LOCAL CONSTRUCTION PROGRAM (LCP)

CONTRACT NO.: AID-294-I-13-00003

TASK ORDER NO.: AID-294-TO-16-00005

JABA-NUBA TRANSMISSION MAIN PHASE II

MONTHLY PROGRESS REPOERT FROM DECEMBER 01, 2016 TO DECEMBER 31, 2016

DISCLAIMER This report is made possible by the support of the American People through the United States Agency for International Development (USAID.) The contents of this report are the sole responsibility of Arab Brothers CO. LTD. and do not necessarily reflect the views of USAID or the United States Government.

Table of Contents 1. List of Abbreviations ………………………………………………….…………………………………… 3 2. Task Order Overview ……………………………………………….………………………….…………. 4 2.1. Background 2.2. Project Objective 2.3. Statement of Work 2.4. Key data 2.5. Project Key Map.

3. Safety Status ……………………………………………………………………………………….………….....8 3.1 Safety Plan and Measures 3.2 Safety Meetings 3.3 Accident Status 3.4 Notice of Unsafe Condition

4. Traffic Control …………………………………………………………………………………….…….……. 8 4.1 Traffic Control Plan 4.2 Traffic Control Measures.

5. Mitigation, Monitoring and Environmental Compliance ………………………………… 8

6. Construction Risk Management …………………………………………………………………..… 9

7. Community Outreach ...... ……………………….………………………………. 9

8. Gender Consideration...... …………………….. 9

9. Progress and Scheduling ……………………………………………………………………………….. 9 9.1 Activities During the Current Reporting Period 9.2 Planned Activities for Next Month

10. Meetings and Coordination activities …………………………………………………………….. 10

11. Events & Site Visits ………………………………………………………………………………………… 10

12. Task Order Indicators……………………………………………..……………………………………… 10 12.1 Indicator 1: Quantity of drinking water available as a result of USG assistance 12.2 Indicator 2: Person Days of Employment Generated

13. Working / Non – Working Days ……………………………………………………………………… 11

14. Quality Control Status ……………………………………………………………………………………. 12 14.1 Inspection Requests 14.2 Testing Reports 14.3 Non Compliance Report Log - NCR

1 | Page Progress Monthly Report-December 2016

15. Submittals Status ……………………………………………………………………………………………. 12

16. Site Memorandum ………………………………………………………………………………………….. 12

17. Transmittals …………………………………...……………………………………………………….…….. 12 17.1. Outgoing Emails. 17.2. Incoming Email. 17.3. Letters.

18. Requests for Information ………………………………………………………………….……..…….. 14

19. Procurement Status ……………………………………………………………………………………….. 14 19.1 Procurement During Mobilization Phase 19.2 Material and Equipment Delivered on Site

20. Payments ………………………………………………………………………………………….………..….. 14

21. Variation Order Request ………………………………………………………………………………... 15

22. Variation Order …………………………………………………………………………………………….... 15

23. Obstacles and Challenges………………………………………………………………………………… 15

24. Progress Photos ……………………………………………………………………………………………... 15

25. Annexes …………………………………………………………………………………………………………. 18 A. Received Materials- Equipment Log B. Site Memorandum Log C. Inspection Request Log D. RFI’s Log for the Reporting Period E. Payment Log F. Risk Register. G. Project Updated Schedule. H. Progress S-Curve versus Actual I. Submittals Log for the Reporting Period. J. Geo-MIS Data. K. Draft Flyers. L. 60 DAYS PLAN OF OPERATION

2 | Page Progress Monthly Report-December 2016

1. LIST OF ABBREVIATIONS AB Arab Brothers Construction & Infrastructure Group ASAP As Soon as Possible CEng Contracts Engineer CMC Construction Management Contractor CO Contracting Officer COB Close of Business COP Chief of Party COR Contracting Officer Representative CQC Contractor Quality Control CQCP Contractor Quality Control Program CRMP Construction Risk Management Plan CV Curriculum Vita DCL District Civil Liaison FO Field Order IQC Indefinite Quantities Contract LCP Local Construction Program MRR Material Receiving Report NCR Non Compliance Report NUC Notice of Unsafe Conditions O&M Operation and Maintenance OSHA Occupational Safety and Health Act PCO Project Control Officer PIO Public Information Officer PM Project Manager PSU Program Support Unit PWA Palestinian Water Authority QA Quality Assurance QC Quality Control RE Resident Engineers RFI Request For Information RFTOP Request for Task Order Proposal TO Task Order TOL Task Order Leader TOM Task Order Manager SECO Safety & Environmental Compliance Officer SOP Standard Operating Procedure USAID United State Agency for International Development VO Variation Order VOR Variation Order Request WBG West Bank Gaza WBWD West Bank Water Department

3 | Page Progress Monthly Report-December 2016

2. TASK ORDER OVERVIEW 2.1 Background The Local Construction Program (LCP) implements small and medium-scale infrastructure activities resulting in safer roads, better schools, better health clinics, and improved access to water and sanitation services for . Program goals are to improve quality of life for Palestinians through infrastructure activities, and enhance the safety, quality control, reporting, and management capabilities of local construction firms.

This activity is implemented under the Local Construction Program (LCP). The project includes constructing new transmission pipelines, rehabilitating of an existing transmission pipeline, constructing new distribution pipelines, constructing new service connection chambers, improving existing water reservoirs, and constructing new booster pump stations.

2.2 Project Objective The objective of this Task Order is to improve the regional water system and expand services to new customers in order to bring clean water to the northwest villages of the Governorate.

2.3 Statement Of Work The following is a summary of Jaba-Nuba Transmission Main Phase II Project construction works:

 Construction of new facilities:  Booster Station – New booster station including a 250 m3 break tank.  Kharas Booster Station – New booster station including a 250 m3 break tank.

 Construction of New Transmission Pipelines and Distribution Pipelines:  Surif Transmission Pipeline (2.6 km)  Kharas Transmission Pipeline (2.2 km)  Surif Distribution Pipeline (6.2 km)  Kharas Distribution Pipeline (4.5 km)  Nuba Distribution Pipeline (0.1 km)  Hitta Distribution Pipeline (0.2 km)  Distribution Pipeline (0.2 km)

 Improving Existing Water Reservoirs:  Nuba Existing Reservoir.  Surif Existing Reservoir.  Kharas Existing Reservoir.

 Rehabilitation of existing transmission pipeline:  Nuba – Beit Ula (9.5 km)

4 | Page Progress Monthly Report-December 2016

2.4 Key Data

Project Key Data

Task Order Name Jaba‐Nuba Transmission Main Phase II Contract No. AID‐294‐I‐13‐00003 Task Order No. AID‐294‐TO‐16‐00005 Location Hebron Northwest Villages Owner Palestinian Water Authority (PWA) United States Agency for International Development Client (USAID) Engineer AECOM Contractor Arab Brothers Construction & Infrastructure Group BOQ Price $ 7,294,475.37 Day Work $ 500,000.00 Task Order Total Amount $ 7,794,475.37 Modified Task Order Amount ‐ Modified Day Work ‐ Notice of Award September 26, 2016 Notice to Proceed November 15, 2016 Project Duration 390 Calendar Days Planned Completion Date December 09, 2017 Modified Project Duration ‐ Modified Completion Date ‐ Contract Elapsed Time as of 12.05 December 31, 2016 [%] Actual % Complete Baseline Schedule is under Preparation Start of Construction January 18, 2017 ( Planned Date ) Start of Construction ‐ ( Acual Date ) No. of Beneficiaries 45,000 People

5 | Page Progress Monthly Report‐December 2016 2.5 Project Key Map. 2.5.1 Surif Area Key Map

PROPOSED 75mm

SURIF

Project Area

PROPOSED 200mm

CONNECTION OF PROPOSED 250mm TO EXISTING 250mm

PROPOSED100mm PROPOSED 100mm USAID WEST BANK/GAZA PROPOSED SURIF BOOSTER STATION LOCAL CONSTRUCTION PROGRAM LCP PROPOSED 250mm CONTRACT NO. AID-294-I-13-00003 PROPOSED 100mm TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II SURIF EXISTING RESERVOIR SURIF AREA KEY MAP PROPOSED 150mm PROPOSED 150mm MONTHLY PROGRESS REPORT DECEMBER 2016 LEGEND PROPOSED PIPELINE

PROPOSED BOOSTER STATION

EXISTING RESERVOIR VILLAGE NAME 2.5.2 Kharas Area Key Map

50 mm

KHARAS DISTRIBUTION NETWORK

KHARAS CONNECTION POINT HITTA

200 mm Project Area

100

mm PROPOSED KHARAS 75mm KHARAS BOOSTER STATION HITTA DISTRIBUTION NETWORK KHARAS EXISTING RESERVOIR

75 mm

USAID WEST BANK/GAZA NUBA LOCAL CONSTRUCTION PROGRAM LCP mm KHARAS DISTRIBUTION NETWORK CONTRACT NO. AID-294-I-13-00003

150 NUBA DISTRIBUTION NETWORK TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

KHARAS AREA KEY MAP

MONTHLY PROGRESS REPORT DECEMBER 2016 LEGEND PROPOSED PIPELINE

PROPOSED BOOSTER STATION BEIT ULA DISTRIBUTION BEIT ULA NETWORK EXISTING RESERVOIR

mm

200 VILLAGE NAME BEIT ULA DISTRIBUTION NETWORK

3. SAFETY STATUS 3.1 Safety Plan and Measures AB’s Safety plan includes all necessary measures, supervision, and training activities to ensure compliance with the safety and health requirements, and assist the project personnel in the planning, organizing, control monitoring and implementation of corrective measures which are necessary to prevent exposures which could cause injury, accidents or negative environmental consequence.

The safety plan was re-submitted to CMC on December 12, 2016 and the acceptance was obtained on December 13, 2016.

3.2 Safety Meetings AB will conduct safety orientations and safety tool box meetings for all employees before and during the construction phase.

3.3 Accident Status No accidents were reported during this reporting period.

3.4 Notice of Unsafe Condition No Notices of Unsafe Condition (NUCs) were issued during this reporting period.

4. TRAFFIC CONTROL 4.1 Traffic Control Plan General traffic control plan was submitted for CMC review on December 15, 2016 and it was returned back on December 29, 2016. Traffic control plan will be revised and resubmitted to CMC as soon as possible.

4.2 Traffic Control Measures. All traffic measures will be implemented prior the start of construction work.

5. MITIGATION, MONITORING AND ENVIRONMENTAL COMPLIANCE Environmental Monitoring and Mitigation Plan was submitted to CMC on December 08, 2016, CMC acceptance was obtained on December 13, 2016 and revised record copy was requested. Engineers’ record copy is under preparation and will be submitted as soon as possible.

No environmental issues were reported during the current reporting period.

8 | Page Progress Monthly Report-December 2016

6. CONSTRUCTION RISK MANAGEMENT Construction risk management program was submitted to CMC on December 15, 2016 and it was returned back on December 27, 2016. Risk management program will be revised and resubmitted to CMC as soon as possible.

7. COMMUNITY OUTREACH AB prepared the outreach guidelines that should be followed for this task order, to ensure the community awareness and involvement during the different construction stages. AB outreach guidelines will not be used prior obtaining USAID approval.

As part of the company outreach plan; AB intends to use two flyer forms, one for public and one for children with easy language and simple safety instructions. Flayers were prepared and sent to USAID. Flayers will be modified according to USAID comments and resend back for USAID approval.

