THIRD NATIONAL HIGHWAY WORLD BANK PROJECT Public Disclosure Authorized ENVIRONMENTAL MANAGEMENT PLAN

CONSTRUCTION PACKAGE V-A Public Disclosure Authorized

NATIONAL HIGHWAYS AUTHORITY OF INDIA NEW (Ministry of Surface Transport)

March, 2000 Public Disclosure Authorized TABLE OF CONTENTS

B. SCOPE OF THE PROJECT ...... I

C. ENVIRONMENTAL MANAGEMENT PLAN ...... 2.,,,,,....2

C. I INTRODUCTION.2 C.2 OBJECTIVESOF THE EMP ...... 2 C.l7. DesignStage.2 C 2.2 - ConstructionStage ...... 2 C.2.3 Operation Stage.2 C.3 MEETING THE EMP OBJECTIVES . . . 2 C.3.1 Commitment to address environmental health, safetv and social impacts ...... 3 C.3.2 Commitmeritfor constant dialogue with the public and interested stakeholders. 3 C. 3.3 Commitment related to training ...... -- ...... 3....-....3 C.43v Commitment to meet legal requirements .3

D. CRITICAL IMPACTS TO BE ADDRESSED-PACKAGE V-A - -.-.-...-...... - _3

E. ENVIRONMENTAL MANAGEMENT PLAN (EMP)...... _ 3

F. MONITORING PROGRAMME ...... _ _ 19

F. I PERFORMANCEINDICATORS (PIS) .. 19

F.2 SELECTIONOF INDICATORSFOR MONITORING ...... ---- '------'t------.------19 F2. 1 Ambient Air Quality (AAQ) Monitoring.19 F.2.2 Water Quality Monitoring ...... 20 K 7 3 Noise level Monitoring.21 F.2.4 Success of Revegetation ...... 22 F.2.5 Soil Contamination ...... :22 F.3 MONITORINGPLAN .. 22 G. ENVIRONMENTAL MANAGEMENT- BUDGET .24 ENVIRONMENTAL MANAGEMENT PLAN - V A

A. INTRODUCTION

The Governmentof India (GoI), acting through the National HighwaysAuthority of India (NHAI),a part of the Ministry of SurfaceTransport (MOST)is improvingthe Sikandrato Dhanbadportion of the NH-2 as part of the World Bank assistedThird NationalHighway Project. To facilitate implementationof the project, the project corridor has been divided into five packages, referred to as packages I to V. International consultants' have been appointed for the planning and design of each of these five packages. Based on the findings of the various project reports prepared by the consultants, the following contract packageshave been selectedas candidatesfor the appraisal by the World Bank in February2000. Of these, the packagesto be implementedin the first phasewould be selectedduring the AppraisalMission.

Table 1 Contract Packages - IlIrd National Highway Project

Candidatefor WB contract Descnption From (km) To(km) Length(km) Appraisal& package Implementation I - A Agra- Shikohabad 200.000 265.000 65.000 I I 13 Shikohabad- Sarai Ikdil 265.000 330.000 65.000 I - c SaraiIkdi - Bognipur(Sikandra) 330.000 400.000 70.000 11- A Sikandra- Bhaunti 393.000 470.000 61.600 Yes II 11- B Bhaunti- FatehpurBorder 471.000 38.000 51.330 II - c FatehpurBorder- Khaga 38.000 115.000 77.000 Yes III- A Khaga-Kokhraj 115.000 158.000 43.000 Yes III III- B Kokhraj- PaharpurVillage 158.000 245.000 87.000 _ III- c Paharpurvillage -Raja Talab 245.000 317.000 72.000 Yes IV -A RajaTalab - Mohania 318.000 65.000 78.000 IV -B Mohania-Sasarambypass 65.000 110.000 45.000 Yes IV IV -C Sasarambypass 110.000 140.000 30.000 IV - D SoneRiver - Aurangabad 140.000 180.000 40.000 Yes V- A Aurangabao- Barachatti 180.000 240.000 60.000 Yes V V- B Barachatti- Gorhar 240.000 320.000 80.000 IV {-c Gorhar- Barwa-Adda(Dhanbad) 320.000 398.750 78.750 Yes Source EIA Reports,Packages llto V, IlIrd National HighwayProject This report details the EnvironmentalManagement Plan for ContractPackage V-A, of the Third National HighwayProject. The EMPis basedon the EIA/EMPreports carried out along PackageV of the project.

B. SCOPEOF THE PROJECT

The high volume carryingstretch of the NH-2, between Sikandrato Dhanbadis to be widenedto four lane, within the existing RoW,avoiding land acquisitionas far as possible,except for locationswhere it is absolutelyessential from traffic engineering,environmental and social aspects where a diversion from the existingalignment is necessitated. Following is the scope of work as stated in the ToR for feasibility studies and detailed engineering consultancyservices, "... The scope will consist mainly widening of the existing two lane to four lane within the RoW, inter alia including fixation of alignment, alignments of the proposed widening work, improvements, if any. Required to the existing alignment, identification and fixation of alignments of short bypasses, identification of locations of service roads, identification, location and design of toll plazas etc. necessary arbonculture along the highway and plantation on the median strips compatible with the surrounding landscape shall be suitably suggested." The Consultantshall undertake a detailed environmental study in accordancewith the standards presanbed by Gol and World Bank and willmake suitable recommendatons and prepare appropriate,mtibgatbon plan and resettlement action plans 7The Engineenrng design of the project will absorb all acceptable recommendati0os emerying out of the enirounmentalstudies.

C. ENVIRONMENTALMANAGEMENT PLAN

C.1 INTRODUCTION

The Environmental Management Plan (EMP) consists of the set of mitigation, monitoring and institutional measures to be taken during the design, construction and operation stages of the project to eliminate adverse environmental impacts, to offset them, or to reduce them to acceptable levels. The plan also includes the actions needed for the implementation of these measures.

The major components of the Environmental Management Plan are * Mitigation of potentially adverse impacts * Monitoring during project implementation and operation * Institutional Capacity Building and Training * Implementation Schedule and Environmental Cost Estimates i Integration of EMP with Project planning, design, construction and operation.

C.2 OBJECTIVES OF THE EMP

The main aim of the Environmental Management Plan is to ensure that the various adverse impacts are mitigated and the positive impacts are enhanced. The objectives of the EMP at various stages of the project planning and implementation are as follows:

C.2.1 Design Stage

* To have minimum impact on road side trees, forestation and ground cover * To keep land acquisition and building demolition at a minimum * To provide maximum safety to the highway users and road side communities as well as segregation of local and slow moving traffic in the congested areas * To develop a design that incorporates environmental safeguards and * To provide mitigation measures to all expected environmental degradation

C.2.2 Construction Stage

* To prevent and reduce the negative environmental impacts of the project by implementable mitigation measures, to be carried out by the Contractor. * To ensure that the provisions of the EMP are strictly followed and implemented by strengthening implementation arrangements.

