Tradebe Bellshill Clinical Treatment – Draft Permit No: PPC/A/1180708

Permit No: PPC/A/1180708

CONTENTS

INTERPRETATION OF TERMS …………………………………………………………..3

SCHEDULES 1 THE PERMITTED INSTALLATION ...... 6 1.1 Description of Permitted Installation ...... 6 1.2 Site Plan ...... 8 1.3 Location Plan ...... 9 1.4 Site Layout Plan ...... 10 2 GENERAL MANAGEMENT AND ADMINISTRATION CONDITIONS ...... 11 2.1 Administration ...... 11 2.2 Technical Competence and Staffing ...... 11 2.3 Management systems ...... 11 2.4 Financial provision ...... 12 2.5 Records ...... 12 2.6 Reporting ...... 12 2.7 Waste Data Reporting ...... 14 2.8 Incidents ...... 14 3 GENERAL RESOURCE REVIEW CONDITIONS ...... 16 3.1 Resource Utilisation ...... 16 3.2 Waste Generated on the Permitted Installation ...... 17 4 GENERAL ENVIRONMENTAL PROTECTION CONDITIONS ...... 18 4.1 Protection of Surface Water ...... 18 4.2 Protection of Soil and Groundwater ...... 18 4.3 Noise ...... 20 4.4 Odour Conditions ...... 21 4.5 Vermin, and Dust ...... 21 5 GENERAL INFRASTRUCTURE REQUIREMENTS ...... 22 5.1 Permitted Installation Infrastructure ...... 22 5.2 Sampling and Monitoring Facilities ...... 22 5.3 Plant Machinery, Equipment and Instrumentation ...... 22 5.4 Environmentally Critical Items ...... 22 6 COMMISSIONING CYCLE CONDITIONS ...... 25 6.1 Commissioning of Permitted Installation ...... 25 6.2 Re-commissioning of the Heat Treatment Process ...... 26 6.3 De-commissioning of Permitted Installation ...... 26 7 GENERAL CONDITIONS ...... 28 7.1 Start-up and Shutdown ...... 28 8 WASTE TYPES, PRE-ACCEPTANCE, ACCEPTANCE AND STORAGE OF WASTE AT THE PERMITTED INSTALLATION ...... 29 8.1 Permitted Waste Types ...... 29 8.2 Waste Pre-Acceptance ...... 32 8.3 Waste Acceptance ...... 32 8.4 Non-Conforming ...... 33 8.5 Waste Storage ...... 33 8.6 Cleaning ...... 35

Page 1 of 47

Permit No: PPC/A/1180708

8.7 Contingency Plan ...... 36 9 TRACKING OF WASTE THROUGH THE PERMITTED INSTALLATION ...... 37 9.1 Electronic Tracking System ...... 37 10 OPERATIONS ON THE PERMITTED INSTALLATION ...... 38 10.1 General ...... 38 10.2 Shredding Operations ...... 38 10.3 Heat Treatment Process ...... 38 10.4 Routine Efficacy Monitoring of the Heat Treatment Process ...... 39 10.5 Drying System ...... 40 10.6 HEPA Filters ...... 40 10.7 Carbon Filters ...... 40 11 EMISSIONS MONITORING ...... 42 11.1 Microbial Emissions Monitoring ...... 42 11.2 Emissions to Air ...... 42

Page 2 of 47

Permit No: PPC/A/1180708

INTERPRETATION OF TERMS

For the purposes of this permit, and unless the context requires otherwise, the following definitions must apply:

“Authorised Person” means a person who is authorised in writing under section 108 of the Environment Act 1995 to carry out duties on behalf of SEPA;

‘Challenge load’ means a healthcare/clinical waste load that has been constructed by composition (i.e. organic content, density, moisture/liquid content, or other physical or chemical composition) or amount to provide an appropriate challenge to the treatment process and microbial inactivating agent.

“Commissioning” means the start-up of the Permitted Installation, or part thereof, for the first time following construction, or after any significant modification, change or failures of routine efficacy monitoring. It includes: the planning and management of the commissioning of the Permitted Installation or part thereof; functional testing of equipment; introducing process materials to the plant; resolution of technical and procedural problems; confirmation that all aspects of the plant operate as designed or planned; and confirmation the plant operates within the Conditions of this Permit;

“emission” has the same meaning as in the Regulations;

“EPR 5.07” means the How to Comply with your Environmental Permit Additional guidance for Clinical waste (EPR 5.07) (Version 1.1 January 2011) Published by: Environment Agency, Rio House, Bristol BS32 4UD;

“European Waste Catalogue” (EWC) means a list of wastes pursuant to Article 1(a) of Directive 75/442/EEC on waste and Article 1(4) of Directive 91/689/EEC on contained in Council Decision 2000/532/EC (O.J. L 226, 6.9.2000p.3) as amended from time to time;

“Hazardous substance” means substances or mixtures as defined in Article 3 of Regulation (EC) No 1272/2008 of the European Parliament on classification, labelling and packaging of substances and mixtures.

“Hazardous Waste” has the same meaning as “special waste” as in Regulation 2 of The Special Waste Regulations 1996.

“HEPA filter” means High Efficiency Particulate Filter.

“impermeable surface” means a surface constructed of concrete or a similar impermeable material to a standard sufficient to prevent the transmission of liquids beyond the surface.

“heat treatment” means the treatment of waste by steam heated screw auger(s)

“incident” means any of the following situations:  A breach of any condition of this permit;  Where an accident occurs which has caused or may have the potential to cause pollution;  Where any malfunction, breakdown or failure of plant or techniques is detected which has caused or may have the potential to cause pollution;

 Where any substance, vibration, heat or noise specified in any Condition of this permit is detected in an emission from a source not authorised by a Condition of this permit and in a quantity which may cause pollution;

Page 3 of 47

Permit No: PPC/A/1180708

 Where an emission of any pollutant not authorised to be released under any condition of this permit is detected;  Where an emission of any substance, vibration, heat or noise is detected that has exceeded, or is likely to exceed, or has caused, or is likely to cause to be exceeded any limit on emissions specified in a condition of this permit.

