-line form is to go directly to (a) the PIC Head’s email account and (b) internal reporting system for SCHM (excel file).

SCHM Reporting Format The internal reporting system for SCHM (excel file) will have the following entries/columns: 1. Date 2. Subject 3. Road 4. Content 5. Email (of the complainant) 6. Acknowledgment date (Date when PIC sent an email to the complainant to acknowledge that the email has been received, the issue will be handled within that period of time and the response/feedback will be provided to the complainant by that deadline) MORTH TCPL CH - 11/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

7. Responsible Person 8. Deadline for Feedback 9. Actual Date for Feedback 10. Solution/Feedback on the Suggestion/Complaint 11. Additional Comment (e.g., if the person was unsatisfied with the feedback/solution provided and indicated that he/she will go to another authority to complain) The entries 1-5 should be filled in automatically once an on-line form is submitted. The other entries are to be entered manually by the EAP and each State-level PIU. All SCHM-related reports are to be consolidated by the EAP.

MORTH TCPL CH - 11/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 12

GRIEVANCE REDRESSAL MECHANISM (GRM) The Resettlement Policy Framework mandates formation of Grievance Redressal Mechanism in order to resolve disputes in an effective manner and at the door steps of the PAPs. Compensation and assistance as per eligibility is provided in the entitlement matrix of the approved RPF. Grievance of PAPs will be brought to the grievance redress committee for redressal. The decision of the GRC will be binding, unless vacated by court of law.

12.1 Grievance Redressal Committee (GRC)

The GRC will be constituted by the Project Authority with the aim to settle as many disputes as possible on LA and R&R through consultations and negotiation. The GRC will comprise five members headed by a retired Magistrate not below the rank of SDM. Other members of the GRC will include a retired PWD Officer (not below the rank of Executive Engineer), RRO, representative of PAPs and Sarpanch (Elected Head of Village) of the concerned village. Grievances of PAPs in writing will be brought to GRC for redressal by the RAP implementation agency. The RAP implementation agency will provide all necessary help to PAPs in presenting his/her case before the GRC. The GRC will respond to the grievance within 15 days. The GRC will normally meet once in a month but may meet more frequently, if the situation so demands. A time period of 45 days will be available for redressing the grievance of PAPs. The decision of the GRC will not be binding to PAPs. This means the decision of the GRC does not debar PAPs taking recourse to court of law, if he/she so desires. Broad functions of GRC are as under:

♦ Record the grievances of PAPs, categorize and prioritize them and provide solution to their grievances related to resettlement and rehabilitation assistance.

♦ The GRC may undertake site visit, ask for relevant information from Project Authority and other government and non-government agencies, etc in order to resolve the grievances of PAPs.

♦ Fix a time frame within the stipulated time period of 45 days for resolving the grievance.

♦ Inform PAPs through implementation agency about the status of their case and their decision to PAPs and Project Authority for compliance.

The GRC will be constituted within 3 months by an executive order from competent

MORTH TCPL CH - 12/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

authority (centre/ state) from the date of mobilization of RAP implementation agency. The RRO will persuade the matter with assistance from implementation agency in identifying the suitable persons from the nearby area for the constitution of GRC. Secretarial assistance will be provided by the PIU as and when required. The flow diagram (Figure. 12.1) shows the entire process of grievance redressal.

Figure – 12.1: Grievance Redressal Mechanism

Grievance Redressal Mechanism

BROAD F U N C T I O N S

RECORD, CATEGORIZE UNDERTAKE FIELD FIX A TIMEFRAME TO CONVEY DECISION OF AND PRIORITISE VISITS, ASK FOR RESOLVE THE GRC TO PAPS IN GRIEVANCES RELEVANT PAPERS, GRIEVANCE WITHIN WRITING ETC AS REQUIRED STIPULATED TIME PERIOD

P R O C E S S

PIU CO-ORDINATES WITH DECISIONS OF GRC MEETING IS GRC&PAPS DRAFTED

GRC MINUTES PREPARED AND RAP IMPL. AGENCY INITIATES MEETING Redressed Redressed

SIGNED BY MEMBERS Grievances NECESSARY PREPARATION TO

GRC ASSIST PAPS GRC DECISIONS CONVEYED TO

PAPS IN WRITING

RGANIZES RRO CHECK GRIEVANCE &

O

CATEGORIZE AND INFORM RAP DECISION SENT TO GRC PIU

Redressed Redressed IMPL. AGENCY AND FOR CASES PA/EA FOR INFORMATION & TO BE REFERRED TO

Grievances Not Not Grievances GRC COMPLIANCE

PAPS LODGE GRIEVANCE TO BACK TO RRO FOR PIU DIRECTLY OR TO R&R IMPLEMENTATION OPTIONS TO MOVE COURT OFFICER IN WRITING WITH A COPY TO RAP IA

PAPS GRIEVANCE MET POTENTIAL GRIEVANCES OF RAP IMPL. AGENCY TO INITIATE PAPS ACTION

MORTH TCPL CH - 12/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

PAPs will be fully made aware about the GRM for effective, inexpensive and amicable settlement of claims for compensation and assistance by holding meetings with PAPs, public meetings and distributing leaflets containing salient features and procedures of GRM. The RAP IA will assist the PAPs in getting their record of rights updated in case of disputes related to land. The RRO with support from RAP IA will make all possible efforts for amicable settlement. The RAP IA will document all cases brought to GRC and maintain the records of the proceedings of the grievance redressal committee meetings.

MORTH TCPL CH - 12/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 13

MONITORING AND EVALUATION (M&E)

Monitoring and evaluation are important activities of infrastructure development project particularly, those involving involuntary resettlement. It helps making suitable changes, if required during the course of implementation of RAP and also to resolve problems faced by the PAPs. Monitoring is periodical checking of planned activities and provides midway inputs, facilitates changes, if necessary and provides feedback to project authority for better management of the project activities. Evaluation on the other hand assesses the resettlement effectiveness, impact and sustainability of R&R activities. In other words, evaluation is an activity aimed at assessing whether the activities have actually achieved their intended goals and purposes. Thus monitoring and evaluation of resettlement action plan implementation are critical in order to measure the project performance and fulfillment of project objectives.

The monitoring and evaluation of RAP implementation will ensure monitoring of key indicators on inputs, outputs, project processes and evaluation of impact indicators. The overall purpose of the monitoring is to keep track of the implementation processes and progress, achievement of performance targets fixed in the annual work plans, learning lessons and taking corrective actions to deal with emerging constraints and issues. Monitoring and evaluation will constitute the following:

• Implementation progress (physical and financial aspects), monitoring of inputs, and outputs;

• Process documentation (case studies and lessons learnt);

• Impact evaluation based on sample survey and consultations; and

• Thematic studies.

13.1 Institutional Arrangement for M & E

The Resettlement Policy Framework (RPF) stipulates hiring services of an external agency (third party) for monitoring and evaluation of RAP implementation. This means the project authority through an external agency will carry out monitoring and evaluation from the subsequent month of the mobilization of RAP IA at project site. Internal monitoring will be carried out by the Social Officer of Project Coordination Unit (PCU) with assistance from R&R officer and RAP IA whereas external monitoring and evaluation will be carried by the third party engaged for the purpose. This will help

MORTH TCPL CH - 13/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

monitor project activities closely. Regular monitoring by undertaking site visits and consultations with PAPs will help identify potential difficulties and problems faced in the implementation and accordingly help take timely corrective measures including deviations, if needed.

Components of monitoring will include performance monitoring i.e., physical progress of the work and impact monitoring and external evaluation. Indicative indicators to be monitored related to performance are provided in the following sections. In case during the project implementation, if some other indicators are found relevant they will also be considered for monitoring.

13.2 Monitoring and Evaluation (M&E) at Project and Sub-project Level

The Resettlement Action Plan contains indicators and benchmarks for achievement of the objectives under the resettlement programme. These indicators and benchmarks will be of three kinds:

(1) Proposed indicators, indicating project inputs, expenditures, staff deployment, etc.

(2) Output indicators, indicating results in terms of numbers of affected People compensated and resettled, training held, credit disbursed, etc,

(3) Impact indicators, related to the longer-term effect of the project on People’s lives.

The benchmarks and indicators will be limited in number, and combine quantitative and qualitative types of data. Some of these indicators may include, percentage of PAPs actually paid compensation before any loss of assets; percentage of PAPs whose incomes after resettlement are better than, or at least same as before resettlement; percentage of assets valued at replacement cost compensation; percentage grievances resolved; and/or percentage of cases to court. The first two types of indicators, related to process and immediate outputs and results, will be monitored to inform project management about progress and results, and to adjust the work programme where necessary if delays or problems arise. The results of this monitoring will be summarized in reports which will be submitted to the World Bank on a regular basis. Provision will be made for participatory monitoring involving the project affected people and beneficiaries of the resettlement programme in assessing results and impacts. The Project Authority will engage services of an external agency (third party), which will undertake independent concurrent evaluations at least twice a year during the project implementation period. At the end of the project an impact evaluation will be carried out as part of the project completion report. Such independent evaluation will focus on assessing whether the overall objectives of the project are being met and will use the MORTH TCPL CH - 13/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

defined impact indicators as a basis for evaluation. Specifically, the evaluation will assess: (i) The level of success (including the constraints and barriers) in land acquisition programme, resettlement plan, and income recovery of the PAPs after they have been displaced from the project affected area, and, (ii) the types of complaints/ grievances and the success of the handling of grievance and public complaints towards the construction of project’s infra-structures, means of redress for assets and lands and the amount of compensation, resettlement, and other forms of complaints.

Summarizing, M&E would be carried out for regular assessment of both process followed and progress of the RAP implementation. The internal monitoring will be carried out by the State PCU by the Land Acquisition cum Social Development Officer with assistance from RAP Implementation Support Agency and a quarterly report will be submitted to MoRTH. Each quarterly report would also be uploaded on the MoRTH website. The external agency (third party) however, would conduct assessment six monthly for each sub-project by undertaking field visits and all other necessary activities including consultations. The six monthly reports would cover detailed information on process and progress of RAP implementation. The report would highlight issues, if any that need attention of the Project Authority and suggest corrective measures that may be followed for better implementation of RAP.

13.3 Process & Performance Monitoring

Process monitoring would enable the project authority to assess the whether the due process are being followed or not, whereas performance monitoring would mainly relate to achievement in measurable terms against the set targets. Monitoring report will also provide necessary guidance and inputs for any changes, if required during the course of the implementation. A list of indicators is given in Table 13.1.

Table 13.1 - Performance Monitoring for RAP Implementation

Sr. Indicators Target Status Achievement Remarks No. (in %) 1 Land acquisition (Private) Notification published u/s 3D Award declared u/s ……. for Land area (ha) Land owners (No.) Compensation disbursed by Competent Authority to land owners (No.) Govt. land transfer (ha) 2 Verification of identified PAPs completed (No.) 3 New PAPs added, if any (who could not

MORTH TCPL CH - 13/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sr. Indicators Target Status Achievement Remarks No. (in %) be enumerated at the time of survey) 4 Consultations held with regard to RAP (dissemination of information, awareness generation, entitlements, HIV/ AIDS, SCHM, etc) – No. 5 Leaflets, containing salient features of RAP, hand bills, fliers and other awareness materials distributed (No.) 6 Measurement of structures likely to be affected completed (No.) 7 Date of formation of DLC 8 Meetings held by DLC for fixing the replacement cost (No.) 9 Valuation of affected properties completed (No.)

10 Micro plan submitted for THs for approval (No.) 10 Identity cum entitlement card issued to PAPs (No.) 11 Consultations held with local community regarding relocation or rehabilitation of CPRs (No.) 12 Estimate submitted for relocation/ rehabilitation of CPRs for approval 13 Agency to carryout relocation/ rehabilitation of CPRs as agreed by the project authority 14 R&R assistances disbursed to PAPs (THs – No. 15 PAPs re-established their shops/ business (No.) 16 PAPs covered under income generation schemes (No.) 17 PAPs provided training for alternate livelihood (No.) 18 CPRs relocated/ rehabilitated (No.) 19 Grievance/ complaints brought to GRC for redressal (No.) 20 GRC meeting held and cases resolved (No.) 21 Various channels of SCHM used by category (No.) 23 Consultation meetings held by LA cum SDO of Project Coordination Unit (PCU) (No.)

13.4 Evaluation The external agency engaged by the Project Authority shall carry out the evaluation at two stages viz., mid-term and after the completion of RAP implementation. The evaluation will be carried out under a set term of reference. The evaluation study would involve both quantitative and qualitative surveys and compare results before and after

MORTH TCPL CH - 13/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

the implementation of the project. It will focus on assessing whether the overall objectives of the project are being met and will use the defined impact indicators as a basis for evaluation. The evaluation study would undertake the following but not limited to:

• Review monthly progress report submitted by RAP Implementation Agency (RAP IA);

• Undertake consultations with PAPs in order to assess their point of view with regard to overall process;

• Intensity and effectiveness of information dissemination with regard to RAP implementation covering eligibility of different categories of PAPs, frequency of interactions by RAP IA personnel with PAPs, deployment of RAP IA staff, quality of rapport maintained by RAP IA personnel with PAPs, capability of RAP IA personnel, behavior of RAP IA staff, availability of RAP IA staff, level of satisfaction as regards the work of RAP IA, etc;

• Collect information about distribution of awareness generation materials, entitlements, distribution of identity cum entitlement card, adequacy of dissemination of information, consultations meetings with regard to policy and eligibility for entitlement, alternatives and relocation related issues, measurement and valuation of affected properties, understanding and use of grievance procedure, disbursement of assistance, and other R&R related issues, compliance of resettlement policy, etc;

• Conduct sample survey (25% of PAPs) for making comparative analysis substantiated by qualitative surveys and case studies, etc.

It may be noted that one of the key objectives of the project is improvement or at least restoration of economic status of the PAPs to the pre project level. An illustrative list of indicators is given in Table 13.2, which would be measured against the baseline data collected for the preparation of RAP. The M&E agency would finally select the indicators for the evaluation of the project depending upon the progress of R&R activities.

MORTH TCPL CH - 13/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 13.2 - Impact Indicators

Sr. Indicator Unit Before Project During / after No. Implementation RAP Implementation 1 Monthly income of family/household 2 Consumer Durables/ Material Assets owned 3 Ownership of transport and farm implements owned 4 Occupation of head of household and other members 5 Type of dwelling units 6 Number of earning members/household 7 Monthly income of vulnerable households 8 Family under debt 9 Size of loan 10 Households purchased land 11 Households with various sizes of land 12 Ownership/tenancy of dwelling units (owner, encroacher, squatter) 13 Access to water and sanitation facilities 14 Access to modern sources of lighting & cooking 15 Animal & poultry birds owned 16 Migration for employment

13.5 Reporting Monthly Progress Reports on the progress of RAP implementation including mobilization of staff members, opening of site offices, etc of the project would be prepared by RAP IA and submitted to the R&R Officer at sub-project level.

Quarterly Monitoring Reports shall be compiled by the LA cum SDO of Project Coordination Unit (PCU) and submitted to MoRTH for review and onward submission to World Bank

Six monthly reports shall be prepared by the M&E agency by undertaking site visits and review of progress report, consultations, etc.

Evaluation Report shall be prepared by the M&E agency at the end of the project implementation as part of the project completion report.

MORTH TCPL CH - 13/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 14

IMPLEMENTATION ARRANGEMENT AND SCHEDULE

Involuntary resettlement is a sensitive matter to deal with and therefore engagement of experienced RAP Implementation Agency (RAP IA) will be of utmost importance. Experience from projects involving resettlement issues indicates that good rapport with community in general and PAPs in particular help in smooth implementation of RAP. The implementation arrangement necessitates engagement of agency having experience in resettlement issues.

Scheduling of RAP implementation is linked with construction works. As per the standard conditions of civil contracts, land free from all encumbrances will be made available to the contractor. Thus one of the pre-requisites for the start of the construction works is handing over site to the contactor. Delay in handing over sites to contractor after mobilization at site may result in unwarranted claim from the project authority. Upgrading of project road involves land acquisition, dismantling of structures, shifting of CPRs, etc from the proposed right-of-way. The resettlement principles states that compensation and R&R assistances shall be paid before taking over the possession of land for clearing of proposed right-of-way. It is important to note that land acquisition as per the act and transfer of government land through inter-departmental processes invariably takes more time than expected. Thus entire project site (road length) can’t be handed over to the contractor at a time to start the work. Present day road construction works use heavy machinery and less of human labour. Thus unless some reasonable length of project road sections free from encumbrances are not available the construction work can’t be started.

In the Project length land is required to be acquired at total 10 locations out of which 9 locations are each of about 500 m length and in remaining one location of Gangapur bypass land is to be acquired in a length of 2.210 Km. In built up areas in 4 villages structures are required to be removed in a total length of 1.80 Km.

Project Road in 92.15 % of the total length can be readily handed over to the Contractor for starting of the work. Simultaneously RAP implementation activities can be started so that at no point of time because of unavailability of land work is stalled by the Contractor. Table No. 14.1 shows Encumbrance free stretches and the stretches of land acquisition and removal of structures in village.

MORTH TCPL CH - 13/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table14.1- Encumbrance free stretches

Sr. No. Existing Chainage Length Remarks From To (Km) 1 0/00 18/820 18.8 Encumbrance free (EMF) 01 2 18/820 19/120 0.3 Dabar Built Up area 3 19/120 24/250 5.2 EMF 02 4 24/250 24/750 0.5 Pipalai Built up area 5 24/750 27/390 2.6 EMF 03 6 27/390 27/890 0.4 Realignment on 1 LA 7 27/890 35/750 7.9 EMF 04 8 35/750 36/150 0.43 Realignment no 2 LA 9 36/150 46/450 10.3 EMF 05 10 46/450 46/950 0.95 Realignment no 3 LA 11 46/950 49/275 3.5 EMF 06 12 - 51/600 2.210 Gangapur City Bypass LA 13 51/600 56/600 5.0 EMF 07 14 56/600 57/100 0.5 Salempur Builtup area 15 57/100 63/580 6.48 EMF 08 16 63/580 64/100 0.5 Mahmadpura Built up area 17 64/100 73/950 10.0 EMF 09 18 73/950 74/560 0.45 Realignment no. 4 LA 19 74/560 77/960 3.4 EMF 10 20 77/960 78/470 0.5 Realignment no. 5 LA 21 78/470 85/000 6.7 EMF 11

Total Project Length: - 86.620 Km. • L. A. proposed for Gangapur Bypass – 2.210 km • Short realignments at 5 locations - length of 2.79 km • L. A. free length: - 81.62 Km. (94.22% of total project length).

101 structures are likely to be affected in the entire stretch. Dismantling of structures would also be required but at a low scale. Disbursement of compensation and R&R assistance would have to be completed before issuing notice for vacating the place. Mandatory notice period of three months would have to be synchronized with the disbursement and shifting. One of the activities in the process is submission of micro

MORTH TCPL CH - 13/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

plan for approval and release of requisite funds. Based on the site conditions it is proposed that micro plan for all the structures to be affected can be prepared together and submitted for approval. Given the extent of impacts on land and structures it is proposed that Resettlement Action Plan Implementation Agency is mobilized at site simultaneously along with the contractor. The contractor shall be asked to demarcate the land on the ground as per the design. Based on the demarcation, the RAP IA will verify the status of the project affected structures and other properties. Any likely inclusion & exclusion in the list of project affected households shall be initiated at this stage as per the established/defined procedure. It is estimated that activities related to RAP implementation with respect to structures and land along the existing road can be completed in 8 to 10 months. The remaining sections of the existing road can be handed over to the contractor for the work. R&R activities for the Gangapur City Bypass shall be taken up after 6 months from the date of mobilization so that between 12 to 15 months micro plans can be got approved. Micro plan for the bypass shall be prepared separately so that they remain independent from each other keeping in view the complications involved in land acquisition. It is therefore important that mobilization of RAP IA is coordinated with the mobilization of the contractor so that progress of civil works is not affected. A time period of 24 months has been estimated for the implementation of RAP.

Official to be designated as R&R Officer at sub-project level would be in place before the mobilisation of RAP IA. The R&R officer shall be acquainted with RAP and must receive training in order to familiarize with the various aspects of the RAP implementation. Broad understanding of R&R aspects will help better interactions between RRO and personnel of RAP IA and appreciation of activities commenced at site by the RAP IA. Important aspects which need to be understood in resettlement action plan implementation are as under:

• Concept of titleholders, encroachers and squatters,

• Resettlement Policy Framework with specific emphasis on entitlement matrix,

• Stages of land acquisition as per applicable act and disbursement of compensation,

• Preparation of micro plan,

• Institutional arrangements,

• Civil construction works vis-à-vis RAP implementation,

• Development of income restoration plan based on the survey carried out,

MORTH TCPL CH - 13/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• Identification of relocation site for displaced persons, if any,

• Role of various other agencies particularly DRDA and SACO, etc.

14.1 Schedules for Resettlement Plan Implementation

In view the magnitude of the impacts on land, structures and CPRs as indicated above, a time period of 24 months will be needed for the implementation of RAP. The implementation schedule for the major activities of the RAP is presented in the flow chart.

14.2 Implementation Process

The major activities related to the implementation of the resettlement action plan are related to impacts on land, structures and CPRs. The project will provide requisite notice (3 months) to the project affected persons so that they are able to move or take away their assets without undue hardship before commencement of civil works. The implementation of RAP consists of following major activities: • Deployment of required staffs (at Central, State and Sub-Project Level);

• Information dissemination activities by holding consultations, distributing leaflets containing salient features of RPF in local language, etc,

• Finalizing list of PAPs identified by the DPR consultant during the project preparation (RAP) as per the markings on the ground;

• Confirming the status of PAPs (titleholder, encroacher, squatter, etc) with respect existing right-of way;

• Listing and measurement of property and assets affected and their estimation;

• Preparation of micro plan,

• Preparation and distribution of identity card,

• Opening of bank account,

• Disburse of R&R assistance to PAPs,

• Relocation and rehabilitation of CPRs,

• Preparation for relocation of PAPs, if any, etc.

RAP implementation activities to be carried and respective agencies likely to be involved are presented in Table 14.2 & 14.3.

MORTH TCPL CH - 13/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

The activities given in the implementation Schedule are the brief description of the activity statements detailed out as a part of the activity list given in the section on approach and methodology.

MORTH TCPL CH - 13/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 14.2: Activity wise Implementation Schedule - Flow Chart

Sl. Month wise Program Activity No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 A Preparatory Activities Collection and review of RAP Report 1 & other relevant documents Initial consultations with MoRTH team 2 for firming up the activity plan Reconnaissance survey and rapport 3 building with community & district 4 Mobilization of local level staff Training of CRRO and project 5 staff for familiarization with RAP report Preparation and submission of 6 inception report to PIU, PMU and MoRTH Orientation training of project staff on 7 the RAP Submission of Identification and 8 Verification Report for TH and NTH (for existing road/ Bypass) B IEC and Awareness Campaign Preparation and distribution of R&R 9 policy document to the PAPs Organize awareness campaigns for 10 sharing information on RAP Confidence building measures through 11 participatory process Consultation meetings with project 12 staff, contractors and labours

MORTH TCPL CH - 13/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sl. Month wise Program Activity No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Developing messages and training 13 material for awareness on HIV/ AIDS Organize awareness campaigns for 14 construction labours on HIV/ AIDS C Establishment of DLC D Establishment of GRC E Land and Building Valuation Evolving land and building valuation 15 methods Measurement & valuation of land and 16 structures (private /community etc.) Preparation of entitlement/ 17 assistance compensation for the TH & NTHs Photography of EPs for distribution 18 of entitlement- cum- Identity Cards F Micro Plans & Disbursement Preparation of Micro Plans (THs and 19 NTHs) Opening of bank account in joint 20 names for disbursement Informing EPs about entitlement, DLC/ 21 GRC, grievances application, etc Disbursement of entitlement/ 22 compensation/ assistance Community Welfare measures for G SC&ST populated villages

MORTH TCPL CH - 13/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Sl. Month wise Program Activity No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Conducting of consultations for provision of community works in 23 identified SC and ST villages and passing of resolution Preparation of micro plan and 24 approval for community works (in batches) Holding of health awareness, checkup 25 camps and other events under community works Information regarding jobs and provision of labor opportunities by 26 Contractor with preference to vulnerable PAHs and Tribals - Intermittently H Rehabilitation Process Livelihood analysis/options for PAPs/ 27 PDPs Identification of training Needs 28 (Training Needs Assessment)

Formation of Savings/ Self Help 29 Groups (SHGs)

Vocational, skill up gradation trainings 30 based on the micro plans etc. I Monitoring and Evaluation J Completion Process 31 Submission of Completion Report

MORTH TCPL CH - 13/8

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 14.3 - Resettlement Activities vis-à-vis Agencies

Activities Agency Associated with Responsible Land Acquisition : Competent Authority MoRTH, PCU, as per NH Act PIU & RAP IA Institutional Arrangements : Mobilization of RRO at sub-project level : PIU PCU (Designated) Appointment of RAP IA for RAP : MoRTH PCU Implementation Mobilization of RAP IA at site : MoRTH PCU Formation of GRC : PCU/ PIU RRO & RAP IA Training of LA cum Social Development : PCU MoRTH Officer & RRO Formation of DLC for fixing replacement : -do- RRO & RAP IA value Engagement of external M&E agency : MoRTH - Implementation : Finalizing list of PAPs, listing & : RAP IA RRO measurement of structures, categorization of PAPs, etc Preparation of leaflets containing salient : RAP IA RRO features of RPF including entitlement matrix, information brochure, other information dissemination materials in Hindi language Dissemination of information and : RAP IA RRO consultations (at regular intervals) Dissemination of project progress : PCU RRO & RAP IA information and consultations Preparation of micro plan and approval : RAP IA Verification of micro plan : RRO - Approval of micro plan : PCU - ID Card preparation and distribution : RAP IA RRO Opening joint account of PAPs : RAP IA RRO Payment of R&R assistances in : RAP IA RRO transparent manner Clearance of RoW for civil works : RAP IA RRO Identification and training of PAPs for : RAP IA RRO & PCU income restoration Relocation of PAPs, business units, etc. : RAP IA RRO Holding awareness camps with regard to : RAP IA RRO HIV/AIDS, road safety and other aspects Consultations for relocation / rehabilitation : RAP IA RRO & Local of CPRs Admin. MORTH TCPL CH - 13/9

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Activities Agency Associated with Responsible Identification and finalization of community : RAP IA RRO & DLC facilities to be provided as value addition All other activities related to RAP : RAP IA RRO implementation Internal monitoring : PCU RRO & RAP IA External monitoring and evaluation : M&E Agency PCU, RRO, RAP IA Preparation of RAP implementation : RAP IA completion report & withdrawal

Consultations with project affected persons and other community members will be organized by the RAP IA. Consultations will be carried as per the consultation framework with regard to issues related to resettlement and rehabilitation. PAPs to be displaced shall be gradually prepared for relocation by conducting individual consultation, counseling, group consultations and village level consultations involving Panchayats. Information with regard to resettlement action plan will be provided by the RAP IA to individuals as well as community. Consultations with PAPs will also cover explaining the entitlement; method of calculating the assistance, and mechanism for approaching grievance redress committee, etc. In case of PAPs likely to be displaced would be assisted in self-relocation or assisted relocation at resettlement site after they have been paid compensation and R&R assistances as applicable. Some of the above mentioned activities may however, change sequence due to ground condition and other reasons beyond the control of the project.