8. GENDER CONSIDERATION All employment and man power data were disaggregated in daily joint reports to reflect gender. The following table shows number of working hours for female employees as detailed in the daily joint reports during the current reporting period:

Female Person of Employment Female Person of Employment for previous Month 30 Female Person of Employment for Current Month 73 Cumulative Female Person of Employment 103 Table 8.1: Female Person of Employment. 9. PROGRESS AND SCHEDULING 9.1 Activities During the Current Reporting Period.  Continue engineers’ primary filed office furnishing.  Start engineers’ secondary filed office furnishing.  Continue preparation of preconstruction and construction submittals.  Continue the surveying works.  Start preparation work for safety fence and concrete barriers around Surif Booster Station.  Start assessing the existing ductile iron pipes D300mm condition in Nuba and Beit Ula.  Start delivering the New Jersey concrete barriers to Surif Booster Station.

9.2 Planned Activities for Next Month  Continue preparation of preconstruction and construction submittals.

9 | Page Progress Monthly Report-December 2016

 Finish the mobilization works (Engineers’ filed offices, project signs..etc.)  Apply safety measures and security fence for Kharas and Surif Booster Stations.  Start preparation for excavation works at Kharas and Surif Booster Stations. Dumping site acceptance was obtained on November 29, 2016.  Finish storage yard preparation.  CPM Schedule is expected to be submitted on January 11, 2017.

10. MEETINGS AND COORDINATION ACTIVITIES The following table summarizes the list of meetings and coordination activities carried out during December 2016:

Meeting Subject Discussed Issues With Venue Date Gate Valves Submittals, AECOM AB & December Technical Meeting Valves Schedule & Ductile Primary AECOM 08, 2016 Connection Fittings Office Baseline Schedule, Traffic Pre-Construction AECOM Plan & Method Statement AB & December Scheduling Primary Status, Temporary Sign AECOM 15, 2016 Conference Office and Mobilization Phase Grand Park AB & December Safety Orientation Safety Orientation Hotel- AECOM 19, 2016 Ramallah AECOM MCC, Instruments, Pump AB & December Technical Meeting Primary station instruments & PLC AECOM 21, 2016 Office Pre-Construction AECOM AB & December Scheduling Draft Baseline Schedule, Primary AECOM 28, 2016 Conference Office Table 10.1: December 2016 Meetings’ Log.

11. EVENTS & SITE VISITS No site visits/ events were conducted during this reporting period as the field activities did not start yet.

12. TASK ORDER INDICATORS 12.1 Indicator 1: Quantity of drinking water available as a result of USG assistance: Measured by the total volume determined in the design phase per USAID beneficiaries' standard definitions of drinking water supply to be made available as a result of USG assistance in discrete INP projects. The Contractor will request this data from the INP II A-E firm for inclusion in the Contractor's first Geo-MIS report as a target estimate. This indicator will be measured and

10 | Page Progress Monthly Report-December 2016

reported on by the Contractor at the completion of the task order based on the tested capacity of the project. Total number of Male Female Beneficiaries Number % Number % 45,000 22,950 51% 22,050 49% Table 12.1: Beneficiaries Number.

12.2 Indicator 2: Person Days of Employment Generated This indicator is measured by the number of person days of employment generated under this Task Order. The contractor measures person days of employment directly generated by construction work on site.

The following table summarizes the total number of Persons days of employment generated previously and during the current reporting period:

will be provided in the Target value coming report * Employment generated previously 114 Employment generated this month 284.875 Total cumulative employment generated to-date 398.875 * Baseline Schedule is under Preparation. Table 12.2: Employment Generated.

13. WORKING / NON – WORKING DAYS The following table summarizes the total number of working and non-working days during this reporting period:

Total Period of Performance (Original) 390 Calendar Days Total Excusable delays/approved extensions 0 Modified Period of Performance --- Modified Completion Date ---

Working Days Previous Working Days 13 Working Days Number of Working Days for Current Month 26 Working Days Accumulated Working Days 39 Working Days Non-Working Days Cause Previous non-working days (Holidays and 2 Calendar Days Weekend weekends) Number of non-working days (holidays 5 Calendar Days Weekend and weekends) Accumulated non-working days (Holidays 7 Calendar Days Weekend and weekends) Number of other non-working days ------

11 | Page Progress Monthly Report-December 2016

Accumulated other non-working days ------Project Elapsed Time Project Elapsed Time 46 Calendar Days Table 13.1: Working and Non-Working Days.

14. QUALITY CONTROL STATUS The Quality Control Plan (QCP) was submitted to CMC for review and acceptance on November 29, 2016. CMC acceptance was obtained on December 08, 2016 and revised record copy was requested. Engineers’ record copy is under preparation and will be submitted as soon as possible.

14.1 Inspection Requests: No inspection requests were issued during this reporting period.

14.2 Testing Reports: Zero tests were conducted during this reporting period.

14.3 Non Compliance Report Log - NCR No NCRs were issued during this reporting period.

15. SUBMITTALS STATUS The following chart summarizes the status of submittals during this reporting period.

SUBMITTALS STATUS Pre- Construction Submittal Type # Submittals Pre- Construction Submittal 26 6%3 % Material-Civil Material-Civil 8 35% Material-Mechanical 39 21% Material-Mechanical Material-Electrical 15 Shop Drawings-Civil 3 Material-Electrical Others 3 9%

SUM 94 Shop Drawings-Civil 29%

Figure 15.1: Submittals Status. Others

For more details please refer to submittals log ‘’ Annex I’’.

16. SITE MEMORANDUM No site memos were issued during this reporting period.

17. TRANSMITTALS 17.1 Outgoing Emails: The following is the Outgoing Emails’ log during the current reporting period:

12 | Page Progress Monthly Report-December 2016

DCN No. Email Subject From To Sent Date MAIL-05-OUT-0001 Submittals' Numbering AB AECOM December 1, 2016 Project key Personnel- MAIL-05-OUT-0002 AB USAID December 1, 2016 Vetting Requirement MAIL-05-OUT-0003 Draft Flayer AB USAID December 3, 2016 Progress Monthly Report# MAIL-05-OUT-0004 AB USAID December 5, 2016 001-November 2016 MAIL-05-OUT-0005 Sub Awards Report AB USAID December 5, 2016 Technical Meeting MAIL-05-OUT-0006 AB AECOM December 6, 2016 Request. MAIL-05-OUT-0007 PVS-User request AB USAID December 10, 2016 MAIL-05-OUT-0008 Flyers Design AB USAID December 13, 2016 Jana Nuba Transmission MAIL-05-OUT-0009 Main Phase II Project - AB USAID December 13, 2016 Q1/FY2017 Accruals Pre-Construction Meeting- MAIL-05-OUT-0010 AB USAID December 13, 2016 Presentation Pre-Construction MAIL-05-OUT-0011 AB AECOM December 13, 2016 Scheduling Conference Jana Nuba Transmission MAIL-05-OUT-0012 Main Phase II Project - AB USAID December 16, 2016 Q1/FY2017 Accruals Requirements to Submit MAIL-05-OUT-0013 for Permission of Pipes AB USAID December 21, 2016 Entry Table 17.1: Outgoing Emails’ Log.

17.2 Incoming Emails: The following is the Incoming Emails’ log during the current reporting period: DCN No. Email Subject From To Sent Date MAIL-05-IN-0001 Draft Flayer USAID AB December 5, 2016 MAIL-05-IN-0002 Sub Awards Report USAID AB December 5, 2016 MAIL-05-IN-0003 Sub Awards Report USAID AB December 6, 2016 TO 05 JNTII: Technical MAIL-05-IN-0004 AECOM AB December 6, 2016 Meeting Request. TO 05: Progress Monthly MAIL-05-IN-0005 Report# 001-November USAID AB December 6, 2016 2016 MAIL-05-IN-0006 PVS-User request USAID AB December 7, 2016 Pre-Construction MAIL-05-IN-0007 AECOM AB December 13, 2016 Scheduling Conference Jana Nuba Transmission MAIL-05-IN-0008 Main Phase II Project - USAID AB December 13, 2016 Q1/FY2017 Accruals Jana Nuba Transmission MAIL-05-IN-0009 USAID AB December 16, 2016 Main Phase II Project -

13 | Page Progress Monthly Report-December 2016

Q1/FY2017 Accruals Jaba Nuba Transmission MAIL-05-IN-0010 Main Phase II Project - USAID AB December 27, 2016 Permits Progress Monthly Report# MAIL-05-IN-0011 001-November 2016- USAID AB December 30, 2016 USAID Comments Table 17.2: Incoming Emails’ Log.

17.3 Letters: The following is the Letters’ log during the current reporting period: Description Date From To Internal Assessment of the Project Key Personnel and the Vetting Requirements Addressed Under December 01, 2016 AB USAID Mission Order 21, Section V, Sub- Section C Transportation Traffic Plan December 15, 2016 AB Supreme Council Electrical and Water Lines Request for Kharas December 28, 2016 AB Kharas Booster Station Municipality Electrical and Water Lines Request for Surif December 28, 2016 AB Surif Booster Station Municipality Table 17.3: Letters’ Log.

18. REQUESTS FOR INFORMATION. 4 requests for information were submitted during this reporting period. Refer to Annex D: requests for information log.

19. PROCUREMENT STATUS. 19.1 Procurement During Mobilization Phase. The following major procurement has been initiated during this reporting period:  Continue the procurement of furniture and equipment for the engineers’ filed offices.  Continue the procurement of the engineers’ offices computer system.

19.2 Material and Equipment Delivered on Site. Refer to Annex A: Received Materials- Equipment Log Note: All equipment/vehicles insurances, registration licenses, and driving/operators licenses will be submitted to the CMC for review and records.

20. PAYMENTS. No Payments were submitted during this reporting period.

14 | Page Progress Monthly Report-December 2016

21. VARIATION ORDER REQUEST. No Variation Order requests were issued during this reporting period.

22. VARIATION ORDER. No Variation Orders were issued during this reporting period.

23. OBSTACLES AND CHALLENGES. No obstacles were encountered during this reporting period.

24. PROGRESS PHOTOS

Photo # 01: Preparation work for safety fence around Surif Booster Station.

15 | Page Progress Monthly Report‐December 2016

Photo # 02: Delivering the New Jersey Concrete Barriers to Surif Booster Station. .

Photo # 03: Pre-Construction Scheduling Conference-December 15, 2016.

16 | Page Progress Monthly Report-December 2016

. Photo # 04: Pre-Construction Scheduling Conference-December 28, 2016

17 | Page Progress Monthly Report-December 2016

(LCP) ANNEXES

25. ANNEXES

18 | Page Progress Monthly Report-December 2016

A

ANNEXE

ANNEXE A

Materials- Equipment Log

19 | Page Progress Monthly Report-December 2016

A. Materials- Equipment Log.

1- Materials

Date Description Qty. Location

December 28, 2016 New Jersey Barriers 48 ML Surif Booster Station

December 31, 2016 Base Course , 18 m³ Surif Booster Station

2- Equipment Date Description Qty. Location KIA Vehicle-(Without driver) 1 December 01, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 December 02, 2016 Weekend 0 KIA Vehicle-(Without driver) 1 December 03, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 04, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 05, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 06, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 07, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 08, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 December 09, 2016 Weekend 0 KIA Vehicle-(Without driver) 1 December 10, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 11, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 12, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 13, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 14, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 15, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 December 16, 2016 Weekend 0 KIA Vehicle-(Without driver) 1 December 17, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 18, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1

20 | Page Progress Monthly Report-December 2016

KIA Vehicle-(Without driver) 1 December 19, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 20, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 21, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 22, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 December 23, 2016 Weekend 0 KIA Vehicle-(Without driver) 1 December 24, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 December 25, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver) 1 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 December 26, 2016 JCB 1 Surif Booster Wheel Excavator 1 Station KIA Vehicle-(Without driver) 1 December 27, 2016 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 KIA Vehicle-(Without driver 1 Surif ‘’ Site Offices’’ Surif Booster Truck Mounted Crane 1 Station December 28, 2016 Surif Booster Pickup (DMAX 2008) 1 Station & Site Offices KIA Vehicle-(Without driver) 1 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 Surif Booster Truck Mounted Crane 1 Station December 29, 2016 Surif Booster JCB 1 Station Surif Booster Pickup (DMAX 2008) 1 Station & Site Offices December 30, 2016 Weekend 0 KIA Vehicle-(Without driver) 1 Surif ‘’ Site Offices’’ Bejo Vehicle-(Without driver) 1 Surif Booster JCB 1 December 31, 2016 Station Surif Booster Pickup (DMAX 2008) 1 Station & Site Offices Table 25.1: Materials- Equipment Log.