“Location Plan” means the plan in schedule 1 of this permit;

“Permitted Activities” are defined in schedule 1 of this permit;

“Permitted Installation” is defined in schedule 1 of this permit and includes references to parts of the Permitted Installation;

“pollutant” and “pollution” have the same meaning as in the Regulations;

“recommissioning” means to repeat the “commissioning” process in accordance with Condition 6.1 and 6.2;

“sealed drainage system” means a drainage system with impermeable components which does not leak and which will ensure that- (a) no liquid will run off the surface otherwise than via the system; and (b) except where they may be lawfully discharged, all liquids entering the system are collected in a sealed sump.

“SEPA” means the Scottish Environment Protection Agency;

“STAATT” Means the State and Territorial Association on Alternative Treatment Technologies;

“STAATT Level III” means inactivation of vegetative bacteria, fungi and lipophilic/hydrophilic viruses, parasites, mycobacteria at a 6 log 10 reduction or greater; and inactivation of B. stearothermophilus spores or B. atrophaeus at 4 log10 reduction or greater.

“start-up” means the restarting of the Permitted Installation or part thereof following any shutdown for any reason, it includes partial shutdowns, for example to repair equipment necessary to ensure compliance with the Conditions in this Permit;

“shutdown” means the cessation of the heat treatment of waste and can include the cooling of the augers to ambient temperature, cooling of the washing facilities, or the cessation of fuel to the on site boilers;

”the site boundary” is defined in schedule 1 of this permit;

“Site Plan” means the plan(s) attached at schedule 1;

“the Regulations” means The Pollution Prevention and Control (Scotland) Regulations 2012 (As amended);

“water environment” has the same meaning as in the Water Environment and Water Services (Scotland) Act 2003 that is all surface water, groundwater and wetlands; and “surface water”, “groundwater” and “wetlands” must have the same meanings as in the Act.

“Waste” Has the same meaning as in Section 75 of the Environmental Protection Act 1990

Page 4 of 47

Permit No: PPC/A/1180708

“Waste Treatment Operations” means the operation of the shredders, steam heated screw augers and drier system(s).

Any reference to a numbered condition, group of conditions, schedule, Table, appendix, figure or paragraph is a reference to the condition, group of conditions, schedule, Table, appendix, figure or paragraph bearing that number in this licence;

Except where specified otherwise in this permit:

 “day” means any period of 24 consecutive hours,

 “week” means any period of 7 consecutive days,

 “month” means a calendar month,

 “quarter” means a calendar quarter

 “year” means any period of 12 consecutive months; and any derived words (e.g. “monthly”, “quarterly”) must be interpreted accordingly;

Except where specified otherwise in this permit, any reference to an enactment or statutory instrument includes a reference to it as amended (whether before or after the date of this permit) and to any other enactment, which may, after the date of this permit, directly or indirectly replace it, with or without amendment.

Page 5 of 47

Permit No: PPC/A/1180708

1 THE PERMITTED INSTALLATION

1.1 Description of Permitted Installation

The Permitted Installation to which this permit applies (“the Permitted Installation”) is:

1.1.1.1 The stationary technical unit specified in paragraph 1.1.5 (the stationary technical unit), where the activities specified in paragraph 1.1.4 are carried out (“the activities”), together with the directly associated activities specified in paragraph 1.1.6 (“the directly associated activities”).

1.1.1.2 The site of the Permitted Installation is delineated in red on the site plan (“the site boundary”).

The general location of the Permitted Installation is as shown on the location plan.

The general layout of the Permitted Installation is as shown on the site layout plan.

The activities carried out at the stationary technical unit are:

1.1.4.1 The disposal or recovery of hazardous waste (other than by or ) in plant with a capacity exceeding 10 tonnes per day for hazardous waste falling within Schedule 1, Part 1, Chapter 5, Section 5.3, Part A (b) (ii) of the Regulations namely the Heat Treatment of shredded hazardous, infectious waste in steam heated screw augers;

1.1.4.2 The recovery or a mix of recovery and disposal of non-hazardous waste at an installation with a capacity exceeding 75 tonnes per day falling within Schedule 1, Part 1, Chapter 5, Section 5.4, Part A (b) (ii) of the Regulations; namely the pre-treatment of non-hazardous waste for incineration using a drier system.

1.1.4.3 The temporary storage in an installation with a capacity of more than 50 tonnes of hazardous waste pending any of the activities described in any of Sections 5.1 to 5.3 of the Regulations falling within Schedule 1, Part 1, Chapter 5, Section 5.6, Part A (a) of the Regulations.

1.1.4.4 The burning of Fuel in a Medium Combustion Plant with a Rated Thermal Input of 1 – 20MW, falling within Schedule 1, Part 1, Chapter 1, Section 1.1, Part B (d) of the Regulations, the principal purpose of which is to produce steam to heat the screw augers used in the Heat Treatment process.

The stationary technical unit comprises the following units:

1.1.5.1 Area(s) for storage of hazardous waste pending treatment or transfer off site;

1.1.5.2 Two shredder units capable of fully enclosing waste during operation, operating under negative pressure, used to render waste unrecognisable, each serving a single steam heated screw auger;

Page 6 of 47

Permit No: PPC/A/1180708

1.1.5.3 Two 19m long steam heated screw augers which use a combination of direct steam injection into the waste, and into the auger shaft itself, capable of disinfecting hazardous, infectious waste, to STAATT Level III, each with 48 tonnes per day capacity, and serving one of two separate waste treatment lines;

1.1.5.4 One continuous flow drier system used to reduce the moisture content of disinfected, heat treated waste, serving one of two separate waste treatment lines and discharging exhaust air to atmosphere;

1.1.5.5 Outlet screw(s) serving the drier(s) described in paragraph 1.1.5.4 used to convey waste from the drier(s) to the waste compactors;

1.1.5.6 Waste compactors used to reduce the volume of waste prior to transfer off site;

1.1.5.7 Two natural gas boilers providing steam to the steam heated screw augers described in paragraph 1.1.5.3, each with a net rated thermal input of between 1 and 5 MWth;

1.1.5.8 Air extraction fans serving the shredder units described in paragraph 1.1.5.2 used to maintain the shredders under negative pressure and discharge extracted air to atmosphere via HEPA filters and carbon filters; and

1.1.5.9 Air extraction fans serving the thermal screw augers described in paragraph 1.1.5.3 used to maintain the augers under negative pressure and discharge exhaust air to atmosphere via a system comprising a condenser, cooler, coalescing filter and carbon filter, the condensate will be discharged to sewer.