Relocation of Common Property Resources (CPRs): There would be impact on 25 common property resources in varying magnitude. CPRs likely to be affected by the widening and upgrading of project road include government, community, religious and other structures. Religious structures include temple, dharamshala, handpumps, well etc., Government structures include government offices, schools, passenger shelter, etc. Consultations with local people indicated that relocation of religious structures may be done but utmost efforts should be made to avoid religious and community structures as far as feasible. RAP IA’s role in resolving the contentious issues like relocation of religious and community in consultation with local people would be vital. CPRs affected by the project will be restored with value addition at project cost. Valuation of property affected shall be carried out by the certified valuer. Budget for replacement or relocation of CPR or provision of new resources shall be worked out by the valuer. It would be known at the time of RAP implementation when the proposed ROW is marked on the

MORTH TCPL CH - 13/10

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

ground. The RAP IA will identify land for relocation of CPRs in consultation with local community preferably the government land or village land. Consultations held with local community with regard to each CPR would be properly documented by way of signature of participants, video recordings of consultations, etc. After the agreement on modalities of relocation of CPRs, a document stating the details of items agreed shall be prepared by the RAP IA and shall have signatures of community members, their leaders, representative of RAP IA and RRO. The RAP IA will prepare micro plan for each CPR and submit to project authority for approval. After the approval, necessary actions would be taken by the contractor either through a variation order or some other arrangement as may be deem fit.

R&R Assistance Disbursements: Resettlement and rehabilitation assistance to PAPs will be disbursed by the executing agency through RAP IA either by cheque or account transfers. The RAP IA will facilitate the opening of joint bank account of PAPs. PAPs will be informed well in advance by the RAP IA the date, location for the disbursement of cheques. Proper documentation such as, signature or thumb impression of PAP, still photographs of recipient of cheques, etc would be arranged by the RAP IA for record purpose.

14.3 RAP Completion

The resettlement action plan will be considered complete if all the activities mentioned+ envisioned in the RAP is implemented before demobilization of RAP IA and the intended objectives of the RAP are achieved.

14.4 Awareness Creation about HIV / AIDS

HIV/AIDS have attracted the attention of national and international agencies involved in development projects and have committed to fight against it. Studies on HIV/AIDs have revealed that the disease is more prevalent among the poor, marginalized groups, sex worker, drug users, migrant labors, and truck drivers. These groups, particularly truck drivers who are always on the move carry the infection from one place to another place thereby spreading the infection to other areas.

The RPF provides for measures to increase awareness among target groups and others along the project road. Information and education campaign on HIV/AIDS and other sexually transmitted diseases (STDs) will be conducted by the RAP IA during the RAP implementation period. The campaign will target the construction workers at labour camps, truckers at parking places, general people near markets/haats and other strategic locations along the road. The RAP IA will develop network with State AIDS

MORTH TCPL CH - 13/11

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Control Society and other relevant agencies working for the prevention of HIV/AIDS. Hand bills, brochures, leaflets meant to create awareness about HIV/AIDS and risk/danger involved shall be printed in local language and distributed to target groups. Posters, hoardings indicating prevention from HIV/AIDs shall be displayed at suitable locations for the benefit of general people. Also some innovative measures will be adopted to increase awareness among target groups from time to time.

MORTH TCPL CH - 13/12

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 15

LIVELIHOOD RESTORATION AND INCOME GENERATION PLAN Involuntary resettlement is an inevitable outcome of development-induced displacement. It disrupts livelihood and sometimes source livelihood is completely lost. In many cases, impacts on existing properties, assets and resources lead to impoverishment. One of the main objectives of the RAP is to restore livelihood conditions of the PAPs at pre-project level; if not enhanced. It is therefore important that the project includes income restoration mechanism. Generally, R&R has been limited to payment of compensation and some training for skill up-gradation to support income generation activities which usually provide relief for a short duration. There has been an increasing realisation of the fact that livelihoods assistance under the project is not enough and R&R activities must endeavour for income restoration measures aimed at long term sustainability. The RPF provides for livelihood restoration and also covers strategy to be adopted for income generation on a long term basis.

15.1 Measures to Reduce Impacts on Livelihood

The CoI in built-up sections of the project road has been limited to 15 to 16 m so as to minimize impacts on road side establishments. Similarly, in open areas as far as possible existing right of way has been utilized to minimize land acquisition. Further, bypass have been provided at one place (Gangapur City) to avoid large scale impacts on structures and thereby impacts on livelihood.

15.2 Income Restoration Measures under the Project

The entitlement matrix in the RPF provides for income restoration for those whose livelihoods are likely to be affected. Both THs and NTHs including sharecroppers, agricultural, labourers and employees will be eligible for livelihood assistance as under:

• Monthly subsistence + transitional allowance equivalent to twenty-five days minimum agricultural wages per month for a period of one year from the date of displacement (para 7.16 of NRRP-2007). (PAPs covered under 1(f), 2 (f) and 5 (e)(i) above would not be eligible for this assistance).

• Training Assistance of Rs 10,000/- for income generation per family.

• Temporary employment in the project construction work to project affected persons with particular attention to vulnerable groups by the project contractor during construction, to the extent possible.

MORTH TCPL CH - 15/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

15.3 Income Restoration Strategy

Livelihood restoration has been provided in the entitlement matrix of RPF. Besides, the project will provide income generation opportunities by way of skill development training and linkage with the on-ongoing government schemes. RAP IA with support from PIU will assist PAPs in making a choice for feasible income generation activities. Market feasibility study and training need assessment shall be undertaken by the RAP IA to choose the most viable and promising income restoration programs for PAPs. The RAP IA will play a proactive role to mobilize various government schemes in the concerned districts for the benefit to PAPs, particularly BPL, WHH and other vulnerable groups through self-help groups (SHGs) and project beneficiary groups (PBGs) or individually. The RAP IA will work with the PAPs and line department of the concern districts to dovetail these programs to benefit PAPs. RAP IA shall prepare social action plans detailing out specific activities to be undertaken by them in consultation with the PAPs and concerned departmental officials.

15.4 Disruption of Livelihood of PAPs

Based on socio-economic survey it is observed that socio economic conditions of about half of the project affected households is poor and have limited capacity to benefit from the livelihood opportunities created under the projects or any government sponsored programme.

Upgrading of project road would disrupt livelihoods of those involved in commercial activities and also of land owners whose land would be acquired for bypass mainly. Upgrading of project road two lane standards is likely to disrupt livelihood of 101 households and Seventy one land owners in the bypass. Land acquisition is also proposed along the existing road but the land width required is limited (less than 20% of the area of individual land plot) and might not affect the livelihood of land owners. In case of bypass, 30 m of land width is required.

A large majority of the PAHs likely to be affected preferred cash compensation and assistance as income restoration options during consultations. More than 70% of the PAHs indicated preference for work opportunities during construction stage that they would prefer to continue with the existing occupation (Table -15.1)

MORTH TCPL CH - 15/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Table 15.1 Income Restoration Assistance

Land Structure Income Total Restoration Owner Owner Tenant Options No. % No. % No. % Nos. %age Employment Opportunities in 47 66.20 73 73.00 1 100 121 70.35 Construction work Assistance/ Loan from other ongoing 0 0 14 14.00 0 0 14 8.14 development scheme Vocational Training 0 0 0 0 0 0 0 0 Others 0 0 3 3.00 0 0 3 1.74 Don’t’ know 24 33.80 10 10.00 0 0 34 19.77 Total 71 100 100 100 1 100 172 100

15.5 Skill Mapping

PAPs eligible for income restoration include land owners and businessmen. It is important that PAPs are able to regain their livelihoods. One of the aspects for income restoration activities involves skill mapping of PAPs whose livelihoods are likely to be affected. RAP IA engaged for the implementation of RAP will conduct survey among the PAPs whose livelihood will be disrupted for skill development. Thereafter, skill development options linked to the resource base of the area and availability of market shall be discussed with PAPs. PAPs will opt for certain skill development training. RAP IA in consultation with the PAPs, R&R Officer at project site, district administration and other stakeholders in institutional financing and marketing federations will prepare IR plan/proposal for PAPs. The proposal will be submitted to project authority for approval. Upon approval, the IR activities will be started by the RAP IA. The scope of work of the RAP IA to be engaged for the implementation of RAP will include all the above aspects related income generation/restoration activities for PAPs. In case of upgrading agriculture productivity, the training on technical know-how will be arranged with suitable agencies. PAPs will be persuaded to participate in developing feasible long- term income generating schemes instead of short-term arrangements.

Government of India along with the State Governments runs various poverty alleviation programmes through DRDA. Participation of PAPs in those schemes will be helpful for short-term IR gains. RAP IA with help from PIU (Project Authority) will facilitate inclusion of PAPs in the government sponsored poverty alleviation programmes in the area as per MORTH TCPL CH - 15/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

the eligibility criteria of the respective programmes. The existing programmes are target oriented and have enough funds for new beneficiaries. In several cases, funds far exceed the targets. Some of the ongoing poverty alleviation programmes are Rajasthan Rural Livelihoods Development Project, Swarnajayanti Gram Swarozgar Yojna (SGSY), Jawahar Gram Samridhi Yojna (JGSY), Mahatma Gandhi National Rural Employment Guarantee Scheme, etc.

15.6 Income Restoration Plan

Steps in income restoration will involve segregation between (i) Land based economic activities, and (ii) Non-land economic activities. RAP IA along with PAPs shall participate in developing a range of feasible long-term IR options. Long-term options are affected by the magnitude of impacts. The long-term options are government financed; therefore no separate budget is required. However, in R&R budget provision has been made for the expenses to be incurred towards the coordination between project and concerned departments. RAP IA with help from project authority will coordinate with various agencies of the concerned district for long-term income restoration scheme. Some of the non-land based economic activities are discussed under:

Allied Agriculture Activities: Under allied agriculture activities, various IR options are available viz., dairy, poultry, goatery, sheep rearing, piggery, etc. PAPs who are agriculturist can take up any of these options. These will require training, which can be imparted by Khadi Village Industries Commission (KVIC) & District Dairy Development Authority (DDDA) and milk route for daily milk collection can be extended by local milk federation.

Petty Traders: Under this scheme, the available options are grocery shop, vegetable & fruit shop, stationary, clothe, tea & snacks, ready-made garments, beetle shop etc. PAPs those who are already in the trade and business are suitable for these activities. The PAPs will opt the type of shops to be established as per demand in consultation with RAP IA.

Skill Related Schemes: The options available under this scheme are tailoring, carpentry, masonry, gold smith, black smith, motor winding, cycle and auto repair, driving, electronic items and watch repairing, pottery, leather works, etc. PAPs those who are in such trades can undergo training for skill upgradation to supplement their annual income. District Industries Centre, Industrial Training Institutes, etc impart such trainings. Training can also be imparted through professional and competent outside agency especially hired for the purpose.

MORTH TCPL CH - 15/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Other Schemes: Other schemes include loan for various agriculture implements to increase productivity viz., pump sets, dug well, bore well, bullock cart, etc. PAPs those who are into agriculture and do not have any irrigation facilities can avail such loans. Such loans are given by bank after District Rural Development Authority processes the applications.

Extending financial credit support is an important component for non-land based IR schemes. It requires organization of credit camps for PAPs. The RAP IA will facilitate organize credit camps with support from project authority and district officials. PAPs will be encouraged and persuaded to attend the credit camps and collect as much information as possible regarding the entire process of availing credits. Similarly, the representative of the financial institutions will be to provide detailed information to PAPs about the credit options and how to avail credits expeditiously.

15.7 Training

One of the strategies for economic sustenance of the PAPs is to help them improve their production level or to impart new skills+up-grade skills through training. As quite a significant number of PAPs are dependent on agriculture and others have no skill endowment, training is an important component of income restoration. For PAPs who intend to diversify their economic activity, suitable income restoration schemes will be identified on individual basis and training need would be assessed. Besides training in scheme specific skills, general entrepreneurship development will also form part of the training programme, mainly to improve the management capabilities of PAPs.

Trainings are regularly conducted by District Rural Development Agency (DRDA) through its programme names Training of Rural Youths for Self Employment (TRYSEM). Project authority will ensure that PAPs receive training in desired trades. The RAP IA will facilitate training by suitable agency such as DIC, KVIC, ITDA, ITI, etc. or a professional and competent outside agency. The monitoring of IR schemes will be carried out along with the monitoring of other components of RAP by the external monitoring and evaluation agency.

MORTH TCPL CH - 15/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 16 GENDER PLAN

16.1 Introduction

The socio economic profile of the three districts and project affected households reveal significant gender gap in literacy, sex ratio, work force participation and access to basic facilities. Low awareness level coupled with insignificant role in decision making at household and community level further poses constraints for women and other vulnerable groups to access the opportunities created by the project equitably.

Like in many other infrastructure projects, this project is also likely to have differential impact on women and other vulnerable groups. For example, changes caused by relocation would not have equal implications for members of both sexes and may result in greater inconvenience to women. Due to disturbance in production systems, reduction in assets like land and livestock, women and marginalized and vulnerable groups may have to face additional challenge of running a household on limited income and resources. This may force women as well as children to participate in involuntary work to supplement household income, which may also lead to deteriorate social network of women and men alike hence making them more vulnerable to both social and environmental hazards. It is therefore important to assess status of project affected women, their potential impacts, and accordingly, design an appropriate strategy.

16.2 Potential Project Impacts on Women

The status of women in project districts as compared to men is marginalized. Women are dependent on male members of the households. Households headed by women do not enjoy similar status as their counterpart. The project influence area is a male dominated society and women have very less role to play. Marginalization of women was observed during census and socio-economic survey and public consultation meetings. Only in the absence of male members of the household women members responded to surveys and in public consultation meetings women present in the meeting maintained low profile excepting a few places. Group consultations with women also did not bring out specific concerns except for compensation and financial help from government, and possibility of increased number of accidents, etc. Similarly, it was also pointed out that upgrading of project road will facilitate access to health and education facilities for women and girl child.

MORTH TCPL CH - 16/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

It is obvious that the project would have differential impacts on men and women. Women being the marginalized group have been considered vulnerable and hence provision of additional assistance has been made in the project.

16.3 Women Involvement in Development Process

Besides, participation of women in the project has been envisaged from the project preparation to implementation stage. It has been envisaged in the following areas:

• In the project preparation stage, participation of women though at a lower scale was made possible during survey and consultation.

• During RAP implementation all project affected women would be consulted from time to time by the women members of the RAP IA. It will not be possible to consult women members of the households otherwise because of the prevailing custom (purdah system). This necessitates presence of female members in the RAP IA team. At least one third members of the RAP IA shall be female. The ToR for engagement of RAP IA shall include this clause as mandatory.

• Compensation for land and assets lost being same for all the affected or displaced families, women headed households (2 Nos. – one losing land and another one losing structure) shall be provided adequate attention and counseling by the RAP IA during RAP implementation.

• The RAP IA will take pro-active initiatives so that women are properly consulted and also invited to participate in group-based activities to gain access to the resources.

• The RAP IA shall make sure that women take part in RAP implementation processes such as issuance of identity cards, opening of bank account, receipt of compensation, etc.

• The entitlement framework has provisions for compensation and assistances towards the losses incurred upon the impacted women headed households by the project.

• Women's participation shall also be ensured for monitoring and evaluation activities.

• The assistances to be provided to women as a vulnerable group should create alternative livelihood for them to ensure their sustainable socio-economic upliftment.

• The implementing agency shall provide trainings for upgrading the skill in the alternative livelihoods and assist throughout till the beneficiaries start up with production and business.

MORTH TCPL CH - 16/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

• Women's participation shall be initiated through Self-Help Group formation in each of the villages affected by the project. These groups should then be linked to special development schemes of the Government, like SGSY.

• Monitoring of project inputs concerning benefit to women will invite their participation that will make the process more transparent to them. Women shall be encouraged to evaluate the project outputs from their point of view and their useful suggestions shall be noted for taking necessary actions for further modifications in the project creating better and congenial situation for increasing participation from women.

16.4 Involvement of Women in Construction Activities

A limited number of high-skilled labour forces will be required for the construction activities. These skilled labour forces are mainly involved in machinery work of road construction. Most of these workers are regular employee with the civil contractor and work with the contractor on a long term basis. These labour force moves with the contractor. The requirement of un-skilled labour forces will be met from the project influence area. Majority of un-skilled labour forces will be from the local area. It is important to mention that seasonal migration from the project influence area to other states take place for employment. Employment in road construction works will be taken by both men and women. Local labour forces are not likely to stay in labour camps as majority of them will be commuting from their home. Whereas women members of the skilled and semi-skilled labourers will be staying in the construction camps and some of them will also be directly/indirectly involved in the construction. The families of these labour forces include their children also. There will be involvement of local women also in the local labour force. Foreseeing the involvement of women both directly and indirectly in the construction activities, certain provisions have been made for the welfare of women and children, in particular during the road construction work.

16.5 Provisions for Women in Construction Camp

Temporary Housing - Families of labourers /workers shall be provided suitable accommodation during the construction work at labour camp site. The size of the room shall be as per the standard. In case of non-availability of standards, a design for the same will be prepared by the contractor. The design will be duly approved by the construction supervision consultant. Rooms for such families will be constructed as per the approved design.

Health Centre - Health problems of the workers shall be taken care of by providing basic health-care' facilities through health centres temporarily set up

MORTH TCPL CH - 16/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

for the construction camp. The health centre shall have at least a visiting doctor, nurses, general duty staff, free medicines and minimum medical facilities to tackle first-aid requirements or minor accidental cases, linkage with nearest higher order hospital to refer patients of major illnesses and critical cases. The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart from this, the health centre shall provide with regular vaccinations required for children.

Day Crèche Facilities - It is expected that among the women workers there will be mothers with infants and small children at the construction site. Provision of a day crèche may solve the problems of such women who can leave behind their children in such crèche and work for the day in the construction activities. The crèche should be provided with at least a trained ICDS (Integrated Child Development Scheme) worker with 'ayahs' to look after the children. The ICDS worker, preferably women, may take care of the children in a better way and can manage to provide nutritional food (as prescribed in ICDS and provided free of cost by the government) to them. In cases of emergency, she, being trained, can tackle the health problems of the children and can organize treatment linking the nearest health centre.

Scheduling of Construction Works - Owing to the demand of a fast construction work it is expected that a 24 hours- long work schedule would be in operation. Women shall be exempted from night shifts.

Education Facilities - The construction workers are mainly mobile groups of people. They are found to move from one place to another taking along their families with them. Thus there is a need for educating their children at the place of their work. For this, access to primary schools at least should be ensured for these children. Wherever feasible, day crèche facilities could be extended with primary educational facilities.

Measures for Controlling STD and AIDS - Solitary adult males usually dominate the labour force of construction camps. They play a significant role in spreading sexually transmitted diseases. In the construction camps as well as in the neighboring areas they are found to indulge in physical relations with different women. This unhealthy sexual behavior gives rise to STDs and AIDS. While it is difficult to stop such activities, it is wise to make provisions for means of controlling the spread of such diseases.

Awareness camps for the target people, both in the construction camp and neighboring villages as well, and supply of condoms at concession rate to the male workers may help to a large extent in this respect for controlling the deadly disease.

MORTH TCPL CH - 16/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

The Civil Works Contractor shall be responsible for the above interventions to the maximum extent possible and suitable provisions in this regard are incorporated in the bid document.

Women as Managers in the RAP IA - The services of RAP IA will be procured to implement the RAP. It is proposed that the quality to be considered and/or selected for such contracts, the RAP IA must fulfill the following conditions.

That the RAP IA must propose at least one woman as part of the key personnel. The proposed women key person shall be available to work at site for at least 50% of the duration of the contract.

That the women key persons, if selected for the contract, may be replaced during the period of contract, only with women key persons of equivalent or better qualifications and experience.

That the RAP IA will depute a 'technical/sub-professional' team to work at the site, which will consist at least 33% of women members. Junior support personnel and administrative staff will not be considered as technical/professional.

16.6 Women as Members of the Consultant Teams for RAP Evaluation

Mid and end term evaluation of the RAP component will be carried out by the external agency engaged by the MoRTH. It will be ensured that the external agency engaged to carry out monitoring and evaluation have at least one woman member as part of the team.

MORTH TCPL CH - 16/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Chapter – 17 TRIBAL DEVELOPMENT PLAN

17.1 Tribal Scenario in the Project Area

The project influence area covers Dausa, Sawai Madhopur and Karauli districts. The ST population in these districts ranges from 22.4% to 26.8%. The project road does not pass through any notified schedule area of the State. ST population is less than 5% of the total population of the corresponding villages in 26 villages. In 17 villages, ST population however, constitutes more than 25% of the total population of the corresponding village. Of these 17 villages, in four villages almost the entire population belongs to ST. Overall ST population constitutes 15.6% of the total population in rural areas and 3.2% of the total population in the urban areas, see Annex 3.4

ST comprises 3.5% of the project affected households as per census and socio-economic survey. The survey identified 6 schedule tribe titleholder households (4 land owners & 2 structure owners) along the project road.

17.2 Methodology used to Assess Tribal Issues

Structured questionnaires, open-ended formats, group discussion were used to assess the impacts. The data collected through socio-economic survey and census survey was another source of information for social assessment of tribes. Consultations was carried out with the likely affected tribal population in a culturally appropriate manner in different modes – one on one interaction during household survey and group meetings along with other PAPs. All of these consultations were free, prior, and informed to the affected tribal people.

The language spoken by the affected tribal households is Rajasthani which is similar to the general population along the project road. No unique socio-cultural practices were reported during the one to one interviews.

Six titleholder tribal households are likely to be affected. Semi-pucca residential structures of these two households will be affected. These structures are likely to be affected only partially and hence they will not be displaced from the existing location. Since the affected tribal families is very limited and scattered, their views were recorded through one to one interviews and village level meetings. The concerns raised were no different from the concerns raised by the general community.

17.3 Impact Mitigation Measures

The objective of the Tribal Development Framework in the RPF is to design and implement projects in a way that fosters full respect for Indigenous Peoples’ dignity, human rights, and

MORTH TCPL CH - 17/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

cultural uniqueness and so that they: (a) receive culturally compatible social and economic benefits; and (b) do not suffer adverse effects during the development process. Mitigation measures proposed below are in line with the objectives of this framework.

