The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Power Sector Recovery Project (P146696)
AFRICA | Guinea | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 10 | ARCHIVED on 19-Dec-2019 | ISR39910 | Public Disclosure Authorized
Implementing Agencies: Ministry of Energy and Hydraulics, The Republic of Guinea, Electricite de Guinee (EDG), Unité de Gestion du PRSE/MEH, Unité de Gestion du Projet/EDG
Key Dates
Key Project Dates
Bank Approval Date: 16-Jun-2014 Effectiveness Date: 30-Jan-2015 Planned Mid Term Review Date: 16-Nov-2017 Actual Mid-Term Review Date: 30-Apr-2018 Original Closing Date: 31-Dec-2019 Revised Closing Date: 31-Dec-2020 pdoTable Public Disclosure Authorized Project Development Objectives
Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve the technical and commercial performance of the national power utility.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
Components Table
Name Support the improvement of EDGâs performance through a Management Services Contract:(Cost $16.00
Public Disclosure Authorized M) Improvement of Conakry Distribution Network and Commercial Performance of EDG:(Cost $46.70 M) Technical Assistance, Capacity building and Project Implementation Support:(Cost $12.30 M)
Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating High High
Implementation Status and Key Decisions
As of end November 2019, the project progress can be summarized as follows:
Public Disclosure Authorized The overall disbursement of the project, considering the additional financing of US$25 million, has improved from 62% in May 2019 to 70%. The component 1 –Management service contract (MSC) of Electricité de Guinée (EDG): the four-year MSC has completed on October 9, 2019. Implementation of the MSC contributed to technical improvement of EDG. The commercial performance, has only marginally improved, and there have been few results in capacity building of local human resources. Rollout of meters, including smart meters for large consumers and capacity building constitute top priority for EDG and component 2 provides support in that direction. The final technical audit of the MSC will be carried out in February 2020, to document the outcomes of the MSC and lessons learnt.
12/19/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
The implementation of Component 2- physical investments to improve network conditions and commercial performance of EDG and component 3- technical assistance, capacity building and support to project implementation remains Moderately Satisfactory. There has been a satisfactory progress on the implementation of key contracts. Key ongoing activities include the rehabilitation of distribution network and regularization of connections in Dixinn; the regularization of illegal connections in Kaloum, Ratoma and Matoto; the implementation of a Revenue Protection Program for 6000 large consumers accounting for more than 70% of annual revenues; the supply and installation of electricity consumption meters and the census/mapping of all consumers of EDG. These contracts are at an advanced stage of implementation.
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance -- High High Macroeconomic -- Substantial Substantial Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Sustainability Substantial Substantial Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- High High Other ------
Overall -- High High
Results
PDO Indicators by Objectives / Outcomes
Improve the technical performance of the national power utility
IN00783042
►Direct project beneficiaries (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 1,400,000.00 3,000,000.00 3,160,000.00 3,200,000.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783052
Female beneficiaries (Percentage, Custom Supplement)
Baseline Actual (Previous) Actual (Current) End Target
12/19/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Value 52.00 52.00 52.00 52.00
IN00783054
►Electricity losses per year (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 42.00 30.00 29.90 23.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
Improve the commercial performance of the national power utility
IN00783043
►Bill collection rate (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 77.00 84.13 83.00 96.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
Improve the technical performance of the national power utility
IN00783051
►Average daily hours of service (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 12.00 19.00 19.00 18.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
Improve the technical performance of the national power utility
IN00783044
►Average interruption frequency per year in the project area (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 942.00 350.00 350.00 350.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
People provided with new or improved electricity service
IN00783045
►People provided with new or improved electricity service (Number, Corporate)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 205,000.00 220,726.00 318,000.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783053
People provided with new or improved electricity service - Female (Number, Corporate Supplement)
12/19/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 106,000.00 114,777.00 165,360.00
Intermediate Results Indicators by Components
Technical Assistance, Capacity building and Project Implementation Support
IN00783057
►Average number of hours of training per staff per year (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 17.00 17.00 17.00
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
Support the improvement of EDGs performance through a Management Services Contract
IN00783055
►Operator appointed (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No Yes Yes Yes
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783058
►Technical auditor appointed (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No Yes Yes Yes
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
Improvement of Conakry Distribution Network and Commercial Performance of EDG
IN00783056 ►People provided with access to electricity services under the project by household connections â rehabilitation and standardization of household connections in Kaloum Ratoma and Matoto (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 205,000.00 216,150.00 216,150.00
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783059
►Number of substations refurbished (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 55.00 55.00 67.00
12/19/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783060 ►People provided with access to electricity services under the project by household connections â Rehabilitation and extension of Distribution network in Dixinn (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 26,000.00 36,574.00 74,178.00
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783061
►Beneficiary satisfaction survey completed, published (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No No No Yes
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783062
►Number of meters installed, of which large consumer smart meters (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 52,256.00 61,786.00 57,887.00
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783063
►Number of transformers installed (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 12.00 39.00 24.00
Date 25-Aug-2017 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783064
►Distribution lines constructed or rehabilitated under the project (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 80.33 157.00 96.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
IN00783065
Distribution lines rehabilitated under the project (Kilometers, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 80.33 157.00 96.00
Date 21-May-2014 12-Jun-2019 11-Dec-2019 31-Dec-2020
Data on Financial Performance
12/19/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed
P146696 IDA-54990 Effective USD 22.60 22.60 0.00 20.20 0.10 99%
P146696 IDA-61830 Effective USD 25.00 25.00 0.00 3.69 20.55 15%
P146696 IDA-H9690 Effective USD 27.40 27.40 0.00 24.79 0.00 100%
Key Dates (by loan)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P146696 IDA-54990 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020 P146696 IDA-61830 Effective 16-Mar-2018 17-Apr-2018 09-Nov-2018 31-Dec-2020 31-Dec-2020 P146696 IDA-H9690 Effective 16-Jun-2014 02-Jul-2014 30-Jan-2015 31-Dec-2019 31-Dec-2020
Cumulative Disbursements
12/19/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Power Sector Recovery Project (P146696)
Restructuring History
There has been no restructuring to date.
Related Project(s)
P160771-Power Sector Recovery Project - Additional Financing
12/19/2019 Page 7 of 7