The following directly associated activities are carried out on the site:

1.1.6.1 The weighing of waste on platform weigh scales;

1.1.6.2 The handling and storage of non-hazardous wastes pending treatment or transfer off site;

1.1.6.3 The washing of empty healthcare, clinical or hygiene waste bins, containers and carts;

1.1.6.4 The washing of delivery vehicles;

1.1.6.5 Delivery and dispatch of raw materials, wastes and residues to and from the site;

1.1.6.6 The consented discharge of effluent from the Permitted Activities to the public sewerage system; and

1.1.6.7 The operation of a back-up diesel generator.

1.1.6.8 For the purposes of this permit, the activities and directly associated activities must be known together as “the permitted activities”.

Page 7 of 47

Permit No: PPC/A/1180708

1.2 Site Plan

Page 8 of 47

Permit No: PPC/A/1180708

1.3 Location Plan

Page 9 of 47

Permit No: PPC/A/1180708

1.4 Site Layout Plan

Page 10 of 47

Permit No: PPC/A/1180708

2 GENERAL MANAGEMENT AND ADMINISTRATION CONDITIONS

2.1 Administration

An appropriate person (and deputy) must be appointed as the primary point of contact with SEPA. SEPA must be notified in writing of the name of the appointed person (and deputy) within 4 weeks of the date of the Permit.

In the event of a different person being appointed to act as primary point of contact (or deputy) SEPA must be notified in writing of the name of the appointed person or deputy without delay.

A copy of this Permit must be kept at the Permitted Installation and must be made readily accessible for examination by all staff.

Any systems or procedures used by the operator to demonstrate compliance with a condition of this permit must be recorded.

2.2 Technical Competence and Staffing

All staff or persons engaged in carrying on the permitted activities must be provided with adequate professional and technical development; training and written operating instructions to enable them to carry out their duties, and to ensure they are fully conversant with those aspects of the permit conditions which are relevant to those duties.

The operator must maintain a record of the skills and training requirements for each job and must keep records of all relevant training.

The Permitted Installation must be managed and supervised by a designated technically competent person to ensure that the conditions of the permit are complied with.

The operator must inform SEPA in writing of all persons, and their qualifications, engaged in the operation or management of the Permitted Installation who are designated as technically competent.

Where the operator or another relevant person is convicted of an offence prescribed under section 74(6) of the Environmental Protection Act (EPA) 1990 for the purposes of section 74(3)(a) of EPA 1990 the operator must notify SEPA within seven days of the conviction, whether or not the conviction is subsequently appealed.

2.3 Management systems

The operator must complete a review of the Permitted Installation’s operational, management and maintenance systems by six months from the date of permit issue. This review must identify, scope, define, implement and thereafter maintain such additional operational, management and maintenance systems as are necessary to ensure compliance with the conditions of this permit. The systems must be subject to further documented review at intervals of not more than two years. Any systems put in place as a result of this condition must be recorded.

Any amended or additional systems required by Condition 2.3.1 must include specification of the organisational structure, and the personnel roles, numbers, qualifications, training,

Page 11 of 47

Permit No: PPC/A/1180708

experience and certification, of persons required to operate, and supervise the operation of, the Permitted Installation, or part thereof, in accordance with this permit.

2.4 Financial provision

The operator must ensure that the financial provision as required by Regulation 18(4)(b) of the regulations is maintained until the permit is surrendered.

No later than three months prior to a proposed change to any material particular of the financial provision set in place under Condition 2.4.1, the operator must notify SEPA of the details of that proposed change.

For the purposes of Condition 2.4.2, material particulars of the financial provision used to satisfy Condition 2.4.1 must include but not be limited to:

a) the provider of the financial instrument;

b) the type and form of financial provision;

c) a change in any Condition in relation to the financial provision including its determined value.

The operator must not proceed with any proposed change to the financial provision until they have received agreement in writing from SEPA who will supply this within 4 weeks.

2.5 Records

All records made in compliance with this permit must be kept in a systematic manner.

Unless otherwise specified in a condition of this permit, every record made in compliance with a condition of this permit must be preserved for not less than 6 years from the date of its being made. Every such record must be kept at the Permitted Installation for not less than one year from the date of its being made and thereafter preserved at a location, previously notified to SEPA in writing, if that location is not the Permitted Installation.

All records must be legible, and any amendment made to any record made in compliance with a condition of this permit must be made in such a way as to leave the original entry clear and legible. The reason for each amendment must be explained in the said record.

Without prejudice to Condition 2.5.2 all operators’ records relevant to the operation or maintenance of the Permitted Installation must be kept at the Permitted Installation for not less than one year from the end of the period to which they apply.

2.6 Reporting

Where any condition of this permit requires information to be reported, a report must be forwarded to SEPA by the date(s) or within the period or at the frequency specified in Table 1 and, where appropriate, the first report must be due on the date specified in that Table. All such reports must include the permit number and the name of the operator.

The reports referred to in Condition 2.6.1 must be submitted to SEPA in an electronic format to the email address specified by SEPA.

Where any condition of this permit requires a report to be submitted, that report must contain sufficient and accurate information to allow an assessment of the compliance with the

Page 12 of 47

Permit No: PPC/A/1180708 condition requiring the report and the report must be made in accordance with any guidance published by SEPA.

Where the Permitted Installation has not operated for the duration of any reporting period specified in Table 1, the operator must provide written notification to SEPA. This must confirm that no reports have been made in terms of condition 2.6.1 because the Permitted Installation has not operated during the said period. Notifications must be submitted within one month of the end of the reporting period concerned.

All notifications required by any condition of this permit must be made to SEPA in the manner specified in that condition to the address specified in the explanatory notes attached to this permit by the date(s) or within the period or at the frequency specified in Table 1 and, where appropriate, the first notification must be due on the date specified in that Table. All such notifications must include the permit number and name of the operator.

Table 1: Reporting and Notification Requirements

Summary of Information Date/Within period/ Frequency to Date First to be Reported or Condition be Reported Report Due Notified Financial Provision 2.4.2 3 months prior to proposed change. N/A Notification of change to Financial Provision. Records Management 2.5.2 Prior to archiving records. N/A Off-site location of archived records. Waste Data Returns 2.7.1 Within 28 days from the last day of As required. March, June, September and December. Incident Notification 2.8.4 Without delay. As required.