C.2.3 Operation Stage

* To prevent deterioration of environment components of air, water, soil, noise etc. * To improve the safety of the highway users and road side communities

C.3 MEETING THE EMP OBJECTIVES

The following commitments are important to effectively implement the EMP and have been adopted to address the various objectives of the EMP.

2 C.3.1 Commitmentto address environmentalhealth, safety and social impacts To improve the environmentalconditions, including areas such as environmental health, safety and socialimpacts, measureshave been suggestedand includedas part of the EMP.Such measureswill be continuouslydeveloped as an interactiveprocess.

C.3.2 Commitmentfor constant dialoguewith the publicand interestedstakeholders The community consultation processwas carried out right from the inception stage of the project. Continuous dialogue with local inhabitants and stakeholders including public agencies has been establishedon various environmental issuesto obtain their feedback. Consultationwould continue throughoutthe implementationStage of the project.

C.3.3 Commitmentrelated to training For the effective implementationof the EMPmeasures proposed, sustainable institutional arrangements have been proposed.To educate and train the PIU, the personnel of the ConstructionSupervision Consultantsand the Contractors,an extensivetraining schedulehas been worked out as part of the EMP. The training programmewill be implementedas per the scheduleproposed.

C.3.4 Commitmentto meet legal requirements The legal requirements,procedures, etc., that are necessaryor mandatoryfor the commencementof the project have been met. The conditionsstipulated by the various StatutoryAuthorities as the State PollutionControl Boards, Forest Departments etc. will be compliedwith.

D. CRITICALIMPACTS TO BE ADDRESSED- PACKAGEV-A

On the basis of the assessmentof the potential impacts,the critical environmentalcomponents that need to be addressedin the EnvironmentalManagement Plan have been identified. The most critical issuesto be addressedat various locationsalong the project corridor are describedin Table 2 below.

Table 2: Critical Environmental Issues to be Addressed CriticalEnvironmental Issues Location HighPollutant Concentrations - Poor Air Quality Alongthe congestedsettlements and intersections Continuousexposure to highnoise levels Alongthe congestedsettlements and sensitive land uses. Affectingwater resources Communityand village ponds in the directinfluence area Removalof vegetativecover/ roadside tree Alongthe whole stretch plantations Encroachmentonto forest areas, disruption to ProtectedForests (KM 237-KM249.5) wildlife Lossof productiveagricultural lands Marginalin one realignment Soilerosion along the highway Notanticipated SoilContamination Notanticipated Pedestrianand Traffic Safety morepronounced in majorsettlements Trafficcongestion due to encroachmentwithin the existingRoW EnvironmentalQuality at SensitiveReceptors Hospitals,educational institutions and other sensitive land uses E. ENVIRONMENTALMANAGEMENT PLAN (EMP)

The EnvironmentalManagement Plan is meant for mitigation/management/avoidanceof the negative impactsand the enhancementof the variousenvironmental components along the project package.For each measure on the various environmental components to be taken, its location, timeframe, implementationand overseeing/supervisingresponsibilities are listed.The measuresadopted and/or to be adopted during the different stages of the project have been detailed in Table 3.

3 ENVIRONMENTALMANAGEMENT PLAN V A

Table 3 EnvironmentalManagement Plan - PackageVA Environmental RemedialMeasure Reference Location Timeframe MitigationCost Institutionalresponsibility issue/ to contract component documents Implementation Supervision

DESIGN/ PRE-CONSTRUCTON STAGEt M ______

D... 500mlong service road on the northside has been Km185.95 - 186.50, Duringthe Projectpreparation DesignConsultant PIU,NHAI Constricted provided. Madanpur DesignStage cost sections/ 700mservice roads on both sides have been settlements providedwith a underpass. Km210.6-211.430, 600mservice road on bothsides with grade separation;with provision of 16mwide underpass to segregateGaya - Chatratraffic has been suggested. Km.221.75 - 222.30 Thisintersection design will segregatethe cross Dobhi trafficmovement from the highwaymovement.

2.LAND ______.__ D.2.1. At all criticalslopes along the roadsides,turfing will Basedon existing Duringthe Projectpreparation Design PIU,NHAI Embankment bedone to protectthe slopes.This will followthe pavement. DesignStage cost Consultant slopes recommendedpractice for treatmentof Locationof moderate embankmentslopes for erosioncontrol, IRC: 56- . sp: 1974. KM206, 207, 213, 223,225 Locationof critical slopesare: 212, 224

D.2.2Road Theraising of the proposedpavement by 0.6to 1.5 Alongsettlements Duringthe ProjectPreparation Design PIU,NHAI Inundation m from theexisting level in marketplaces will avoid DesignStage cost consultant inundation

4 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental RemedialMeasure Reference Location Timeframe MitigationCost Institutionalresponsibility issue/ to contract component documents Implementation supervision D.2.3.Quarries Existinglicensed quarries that are already in All selectedquarry Duringthe Projectpreparation Design PIU,NHAI and Borrow operationhave been recommended. andborrow pits given DesignStage cost Consultant Areas Non-productive,barren lands, raised lands, river in Appendix1. beds,waste lands have been recommended for borrowingearth. Throughcommunity consultation with the villagers andinteractions with State Department of Fisheries, lowlying areas, wastelands that have a potentialof beingdeveloped into fish ponds/ pisciculture have beenrecommended for borrowareas. D.2.4 Borrowpit will beselected from wastelandoutside All borrowareas Duringdesign ProjectPreparation Design PIU,NHAI Modificationof the roadland; identifiedfor the stage cost consultant Landform Fromhumps above the generalground level within projectgiven in the roadland; Appendix1. Byexcavating tank; Fromland acquired temporary outside the roadland; Frommounds resulting from the diggingof welland loweringof fieldsin vicinityof the road. Whenit becomesnecessary to borrowearth from temporarilyacquired cultivated lands, the depthof borrowpits should not exceed45cm., in suchcases withthe consentof the landowner it couldbe used as borrowand excavated maximum up to adepth of 100cm.

5 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract Il component documents | L Implementton Supervision

3. W ATER _:V__i___X______i;_.Q. D.3.1. Water Compensatory The water resources Duringthe Project preparation Design PIU, NHAI sources Communitypond perennialin nature, will be likely will be impacted DesignStage cost Consultant protectedwith 2m high embankment.Particularly on listed in Appendix3. the highwayside. Theseponds will be excavatedto increasethe depth of the pond. Protection Someponds are closeto pavementshoulder; less KM 186.900(S) than 10m distance.These slopes of these ponds have will bemodifiedso that the water bodiesare at least 10m away from the pavementshoulder. KM 180.825(N) Enhancement KM 219.500 (S) Someponds are close but beyond10m from the pavementshoulder, These ponds only need Im high KM 205.650 (N) earthen pavementso that surfacerun-off does not contaminatethese water bodies.