17.4 Compensation and R&R Assistances

Compensation and R&R assistances shall be provided for the identified impacts on structures based on the Resettlement Policy Framework. Additional provisions made in the entitlement framework for the project are:

The affected CPRs shall be relocated or restored in consultation with the community in compliance with the RPF.

i) Additional/ new community facilities will be provided in certain habitations along the project road as value addition to the project. Details of these community welfare facilities/works are given below:

i. Criteria: The criteria for selection and implementation of works would be as follows: a. Habitations which have high percentage (> 50%) of SC & ST population would be selected for providing community facility/works; and ; b. Community works shall be those that strictly benefit the larger section of the village rather than an individual or a small group/section of individuals c. The activity should not be already covered under some existing government scheme; d. An indicative list of works are: a. Provision of boundary wall for education and health facilities, community building, religious structure; b. Provision of furniture for school and health facilities c. Provision of shelter for bus stand; d. Hand pumps or repair to hand pumps; e. Repair of dug-well, other village community infrastructure; and f. Platform for meeting place of village community or women g. Repair works, leveling, etc. of internal paths ii. Process: In selected habitations implementation support agency shall hold consultations with community /villagers to ascertain the need and benefit of any community good. The villagers will decide as to what type of community facility is needed in their habitation unanimously. A resolution in this regard will be passed by the villagers following the official procedure which will then be submitted to the Project Authority. The resolution shall contain details

MORTH TCPL CH - 17/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

a. on the nature and type of community work requested; b. the likely benefit accrued; c. an approximate number of persons who shall benefit from it; d. consensus reached amongst the village community members on the activity; and e. Post Construction management measures by the community f. finally a statement of proposed support and cooperation for the activity with signatures (or thumb-impressions) of the participants

The RAP Implementation Support Agency shall support in documentation of the minutes of the meeting and preparation of the resolution and forward the same to the RRO. The RRO will verify the activity and confirm that all pre-set criteria for such works have been met. Upon approval of RRO and Sub-project level agency, the RAP Implementation Support Agency shall prepare a micro-plan for submission to RRO who shall forward it to SPIU with appropriate justification. The SPIU shall forward the same for approval of MoRTH. MoRTH will review the micro plan that contains the following details: i. Planned community welfare work (s) ii. Location and population of the village, iii. Cost of the activity iv. Intended and likely benefit v. Procurement plan for materials vi. Likely duration for execution of the work(s) vii. Number of labor required viii. Details of Minutes of meeting and resolution passed by the village, ix. Design required, if any

iii. Implementation: Upon approval and sanction of the requisite amount by MoRTH, Sub-project level agency through RRO and RAP Implementation Support Agency will a. get the design prepared, in case it is required b. hold consultations with the community/villagers with the designin presence of the RRO to ensure that modifications or changes suggested by the community/villagers are heard and incorporated. c. The Project Authority will then issue a purchase order for purchase of necessary materials and goods

d. The RAP Implementation Support Agency shall periodically update the RRO on the progress of the works. MORTH TCPL CH - 17/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

e. Upon completion, it shall prepare a Work Completion Report with details of the activity – final actual cost, working condition of the community asset along with photographs;

f. RRO shall visit the site for verification and ensure handing over of the asset to the community prior to approval of the report

g. Upon verification by the RRO and handover of the community work, the RRO shall submit his report to SPIU and MoRTH Monitoring will be done by the Sub-project Agency while the evaluation of the community works shall be undertaken during the end-term evaluation by the agency contracted by MoRTH

An amount for undertaking community works has been provisioned for in the budget (See Chapter 18)

17.5 Other Possible Impacts (Direct and Indirect) to Tribal Populations and Management/ Mitigation Measures

Based on the consultations with the community along the project road, other direct and indirect impacts envisaged during construction are listed in table below. Additional assistance for tribal and other vulnerable groups has been recommended as part of mitigation measures.

Table-17.1 Management/ Mitigation Measures

Phase Likely Direct Likely Indirect Likely Management/Mitigation Measures Impacts Impacts Project Demand for Frustration of • Advise the contractors about the Execution labor Local people not criteria for selecting workers, being included in prioritizing the people in the Project the construction Area as long as they meet the activities technical requirements. Give preference to the vulnerable especially, the tribal population.

• Inform the community in the Project Area about the job vacancies, identifying the number of available positions and the application requirements. This information will be displayed by the offices of the implementing agency, as well as the contractor’s site office. Preference will be given to tribal and other vulnerable

MORTH TCPL CH - 17/4

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Phase Likely Direct Likely Indirect Likely Management/Mitigation Measures Impacts Impacts population.

• The executing agency or their contractors will train the local workers including tribal in the application of environmental, safety, and occupational health provisions, as well as in the knowledge and mandatory compliance of the Workers Code of Conduct.

Increase in the • Contractor to design and implement a expectations of Temporary Hiring Program for the local population local population that will anticipate the and demand of skilled and unskilled work stakeholders. force, the time the employment will last and the requirements the applicant will have to meet to be accepted. Needs of the Tribal population will have to be specially addressed.

• Inform local stakeholders, through local and regional communication media on the location of his offices where they may learn about job opportunities for laborers and the priorities that will be given to local workers. The Tribal welfare officer and the Implementation Support Agency may also be involved for increased participation and information dissemination.

Migration to the • To decrease and control the flow of project area in population or people seeking order to seek employment in the Project area. employment • It must be made clear through the mass media that priority will be given to the people who live in the Project area and especially the vulnerable including ST.

Generation of Increased level • The PIU will consider mechanisms to jobs, as well as of income in the allow purchasing local products, as an increased Project area long as the local market prices remain demand for competitive and are not affected by goods and Stimulation of the company's interest. If there are services (raw local economy any material being sold by a Tribal materials, trader he may be given preference equipment over others rental, food supply, • Offer training to local economic MORTH TCPL CH - 17/5

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Phase Likely Direct Likely Indirect Likely Management/Mitigation Measures Impacts Impacts accommodation agencies for the development of small s, etc.) during and micro enterprises. Training construction of programmes with Tribals will be the road organized.

Conflicts and • Implement a sales system to quarrels determine the best offer regarding between competitive products and services. suppliers and contractors • The grievance redressal committee shall have invited representation from Tribal Welfare Department.

• In other words, implement a sales system designed to locate goods and services at competitive prices, good quality and in amounts required.

The possible Interaction • Wide diffusion of the Project Workers arrival of outside between the Code of Conduct and the workers in the Project workers establishment of sanctions for area (Outside and the women offenders specially for tribal refers to workers from local population who are not populations • All workers and subcontractors must residents/locals be subject to a Social Code of of the area) Conduct. Documentation and diffusion of training and educational programs Risk of traffic Traffic accidents • Provide training for the project accidents caused by working force (contractors and dumping subcontractors) on the Security and construction Health Plan material on the • Sensitization programme on safety site issues for end users and specifically for tribal population • Erect traffic signals in the critical areas of the Project. • Provide informative talks for the local population on security measures to reduce risk of accidents. • Establish and inform drivers of the speed limits • Ensure that contractors and subcontractors implement measures to reduce or avoid potential accidents that may affect the population in the area and the project workers themselves • Provide suitable safety measures (speed breakers, rumble strips, signage, etc) near habitations, schools and market places. MORTH TCPL CH - 17/6

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA & RAP

Phase Likely Direct Likely Indirect Likely Management/Mitigation Measures Impacts Impacts • Hire and train security personnel devoted exclusively to preventing accidents in the access road and controlling the speed of the vehicles transporting construction materials.

17.6 Consultation and Participation

As presented, the project does have some minor negative impacts to tribal populations, which are easily manageable. The tribal have extended their support to the project given that the potential negative impacts and risks are properly mitigated or managed, as outlined in this chapter. It is also highly recommended that the tribal are regularly consulted at different stages of project implementation. All communication and information dissemination in the project area shall be done in the culturally appropriate way.

17.7 Implementation Arrangements

The service of RAP and TDP Implementation Agency will be required for 2 years during implement of RAP. It is recommended to give 10% weightage to the RAP and TDP Implementation Agency native to the region for implementation of RAP at the time of hiring. In case the RAP and TDP Implementation Agency that is selected happens to be from outside the region, it would be ensured to include representation from the project area in the team of field professionals. This is to ensure that the RAP and TDP Implementation Agency is sensitive to the socio cultural profile and practices of the project area, particularly scheduled castes and scheduled tribes.

MORTH TCPL CH - 17/7

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

Chapter – 18

RESETTLEMENT BUDGET

The resettlement budget comprise estimated value of compensation for land, structures, trees, crops, various resettlement assistances, cost of CPRs, institutional cost, contingency, hiring of RAP IA for RAP implementation, monitoring and evaluation consultant, etc. The project authority will be release requisite funds covered under resettlement budget in a timely manner. The total resettlement cost for the sub-project is estimated at about Rs. 10.97 Crores including land cost, Table 18.1.

The resettlement and rehabilitation budget has been estimated based on the information, data collected from field and other reliable sources. The budget will be updated and adjusted as per the market rate of various items as the project continues. The compensation amount for the acquisition of land, structures, trees, standing crops etc will be determined by the Competent Authority of the concerned Districts as per the “NH Act 1956” and its amendments. In addition, PAPs will be entitled to R&R assistance in accordance with the entitlement matrix provided in the RPF and its letter and spirit.

The resettlement budget is indicative and has been estimated as per the present rate. The unit costs would be updated and adjusted to the inflation rate as the project continues. Compensation for land will be as per the NH Act 1956. Differential amount between replacement value and compensation amount will be paid by the Project Authority as assistance.

18.1 Land Rate

Land rate varies substantially from one place to another and even within the same villages depending upon the location of land and quality of land. Further, rate of land presently used for commercial purpose is significantly higher than other types of land. During public consultations participants stated prevailing market rate of land in their area. In order to work out the unit cost of land for budget estimation, land market survey was conducted in the project corridor. The survey involved discussion with a large number of local people. Land rate stated by affected persons and other stakeholders. Based on the exercises conducted the average prevailing market rate of land was found to be higher than the rate at which lands are being transacted. During consultations participants accepted that land is transacted at much lower rate than the prevailing market rate in order to save registration fees. Government approved rate per decimal for land for concerned villages is provided as Annexure- 18.1.

MORTH TCPL CH - 18/1

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

Land area likely to be acquired in each revenue village has been multiplied with the land rate then and then 50% and 60% has been added to arrive at the estimated budget for land acquisition.

18.2 Replacement Value of Structure

The unit cost of pucca, semi-pucca and katcha structure is based on the consultations and discussions with the local people. The replacement cost of one unit of structure on an average is 15-20% higher than the government rate of structure. The compensation amount of structure will be calculated without depreciation. Actual valuation of structure would be carried out by certified valuer during the RAP implementation and the differential amount between the replacement value and the compensation amount will be paid by the Project Authority as assistance. The unit cost of structure considered for the purpose of budget estimation is as under:

♦ Pucca structure/sqm – Rs. 5000/-

♦ Semi-pucca structure/sqm – Rs. 2500/-

♦ Kutcha structure/sqm – Rs. 1200/-.

18.3 Compensation for Trees & Standing Crops

Compensation for trees and damage to standing crops in private land will be in accordance with the Act. Loss of timber trees will be compensated at their replacement cost while the compensation for the loss of fruit bearing trees will be calculated as annual produce value calculated for the number of years (as per standard procedure followed by concerned department) depending on the nature of trees/crops.

18.4 Budget

Resettlement and rehabilitation budget is given in Table 18.1. The budget is indicative and shall be updated and adjusted during the course of implementation of Resettlement Action Plan. The total budget for resettlement action plan has been estimated at Rs. 10.21 Crores which covers compensation for land, physical assets affected and various resettlement and rehabilitation assistance including restoration of livelihoods. Out of the total resettlement budget land acquisition alone comprises 60.65% of the total resettlement budget followed by compensation cost of structures likely to be affected (15.07%). R&R assistance, institutional cost, awareness programme and capacity building of executing authority etc constitute 9.75% of the total resettlement budget.

MORTH TCPL CH - 18/2

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

Table 18.1 - Estimated Budget for Resettlement and Rehabilitation

Sl. Amount in Items Unit Rate (Rs.) Quantity No. Crore Rs. 1 Compensation i Land Dausa Ha 0 0.00 0.00 Sawai Madhopur Ha 4496097 11.33 5.09 Karauli Ha 1644232 4.05 0.67 Sub-total 15.38 5.76 ii Structure Pucca Sqm. 5000 502.59 0.25 Semi-Pucca Sqm. 2500 1605.69 0.40 Kutcha Sqm. 1200 588.03 0.07 Sub-total 2697.31 0.72 2 R&R Assistance Partially affected structures and the remaining structure continue to be viable No. 3500 73 0.03 additional 25% of compensation amount as restoration grant. Monthly subsistence/ transitional allowance equivalent to 25 days minimum agricultural No. 175 28 0.15 wages/month for a period of 1 year from the date of displacement Shifting allowance No. 10000 28 0.03 Each affected person who is a rural artisan, small trader or self-employed person and who has been displaced (in this project owner of any residential–cum commercial No. 25000 28 0.07 structure) shall get a one-time financial assistance of Rs 25,000/- for construction of working shed or shop House construction assistance of Rs. 10,000 for families belonging to vulnerable No. 10000 75 0.075 group will be provided Compensation for standing crops and trees LS 0.25

Monthly subsistence/transitional allowance equivalent to twenty-five days minimum No. 175 28 0.15 agricultural wages per month for a period of one year from the date of displacement Training Assistance of Rs 10,000/- for No. 10000 28 0.03 income generation per family. Economic Rehabilitation Grant (One time additional financial assistance) equivalent 52500 No. 75 0.39 to 300 days of minimum wages to all (300x175) vulnerable Financial assistance equivalent to two hundred days of minimum agricultural 35000 (200 wages for STs No. 6 0.021 x 175)

MORTH TCPL CH - 18/3

SIA & RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan DRAFT SIA & RAP

Sl. Amount in Items Unit Rate (Rs.) Quantity No. Crore Rs. Relocation cost for CPRs LS 200000 25 0.50 Provisional sum for value added community works for villages with ST and LS 0.3 SC population Sub-total 1.996 3 Institutional Cost (RAP IA) LS 0.80 4 Awareness on HIV/AIDS LS 0.20 5 Capacity building of executing agency 0.10 6 Cost of External M&E agency LS 0.30 Dissemination of project information and 7 LS 0.10 project progress by PCU Sub-total 1.50 Total 9.976 8 Contingency (10% of Total) 0.998 Grand Total 10.974

18.5 R&R Assistance Disbursements

Resettlement and rehabilitation assistance to PAPs will be disbursed by the executing agency through RAP IA either by cheque or account transfers. The RAP IA will facilitate the opening of joint bank account of PAPs. PAPs will be informed well in advance by the RAP IA the date, location for the disbursement of cheques. Proper documentation such as, signature or thumb impression of PAP, still photographs of recipient of cheques, etc would be arranged by the RAP IA for record purpose.

MORTH TCPL CH - 18/4

Annexure - 2.1

Census and Community Asset Survey Schedules Census Survey Questionnaires

PART: 1 – ASSET INFORMATION

Census Survey Code.

GENERAL A. Questionnaire No: ………B. Subproject Road Name: ......

C. Village: ……..………………D. District: ………………….E. State: ……………

F. Plot No...... G. Km/Chainage……….H. Side 1. Left 2. Right

I. Name of the person answering to survey…………………………………………………………….

J. Relation to the owner:…………………………………………………………………………………..

K. Years of Occupation of the Affected Property _____ Years

L. Present Address of the Property: ______

M. Mother Tongue ______(Hindi-1; Odiya-2; Others-3; in case of others specify.)

DETAILS OF LAND 1. Ownership of the Land 1. Private 2. Government 3. Religious 4. Community 5. Others 2. Type of Land 1. Irrigated 2. Non-Irrigated 3. Barren 4. Forest 5. Other 3. Use of Land 1.Cultivation 2. Orchard 3. Residential 4. Commercial 5. Forestation 6. Others 7. No Use/ Barren 4. Affected area of the Land (in square meter) ...... 5. Total Area of the Land/Plot (in square meter) ...... 6. Rate of the Land (Per sq. m) 1. Market Rate (Rs)...... ……………….. 7. Status of Ownership 1. Titleholder (Pvt Owner) 2. Customary Right 3. Encroacher 4. Squatter 8. Name of the Owner/Occupier: ……………...... 9. Father’s Name: ...... 10. Name of the owner, if the occupier is tenant……………………………………….…………………………………….. …………………………………………………………………………………………………………………………… ……………………………..… 11. Total Land Holding (in Acre) ………………………………………….. Annexure - 2.1

12. Any of the following people associated with the Land A. Agricultural Laborer 1. Yes 2. No (i). If Yes then How many ……………………………………………………..….. B. Sharecropper 1. Yes 2. No (ii). If Yes then How many …………………………………………………………… 13. Number of trees within the affected area 1. Total………………2. Fruit Bearing………………3. Non-fruit Bearing………………

DETAILS OF STRUCTURES (cross check with part III) 14. Any structure in the Affected Land 1. Yes...... 2. No...... 15. Area of the affected structure (in Square Meter) a) Length along the road...... …b) Width perpendicular to the road...... …...c) Floor ……… 16. Area of the total structure (in Square Meter) a) Length along the road...... b) Width perpendicular to the road...... ….c) Floor ……… 17. Distance of structure from center line of the road (in mtr.)………………………… 18. Type of Construction of the Structure 1. Temporary (buildings with mud/brick/wood made walls, thatched/tin roof) 2. Semi-Permanent (buildings, with tiled roof and normal cement floor) 3. Permanent (with RCC, Single/ Double storey building) 19. Market Value of the Structure (in Rs.)...... 20. Use of the Structure (select appropriate code from below) A. Residential Structure 1 House 2 Hut 3 Other ……….. B. Commercial Structure 4 Shops 5. Hotel 6 Small Eatery 7 Kiosk 8 Farm House 9 Petrol Pump 10 Clinic 11 STD Booth 12 Workshop 13 Vendors 14 Com. Complex 15 Industry 16. Restaurant 17. Others………. C. Mixed Structure 18 Residential-cum-Commercial Structure D. Community Structure 19 Comm. Center 20 Club 21 Trust 22 Memorials 23 Other…. E. Religious Structure 24 Mosque, 25 Shrine 26 Burial 27. Temple 28. Other… F. Government Structure 29 Govt. Office 30 Hospital 31 School 32 College 33 Other ………… G. Other Structure 34 Boundary Wall 35 Foundation 36 Cattle Shed 37 Well/Tube Well 21. Status of the Structure 1. Legal Titleholder 2. Customary Right 3. Encroacher 4. Squatter 22. Name of the Owner/Occupier: ……………...... 23. Father’s Name: ...... 24. Name of the owner, if the occupier is tenant………………………………………………………….. …………………………………………………………………………………………………………………… a. Tenure Status…………………………………………….. (Own-1; Rented-2; Leasehold-3) b. Monthly Rent……………………………………………… c. Utility Connection…………………………………………(1-Electricity; 2- Water; 3- Sewer) 25. Any of the following people associated with the Structure? A. Employee/wage earner in commercial structure 1. Yes 2. No (i). If Yes, How Many?…………………………………………………….. Annexure - 2.1

B. Employee/ wage earner in residential structure 1. Yes 2. No (ii). If Yes, How Many?.…………………………………………………….. 26. Number of trees within the affected area 1. Total………………2. Fruit Bearing………………3. Non-fruit Bearing……………… 27. Social Category 1. SC 2. ST 3. OBC 4. General 5. Others (specify)………………………… 28. Religious Category 1. Muslim 2. Hindu 3. Other (specify)………… 29. Vulnerability Status of the Household: A. Is it a woman headed household? 1. Yes 2. No B. Is it headed by physically/mentally challenged person? 1. Yes 2. No C. Is it a household Below Poverty Line (BPL) 1. Yes 2. No D. If BPL, provide BPL card number------30. Monthly income of the family in (Total of Q.No. 36) Rs.…………. Resettlement and Rehabilitation Option 31. Willing to shift 1. Voluntarily 2. Non-voluntarily 32. Assistance Option 1. Self Relocation 2. Cash for Land loss 3. Cash for House/ Shop loss 4. Project Assistance 33. Income Restoration Assistance (The most preferred option) 1. Employment Opportunities in Construction work 2. Assistance/ Loan from other ongoing development scheme 3. Vocational Training 4. Others (specify ...... )

34. Other Support from Project (Specify)......

Part II SOCIOECONOMIC DETAILS

35. Name of the Head of the Household………………………………………………………

36. Number of family members Total………….Male………..Female………… Details of Family Members above 18 years of age: (fill appropriate code) Annexure - 2.1

Sl. Name of Persons Relationship with Sex Age Marital Educational Main Monthly Other Monthly No Head of the (M/F) Status Qualification Occupation Income Occupation Income Household 1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

Marital Status: Married-1; Unmarried-2; Divorcee-3; Separate-4; Widowed-5; Educational Qualification: Illiterate-1; Primary Schooling-2; Upper Primary Schooling-3; High School-4; Graduate-5; Post-Graduate-6; Technical-7 Occupation : Cultivator-1: Agricultural Labourer-2; Daily Wage Earner-3; Salaried-4; Business- 6; Other-7; in case of others specify. Annexure - 2.1

37. Possession of Material /Assets (Please Record Numbers) Television Tape Radio Refrigerator Telephone Vehicles Cooking Any Other Recorder Gas (specify) Cycles Three Two- Four Bus / Wheeler Wheeler Wheeler Truck

38. Live Stock Assets (Please Record Numbers) Classification Cows Buffaloes Sheep Goats Poultry Others Give Number

39. Likely Loss of Other Assets Tree Well Other Category I (Specify) Individual Assets

No. Species No. Type No.