Incident Confirmation 2.8.5 Next day after identification of As required. incident. Incident Investigation 2.8.6 Within 14 days of the date of the As required. Incident unless otherwise agreed in writing with SEPA Resource Review 3.1.2 At least once every 4 years 4 years from date of permit Waste Review 3.2.1 Every 2 years 2 years from date of permit. Drainage System Report 4.2.1 Prior to carrying out any Permitted Prior to carrying Waste Activities out any Permitted Waste Activities Review of soil and 4.2.5 Every 2 years. 2 years from date groundwater protection of permit. measures. Bund, Tank and Container 4.2.8 Annually 1 year from date Condition of permit. Soil Monitoring Report 4.2.10 Every 10 years 10 years from date of permit Soil Monitoring Plan 4.2.11 3 months from date of permit 3 months from date of permit Soil Monitoring Plan – 4.2.13 5 months after monitoring – only if As required. revisions changes are proposed. Noise Review 4.3.1 Every 2 years 2 years from date of permit. Odour Management Plan 4.4.5 At least 14 days prior to One off commencing the Waste Treatment submission Operations

Page 13 of 47

Permit No: PPC/A/1180708

Odour modelling 4.4.8 6 months after commencement of One off validation report the Waste Treatment Operations submission Commissioning Plan 6.1.1 Prior to commencing Waste As required. Treatment Operations Commissioning Report 6.1.4 Upon implementation and As required. completion of the Commissioning Plan Recommissioning Plan 6.2.2 At least 2 months before As required. recommissioning. Recommissioning Report 6.2.3 Upon implementation and As required. completion of the Recommissioning Plan. Notification to cease 6.3.2 1 month prior to any proposed As required. Operation cessation lasting more than 12 months. Notification of Waste 8.4.1 Without undue delay. As required. Refusal Routine Efficacy 10.4.2 Within 14 days of the monitoring As required. Monitoring taking place.

Weekly during the first 6 months of operation, monthly thereafter. Microbial Emissions 11.1.1 Annually 30 December Monitoring Report 2019 Microbial Emissions 11.1.2 28 days before monitoring takes As required. Monitoring Protocol place. Emissions to Air 11.2.3 As required by Table 11 Monitoring Report

2.7 Waste Data Reporting

The operator must complete a quarterly waste data report using the licensed/permitted site returns form located on SEPA’s website at: www.sepa.org.uk. This form must be completed and submitted electronically to the email address specified by SEPA, within 28 days of the last day of March, June, September and December each year.

2.8 Incidents

In the event of an incident all necessary measures must immediately be taken:

To prevent, or where that is not practicable to reduce, emissions from the Permitted Installation;

to limit the environmental consequences as a result of that incident; and

To prevent further possible incidents.

Without prejudice to the requirements of Condition 2.8.1, in the event of a breach of any condition of this permit the operator must immediately take the measures necessary to ensure that compliance is restored in the shortest possible time.

Notwithstanding the requirements of Condition 2.8.1 and 2.8.2 where a breach of any condition of this permit or an incident poses an immediate danger to human health, or threatens to cause an immediate significant adverse effect on the environment, the operator

Page 14 of 47

Permit No: PPC/A/1180708 must suspend operation of the Permitted Installation or relevant part thereof until such time as it can be operated in compliance with this permit.

In the event of an incident and/or a breach of any condition of this permit, the operator must notify SEPA by telephone without undue delay to 0800 80 70 60. A notification that relates to an incident must include as far as practicable the information specified in Condition 2.8.5.

The operator must confirm any incident to SEPA in writing by the next working day after identification of the incident. This confirmation must include:

a) the time and duration of the incident,

b) the receiving environmental medium or media where there has been any emission as a result of the incident,

c) an initial estimate of the quantity and composition of any emission,

d) the measures taken to prevent or minimise any emission or further emission and a preliminary assessment of the cause of the incident.

Any incident notified to SEPA must be investigated by the operator, and a report of the investigation sent to SEPA within 14 days of the date of the incident unless otherwise agreed in writing with SEPA. The report must detail, as a minimum:

a) the circumstances of the incident,

b) an assessment of any harm to the environment

c) the steps taken by the operator to bring the incident to an end

d) proposals for remediation, where necessary, and

e) proposals for preventing a repetition of the incident

Within 6 months of the date of permit issue the operator must prepare, implement and maintain an Incident Prevention and Mitigation plan.

The Incident Prevention and Mitigation Plan required under Condition 2.8.7 must include details of what action, including additional sampling that the operator must take in the event of the following:

a) Failure to meet stated temperature in the thermal screw auger(s) as indicated by the temperature probe, or time as indicated by the auger rotation speed;

b) Failure of a spore strip(s) and/or thermal indicator strip during routine efficacy monitoring.

At least every 2 years, the operator must review the incident prevention and mitigation plan required under Condition 2.8.7. Each review of the said incident prevention and mitigation plan must be recorded and where the operator makes any revisions to the said plan, said revisions must be recorded.

Page 15 of 47

Permit No: PPC/A/1180708

3 GENERAL RESOURCE REVIEW CONDITIONS

3.1 Resource Utilisation

At least every four years, the Operator must carry out a systematic assessment to determine:

a) How and where raw materials (including water and fuel) and energy are used within the Permitted Installation;

b) The quantities of raw materials (including water and fuel) and energy used within the Permitted Installation;

c) How and where material losses and wastes are generated within the Permitted Installation;

d) The quantities of material losses and wastes are generated within the Permitted Installation;

e) How and where raw materials (including water) and energy can be utilised more efficiently within the Permitted Installation to reduce resource use and minimise material losses and waste; and

f) Which of the resource efficiency measures identified in Condition 3.1.1(e) will be implemented at the Permitted Installation during the 4 year assessment cycle.

The assessment required by Condition 3.1.1 must be recorded using the SEPA “systematic assessment of resource use and efficiency template” (IED-T-04), or an equivalent format as agreed by SEPA, and reported to SEPA as specified in Table 1.

The operator must implement the resource efficiency measures identified in the systematic assessment within the timescales specified in the systematic assessment.

The information required in conditions 3.1.1(b) and 3.1.1(d) must be recorded annually.

For the purposes of condition 3.1.1(b) “raw materials”, “energy” and “fuel” must, as a minimum, include the materials listed in Table 2.

Table 2: Resource Utilisation Data Recording

Raw Materials, Energy or Fuel Unit of Measurement Fuel (Gas, oil, diesel, etc) m3, litres Activated carbon filters Kg Water m3 Boiler water treatment chemicals Litres/kg Disinfectant/detergents Litres/kg Refrigerants Litres Plastic wrap Kg

Page 16 of 47

Permit No: PPC/A/1180708

3.2 Waste Generated on the Permitted Installation

At least every 2 years, the Operator must carry out a systematic assessment and review of the management of all wastes generated by the Permitted Activities. The purpose of the assessment must be to identify methods of avoiding or reducing the impact on the environment of the disposal of waste. Each assessment must be recorded and reported.