D.3.2. Drainage The drains will be suitably modifiedso that highway At KM 218.100 to During the Project preparation Design PIU, NHAI does not obstruct these drains. 218.400,on the DesignStage cost Consultant south.( ReferDrawing no. NH/VA-SP-039)

The proposedproject alignmenthas been At 219.9to 220.700 adequatelyprovided with necessaryengineering on the south. solution. This has been done on the basisof highest ( ReferDrawing no. flood level data for the past 50 years. NH/VA-SP-041)

6 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents Implementation Supervision

4. FLORAAND FAUNA ._ __ _ _ .. ____...._,_I;__ D.4.1. Roadside Trees saved by expanding the road on one side in ThroughoutProject During the Rs. 0.12 million for DFO,Design PIU, NHAI plantation uninhabitedstretches. Corridorwithin ROW DesignStage tree removal Consultant,PIU, Treeswill be removedwith prior approvalof DFO. NHAI Compensatoryafforestation as per Forest conservationAct 1980 will be adopted

5. ENVIRONMENTAL QUALITY . . ;-...:.*_ __ N D.5.1. Air Quality Improving road geometryand wideningof ThroughoutProject Duringthe Project preparation Design PIU, NHAI road to smoothentraffic flow. Corridor,especially at DesignStage cost Consultant Pavementroughness will be improvedto a level less sensitivelocations than 3000 mm / KM. Thiswill be done through appropriatepavement designs - MadanpurKM 186. Tree Plantationwill be done on both sides of the - Sherghatiat KM road and medianverges will be planted with shrubs 210. of suitable speciesto reducethe air pollutants - Dobhi at KM 222. concentrationsand to alternatenoise.

7 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental RemedialMeasure Reference Location Timeframe MitigationCost Institutionalresponsibility issue/ to contract component documents Implementation Supervision D.5.2.Noise Removalof bottlenecksand relieving congestion in ThroughoutProject Duringthe Projectpreparation Design PIU,NHAI levels built-upstretches through improved design. Corridor,especially at DesignStage cost Consultant Improvementof junctions/intersections. sensitivelocations Segregationof slowand fast moving traffic. Plantationwill be donewith mixed and large leaf Lowat: area,evergreen species with some deciduous KM216, Gopalpur specieson the slopeportion of the proposed KM234-Barachatti highway. Moderateat: Placesthat are categorized as highlycritical will be KM186-Madanpur providedwith a noisebarrier like a boundarywall KM210-Sherghati alongwith shrubs plantation in frontof them,such asSchools and Hospitals KM222-Dobhi

Placesthat are categorized as critical will be planted withshrubs to providethe requirednoise barrier. Criticalat: Nil

HighlyCritical: KM182.05 (N) KM190.65 (N) KM203.05 (S) KM227.80 (S) KM228.26 (S)

KM189.80 (N) KM 208.025 (N)

6. U TILM ES ______D.6.1. All utilities,likely will beimpacted will berelocated Asper the utility Duringthe Projectpreparation PIU,NHAI, PIU,NHAI Utilitylines / withprior approval of the concemedagencies. relocationdrawings DesignStage cost Concerned community All communityutilities likely will beimpacted, such preparedseparately Government utilities assources of waterwill berelocated to suitable for thisproject. Departments places,identified based on communityneeds.

8 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental RemedialMeasure Reference Location Timeframe MitigationCost Institutionalresponsibility issue/ to contract component . documents Implementation Supervision

7. CULTURALHERiTAGE .. __*______D.7.1. Alignmentwill besuitably routed to avoid/minimize At locationsof cultural Duringthe Projectpreparation PIU, NHAI,NGOs PIU,NHAI Cultural impactto culturalproperty propertieslisted in DesignStage cost andR&R unit properties Engineeringsolutions will beworked out to minimize Appendix4 impact on cultural properties 8. ENVIRONMENTALSAFETY .. ._ .. . . D.8.1.Accidents DesignImprovements at curves. KM180 to KM398.75 Duringthe Projectpreparation Design PIU,NHAI Segregatingslow moving traffic in the marketplaces DesignStage cost Consultant by servicelanes. Serviceroad at: Provisionof widermedian in ruralstretches and KM185 & 186 plantationof shrubs/undertreesto avoid the glare of KM202.6 to 203.3 vehiclesmoving in opposite directions during night. KM210.6 to 211.430 Provisionof propersignage. KM220.950 to Properlighting arrangementswill be made. 222.300 1 1 1 CONSTRUCTIONSTAGE

1. SOIL . . _ - . , _ _ . . - . : . _ . . . . ' ______C.1.1. Soil In borrowpits, the depthof the pit will beregulated ThroughoutProject During Engineeringcost Contractor SC, Erosion that thesides of theexcavation will havea slopenot corridor,borrow pits construction PIU,NHAI steeperthan 1: 4, from the edgeof the finalsection andservice roads of bank. Soilerosion-checking measures such as the formationof sedimentbasins, slope drains, etc, will be carriedout. Whereverthere are earth materials will becut for the roadalignment, care should be taken the rolling terrainwhere the slopegrades are more than 1.5 percentso thatcut side of the earthis not absolutelyvertical, It shouldhave gentle slope while cutting. _ C.1.2.Loss of Normallyagricultural areas will beavoided for During Engineeringcost Contractor SC, topsoil borrowingof materials. construction PIU,NHAI

C.1.3. Constructionvehicles, machinery and equipment will ThroughoutProject During Engineeringcost Contractor SC, Compactionof move,or bestationed in the designatedRoW, to Corridor construction PIU,NHAI soil avoidcompaction of soil. l__

9 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibillity issue/ to contract component documents Implementation Supervision C.1.4. Borrowing No earth will be borrowedfrom within the RoW All borrow areas During Engineeringcost Contractor SC, of Earth Non-productive,barren lands,raised lands,river recommendedin construction PIU,NHAI beds, waste lands havebeen recommendedfor Appendix1 borrowing earth. If new borrow areas are selected,there will be no lossof productivesoil, and environmental considerationsare will be met with. If vehiclescarrying materialsfrom borrow areasare passingthrough some villages,the excavationand carrying of earth will be done during day time only. The unpavedsurfaces used for the haulageof borrow materialswill be maintainedproperly Precautionarymeasures as the coveringof vehicles will be taken to avoidspillage of borrow materials. To avoid any embankmentslippages, the borrow areaswill not be dug continuously. Replantationof trees in borrow areaswill be carried out if required.