40. Participation in economic activities of family members S. No. Economic/Non-economic Activities Male Female Both 1 Cultivation 2 Allied Activities (Dairy, Poultry, Sheep rearing, etc.) 3 Collection and Sale of forest products 4 Trade & Business 5 Agricultural Labor 6 Non Agricultural Labor 7 HH Industries 8 Service 9 Households Work 10 Collection of Water 11 Collection of Fuel 12 Others (Specify): Annexure - 2.1

41. Decision making and participation at Household Level

Sl. No. Subject Male Female Both

1 Financial matter 2 Education of child 3 Health care of child 4 Purchase of assets 5 Day to day household activities 6 On social function and marriages 7 Women to Earn for Family 8 Land and property 9 Others

42. Women Participation at Community level

1 Do women of the household participate in decision making processes at Yes- 1 community level No- 2 2 Is any member of the household a member or office bearer of village / block / Male Female zilla panchayat? Yes – 1; No – 2; If yes whether such member is male or female? 3 Is any women member of the household works as Anganwadi worker or ANM? Yes No 4 Is any household member also a member of any self help groups? Yes - ; No -2 Male Female If yes, whether male or female? 5 If yes, is that SHG still active? Yes No

43. Employment opportunity in the area

1. Seasonal 2. Employed throughout the Year 3. None Annexure - 2.1

44. Do family members migrate for work S. No. Type of Work In Rs. Per year Do men migrate for work Do women also migrate for outside the village work outside the village Daily -1 Daily -1 Seasonal - 2 Seasonal - 2 Long term – 3 Long term – 3 No - 4 No - 4 1 Agriculture 2 Shopkeeper/Business (including petty business) 3 Employer (industrialist/Factory/Mill owner, etc) 4 Government Service 5 Private Service 6 Wage Labour (Agriculture) 7 Wage Labour (Non Agriculture) 8 Self employed (insurance, finance, doctor, engineer, lawyer) 9 Not employed (income recipient such as retired, remittance, property rent, bank interest, etc) 10 Household work 11 Others (specify ) Total Annexure - 2.1

45. Quality of Life (Consumption Pattern) Kindly indicate the consumption/expenditure on different items in last one year Sl. No. Particulars Monthly Rank them from highest to Expenditure in Rs. lowest 1 Food 2 Agriculture 3 Housing 4 Cooking Fuel 5 Clothing 6 Health 7 Education 8 Transport 9 Communication 10 Social functions 11 Others

46. Loan and Indebtedness 1 Have you taken any loan? 1-Yes, 2-No 2 Who has taken the loan? 1. Head of the HH; 2. Spouse; 3. Son; 4. Daughter in law; 5.Head and spouse together; 6. Son and Head of the HH; 7. Daughter in law and Mother in law; 8. Other……… 3 If yes, tell us sources of loan: 1-Bank, 2-NGO, 3-Money lender, 4-Relative/friend, 5- SHG; 6. Others (specify……………) 4 If yes, Amount of loan (in Rs.) 5 Could you please tell us the purpose of loan? 1-Productive investment, 2- Purchasing durables, 3-Meeting up emergencies, 4-Marrying of children, 5- Paying off loan, 6-Others (specify………………………)

47. Access to facilities Code Distance of followingfacilities/amenities Approx. Mode to Frequency Trips made from the location of interview? km access by M/F/Both 1 Primary School 2 Secondary School 3 College 4 Regular Market 5 Commonly visited health service place 6 Hospital 7 District Office 8 Block Office Mode: Walk-1; Cycle-2; Personal transport-3; Public transport-4; Frequency: Daily-1; Weekly-2; Monthly-3; Very Rare-4;

48. Health Seeking behaviour 1 Has any of your family members If yes, who Code : suffered from any disease suffered: Men – 1, Women - 2 during last 12 months? Both- 3, Boy child- 4 1-Yes, 2-No, 3-Don’t Know Girl child – 5, Both children - 6 2 If yes, please specify type of disease? 3 Type of treatment taken: 1-Allopathic Government, 2-Allopathic Private, 3-Allopathic Govt. & Private both, 4- Homeopathy, 5- Ayurved, 6- Faith healers; 7- quacks; 8-No Treatment, 9-Others (specify…………) Annexure - 2.1

4 Which is the nearest formal medical facility available? PHC – 1; CHC- 2; District Hospital – 3; Private clinic – 4; Private Hospital – 5; Others - 6 5 Did you avail any health/medical Yes - 1 If coded 1 or 3 skip the next question facility (like medicine, routine No - 2 check-up, advice from doctor Has not been etc.) during the last pregnancy? pregnant yet - 3 6 If no, who attended while giving Females birth to the baby? (Multiple neighbor - 1 responses possible) relatives and friends - 2 Mother-in-law - 3 Sister-in-law - 4 Others specify - 5 7 Have you heard about Yes 1; No - 2 HIV/AIDS: 8 If yes, what is the source? Newspaper – 1; TV- 2; radio- 3; NGO camp– 4; Govt. camp – 5;

Signature of a person Answering the Survey…………………………………

(Name of the Investigator) Date: ...... (Signature of the investigator) Annexure - 2.1

PART III

EXTENT OF LOSS

(NOT TO BE ASKED BUT TO BE ASSESSED BY THE INVESTIGATOR)

1. Losing Total House 2. Losing Partial House 3. Losing Total House and part of Plot (Aangan or Courtyard) 4. Losing Total Plot and Total House 5. Losing Total Plot and Partial House 6. Losing Partial Plot 7. Losing Total Commercial Structure 8. Losing Partial Commercial Structure 9. Losing Total Commercial Structure and Partial Plot 10. Losing Total Commercial Structure and Total Plot 11. Losing Partial Commercial Structure and Total Plot 12. Losing Total House and Total Commercial Structure 13. Losing Total House, Total Commercial Structure and Total Plot 14. Losing Total House, Total Commercial Structure 15. Losing Total House, Partial Commercial Structure and Part of Plot 16. Losing Partial House, Partial Commercial Structure and Part of Plot 17. Losing Total House and Partial Commercial Structure 18. Losing Total Commercial Structure and Part of House 19. Losing Total Boundary Wall 20. Losing Partial Boundary Wall 21. Losing Total Agricultural Land 22. Losing Partial Agricultural Land 23. Losing Total Cattle Shed 24. Losing Part of Cattle Shed 25. Losing Water bodies 26. Losing Total Livelihood for Commercial Tenant 27. Others (Specify)

Status of Occupier of affected property

1. Status of Occupier (Tick in the appropriate box)

Owner Legal Non-title Holders Vacant Tenant/sharecropper Squatter Encroacher

2. Since how long your family has been using this property (in years) ______

3. Do you possess a documentary proof

1. Yes 2. No.

4. If yes, Type of documentary proof of occupation of affected property

Ration card no______Voter IC no ______Receipt/Bill ______Bank/A/c ______Annexure - 2.1

5. Land Ownership (Tick under appropriate type and enter the no. of households under the same)

Single Joint Trust Community Government Forest Unclear (specify) 5.1 Type of ownership

Male Female 5.2 Ownership by Gender ( if private)

6. Does the family have legal document to prove ownership of

Structure 1. Yes 2. No. RTC No. Sub No.

land 1. Yes 2. No. RTC No. Sub No. (to be asked only to the owner) (If yes, ask for the legal document and check with the Land Revenue Office)

Measurements

2.1 Structure

Offset From Existing Offset from Edge of Asset Central Line up to Area Getting Affected Land Structure Land Structure Starting Meter Ending Meter Width Total Area (in sq.m) No. of Floors (G, G+1, G+n)

2.2 Land Total Affected Sl. Area Length Width Total Length Width Total No. Area (in Area (in sqm) sqm) 1. Built up area 2. Open Space 3. Total Area

2.3 Boundary Wall Details Sl. Boundary / Length Total length No. Compound Wall affected (in sqm) 1. Barbed wire fencing 2. Stone Dry Masonry 3. Brick / Stone Masonry 4. Mud Wall 5. Others (Specify) Annexure - 2.1

2.4 Gate Details Sl. Type of Gate Length Height No. (in m) (in m) 1. M S 2. Wooden 3. Others

2.5 WATER SOURCES GETTING AFFECTED

Sources (in No.) User (use code)* Units to be acquired Dug Wells Tube Wells Supply Points

*[1.Domestic 2.Agriculture 3.Industrial 4. Others (to be specified)]

6 Diagram of the affected property (Rough diagram with dimension – Not to scale)

(PHOTOGRAPH TO BE ATTACHED – STRUCTURE ALONG WITH HEAD OF HOUSEHOLD/ RESPONDENT)

In case the tenancy/ownership is under dispute (legal or otherwise) please make a short note below

Field Supervisor: ______Date: ______

Endorsed by:

Revenue Officer: ______Date: ______

MoRTH / PWD Officer: ______Date: ______SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 3.1

Project Road Marked on Census Maps

NH-11B Project Road

MORTH TCPL Annex 3.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 3.1

NH-11B Project Road

MORTH TCPL Annex 3.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 3.1

NH-11B Project Road

MORTH TCPL Annex 3.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 3.1

NH-11B Project Road

MORTH TCPL Annex 3.1/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot SIA and RAP – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.2

Project Road Marked on Census Maps

NH-11B Project Road

MORTH TCPL Annex 3.2/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot SIA and RAP – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.2

NH-11B Project Road

MORTH TCPL Annex 3.2/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot SIA and RAP – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.2

NH-11B Project Road

MORTH TCPL Annex 3.2/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot SIA and RAP – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.2

NH-11B Project Road

MORTH TCPL Annex 3.2/4 SIA and RAP including TDP for Rehabilitation and Upgrading of SIA and RAP Lalsot – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.3

List of Census Villages

Sr. No. Name Village/Towns District

1 Lalsot (M) Urban Dausa

2 Rajauli Rural

3 Shyonanda Rural

4 Nagariyavas Rural

5 Toda Ganga Chak no. 1 Rural

6 Bheruwas Rural

7 Mukundpura Rural

8 Todadhama Rural

9 Khemvas Rural

10 Shahapura Rural

11 Toda thekala Rural

12 Binori Rural

13 Suratpura Rural

14 Mandavari Rural

15 Khanpur Rural

16 Sirsali Rural Sawai – Madhopur

17 Sitarampura Rural

18 Dabar Rural

19 Nagarheda Rural

MORTH TCPL Annex 3.3/1 SIA and RAP including TDP for Rehabilitation and Upgrading of SIA and RAP Lalsot – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.3

Sr. No. Name Village/Towns District

20 Kheadli Rural

21 Pipalai Rural

22 Sitod Rural

23 Badh Sitod Rural

24 Badh Ghanoli Chak No.1 Rural

25 Koyla Rural

26 Badh Koyla Rural

27 Badh Bidarka Rural

28 Thali Rural

29 Ahamadpur Rural

30 Badh Bichala Rural

31 Badh Khurd Rural

32 Badh Kalan Rural

33 Jalokhara Rural

34 Hingotiya Rural

35 Mahanandpura Rural

36 Mirjapur Rural

37 Brahmwad Rural

38 Udaikalan Rural

39 Saloda Rural

MORTH TCPL Annex 3.3/1 SIA and RAP including TDP for Rehabilitation and Upgrading of SIA and RAP Lalsot – Karauli section of NH – 11B in the State of Rajasthan Annexure – 3.3

Sr. No. Name Village/Towns District

40 Dibsya Rural

41 Khanpur Baroda Rural

42 Jat Baroda Rural

43 Toksi Rural

44 Salempur Rural Karauli

45 Govindpura Rural

46 Kudgaon Rural

47 Mahmadpur Rural

48 Bhadkya Rural

49 Bijalpur Rural

50 Manch Rural

51 Dhugadh Rural

52 Gunesara Rural

53 Taroli Rural

54 Gopalpursay Rural

55 Rampur Rural

56 Barkheda Rural

57 Karauli (M) Urban

MORTH TCPL Annex 3.3/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure - 3.4

Project affected Villages (Census 2001)

Sl. No. District Sub District Village Rural/ Total HH Total Male (%) Female Sex Population (0- SC (%) ST (%) Overall Male Female Urban Population (%) Ratio 6 Yrs) literacy (%) literacy literacy (%) (%) 1 Dausa 0 Dausa Total 193498 1317063 52.65 47.35 899 264978 21.21 26.82 49.40 33.40 15.99 2 Dausa 0 Dausa Rural 172097 1181245 52.62 47.38 900 241998 21.73 29.22 47.81 32.75 15.06 3 Dausa 0 Dausa Urban 21401 135818 52.90 47.10 890 22980 16.70 5.92 63.17 39.04 24.13

745 Dausa 5 Lalsot Total 39418 279619 52.15 47.85 917 59226 20.23 37.35 43.30 30.47 12.83 746 Dausa 5 Lalsot Rural 35323 251370 52.20 47.80 916 53956 21.05 41.42 41.76 29.89 11.87 747 Dausa 5 Lalsot Urban 4095 28249 51.75 48.25 932 5270 12.89 1.14 56.97 35.67 21.30 989 Dausa 5 Salemabad Rural 8 83 54.22 45.78 844 17 0.00 53.01 74.70 45.78 28.92 990 Dausa 5 Malwas Rural 31 223 52.02 47.98 922 40 0.00 100.00 63.68 38.57 25.11 992 Dausa 5 Toda Dhama @ Gopalpura Rural 78 607 48.43 51.57 1065 119 34.76 7.91 58.48 36.08 22.41 993 Dausa 5 Toda Dhama Chak No 1 Rural 17 120 50.83 49.17 967 10 100.00 0.00 43.33 35.83 7.50 994 Dausa 5 Khemawas Rural 120 1109 50.86 49.14 966 234 55.09 0.18 42.20 30.75 11.45 995 Dausa 5 Bheroowas Chak No 2 Rural 26 235 51.91 48.09 926 58 100.00 0.00 47.23 33.62 13.62 1002 Dausa 5 Chak Mukandpura Wake Nagariyawas Rural 2 12 50.00 50.00 1000 1 0.00 100.00 41.67 25.00 16.67 1006 Dausa 5 Rajoli Rural 210 1616 50.56 49.44 978 330 16.89 5.45 45.92 31.37 14.54 1011 Dausa 5 Kishanpura Rural 116 908 53.19 46.81 880 156 0.66 0.00 46.92 34.47 12.44 1012 Dausa 5 Patti Sultanpura Rural 22 174 48.85 51.15 1047 38 0.00 99.43 44.83 32.76 12.07 1024 Dausa 5 Kherla Khurd Rural 233 1598 52.07 47.93 921 344 22.28 2.63 50.00 32.54 17.46 1025 Dausa 5 Khanpur Rural 89 715 51.47 48.53 943 122 26.15 67.69 51.89 34.69 17.20 1027 Dausa 5 Mandawari Rural 1382 8934 52.00 48.00 923 1610 16.77 32.74 56.30 37.02 19.29 1030 Dausa 5 Shyampura Khurd Rural 141 875 50.06 49.94 998 168 18.86 38.29 51.77 33.94 17.83 1048 Dausa 5 Lalsot (M) Urban 4095 28249 51.75 48.25 932 5270 12.89 1.14 56.97 35.67 21.30 1049 Sawai Madhopur 0 Sawai Madhopur Total 176738 1117057 52.93 47.07 889 206750 19.98 21.58 46.19 32.72 13.47 1050 Sawai Madhopur 0 Sawai Madhopur Rural 141589 904417 52.93 47.07 889 171882 20.28 25.71 42.63 31.40 11.24 1051 Sawai Madhopur 0 Sawai Madhopur Urban 35149 212640 52.95 47.05 889 34868 18.73 4.01 61.29 38.35 22.95 1052 Sawai Madhopur 1 Gangapur Total 43343 284605 53.26 46.74 878 54265 19.84 16.94 50.95 34.87 16.08 1053 Sawai Madhopur 1 Gangapur Rural 26545 179209 53.32 46.68 875 36353 22.03 24.39 45.74 33.17 12.56 1054 Sawai Madhopur 1 Gangapur Urban 16798 105396 53.14 46.86 882 17912 16.13 4.28 59.81 37.74 22.07 1098 Sawai Madhopur 1 Toksi Rural 393 2535 53.02 46.98 886 450 22.13 48.64 59.17 37.67 21.50 1100 Sawai Madhopur 1 Barh Chhawa No.1 Rural 5 27 51.85 48.15 929 2 0.00 0.00 37.04 29.63 7.41 1103 Sawai Madhopur 1 Tajpur Rural 128 643 53.65 46.35 864 104 35.61 25.19 53.34 35.30 18.04 1105 Sawai Madhopur 1 Mahu Khurd (Rural) Rural 153 838 51.19 48.81 953 148 7.64 0.00 50.95 37.83 13.13 1106 Sawai Madhopur 1 Khanpur Baroda Rural 532 3806 54.26 45.74 843 794 22.54 0.03 46.43 33.29 13.14 1123 Sawai Madhopur 1 Jalokhara Rural 135 873 53.04 46.96 886 185 11.80 0.11 47.77 33.56 14.20 1127 Sawai Madhopur 1 Motipur Rural 117 874 54.92 45.08 821 141 23.80 0.00 46.45 36.50 9.95 1128 Sawai Madhopur 1 Bidarkha Rural 304 2161 52.11 47.89 919 457 12.82 0.00 41.05 31.14 9.90 1129 Sawai Madhopur 1 Dhoodhoopura Rural 135 777 53.80 46.20 859 127 43.11 0.00 60.49 39.12 21.36 1168 Sawai Madhopur 1 Gangapur City (M) Urban 15468 96845 53.23 46.77 879 16398 15.28 4.52 59.90 37.74 22.16

MORTH A-1 TCPL SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure - 3.4

Project affected Villages (Census 2001)

Sl. No. District Sub District Village Rural/ Total HH Total Male (%) Female Sex Population (0- SC (%) ST (%) Overall Male Female Urban Population (%) Ratio 6 Yrs) literacy (%) literacy literacy (%) (%) 1170 Sawai Madhopur 2 Bamanwas Total 22901 149429 53.13 46.87 882 26550 19.08 31.75 48.44 33.86 14.58 1171 Sawai Madhopur 2 Bamanwas Rural 22901 149429 53.13 46.87 882 26550 19.08 31.75 48.44 33.86 14.58 1172 Sawai Madhopur 2 Bamanwas Urban 0 0 0.00 0.00 0 0 0.00 0.00 0.00 0.00 0.00 1237 Sawai Madhopur 2 Barh Koyla Rural 82 510 54.51 45.49 835 51 64.71 30.20 55.69 41.57 14.12 1238 Sawai Madhopur 2 Gahnoli Rural 189 1185 55.27 44.73 809 207 21.35 0.00 51.31 37.72 13.59 1239 Sawai Madhopur 2 Koyla Rural 164 1067 50.70 49.30 972 156 0.00 81.16 55.30 37.58 17.71 1241 Sawai Madhopur 2 Barh Gahnoli Chak No.1 Rural 35 184 53.26 46.74 878 16 0.00 0.00 62.50 42.93 19.57 1242 Sawai Madhopur 2 Barh Sitor Rural 1 14 57.14 42.86 750 3 100.00 0.00 28.57 21.43 7.14 1244 Sawai Madhopur 2 Sitor or Sitod Rural 403 2478 50.85 49.15 967 450 28.81 7.95 56.13 33.70 22.44 1245 Sawai Madhopur 2 Piplai Rural 766 5272 52.41 47.59 908 1065 11.46 2.20 51.21 34.54 16.67 1246 Sawai Madhopur 2 Kherli Rural 329 2280 54.08 45.92 849 446 15.09 0.26 39.43 30.09 9.34 1247 Sawai Madhopur 2 Koochawar Chak No.2 Rural 15 104 50.96 49.04 962 23 0.00 7.69 29.81 24.04 5.77 1248 Sawai Madhopur 2 Nagarhera Rural 105 664 52.56 47.44 903 139 7.68 0.00 46.54 35.09 11.45 1250 Sawai Madhopur 2 Dabar Rural 252 2020 50.99 49.01 961 470 16.39 23.61 43.42 31.14 12.28 1251 Sawai Madhopur 2 Sarsali Rural 190 1333 53.56 46.44 867 242 14.48 66.47 51.99 36.53 15.45 1798 Karauli 0 Karauli Total 180512 1209665 53.90 46.10 855 249342 23.16 22.37 50.32 34.12 16.20 1799 Karauli 0 Karauli Rural 154877 1037720 54.00 46.00 852 217137 23.90 25.35 49.33 33.82 15.51 1800 Karauli 0 Karauli Urban 25635 171945 53.29 46.71 877 32205 18.69 4.38 56.27 35.89 20.38 2162 Karauli 4 Karauli Total 43890 288860 54.09 45.91 849 62017 20.42 15.69 45.84 32.01 13.83 2163 Karauli 4 Karauli Rural 33789 222621 54.37 45.63 839 49330 22.49 19.73 43.95 31.54 12.40 2164 Karauli 4 Karauli Urban 10101 66239 53.14 46.86 882 12687 13.46 2.10 52.20 33.55 18.64 2196 Karauli 4 Pator Rural 71 427 50.59 49.41 977 80 0.00 61.83 60.66 35.60 25.06 2308 Karauli 4 Barkhera Rural 434 3016 53.02 46.98 886 719 10.74 0.00 34.05 25.17 8.89 2316 Karauli 4 Rampur Rural 542 3498 53.14 46.86 882 845 13.89 0.00 32.42 26.47 5.95 2317 Karauli 4 Birhati Rural 118 706 54.53 45.47 834 205 18.56 0.00 45.89 34.84 11.05 2320 Karauli 4 Taroli Rural 152 1007 56.01 43.99 785 210 36.84 27.41 45.88 33.47 12.41 2323 Karauli 4 Kota Rural 657 4651 54.14 45.86 847 1031 25.03 9.12 34.90 27.52 7.37 2324 Karauli 4 Harjanpura Rural 76 527 56.17 43.83 780 138 0.00 0.00 33.02 28.84 4.17 2325 Karauli 4 Barrif Rural 109 771 53.70 46.30 862 192 71.34 0.00 41.12 31.39 9.73 2360 Karauli 4 Karauli (M) Urban 10101 66239 53.14 46.86 882 12687 13.46 2.10 52.20 33.55 18.64 2416 Karauli 6 Sapotra Total 26008 171331 53.83 46.17 858 34434 21.85 38.50 46.36 32.21 14.15 2417 Karauli 6 Sapotra Rural 26008 171331 53.83 46.17 858 34434 21.85 38.50 46.36 32.21 14.15 2418 Karauli 6 Sapotra Urban 0 0 0.00 0.00 0 0 0.00 0.00 0.00 0.00 0.00 2436 Karauli 6 Barh Salempur Rural 184 1340 53.58 46.42 866 287 64.10 0.00 48.88 34.25 14.63 2437 Karauli 6 Salempur Rural 492 3762 53.72 46.28 861 781 25.33 10.58 47.66 33.47 14.19 2439 Karauli 6 Rundi Rural 150 909 52.59 47.41 902 146 13.09 65.57 46.53 33.88 12.65 2440 Karauli 6 Govindpura Rural 141 974 53.18 46.82 880 178 0.00 98.25 51.13 35.52 15.61 2442 Karauli 6 Kurgaon Rural 538 3396 52.71 47.29 897 674 39.96 0.09 53.06 35.31 17.76 2443 Karauli 6 Mahmadpur Rural 246 1682 53.63 46.37 865 335 26.58 1.96 53.39 34.90 18.49 Total 766790 5082482 41.65 37.30 709 1006661 18.47 17.03 38.31 26.63 11.68

MORTH A-2 TCPL SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure - 3.4

Project Affected Vilages (Census 2001)

Sl. District Sub District Village Rural/ Total Total Total Total Main Main Main Main Main Main Main Marginal Marginal Marginal Marginal Marginal No. Urban Population Workers Workers Workers Workers Workers Workers Workers (%) Workers Workers Workers Workers Workers Workers Workers Workers (%) (%) - M* (%) - F** (%) (%) - M (%) - F - CL (%) - AL (%) - HH (%) - Oth (%) (%) - CL (%) - AL (%) - HH (%) - Oth