Page 17 of 47

Permit No: PPC/A/1180708

4 GENERAL ENVIRONMENTAL PROTECTION CONDITIONS

4.1 Protection of Surface Water

Unless specified elsewhere in this permit there must be no emission of any pollutants to surface water from the Permitted Installation.

4.2 Protection of Soil and Groundwater

Prior to carrying out any Permitted Activities, the Operator must submit a report to SEPA demonstrating that all drainage systems within the Permitted Installation are capable of ensuring compliance with condition 4.2.2.

Unless specified elsewhere in this permit there must be no emission of any pollutants to soil or groundwater from the Permitted Installation.

The operator must maintain a record of any incident that has, or might have, impacted on the condition of any soil or groundwater under the Permitted Installation, either as a result of that incident or as a result of an accumulation of incidents, together with a record of any further investigation or remediation work carried out.

Notwithstanding the requirements of Condition 2.5.2, the record required by Condition 4.2.3 must be preserved until this permit is surrendered.

At least every 2 years, the operator must carry out a systematic assessment of all measures used to prevent emissions from the Permitted Installation to soil and groundwater, this should include a CCTV survey of the drainage systems including the process area. A written report of each assessment must be recorded and reported to SEPA. The report must include details of and timescales for any additional measures that are required to prevent emissions to soil and groundwater.

Unless otherwise specified in any other condition, all containers and tanks used to store liquids must be located in a bund. The minimum capacity of any bund must be either 110% of the capacity of the largest container within the bund, or 25% of the total capacity of all the containers within the bund, which-ever is the greater. In the event of any containers being connected to one another, they must be treated as one container.

Unless otherwise specified in any other condition the bunded area(s), tanks and containers referred to in condition 4.2.6 must conform to the following standards:

a) the walls and base of the bund must be impermeable and the base of the bunded area must drain to a sump b) when not in use all taps, valves, pipes and every part of each container must be located within the area served by the bund c) vent pipes must be directed downwards into the bund d) no part of the bund must be within 10 metres of a watercourse e) All containers with a design capacity above 1250 litres must be fitted with a device for continuously monitoring the level of the contents. f) The accumulation of rainwater, spillages or leaks must be managed to ensure that at least 95% of the capacity of the bund is free of liquid.

Page 18 of 47

Permit No: PPC/A/1180708

At least annually, the Operator must assess the condition of the site bunding, tanks and containers sufficient against the standards specified in condition 4.2.7 and must prepare a report detailing the results of the assessment.

The report required by condition 4.2.8 must be submitted to SEPA within two months of the assessment being completed. The report must detail any remedial work required to ensure that the bunding, tanks and containers meet the standards specified in condition 4.2.7.

The operator must monitor the soil at the site for the relevant hazardous substances specified in Table 3 at the frequency specified in Table 3, the purpose of which must be to identify soil contamination associated with the activities specified in Table 3 by those relevant hazardous substances. Each assessment must be recorded and reported to SEPA within one month of completion. The first assessment must be completed within 10 years of date of permit. The assessment must include interpretation of the results with reference to previous monitoring undertaken (including the site and where applicable baseline reports) and operations at the Permitted Installation and details of corrective actions that are required to protect groundwater and remedy any contamination that has occurred as a result of permitted activities.

Table 3: Soil monitoring requirements

Relevant Soil Activity to be hazardous Frequency monitored substance TPH CWG speciated Soil samples will be Transformer 10 years aliphatic and required to be tested for aromatic fraction the Relevant Hazardous BTEX (Benzene, Substances associated 10 years Toluene, with the transformer in Ethylbenzene and the area relevant to the Xylenes) transformer as per Site Condition Report Polycyclic Aromatic baseline 10 years Hydrocarbons (speciated PAH-16) TPH CWG speciated Soil samples will be Diesel generator 10 years aliphatic and required to be tested for aromatic fraction the Relevant Hazardous BTEX (Benzene, Substances associated 10 years Toluene, with the diesel Ethylbenzene and generator in the area Xylenes) relevant to the diesel generator as per Site Polycyclic Aromatic Condition Report 10 years Hydrocarbons baseline (speciated PAH-16)

The operator must submit a detailed soil monitoring plan, for the monitoring required by condition 4.2.10 to SEPA at least three months in advance of carrying out the monitoring,

Page 19 of 47

Permit No: PPC/A/1180708

which must include the locations at which monitoring must be carried out and the methodology which must be used.

The operator must carry out the monitoring required by Condition 4.2.10 in accordance with the soil monitoring plan required by Condition 4.2.11.

The operator must review the plan required by Condition 4.2.11 no later than 5 months after each monitoring event. The purpose of the review must be to determine whether any changes to monitoring locations, frequency or parameters are required and where changes are proposed, submit a revised plan to SEPA.

Notwithstanding the requirements of Condition 2.5.2 all plans, monitoring and assessments reports undertaken in accordance with Conditions 4.2.5, 4.2.8, 4.2.10 and 4.2.11 must be preserved until the permit is surrendered.

Unless specified elsewhere in this Permit, there must be no emission of any pollutants to surface water from the Permitted Installation.

Drainage within the Permitted Installation must be provided and maintained to ensure that:

a) Rainfall run-off does not drain into the waste storage areas;

b) Contaminated rainwater, spillages or firefighting water from containing and extinguishing fires can be contained prior to any discharge to the water environment or sewer; and

All working surfaces, including designated vehicle and container washing areas, must be impermeable to water, constructed of concrete or similar material and laid to falls that direct surface run-off to a sealed drainage system and maintained in a condition such that their use is not compromised by debris, ruts, potholes or ponded surface water. The impermeable surface must be of such a design that any spillage on it or run-off from it is fully contained and cannot escape onto adjacent ground.

The operator must record and maintain up-to-date drainage plans of the Permitted Installation.

4.3 Noise

At least every 2 years, the operator must carry out a systematic assessment of noise emissions associated with the permitted activities, the purpose of which must be to identify

Page 20 of 47

Permit No: PPC/A/1180708

methods of reducing noise emissions. Each assessment must be recorded and reported to SEPA.