C.1.5. Quarry The quarry materialwill be obtained from licensed Quarrysites During Engineeringcost Contractor SC, sites, which operatewith proper environmental recommendedin construction PIU,NHAI clearances,including clearances under the Air Act. Appendix1

C.1.6. Constructionvehicles and equipmentswill be Throughout Project During Engineeringcost Contractor SC, Contaminationof maintainedand refuelled in such a fashion that Corridorand borrow construction PIU,NHAI soil from fuel and oil/dieselspillage does not contaminatethe soil. areas lubricants Fuel storage and refuellingsites will be kept away from drainagechannels and importantwater bodies.

10 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents Implementatbon Supervision C1.7. Earth, if required, will be dumped in selected& All constructionsites During Engineeringcost Contractor SC, Contaminationof approvedarea by the supervisionconsultant. All ThroughoutProject construction PJU,NHAI soil from spoilswill be disposedoff as desiredand the site will Corridor construction be fully cleanedbefore handing over. wastes and The constructionwastes includingbituminous waste quarry materials will be dumped in selectedpits, developedon infertile land. Non-bituminouswastes from constructionactivities will be dumped in borrow pits and coveredwith a layer of the conservedtopsoil. Bituminouswastes will be disposedoff in an identifieddumping site approvedby the SC

2. WATER .. - - ______C.2.1.Water Water sourcesas ponds etc. impactedwill be At all locationsof During Rs. 1,00,000per Contractor SC, bodies replacedand compensatedfor, immediately. water bodiesor cross construction pond PIU,NHAI Desiredmeasures to preventtemporary or drainage permanentdamage to water bodiesIdentified will beavoidedas per EMPClause D.3.1. C.2.2. Other Any communitywater sourceas wells, tube-wells, ReferAppendix 6 and During Engineeringcost Contractor SC, Watersources etc. lost incidentallywill be replacedimmediately. 7 construction + PIU,NHAI Rs. 0.28 million for Beforeand pond protection during the works commencement of construction C.2.3. Drainage At crossdrainage structures, the earth, stone or any ThroughoutProject During Engineeringcost Contractor SC, and run-off other constructionmaterial will be properly disposed Corridor construction PIU,NHAI off, so as not to block the flow of water.

11 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component . documents _ Impiementation Supervision C.2.4. Constructionwork closeto the streams or other ThroughoutProject During Engineeringcost Contractor SC, Contaminationof water bodies will be avoided,especially during Corridor constructionand PIU,NHAI water from monsoon period. after construction All necessaryprecautions will be taken to construct waste temporaryor permanentdevices to preventwater pollution due to increasedsiltation and turbidity. All necessarymeasures will be taken to prevent earthworksand stone works from impedingrivers, streamsand water canalsor existingdrainage system. Wastesmust be collected,stored and taken to approveddisposal site. Water quality will be monitored as envisagedis the MorharRiver EnvironmentalMonitoring Plan MadanpurPond Lilajancanal C.2.5. To avoidcontamination from fuel and lubricants,the ThroughoutProject During Engineeringcost Contractor SC, Contaminationof vehiclesand equipmentswill be properly maintained Corridor construction PIU,NHAI water from fuel and refueled. and lubricants Oil and grease traps will be providedat fuelling locations,to prevent contaminationof water. The slopesof embankmentleading to water bodies will be modifiedand rechanelisedso that Rs. 70,000 per contaminantsdo not enter the water body. pn C.2.6. Sanitation The constructioncamps will be located away from At Constructioncamp During Engineeringcost Contractor SC, and waste the habitation. locations,wherever construction PIU,NHAI disposalin The sewagesystem for such camps will be properly locatedalong the construction designedand built so that no water pollution takes Projectcorridor camps placeto any water body or watercourse. The workplacewill have propermedical facilities. C.2.7. Useof The contractorwill make arrangementsfor water ThroughoutProject During Engineeringcost Contractor SC, water for requiredfor constructionin such a way that the Corridor construction PIU,NHAI construction water availabilityand supply to nearbycommunities remain unaffected. Wastageof water during the constructionwill be minimized.

12 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents Implementation Supervision 3. AIR . :.-.... f^;;4 .;-:*9~.., ;.i .,i!k C.3.1. Emission All vehicles,equipment and machineryused for Monitoringat During Rs. 0.072 million Contractor SC, from construction constructionwill be regularly maintainedto ensure constructionsite near constructionand for air monitoring PIU,NHAI vehicles and that the pollution emissionlevels conform to the Sherghatiand after machinery SPCBnorms. Chauparan Regularmonitoring of air pollutant parameters during the constructionperiod as envisagedin the EnvironmentalMonitoring Plan. The asphalt plants, crushersand the batchingplants will be sited at least 500 m in the downwind directionfrom the nearesthuman settlement. All precautionsto reducethe level of dust emissions ThroughoutProject During Engineeringcost Contractor SC, C.3.2. Dustand from the hot mix plants, crushersand batching Corridor construction PIU,NHAI its treatment plants will be taken up. The hot-mix plants, crushersand batchingplants will be sited at least 800m downwindfrom the nearest habitation.The hot mix plant witl be fitted with dust extractionunits. Water will be sprayedin the lime/cementand earth mixing sites, asphalt mixingsite and temporary serviceand accessroads. After compacting,water will be sprayedon the earthworkregularly to preventdust. Vehiclesdelivering material will be covered. 4. NOISE LEVELS C.4.1. Noisefrom The plants and equipmentused for constructionwill ThroughoutProject During the Contractor SC, vehicles,asphalt strictly conform to CPCBnoise standards. Corridor construction,till PIU,NHAI plants and Vehiclesand equipmentsused will be fitted with the closureof equipments silencer. such sites Noisestandards of industrialenterprises will be strictly enforcedto protect constructionworkers from severenoise impacts. Noise levelwill be monitoredduring the construction Chandisthan, stage, as mentionedin the EnvironmentalMonitoring Sherghati,Dobhi Plan. GopalpurBarachatti

13 ENVIRONMENTAL MANAGEMENTPLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents Implementation Supervision C.4.2. Noisefrom Blastingas per Indian ExplosivesAct will be carried Quarrysites During Engineeringcost Contractor SC, blasting out. construction PIU,NHAI operations Peopleliving near such blastingsites will have prior informationof operationalhours. Blastingwill not be undertakenin night hours. Materialhaulage roads will be properlyregulated. Workersat blasting sites will be providedwith earplugs. C.4.3 Noise Constructionof noise barriersin form of walls and Sensitivelocations During Rs. 0.30 million for Contractor SC, barriers vegetation at locationswith high noiselevels identified construction wall barriers PIU,NHAI exceedingCPCB norms against noise 5. FLORA C.5.1. Lossor Area of tree plantationcleared will be replaced Throughout Project Just before the Rs. 0.09 million for Forest SC, damage to accordingto compensatoryAfforestation Policy Corridor beginning of the compensatory Department PIU,NHAI vegetation under ForestConservation Act-1980. construction afforestation Apart from trees earmarkedfor felling, no additional tree clearingwithin the RoWwill be carried out. Replantationof tree speciesalong new ROW. Rs. 0.72 million for Plantationof shrubsand under trees in the median. plantation in the median