1 Dausa 0 Dausa Total 1317063.00 41.19 58.48 41.52 76.91 68.61 31.39 67.60 2.70 2.68 27.02 30.02 19.25 5.93 1.00 3.84 2 Dausa 0 Dausa Rural 1181245.00 42.80 56.55 43.45 76.10 66.85 33.15 72.64 2.83 2.35 22.18 31.40 20.70 6.31 0.86 3.52 3 Dausa 0 Dausa Urban 135818.00 27.24 84.84 15.16 87.95 89.42 10.58 7.97 1.14 6.62 84.28 13.71 2.05 1.44 2.58 7.64 745 Dausa 5 Lalsot Total 279619 42.04 57.08 42.92 84.45 62.00 38.00 74.72 2.70 2.54 20.04 18.41 10.33 3.70 0.95 3.43 746 Dausa 5 Lalsot Rural 251370 43.60 55.36 44.64 84.30 60.17 39.83 79.14 2.80 2.40 15.66 18.62 10.84 3.86 0.84 3.08 747 Dausa 5 Lalsot Urban 28249 28.15 80.73 19.27 86.50 86.61 13.39 15.34 1.41 4.38 78.87 15.60 3.47 1.48 2.54 8.10 989 Dausa 5 Salemabad Rural 83 15.66 53.85 46.15 100.00 53.85 46.15 100.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 990 Dausa 5 Malwas Rural 223 27.35 50.82 49.18 100.00 50.82 49.18 96.72 0.00 0.00 3.28 0.00 0.00 0.00 0.00 0.00 992 Dausa 5 Toda Dhama @ Gopalpura Rural 607 42.34 54.47 45.53 81.71 62.38 37.62 53.81 36.19 0.00 10.00 22.38 4.76 16.19 0.00 1.43 993 Dausa 5 Toda Dhama Chak No 1 Rural 120 45.83 52.73 47.27 100.00 52.73 47.27 87.27 0.00 9.09 3.64 0.00 0.00 0.00 0.00 0.00 994 Dausa 5 Khemawas Rural 1109 39.22 54.94 45.06 99.77 54.84 45.16 65.21 7.37 3.00 24.42 0.23 0.00 0.00 0.00 0.23 995 Dausa 5 Bheroowas Chak No 2 Rural 235 47.23 42.34 57.66 100.00 42.34 57.66 94.59 0.00 0.00 5.41 0.00 0.00 0.00 0.00 0.00 1002 Dausa 5 Chak Mukandpura Wake Nagariyawas Rural 12 66.67 50.00 50.00 87.50 42.86 57.14 100.00 0.00 0.00 0.00 14.29 14.29 0.00 0.00 0.00 1006 Dausa 5 Rajoli Rural 1616 29.83 76.76 23.24 87.14 82.14 17.86 26.43 1.90 0.48 71.19 14.76 5.95 3.57 0.00 5.24 1011 Dausa 5 Kishanpura Rural 908 49.12 49.10 50.90 95.74 48.48 51.52 88.76 0.00 1.17 10.07 4.45 3.04 1.41 0.00 0.00 1012 Dausa 5 Patti Sultanpura Rural 174 54.02 47.87 52.13 89.36 47.62 52.38 97.62 0.00 0.00 2.38 11.90 11.90 0.00 0.00 0.00 1024 Dausa 5 Kherla Khurd Rural 1598 39.24 59.81 40.19 58.69 94.29 5.71 51.36 14.67 2.17 31.79 70.38 17.66 49.46 2.17 1.09 1025 Dausa 5 Khanpur Rural 715 41.12 47.62 52.38 39.80 97.44 2.56 72.65 0.85 0.00 26.50 151.28 86.32 59.83 5.13 0.00 1027 Dausa 5 Mandawari Rural 8934 32.53 70.37 29.63 83.90 75.27 24.73 44.26 2.38 6.32 47.05 19.20 6.36 3.98 1.07 7.79 1030 Dausa 5 Shyampura Khurd Rural 875 39.09 59.94 40.06 99.71 60.12 39.88 97.95 0.59 0.00 1.47 0.29 0.00 0.00 0.00 0.29 1048 Dausa 5 Lalsot (M) Urban 28249 28.15 80.73 19.27 86.50 86.61 13.39 15.34 1.41 4.38 78.87 15.60 3.47 1.48 2.54 8.10 1049 Sawai Madhopur 0 Sawai Madhopur Total 1117057 42.00 60.16 39.84 78.18 68.45 31.55 66.48 4.02 2.73 26.77 27.91 15.29 6.74 1.05 4.83 1050 Sawai Madhopur 0 Sawai Madhopur Rural 904417 45.58 56.64 43.36 77.46 65.35 34.65 75.81 4.45 2.29 17.45 29.10 17.50 7.52 0.80 3.28 1051 Sawai Madhopur 0 Sawai Madhopur Urban 212640 26.76 85.68 14.32 83.40 89.32 10.68 3.72 1.12 5.68 89.48 19.90 0.47 1.52 2.68 15.23 1052 Sawai Madhopur 1 Gangapur Total 284605 34.65 66.49 33.51 76.13 76.43 23.57 50.13 4.20 2.19 43.49 31.36 13.08 8.67 1.28 8.34 1053 Sawai Madhopur 1 Gangapur Rural 179209 40.32 58.22 41.78 73.32 69.86 30.14 69.78 5.72 1.41 23.09 36.39 18.31 11.70 1.00 5.37 1054 Sawai Madhopur 1 Gangapur Urban 105396 25.01 89.19 10.81 83.82 92.19 7.81 3.00 0.55 4.05 92.40 19.30 0.52 1.39 1.93 15.47 1098 Sawai Madhopur 1 Toksi Rural 2535 45.64 50.65 49.35 52.64 83.74 16.26 72.91 3.45 1.48 22.17 89.98 67.32 14.78 0.82 7.06 1100 Sawai Madhopur 1 Barh Chhawa No.1 Rural 27 44.44 50.00 50.00 50.00 100.00 0.00 0.00 0.00 0.00 100.00 100.00 50.00 0.00 0.00 50.00 1103 Sawai Madhopur 1 Tajpur Rural 643 25.82 96.99 3.01 65.06 96.30 3.70 38.89 8.33 0.00 52.78 53.70 4.63 7.41 0.00 41.67 1105 Sawai Madhopur 1 Mahu Khurd (Rural) Rural 838 40.81 62.28 37.72 76.32 69.73 30.27 26.05 0.38 0.00 73.56 31.03 6.13 0.77 0.00 24.14 1106 Sawai Madhopur 1 Khanpur Baroda Rural 3806 28.59 81.89 18.11 87.59 89.72 10.28 37.99 3.57 0.63 57.82 14.17 9.02 0.52 0.21 4.41 1123 Sawai Madhopur 1 Jalokhara Rural 873 37.92 59.21 40.79 77.04 75.69 24.31 58.04 2.35 1.18 38.43 29.80 18.43 9.80 0.00 1.57 1127 Sawai Madhopur 1 Motipur Rural 874 51.03 56.05 43.95 78.25 68.77 31.23 83.95 2.01 0.29 13.75 27.79 22.06 3.44 0.00 2.29 1128 Sawai Madhopur 1 Bidarkha Rural 2161 43.59 55.94 44.06 83.65 57.36 42.64 91.75 0.76 0.00 7.49 19.54 9.52 7.36 0.00 2.66 1129 Sawai Madhopur 1 Dhoodhoopura Rural 777 41.83 63.38 36.62 95.38 61.94 38.06 69.68 27.10 0.32 2.90 4.84 0.00 1.29 0.65 2.90 1168 Sawai Madhopur 1 Gangapur City (M) Urban 96845 25.18 89.08 10.92 84.37 92.07 7.93 3.03 0.44 4.16 92.37 18.53 0.36 1.29 1.93 14.95 1170 Sawai Madhopur 2 Bamanwas Total 149429 43.43 56.84 43.16 74.76 68.90 31.10 78.14 5.72 2.32 13.82 33.77 19.59 10.33 1.13 2.73 1171 Sawai Madhopur 2 Bamanwas Rural 149429 43.43 56.84 43.16 74.76 68.90 31.10 78.14 5.72 2.32 13.82 33.77 19.59 10.33 1.13 2.73 1172 Sawai Madhopur 2 Bamanwas Urban 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1237 Sawai Madhopur 2 Barh Koyla Rural 510 32.16 84.76 15.24 78.05 92.97 7.03 73.44 0.00 0.00 26.56 28.13 6.25 18.75 0.00 3.13 1238 Sawai Madhopur 2 Gahnoli Rural 1185 40.25 57.65 42.35 58.91 77.22 22.78 70.82 4.98 1.42 22.78 69.75 34.52 24.20 0.71 10.32 1239 Sawai Madhopur 2 Koyla Rural 1067 29.71 75.08 24.92 70.66 97.77 2.23 81.25 3.57 2.23 12.95 41.52 33.48 5.36 0.45 2.23 1241 Sawai Madhopur 2 Barh Gahnoli Chak No.1 Rural 184 30.43 96.43 3.57 98.21 98.18 1.82 100.00 0.00 0.00 0.00 1.82 0.00 1.82 0.00 0.00 1242 Sawai Madhopur 2 Barh Sitor Rural 14 57.14 62.50 37.50 62.50 80.00 20.00 0.00 0.00 40.00 60.00 60.00 40.00 0.00 0.00 20.00 1244 Sawai Madhopur 2 Sitor or Sitod Rural 2478 56.17 50.14 49.86 77.59 55.46 44.54 64.07 30.46 2.69 2.78 28.89 14.17 12.13 1.11 1.48 1245 Sawai Madhopur 2 Piplai Rural 5272 29.89 73.73 26.27 75.89 88.63 11.37 46.15 10.79 9.87 33.19 31.77 21.15 3.34 4.26 3.01 1246 Sawai Madhopur 2 Kherli Rural 2280 46.01 54.72 45.28 62.35 81.04 18.96 82.26 5.66 1.22 10.86 60.40 28.44 26.61 1.83 3.52 1247 Sawai Madhopur 2 Koochawar Chak No.2 Rural 104 47.12 57.14 42.86 100.00 57.14 42.86 95.92 0.00 2.04 2.04 0.00 0.00 0.00 0.00 0.00 1248 Sawai Madhopur 2 Nagarhera Rural 664 42.92 50.53 49.47 57.54 81.71 18.29 73.78 16.46 0.61 9.15 73.78 48.78 24.39 0.00 0.61 1250 Sawai Madhopur 2 Dabar Rural 2020 45.79 48.54 51.46 89.51 48.91 51.09 93.24 0.24 2.78 3.74 11.71 1.09 9.54 0.00 1.09 1251 Sawai Madhopur 2 Sarsali Rural 1333 46.44 50.40 49.60 96.45 50.08 49.92 89.95 0.67 1.01 8.38 3.69 0.17 1.17 1.34 1.01 1798 Karauli 0 Karauli Total 1209665 39.94 60.50 39.50 73.58 72.99 27.01 63.48 4.25 2.45 29.82 35.92 19.75 9.84 1.15 5.18 1799 Karauli 0 Karauli Rural 1037720 41.94 58.12 41.88 72.83 70.93 29.07 69.93 4.56 1.99 23.52 37.30 21.55 10.45 0.94 4.36 1800 Karauli 0 Karauli Urban 171945 27.86 82.06 17.94 80.34 90.02 9.98 10.41 1.69 6.24 81.65 24.48 4.96 4.79 2.81 11.93

MORTH TCPL1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure - 3.4

Project Affected Vilages (Census 2001)

Sl. District Sub District Village Rural/ Total Total Total Total Main Main Main Main Main Main Main Marginal Marginal Marginal Marginal Marginal No. Urban Population Workers Workers Workers Workers Workers Workers Workers (%) Workers Workers Workers Workers Workers Workers Workers Workers (%) (%) - M* (%) - F** (%) (%) - M (%) - F - CL (%) - AL (%) - HH (%) - Oth (%) (%) - CL (%) - AL (%) - HH (%) - Oth

2162 Karauli 4 Karauli Total 288860 37.35 64.94 35.06 76.33 75.28 24.72 55.05 2.98 2.98 38.99 31.01 16.75 5.35 1.43 7.48 2163 Karauli 4 Karauli Rural 222621 40.14 61.71 38.29 75.74 73.01 26.99 65.23 3.26 1.51 30.00 32.02 19.88 5.74 0.83 5.58 2164 Karauli 4 Karauli Urban 66239 27.95 80.52 19.48 79.15 85.79 14.21 8.07 1.65 9.80 80.48 26.34 2.29 3.57 4.24 16.24 2196 Karauli 4 Pator Rural 427 44.96 53.65 46.35 89.58 58.14 41.86 76.74 0.00 1.16 22.09 11.63 0.00 0.00 11.63 0.00 2308 Karauli 4 Barkhera Rural 3016 37.86 64.19 35.81 74.08 79.67 20.33 63.71 0.95 0.59 34.75 34.99 22.34 9.81 0.00 2.84 2316 Karauli 4 Rampur Rural 3498 42.94 55.66 44.34 77.56 67.30 32.70 49.27 2.32 1.46 46.95 28.93 14.08 6.35 1.80 6.70 2317 Karauli 4 Birhati Rural 706 39.80 61.21 38.79 84.34 70.46 29.54 41.77 1.69 0.42 56.12 18.57 11.81 4.64 0.00 2.11 2320 Karauli 4 Taroli Rural 1007 41.61 58.95 41.05 46.78 60.20 39.80 78.57 1.02 0.00 20.41 113.78 31.63 80.61 0.00 1.53 2323 Karauli 4 Kota Rural 4651 38.77 61.62 38.38 80.87 72.15 27.85 71.67 0.34 0.82 27.16 23.66 17.42 2.67 0.55 3.02 2324 Karauli 4 Harjanpura Rural 527 51.80 57.88 42.12 97.07 58.11 41.89 99.25 0.38 0.00 0.38 3.02 1.89 1.13 0.00 0.00 2325 Karauli 4 Barrif Rural 771 39.30 59.74 40.26 76.57 76.72 23.28 84.05 15.52 0.00 0.43 30.60 25.43 5.17 0.00 0.00 2360 Karauli 4 Karauli (M) Urban 66239 27.95 80.52 19.48 79.15 85.79 14.21 8.07 1.65 9.80 80.48 26.34 2.29 3.57 4.24 16.24 2416 Karauli 6 Sapotra Total 171331 42.47 59.37 40.63 80.18 66.91 33.09 77.62 3.48 1.89 17.02 24.72 13.82 6.00 0.80 4.11 2417 Karauli 6 Sapotra Rural 171331 42.47 59.37 40.63 80.18 66.91 33.09 77.62 3.48 1.89 17.02 24.72 13.82 6.00 0.80 4.11 2418 Karauli 6 Sapotra Urban 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2436 Karauli 6 Barh Salempur Rural 1340 37.09 61.57 38.43 99.80 61.69 38.31 90.12 0.00 0.00 9.88 0.20 0.00 0.20 0.00 0.00 2437 Karauli 6 Salempur Rural 3762 30.06 74.45 25.55 90.63 81.27 18.73 28.59 3.32 3.02 65.07 10.34 8.98 0.78 0.10 0.49 2439 Karauli 6 Rundi Rural 909 42.68 56.96 43.04 98.97 56.77 43.23 86.46 1.82 1.56 10.16 1.04 0.52 0.00 0.00 0.52 2440 Karauli 6 Govindpura Rural 974 44.66 48.28 51.72 100.00 48.28 51.72 93.56 0.00 0.46 5.98 0.00 0.00 0.00 0.00 0.00 2442 Karauli 6 Kurgaon Rural 3396 36.07 67.10 32.90 78.37 83.23 16.77 36.67 1.77 5.00 56.56 27.60 21.56 3.02 1.15 1.88 2443 Karauli 6 Mahmadpur Rural 1682 34.72 64.90 35.10 57.71 84.87 15.13 47.77 13.65 1.19 37.39 73.29 30.56 41.54 0.00 1.19

Total 5082482 31.57 48.54 30.41 63.68 56.06 22.89 51.77 3.44 1.89 21.85 23.19 11.65 6.92 0.69 3.93

MORTH TCPL2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.1 Typical Cross section Type TCS-1A

MORTH TCPL Annex. – 4.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.2 Typical Cross section Type TCS-1B

MORTH TCPL Annex. – 4.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.3 Typical Cross section Type TCS -1C

MORTH TCPL Annex. – 4.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.4 Typical Cross section Type TCS-2A

MORTH TCPL Annex. – 4.1/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.5 Typical Cross section Type TCS-2A1

MORTH TCPL Annex. – 4.1/5 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.6 Typical Cross section Type TCS-2B

MORTH TCPL Annex. – 4.1/6 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.7 Typical Cross section Type TCS-3

MORTH TCPL Annex. – 4.1/7 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.8 Typical Cross section Type TCS-4

MORTH TCPL Annex. – 4.1/8 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.9 Typical Cross section Type TCS-5A

MORTH TCPL Annex. – 4.1/9 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.10 Typical Cross section Type TCS-5A 1

MORTH TCPL Annex. – 4.1/10 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.11 Typical Cross section Type TCS-6A

MORTH TCPL Annex. – 4.1/11 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA and RAP Annexure – 4.1

Fig. 4.12 Typical Cross section Type TCS-6B

MORTH TCPL Annex. – 4.1/12 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – SIA & RAP Karauli section of NH – 11B in the State of Rajasthan Annexure 4.2

Applicability of cross section to the Project Road.

Existing chainage (km) Project Chainage (km) Cross Road Sr. No. section Remarks Type length (km) From To (Km) From (Km) To (Km) (Km)

1 0/000 1/700 0/000 1/700 1.70 TCS 2A Lalsot, Shyonamda, Nagariyavas 2 1/700 4/200 1/700 4/200 2.50 TCS 2A

3 4/200 5/500 4/200 5/500 1.30 TCS 1A

4 5/500 6/250 5/500 6/250 0.75 TCS 1B

5 6/250 6/500 6/250 6/500 0.25 TCS 2A Bhairuvas

6 6/500 7/000 6/500 7/000 0.50 TCS 1A

7 7/000 7/800 7/000 7/800 0.80 TCS 1B

8 7/800 8/100 7/800 8/100 0.30 TCS 2A Pakka Dhora

9 8/100 10/200 8/100 10/200 2.10 TCS 1B

10 10/200 10/750 10/200 10/750 0.55 TCS 2A Suratpura

11 10/750 11/400 10/750 11/400 0.65 TCS 1A

12 11/400 12/800 11/400 12/800 1.40 TCS 1B

13 12/800 14/700 12/800 14/700 1.90 TCS 2A Mandavari

14 14/700 15/200 14/700 15/200 0.50 TCS 1B

15 15/200 15/700 15/200 15/700 0.50 TCS 1A

16 15/700 17/000 15/700 17/000 1.30 TCS 1B

17 17/000 18/300 17/000 18/300 1.30 TCS 1A

18 18/300 19/000 18/300 19/000 0.70 TCS 2A Dabar

19 19/000 19/250 19/000 19/250 0.25 TCS 5A1 Dabar

20 19/250 19/400 19/250 19/400 0.15 TCS 2A1 Dabar

MORTH TCPL Annex. – 4.2/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – SIA & RAP Karauli section of NH – 11B in the State of Rajasthan Annexure 4.2

Applicability of cross section to the Project Road.

Existing chainage Cross Road Sr. No. (km) Project Chainage (km) section Remarks Type length (km)

21 19/400 20/200 19/400 20/200 0.80 TCS 1B

22 20/200 20/900 20/200 20/900 0.70 TCS 2A Nagarheda

23 20/900 22/050 20/900 22/050 1.15 TCS 1B

24 22/050 22/200 22/050 22/200 0.15 TCS 5A Khedali

25 22/200 22/570 22/200 22/570 0.37 TCS 2A Khedali

26 22/570 24/000 22/570 24/000 1.43 TCS 1B

27 24/000 25/000 24/000 25/000 1.00 TCS 5A1 Pipalai

28 25/000 25/200 25/000 25/200 0.20 TCS 2A1 Pipalai

Construction of ROB by 29 25/200 25/840 25/200 25/840 0.64 RLY. NW Railway

30 25/840 26/800 25/840 26/800 0.95 TCS 1B

31 26/800 27/390 26/800 27/400 0.60 TCS 2A Sitod

Reconstruction of MNB - 32 27/390 27/790 27/400 27/800 0.40 TCS 4 02

33 27/790 31/690 27/800 31/690 3.89 TCS 1A

34 31/690 32/310 31/690 32/310 0.62 TCS 2A Koyala

35 32/310 35/220 32/310 35/220 2.91 TCS 1A

36 35/220 35/510 35/220 35/510 0.29 TCS 2A Thali

37 35/510 35/680 35/510 35/740 0.23 TCS 1A

Reconstruction of MNB – 38 35/680 36/090 35/740 36/170 0.43 TCS 4 03

39 36/090 36/500 36/170 36/500 0.33 TCS 1A

MORTH TCPL Annex. – 4.2/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – SIA & RAP Karauli section of NH – 11B in the State of Rajasthan Annexure 4.2

Applicability of cross section to the Project Road.

Existing chainage Cross Road Sr. No. (km) Project Chainage (km) section Remarks Type length (km)

40 36/500 37/000 36/500 37/000 0.50 TCS 1B

41 37/000 46/250 37/000 46/340 9.34 TCS 1C

Construction of ROB by 42 46/250 47/200 46/340 47/300 0.95 RLY. NW Railway

43 47/200 49/230 47/300 49/330 2.03 TCS 1C

Under Construction ROB 44 49/230 --- 49/330 50/740 1.41 RLY. by RSRDC

Proposed Gangapur 45 --- 51/550 50/740 52/955 2.22 TCS 4 Bypass

(Khanpur baroda) Gangaji 46 51/550 52/600 52/955 54/050 1.10 TCS 2A ki koti

(Khanpur baroda) Gangaji 47 52/600 52/700 54/050 54/150 0.10 TCS 5A ki koti

(Khanpur baroda) Gangaji 48 52/700 53/240 54/150 54/690 0.54 TCS 2A ki koti

49 53/240 53/740 54/690 55/190 0.50 TCS 1B

50 53/740 54/060 55/190 55/510 0.32 TCS 1A

51 54/060 55/025 55/510 56/480 0.97 TCS 1B

52 55/025 56/500 56/480 58/100 1.62 TCS 1A

53 56/500 57/295 58/100 58/700 0.60 TCS 5A1 Salempur

54 57/295 58/360 58/700 59/860 1.16 TCS 1B

55 58/360 60/180 59/860 61/680 1.82 TCS 1A

56 60/180 60/680 61/680 62/180 0.50 TCS 1B

MORTH TCPL Annex. – 4.2/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – SIA & RAP Karauli section of NH – 11B in the State of Rajasthan Annexure 4.2

Applicability of cross section to the Project Road.

Existing chainage Cross Road Sr. No. (km) Project Chainage (km) section Remarks Type length (km)

57 60/680 62/035 62/180 63/500 1.32 TCS 1A

58 62/035 62/335 63/500 63/800 0.30 TCS 5A1 Kudgaon

59 62/335 62/700 63/800 64/170 0.37 TCS 2A1 Kudgaon

60 62/700 63/520 64/170 65/000 0.83 TCS 1A

61 63/520 63/865 65/000 65/350 0.35 TCS 5A1 Mahamadpura

62 63/865 64/535 65/350 66/030 0.68 TCS 2A1 Mahamadpura

63 64/535 66/040 66/030 67/530 1.50 TCS 1A

64 66/040 66/470 67/530 67/960 0.43 TCS 2A Bijalpur

65 66/470 68/420 67/960 69/910 1.95 TCS 1B

66 68/420 68/970 69/910 70/460 0.55 TCS 1A

67 68/970 70/920 70/460 72/410 1.95 TCS 1B

68 70/920 71/140 72/410 72/630 0.22 TCS 4

69 71/140 72/315 72/630 73/830 1.20 TCS 2A Astal, Atta

70 72/315 74/050 73/830 75/560 1.73 TCS 1B

Reconstruction of MNB – 71 74/050 74/500 75/560 76/010 0.45 TCS 4 05

72 74/500 74/970 76/010 76/470 0.46 TCS 2B Karauli

73 74/970 77/935 76/470 79/440 2.97 TCS 2B Karauli

Reconstruction of MNB – 74 77/935 78/475 79/440 79/990 0.55 TCS 4 06

75 78/475 81/930 79/990 83/430 3.44 TCS 6B Karauli

MORTH TCPL Annex. – 4.2/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – SIA & RAP Karauli section of NH – 11B in the State of Rajasthan Annexure 4.2

Applicability of cross section to the Project Road.

Existing chainage Cross Road Sr. No. (km) Project Chainage (km) section Remarks Type length (km)

76 81/930 82/325 83/430 83/830 0.40 TCS 6A Karauli

77 82/325 83/925 83/830 85/570 1.74 TCS 6B Karauli

78 83/925 84/035 85/570 85/680 0.11 TCS 2B

79 84/035 85/000 85/680 86/650 0.97 TCS 1B

TOTAL LENGTH 86.650 km

MORTH TCPL Annex. – 4.2/5 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Summary of Sign Board NH-11B Lalsot- Karauli Sr Sign Nos Remarks No Plate No 1 Stop Sign (900 Octagonal) 66 S-1 2 Speed Limit (600 Dia.) 89 S-4 3 Overtaking Prohibited (900 dia.) 142 S-8 4 Left crossing road (900 triangle) 7 S-9 5 T-Intersection (900 triangle) 54 S-11 6 Round About (900 triangle) 5 S-12 RHS/ LHS Junction Staggered (900 7 4 S-13 triangle) 8 Y-Intersection (900 triangle) 99 S-14 9 Route Marker (600 x 450) 188 S16,S23 10 Hazard Marker (300 x 900) 28 S-17 11 Police Station (600 x 450) 7 S-25 Separate/Dual carriageway ahead (900 12 3 S-29 triangular) 13 Single carriageway ahead (900 triangular) 2 S-30 14 Pedestrian crossing (600 x 450) 78 S-31 15 School (600 x 450) 63 S-32 16 Speed Bump (900 triangular) 103 S-33 17 Gap in Median (900 triangular) 0 S-34 18 Bus Stop (600 x 450) 11 S-37 19 Public Telephone (600 x 450) 34 S-37A 20 LHS/ RHS Curve (900 triangular) 142 S-47 21 Restaurant (600 x 450) 14 S-48 22 Fuel station (600 x 450) 32 S-49 23 Hospital (600 x 450) 10 S-51 24 Cluster of red reflector 29 TA-1 25 Direction sign 205 S-56 26 Place Identification 36 S-57

MORTH TCPL Annexure 5.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Details of Road Signages Sr No Sign Board Type Chainages of Sign Board 1 S-9 CH-10.500 CH-10.700 CH-54.200 CH-54.460 CH-63.650 CH-63.975 CH-82.575 CH-82.650 2 S-11 CH-12.100 CH-12.350 CH-43.150 CH-43.400 CH-43.900 CH-46.160 3 S-12 CH-82.900 4 S-13 CH-71.600 CH-71.800 5 S-14 CH-00.000 CH-01.250 CH-01.650 CH-01.900 CH-05.650 CH-05.950 CH-06.400 CH-06.700 CH-06.800 CH-06.900 CH-06.950 CH-07.050 CH-07.950 CH-08.250 CH-09.500 CH-09.700 CH-09.750 CH-10.000 CH-11.450 CH-11.700 CH-13.700 CH-13.900 CH-13.950 CH-14.050 CH-14.350 CH-14.600 CH-16.700 CH-16.900 CH-17.350 CH-17.600 CH-17.800 CH-18.050 CH-19.050 CH-19.350 CH-22.150 CH-22.350 CH-22.800 CH-23.100 CH-24.150 CH-24.350 CH-25.050 CH-25.350 CH-25.650 CH-25.900 CH-27.300 CH-27.450 CH-28.150 CH-28.450 CH-29.450 CH-29.700 CH-31.450 CH-31.650 CH-31.700 CH-31.900 CH-32.175 CH-32.450 CH-33.850 CH-34.150 CH-36.100 CH-36.350 CH-37.300 CH-37.400 CH-37.450 CH-37.700 CH-38.200 CH-38.450 CH-38.850 CH-39.100 CH-39.650 CH-39.800 CH-41.350 CH-41.700 CH-42.300 CH-42.450 CH-43.560 CH-43.800 CH-48.350 CH-48.550 CH-48.555 CH-48.600 CH-53.400 CH-49.150 CH-49.400 CH-50.600 CH-50.850 CH-52.800 CH-53.050 CH-53.100 CH-55.050 CH-55.250 CH-57.360 CH-57.650 CH-59.400 CH-59.800 CH-63.400 CH-63.650 CH-64.200 CH-64.450 CH-66.450 CH-66.775 CH-66.800 CH-67.050 CH-67.600 CH-67.850 CH-68.050 CH-68.250 CH-68.400 CH-68.600 CH-69.000 CH-69.250 CH-69.400 CH-69.600 CH-73.450 CH-73.650 CH-75.300 CH-75.600 CH-77.000 CH-77.200 CH-78.775 CH-78.880 CH-79.250 CH-79.450 CH-81.250 CH-81.450 CH-81.800 CH-82.050 CH-82.400 CH-82.860 CH-83.100 CH-84.220 CH-84.030 CH-84.600 CH-84.800 CH-85.800 CH-86.000 6 S-29 CH-01.850 CH-80.010 7 S-30 1/590 80/260 85/775 8 S-33 CH-00.050 CH-00.200 CH-03.050 CH-03.300 CH-03.850 CH-04.150 CH-06.250 CH-06.550 CH-07.900 CH-08.150 CH-13.450 CH-13.750 CH-14.500 CH-14.800 CH-18.350 CH-18.700 CH-19.000 CH-19.100 CH-19.150 CH-19.450 CH-20.150 CH-20.400 CH-22.400 CH-22.700