4.4 Odour Conditions

All emissions to air from the Permitted Installation must be free from offensive odour, as perceived by an authorised person, outside the site boundary.

Odour-masking agents or counteractants must not be used to meet the requirements of Condition 4.4.1.

The operator must prepare, implement and thereafter maintain an Odour Management Plan which includes all of the elements required by the published BAT conclusions for waste treatment.

The Odour Management Plan required by Condition 4.4.3 must also include details of how the performance of the odour abatement systems will be monitored and what indicators will be used to determine when the carbon media requires replacing.

At least 14 days prior to commencing the Waste Treatment Operations the operator must submit the Odour Management Plan required by condition 4.4.3.

Within 3 month of commencing the Waste Treatment Operations the operator must carry out odour monitoring at the inlet and outlet to all carbon filters, the outlet from the drier prior to mixing with air from other systems and the final emission points to air from these systems to determine odour concentrations. The purpose of this is to validate the surrogate data and assumptions made in the odour dispersion modelling assessment submitted to SEPA in June 2019 with reference number 443333-03(03).

Within 2 months of receiving the results of the monitoring required by Condition 4.4.6 the Operator must undertake a modelling exercise using this data to validate the odour dispersion modelling assessment submitted to SEPA in June 2019 with reference number 443333- 03(03).

No later than 6 months after commencing the waste treatment operations the operator must report the results of the modelling exercise required by Condition 4.4.7.

4.5 Vermin, Litter and Dust

All operations must be carried out to prevent and minimise the potential escape of litter or dust from the Permitted Installation. Any litter lying within the Permitted Installation must be removed on a daily basis.

All operations must be carried out so as to minimise the potential presence of insects, birds and vermin. The Permitted Installation must be inspected at least once per week for the presence of insects, birds or vermin, and a treatment programme must be undertaken without delay to deal with any identified infestation. The results of each inspection and details of any subsequent treatment must be recorded.

Page 21 of 47

Permit No: PPC/A/1180708

5 GENERAL INFRASTRUCTURE REQUIREMENTS

5.1 Permitted Installation Infrastructure

The Permitted Installation must be maintained in a secure condition to prevent unauthorised access.

A notice board of durable material and finish, must be displayed at the entrance to the Permitted Installation. The notice board must be legible from outwith the Permitted Installation boundary and contain the following information:

a) The Permitted Installation name, address and Permit number; b) The operator’s name; c) The Permitted Installation opening hours; d) The emergency contact telephone number for the operator; and e) The telephone number of the SEPA 24 hour pollution hotline number.

5.2 Sampling and Monitoring Facilities

Sampling measurement and monitoring facilities at the Permitted Installation must conform to the requirements of the relevant test methods specified in any condition of the permit or as otherwise agreed in writing by SEPA.

Unrestricted access to all sampling points required by any condition of this permit must be provided at all times.

5.3 Plant Machinery, Equipment and Instrumentation

All plant, machinery, equipment and instrumentation used at the Permitted Installation must be operated, maintained and inspected in accordance with the manufacturer’s instructions. Should the plant, machinery, equipment or instrumentation for any reason become unserviceable or inoperable, its replacement, repair or arrangements for its repair must be put in hand forthwith.

5.4 Environmentally Critical Items

Within 2 months of permit issue date, the operator must identify and designate as environmentally critical, any item of process plant or instrumentation that it relies on for the prevention, or limitation, of pollution from the Permitted Installation (an environmentally critical item), including, as a minimum, those items specified in Table 4.

Page 22 of 47

Permit No: PPC/A/1180708

Table 4: Environmentally Critical Items

Environmentally Critical Items Building integrity Doors All ductwork and fans for the transfer of process air Shredders HEPA Filters Differential pressure gauges Condensers Coalescing filters Carbon filters Boiler(s) Condensate collection tank, associated pipework and pumps Refrigerator units Monitoring devices connected to the process control system including the thermocouple Heat disinfection unit Bunding, tanks and containers Drainage system prior to discharge to sewer

Within 3 months of permit issue date, the operator must prepare and thereafter maintain a register of all environmentally critical items at the Permitted Installation designated in accordance with Condition 5.4.1. The said register must contain the following records in respect of each environmentally critical item:

a) A description of the said item and its mode of operation.

b) The performance standards expected of the said item.

c) The acceptable range, with justification, for each direct or indirect operating parameter that might materially affect the achievement of the performance standard referred to in Condition 5.4.2(b).

d) Details of all monitoring necessary to assess compliance with the performance standard and operating parameters referred to in Conditions 5.4.2(b) and 5.4.2(c) respectively, including details regarding the handling and storage of such data.

e) A description of the actions that should be taken in the event of any performance standard or acceptable operating parameter not being met, or the item not being operational, and if this is dependent upon any factor (such as the nature of activity), the circumstances in which a particular action would be instigated.

f) A description of all maintenance and/or calibration work that is necessary to secure the performance standard referred to in Condition 5.4.2(b).

g) A description of critical spare parts that will be held at the Permitted Installation for the said item, and the current stock level for each such spare part.

The operator must record the following in respect of each environmentally critical item:

a) Compliance assessment referred to in Condition 5.4.2(d).

b) The time and date of each occasion on which the performance standard and/or an acceptable operating parameter was not met, and the actions taken in response.

Page 23 of 47

Permit No: PPC/A/1180708

c) For each record made as requirement of Condition 5.4.3(b), the reasons why the performance standard and/or an acceptable operating parameter were not met.

d) All maintenance and/or calibration work carried out on the said item.

The operator must undertake and record an annual review of the maintenance records required by Condition 5.4.3(d) to identify equipment that has failed frequently and/or common failure modes. Within three months of each review, where such equipment or failure modes have been identified, an improvement programme must be developed, recorded and implemented to minimise recurrences of the identified failures and failure modes.

Page 24 of 47

Permit No: PPC/A/1180708

6 COMMISSIONING CYCLE CONDITIONS

6.1 Commissioning of Permitted Installation

Prior to any Waste Treatment Operations beginning at the Permitted Installation the Operator must prepare and report (to SEPA) a ‘commissioning plan’ which details how the Operator intends to commission all aspects of the Permitted Installation so as to demonstrate compliance with the conditions of this permit, including timescales for when each aspect of commissioning must be completed.

The Operator must demonstrate that all HEPA filters are fully functioning in situ prior to using any hazardous, infectious waste in the commissioning process.