21 | Page Progress Monthly Report-December 2016

B

ANNEXE

ANNEXE B

Site Memorandum Log No site memos were issued during this reporting period.

22 | Page Progress Monthly Report-December 2016

C

ANNEXE

ANNEXE C

Inspection Requests Log.

No inspection requests were issued during this reporting period.

23 | Page Progress Monthly Report-December 2016

D

ANNEXE

ANNEXE D

RFI’s Log for the Reporting Period

24 | Page Progress Monthly Report-December 2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

RFI No. Description Submitted Date Contract Due Date Response Date Review Days

ABC-05-0-RFI-0001-0 Pressure & Flow Parameters For Control Valves December 13, 2016 January 12, 2017 Pending P

ABC-05-0-RFI-0002-0 Position Indicators of Gate Valves December 14, 2016 January 13, 2017 December 20, 2016 6

ABC-05-0-RFI-0003-0 Lightning Protection System December 29, 2016 January 28, 2017 Pending P

ABC-05-0-RFI-0004-0 Type of Retaining Wall - Surif Booster Station December 29, 2016 January 28, 2017 Pending P

25|Page Progress Monthly Report-December2016

E

ANNEXE

ANNEXE E

Payment Log

No payments were submitted during this reporting period.

26 | Page Progress Monthly Report-December 2016

F

ANNEXE

ANNEXE F

Risk Register

No risks were reported during this reporting period.

27 | Page Progress Monthly Report-December 2016

G

ANNEXE

ANNEXE G

Project Updated Schedule.

Baseline Schedule is under Preparation. Draft CPM was submitted to CMC for review.

28 | Page Progress Monthly Report-December 2016

H

ANNEXE

ANNEXE H

Progress S-Curve versus Actual.

Baseline Schedule is under Preparation

29 | Page Progress Monthly Report-December 2016

I

ANNEXE

ANNEXE I

Submittals Log for the Reporting Period.

30 | Page Progress Monthly Report-December 2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days RFTOP

ABC-05-0-SUB-RFTOP-0001-1 RFTOP JNTII Safety Plan Pre- Construction Submittal December 20, 2016 January 19, 2017 December 22, 2016 2 E

ABC-05-0-SUB-RFTOP-0005-0 RFTOP JNTII Pipes Marking & Branding Pre- Construction Submittal December 7, 2016 January 6, 2017 December 15, 2016 8 A

ABC-05-0-SUB-RFTOP-0006-0 RFTOP JNTII Environmental Monitoring & Mitigation Plan Pre- Construction Submittal December 8, 2016 January 7, 2017 December 13, 2016 5 B

ABC-05-0-SUB-RFTOP-0007-0 RFTOP JNTII Construction Risk Management Program (Surif) Pre- Construction Submittal December 15, 2016 January 14, 2017 December 27, 2016 12 C

ABC-05-0-SUB-RFTOP-0008-0 RFTOP JNTII General Traffic Control Plan Pre- Construction Submittal December 15, 2016 January 14, 2017 December 29, 2016 14 C

ABC-05-0-SUB-RFTOP-0009-0 RFTOP JNTII Copy of Guarantee Certificate Pre- Construction Submittal December 18, 2016 January 17, 2017 December 22, 2016 4 E

ABC-05-0-SUB-RFTOP-0010-0 RFTOP JNTII Traffic Control Plan (Surif Booster Station) Pre- Construction Submittal December 21, 2016 January 20, 2017 December 29, 2016 8 B

ABC-05-0-SUB-RFTOP-0011-0 RFTOP JNTII Jaba Nuba Transmission Main Phase II Project - Permits Pre- Construction Submittal December 28, 2016 January 27, 2017 December 29, 2016 1 E

SECTION # 01015

ABC-05-0-SUB-01015-0001-0 01015 JNTII Excavation & Trenching Safety Plan Pre- Construction Submittal December 27, 2016 January 26, 2017 December 29, 2016 2 C

SECTION # 01300

ABC-05-0-SUB-01300-0001-0 01300 JNTII Safety Plan Pre- Construction Submittal December 12, 2016 January 11, 2017 December 13, 2016 1 A

ABC-05-0-SUB-01300-0002-0 01300 JNTII Light Pole With Light Fixture (Reference to DWG. E-001, E-014) Material-Electrical December 22, 2016 January 21, 2017 December 26, 2016 4 A

ABC-05-0-SUB-01300-0003-0 01300 JNTII Surif Booster Station Layout and General Excavation Plan Shop Drawings-Civil December 22, 2016 January 21, 2017 December 27, 2016 5 B Bedding, Backfilling and Base Course Material Source ‘’Roots Infrastructure ABC-05-0-SUB-01300-0004-0 01300 JNTII Material-Civil December 26, 2016 January 25, 2017 December 29, 2016 3 A and Investment Co. LTD’’. ABC-05-0-SUB-01300-0005-0 01300 JNTII Kharas Booster Station Layout and General Excavation Plan Shop Drawings-Civil December 29, 2016 January 28, 2017 P P P

SECTION # 01310

ABC-05-0-SUB-01310-0001-1 01310 JNTII 60 Days Plan of Operation Pre- Construction Submittal December 13, 2016 January 12, 2017 December 22, 2016 9 B

ABC-05-0-SUB-01310-0002-1 01310 JNTII Project Overview Bar Chart Pre- Construction Submittal December 13, 2016 January 12, 2017 December 22, 2016 9 B

ABC-05-0-SUB-01310-0003-0 01310 JNTII Computerized CPM Capability Statement Pre- Construction Submittal December 7, 2016 January 6, 2017 December 20, 2016 13 C

ABC-05-0-SUB-01310-0003-1 01310 JNTII Computerized CPM Capability Statement Pre- Construction Submittal December 21, 2016 January 20, 2017 December 28, 2016 7 A

SECTION # 01380

ABC-05-0-SUB-01380-0001-0 01380 JNTII Grid Level Shop Drawing for Surif Booster Station & Kharas Booster Station Shop Drawing-Civil December 7, 2016 January 6, 2017 December 8, 2016 1 B

31|Page Progress Monthly Report-December2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days ABC-05-0-SUB-01380-0002-0 01380 JNTII Dilapidation Survey-Surif Pre- Construction Submittal December 15, 2016 January 14, 2017 December 22, 2016 7 C

SECTION # 01500

ABC-05-0-SUB-01500-0001-0 01500 JNTII Project Temporary Signs Locations Pre- Construction Submittal December 12, 2016 January 11, 2017 December 12, 2016 0 B

ABC-05-0-SUB-01500-0002-0 01500 JNTII Storage Yard Pre- Construction Submittal December 12, 2016 January 11, 2017 December 15, 2016 3 B

SECTION # 01591

ABC-05-0-SUB-01591-0001-0 01591 JNTII Secondary Office Location Pre- Construction Submittal December 8, 2016 January 7, 2017 December 12, 2016 4 A

ABC-05-0-SUB-01591-0002-0 01591 JNTII Engineer ’s Secondary Field Office Layout Pre- Construction Submittal December 12, 2016 January 11, 2017 December 12, 2016 0 A

ABC-05-0-SUB-01591-0003-0 01591 JNTII Engineers' Secondary Office Furniture Pre- Construction Submittal December 18, 2016 January 17, 2017 December 22, 2016 4 A

ABC-05-0-SUB-01591-0004-0 01591 JNTII Secondary Office Computer System Pre- Construction Submittal December 18, 2016 January 17, 2017 December 22, 2016 4 A

SECTION # 02200

ABC-05-0-SUB-02200-0001-1 02200 JNTII Filter Fabric (Geotextile) Material Material-Civil December 13, 2016 January 12, 2017 December 20, 2016 7 B

SECTION # 02202

ABC-05-0-SUB-02202-0001-0 02202 JNTII Filter Fabric (Geotextile) Material ( Type A)- For Trench Pipeline Material-Civil December 13, 2016 January 12, 2017 December 20, 2016 7 B

ABC-05-0-SUB-02202-0002-0 02202 JNTII Underground Warning Tapes Material-Mechanical December 20, 2016 January 19, 2017 December 29, 2016 9 C

SECTION # 02606

ABC-05-0-SUB-02606-0001-0 02606 JNTII Manhole Cover 750 & 600 mm (Al- Haddad Steel Co) Data and Sample Material-Civil December 27, 2016 January 26, 2017 P P P

SECTION # 02832

ABC-05-0-SUB-02832-0001-1 02832 JNTII Steel Mesh Fence and Posts Material-Civil December 27, 2016 January 26, 2017 December 27, 2016 0 B

SECTION # 03200

ABC-05-0-SUB-03200-0001-0 03200 JNTII Concrete Reinforcing Steel Certificates and Data Sheets Manufacturer-CVs December 18, 2016 January 17, 2017 December 27, 2016 9 C

SECTION # 03250

ABC-05-0-SUB-03250-0001-0 03250 JNTII Waterstops (230 mm wide), (150 mm wide) & (100 mm wide) Material-Civil December 18, 2016 January 17, 2017 December 27, 2016 9 C

ABC-05-0-SUB-03250-0001-1 03250 JNTII Waterstops (230 mm wide), (150 mm wide) & (100 mm wide) Material-Civil December 28, 2016 January 27, 2017 P P P

SECTION # 07900

32|Page Progress Monthly Report-December2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days ABC-05-0-SUB-07900-0001-0 07900 JNTII Joint Sealant Thioflex 600 Material-Civil December 26, 2016 January 25, 2017 December 29, 2016 3 B

SECTION # 13100

ABC-05-0-SUB-13100-0001-0 13100 JNTII Cathodic Protection Test Stations & Shunts Material-Mechanical December 28, 2016 January 27, 2017 P P P

SECTION # 13110

ABC-05-0-SUB-13110-0003-0 13110 JNTII Cathodic Production Handy Caps Material-Mechanical December 7, 2016 January 6, 2017 December 12, 2016 5 A

ABC-05-0-SUB-13110-0004-0 13110 JNTII Flange Insulating Kit Material-Mechanical December 18, 2016 January 17, 2017 December 20, 2016 2 B

ABC-05-0-SUB-13110-0004-1 13110 JNTII Flange Insulating Kit Material-Mechanical December 26, 2016 January 25, 2017 December 29, 2016 3 A

ABC-05-0-SUB-13110-0005-0 13110 JNTII Cathodic Protection Pin Brazing & Consumables Material-Mechanical December 28, 2016 January 27, 2017 P P P

ABC-05-0-SUB-13110-0006-0 13110 JNTII Cathodic Protection Reference Electrodes & Installation Instructions Material-Mechanical December 28, 2016 January 27, 2017 P P P

SECTION # 13500

ABC-05-0-SUB-13500-0001-0 13500 JNTII System Supplier Profile Pre- Construction Submittal December 13, 2016 January 12, 2017 December 20, 2016 7 B

SECTION # 13562

ABC-05-0-SUB-13562-0001-0 13562 JNTII Target-Type Flow Switch Material-Electrical December 4, 2016 January 3, 2017 December 20, 2016 16 C

ABC-05-0-SUB-13562-0002-0 13562 JNTII Propeller Water meter Material-Mechanical December 18, 2016 January 17, 2017 December 22, 2016 4 B

ABC-05-0-SUB-13562-0003-0 13562 JNTII Magnetic Flow Meter for Surif and Kharas Booster Stations Material-Electrical December 26, 2016 January 25, 2017 P P P