MORTH TCPL Annexure 5.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr No Sign Board Type Chainages of Sign Board CH-26.700 CH-26.950 CH-32.100 CH-32.400 CH-35.300 CH-35.550 CH-37.400 CH-37.750 CH-39.600 CH-39.850 CH-41.450 CH-41.800 CH-53.900 CH-54.200 CH-64.175 CH-64.400 CH-67.850 CH-68.100 CH-69.200 CH-69.450 CH-72.700 CH-73.100 CH-73.385 CH-73.580 CH-77.500 CH-77.800 CH-78.800 CH-79.050 CH-81.100 CH-81.300 CH-83.380 CH-83.575 9 S-34 CH-00.000 CH-01.350 10 S-47 CH-00.250 CH-00.450 CH-00.500 CH-00.700 CH-01.300 CH-01.550 CH-02.100 CH-02.400 CH-03.340 CH-03.750 CH-12.850 CH-13.150 CH-13.925 CH-14.160 CH-14.325 CH-14.550 CH-14.950 CH-15.250 CH-16.350 CH-16.650 CH-16.900 CH-17.175 CH-18.900 CH-19.100 CH-19.150 CH-19.400 CH-21.500 CH-21.850 CH-22.110 CH-22.360 CH-23.200 CH-23.470 CH-23.950 CH-24.200 CH-24.300 CH-24.550 CH-24.565 CH-24.850 CH-25.100 CH-25.575 CH-27.300 CH-27.445 CH-27.446 CH-27.840 CH-27.850 CH-28.140 CH-30.750 CH-31.000 CH-32.360 CH-32.650 CH-34.560 CH-34.750 CH-34.950 CH-35.250 CH-35.300 CH-35.600 CH-36.360 CH-36.650 CH-38.825 CH-39.050 CH-39.100 CH-39.300 CH-40.050 CH-40.250 CH-41.100 CH-41.700 CH-42.425 CH-42.650 CH-43.450 CH-43.650 CH-44.225 CH-44.500 CH-45.050 CH-45.325 CH-46.500 CH-46.875 CH-48.250 CH-48.560 CH-51.050 CH-51.350 CH-51.570 CH-52.050 CH-52.060 CH-52.400 CH-56.300 CH-56.500 CH-56.720 CH-58.380 CH-58.825 CH-59.400 CH-59.770 CH-60.650 CH-60.850 CH-61.075 CH-64.850 CH-65.180 CH-65.275 CH-65.500 CH-65.575 CH-65.700 CH-66.280 CH-66.575 CH-67.900 CH-68.180 CH-68.880 CH-69.300 CH-69.455 CH-69.840 CH-70.625 CH-70.880 CH-72.650 CH-72.890 CH-74.000 CH-74.280 CH-75.250 CH-75.650 CH-78.650 CH-79.000 CH-79.200 CH-79.480 CH-79.685 CH-79.900 CH-80.040 CH-80.500 CH-80.715 CH-80.880 CH-82.825 CH-83.815 CH-84.170 CH-84.225 CH-84.400 CH-84.400 CH-84.575 CH-84.575 CH-84.700 CH-86.200 CH-86.460 CH-86.700 CH-86.860 11 TA-1 0/000 1/350 1/450 41/560 41/600 46/000 46/050 50/650 50/700 52/900 53/000 57/500 57/600 59/500 59/600 77/100 77/150 81/300 81/375 81/400 82/500 82650 83/00 83/100 84/650 84/700 85/800 85/100

MORTH TCPL Annexure 5.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr No Sign Board Type Chainages of Sign Board 12 S-4 CH-26.450 CH-30.550 CH-37.875 CH-40.640 CH-49.000 CH-53.300 CH-56.275 CH-56.880 CH-57.150 CH-60.465 CH-60.600 CH-61.200 CH-61.360 CH-64.650 CH-66.700 CH-66.835 CH-78.250 CH-85.650 CH-85.884 CH-87.050

13 S-8 CH-00.250 CH-00.450 CH-00.500 CH-00.700 CH-01.300 CH-01.550 CH-02.100 CH-02.400 CH-03.340 CH-03.750 CH-12.850 CH-13.150 CH-13.925 CH-14.160 CH-14.325 CH-14.550 CH-14.950 CH-15.250 CH-16.350 CH-16.650 CH-16.900 CH-17.175 CH-18.900 CH-19.100 CH-19.150 CH-19.400 CH-21.500 CH-21.850 CH-22.110 CH-22.360 CH-23.200 CH-23.470 CH-23.950 CH-24.200 CH-24.300 CH-24.550 CH-24.565 CH-24.850 CH-25.100 CH-25.575 CH-27.300 CH-27.445 CH-27.446 CH-27.840 CH-27.850 CH-28.140 CH-30.750 CH-31.000 CH-32.360 CH-32.650 CH-34.560 CH-34.750 CH-34.950 CH-35.250 CH-35.300 CH-35.600 CH-36.360 CH-36.650 CH-38.825 CH-39.050 CH-39.100 CH-39.300 CH-40.050 CH-40.250 CH-41.100 CH-41.700 CH-42.425 CH-42.650 CH-43.450 CH-43.650 CH-44.225 CH-44.500 CH-45.050 CH-45.325 CH-46.500 CH-46.875 CH-48.250 CH-48.560 CH-51.050 CH-51.350 CH-51.570 CH-52.050 CH-52.060 CH-52.400 CH-56.300 CH-56.500 CH-56.720 CH-58.380 CH-58.825 CH-59.400 CH-59.770 CH-60.650 CH-60.850 CH-61.075 CH-64.850 CH-65.180 CH-65.275 CH-65.500 CH-65.575 CH-65.700 CH-66.280 CH-66.575 CH-67.900 CH-68.180 CH-68.880 CH-69.300 CH-69.455 CH-69.840 CH-70.625 CH-70.880 CH-72.650 CH-72.890 CH-74.000 CH-74.280 CH-75.250 CH-75.650 CH-78.650 CH-79.000 CH-79.200 CH-79.480 CH-79.685 CH-79.900 CH-80.040 CH-80.500 CH-80.715 CH-80.880 CH-82.825 CH-83.815 CH-84.170 CH-84.225 CH-84.400 CH-84.400 CH-84.575 CH-84.575 CH-84.700 CH-86.200 CH-86.460 CH-86.700 CH-86.860

14 S-17 3/550 3/050 23/600 23/700 25/450 26/650 27/550 27/650 35/850 35/890 40/850 40/920 46/500 46/900 55/100 55/150 60/180 60/200 76/100 76/090 79/900 80/020 83/850 83/880 86/600 86/700

MORTH TCPL Annexure 5.1/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Chainages of Sign Board Sr No Sign Board Type 86/675 86/615 85/766 85/600 85/634 85/531 85/420 84/530 15 S-23,16 84/420 84/400L 84/400R 84/380 84/220 83/205 83/100 82/900

82/770 82/700 82/710 82/640 82/515 82/420 82/360 82/220

82/116 81/800 81/700 81/590 81/500 81/210 81/100 81/050L

81/050R 81/000 80//830 80/420 80/570 76/980 76/868 76/800L

76/800R 76/745 76/605 76/210 76/080 73/287 73/045 69/910

69/820 69/015 68/900 68/800 68/700 67/546 67/473 67/400

67/238 66/454 66/325 66/224 66/105 64/256 64/080 63/949

63/874 63/630 63/575 63/425 63/280 61/820 61/700 69/400

57/415 53/400 53/530 53/175 53/025 52/955L 52/955R 52/895

52/790 50/920 50/775 50/740L 50/740R 49/288 49/087 47/472

47/375 46/210 46/092 45/975 45/863 43/840 43/625 43/740

43/420 43/500 43/231 43/200 43/099 41/900 41/925 41/768

41/647 41/568L 41/568R 41/550 41/380 39/175 39/035 38/939

38/810 38/540 38/340 38/220 38/140 37/640 37/435 37/460

37/300 36/800 36/720 34/190 34/025 33/925 33/215 33/250

MORTH TCPL Annexure 5.1/5 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Chainages of Sign Board Sr No Sign Board Type 26/250 26/035 25/860 23/100 22/830 22/980 22/700 18/625

18/575 17/650 17/450 17/420 17/250 15/250 15/220 12/400

12/300 12/200 12/020 11/680 11/620 11/530 11/380 10/025

9/970 9/650 9/660 9/600 9/450 9/120 7/825 7/100

6/820 6/900 6/700 6/000 5/820 5/780 5/620 5/300

5/040 1/610 1/500 1/425L 1/425R 1/400 1/240 0/155

0/056 0/000L 0/000R 0/000L-JN 0/000R-JN

16 S-25 13/800 25/770 25/850 64/180 64/450 78/780 78/880 17 S-31 CH-00.050 CH-00.200 CH-03.050 CH-03.300 CH-03.850 CH-04.150 CH-06.250 CH-06.550 CH-07.900 CH-08.150 CH-13.450 CH-13.750 CH-14.500 CH-14.800 CH-18.350 CH-18.700 CH-19.000 CH-19.100 CH-19.150 CH-19.450 CH-20.150 CH-20.400 CH-22.400 CH-22.700 CH-26.700 CH-26.950 CH-32.100 CH-32.400 CH-35.300 CH-35.550 CH-37.400 CH-37.750 CH-39.600 CH-39.850 CH-41.450 CH-41.800 CH-53.900 CH-54.200 CH-64.175 CH-64.400 CH-67.850 CH-68.100 CH-69.200 CH-69.450 CH-72.700 CH-73.100 CH-73.385 CH-73.580 CH-77.500 CH-77.800 CH-78.800 CH-79.050 CH-81.100 CH-81.300 CH-83.380 CH-83.575 18 S-32 CH-00.050 CH-00.200 CH-03.050 CH-03.300 CH-03.850 CH-04.150 CH-06.250 CH-06.550 CH-07.900 CH-08.150 CH-13.450 CH-13.750 CH-14.500 CH-14.800 CH-18.350 CH-18.700 CH-19.000 CH-19.100 CH-19.150 CH-19.450 CH-20.150 CH-20.400 CH-22.400 CH-22.700 CH-26.700 CH-26.950 CH-32.100 CH-32.400 CH-35.300 CH-35.550 CH-37.400 CH-37.750 CH-39.600 CH-39.850 CH-41.450 CH-41.800 CH-53.900 CH-54.200 CH-64.175 CH-64.400 CH-67.850 CH-68.100 CH-69.200 CH-69.450 CH-72.700 CH-73.100 CH-73.385 CH-73.580 CH-77.500 CH-77.800 CH-78.800 CH-79.050 CH-81.100 CH-81.300 CH-83.380 CH-83.575

MORTH TCPL Annexure 5.1/6 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr No Sign Board Type Chainages of Sign Board 19 S-37 16/620 16/850 25/700 25/820 68/160 68/220 84/450 84/620 20 S-37A 19/420 19/500 21/850 22/020 25/950 26/020 26/670 26/690 27/450 27/470 35/180 35/200 35/620 35/640 39/260 39/280 41/400 41/420 53/420 54/580 63/620 66/380 72/900 74/180 80/820 85/700 21 S-48 0/100 0/200 3/050 3/200 12/620 12/850 23/150 23/400 38/420 38/700 41/950 42/100 54/900 55/150 22 S-49 0/000 0/100 0/600 0/850 1/240 1/540 3/720 3/970 11/700 11/900 14/380 14/680 23/170 23/430 26/100 39/850 40/150 54/950 55/220 55/900 56/200 76/640 76/850 80/240 80/470 82/050 82/360 83/400 83/560 23 S-51 13/400 13/600 65/100 65/250 67/700 67/900 76/810 77/000 78/700 78/800

24 S-1 CH-03.387 CH-03.582 CH-25.428 CH-25.630 CH-46.577 CH-46.925 CH-49.876 CH-49.888

25 S-56 CH-00.000 CH-01.250 CH-01.650 CH-01.900 CH-05.650 CH-05.950 CH-06.400 CH-06.700 CH-06.800 CH-06.900 CH-06.950 CH-07.050 CH-07.950 CH-08.250 CH-09.500 CH-09.700 CH-09.750 CH-10.000 CH-10.500 CH-10.700 CH-11.450 CH-11.700 CH-12.100 CH-12.350 CH-13.700 CH-13.900 CH-13.950 CH-14.050 CH-14.350 CH-14.600 CH-16.700 CH-16.900 CH-17.350 CH-17.600 CH-17.800 CH-18.050 CH-19.050 CH-19.350 CH-22.150 CH-22.350 CH-22.800 CH-23.100 CH-24.150 CH-24.350 CH-25.050 CH-25.350 CH-25.650 CH-25.900 CH-27.300 CH-27.450 CH-28.150 CH-28.450 CH-29.450 CH-29.700 CH-31.450 CH-31.650 CH-31.700 CH-31.900 CH-32.175 CH-32.450 CH-33.850 CH-34.150 CH-36.100 CH-36.350 CH-37.300 CH-37.400 CH-37.450 CH-37.700 CH-38.200 CH-38.450 CH-38.850 CH-39.100 CH-39.650 CH-39.800 CH-41.350 CH-41.700 CH-42.300 CH-42.450 CH-43.150 CH-43.400 CH-43.560 CH-43.800 CH-43.900 CH-46.160 CH-48.350 CH-48.550 CH-48.555 CH-48.600 CH-49.150 CH-49.400 CH-50.600 CH-50.850 CH-52.800 CH-53.050 CH-53.100 CH-53.400 MORTH TCPL Annexure 5.1/7 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr No Sign Board Type Chainages of Sign Board CH-54.200 CH-54.460 CH-55.050 CH-55.250 CH-57.360 CH-57.650 CH-59.400 CH-59.800 CH-63.400 CH-63.650 CH-63.975 CH-64.200 CH-64.450 CH-66.450 CH-66.775 CH-66.800 CH-67.050 CH-67.600 CH-67.850 CH-68.050 CH-68.250 CH-68.400 CH-68.600 CH-69.000 CH-69.250 CH-69.400 CH-69.600 CH-73.450 CH-73.650 CH-75.300 CH-75.600 CH-77.000 CH-77.200 CH-78.880 CH-79.250 CH-79.450 CH-81.250 CH-81.450 CH-81.800 CH-82.050 CH-82.400 CH-82.575 CH-82.650 CH-82.860 CH-83.100 CH-84.220 CH-84.030 CH-84.600 CH-84.800 CH-85.800 CH-86.000

MORTH TCPL Annexure 5.1/8 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

RUMBLE STRIP

Sr No Proposed Chainage in 'Km' Village/ Town Rumble Strips at Entery of village/ town/ habbited area 1 4/250 NAGARIAVAS 2 6/200 BHERUVAS 3 6/600 BHERUVAS 4 7/750 PAKKA DHORA 5 8/150 PAKKA DHORA 6 10/150 SURATPURA 7 10/800 SURATPURA 8 12/750 MANDAWARI 9 14/800 MANDAWARI 10 18/300 DABAR 11 19/400 DABAR 12 20/200 NAGAR HEDA 13 20/900 NAGAR HEDA 14 22/000 KHEDALI 15 22/575 KHEDALI 16 24/000 PIPALAI 17 25/000 PIPALAI 18 26/800 BHATTA GAON 19 27/400 BHATTA GAON 20 31/675 KOYALA 21 32/325 KOYALA 22 35/200 THALI 23 35/510 THALI 24 37/450 BADHBICHALA 25 37/650 BADHBICHALA 26 39/200 JALOKHARA 27 39/850 JALOKHARA 28 52/800 GANGAJIKI KOTHI 29 54/650 GANGAJIKI KOTHI 30 56/600 SALEMPUR 31 57/300 SALEMPUR 32 63/800 KUDGAON 33 64/500 KUDGAON 34 65/225 MAHMEDPUR MAHMEDPUR 66/400 MORTH 35 TCPL Annexure 5.1/9 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr No Proposed Chainage in 'Km' Village/ Town 36 67/850 BIJALPUR 37 68/300 BIJALPUR 38 72/950 ASTHAL & ATTA 39 74/200 ASTHAL & ATTA 40 76/750 KAILADEVI ROAD 41 79/000 KAILADEVI ROAD 42 80/300 KAILADEVI ROAD 43 86/250 KAILADEVI ROAD Rumble Strips at substandard Curve Location 1 0/270 Lalsot 2 0/450 Lalsot 3 19/000 Dabar 4 19/290 Dabar 5 24/340 Piplai 6 24/500 Piplai Gangapur city 7 45/100 bypass Gangapur city 8 45/260 bypass Gangapur city 46/750 9 bypass Gangapur city 46/925 10 bypass Gangapur city 47/000 11 bypass Gangapur city 47/150 12 bypass Gangapur city 48/310 13 bypass Gangapur city 48/570 14 bypass 15 56/420 Salempur

MORTH TCPL Annexure 5.1/10 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

SPEED HUMP

Proposed No. of Sr Chainage Side Place speed No in ‘Km’ hump 1 5/800 LHS MEHERVAS 1 2 6/560 RHS KHAMAVAS 1 3 6/879 RHS SHAYAMPURA 1 4 6/997 LHS DATHAKALA 1 5 8/080 RHS KISHANPURA 1 6 9/628 LHS BINORI VILLAGE 1 7 9/860 RHS SURATHPURA 1 8 11/565 LHS PATTI KISHORPURA 1 9 12/238 LHS MAHRAJAPURA 1 10 12/238 RHS SHAYAMPURA 1 11 13/800 LHS HAMIPURA 1 12 14/477 RHS BASLAXMIPURA 1 13 16/785 LHS KHEDLA 1 14 17/485 RHS SARSALI VIILLAGE 1 15 19/205 LHS RAMNAGAR DOSHI 1 16 22/930 RHS VATODA 1 17 25/190 LHS SITAPURA 1 18 25/768 LHS BAMANVAS 1 19 28/300 LHS SITOD 1 20 29/577 RHS GURJAR BARODA 1 21 31/562 LHS RADHEKI 1 22 31/770 RHS CHHENOLI 1 23 34/000 RHS BAMAN BARODA 1 24 36/217 LHS KHUNTRA 1 25 37/350 RHS KANKAR RETI ROAD 1 26 37/503 LHS BADHBICHALA ROAD 1 27 38/315 LHS NAVIAKA BAD ROAD 1 28 39/010 LHS JALOKHARA 1 29 43/259 LHS ALIGANJ 1 30 43/259 RHS GANGAPUR CITY 1 31 43/685 LHS DOLATPURA ROAD 1 32 48/510 LHS NADAUTRI 1 33 48/510 LHS PILODA 1 34 53/252 LHS KHANPUR BARODA 1 35 56/700 RHS SALEMPUR 1 36 63/590 LHS RUNDI 1 MORTH TCPL Annexure 5.1/11 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Proposed No. of Sr. Chainage Side Place speed No in ‘Km’ hump 37 63/816 LHS SEVA 1 38 64/348 RHS SAPOTARA 1 39 66/620 RHS BARRIF 1 40 66/946 LHS BHADKYA 1 41 67/775 LHS MAKHANPUR 1 42 69/190 LHS MANDHI 1 43 71/715 LHS DALIPURA 1 44 71/735 RHS MANCH 1 45 73/600 LHS GUNASARA 1 46 75/460 LHS GOPALPUR ROAD 1 47 78/880 LHS VAJIRPUR 1 48 79/370 RHS BARKHEDA 1 49 81/987 RHS MANDRAYAL 1

DETAILS OF RETAINING WALL LHS Retaining wall RHS Retaining wall Sr No Pro. Chainages Km Sr No Pro. Chainages Km From To From To 1 23/450 23/510 1 23/600 23/649 2 23/683 23/800 2 27/800 27/850 3 23/600 23/649 3 29/450 29/500 4 27/400 27/530 4 45/160 45/190 5 27/530 27/584 5 45/920 46/155 6 27/624 27/750 6 60/910 61/000 7 34/750 34/850 7 61/000 61/060 8 35/500 35/550 8 61/075 61/170 9 35/550 35/600 9 76/100 76/121 10 35/600 35/650 10 76/170 76/200 11 35/650 35/750 11 76/275 76/325 12 35/750 35/800 12 83/800 83/850 13 36/000 36/050 13 83/850 83/900 14 42/540 42/570 14 83/900 83/911 15 45/920 46/155 15 83/919 83/950 16 61/075 61/150 16 83/950 84/000 17 83/800 83/850 17 84/000 84/050 18 83/850 83/900 18 84/050 84/125 19 83/900 83/911

MORTH TCPL Annexure 5.1/12 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

LHS Retaining wall RHS Retaining wall Sr No Sr No Pro. Chainages Km Pro. Chainages Km From To From To 20 83/919 83/950 21 83/950 84/000 22 84/000 84/050 23 84/050 84/125

ADDITIONAL RETAINING WALL LOCATION PROPOSED CHAINAGES

Sr No FROM TO REMARK

1 83/800 83/850 2 83/850 83/900 3 83/900 83/911 FOR THE PURPOSE OF DIVERSION 4 83/919 83/950 OF TRAFFIC 5 83/950 84/000 6 84/000 84/050 7 84/050 84/125 8 Junction at Ch. 57/600 at RHS of approach road 9 at both side of RHS approach road Junction at Ch 46/000 10 at both side of LHS approach road

GUARD RAILING Existing Proposed Sr. Chainage Km Chainage Km RAILING AT SCHOOL/HOSPITAL/TEMPLE No. FOOTPATH(m) LOCATIONS From To From To 1 0 1700 0 1700 3264 0 2 1700 4200 1700 4200 644 0 3 4200 5500 4200 5500 0 150 4 5500 6250 5500 6250 0 0 5 6250 6500 6250 6500 0 150 6 6500 7000 6500 7000 0 0 7 7000 7800 7000 7800 0 0 8 7800 8100 7800 8100 0 170 9 8100 10200 8100 10200 0 118 10 10200 10750 10200 10750 200 0 11 10750 11400 10750 11400 0 0 12 11400 12800 11400 12800 0 0

MORTH TCPL Annexure 5.1/13 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Existing Proposed Sr. Chainage Km Chainage Km RAILING AT SCHOOL/HOSPITAL/TEMPLE No. FOOTPATH(m) LOCATIONS From To From To 13 12800 14700 12800 14700 2881 131 14 14700 15200 14700 15200 0 169 15 15200 15700 15200 15700 0 0 16 15700 17000 15700 17000 0 0 17 17000 18300 17000 18300 0 0 18 18300 19000 18300 19000 0 150 19 19000 19400 19000 19400 705 0 20 19400 20200 19400 20200 0 0 21 20200 20900 20200 20900 0 150 22 20900 22050 20900 22050 50 0 23 22050 22570 22050 22570 1040 0 24 22570 24000 22570 24000 10 0 25 24000 24800 24000 24800 1569 0 26 24800 25200 24800 25200 785 0 27 25200 25840 25200 25840 1258 0 28 25840 26800 25840 26800 320 0 29 26800 27400 26800 27400 1185 0 30 27400 27800 27400 27800 0 0 31 27800 31690 27800 31690 0 0 32 31690 32310 31690 32310 0 135 33 32310 35220 32310 35220 0 0 34 35220 35510 35220 35510 573 0 35 35510 35740 35510 35740 0 0 36 35740 36090 35740 36090 0 0 37 36090 36500 36090 36500 0 0 38 36500 37000 36500 37000 0 0 39 37000 46250 37000 46250 935 125 40 46250 47200 46250 47200 0 25 41 47200 49330 47200 49330 0 150 42 0 210 49330 49540 0 0 43 210 1010 49540 50340 0 0 44 1010 1400 50340 50720 0 0 45 1400 1960 50720 51290 0 0 46 1960 2340 51290 51675 0 0 47 2340 2790 51675 52120 0 0 48 2790 3600 52120 52940 0 0 49 51550 53239 52940 54650 200 150 50 53239 53739 54650 55150 0 0 51 53739 54059 55150 55470 0 0 52 54059 55025 55470 56440 0 0 MORTH TCPL Annexure 5.1/14 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Existing Proposed Sr. Chainage Km Chainage Km RAILING AT SCHOOL/HOSPITAL/TEMPLE No. FOOTPATH(m) LOCATIONS From To From To 53 55025 55985 56440 57450 0 0 54 0 750 57450 58200 0 0 55 750 1350 58200 58800 0 0 56 1350 1550 58800 59000 0 0 57 1550 2250 59000 59700 0 0 58 58120 58620 59700 60200 0 0 59 58620 60440 60200 62020 0 0 60 60440 60940 62020 62520 0 0 61 60940 62220 62520 63800 0 0 62 62220 62920 63800 64500 1370 0 63 62920 63690 64500 65270 0 0 64 63690 64790 65270 66370 1740 0 65 64790 66290 66370 67870 0 0 66 66290 66720 67870 68300 0 150 67 66720 68670 68300 70250 0 0 68 68670 69220 70250 70800 0 0 69 69220 71170 70800 72750 0 0 70 71170 71390 72750 72970 80 0 71 71390 72590 72970 74170 400 0 72 72590 74320 74170 75900 0 300 73 74320 74770 75900 76350 0 0 74 74770 75200 76350 76780 0 0 75 75200 78200 76780 79780 76 78200 78720 79780 80300 790 50 77 78720 82170 80300 83750 48345 300 78 82170 82570 83750 84150 0 0 79 82570 84420 84150 86000 3210 150 80 84420 85390 86000 86970 0 0