Any hazardous, infectious waste used in the commissioning process must be considered untreated until the Commissioning Report is approved by SEPA.

Upon implementing and completing the commissioning plan the Operator must submit to SEPA a commissioning report which details the results of the commissioning activities as described in the commissioning plan, demonstrating full compliance with the conditions of this permit.

The Commissioning Report required by Condition 6.1.4 must include as a minimum the following details:

a) The results of all commissioning activity relevant to demonstrating compliance with the conditions of this permit;

b) A finalised process flow diagram showing the movement of waste through the Permitted Installation;

c) A finalised piping and instrumentation diagram showing the layout associated with the Permitted Installation;

d) Specifically, in relation to the commissioning of the Heat Treatment process the commissioning report must comply with Annex 1 of EPR 5.07, and as a minimum include the following details:

i. Confirmation of the treatment parameters being validated by the commissioning process (i.e. shredder particle size, auger temperature, auger rotating speed, waste exposure time);

ii. Details of the unit that the testing applies to;

iii. The date, start time and end time of all testing;

iv. Identification of who undertook each aspect of testing, their roles and relevant qualifications, and when the testing was undertaken;

v. Details of the spore type(s) used and why they were considered appropriate for the commissioning process (including details on the spore strips used, the manufacturers name, spore density, d-values, batch number and expiry date, etc.);

vi. Details of the number of spore strips used in each test (including control strips), the method of introduction into plant, the choice of spore strip carrier, the position

Page 25 of 47

Permit No: PPC/A/1180708

within the treatment process, the method of spore strip recovery, and the description of thermal indicator strips or multi point thermal loggers used;

vii. Details of the worst case challenge load;

viii. Evidence of the parametric controls at the time of testing (i.e. recording of auger temperature, auger rotating speed, time);

ix. Identification of the analytical laboratory used to analyse all test and control strips; its accreditation status; a description of the laboratories analytical methods; the date of sample receipt and analysis;

x. The quantitative results from all test strips used, including untreated control strips, and the results of thermal indicator strips (or multi point thermal loggers), including any failures;

xi. Description of how the results were used to calculate the treatment efficacy in terms of required log kill;

xii. A statement of confirmation that the results from the commissioning process demonstrate that the Heat Treatment process meets the STAATT Level lII criteria for the worst case “challenge load” under the treatment parameters defined under Condition 6.1.5.(d)(i).

xiii. A statement of confirmation that all process emissions associated with the Heat Treatment of waste, including emissions from the shredder units, are fully contained and comply with the requirements of the conditions of the permit.

Waste Treatment Operations must not commence, other than to undertake commissioning requirements, until SEPA provides written confirmation that the Commissioning Report required by Condition 6.1.4 is approved.

Prior to the Waste Treatment Operations commencing at the Permitted Installation the Operator must notify SEPA in writing of the intended start date.

6.2 Re-commissioning of the Heat Treatment Process

The operator must re-commissioning the heat treatment process, every 48 months starting from completion date of the commissioning process, in accordance with a Recommissioning Plan.

The Recommissioning Plan required by Condition 6.2.1 must be submitted to SEPA two months prior to the start of the recommissioning process.

Upon implementing and completing the recommissioning plan the Operator must submit to SEPA a recommissioning report which details the results of the recommissioning activities as described in the recommissioning plan.

The recommissioning report required by Condition 6.2.3 must comply with Annex 1 of EPR 5.07, and as a minimum must include the details stated in Condition 6.1.5.(d).

6.3 De-commissioning of Permitted Installation

Within 12 months of permit issue date the operator must prepare and maintain a plan (“the de-commissioning plan”) for the decommissioning of the Permitted Installation.

Page 26 of 47

Permit No: PPC/A/1180708

The de-commissioning plan must set out the steps to be taken by the operator after final cessation of the permitted activities.

The operator must notify SEPA in writing of its intention to cease the permitted activities, or any part thereof, for any period exceeding 12 months, no later than 1 month prior to the proposed date of cessation.

The operator must implement the de-commissioning plan on final cessation of the permitted activities or any part thereof.

The operator must review, record and, where necessary, update the de-commissioning plan at least every 4 years.

Page 27 of 47

Permit No: PPC/A/1180708

7 GENERAL CONDITIONS

7.1 Start-up and Shutdown

The Operator must prepare implement and maintain a plan (“the Start-up and Shutdown Plan”) setting out the necessary steps to be taken by the Operator prior to start-up or shutdown of operations of the Permitted Installation, or part thereof, to ensure that all appropriate preventative measures are taken against pollution and that no significant pollution is caused.

At least every 2 years the Operator must review the Start-up and Shutdown Plan required under Condition 7.1.1. Each review of the plan must be recorded and where the Operator makes any revisions to the plan, these revisions must be recorded.

Page 28 of 47

Permit No: PPC/A/1180708

8 WASTE TYPES, PRE-ACCEPTANCE, ACCEPTANCE AND STORAGE OF WASTE AT THE PERMITTED INSTALLATION

8.1 Permitted Waste Types

Only waste types defined by the six figure EWC codes listed in Column I, and described by Colum II and Column III of Table 5, must be accepted at the Permitted Installation.

Page 29 of 47

Permit No: PPC/A/1180708

Table 5: Waste Types which can be accepted and treated at the Permitted Installation