SECTION # 13563

ABC-05-0-SUB-13563-0001-0 13563 JNTII Premium Accuracy Pressure and Pressure Sensing Level Transmitter Material-Electrical December 4, 2016 January 3, 2017 December 6, 2016 2 D

ABC-05-0-SUB-13563-0001-1 13563 JNTII Premium Accuracy Pressure and Pressure Sensing Level Transmitter Material-Electrical December 26, 2016 January 25, 2017 December 29, 2016 3 B

ABC-05-0-SUB-13563-0002-0 13563 JNTII Flanged Mounted Pressure Sensing Level Transmitter Material-Electrical December 4, 2016 January 3, 2017 December 6, 2016 2 D

ABC-05-0-SUB-13563-0002-1 13563 JNTII Flanged Mounted Pressure Sensing Level Transmitter Material-Electrical December 26, 2016 January 25, 2017 December 29, 2016 3 C

ABC-05-0-SUB-13563-0003-0 13563 JNTII Instruments Shutoff Valve Material-Electrical December 4, 2016 January 3, 2017 December 20, 2016 16 C

SECTION # 15020

ABC-05-0-SUB-15020-0001-0 15020 JNTII GABI SHOEF – Nondestructive Testing Lab-Alternative Pre- Construction Submittal December 13, 2016 January 12, 2017 December 15, 2016 2 A

ABC-05-0-SUB-15020-0002-0 15020 JNTII MOREX 71 – Nondestructive Testing Lab Pre- Construction Submittal December 13, 2016 January 12, 2017 December 15, 2016 2 A

33|Page Progress Monthly Report-December2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days SECTION # 15061 Technical Proposal- ABC-05-0-SUB-15061-0001-0 15061 JNTII Technical Proposal for Connections to Existing Ductile Iron Pipelines December 12, 2016 January 11, 2017 December 29, 2016 17 C Mechanical

SECTION # 15062

ABC-05-0-SUB-15062-0001-1 15062 JNTII Steel Pipes and Factory Made Fittings Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 C

ABC-05-0-SUB-15062-0001-2 15062 JNTII Steel Pipes and Factory Made Fittings Material-Mechanical December 29, 2016 January 28, 2017 P P P

ABC-05-0-SUB-15062-0003-1 15062 JNTII Shrinkable Sheets and Tapes Material-Mechanical December 18, 2016 January 17, 2017 December 20, 2016 2 A

ABC-05-0-SUB-15062-0004-1 15062 JNTII Threaded Malleable Galvanized Fittings Material-Mechanical December 19, 2016 January 18, 2017 December 20, 2016 1 A

ABC-05-0-SUB-15062-0005-0 15062 JNTII Bolts, Washers, and Nuts Material-Mechanical December 4, 2016 January 3, 2017 December 7, 2016 3 A

ABC-05-0-SUB-15062-0006-0 15062 JNTII Dismantling Joints – Option 1 Material-Mechanical December 13, 2016 January 12, 2017 December 15, 2016 2 A

ABC-05-0-SUB-15062-0007-0 15062 JNTII Dismantling Joints – Option 2 Material-Mechanical December 13, 2016 January 12, 2017 December 15, 2016 2 A

ABC-05-0-SUB-15062-0008-0 15062 JNTII Mechanical Couplings for the Booster Stations Material-Mechanical December 13, 2016 January 12, 2017 December 15, 2016 2 B Welders Testing & ABC-05-0-SUB-15062-0009-0 15062 JNTII ARCEYES - For Welding Procedures and Welders Testing and Qualification December 13, 2016 January 12, 2017 December 15, 2016 2 A Qualification ABC-05-0-SUB-15062-0010-0 15062 JNTII Flanged Coupling Adapter HDPE - Steel Adapt Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 C

ABC-05-0-SUB-15062-0011-0 15062 JNTII Watertight Pipe Sleeves (Pen Seal) Material-Mechanical December 22, 2016 January 21, 2017 P P P

SECTION # 15064

ABC-05-0-SUB-15064-0001-0 15064 JNTII Stainless Steel Pipes, Fittings, and Flanges Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 A

ABC-05-0-SUB-15064-0002-0 15064 JNTII Stainless Steel Bolts, Nuts, & Washers Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 A

SECTION # 15065

ABC-05-0-SUB-15065-0002-1 15065 JNTII Vent Pipes for Chambers Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 A

ABC-05-0-SUB-15065-0003-0 15065 JNTII Galvanized & Coated 2" Steel pipes Material-Mechanical December 4, 2016 January 3, 2017 December 7, 2016 3 B

ABC-05-0-SUB-15065-0003-1 15065 JNTII Galvanized & Coated 2" Steel pipes Material-Mechanical December 21, 2016 January 20, 2017 P P P

ABC-05-0-SUB-15065-0004-0 15065 JNTII SCH40 Steel Pipes With 3 LPE Coating & Cement Lining Material-Mechanical December 21, 2016 January 20, 2017 December 29, 2016 8 B

SECTION # 15067

ABC-05-0-SUB-15067-0001-0 15067 JNTII Connections to Existing HDPE Pipelines & Associated Fittings Material-Mechanical December 4, 2016 January 3, 2017 December 14, 2016 10 B

34|Page Progress Monthly Report-December2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days ABC-05-0-SUB-15067-0002-0 15067 JNTII Underdrain Perforated Pipes Material-Mechanical December 19, 2016 January 18, 2017 December 29, 2016 10 B

ABC-05-0-SUB-15067-0003-0 15067 JNTII Underdrain Solid Pipes & Fittings Material-Mechanical December 20, 2016 January 19, 2017 P P P

SECTION # 15091

ABC-05-0-SUB-15091-0001-0 15091 JNTII Ball Valves (VB-1, 38mm & Smaller) Material-Mechanical December 4, 2016 January 3, 2017 December 12, 2016 8 A

SECTION # 15093

ABC-05-0-SUB-15093-0001-0 15093 JNTII Swing Check Valves (80mm & Larger) Material-Mechanical December 20, 2016 January 19, 2017 December 22, 2016 2 A

ABC-05-0-SUB-15093-0002-0 15093 JNTII Internal Spring-Loaded Check Valves (PN16 & PN25) Material-Mechanical December 20, 2016 January 19, 2017 December 22, 2016 2 C

SECTION # 15101

ABC-05-0-SUB-15101-0001-0 15101 JNTII Butterfly Valves Material-Mechanical December 12, 2016 January 11, 2017 December 20, 2016 8 C

SECTION # 15104

ABC-05-0-SUB-15104-0001-1 15104 JNTII Gate Valves PN 16 Material-Mechanical December 13, 2016 January 12, 2017 December 22, 2016 9 C

ABC-05-0-SUB-15104-0002-1 15104 JNTII Medium Pressure Gate Valves PN25 (GV-3) Material-Mechanical December 21, 2016 January 20, 2017 P P P

SECTION # 15108

ABC-05-0-SUB-15108-0001-0 15108 JNTII Combination Air Valves PN16 & PN25 Material-Mechanical December 13, 2016 January 12, 2017 December 20, 2016 7 A

ABC-05-0-SUB-15108-0002-0 15108 JNTII PN40 Combination Air Valves Material-Mechanical December 21, 2016 January 20, 2017 P P P

SECTION # 15130

ABC-05-0-SUB-15130-0001-0 15130 JNTII Pressure Gauges & Snubbers Material-Mechanical December 7, 2016 January 6, 2017 December 13, 2016 6 C

ABC-05-0-SUB-15130-0001-1 15130 JNTII Pressure Gauges & Snubbers Material-Mechanical December 20, 2016 January 19, 2017 December 22, 2016 2 A

ABC-05-0-SUB-15130-0002-0 15130 JNTII Diaphragm Seal for Pressure Gauge Material-Mechanical December 26, 2016 January 25, 2017 P P P

SECTION # 15450

ABC-05-0-SUB-15450-0001-0 15450 JNTII Flanged Strainers Material-Mechanical December 7, 2016 January 6, 2017 December 12, 2016 5 A

SECTION # 16050

ABC-05-0-SUB-16050-0002-1 16050 JNTII MV Power Cable Material-Electrical December 21, 2016 January 20, 2017 December 26, 2016 5 E

ABC-05-0-SUB-16050-0004-1 16050 JNTII Cable Termination Material-Electrical December 22, 2016 January 21, 2017 December 26, 2016 4 E

35|Page Progress Monthly Report-December2016 USAID WEST BANK/GAZA LOCAL CONSTRUCTION PROGRAM LCP CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 JABA-NUBA TRANSMISSION MAIN PHASE II

SubmittalS' Log

Review Submittal No. Spec. # Project Description Submittal Classification Submitted Date Contract Due Date Response Date Status Days ABC-05-0-SUB-16050-0007-1 16050 JNTII Cable Ladder and Wall Brackets Material-Electrical December 21, 2016 January 20, 2017 December 26, 2016 5 A

ABC-05-0-SUB-16050-0008-0 16050 JNTII Underground PVC PN16 Conduits and Fittings for Duct Banks Material-Electrical December 22, 2016 January 21, 2017 December 26, 2016 4 B

ABC-05-0-SUB-16050-0009-0 16050 JNTII Lighting Fixtures Material-Electrical December 26, 2016 January 25, 2017 December 29, 2016 3 A

SECTION # 16320

ABC-05-0-SUB-16320-0001-0 16320 JNTII Pad Mount Transformer Material-Electrical December 7, 2016 January 6, 2017 December 18, 2016 11 C

ABC-05-0-SUB-16320-0001-1 16320 JNTII Pad Mount Transformer Material-Electrical December 19, 2016 January 18, 2017 December 26, 2016 7 B

SECTION # Spec.

ABC-05-0-SUB-Spec-0001-1 Whole Spec. JNTII Submittals Register Pre- Construction Submittal December 26, 2016 January 25, 2017 P P P

SECTION # CM

ABC-05-0-SUB-CM-0002-0 CM JNTII General Construction Method Statement Pre- Construction Submittal December 18, 2016 January 17, 2017 December 29, 2016 11 C

LEGEND #

Submittals withwith code A B (A= (B =No Exceptions Exceptions Noted) Noted) 29

23

Submittal with Code C D (C= (D= Returned Not Acceptable) or Correction) 202

Submittal with Code E (

E= Record Copy) 5

Pending Submittals (Under Engineers Review) 15

SUM 94

36|Page Progress Monthly Report-December2016

J

ANNEXE

ANNEXE J

GEO-MIS DATA

37 | Page Progress Monthly Report-December 2016 USAID WEST BANK/ GAZA ARCHITECTURE AND ENGINEERING SERVICES CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 PROJECT NAME: JABA-NUBA TRANSMISSION MAIN PHASE II Temproray Job Days Summary Report Task Order Name: Jaba-Nuba Transmission Main Phase II PERIOD FROM: November 16, 2016 Project # and Name: Jaba-Nuba Transmission Main Phase II PERIOD TO: December 31, 2016 Contractor: Arab Brothers Construction & Infrastructure Group No of Female Full Date Site Staff Job Days** Total No. of Full Time No of Male Full Time Total Job Total Job Total Job Days Time Equivalent Notes of Equivalent (FTE) Jobs Equivalent (FTE) Jobs Unskilled Days Days (Male) (Female) (FTE) Jobs in the Comments Month Year Management Engineers Skilled Labor Other in the Month* in the Month* Labor Month* November 2016 0 106 0 0 8 114 4.79 84 30 3.529 1.261 December 2016 13 216 4.875 5 46 284.875 11.970 211.875 73 8.902 3.067 Total of FY 2016 398.875 16.759 295.875 103.000 12.432 4.328 Note : * No of Full Time Equivalent (FTE) Jobs in the Month = Total Job Days / Avg. Days in the Month(23.8) ** This data collection sheet is for Palestinian staff only , experts and foreign employee shall not be included.