C.5.2. Constructionvehicles, machinery and equipmentwill ThroughoutProject Just before Engineeringcost Forest SC, Compactionof move or be stationed in the designatedarea only Corridor commencement Department PIU,NHAI vegetation (RoW or Col, as applicable),to prevent compaction of construction Bihar of vegetation. While operating on temporarily acquiredland for traffic detours, storage, materialhandling or any other constructionrelated or incidentalactivities, it will be ensuredthat the trampling of soil and damage to naturally occurring herbsand grasseswill be avoided.

14 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents . Implementation I Supervision 6. FAUNA C.6.1. Loss, Constructionworkers will be directednot to disrupt Throughout Project During Not needed Contractor SC, damage or or damage the fauna. Corridor construction PIU,NHAI disruptionto Huntingwill be strictly prohibited fauna 7. SAFETYAND ACCIDENTRISKS .1 - To ensuresafe constructionin the temporary Throughout Project During Engineeringcost Contractor SC, C.7.1. Accident accessesduring construction,lighting devicesand Corridor construction PIU,NHAI risks from safety signal deviceswill be installed. construction Traffic rulesand regulationswill be strictly adhered activites to. At blastingsites, the blasting time, signal and guardingwill be regulated.Prior to blasting the site will be thoroughlyinspected. Blasting will not be carried out during rush hours Safetyof workers undertakingvarious operations during constructionwill be ensured by providing helmets,masks, safety goggles,etc The electricalequipment will be checkedregularly At every work place, a readily availablefirst aid unit includingan adequatesupply of dressingmaterials, a modeof transport (ambulance),nursing staff and an attending doctor will be provided. C.7.2. Health At every workplace,good, and sufficient water ThroughoutProject During Engineeringcost Contractor SC, issues supply will be maintainedto avoid Corridor construction PIU,NHAI waterborne/water-relatedand water-baseddiseases and to securethe health of workers Constructioncamps Adequatedrainage, sanitation and waste disposal will be providedat workplaces. PreventiveMedical care will be providedto workers.

15 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location | Timeframe Mitigation Cost Institutional responsibility issue/ to contract l component documents l Implementation ] Supervision

8.CULTURAL PROPERTIESA _ _ | C.8.1. Damage Relocationof cultural properties ReferAppendix 5 Before Coveredin RAP Contractorand SC, or lossof cultural If any valuableor invaluablearticles such as fabrics, construction Archaeology PIU,NHAI properties coins, artefacts, structures,or other archaeological starts Department relics are discovered,the excavationwill be stopped Bihar. and ArchaeologyDepartment, Bihar. will be intimated. During construction

9. ENVIRONMENTALENHANCEMENT ^ ____it_____-_ C.9.1.Roadside Avenueplantation of foliage shade trees mixed with ThroughoutProject During Contractor SC, landscape flowering trees, shrubsand aromatic plantsas per Corridor construction PIU,NHAI development detailedschemes prepared, will be carriedout.

C.9.2. Roadside Restorationand improvementof bus shelters,bus ThroughoutProject During Engineeringcost Contractor SC, amenities bays and truck lay byes as per detaileddesign will Corridor construction PIU,NHAI be carried out Roadfurniture includingfootpaths, railings,traffic signs, speed zonesigns, etc. will be erected as per design C.9.3. Cultural Enhancementof all cultural propertiesand the ThroughoutProject During Rs.0.21millions Contractor SC, properties accessroads will be completedas per design. Corridor construction PIU,NHAI OPERATION STAGe 0.1.1. The spills at the accidentsites will be cleared Throughout Project Operationperiod Engineeringcost LocalGovt. NHAI Contamination immediately corridor Bodiesincluding from spills due to The left over spills will be scrappedto small lined State PWD, traffic and confinedpits nearby, within the ROW NHAI accidents 0.1.2. Dust Roadsidetree plantationsplanted will be Throughout Project Operationperiod EngineeringCost NHAI NHAI Generation maintained corridor Afforestationwill be taken up at new sites (for example,gram panchayatland, etc.) nearthe road.

16 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility Issue/ to contract component documents Impfementation Supervision 0.1.3. Air Vehicularemissions of critical pollutant parameters MadanpurSherghati Operationperiod Rs. 0.036for air Motor Vehicle NHAI pollution (SPM,RSPM, CO, SO 2 , NO. and Pb)will be Dobhi quality Department, and monitored as per the EnvironmentalMonitoring Plan. management SPCB,NHAI Roadsidetree plantationwill be maintained Vehicularair pollution will be managedand monitored at the proposedtoll plazalocations Public awarenesswill be generated 0.1.4. Noise Noisepollution will be monitored At monitoring Operationperiod Rs. 0.03 million for Motor Vehicle NHAI pollution Public awarenessprogramme will be launched. locations noisemanagement Department and SPCB,NHAI 0.1.5. Water The drainagesystem will be periodicallycleaned MorharRiver Lilajan OperationStage Rs. 0.006 million LocalGovt. NHAI Water quality will be monitoredas per the River for water quality Bodies, NHAI monitoring plan monitoring 0.1.6. Floraand The replantationscheme, containing keystone Throughout Project OperationStage Rs. 2.4 million Forest Forest Fauna (key stone specieswill be strictly monitoredfor first 3 years Corridor +Rs.6.75millions Department UP Department species) for additionaltree UP, NHAI plantation 0.1.7 Soil quality monitoringas per monitoringplan OperationStage Rs. 0.02 million NHAI NHAI Soil 0.1.8 Accidents The 'rules' as definedin Environmental(Protection) Throughout Project OperationStage Motor Vehicle Motor involving Act, 1986will be complied. Corridor Departmentand Vehicle hazardous For deliveryof hazardoussubstances, three SPCB Department, materials certificatesissued by transportationdepartment, NHAI namely permit license,driving licenseand guarding licensewill be required. Vehiclesdelivering hazardous substances will be printed with appropriatesigns. In case of spillage,the report to relevant departmentswill be madeand instructionsfollowed in taking up the contingencymeasures.