MORTH TCPL Annexure 5.1/15 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

METAL BEAM CRASH BARRIER AT CURVE LOCATIONS Chainage (Km) Sr. No NO From To 1 34626.00 34745.00 1 2 36215.00 36297.00 1 3 60677.00 60737.00 1 4 64782.00 64835.00 1 5 15052.00 15122.00 1 6 68771.00 68838.00 1 7 69141.00 69206.00 1 8 69547.00 69768.00 1 9 86296.00 86442.00 1 10 86691.00 86820.00 1 11 38936.00 39015.00 1 12 39150.00 39217.00 1 13 42526.00 42601.00 1 14 44380.00 44443.00 1 15 45095.00 45256.00 1 16 48318.00 48500.00 1 17 66410.00 66479.00 1 18 78748.00 78926.00 1 19 79362.00 79442.00 1 20 25308.00 25376.00 1 21 46644.00 46705.00 1 a) At Realignment 1 27666.00 27756.00 1

2 30825.00 30902.00 1

3 60869.00 60947.00 1 4 64961.00 65068.00 1 5 72802.00 72893.00 1 6 75399.00 75491.00 1 7 79774.00 79895.00 1 b) At Gangapur Bypass 1 51863.00 51966.00 1 2 52157.00 52284.00 1 A METAL BEAM CRASH BARRIER FOR STRUCTURE 1 Major bridge 1

MORTH TCPL Annexure 5.1/16 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

2 Approaches 1 3 Minor bridge 1 4 Box culvert 1 B Pond Lcations (Exst. Km.) 1 1 9/400 (LHS pond with Earthen bund) 1 2 19/100 (LHS pond with Earthen bund) 1 3 31/450 (RHS) 1 4 34/750 (RHS) 1 5 43/400 (RHS pond with Earthen bund) 1 6 52/520 (RHS Gangapur Bypass) 1 7 71/000 (RHS pond with Earthen bund) 1 8 78/800 (RHS pond with Earthen bund) 1

Zebra Crossing at School Locations

Sr.No. Existing Chainage Side Location

1 0/450 LHS Cinema hall 2 3/150 LHS Secondary School B.Ed Collage 3 4/000 RHS Higher Secondary School 4 6/400 RHS Adarsh Indian Primary School 5 8/000 LHS Primary School 6 13/550 LHS Civil Hospital 7 13/650 RHS School 8 14/700 LHS Govt. Primary School 9 19/050 RHS Govt. Primary School 10 20/300 LHS Govt. Primary School 11 32/250 LHS Govt. Primary School 12 35/400 LHS Primary School 13 37/450 RHS School 14 37/600 RHS Govt. Primary School 15 39/700 RHS Adarsha Primary School 16 48/790 RHS Shriji I.T.I. 17 62/750 RHS Higher Secondary School 18 66/425 RHS Govt. Primary school 19 66/700 RHS Grampanchyayat 20 71/425 LHS Govt. Primary school Bijalpur 21 71/950 LHS Primary school Ata 22 76/070 RHS Govt. Primary school 23 77/359 RHS School 24 78/215 RHS I.T.I. Collage

MORTH TCPL Annexure 5.1/17 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Zebra Crossing at Junctions

Sr. No. Chainage Side Location 1 00/00 RHS Lalsot 2 1/440 RHS Sawai Madhopur 3 5/770 LHS Mehervas 4 6/855 LHS Shahpura village 5 8/060 RHS Kishanpura 6 9/610 LHS Binori Village 7 11/550 LHS Pati Kishorpura 8 12/220 RHS/LHS Shampura ,Mahrajapura 9 13/770 LHS Hamirpura 10 14/460 RHS Baslaxmipura 11 16/765 LHS Khanpur Village 12 17/470 RHS Sirsali Village 13 19/180 RHS Ramjanipura 14 19/190 LHS Ramnagar Dosi 15 22/915 RHS Vatoda 16 25/180 LHS Sitapur 17 25/750 LHS Bamanvas 18 28/280 LHS Sitod 19 29/560 RHS Gujar badoda 20 31/550 LHS Radheki 21 33/980 RHS Baman Badoda 22 36/200 LHS Khutla 23 37/340 RHS Kakaerthi 24 37/490 LHS Badvichla 25 37/560 RHS Aarniya 26 38/300 LHS Badkhurd 27 38/995 LHS Jalokhara 28 41/550 RHS Gangapur city 29 43/250 LHS/RHS Aliganj ,Mirajapur 30 43/665 LHS Daulatpur 31 46/025 LHS/RHS Nadhota, Gangapur city 32 48/460 LHS Piloda 33 49/280 RHS Gangapur city 34 50/400 LHS Hindaun 35 51/950 RHS Khanpur Badoda, Gangapur city 36 51/670 RHS Khanpur Baroda 37 52/000 LHS Salempur 38 61/940 LHS Rundi 39 62/180 LHS Dalalpura 40 62/720 RHS Sapotara 41 64/990 RHS Barif 42 65/370 LHS Bhadka 43 66/150 LHS Makhanpur

MORTH TCPL Annexure 5.1/18 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in SIA and RAP the State of Rajasthan Annexure – 5.1

Sr. No. Chainage Side Location 44 67/570 LHS Madai 45 70/140 LHS Petoli 46 70/155 RHS Manchi 47 72/030 LHS Gunesara 48 72/150 RHS Taroli 49 73/900 LHS Goplapursay 50 75/530 RHS Kailadevi Road 51 77/240 LHS Vajirpur 52 77/755 RHS Barkheda 53 79/800 RHS Mandaryal 54 80/450 RHS Mandaryal 55 81/050 RHS Mandaryal 56 81/450 RHS, LHS Karauli City,Mandaryal 57 83/110 RHS Karauli City 58 84/280 LHS Hindaun

MORTH TCPL Annexure 5.1/19 20

PROJECT ROAD NH-11B

PROJECT ROAD NH-11B

'A' TYP. 20

TRAFFIC DIVERSION DURING CONSTRUCTION, WHERE TRAFFIC CAN BE PASSED OVER PART WIDTH.

DETAILS AT 'A'

MINISTRY OF ROAD TRANSPORT & HIGHWAYS TYPICAL DRAWING FOR Government of India TRAFFIC DIVERSION DURING ROAD CONSTRUCTION REHABILITATION AND UPGRADING TO 2 LANES / 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF LALSOT - KARAULI SECTION (KM 0 - KM 85) OF NH - 11B IN THE STATE OF RAJASTHAN ( PACKAGE NO. SP/C/4) DIVERSION 20 VERSION I S R E IV D GO SLOWGO SI ON IVER D HED A

WORK AREA

PROJECT ROAD NH-11B PROJECT ROAD NH-11B

'X' TYP. A HED D IVER SI ON GO SLOW 20 D IVERSION

'Y' TYP. TRAFFIC DIVERSION DURING RECONSTRUCTION OF C. D. WORKS, MINOR BRIDGE DIVERSION DIVERSION AHED GO SLOW

DETAILS AT 'X' DETAILS AT 'Y'

MINISTRY OF ROAD TRANSPORT & HIGHWAYS TYPICAL DRAWING FOR Government of India TRAFFIC DIVERSION DURING RECONSTRUCTION OF C.D. WORK REHABILITATION AND UPGRADING TO 2 LANES / 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF LALSOT - KARAULI SECTION (KM 0 - KM 85) OF NH - 11B IN THE STATE OF RAJASTHAN ( PACKAGE NO. SP/C/4) SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

LIST OF PAP’S

DATA ENTRY FORMAT FOR PRIVATE STRUCTURE ( Temporary ,Semi-Permanent and Permanent)

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST RHS) of Village SC OBC Other Pucca Pucca Kachcha Kachcha Squarters Residential Title Holder Title commercial Semi Pucca Semi Pucca comm+Resi Enchroachers Women Headed Backward Class Backward 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Pathani Brother 1 PP1 0/000 RHS Lalsot 1 1 11.40 1 1 (shop) Suresh kumar Sharma Mandavar 2 PS2 13/650 RHS 1 1 16.20 Compound Wall 1 1 i Private School ht.2.0m Madanmohan 3 PS3 19/150 RHS Dabar 1 1 12.32 Brajmohan 1 1 Sharma Vinod Mulchand 4 PS4 19/165 RHS Dabar 1 1 14.45 1 1 Sharma Kalyansingh 5 PS5 22/150 LHS Khedali 1 1 27.94 Brajvasisingh 1 1 Gujjar Veersingh 6 PS6 22/210 RHS Khedali 1 1 48.00 Hukamsingh 1 1 Gujjar Ramkesh 7 PS7 22/235 LHS Khedali 1 1 7.50 1 1 Chiranjilal Gujjar

MORTH TCPL Annexure6.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Ghansham 8 PK8 22/220 RHS Khedali 1 1 18.90 Radhakishan 1 1 Sharma Dilip Shivprasad 9 PS9 22/300 RHS Khedali 1 1 10.20 1 1 Gujjar

Visharamsingh 10 PS10 22/335 RHS Khedali 1 1 42.00 1 1 Prasadilal Gujjar

Ramprasad Kallu 11 PP11 24/265 RHS Piplai 1 1 15.30 1 1 Mali

Ramcharan 12 PS12 24/307 RHS Piplai 1 1 10.00 1 1 Gopali Mali Ghansham 13 PS13 24/350 RHS Piplai 1 1 10.50 Ramsahay 1 1 Khandlewal Payresingh 14 PK14 24/400 LHS Piplai 1 1 3.30 1 1 Ramsahay Gujjar Narendrakumar 15 PS15 24/480 RHS Piplai 1 1 18.00 Laxminarayan 1 1 Sharma Ramsawroop 16 PP16 24/500 RHS Piplai 1 1 8.50 1 1 Sharma

MORTH TCPL Annexure6.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Harishankar 17 PK17 24/545 LHS Piplai 1 1 25.30 Shrinarayan 1 1 Uppdhaya Kedarprasad 18 PS18 24/600 LHS Piplai 1 1 30.00 1 1 Ghudamal Joshi

Kedarprasad 19 PP19 24/625 RHS Piplai 1 1 26.00 1 1 Surajmal Gupta

20 PS20 24/620 LHS Piplai 1 1 18.00 Purushottam Joshi 1 1

Mukeshkumar 21 PS21 24/620 RHS Piplai 1 1 24.00 Shambhudayal 1 1 Sharma Radhesham 22 PS22 24/650 LHS Piplai 1 1 15.00 Ramswaroop 1 1 Joshi Dharamsingh 23 PS23 24/670 RHS Piplai 1 1 9.00 Pukharaj Gujjar 1 1 Piplai Sunil Sharma and Khanpur 24 PS24 51/020 LHS 1 1 79.38 Ghansham 1 1 Baroda Bawariya Khanpur Battilal Meena 25 PS25 51/040 RHS 1 1 137.75 1 1 Baroda Sapotara

MORTH TCPL Annexure6.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Khanpur Laxminarayan 26 PS26 51/270 RHS 1 1 420.36 1 1 Baroda Gujjar

Khanpur Kousaliya Hari 27 PS27 51/960 LHS 1 1 40.00 1 1 Baroda Saini

Khanpur Moharsingh Nathu 28 PK28 52/700 RHS 1 1 24.00 1 1 Baroda Mali

Khanpur 185.0 29 PK29 52/780 LHS 1 1 Sukharam Mali 1 1 Baroda 0

Khanpur 30 PK30 52/790 LHS 1 1 45.20 Sukharam Mali 1 1 Baroda

Khanpur 31 PK31 52/795 LHS 1 1 2.68 Sukharam Mali 1 1 Baroda

Abdul Samad 32 PK32 56/620 RHS Salempur 1 1 13.00 1 1 Khan

33 PS33 56/655 LHS Salempur 1 1 23.68 Jamil Nur Khan 1 1

Vinodkumar 34 PP34 56/670 RHS Salempur 1 1 20.40 Soni+Pitambar 1 1 Soni Radheshyam 35 PS35 56/730 RHS Salempur 1 1 7.40 Devnarayan 1 1 Sharma MORTH TCPL Annexure6.1/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Dindayal 36 PK36 56/715 RHS Salempur 1 1 20.40 Devnarayan 1 1 Sharma Radheshyam Devnarayan 37 PP37 56/765 LHS Salempur 1 1 1.58 Sharma+ Dindayal 1 1 Devnarayan Sharma Ramswroop 38 PK38 56/770 RHS Salempur 1 1 36.54 1 1 Mahesh Meena

39 PK39 56/780 LHS Salempur 1 1 7.06 Vijaysinh Rajput 1 1

Suraj 40 PP40 56/810 LHS Salempur 1 1 58.09 Madanmohan 1 1 Gupta Baliprasad,Ompra 41 PK41 56/815 RHS Salempur 1 1 23.50 kash,Bajran 1 1 Sharma Ramsahay 42 PS42 56/845 RHS Salempur 1 1 33.35 1 1 Bhorilal Sharma

43 PP43 56/850 LHS Salempur 1 1 23.20 Naval Gupta 1 1

MORTH TCPL Annexure6.1/5 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name s

RHS) of Village ST SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroacher

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

44 PP44 56/860 LHS Salempur 1 1 22.27 Suraj Gupta 1 1

45 PP45 56/870 LHS Salempur 1 1 36.00 Mohanlal Gupta 1 1

Omprakash 46 PK46 56/870 RHS Salempur 1 1 7.70 1 1 Sharma Baliprasad 47 PS47 56/875 RHS Salempur 1 1 12.80 Sharma and 1 1 Vishanu Sharma Jagdish 48 PP48 56/885 LHS Salempur 1 1 41.40 Gupta,Neeraj 1 1 Gupta

49 PP49 56/885 RHS Salempur 1 1 13.90 Damodarlal Gupta 1 1

Bhagwansahay 50 PP50 56/900 LHS Salempur 1 1 28.20 1 1 Baliprasad Gupta

Radheshyam 51 PP51 56/910 LHS Salempur 1 1 15.20 1 1 Sharma

52 PS52 56/910 RHS Salempur 1 1 14.60 Mahesh Gupta 1 1

MORTH TCPL Annexure6.1/6 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

53 PK53 56/915 RHS Salempur 1 1 4.50 Kailash Jogi 1 1

54 PP54 56/920 RHS Salempur 1 1 12.50 Zuber Khan 1 1

Shambhudayal 55 PK55 56/920 LHS Salempur 1 1 0.80 1 1 Sharma

56 PP56 56/930 RHS Salempur 1 1 18.80 Trilokchand Gupta 1 1

Durgaprasad 57 PK57 56/945 LHS Salempur 1 1 7.50 1 1 Sharma

Jagmohan 58 PP58 56/950 RHS Salempur 1 1 37.25 1 1 Sharma

59 PS59 56/960 RHS Salempur 1 1 23.30 Barasingh lal 1 1

Giriraj Prasad 60 PP60 56/960 LHS Salempur 1 1 27.89 1 1 Sharma

61 PP61 56/975 LHS Salempur 1 1 4.21 Motilal Gupta 1 1

62 PP62 56/975 RHS Salempur 1 1 14.30 Babulal Sharma 1 1

MORTH TCPL Annexure6.1/7 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

63 PP63 56/980 RHS Salempur 1 1 16.25 Umar Khan 1 1

64 PP64 57/000 LHS Salempur 1 1 3.50 Harun Khan 1 1

65 PS65 57/010 RHS Salempur 1 1 14.15 Jamil Khan 1 1

Mahamad Sampantsingh 66 PS66 65/400 LHS 1 1 24.15 1 1 pur Moharsingh Jat

Mahamad 67 PS67 65/400 RHS 1 1 12.50 Suresh Jogi 1 1 pur

Mahamad Murari Parmali 68 PS68 65/410 RHS 1 1 11.05 1 1 pur Jogi

Mahamad Dharamsingh 69 PS69 65/425 RHS 1 1 13.50 1 1 pur Sardarsingh Jat

Mahamad Prabhu 70 PP70 65/450 LHS 1 1 19.78 1 1 pur Sonnarayan Jat

Mahamad Shivcharan Ramji 71 PS71 65/450 RHS 1 1 15.75 1 1 pur Jogi

MORTH TCPL Annexure6.1/8 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Bhavanishankar Mahamad 72 PS72 65/475 RHS 1 1 16.56 Shrigulabcahnd 1 1 pur Sharma Mahamad Attarsingh 73 PS73 65/500 RHS 1 1 5.00 1 1 pur Ramkhiladi Jat

Mahamad Raju Giriraj 74 PS74 65/500 LHS 1 1 13.44 1 1 pur Prasad Gupta

Mahamad Gharasing 75 PS75 65/500 LHS 1 1 3.35 1 1 pur Kisanlal Jat

Mahamad 76 PS76 65/500 RHS 1 1 13.00 Shivcharan Gupta 1 1 pur

Mahamad 77 PS77 65/550 LHS 1 1 23.20 Manoj Kumar 1 1 pur

Mahamad Girij Naniga 78 PS78 65/550 LHS 1 1 10.58 1 1 pur Sharma

Mahamad Madan Mohan 79 PK79 65/557 LHS 1 1 48.60 1 1 pur Ramful Mali

Mahamad Rambabu Murali 80 PP80 65/527 RHS 1 1 30.00 1 1 pur Gupta

MORTH TCPL Annexure6.1/9 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name rs

RHS) of Village ST SC OBC Class Other Pucca Pucca Headed Women Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial Semi Pucca Semi Pucca comm+Resi Enchroache 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Mahamad Madanmohan 81 PS81 65/525 LHS 1 1 8.70 1 1 pur Ramsahay Jangid

Mahamad Rameshwar 82 PS82 65/540 RHS 1 1 22.50 1 1 pur Mulchand Gupta Sureshchand Mahamad 83 PS83 65/525 LHS 1 1 68.80 Ramnarayan 1 1 pur Sharma Mahamad Omprakash 84 PP84 65/555 RHS 1 1 6.00 1 1 pur Mashrilal Gupta

Mahamad Sukhram 85 PS85 65/555 RHS 1 1 36.00 1 1 pur Shrikanchan Mali

Mahamad 86 PS86 65/600 LHS 1 1 55.00 Kelu Ghalita Ramji 1 1 pur

Mahamad Ramniwas Jaylal 87 PK87 65/600 RHS 1 1 3.00 1 1 pur Mali

Mahamad Devising 88 PS88 65/600 RHS 1 1 5.00 1 1 pur Ramcharan Mali

Mahamad Omprakash 89 PS89 65/600 RHS 1 1 25.50 1 1 pur Kedarnath jangid

Mahamad Pandit .Balcharan 90 PS90 65/640 RHS 1 1 6.24 1 1 pur Joshi

MORTH TCPL Annexure6.1/10 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Mahamad Mohan Kedar 91 PP91 65/645 RHS 1 1 27.60 1 1 pur Gupta

Mahamad Ramkhiladi Genda 92 PS92 65/650 LHS 1 1 6.50 1 1 pur Mali

Mahamad Ramdayal 93 PK93 65/650 RHS 1 1 8.40 1 1 pur Kedarlal Gupta Maheshchandra Mahamad 94 PK94 65/675 RHS 1 1 8.40 Giraj Prasad 1 1 pur Sharma Mishrilal Arosilal 95 PP95 73/050 LHS Astal 1 1 9.60 1 1 Mali

Mohan Pyarilal 96 PK96 73/800 RHS Atta 1 1 6.25 1 1 Mali

Babu Pratap 97 PK97 73/850 RHS Atta 1 1 17.00 1 1 Singh Charan Singh 98 PS98 73/850 RHS Atta 1 1 22.40 Madan Singh 1 1 Jardon

99 PS99 73/800 LHS Atta 1 1 9.00 Mamraj Jain 1 1

MORTH TCPL Annexure6.1/11 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Shivcharan 100 PK100 78/010 RHS Barkheda 1 1 71.00 1 1 Kashinath Mali

Centr 101 PP101 78/450 Barkheda 1 1 11.56 Abundant Shop 1 1 e 502.5 1605.6 588.0 Total 28 53 20 27 51 23 0 1 100 0 0 4 35 62 9 9 3

MORTH TCPL Annexure6.1/12 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

LIST OF PAP’S

DATA ENTRY FORMAT FOR PRIVATE STRUCTURE ( Temporary ,Semi-Permanent and Permanent)

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST RHS) of Village SC OBC Other Pucca Pucca Kachcha Kachcha Squarters Residential Title Holder Title commercial Semi Pucca Semi Pucca comm+Resi Enchroachers Women Headed Backward Class Backward 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Pathani Brother 1 PP1 0/000 RHS Lalsot 1 1 11.40 1 1 (shop) Suresh kumar Sharma Mandavar 2 PS2 13/650 RHS 1 1 16.20 Compound Wall 1 1 i Private School ht.2.0m Madanmohan 3 PS3 19/150 RHS Dabar 1 1 12.32 Brajmohan 1 1 Sharma Vinod Mulchand 4 PS4 19/165 RHS Dabar 1 1 14.45 1 1 Sharma Kalyansingh 5 PS5 22/150 LHS Khedali 1 1 27.94 Brajvasisingh 1 1 Gujjar Veersingh 6 PS6 22/210 RHS Khedali 1 1 48.00 Hukamsingh 1 1 Gujjar Ramkesh 7 PS7 22/235 LHS Khedali 1 1 7.50 1 1 Chiranjilal Gujjar

MORTH TCPL Annexure6.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Ghansham 8 PK8 22/220 RHS Khedali 1 1 18.90 Radhakishan 1 1 Sharma Dilip Shivprasad 9 PS9 22/300 RHS Khedali 1 1 10.20 1 1 Gujjar

Visharamsingh 10 PS10 22/335 RHS Khedali 1 1 42.00 1 1 Prasadilal Gujjar

Ramprasad Kallu 11 PP11 24/265 RHS Piplai 1 1 15.30 1 1 Mali

Ramcharan 12 PS12 24/307 RHS Piplai 1 1 10.00 1 1 Gopali Mali Ghansham 13 PS13 24/350 RHS Piplai 1 1 10.50 Ramsahay 1 1 Khandlewal Payresingh 14 PK14 24/400 LHS Piplai 1 1 3.30 1 1 Ramsahay Gujjar Narendrakumar 15 PS15 24/480 RHS Piplai 1 1 18.00 Laxminarayan 1 1 Sharma Ramsawroop 16 PP16 24/500 RHS Piplai 1 1 8.50 1 1 Sharma

MORTH TCPL Annexure6.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Harishankar 17 PK17 24/545 LHS Piplai 1 1 25.30 Shrinarayan 1 1 Uppdhaya Kedarprasad 18 PS18 24/600 LHS Piplai 1 1 30.00 1 1 Ghudamal Joshi

Kedarprasad 19 PP19 24/625 RHS Piplai 1 1 26.00 1 1 Surajmal Gupta

20 PS20 24/620 LHS Piplai 1 1 18.00 Purushottam Joshi 1 1

Mukeshkumar 21 PS21 24/620 RHS Piplai 1 1 24.00 Shambhudayal 1 1 Sharma Radhesham 22 PS22 24/650 LHS Piplai 1 1 15.00 Ramswaroop 1 1 Joshi Dharamsingh 23 PS23 24/670 RHS Piplai 1 1 9.00 Pukharaj Gujjar 1 1 Piplai Sunil Sharma and Khanpur 24 PS24 51/020 LHS 1 1 79.38 Ghansham 1 1 Baroda Bawariya Khanpur Battilal Meena 25 PS25 51/040 RHS 1 1 137.75 1 1 Baroda Sapotara

MORTH TCPL Annexure6.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Khanpur Laxminarayan 26 PS26 51/270 RHS 1 1 420.36 1 1 Baroda Gujjar

Khanpur Kousaliya Hari 27 PS27 51/960 LHS 1 1 40.00 1 1 Baroda Saini

Khanpur Moharsingh Nathu 28 PK28 52/700 RHS 1 1 24.00 1 1 Baroda Mali

Khanpur 185.0 29 PK29 52/780 LHS 1 1 Sukharam Mali 1 1 Baroda 0

Khanpur 30 PK30 52/790 LHS 1 1 45.20 Sukharam Mali 1 1 Baroda

Khanpur 31 PK31 52/795 LHS 1 1 2.68 Sukharam Mali 1 1 Baroda

Abdul Samad 32 PK32 56/620 RHS Salempur 1 1 13.00 1 1 Khan

33 PS33 56/655 LHS Salempur 1 1 23.68 Jamil Nur Khan 1 1

Vinodkumar 34 PP34 56/670 RHS Salempur 1 1 20.40 Soni+Pitambar 1 1 Soni Radheshyam 35 PS35 56/730 RHS Salempur 1 1 7.40 Devnarayan 1 1 Sharma MORTH TCPL Annexure6.1/4 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Dindayal 36 PK36 56/715 RHS Salempur 1 1 20.40 Devnarayan 1 1 Sharma Radheshyam Devnarayan 37 PP37 56/765 LHS Salempur 1 1 1.58 Sharma+ Dindayal 1 1 Devnarayan Sharma Ramswroop 38 PK38 56/770 RHS Salempur 1 1 36.54 1 1 Mahesh Meena