38|Page Progress Monthly Report-December2016 USAID WEST BANK/ GAZA ARCHITECTURE AND ENGINEERING SERVICES CONTRACT NO. AID-294-I-13-00003 TASK ORDER NO. AID-294-TO-16-00005 PROJECT NAME: JABA-NUBA TRANSMISSION MAIN PHASE II TEMPORARY JOB DAYS REPORT Task Order Name: Jaba-Nuba Transmission Main Phase II PERIOD FROM: December 01, 2016 Project # and Name: Jaba-Nuba Transmission Main Phase II PERIOD TO: December 31, 2016 Contractor: Arab Brothers Construction & Infrastructure Group Sub-contractor Site Staff Job Days **

Gender Aggregated Worker/Classification (Hours) Man-days* Man-days*

Unskilled Management Engineers Skilled labor labor DATE Male Female Total Other Surveyor Flagman Total Skilled Foreman Office Boy Office Planner (F) Planner Total Unskilled Total Engineers Skilled Labor Civil Engineer Security Guard Security Unskilled Labor Total Management Housekeeper (F) Housekeeper Electrical Engineer Project Coordinator Project (F) Engineer Office Storage Yard Guard Storage Task Order Manager Task Order Equipment Operator Mechanical Engineer Mechanical Safety & Envi. Manager Quality Control Manager Electro- Mechanical Engineer Electro- Mechanical December 1, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 2, 2016 Weekend Holiday "Friday" December 3, 2016 8 0 8 16 8 8 8 8 16 0 0 0 0 0 8 0 0 0 1 9 0 0 1 8 3 December 4, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 5, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 6, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 7, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 8, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 9, 2016 Weekend Holiday "Friday" December 10, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 11, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 12, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 13, 2016 8 0 8 16 8 8 8 8 16 0 0 0 0 0 8 0 0 0 1 9 0 0 1 8 3 December 14, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 15, 2016 8 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 1 8 0 0 1 7 3 December 16, 2016 Weekend Holiday "Friday" December 17, 2016 0 0 8 16 8 8 8 8 8 0 0 0 0 0 8 0 0 0 0 8 0 0 1 6 3 December 18, 2016 0 0 8 16 8 8 8 8 8 0 0 0 0 0 8 8 8 0 0 8 0 0 3 8 3 December 19, 2016 0 0 8 16 8 8 8 8 8 0 0 0 0 0 8 8 8 0 0 8 0 0 3 8 3

39|Page Progress Monthly Report-December2016 40|Pag ** * Total Man Total Total of Month Totalof December December December December December December December December December December December December This data collection sheet is forLocal sheet is collection data This e Progress MonthlyReport-December2016 DATE - days 30 29 28 27 26 25 24 23 22 20 21 31 , , , , , , , , , , , , 2016 2016 2016 2016 2016 2016 2016 2016 2016 2016 2016 2016 = Total Hours Total

0 Task Order Manager / Management 8 0 Quality Control Manager ( CCN 104 0 0 0 0 0 0 0 0 0 0 Safety & Envi. Manager ) staff only staff 0 0 0 0 0 0 0 0 0 0 0 Project Coordinator 192 4 4 0 8 8 8 8 8 8 8 ,

expatriate and third country national employee shall not be included not employee shall country national third and expatriate Electro- Mechanical Engineer 488 24 24 24 24 24 24 24 24 24 16 Civil Engineer 192 8 8 8 8 8 0 0 8 8 8 Mechanical Engineer Engineers 208 8 8 8 8 8 8 8 8 8 8 Electrical Engineer Worker/Classification (Hours) 208 8 8 8 8 8 8 8 8 8 8 Office Engineer (F) 200 8 8 8 8 0 8 8 8 8 8 Planner (F) 240 16 16 8 8 8 8 8 8 8 8 Surveyor 24 8 8 8 0 0 0 0 0 0 0

Foreman Skilledlabor 0 0 0 0 0 0 0 0 0 0 0 Weekend HolidayWeekend"Friday" HolidayWeekend"Friday" Skilled Labor Site Staff Job Days ** Job Site Staff 15 8 5 2 0 0 0 0 0 0 0 Equipment Operator . Unskilled 0 0 0 0 0 0 0 0 0 0 0

Flagman labor 40 16 16 8 0 0 0 0 0 0 0 Unskilled Labor 176 4 4 4 4 4 4 4 4 8 8 Housekeeper (F) 96 8 8 8 8 8 8 8 8 8 8 Office Boy 96 8 8 8 8 8 8 8 8 8 8 Security Guard 0 0 0 0 0 0 0 0 0 0 0 Storage Yard Guard 13 0 0 0 0 0 0 0 0 0 0 Total Management 216 9.5 9.5 8 9 8 8 8 9 9 8

Total Engineers Man-days* 4.875 1.625 1.25 2 0 0 0 0 0 0 0 Total Skilled 5 1 2 2 0 0 0 0 0 0 0 Total Unskilled 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 46 3 3 Total Other Gender Aggregated Gender 211.875 13.125 11.25 12.5 9 9 8 8 9 9 8 Male Man-days* 2.5 2.5 2.5 2.5 1.5 2.5 2.5 2.5 73 3 3 Female

K

ANNEXE

ANNEXE K

DRAFT FLYERS.

41 | Page Progress Monthly Report-November 2016 USAID Funded Infrastructure Needs Program: USAID funded infrastructure Needs Program focuses on the rehabilitation or construction of roads, water and wastewater. The USAID objective is to help the Palestinian economy by improving Palestinian access to basic infrastructure and services. Jaba-Nuba Transmission Main Phase II: With funding from the American people, and in cooperation with the Palestinian Water Authority and Surif Municipality, Kharas Municipality, Nuba Municipality, Beit Ula Municipality and Hatta village council and the Arab Brothers Local CO. is implementing the second phase of Jaba-Nuba Transmission Main Pipeline Project. Project Objective: The objective of this project is to improve the regional water system and expand services to new customers in order to bring clean water to the northwest villages of the . This project includes: • Constructing new transmission pipelines. • Rehabilitating an existing transmission pipeline. • Constructing new distribution pipelines. • Constructing new service connection chambers, • Improving existing water reservoirs and constructing new booster pump stations. Project’s Completion Date: Project implementation is expected to last 390 days, ending in December 2017.