17 ENVIRONMENTALMANAGEMENT PLAN V A

Environmental Remedial Measure Reference Location Timeframe Mitigation Cost Institutional responsibility issue/ to contract component documents Implementation supervision 0.1.9 Traffic managementplan will be developed, ThroughoutProject Operationstage EngineeringCost Local NHAI Safety measures especiallyalong congestedlocations corridor Government Traffic control measuresincluding speed limits will Bodies be enforcedstrictly. Further growth of encroachmentand squatting within the ROWwill be discouraged No schoolor hospitalwill be establishedwithin 200 m of the project highway,

18 F. MONITORINGPROGRAMME

The purposeof the monitoring programmeis to ensurethat the envisagedobjectives of the project is achieved and results in desired benefits to the target population. To ensure the effective implementationof the EMP,it is essentialthat an effective monitoring programme be designedand carried out. The broad objectivesare * To evaluatethe performanceof mitigation measuresproposed in the EMP * To evaluatethe adequacyof EnvironmentalImpact Assessment * To suggestimprovements in managementplan, if required * To enhanceenvironmental quality * To satisfy the legaland communityobligations.

F.1 PERFORMANCEINDICATORS (PIS) The physical, biologicaland social componentsidentified as of particular significancein affecting the environmentat critical locationshave been suggestedas PerformanceIndicators (PIs), and are listed below. Air quality Water quality Noiselevels around sensitive locations. Replantationsuccess / survival rate Soil contamination Erosionindices Restorationof borrow pits Sedimentationrate in the downstreamwhere bridges,culverts, etc are built Vital statisticson health * Accidentfrequency

F.2 SELECTIONOF INDICATORSFOR MONITORING The environmental parametersthat may be qualitativelyand quantitatively measuredand compared over a period of time, due to their importance and the availability of standardisedprocedures and expertise,have beenselected as PerformanceIndicators (PIs). Air Quality Noiselevels Water Quality . Flora * Soil Contamination Followingsub-sections describe each of these PIs in detail.

F.2.1 Ambient Air Quality (AAQ) Monitoring Ambient air quality parametersrecommended for monitoring road transportation developmentsare Respirable Particulate Matter (RPM), SuspendedParticulate Matter (SPM), Carbon Monoxide (CO), Oxidesof Nitrogen (NOx),Hydro-Carbons (HC), Sulphur Dioxide (SO2) and Lead (Pb). These are will bemonitored at designated locationsstarting from the commencementof construction activity. Data should be generatedover three days at all identified locationsin accordanceto the NationalAmbient Air Quality Standards.(Table4) The location, duration and the pollution parameterswill bemonitored and the responsibleinstitutional arrangements are detailedout in the MonitoringPlan (Table 7)

19 Table 4: National Ambient Air Quality Standards

Pollutants Time Sensitive Industrial Residential Weighted average Area Area Rural &other Area

SulphurDioxide (SO 2) Annual* 15 pg/m 80 pg/mr 60 pg/mr 24 hours" 30 1201g/mj pg/m' 90 pg/mr Oxides of Nitrogen (No.) Annual& 15 pgg/m 80 pg/mr 65 pg/mr 3 24 hours** 30 pg/rn 120 pg/rn3 91 pg3m3 CarbonMonoxide (CO) 8 hours* 1000 pg/m3 5000pg/m3 2000 pg/mr 1 hour 2000 mg/mr 1000 pg/m3 4000 pg/mr Lead (Pb) Annual* 0.50 gg/mr 1.0 pg/mr 0.75 pg/m3 24 hours* 0.75 pg/mr 1.5 pg/mr 1.00 jg/mr RespirableParticulate Matter Annual* 50`-g/mn 120Ag/mr 60 pg/mr 3 (RPM)-Size less then 10 jm 24 hours" 75 pg/m 150 pg/rm 100 pg/mr SuspendedParticulate Annual* T70ms 360 pg/m' 140 pg/mr Matter (SPM) 24 hours*" 100jg/m 3 500 pg/m3 200 pg/m3

SourceAnon 1996-97,National Ambient Air Quality MonitoringSeries NAQMS/a/1996-97,Central Pollution Control Board, Delhi.

*Average Arithmetic mean of minimum 104 measurement in a year taken for a week 24 hourly at uniform interval.

**24 hourly/8 hourly values should meet 98 percent of the time in a year

F.2.2 Water Quality Monitoring The physicaland chemicalparameters recommended for analysisof water quality relevantto road developmentprojects are pH,total solids,total dissolvedsolids, total suspendedsolids, oil and grease, COD,chloride, lead, zinc and cadmium.The location,duration and the pollutionparameters will bemonitoredand the responsibleinstitutional arrangements are detailedout in the Environmental MonitoringPlan (Table 7) The monitoringis will becarriedout in accordanceto the Indian Standard DrinkingWater Specification - IS10500: 1991 (Table5)

Table 5: Indian Standard Drinking Water Specification-IS 10500:1991

St. Substance or Requirement UndesirableEffect Outside the PermissibleLimit Methods of Remarks No. Characteristic (Desirable Desirable Limit in the Absenceof Test (Ref. To Limit) Alternate Source IS) EssentialCharacteristics 1 Colour,Hazen 5 Above 5, consumeracceptance decreases 25 3025 (Part4) Extendedto 25 only if toxic units, Max. 1983 substancesare not suspected,in absenceof alternatesources 2 Odour Unobjectionable 3025 (Parts a) Test cold and when 5):1984 heated b) Test at severaldilutions 3 Taste Agreeable 3025 (Part 7 Test will beconductedonly and 8) after safety has been 1984 established 4 Turbidity NTU, 5 Above 5, consumeracceptance decreases 10 3025 (Part 10) Max. 1984 5 pH Value 6.5 to 8.5 Beyondthis range the water will affect the No relaxation 3025 (Part 11) mucousmembrane and/or water supply 1984 system 6 Total hardness(as 300 Encrustationin water supplystructure an 600 3025 (Part21) CaCO3) MG/l, Max adverseeffects on domesticuse 1983 7 Iron (as Fe) mg/i, 0.3 Beyondthis limit taste/appearanceare 1 32 of 3025: Max affected, hasadverse effect on domestic 1964 usesand water supplystructures, and promotes iron bacteria B Chlorides(as Cl) 250 Beyondthis limit, taste, corrosionand 1000 3025 (Part 32) mcg/1,Max palatabilityare affected 1988 9 Residual,free 0.2 - 3025 (Part26) Will beapplicableonly when chlorine,mg/1, Min 1986 water is chlorinated.Tested at consumerend. For protection againstviral infection it should be Min

