2016 Connect NC Bond - State Parks System Projects

START BOND YEAR PARK FUNDS PROJECT STATUS DECEMBER 2017 2016 Beech Creek Bog State $600,000 Land Acquisition State is awaiting matching Federal Natural Area grant. Bond will contribute $600,000 towards a $1 million project for the acquisition of 175 acres. 2016 $1,500,000 Expanded Parking Design at Rumbling Bald 95% complete. Summit parking improvements design just getting underway. 2016 Cliffs of the Neuse State $692,400 Campground Improvements Project completed. Park 2016 Crowders Mountain State $750,000 Expanded Parking Design 75% complete. Park 2016 $990,750 Land Acquisition Land owner contact underway for multiple tracts. 2016 Knob State Park $900,000 Land Acquisition Four tracts closed. 2016 State Recreation $1,125,000 Bathroom and Picnic Area Project completed. Area Renovations 2016 $135,000 10-Inch Cannon and Project completed. Carriage

2016 $1,477,500 Family Campground Design 85% complete. Improvements 2016 $2,505,750 New Campground Design 45% complete. 2016 Haw State Park $1,500,000 Land Acquisition One tract closed, landowner contact underway 2016 $651,750 Campground Improvements Design 80% complete.

2016 Jordan Lake State $3,000,000 Campground/Electric Hook- Bid award in process. Recreation Area up Improvements 2016 $3,021,000 Visitor Center Design 65% complete. 2016 $750,000 Land Acquisition Landowner contact underway. 2016 Mount Jefferson State $1,500,000 Land Acquisition One tract approved to purchase, one Natural Area under option. 2016 Mountains-to-Sea and other $4,500,000 Land Acquisition One tract closed, one additional tract State approved by COS. Additional landowner contacts are being made. 2016 $675,000 Land Acquisition Multiple tracts have been purchased and all funds expended. 2016 Pilot Mountain State Park $4,481,850 Visitor Center Design 65% complete. 2016 $1,125,000 New Campground Design 80% complete. 2016 Weymouth Woods State $428,250 Land Acquisition Landowner contact underway. Natural Area 2016 Yellow Mountain State $2,250,000 Land Acquisition Two tracts pending approvals, Natural Area landowner contact underway. 2017 Carolina Beach State Park $855,000 Campground Improvements Design just getting underway. Page 2

START BOND YEAR PARK FUNDS PROJECT STATUS DECEMBER 2017 2017 $5,700,750 Long Farm Day Use Negotiating design contract. Development/Farm Seat Renovations 2017 State Park $2,830,500 Visitor Center Negotiating design contract. 2017 Jockey's Ridge State Park $751,500 Visitor Center Renovations Negotiating design contract. 2017 Kerr Lake State Recreation $3,750,000 Campground Renovations Scoping underway, expected to Area advertise for designer fall 2017. 2017 State Park $2,307,000 Campground Improvements Negotiating design contract.

2017 River State Park $2,628,750 Community Building, New Negotiating design contract. Public Access 2017 State Park $600,000 Summit Improvements Negotiating design contract. 2017 $2,830,500 Visitor Center Negotiating design contract. 2018 State $1,501,500 Contact Station Scheduled to start design in 2018. Park 2018 Hammocks Beach State Park $1,125,000 Mainland Improvements Scheduled to start design in 2018.

2018 $2,100,000 Vade Mecum (Camp Scheduled to start design in 2018. Sertoma) Improvements 2018 Medoc Mountain State Park $1,383,750 Education/Community Scheduled to start design in 2018. Building and Play Area 2018 Stone Mountain State Park $1,338,000 Visitor Center Scheduled to start design in 2018. Improvements 2019 Deep River State $1,281,000 Public Access Development Scheduled to start design in 2019. 2019 Falls Lake State Recreation $789,750 Community Building Scheduled to start design in 2019. Area 2019 State Park $1,506,000 New Campground Scheduled to start design in 2019. 2019 Lower State $203,250 Bynum Day Use Scheduled to start design in 2019. Natural Area Development 2019 Merchants Millpond State $870,750 Campground Improvements Scheduled to start design in 2019. Park 2019 Morrow Mountain State $1,537,500 New Rental Cabins Scheduled to start design in 2019. Park 2019 State Park $575,250 Visitor Contact Station Scheduled to start design in 2019. 2019 South Mountains State Park $2,250,000 New Campground Scheduled to start design in 2019. 2019 William B. Umstead State $1,725,000 Community/Education Scheduled to start design in 2019. Park Building ------TOTAL STATE PARK BOND $75,000,000