L

ANNEXE

ANNEXE L

60 DAYS PLAN OF OPERATION

44 | Page Progress Monthly Report-November 2016 AID-294-TO-16-00005 Jaba-Nuba Transmission Main JNT-II Phase II Project TASK filter: 60 Days . Activity ID Activity Name Original Early Start Early Finish Total Activity % Calendar Budgeted Total 2017 2018 Duration Float Complete Cost Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan AID-294-TO-16-00005 Jaba-Nuba Transmission Main Phase II 208.38Project 15-Nov-16 11-Jun-17 135.63 $285,222.78 11-Jun-17, AID-294-TO-16-00005 Jaba-Nuba Transmission Main Phase II Project Milestones 42.00 15-Nov-16 27-Dec-16 22.50 $0.00 27-Dec-16, Milestones General Milestones 0.00 15-Nov-16 15-Nov-16 0.00 (7 days) $0.00 15-Nov-16, General Milestones MS-001 Start Date (NTP) 0.00 15-Nov-16 0.00 0% (7 days) $0.00 Start Date (NTP), 15-Nov-16 Intermediate Milestones 10.00 14-Dec-16 27-Dec-16 18.50 (ABC 6WD) $0.00 27-Dec-16, Intermediate Milestones MS-003 Mobilization Completion Date 0.00 14-Dec-16 0.00 0% (ABC 6WD) $0.00 Mobilization Completion Date, MS-004 Start of Surif Booster Station 0.00 27-Dec-16 18.50 0% (ABC 6WD) $0.00 Start of Surif Booster Station, 27-Dec-16 MS-005 Start of Kharas Booster Station 0.00 27-Dec-16 16.00 0% (ABC 6WD) $0.00 Start of Kharas Booster Station, 27-Dec-16 Coordination with Local and Israeli Authorities Prior to Execution36.00 Phase 15-Nov-16 26-Dec-16 6.00 (ABC 6WD) $0.00 26-Dec-16, Coordination with Local and Israeli Authorities Prior to Execution Phase CO-000 Coordination With Local Authorities ( Municipality, Council )36.00 and Israeli 15-Nov-16Prior to Excution26-Dec-16 Phases 6.00 0% (ABC 6WD) $0.00 Coordination With Local Authorities ( Municipality, Council ) and Israeli Prior to Excution Phases Mobilization 7.00 07-Dec-16 14-Dec-16 0.00 (ABC 6WD) $277,922.78 14-Dec-16, Mobilization MOB-001 Engineers Offices Including Furniture 3.00 07-Dec-16 10-Dec-16 0.00 0% (ABC 6WD) $0.00 Engineers Offices Including Furniture MOB-002 Contractor Offices Including Furniture 5.00 07-Dec-16 12-Dec-16 2.00 0% (ABC 6WD) $0.00 Contractor Offices Including Furniture MOB-003 Storage Yard and all Connections 5.00 07-Dec-16 12-Dec-16 2.00 0% (ABC 6WD) $0.00 Storage Yard and all Connections MOB-004 Electrical and IT Equipments Installation 3.00 10-Dec-16 12-Dec-16 2.00 0% (ABC 6WD) $0.00 Electrical and IT Equipments Installation MOB-005 Temporary Facilities 4.00 07-Dec-16 11-Dec-16 3.00 0% (ABC 6WD) $0.00 Temporary Facilities MOB-006 Security System 1.00 10-Dec-16 10-Dec-16 4.00 0% (ABC 6WD) $0.00 Security System MOB-007 Parking Areas 5.00 07-Dec-16 12-Dec-16 2.00 0% (ABC 6WD) $0.00 Parking Areas MOB-008 Sign Boards 1.00 14-Dec-16 14-Dec-16 0.00 0% (ABC 6WD) $0.00 Sign Boards MOB-009 Summary of Mobilization 7.00 07-Dec-16 14-Dec-16 0.00 0% (ABC 6WD) $277,922.78 Summary of Mobilization Submittals 56.00 15-Nov-16 19-Jan-17 219.50 (ABC 6WD) $0.00 19-Jan-17, Submittals Pre Construction Submittals 35.00 15-Nov-16 25-Dec-16 7.00 (ABC 6WD) $0.00 25-Dec-16, Pre Construction Submittals PCS-001 Prep.&Submit Copy of Guarantee & Insurances (Original to USAID)3.00 15-Nov-16 17-Nov-16 23.00 0% (ABC 6WD) $0.00 Prep.&Submit Copy of Guarantee & Insurances (Original to USAID) PCS-002 Approval of Guarantee & Insurances (Original to USAID) 0.00 01-Dec-16 27.00 0% (ABC 6WD) $0.00 Approval of Guarantee & Insurances (Original to USAID), PCS-003 Prep.&Submit List of Materials&Equip. to be Procured from Israel,5.00 Locally&Abroad22-Nov-16 27-Nov-16 15.00 0% (ABC 6WD) $0.00 Prep.&Submit List of Materials&Equip. to be Procured from Israel, Locally&Abroad PCS-004 Approval of List of Materials&Equip. to be Procured from Israel,0.00 Locally&Abroad 11-Dec-16 19.00 0% (ABC 6WD) $0.00 Approval of List of Materials&Equip. to be Procured from Israel, Locally&Abroad, PCS-005 Prep.&Submit Submittal Schedule 7.00 22-Nov-16 29-Nov-16 13.00 0% (ABC 6WD) $0.00 Prep.&Submit Submittal Schedule PCS-006 Approval of Submittal Schedule 0.00 13-Dec-16 17.00 0% (ABC 6WD) $0.00 Approval of Submittal Schedule, PCS-007 Prep.&Submit List of Permits&Licenses 6.00 26-Nov-16 01-Dec-16 11.00 0% (ABC 6WD) $0.00 Prep.&Submit List of Permits&Licenses PCS-008 Approval of List of Permits&Licenses 0.00 15-Dec-16 15.00 0% (ABC 6WD) $0.00 Approval of List of Permits&Licenses, PCS-009 Prep.&Submit of 60 Day Plan of Operation 7.00 22-Nov-16 29-Nov-16 13.00 0% (ABC 6WD) $0.00 Prep.&Submit of 60 Day Plan of Operation PCS-010 Approval of 60 Day Plan of Operation 0.00 13-Dec-16 17.00 0% (ABC 6WD) $0.00 Approval of 60 Day Plan of Operation, PCS-011 Prep.&Submit Project Overview Bar Chart 6.00 22-Nov-16 28-Nov-16 14.00 0% (ABC 6WD) $0.00 Prep.&Submit Project Overview Bar Chart PCS-012 Approval of Project Overview Bar Chart 0.00 12-Dec-16 18.00 0% (ABC 6WD) $0.00 Approval of Project Overview Bar Chart, PCS-013 Prep.&Submit Key Staff 4.00 22-Nov-16 26-Nov-16 16.00 0% (ABC 6WD) $0.00 Prep.&Submit Key Staff PCS-014 Approval of Key Staff 0.00 10-Dec-16 20.00 0% (ABC 6WD) $0.00 Approval of Key Staff, PCS-015 Prep.&Submit of Project Temporary Sign 3.00 26-Nov-16 28-Nov-16 14.00 0% (ABC 6WD) $0.00 Prep.&Submit of Project Temporary Sign PCS-016 Approval of Project Temporary Sign 0.00 12-Dec-16 18.00 0% (ABC 6WD) $0.00 Approval of Project Temporary Sign, PCS-017 Prep.&Submit of Engineer's Field Offices Layout 3.00 20-Nov-16 22-Nov-16 0.00 0% (ABC 6WD) $0.00 Prep.&Submit of Engineer's Field Offices Layout PCS-018 Approval of Engineer's Field Offices Layout 0.00 06-Dec-16 0.00 0% (ABC 6WD) $0.00 Approval of Engineer's Field Offices Layout, PCS-019 Prep.&Submit Field Office Furniture, Computer Systems and Miscellaneous3.00 20-Nov-16 22-Nov-16 0.00 0% (ABC 6WD) $0.00 Prep.&Submit Field Office Furniture, Computer Systems and Miscellaneous PCS-020 Approval of Field Office Furniture, Computer Systems and Miscellaneous0.00 06-Dec-16 0.00 0% (ABC 6WD) $0.00 Approval of Field Office Furniture, Computer Systems and Miscellaneous, PCS-021 Prep.&Submit of QC/QA Plan with Testing Lab CV 7.00 22-Nov-16 29-Nov-16 13.00 0% (ABC 6WD) $0.00 Prep.&Submit of QC/QA Plan with Testing Lab CV PCS-022 Approval of QC/QA Plan with Testing Lab CV 0.00 13-Dec-16 17.00 0% (ABC 6WD) $0.00 Approval of QC/QA Plan with Testing Lab CV, PCS-023 Prep.&Submit Safety Plan 7.00 26-Nov-16 03-Dec-16 10.00 0% (ABC 6WD) $0.00 Prep.&Submit Safety Plan PCS-024 Approval of Safety Plan 0.00 17-Dec-16 14.00 0% (ABC 6WD) $0.00 Approval of Safety Plan, PCS-025 Prep.&Submit General Traffic Control Plan 7.00 29-Nov-16 06-Dec-16 7.00 0% (ABC 6WD) $0.00 Prep.&Submit General Traffic Control Plan PCS-026 Approval of General Traffic Control Plan 0.00 20-Dec-16 11.00 0% (ABC 6WD) $0.00 Approval of General Traffic Control Plan, PCS-027 Prep.&Submit Environmental Monitoring & Mitigation Plan 7.00 27-Nov-16 04-Dec-16 9.00 0% (ABC 6WD) $0.00 Prep.&Submit Environmental Monitoring & Mitigation Plan PCS-028 Approval of Environmental Monitoring & Mitigation Plan 0.00 18-Dec-16 13.00 0% (ABC 6WD) $0.00 Approval of Environmental Monitoring & Mitigation Plan, PCS-029 Prep.&Submit General Construction Method Statement 7.00 26-Nov-16 03-Dec-16 10.00 0% (ABC 6WD) $0.00 Prep.&Submit General Construction Method Statement PCS-030 Approval of General Construction Method Statement 0.00 17-Dec-16 14.00 0% (ABC 6WD) $0.00 Approval of General Construction Method Statement, PCS-031 Prep.&Submit Original CPM Construction Schedule 4.00 07-Dec-16 11-Dec-16 3.00 0% (ABC 6WD) $0.00 Prep.&Submit Original CPM Construction Schedule PCS-032 Approval of Original CPM Construction Schedule 0.00 25-Dec-16 7.00 0% (ABC 6WD) $0.00 Approval of Original CPM Construction Schedule, PCS-033 Prep.&Submit Construction Risk Management Program 4.00 29-Nov-16 03-Dec-16 10.00 0% (ABC 6WD) $0.00 Prep.&Submit Construction Risk Management Program PCS-034 Approval of Construction Risk Management Program 0.00 17-Dec-16 14.00 0% (ABC 6WD) $0.00 Approval of Construction Risk Management Program, PCS-035 Prep.&Submit Dilapidation Survey 5.00 29-Nov-16 04-Dec-16 9.00 0% (ABC 6WD) $0.00 Prep.&Submit Dilapidation Survey PCS-036 Approval of Dilapidation Survey 0.00 18-Dec-16 13.00 0% (ABC 6WD) $0.00 Approval of Dilapidation Survey, PCS-046 Prep. & Submit of Dump Site. 5.00 22-Nov-16 27-Nov-16 15.00 0% (ABC 6WD) $0.00 Prep. & Submit of Dump Site. PCS-056 Approval of Dump Site 0.00 11-Dec-16 19.00 0% (ABC 6WD) $0.00 Approval of Dump Site, Construction Submittals 56.00 15-Nov-16 19-Jan-17 219.50 (ABC 6WD) $0.00 19-Jan-17, Construction Submittals Material Submittals 50.00 15-Nov-16 12-Jan-17 225.50 (ABC 6WD) $0.00 12-Jan-17, Material Submittals Civil 37.00 30-Nov-16 12-Jan-17 225.50 (ABC 6WD) $0.00 12-Jan-17, Civil CS-001 Prep.&Submit Shrinkable & Raping Tape - Product Data 7.00 05-Dec-16 12-Dec-16 22.50 0% (ABC 6WD) $0.00 Prep.&Submit Shrinkable & Raping Tape - Product Data CS-002 Approval of Shrinkable & Raping Tape - Product Data 0.00 12-Jan-17 22.50 0% (ABC 6WD) $0.00 Approval of Shrinkable & Raping Tape - Product Data, CS-003 Prep.&Submit Backfilling Material-Test Report/Soil Classification7.00 08-Dec-16 15-Dec-16 49.50 0% (ABC 6WD) $0.00 Prep.&Submit Backfilling Material-Test Report/Soil Classification CS-005 Prep&Submit Indentification Tape - Sample 7.00 05-Dec-16 12-Dec-16 15.50 0% (ABC 6WD) $0.00 Prep&Submit Indentification Tape - Sample Actual Level of Effort Milestone Date Revision Approved Actual Work summary 11 Dec 2016 Sr.Planning Eng. H. Swaiti Ali Naser - CEO Remaining Work Critical Remaining Work © Oracle Corporation