Desirable Characteristics TDissolvedsolids 500 Beyondthis palatabilitydecreases and may 2000 3025 (Part 16) ma/1, Max causegastro intestinal irritation 1984 2 Calcium(as Ca> 75 Encrustationin water supplystructure and 200 3025 (Part 40) m/l, Max adverseeffects on domesticuse 1991 20 Si. Substanceor Requirement UndesirableEffect Outside the Permissible Limit Methods of Remarks No. Characteristic (Desirable Desirable Limit in the Absenceof Test (Ref. To Limit) Alternate Source IS) 3 Magnesium(as 30 Encrustationto water supplystructure and 100 16, 33, 34 of IS Mg),mg/1, Max adverseeffects on domestc use 3025: 1964 4 Copper (as Cu) 0.05 Astringenttaste, discolorationand corrosion 1.5 36 of 3025: mg/1, Max of pipes,fittng and utensilswill be caused 1964 beyond this S Maganese(as Mn) 0.1 Beyondthis limit taste/appearanceare 0.3 35 of 3025: mg/1, Max affected, has adverseeffect on domestic 1964 uses and water supplystructures 6 Sulphate(as 200 200 Beyondthis causesgastro intestinal 400 3025 (Part 24) May be extendedup to 400

SO4) mg/1, Max iritation when magnesiumor sodiumare 1986 provided(as Mg) doesnot resent exceed30 7 Nitrate (as NO2) 45 Beyondthis methaemoglobinemiatakes 100 3025 (Part 34) mg/l, Max place 1988 8 Fluoride(as F) 1 Fluridemay be kept as low as possible. 1.5 23 of 3025: mg/I, Max High fluoride may causefluorosis 1964 9 Phenolic 0.001 Beyondthis, It may causeobjectionable 0.002 54 of 3025: compounds(As taste and odour 1964 ___,H,OH) ma/l, Max 10 Mercury(as Hg) 0.001 Beyondthis, the water becomestoxic No relaxaton (see note) Will betestedwhen pollution mg/l, Max Mercuryion is suspected analyser II Cadmium(as Cd), 0.01 Beyondthis, the water becomestoxic No relaxation (See note) Will betestedwhen pollution mg/1, Max is susoected 12 Selenium(as Se), 0.01 Beyondthis, the water becomestoxic No relaxation 28 of 3025: Will betestedwhen pollution mg/i, Max 1964 s suspected 13 Arsenic(As) mg/1, 0.05 Beyondthis, the water becomestoxic No relaxation 3025 (Part37) Will betestedwhen pollution max 1988 Is suspected 14 Cyanide(As CN), 0.05 Beyondthis limit, the water becomestoxic No relaxation 3025 (Part27) Will betested when pollution ma/i, Max 1986 is susDected 15 Lead(as Pb), mg/i, 0.05 Beyondthis limit, the water becomestoxic No relaxation (see note) Will betestedwhen pollution Max __l_____=_=__is suspected 16 IZinc (As Zn). Mg/i. 5 Beyondthis limit it can causeastringent is 39 of 3025: Will betested when pollution Max I jtaste and an opalescencein water ! 1964) is suspected 17 Anionic detergents 0.2 Beyondthis limit it can causea light froth in 1 Methylene-blue Will betestedwhen pollution (As MBAS)mg/i, water extraction is suspected Max i method 18 Chromium(As 0.05 May be cardnogenicabove this limit No relaxation 38 of 3025: Will betestedwhen pollution 5 Cr +) mg/I, Max L 1964 is suspected 19 Polynuclear May be caronogenicabove this limit . aromatic hydrocarbons(as PAH)c/ll Max 20 Mineraloil mg/i, 0.01 Beyondthis limit undesitabletaste and 0.03 Gas Max odour after chlorinationtake place Chromatographi c method 21 Pesticidesmg/i, Absent Toxic 0.001 - Max 22 Radioactivematenals: 58 of 3025:01964 23 a) Alpha emiters 0.1 - Bq/l, Max 24 Betaemiters pci/i, 1 - Max 25 Aluminium(as Al), 200 Beyondthis limit taste becomesunpleasant 600 13 of 3025:1964- mg/I,Max 26 Aluminium(as Al), 0.03 Cumulativeeffect is reportedto cause 0.2 31 of 3025: mg/i,Max _dementia 1964 27 Boron,mq/1, Max .1 5 29 of 3025:1964 Source: IndIan Standard Dnnk,ng WatarSpecIfIcation-ISIOSOD1991

F.2.3 Noiselevel Monitoring The measurementsfor monitoring noise levelswould be carried out at all designatedlocations along all contract packages in accordanceto the Ambient Noise Standards formulated by Central Pollution ControlBoard (CPCB)in 1989 (refer Table6) Sound pressurelevels would be monitored on twenty-four hour basis.Noise should be recordedat a "A" weighted frequency using a " slow time responsemode" of the measuring instrument. The location, duration and the noise pollution parameters will be monitored and the responsible institutional arrangements are detailed out in the Environmental MonitoringPlan (Table: 7)

21 Table 6: Noise LevelStandards (CPCB) Zone Noiselevel for Noiselevel for Day NightTime Industrialarea 75 70 Commerdalarea 65 55 Residenbalarea 55 45 Silencezone 50 40 iResidential 65 So Commeraal 70 I Daytme - 6.00am - 9.00pm (15 hours) Nighttime - 9.00pm - 6.00am (9 hours)

F.2.4 Successof Revegetation To ensurethe proper maintenanceand monitoringof the compensatoryafforestation being carried out, a regular maintenanceand monitoring of the survival rate of the planted trees is being proposed upto a period of 3 years from the operationalisationof the project. The responsible institutionalarrangements are presentedin the EnvironmentalMonitoring Plan (Table 7).

F.2.5 Soil Contamination Contaminationof the soil, especiallydue to increasedlevels of Pb, Cd and Cr are likely due to the increasedtraffic movement on the project corridor. The comparisonof the concentrationsof these parameters before and after the project coming up would aid in arriving at the increase in concentrationsof these heavy metals,if any.

F.3 MONITORINGPLAN The monitoringplan for the variousperformance indicators of the project in the constructionand operation stages,is summarisedin Table7 below.

22 ENVIRONMENTAL MANAGEMENT PLAN V A

Table 7: Environmental Monitoring Plan Environmental Project Parameters Location(ch.) Frequency Standards Approximate Implementation Supervision component Stage cost(Rs.)