39 PK39 56/780 LHS Salempur 1 1 7.06 Vijaysinh Rajput 1 1

Suraj 40 PP40 56/810 LHS Salempur 1 1 58.09 Madanmohan 1 1 Gupta Baliprasad,Ompra 41 PK41 56/815 RHS Salempur 1 1 23.50 kash,Bajran 1 1 Sharma Ramsahay 42 PS42 56/845 RHS Salempur 1 1 33.35 1 1 Bhorilal Sharma

43 PP43 56/850 LHS Salempur 1 1 23.20 Naval Gupta 1 1

MORTH TCPL Annexure6.1/5 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name s

RHS) of Village ST SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroacher

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

44 PP44 56/860 LHS Salempur 1 1 22.27 Suraj Gupta 1 1

45 PP45 56/870 LHS Salempur 1 1 36.00 Mohanlal Gupta 1 1

Omprakash 46 PK46 56/870 RHS Salempur 1 1 7.70 1 1 Sharma Baliprasad 47 PS47 56/875 RHS Salempur 1 1 12.80 Sharma and 1 1 Vishanu Sharma Jagdish 48 PP48 56/885 LHS Salempur 1 1 41.40 Gupta,Neeraj 1 1 Gupta

49 PP49 56/885 RHS Salempur 1 1 13.90 Damodarlal Gupta 1 1

Bhagwansahay 50 PP50 56/900 LHS Salempur 1 1 28.20 1 1 Baliprasad Gupta

Radheshyam 51 PP51 56/910 LHS Salempur 1 1 15.20 1 1 Sharma

52 PS52 56/910 RHS Salempur 1 1 14.60 Mahesh Gupta 1 1

MORTH TCPL Annexure6.1/6 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

53 PK53 56/915 RHS Salempur 1 1 4.50 Kailash Jogi 1 1

54 PP54 56/920 RHS Salempur 1 1 12.50 Zuber Khan 1 1

Shambhudayal 55 PK55 56/920 LHS Salempur 1 1 0.80 1 1 Sharma

56 PP56 56/930 RHS Salempur 1 1 18.80 Trilokchand Gupta 1 1

Durgaprasad 57 PK57 56/945 LHS Salempur 1 1 7.50 1 1 Sharma

Jagmohan 58 PP58 56/950 RHS Salempur 1 1 37.25 1 1 Sharma

59 PS59 56/960 RHS Salempur 1 1 23.30 Barasingh lal 1 1

Giriraj Prasad 60 PP60 56/960 LHS Salempur 1 1 27.89 1 1 Sharma

61 PP61 56/975 LHS Salempur 1 1 4.21 Motilal Gupta 1 1

62 PP62 56/975 RHS Salempur 1 1 14.30 Babulal Sharma 1 1

MORTH TCPL Annexure6.1/7 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

63 PP63 56/980 RHS Salempur 1 1 16.25 Umar Khan 1 1

64 PP64 57/000 LHS Salempur 1 1 3.50 Harun Khan 1 1

65 PS65 57/010 RHS Salempur 1 1 14.15 Jamil Khan 1 1

Mahamad Sampantsingh 66 PS66 65/400 LHS 1 1 24.15 1 1 pur Moharsingh Jat

Mahamad 67 PS67 65/400 RHS 1 1 12.50 Suresh Jogi 1 1 pur

Mahamad Murari Parmali 68 PS68 65/410 RHS 1 1 11.05 1 1 pur Jogi

Mahamad Dharamsingh 69 PS69 65/425 RHS 1 1 13.50 1 1 pur Sardarsingh Jat

Mahamad Prabhu 70 PP70 65/450 LHS 1 1 19.78 1 1 pur Sonnarayan Jat

Mahamad Shivcharan Ramji 71 PS71 65/450 RHS 1 1 15.75 1 1 pur Jogi

MORTH TCPL Annexure6.1/8 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Bhavanishankar Mahamad 72 PS72 65/475 RHS 1 1 16.56 Shrigulabcahnd 1 1 pur Sharma Mahamad Attarsingh 73 PS73 65/500 RHS 1 1 5.00 1 1 pur Ramkhiladi Jat

Mahamad Raju Giriraj 74 PS74 65/500 LHS 1 1 13.44 1 1 pur Prasad Gupta

Mahamad Gharasing 75 PS75 65/500 LHS 1 1 3.35 1 1 pur Kisanlal Jat

Mahamad 76 PS76 65/500 RHS 1 1 13.00 Shivcharan Gupta 1 1 pur

Mahamad 77 PS77 65/550 LHS 1 1 23.20 Manoj Kumar 1 1 pur

Mahamad Girij Naniga 78 PS78 65/550 LHS 1 1 10.58 1 1 pur Sharma

Mahamad Madan Mohan 79 PK79 65/557 LHS 1 1 48.60 1 1 pur Ramful Mali

Mahamad Rambabu Murali 80 PP80 65/527 RHS 1 1 30.00 1 1 pur Gupta

MORTH TCPL Annexure6.1/9 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name rs

RHS) of Village ST SC OBC Class Other Pucca Pucca Headed Women Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial Semi Pucca Semi Pucca comm+Resi Enchroache 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Mahamad Madanmohan 81 PS81 65/525 LHS 1 1 8.70 1 1 pur Ramsahay Jangid

Mahamad Rameshwar 82 PS82 65/540 RHS 1 1 22.50 1 1 pur Mulchand Gupta Sureshchand Mahamad 83 PS83 65/525 LHS 1 1 68.80 Ramnarayan 1 1 pur Sharma Mahamad Omprakash 84 PP84 65/555 RHS 1 1 6.00 1 1 pur Mashrilal Gupta

Mahamad Sukhram 85 PS85 65/555 RHS 1 1 36.00 1 1 pur Shrikanchan Mali

Mahamad 86 PS86 65/600 LHS 1 1 55.00 Kelu Ghalita Ramji 1 1 pur

Mahamad Ramniwas Jaylal 87 PK87 65/600 RHS 1 1 3.00 1 1 pur Mali

Mahamad Devising 88 PS88 65/600 RHS 1 1 5.00 1 1 pur Ramcharan Mali

Mahamad Omprakash 89 PS89 65/600 RHS 1 1 25.50 1 1 pur Kedarnath jangid

Mahamad Pandit .Balcharan 90 PS90 65/640 RHS 1 1 6.24 1 1 pur Joshi

MORTH TCPL Annexure6.1/10 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Mahamad Mohan Kedar 91 PP91 65/645 RHS 1 1 27.60 1 1 pur Gupta

Mahamad Ramkhiladi Genda 92 PS92 65/650 LHS 1 1 6.50 1 1 pur Mali

Mahamad Ramdayal 93 PK93 65/650 RHS 1 1 8.40 1 1 pur Kedarlal Gupta Maheshchandra Mahamad 94 PK94 65/675 RHS 1 1 8.40 Giraj Prasad 1 1 pur Sharma Mishrilal Arosilal 95 PP95 73/050 LHS Astal 1 1 9.60 1 1 Mali

Mohan Pyarilal 96 PK96 73/800 RHS Atta 1 1 6.25 1 1 Mali

Babu Pratap 97 PK97 73/850 RHS Atta 1 1 17.00 1 1 Singh Charan Singh 98 PS98 73/850 RHS Atta 1 1 22.40 Madan Singh 1 1 Jardon

99 PS99 73/800 LHS Atta 1 1 9.00 Mamraj Jain 1 1

MORTH TCPL Annexure6.1/11 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA &RAP Annexure-6.1

Type of Type of Built up Area ( Sqm) Type of PAHs Social Category Structure Construction Side Name of PHAs ( Sr. Str Chaina (LHS Name of Head of Family / No. No. ge (KM) / Village owner ) & Name ST

RHS) of Village SC OBC Class Other Pucca Pucca Women Headed Kachcha Kachcha Squarters Backward Residential Title Holder Title commercial comm+Resi Semi Pucca Semi Pucca Enchroachers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Shivcharan 100 PK100 78/010 RHS Barkheda 1 1 71.00 1 1 Kashinath Mali

Centr 101 PP101 78/450 Barkheda 1 1 11.56 Abundant Shop 1 1 e 502.5 1605.6 588.0 Total 28 53 20 27 51 23 0 1 100 0 0 4 35 62 9 9 3

MORTH TCPL Annexure6.1/12 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of SIA and RAP NH – 11B in the State of Rajasthan Annexure-7.1

List of Common Properties on NH-11B

DATA ENTRY FORMAT FOR Community / Govt. Structure

Structure Name of Type of Construction Built up Area ( Sqm) Cenus Side Fully Name of Str Chainage Name of Community / Sr.No. Survey (LHS Affected Property No. (KM) Village Govt. Semi Semi Code / RHS) Pucca Kachcha / Partially Pucca Kachcha Holder Structure Pucca Pucca Affected 1 2 3 4 5 6 7 8 9 10 11 RJSPC4112 1 CK1 19/100 LHS Dabar Pir baba 1 Fully 6.72 Community C 00001 Gram RJSPC4112 2 CS2 19/100 LHS Dabar panchayat 1 Partially 13.60 Government C 00002 Dabar RJSPC4112 3 CP3 19/560 LHS Dabar Handpump 1 Fully Government C 00003 RJSPC4112 4 CP4 21/050 RHS Khedali Handpump 1 Fully Government C 00004 RJSPC4112 5 CK5 22/100 RHS Khedali Samadhi 1 Fully 5.00 Community C 00005 RJSPC4112 6 CP6 22/190 LHS Khedali Handpump 1 Fully Government C 00006 RJSPC4112 7 CP7 22/400 LHS Khedali Handpump 1 Fully Government C 00007 RJSPC4112 8 CP8 27/380 LHS Bad-Sithod Handpump 1 Fully Government C 00008

MORTH TCPL Annexure7.1/1 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of SIA and RAP NH – 11B in the State of Rajasthan Annexure-7.1

Structure Name of Cenus Side Type of Construction Fully Built up Area ( Sqm) Name of Str Chainage Name of Community / Sr.No. Survey (LHS Affected Property No. (KM) Village Govt. Code / RHS) Semi / Partially Semi Holder Structure Pucca Kachcha Pucca Kachcha Pucca Affected Pucca 1 2 3 4 5 6 7 8 9 10 11 RJSPC4112 9 CS9 27/560 RHS Bad-Sithod Well 1 Fully 1.77 Government C 00009 RJSPC4112 Khanpur 10 CP10 51/950 RHS Well 1 Fully 19.63 Community C 00010 Baroda RJSPC4112 Khanpur 11 CS11 52/530 Center Shiv Mandir 1 Fully 20.00 Community C 00011 Baroda RJSPC4113 12 CP12 55/745 RHS Salempur Handpump 1 Fully Government C 00001 RJSPC4113 13 CK13 56/665 LHS Salempur Kabarsthan 1 Partially 50.00 Community C 00002 Rajkiya RJSPC4113 Ayurvedic 14 CS14 56/790 RHS Salempur 1 Partially 14.29 Government C 00003 Kendra Closed RJSPC4113 15 CS15 56/815 LHS Salempur Patwari Office 1 Partially 17.82 Government C 00004

RJSPC4113 Pashupatinath 16 CK16 56/850 RHS Salempur 1 Partially 6.50 Community C 00005 Temple

RJSPC4113 NREGA Post 17 CK17 57/655 RHS Govindpura 1 Fully 1.50 Government C 00006 Pillar (3nos) RJSPC4113 Compund wall 18 CK18 65/500 LHS Mahamdpur 1 Fully 10.64 Government C 00007 school

MORTH TCPL Annexure7.1/2 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of SIA and RAP NH – 11B in the State of Rajasthan Annexure-7.1

Structure Name of Cenus Side Type of Construction Fully Built up Area ( Sqm) Name of Str Chainage Name of Community / Sr.No. Survey (LHS Affected Property No. (KM) Village Govt. Code / RHS) Semi / Partially Semi Holder Structure Pucca Kachcha Pucca Kachcha Pucca Affected Pucca 1 2 3 4 5 6 7 8 9 10 11 RJSPC4113 19 CS19 65/530 LHS Mahamdpur Shiv Mandir 1 Fully 10.64 Community C 00008 Water Tank RJSPC4113 20 CS20 68/200 LHS Bijalpur and Shiv 1 Partially 36.00 Community C 00009 Mandir RJSPC4113 21 CP21 73/840 LHS Astal Handpump 1 Fully Government C 00010 RJSPC4113 22 CS22 77/475 LHS Barkheda Dharmashala 1 Fully 58.20 Community C 00011 Primary RJSPC4113 Health Center 23 CS23 78/800 LHS Barkheda 1 Fully 16.00 Community C 00012 Gadka Ki Chowki RJSPC4113 Hanumanji 24 CS24 82/600 Center Karauli 1 Fully 20.00 Community C 00013 Mandir RJSPC4113 25 CK25 84/600 LHS Karauli Chruch C.wall 1 Fully 11.40 Community C 00014

Total 8 10 7 231.09 32.11 56.50

MORTH TCPL Annexure7.1/3 SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA RAP Annexure -7.2

Sub Sr Chainage Chainage Affected Dist Tehsil Village Project State Package Cenus Code Name Land Owner Khasra No Side Land Type No From To Area Name Sawai 1 Bamanvas Sithod NH-11B Rajasthan SPC4 RJSPC411200001 Subudhi Gujar 1005,1006,1008 RHS Irrigated 1300 Madhopur Sawai 2 Bamanvas Sithod NH-11B Rajasthan SPC4 RJSPC411200002 Gangasahay Gujar 1007 RHS Irrigated 50 Madhopur Sawai 3 Bamanvas Sithod NH-11B Rajasthan SPC4 RJSPC411200003 Ramprasad Gujar 1030 CH-27/400 CH-27/800 RHS Irrigated 475 Madhopur Sawai Ramgopal Nanaga 4 Bamanvas Sithod NH-11B Rajasthan SPC4 RJSPC411200004 1031,1032 RHS Irrigated 385 Madhopur Gujar Sawai Radhesham Laxman 5 Bamanvas Sithod NH-11B Rajasthan SPC4 RJSPC411200005 1033,1034,1035 RHS Mix 470 Madhopur Gujar Sawai Ramshri Bherubaksh 456,457,458,459,46 6 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200006 RHS Irrigated 2380 Madhopur Gujar 0,461 Sawai 7 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200007 Dharoopsingh gujar 494 RHS Irrigated 1330 Madhopur Sawai Kishor Lalchand 8 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200008 492 RHS Barren 430 Madhopur Brahman Sawai Laxminarayan Ramdev 9 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200009 500 RHS Non Irrigated 935 Madhopur Gujar CH- CH-35/600 Sawai 36/200 10 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200010 Prabhu Misaraya Gujar 501,502,503 RHS Non Irrigated 5865 Madhopur Sawai 11 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200011 Ramjilal Bansi Khati 270 LHS Non Irrigated 3200 Madhopur Sawai 12 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200012 Mukesh Lallu Bereva 275 LHS Irrigated 2475 Madhopur Sawai 13 Gangapurcity Thali NH-11B Rajasthan SPC4 RJSPC411200013 Dharoopsingh gujar 276 RHS Irrigated 1330 Madhopur Sawai 14 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200014 Mohammad-Akhtar 4967 RHS Non Irrigated 800 Madhopur Sawai Anwarali Manjurali 15 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200015 4957 RHS Non Irrigated 550 Madhopur Musalman Sawai Rajeshkumar 16 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200016 4960 LHS Non Irrigated 450 Madhopur Madanmohan Mahajan Sawai Mohammad Arsad 17 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200017 4165 LHS Barren 500 Madhopur Abdulrahim Musalman Sawai Anishabanu Isthak 18 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200018 4164 LHS Non Irrigated 1000 Madhopur Ahmed Musalman CH-46/470 CH-47/100 Sawai Najimali Manjurali 19 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200019 4124 LHS Irrigated 150 Madhopur Masulman 4161,4162,4144,4 143,4145,4146,41 47,4142,4141,412 Sawai Shabbirali, Atikali 20 Gangapurcity Udaikalan NH-11B Rajasthan SPC4 RJSPC411200020 5,4126,4118,4110 LHS Irrigated 7105 Madhopur Mohammad Musalman ,4111,4112,4113, 4114,4116,4966,4 127 Sawai 21 Gangapurcity Dibsya NH-11B Rajasthan SPC4 RJSPC411200021 Kirodilal Ramjya Meena 1718,1719,1720 RHS Non Irrigated 400 Madhopur Omprakash Gajanand Meena, Santra devi Sawai Kantichand Meena , 22 Gangapurcity Dibsya NH-11B Rajasthan SPC4 RJSPC411200022 1720/1818 LHS Non Irrigated 400 Madhopur Goranti Shivcharan Meena , Kamala Ramlal Meena SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA RAP Annexure -7.2

Sub Sr Chainage Chainage Affected Dist Tehsil Village Project State Package Cenus Code Name Land Owner Khasra No Side Land Type No From To Area Name Sawai Khanpur Abdul Shakurkhan 64,66,67,69,70,71 23 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200023 RHS,LHS Irrigated 5847 Madhopur Baroda Musalman ,72 Sawai Khanpur Abdul Shakurkhan 24 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200024 87 LHS Irrigated 56 Madhopur Baroda Musalman Sawai Khanpur 25 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200025 Giriraj Ramsahay Gujar 173 RHS Non Irrigated 2140 Madhopur Baroda Sawai Khanpur Rampati Kesher 26 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200026 172,211 LHS Non Irrigated 1057 Madhopur Baroda Ramjilal Gujar Sawai Khanpur Ramkuwar Ghudya 27 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200027 171 RHS Non Irrigated 1473 Madhopur Baroda Gujar Sawai Khanpur 28 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200028 Gordhan Ramhet Mali 179,180 RHS,LHS Irrigated 1220 Madhopur Baroda Sawai Khanpur Chajulal Radheshyam 29 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200029 426 RHS Irrigated 85 Madhopur Baroda Fondilal Mahajan Sawai Khanpur Hariprasad KIshanlal 30 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200030 471 LHS Irrigated 655 Madhopur Baroda Gujar Sawai Khanpur 31 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200031 Kishanlal Mahesh Gujar 423,424,472,482 RHS,LHS Irrigated 3715 Madhopur Baroda Naval, Shivdayal, Sawai Khanpur 32 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200032 Megharam, Suresh 212 RHS Non Irrigated 1515 Madhopur Baroda Dinesh Chimman Gujar Sawai Khanpur Narasi, Amarlal, Zandu, 33 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200033 204 RHS Non Irrigated 875 Madhopur Baroda Rampati, Motilal Gujar Sawai Khanpur 34 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200034 Dayaram Hajari Gujar 205 RHS Non Irrigated 1276 Madhopur Baroda Sawai Khanpur Hariom Mishrilal 35 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200035 441 RHS Irrigated 745 Madhopur Baroda Brahman Sawai Khanpur Ghanshyam Motilal 36 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200036 454 RHS Irrigated 635 Madhopur Baroda Mahajan Sawai Khanpur 37 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200037 Chirmoli Bhola Gujar 199 LHS Non Irrigated 1926 Madhopur Baroda CH-50/700 CH-52/900 Sawai Khanpur 38 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200038 Mishraya Bharaya Gujar 200 LHS Non Irrigated 1042 Madhopur Baroda Sawai Khanpur 39 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200039 Parsadi Gujar 201,202 RHS,LHS Non Irrigated 1335 Madhopur Baroda Sawai Khanpur Kailashchand Chiranjilal 40 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200040 425 RHS Irrigated 545 Madhopur Baroda Mahajan Sawai Khanpur Hariom Mishrilal 41 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200041 443 RHS Irrigated 745 Madhopur Baroda Brahman Sawai Khanpur 42 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200042 Shreeful Choutya Mali 485 LHS Non Irrigated 1540 Madhopur Baroda Sawai Khanpur 43 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200043 Radha Gupta 83,86,89 RHS,LHS Non Irrigated 5181 Madhopur Baroda Lakshmidube Sawai Khanpur Santoshkumar Dube, 44 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200044 92 RHS,LHS Non Irrigated 3432 Madhopur Baroda Chandodevi Ramcharan Khandelwal Sawai Khanpur 45 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200045 Rukmanidevi agrawal 82 LHS Irrigated 210 Madhopur Baroda Sawai Khanpur 46 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200046 Ramjilal Chamar 104 RHS,LHS Non Irrigated 1600 Madhopur Baroda Sawai Khanpur 47 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200047 Ghoodya Kamal Teli 167 RHS Irrigated 70 Madhopur Baroda Sawai Khanpur 48 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200048 Kashiprasad Mahajan 407 RHS Irrigated 630 Madhopur Baroda SIA and RAP including TDP for Rehabilitation and Upgrading of Lalsot – Karauli section of NH – 11B in the State of Rajasthan SIA RAP Annexure -7.2

Sub Sr Chainage Chainage Affected Dist Tehsil Village Project State Package Cenus Code Name Land Owner Khasra No Side Land Type No From To Area Name Sawai Khanpur 49 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200049 Hari Harful Mali 177,178,183 RHS Irrigated 4156 Madhopur Baroda Sawai Khanpur 50 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200050 Ramkishor Harful Gujar 213,392 RHS,LHS Irrigated 1869 Madhopur Baroda Sawai Khanpur 51 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200051 Ramdhan Natthilal Gujar 393 LHS Irrigated 825 Madhopur Baroda Sawai Khanpur 52 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200052 Chirmoli Jauhari Gujar 394,401,402 LHS Non Irrigated 2400 Madhopur Baroda Sawai Khanpur 53 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200053 Moharsinh Nattua Mali 444,445 RHS Non Irrigated 1200 Madhopur Baroda Sawai Khanpur Ramjilala Sonya 54 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200054 455 RHS Non Irrigated 1465 Madhopur Baroda Brahman Sawai Khanpur Chirmoli Ramsahay 55 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200055 457 LHS Non Irrigated 1025 Madhopur Baroda Gujar Sawai Khanpur 56 Gangapurcity NH-11B Rajasthan SPC4 RJSPC411200056 Sukharam Mannu Mali 470,484 LHS Non Irrigated 1900 Madhopur Baroda Gopalpurs Atersinh Swaroopsinh 57 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300001 329/2 RHS Non Irrigated 1960 ay Gujar Gopalpurs Radhabai Motisinh 58 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300002 329/1 RHS Non Irrigated 1300 ay Rajput Gopalpurs Nandkishor Motilal 266,265,255,327/ 59 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300003 LHS Non Irrigated 14000 ay Brahman 2/337 Gopalpurs 60 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300004 Ganesh Fatariy Mali 326/1 RHS Non Irrigated 1000 ay Gopalpurs Shreeram 61 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300005 326/2 RHS Non Irrigated 1000 ay Lakshhiminarayan Mali CH-75/850 CH-76/400 Gopalpurs Sureshchandra 62 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300006 328 RHS Non Irrigated 1600 ay Jugalkishor Bansal Gopalpurs 63 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300007 Shrifal Netram Gujar 254/1 LHS Non Irrigated 1200 ay Rampur 64 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300008 Bhabuti Devilal Gujar 78,79 RHS Barren 970 Ghabiyan Rampur Sureshchandra 65 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300009 80/1 RHS Non Irrigated 1100 Ghabiyan Ramswruplal Brahman Rampur 66 Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300010 Bharosi Gulbi Chamar 80/2 RHS Non Irrigated 900 Ghabiyan 67 Karauli Karauli Barkheda NH-11B Rajasthan SPC4 RJSPC411300011 Harilal Sarvansinh Mali 462,517/905 LHS Barren 1000 542/1,542/2,539/1 ,539/2,538/1,538/ 68 Karauli Karauli Barkheda NH-11B Rajasthan SPC4 RJSPC411300012 Kashinath Chiranji Nai 2,537/1,537/2,533 RHS Irrigated 3270 /1,533/2,539/1065 ,539/1066,539/10 CH-79/700 CH-80/300 67,539/1068 Ganeshram Harbhajan 69 Karauli Karauli Barkheda NH-11B Rajasthan SPC4 RJSPC411300013 536 RHS Irrigated 320 Meena 6492,6493,6491,6 70 Karauli Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300014 Ramsinh Shankar Mali RHS Mix 1520 488,6485,6484 71 Karauli Karauli Karauli NH-11B Rajasthan SPC4 RJSPC411300015 Mula Kaula Mali 6487 RHS Abadi 280

Photograph for Public Consultation in Second Round (Mandawari Village)

Photograph for Public Consultation in Second Round (Pipalai Village)

Photograph for Public Consultation in Second Round (Khanpur Baroda)

Photograph for Public Consultation in Second Round (Salempur Village)