4 5 |Page Progress Monthly Report - December 2016 AID-294-TO-16-00005 Jaba-Nuba Transmission Main JNT-II Phase II Project TASK filter: 60 Days . Activity ID Activity Name Original Early Start Early Finish Total Activity % Calendar Budgeted Total 2017 2018 Duration Float Complete Cost Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan CS-006 Approval of Indentification Tape - Sample 0.00 12-Jan-17 15.50 0% (ABC 6WD) $0.00 Approval of Indentification Tape - Sample, CS-007 Prep.&Submit Bedding Material - Test Report/Soil Classification7.00 08-Dec-16 15-Dec-16 49.50 0% (ABC 6WD) $0.00 Prep.&Submit Bedding Material - Test Report/Soil Classification CS-009 Prep.&Submit Perforated Pipes (Tank Underdrain System) 7.00 10-Dec-16 17-Dec-16 34.50 0% (ABC 6WD) $0.00 Prep.&Submit Perforated Pipes (Tank Underdrain System) CS-011 Prep.&Submit (Tank Piping(gravity / Pressure),Fixtures&Equipment)7.00 - Product25-Dec-16 Data 02-Jan-17 72.50 0% (ABC 6WD) $0.00 Prep.&Submit (Tank Piping(gravity / Pressure),Fixtures&Equipment) - Product Data CS-013 Prep.&Submit Base Course, Gradation and Physical Properties7.00 08-Dec-16 15-Dec-16 40.50 0% (ABC 6WD) $0.00 Prep.&Submit Base Course, Gradation and Physical Properties CS-015 Prep.&Submit Asphalt Mix Design - Test Report 7.00 08-Dec-16 15-Dec-16 248.50 0% (ABC 6WD) $0.00 Prep.&Submit Asphalt Mix Design - Test Report CS-017 Prep.&Submit MC Prime Coat - Data Sheet 7.00 15-Dec-16 22-Dec-16 187.50 0% (ABC 6WD) $0.00 Prep.&Submit MC Prime Coat - Data Sheet CS-019 Prep.&Submit of RC Tack Coat - Data Sheet 7.00 04-Jan-17 11-Jan-17 171.50 0% (ABC 6WD) $0.00 Prep.&Submit of RC Tack Coat - Data Sheet CS-021 Prep.&Submit Manhole Cover,Handhole Manhole, Frame and Steps7.00 - Product21-Dec-16 Data 28-Dec-16 37.50 0% (ABC 6WD) $0.00 Prep.&Submit Manhole Cover,Handhole Manhole, Frame and Steps - Product Data CS-023 Prep.&Submit Precast Reinforced Concrete Manhole - Data Sheet7.00 & Certificates10-Dec-16 17-Dec-16 47.50 0% (ABC 6WD) $0.00 Prep.&Submit Precast Reinforced Concrete Manhole - Data Sheet & Certificates CS-025 Prep.&Submit Formwork & Ties - Product Data 7.00 15-Dec-16 22-Dec-16 5.50 0% (ABC 6WD) $0.00 Prep.&Submit Formwork & Ties - Product Data CS-027 Prep.&Submit Steel Reinforcement - Data Sheet&Certificates7.00 20-Dec-16 27-Dec-16 1.50 0% (ABC 6WD) $0.00 Prep.&Submit Steel Reinforcement - Data Sheet&Certificates CS-029 Prep.&Submit Water Stop&Joints in Concrete - Product Data 7.00 10-Dec-16 17-Dec-16 2.50 0% (ABC 6WD) $0.00 Prep.&Submit Water Stop&Joints in Concrete - Product Data CS-031 Prep.&Submit Concrete Mix Design - B200,B250,B300 7.00 13-Dec-16 20-Dec-16 10.50 0% (ABC 6WD) $0.00 Prep.&Submit Concrete Mix Design - B200,B250,B300 CS-041 Prep.&Submit Tank Construction Joints- Sample & Product Data7.00 15-Dec-16 22-Dec-16 37.50 0% (ABC 6WD) $0.00 Prep.&Submit Tank Construction Joints- Sample & Product Data CS-399 Prep.&Submit Cathodic Protection Anods and Accessories Product7.00 Data 15-Dec-16 22-Dec-16 40.50 0% (ABC 6WD) $0.00 Prep.&Submit Cathodic Protection Anods and Accessories Product Data CS-419 Prep.&Submit Fence and Gates Data Sheet 7.00 30-Nov-16 07-Dec-16 202.50 0% (ABC 6WD) $0.00 Prep.&Submit Fence and Gates Data Sheet CS-429 Approval of Fence and Gates Data Sheet 0.00 08-Jan-17 202.50 0% (ABC 6WD) $0.00 Approval of Fence and Gates Data Sheet, Electrical and Instruments 49.00 15-Nov-16 11-Jan-17 116.50 (ABC 6WD) $0.00 11-Jan-17, Electrical and Instruments CS-047 Prep.&Submit Earthing and lightning system - Product Data 7.00 15-Dec-16 22-Dec-16 117.50 0% (ABC 6WD) $0.00 Prep.&Submit Earthing and lightning system - Product Data CS-049 Prep&Sub of Instrumentation (flow meter, pressure regulating valve,7.00 level 31-Dec-16element, level 08-Jan-17switches, intrusion113.50 switches)0% (ABC 6WD) $0.00 Prep&Sub of Instrumentation (flow meter, pressure regulating valve, level element, level switches, intrusion switches) CS-053 Prep.&Submit Electrical light panel (Power Panel) - Product Data7.00 04-Jan-17 11-Jan-17 72.50 0% (ABC 6WD) $0.00 Prep.&Submit Electrical light panel (Power Panel) - Product Data CS-055 Prep.&Submit Electrical conductors, conduits, and electrical manholes7.00 - Product10-Dec-16 Data 17-Dec-16 137.50 0% (ABC 6WD) $0.00 Prep.&Submit Electrical conductors, conduits, and electrical manholes - Product Data CS-081 Prep.&Submit MCC 7.00 31-Dec-16 08-Jan-17 2.50 0% (ABC 6WD) $0.00 Prep.&Submit MCC CS-092 Prep.&Submit Hydroponeumatic Control Bladder Tank Instruments7.00 15-Nov-16 22-Nov-16 78.50 0% (ABC 6WD) $0.00 Prep.&Submit Hydroponeumatic Control Bladder Tank Instruments CS-093 Approval of Hydroponeumatic Control Bladder Tank Instruments0.00 22-Dec-16 78.50 0% (ABC 6WD) $0.00 Approval of Hydroponeumatic Control Bladder Tank Instruments, CS-179 Prep.&Submit of Cable and Wires 7.00 15-Dec-16 22-Dec-16 129.50 0% (ABC 6WD) $0.00 Prep.&Submit of Cable and Wires Mechanical 46.00 15-Nov-16 08-Jan-17 90.50 (ABC 6WD) $0.00 08-Jan-17, Mechanical CS-070 Prep.&Submit Booster Pumps and VFD's and Cans 7.00 31-Dec-16 08-Jan-17 2.50 0% (ABC 6WD) $0.00 Prep.&Submit Booster Pumps and VFD's and Cans CS-102 Prep&Submit Steel Pipes,Specials,Fittings - Product Data 7.00 17-Nov-16 24-Nov-16 0.50 0% (ABC 6WD) $0.00 Prep&Submit Steel Pipes,Specials,Fittings - Product Data CS-103 Approval of Steel Pipes,Specials,Fittings - Product Data 0.00 25-Dec-16 0.50 0% (ABC 6WD) $0.00 Approval of Steel Pipes,Specials,Fittings - Product Data, CS-110 Prep&Submit Butter Fly Valves - P roduct Data 7.00 15-Nov-16 22-Nov-16 103.50 0% (ABC 6WD) $0.00 Prep&Submit Butter Fly Valves - Product Data CS-111 Approval of Butter Fly Valves - Product Data 0.00 22-Dec-16 103.50 0% (ABC 6WD) $0.00 Approval of Butter Fly Valves - Product Data, CS-126 Prep&Submit Magnetic Flow Water Meters - Product Data 7.00 31-Dec-16 08-Jan-17 31.50 0% (ABC 6WD) $0.00 Prep&Submit Magnetic Flow Water Meters - Product Data Shop Drawings Submittals 43.00 30-Nov-16 19-Jan-17 29.50 (ABC 6WD) $0.00 19-Jan-17, Shop Drawings Submittals Civil 43.00 30-Nov-16 19-Jan-17 29.50 (ABC 6WD) $0.00 19-Jan-17, Civil CS-141 Prep&Submit Pums / Tank / Room Lands Survey Layout & Sections5.00 (Exacavation15-Dec-16 Plan)20-Dec-16 0.00 0% (ABC 6WD) $0.00 Prep&Submit Pums / Tank / Room Lands Survey Layout & Sections (Exacavation Plan) CS-143 Prep&submit Shop Drawing for Retaining Wall / Fence Wall 5.00 15-Dec-16 20-Dec-16 2.50 0% (ABC 6WD) $0.00 Prep&submit Shop Drawing for Retaining Wall / Fence Wall CS-145 Prep&submit Shop Drawing for Surif Tank 10.00 31-Dec-16 11-Jan-17 6.50 0% (ABC 6WD) $0.00 Prep&submit Shop Drawing for Surif Tank CS-147 Prep.&Submit Shop Drawing for Kharas Tank 10.00 31-Dec-16 11-Jan-17 36.50 0% (ABC 6WD) $0.00 Prep.&Submit Shop Drawing for Kharas Tank CS-149 Prep&Submit Transmission Pipeline Surif - Shop Drawing 10.00 09-Jan-17 19-Jan-17 20.50 0% (ABC 6WD) $0.00 Prep&Submit Transmission Pipeline Surif - Shop Drawing CS-258 Prep. & Submit Fence and Posts 10.00 30-Nov-16 11-Dec-16 21.50 0% (ABC 6WD) $0.00 Prep. & Submit Fence and Posts CS-268 Approval of Fence and Posts 0.00 11-Jan-17 21.50 0% (ABC 6WD) $0.00 Approval of Fence and Posts, Method Statements 18.00 10-Dec-16 29-Dec-16 144.50 (ABC 6WD) $0.00 29-Dec-16, Method Statements CS-300 Prep.&Submit Confined Space Safety Plan 5.00 25-Dec-16 29-Dec-16 144.50 0% (ABC 6WD) $0.00 Prep.&Submit Confined Space Safety Plan CS-302 Prep.&Submit Welder Qualifications&Field Welding Procedure5.00 15-Dec-16 20-Dec-16 45.50 0% (ABC 6WD) $0.00 Prep.&Submit Welder Qualifications&Field Welding Procedure CS-304 Prep.&Submit Trench Excavation Safety Plan 5.00 10-Dec-16 14-Dec-16 50.50 0% (ABC 6WD) $0.00 Prep.&Submit Trench Excavation Safety Plan CS-306 Prep.&Submit Testing Laboratory Certifications for Shop&Steel5.00 Welders 10-Dec-16 14-Dec-16 50.50 0% (ABC 6WD) $0.00 Prep.&Submit Testing Laboratory Certifications for Shop&Steel Welders Procurement 156.00 05-Dec-16 11-Jun-17 105.50 (ABC 6WD) $0.00 11-Jun-17, Procurement Construction Materials and Equipments 7.00 05-Dec-16 12-Dec-16 18.00 (ABC 6WD) $0.00 12-Dec-16, Construction Materials and Equipments PR-001 Supply all needed construction material and equipment to storage7.00 Yards 05-Dec-16 12-Dec-16 18.00 0% (ABC 6WD) $0.00 Supply all needed construction material and equipment to storage Yards Supply and Deliver of Steel Pipes,Fittings,Valves,Instruments,Paints By ABC140.00 24-Dec-16 11-Jun-17 105.50 (ABC 6WD) $0.00 11-Jun-17, Supply and Deliver of Steel Pipes,Fittings,Valves,Instruments,P aints By ABC Galvanized Steel Pipes and Fittings 60.00 26-Dec-16 06-Mar-17 45.50 (ABC 6WD) $0.00 06-Mar-17, Galvanized Steel Pipes and Fittings Material Ordered and Manufacturer 60.00 26-Dec-16 06-Mar-17 45.50 (ABC 6WD) $0.00 06-Mar-17, Material Ordered and Manufacturer PR-006 First Order and Manufacturer of Galvanized Steel Pipes and Fittings60.00 26-Dec-16 06-Mar-17 45.50 0% (ABC 6WD) $0.00 First Order and Manufacturer of Galvanized Steel Pipes and Fittings Welded Pipes and Fittings 60.00 26-Dec-16 06-Mar-17 0.50 (ABC 6WD) $0.00 06-Mar-17, Welded Pipes and Fittings Material Ordered and Manufacturer 60.00 26-Dec-16 06-Mar-17 0.50 (ABC 6WD) $0.00 06-Mar-17, Material Ordered and Manufacturer PR-002 First Order and Manufacturer of Welded Steel Pipes and Fittings60.00 26-Dec-16 06-Mar-17 0.50 0% (ABC 6WD) $0.00 First Order and Manufacturer of Welded Steel Pipes and Fittings Hydro-pneumatic Bladder Surge Tank 140.00 24-Dec-16 11-Jun-17 78.50 (ABC 6WD) $0.00 11-Jun-17, Hydro-pneumatic Bladder Surge Tank Material Ordered and Manufacturer 140.00 24-Dec-16 11-Jun-17 78.50 (ABC 6WD) $0.00 11-Jun-17, Material Ordered and Manufacturer PR-056 Order and Manufacturer of Hydro-pneumatic Bladder surge tank140.00 24-Dec-16 11-Jun-17 78.50 0% (ABC 6WD) $0.00 Order and Manufacturer of Hydro-pneumatic Bladder surge tank Fence 30.00 09-Jan-17 12-Feb-17 202.50 (ABC 6WD) $0.00 12-Feb-17, Fence Material Ordered and Manufacturer 30.00 09-Jan-17 12-Feb-17 202.50 (ABC 6WD) $0.00 12-Feb-17, Material Ordered and Manufacturer PR-483 Order and Manufacturer of Fence /Gates 30.00 09-Jan-17 12-Feb-17 202.50 0% (ABC 6WD) $0.00 Order and Manufacturer of Fence /Gates Execution Phase 15.00 27-Dec-16 14-Jan-17 6.50 (ABC 6WD) $7,300.00 14-Jan-17, Execution Phase Boosters Execution Phase 15.00 27-Dec-16 14-Jan-17 6.50 (ABC 6WD) $7,300.00 14-Jan-17, Boosters Execution Phase Surif Booster Station 8.00 27-Dec-16 05-Jan-17 13.50 (ABC 6WD) $7,300.00 05-Jan-17, Surif Booster Station Site Preparation / First Stage 8.00 27-Dec-16 05-Jan-17 13.50 (ABC 6WD) $7,300.00 05-Jan-17, Site Preparation / First Stage Civil Works 8.00 27-Dec-16 05-Jan-17 13.50 (ABC 6WD) $7,300.00 05-Jan-17, Civil Works

Actual Level of Effort Milestone Date Revision Approved Actual Work summary 11 Dec 2016 Sr.Planning Eng. H. Swaiti Ali Naser - CEO Remaining Work Critical Remaining Work © Oracle Corporation