Air Construction SPM/RPM/NO,/CO Constructionsite near Oncein 3- Air qualitystandard 2x4000x3x3 Contractor NHAI stage Sherghatiand monthsfor 3 byCPCB =Rs.72000 throughapproved Chauparan years monitoring agency Operation SPM/RPM/NO,jCO/HC/Pb/Madanpur (186), 3 timesin a Air qualitystandard 3x4000x3 Contractor PIU,NHAI/SC stage S02 Sherghati(211), Dobhi yearfor one by CPCB =Rs.36000 throughapproved (222) year monitoring agency WaterQuality Construction All theparameters for Morharriver (210) Pond 3 timesa year Waterquality 4x1000x3x3 NHAI NHAI stage inlandsurface water at Madanpur(186); for 3 years standardby CPCB =Rs.36000 qualitystandard for Class- LilajanCanal (221) D will betested Operation All the parametersfor Morharriver; Lilajan Threetimes a Waterquality 2x1000x3 Contractor PIU,NHAI/SC stage inlandsurface water river yearfor 3 years standardby CPCB =Rs.6000 throughapproved qualitystandard for Class- monitoringagency D will betested Noiselevels Construction Noiselevel Gazett Constructionsites in 3 timesa year Noiselevel standard 5x2000x3x3 NHAI NHAI stage Notification643 dt. criticallocations for threeyears by CPCB =Rs.90000 26/12/89of MoeF Operation Noiselevel Gazett Madanpur(186), Twicein ayear Noiselevel standard 5x2000x3 Contractor PIU,NHAI/SC stage Notification643 dt. Chandisthan,Sherghati for oneyear by CPCB =Rs 30000 throughapproved 26/12/89of MoeF (111),Dobhi (222), monitoringagency Gopalpur(213), Barachatti(234) Flora Operation Maintainthe species at Entirestretch Forthree years Rs.90000 NHAI NHAI stage 75%survival rate afterPlantation 3 yearsonce in NHAI NHAI Soil Soil ~~~stageOperation MonitoringofP,C,of Pb, Cr, Cd Cnetd~wintersCongestedlocations a year during Rs. 2000

Total Monitoring Costs Rs. 362000

23 G. ENVIRONMENTALMANAGEMENT - BUDGET

The environmentalbudget for the variousenvironmental management measures proposed in the EMP are detailedin Table 8 below.

Table 8: EnvironmentalBudget - PackageV-A

Component Item Unit | uantty Rate Amount I I . # ...... (million Rs) l l J I CONSTRUCTIONSTAGE Flora * Cleanngof Roadsideplantation km 60.000 Rs.2000/- 0.12

* Compensatoryafforestabon (Minimum no. 3566 Rs. 675 / no 2.407 of 2 trees planted for every tree cut) * Landscaping/Plantationin the median no. 60.0 Rs.12,0001 0.72

* Plantationof additonal Trees if land No. 10000 Rs. 6751 no 6.75 availableII Slope . Turfing of embankmentwith grasses Coveredin engineeringcosts 0.00 /Embankment and herbs protection Borrowareas . Redevelopmentof borrowareas by tree Coveredin engineeringcosts 0.00 plantabonand fisheries Water * Relocationof hand pumps No 66 Rs.20,000/- 1.32

Noise * Provisionof noise barrers/Walls m 300 Rs.1000/- 0.30

Culturalproperties * Relocationof culturalproperties Coveredin RAP 0.00

* Protectve measuresfor cultural Coveredin RAP 0.00 propertes _ Environmental * Ambient air qualitymanagement Cost as mentoned in monitorngplan for performance 0.072 issues at indicator constructionsites * Noise level management 0.09

* Water quality management 0.036

* SewageDisposal Coveredin ContractDocument 0.00

* Waste disposalat servicecentres Coveredin ContractDocument 0.00

* Accident risks in constructionactivity Coveredin ContractDocument 0.00

* Healthissues Coveredin ContractDocument insuranceclauses 0.00

Environmental * Enhancementof ponds no 1 Rs.1,00,000/ 0.10 Enhancements l . Enhancementof culturalproperties no 3 Rs.70,0001 0.21

* Provisionof pond protectionwork no 4 Rs.70,000/ 0.28

* Pilgnmagepathways km. 0 Rs.1,48,000/- 0.00

OPERATIONSTAGE Monitoringof * Air quality 0.036 performance . Cost/yearas mentionedin the Monitonngplan for 0.03 PerformanceIndicators * Water quality 0.006

* Vegetation 0.09

* Soil 0.002

TRAINING

* Mobilisationfor Polluton monitorng Lumpsum - | 0.10

Training * Environmentaltraining Lump sum Coveredin CentralisedTraining Budget

SUBTOTAL 12.669

CONTINGENCIESQ 5 % on total EnviromentalCosts 0.633

GRANDTOTAL 13.302

24 Appendix1: RecommendedSoil BorrowAreas

Si. No. Km. Place : Distancefrom NH-2 SI. No. Km. Place ~~~~~~~~~~(inin.)

1 181 Kusaha lOOm Z 185 Patiyn lOOOm 186 Madanpur lOOOm 187 Valuvan 500m 5______197 BEindawan 2000m 6______198 Shawkala 500m 202 Muraniya 500m 205 Hamjapur 500m 212 Uddan Bigha 1000m 10 213 Gopalpur 200m 11 214 Gopalpur 200m 12 214 Gopalpur 200m 13 221 Dobhi 1000m 14 223 Amarua 100Gm 15 224 Surajmandal 100m 16 224 Surajmandal 10Gm 17 228 Bachdeya SOOm 18 236 Kahudag 100m 19 237 Nayagardan 2000m 20 237 Kanudag loom 21 238 Kanudag 100Gm

Appendix2: RecommendedQuarry Areas

Si. No. Km. Place 1 124-50 2 210-17 3 222-32 Gaya 4 222-50 Bela 5 222-65 BarwarPahar 6 283-27 Ambadah 7 283-33 Pumadi 8 283-36 9 283-49 10 362-3

25 Appendix3: Water Sourceswill beimpacted

Si. No. Water Sources 1 Pond at km 186.900(S) 2 Pond at km 180.825 (N) 3 Pond at km 219.500 (S) 4 Pond at km 205.650 (N) 5 Jhari Nadi at km 182.642 6 Stream at 182.882 7 Badi river at km 193.128 8 Brindavanriver at km 197.865 7 Morhar river at km 210.328 8 Buddhariver at km 211.647 9 Streamat km 217.933 10 Streamat km 222.750 11 Ulajan nver at km 223.764 12 Gulshakririver at km 229.108 13 Gokhlenver at km 234.300

Appendix4: ReligiousStructures likely to be impacted

S. No. Km. Type Distance from Carriageway 1 207.850 Mosque 7 m away from the pavement 2 212.550 Temple 18 m away from the pavementedge 3 228.200 Mosque B m from the pavement 4 235.940 Temple 3 m from the proposedroad 180-240 Shrine 12 nos at different locations

Appendix5: ReligiousStructures to be relocated

S. No. Km. Type Distance Side | 1 | 212.550 Temple 18m from Pavement North

Appendix6: Pondsto be Protected

S. No. Km. Side 1 186.900 South 2 180.825 North 3 219.5 South

Appendix7: Pondsto be enhanced

S. No. Km. Side 1 205.650 North