DEVELOPMENT ON THE ROMANIAN TERRITORY OF THE NATIONAL GAS TRANSMISSION SYSTEM ON THE BULGARIA – ROMANIA – HUNGARY – AUSTRIA ROUTE (BRUA PROJECT, PHASE 1)
- CURRENT STATUS -
CESEC MEETING
February 13th 2020
1 PROJECT DESCRIPTION
BRUA Project Phase 1 represents the construction of new gas transmission pipeline sections to facilitate the connection between incumbent gas lines, from Podișor to Recaş, along Podișor-Corbu- Hurezani-Hațeg-Recaș and consisting of: Gas transmission pipeline Podișor – Recaș:
o Length: 479 km o Pressure: 63 bar o Diameter: Dn 800
Compressor stations:
o TCS Podișor (Giurgiu county) o TCS Bibești (Gorj county) o TCS Jupa (Caraș-Severin county)
The pipeline route crosses the Counties: Giurgiu, Teleorman, Dâmbovița, Argeș, Olt, Vâlcea, Gorj, Hunedoara, Caraș- Severin and Timiș Investment value 478.6 mil. Euro.
2 PROJECT CONSTRUCTION (1)
The pipeline construction works between TN Podișor and TN Recaș are divided as follows: Pipeline execution of LOT 1 from KM 0 to KM 180, the works are ongoing, and the section between Podișor and Corbu (approx. 82 km) is completed and commissioned Pipeline execution of LOT 2 from KM 180 to KM 320, the works are ongoing Pipeline execution of LOT 3 from KM 320 to KM 479, the works are ongoing and the section Jupa and Recas (approx. 72 km) is completed and commissioned Pipeline automation and security LOT –executed on the entire route, from KM 0 to KM 479
Additionally the construction of the Project included also the procurement by Transgaz of the materials and equipment, namely: pipes and bends, valves, electro insulated joints and compressor units for the three compressor stations. All such contracts are currently completed, all the materials and equipment are received and are on the construction site, at various stages of execution.
3 PROJECT CONSTRUCTION (2)
Construction of the compressor stations Construction of TCS JUPA – completed and commissioned on 30 September 2019 Construction of TCS BIBEȘTI – ongoing, to be commissioned on 30 June 2020 Construction of TCS PODIȘOR – completed and commissioned on 31 October 2019
l
The total current progress of the Project: 84,2 % at the beginning of February 2020 Welded pipe: approx. 380 km
4 PROJECT CONSTRUCTION (3)
Considering the progress achieved, Transgaz Offers the firm exit capacity through IP Csanádpalota of 0.75 bcm/y as of 1 October 2019 Offers the firm exit capacity through IP Ruse – Giurgiu of 0.75 bcm/y as of 1 November 2019.
• Following the implementing of the BRUA Project Phase 1 Transgaz will offer: The firm reverse flow capacity through IP Csanádpalota – Nădlac of 1.75 bcm/y starting with 01.10.2020 and The firm reverse flow capacity at IP Ruse – Giurgiu of 1.5 bcm/y starting with 01.10.2020.
5 Disclaimer: The sole responsibility for this publication lies with the author. The European Union and the Innovation & Networks Executive Agency (I.N.E.A) are not responsible for any use that may be made of the information contained herein.