46|Page Progress Monthly Report - December 2016 AID-294-TO-16-00005 Jaba-Nuba Transmission Main JNT-II Phase II Project TASK filter: 60 Days . Activity ID Activity Name Original Early Start Early Finish Total Activity % Calendar Budgeted Total 2017 2018 Duration Float Complete Cost Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan A1000 Apply Safety Measures /Fencing/ Demolition, removal, clear and5.00 grub site27-Dec-16 (Open Access 02-Jan-17Road) 13.50 0% (ABC 6WD) $2,500.00 Apply Safety Measures /Fencing/ Demolition, removal, clear and grub site (Open Access Road) A1010 Site grading and preparation 3.00 03-Jan-17 05-Jan-17 13.50 0% (ABC 6WD) $4,800.00 Site grading and preparation Kharas Booster Station 15.00 27-Dec-16 14-Jan-17 6.00 (ABC 6WD) $0.00 14-Jan-17, Kharas Booster Station Site Preparation / First Stage 15.00 27-Dec-16 14-Jan-17 6.00 (ABC 6WD) $0.00 14-Jan-17, Site Preparation / First Stage Civil Works 15.00 27-Dec-16 14-Jan-17 6.00 (ABC 6WD) $0.00 14-Jan-17, Civil Works A5720 Apply Safety Measures /Demolition, removal, clear and grub site10.00 (Open Access27-Dec-16 Road) 08-Jan-17 6.00 0% (ABC 6WD) $0.00 Apply Safety Measures /Demolition, removal, clear and grub site (Open Access Road) A5730 Site grading and preparation 5.00 09-Jan-17 14-Jan-17 6.00 0% (ABC 6WD) $0.00 Site grading and preparation (O&M),Inspection,Commissioning,Start Up and Training 10.00 21-Dec-16 02-Jan-17 11.00 (ABC 6WD) $0.00 02-Jan-17, (O&M),Inspection,Commissioning,Start Up and Training Initial Operation and Manufacturer Technical Manual Submittals (O&M) 10.00 21-Dec-16 02-Jan-17 11.00 (ABC 6WD) $0.00 02-Jan-17, Initial Operation and Manufacturer Technical Manual Submittals (O&M) A5750 Prep and Submit Safety and Health Training 10.00 21-Dec-16 02-Jan-17 11.00 0% (ABC 6WD) $0.00 Prep and Submit Safety and Health Training

Actual Level of Effort Milestone Date Revision Approved Actual Work summary 11 Dec 2016 Sr.Planning Eng. H. Swaiti Ali Naser - CEO Remaining Work Critical Remaining Work © Oracle Corporation

47|Page Progress Monthly Report - December 2016 GRAPHICAL REPORT FOR SUMMARY SCHEDULE 11-Dec-16 11:18

WBS Code WBS Name Total Activities 2017 2018 Q4 Q1 Q2 Q3 Q4 Q1 JNT-II AID-294-TO-16-00005 Jaba-Nuba Trans mission Main Phase II Project 1217 09-Dec-17 JNT-II.1 Milestones 21 09-Dec-17 JNT-II.1.1 General Milestones 2 09-Dec-17 JNT-II.1.2 Intermediate Milestones 14-Dec-1619 29-Nov-17 JNT-II.2 Coordination with Local and Israeli Authorities Prior to Execution Phase 1 26-Dec-16 JNT-II.3 Mobilization 07-Dec-169 14-Dec-16 JNT-II.4 Submittals 264 09-Dec-17 JNT-II.4.1 Pre Construction Submittals 38 25-Dec-16 JNT-II.4.2 Construction Submittals 216 25-Apr-17 JNT-II.4.2.1 Material Submittals 132 11-Apr-17 JNT-II.4.2.1.1 Civil 30-Nov-1650 02-Apr-17 JNT-II.4.2.1.2 Electrical and Instruments 36 11-Apr-17 JNT-II.4.2.1.3 Mechanical 46 11-Apr-17 JNT-II.4.2.2 Shop Drawings Submittals 30-Nov-1674 25-Apr-17 JNT-II.4.2.2.1 Civil 30-Nov-1636 25-Apr-17 JNT-II.4.2.2.2 Mechanical 18 04-Feb-17 24-Apr-17 JNT-II.4.2.2.3 Electrical 20 04-Feb-17 22-Apr-17 JNT-II.4.2.3 Method Statements 10-Dec-1610 30-Mar-17 JNT-II.4.3 Post Construction Submittals 10 29-Nov-17 09-Dec-17 JNT-II.5 Procurement 05-Dec-1699 11-Oct-17 JNT-II.5.1 Construction Materials and Equipments 05-Dec-161 12-Dec-16 JNT-II.5.2 Supply and Deliver of Steel Pipes,Fittings,Valves,Instruments,Paints By ABC 98 24-Dec-16 11-Oct-17 JNT-II.5.2.2 Galvanized Steel Pipes and Fittings 2 26-Dec-16 14-Mar-17 JNT-II.5.2.1 Welded Pipes and Fittings 2 26-Dec-16 14-Mar-17 JNT-II.5.2.3 Flanged Gate Valves 2 24-Apr-17 29-Jul-17 JNT-II.5.2.29 Pipe Identification Tape 2 14-Jan-17 25-Feb-17 JNT-II.5.2.37 Shrinkable & Raping Tape 2 14-Jan-17 25-Feb-17 JNT-II.5.2.5 Ball Valves 2 24-Apr-17 29-Jul-17 JNT-II.5.2.6 Threaded Gate Valves 2 24-Apr-17 07-Aug-17 JNT-II.5.2.7 Butter Fly Valves 2 24-Apr-17 07-Aug-17 JNT-II.5.2.8 Combination Air Release Valves 2 24-Apr-17 03-Aug-17 JNT-II.5.2.9 Pressure Reducing Valves 2 24-Apr-17 18-Sep-17 JNT-II.5.2.10 Pressure Relief Valves 2 24-Apr-17 30-Aug-17 JNT-II.5.2.11 Flow Control Valves with Orifice Plate 2 24-Apr-17 12-Sep-17 JNT-II.5.2.12 Float Level Valve 2 24-Apr-17 07-Sep-17 JNT-II.5.2.13 Magnetic Flow Water Meter 2 24-Apr-17 29-Jul-17 JNT-II.5.2.14 Mechanical Water Meter 2 24-Apr-17 29-Jul-17 JNT-II.5.2.15 Check Valves 2 24-Apr-17 07-Aug-17 JNT-II.5.2.16 Strainers 2 24-Apr-17 07-Aug-17 JNT-II.5.2.18 Dismantling / Flexible / Restrained Joint Dressers 2 24-Apr-17 29-Jul-17 JNT-II.5.2.19 Service Connection 2 07-Mar-17 04-May-17 JNT-II.5.2.20 Future Service Connection Fittings 2 07-Mar-17 04-May-17 JNT-II.5.2.21 Pre-Cast Concrete Manholes 2 18-Jan-17 22-Mar-17 JNT-II.5.2.38 Manhole Cover,Handhole Manhole, Frame and Steps 2 30-Jan-17 03-Apr-17 JNT-II.5.2.22 Yard Pressure Piping 2 02-Feb-17 30-Apr-17 JNT-II.5.2.23 Yard Gravity Piping 2 02-Feb-17 30-Apr-17 JNT-II.5.2.25 Step Down Transformer 2 21-Feb-17 11-Oct-17

All Projects Summary Page 1 of 3 © Oracle Corporation WBS Elements below Project

48 Page Progress Monthly Report - December 2016 11-Dec-16 11:18

WBS Code WBS Name Total Activities 2017 2018 Q4 Q1 Q2 Q3 Q4 Q1 JNT-II.5.2.26 Hydro-pneumatic Bladder Surge Tank 2 24-Dec-16 18-Jun-17 JNT-II.5.2.27 Water Stop 2 18-Jan-17 05-Mar-17 JNT-II.5.2.28 Booster Pump & Cans & Booster VFDs 2 08-Feb-17 24-Aug-17 JNT-II.5.2.31 Control System (Sofware ) 2 04-Mar-17 03-May-17 JNT-II.5.2.32 Instruments 2 08-Feb-17 10-Apr-17 JNT-II.5.2.33 Power,Control,Single Cables 2 12-Apr-17 15-Jun-17 JNT-II.5.2.34 Conduits 2 18-Jan-17 13-Mar-17 JNT-II.5.2.35 Sump Pump LCP 2 23-Feb-17 23-Sep-17 JNT-II.5.2.36 Sump Pump (P-301) 220V/1Ph/50Hz 2 21-Feb-17 01-Oct-17 JNT-II.5.2.39 Power Panel 2 12-Feb-17 06-Jun-17 JNT-II.5.2.40 RTU Panel with PLC 2 27-Feb-17 16-Sep-17 JNT-II.5.2.41 Motor Control Center ( MCC ) 2 08-Feb-17 02-Oct-17 JNT-II.5.2.42 Power Protection Material (Generator Box,UPS,Batteries) 2 08-Mar-17 23-May-17 JNT-II.5.2.4 Cathodic Protection Anods and Accessories 2 24-Jan-17 16-Mar-17 JNT-II.5.2.17 Fence 2 09-Jan-17 18-Feb-17 JNT-II.5.2.24 Coating Material 2 12-Feb-17 23-Mar-17 JNT-II.5.2.30 Lightning Protection and Grounding System 2 24-Jan-17 05-Mar-17 JNT-II.5.2.43 Fire Detection and Firefighting System 2 01-Apr-17 22-Jun-17 JNT-II.5.2.44 Doors and Windows 2 03-Apr-17 15-Aug-17 JNT-II.5.2.45 Plumbing Fixtures 2 12-Apr-17 09-Jul-17 JNT-II.5.2.46 Scupper Drains Roofing 2 12-Apr-17 09-Jul-17 JNT-II.5.2.47 HVAC-Plumbing Material 2 12-Apr-17 09-Jul-17 JNT-II.5.2.48 Split Units and Accessories 2 12-Apr-17 13-Aug-17 JNT-II.5.2.49 Lighting Poles 2 12-Apr-17 09-Jul-17 JNT-II.6 Execution Phase 811 27-Dec-16 29-Nov-17 JNT-II.6.1 Boosters Execution Phase 536 27-Dec-16 29-Nov-17 JNT-II.6.1.1 Surif Booster Station 265 27-Dec-16 29-Nov-17 JNT-II.6.1.1.1 Site Preparation / First Stage 4 27-Dec-16 25-Jan-17 JNT-II.6.1.1.3 Retaining Walls 40 25-Jan-17 02-Apr-17 JNT-II.6.1.1.4 Break Tank- 250 Cubic Meter 45 19-Feb-17 12-Oct-17 JNT-II.6.1.1.5 Electrical and Control Building - Small 35 27-Apr-17 25-Nov-17 JNT-II.6.1.1.7 Booster / Transmission Pump System 33 23-May-17 25-Nov-17 JNT-II.6.1.1.10 Septic and Seepage Tank 18 23-May-17 10-Aug-17 JNT-II.6.1.1.6 Guard House 40 22-Jun-17 18-Nov-17 JNT-II.6.1.1.2 Yard Works 34 06-Aug-17 12-Sep-17 JNT-II.6.1.1.9 Site Preparation / Second Stage 2 24-Oct-17 05-Nov-17 JNT-II.6.1.1.8 Site Finishing Works 14 27-Aug-17 29-Nov-17 JNT-II.6.1.2 Kharas Booster Station 271 27-Dec-16 27-Nov-17 JNT-II.6.1.2.1 Site Preparation / First Stage 3 27-Dec-16 24-Jan-17 JNT-II.6.1.2.9 Fence Walls 35 24-Jan-17 21-Mar-17 JNT-II.6.1.2.3 Retaining Walls 15 24-Jan-17 18-Mar-17 JNT-II.6.1.2.10 Site Preparation / Second Stage 2 08-Mar-17 26-Mar-17 JNT-II.6.1.2.4 Break Tank- 250 Cubic Meter 45 26-Mar-17 12-Oct-17 JNT-II.6.1.2.6 Guard House 40 19-Jun-17 01-Oct-17 JNT-II.6.1.2.5 Electrical and Control Building - Small 35 25-Jun-17 27-Nov-17 JNT-II.6.1.2.13 Septic and Seepage Tank 17 03-Aug-17 30-Aug-17 JNT-II.6.1.2.7 Booster / Transmission Pump System 30 29-Aug-17 27-Nov-17

All Projects Summary Page 2 of 3 © Oracle Corporation WBS Elements below Project

49|Page Progress Monthly Report - December 2016