Column I Column II Column III Column IV Column V EWC Description Entry Can the Can it be treated by Waste Type** waste be the Heat Treatment Code shredded? process on site? 02 WASTES FROM AGRICULTURE, HORTICULTURE, AQUACULTURE, FIRESTRY, HUNTING AND FISHING, FOOD PREPARATION AND PROCESSING 02 01 Waste from agriculture, horticulture, aquaculture, forestry, hunting and fishing 02 01 02 animal-tissue waste AN No No 02 01 06 animal faeces, urine and manure (including spoiled straw), effluent, collected separately and treated off-site AN No No 02 02 Wastes from the preparation and processing of meat, fish and other foods of animal origin 02 02 02 animal-tissue waste AN No No 02 02 03 materials unsuiTable for consumption or processing AN No No 15 WASTE PACKAGING, ABSORBENTS, WIPING CLOTHS, FILTER MATERIALS AND PROTECTIVE CLOTHING NOT OTHERWISE SPECIFIED 15 01 Packaging (including separately collected municipal ) 15 01 01 paper and cardboard packaging AN No No 15 01 10* packaging containing residues of or contaminated by hazardous substances AH No No 15 02 Absorbents, filter materials, wiping cloths and protective clothing 15 02 02* absorbents, filter materials (including oil filters not otherwise specified), wiping cloths, protective clothing MH No No contaminated by hazardous substances 15 02 03 absorbents, filter materials, wiping cloths and protective clothing other than those mentioned in 15 02 02 MN No No 16 WASTE NOT OTHERWISE SPECIFIED IN THE LIST 16 03 Off-specification batches and unused products 16 03 03* inorganic wastes containing hazardous substances AH No No 16 03 04 inorganic wastes other than those mentioned in 16 03 03 MN No No 16 03 05* organic wastes containing hazardous substances AH No No 16 03 06 organic wastes other than those mentioned in 16 03 05 MN No No 18 WASTES FROM HUMAN OR ANIMAL HEALTH CARE AND/OR RELATED RESEARCH (except kitchen and restaurant wastes not arising from immediate health care) 18 01 Waste from natal care, diagnosis, treatment or prevention of disease in humans 18 01 01 sharps (except 18 01 03) AN Yes No 18 01 02 Body parts and organs including blood bags and blood preserves (except 18 01 03) AN No No 18 01 03* wastes whose collection and disposal is subject to special requirements in order to prevent infection AH Yes Yes 18 01 04 wastes whose collection and disposal is not subject to special requirements in order to prevent infection (for AN Yes No example dressings, plaster casts, linen, disposable clothing, diapers) 18 01 06* chemicals consisting of or containing hazardous substances MH No No 18 01 07 chemicals other than those mentioned in 18 01 06 MN No No 18 01 08* cytotoxic and cytostatic medicines AH No No 18 01 09 medicines other than those mentioned in 18 01 08 AN No No 18 01 10* amalgam waste from dental care AH No No 18 02 Waste from research, diagnosis, treatment or prevention of disease involving animals 18 02 01 sharps (except 18 02 02) AN Yes No

Page 30 of 47

Permit No: PPC/A/1180708

Column I Column II Column III Column IV Column V EWC Description Entry Can the Can it be treated by Waste Type** waste be the Heat Treatment Code shredded? process on site? 18 02 02* wastes whose collection and disposal is subject to special requirements in order to prevent infection AH Yes Yes 18 02 03 wastes whose collection and disposal is not subject to special requirements in order to prevent infection AN Yes No 18 02 05* chemicals consisting of or containing hazardous substances MH No No 18 02 06 chemicals other than those mentioned in 18 02 05 MN No No 18 02 07* cytotoxic and cytostatic medicines AH No No 18 02 08 medicines other than those mentioned in 18 02 07 AN No No 19 WASTE FROM FACILITIES, OFF-SITE WASTE WATER TREATMENT PLANTS AND THE PREPARATION OF WATER INTENDED FOR HUMAN CONSUMPTION AND WATER FOR INDUSTRIAL USE 19 12 Waste from the mechanical treatment of waste (for example sorting, crushing, compacting, pelletising) not otherwise specified 19 12 12 other wastes (including mixtures of materials) from mechanical treatment of wastes other than those mentioned MN No No in 19 12 11 20 MUNICIPAL WASTES (HOUSEHOLD WASTE AND SIMILAR COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL WASTES) INCLUDING SEPARATELY COLLECTED FRACTIONS 20 01 Separately collected fractions (except 15 01) 20 01 01 paper and cardboard AN No No 20 01 19* pesticides AH No No 20 01 29* detergents containing hazardous substances MH No No 20 01 31* cytotoxic and cytostatic medicines AH No No 20 01 32 medicines other than those mentioned in 20 01 31 AN No No 20 01 99 other fractions not otherwise specified (comprising only of non-clinical human and animal offensive/hygiene AN Yes Yes (see waste (not arising from healthcare and/or related research i.e. not including waste from natal care, diagnosis, footnote) treatment or prevention of disease, which is not subject to special requirements in order to prevent infection). Notes: ** AN = Absolute Non-hazardous AH = Absolute Hazardous MH = Mirror Hazardous MN = Mirror Non-hazardous

20 01 99 in this context means other fractions not otherwise specified (comprising only of separately collected fractions of municipal clinical waste (not arising from healthcare and/or related research i.e. not including waste from natal care, diagnosis, treatment or prevention of disease) which is subject to special requirements in order to prevent infection)

Page 31 of 47

Permit No: PPC/A/1180708

Anatomical wastes with EWC waste codes 18 01 02 or 18 01 03* must not be shredded or treated by the heat treatment process.

Notwithstanding Condition 8.1.1 the Permitted Installation must not process high risk infectious waste through the Waste Treatment Operations.

Notwithstanding Condition 8.1.1 the Permitted Installation must not accept any waste known or likely to contain Class 2, 3 or 4 GMM (genetically modified microorganism) cultures, or wastes containing HG (hazard group) 2, 3 and 4 pathogen cultures or positive specimens, as designated by the Advisory Committee on Dangerous Pathogens (ACDP); any waste from a containment level 3 laboratory; any microbiological cultures from any source; and any potentially infected waste from pathology departments and other clinical or research laboratories (unless provided with evidence that it has been autoclaved before leaving the site of production).

8.2 Waste Pre-Acceptance

Within 3 months of permit issue date the Operator must record, maintain and utilise waste characterisation and pre-acceptance procedures for all waste accepted at the Permitted Installation, which as a minimum, meets the pre-acceptance requirements of EPR 5.07.

The pre-acceptance records produced for each waste producer, must be kept up to date, and must clearly define the treatment and or disposal route for each waste.

8.3 Waste Acceptance

The operator must not unload, or cause or permit the unloading of any delivery of waste, including bulked or containerised waste (e.g. waste in 770 litre carts), until it has inspected the accompanying documentation and concluded that:

a) The documentation, including transfer notes and Special Waste Consignment Notes, are complete, and the information describing the waste(s) is consistent with that information provided during the pre-acceptance checks;

b) Each waste is a permitted waste type;

c) There is sufficient appropriate storage capacity for each waste; and

d) The electronic tracking system is fully functioning.

Waste must be subject to a visual inspection to confirm that the waste types are consistent with those stated in the accompanying documentation. Visual inspection frequencies must, as a minimum, meet the requirements of Section 2.2 of EPR 5.07.

Any waste loads which fail to meet the requirements of Conditions 8.3.1(a), 8.3.1(b) or 8.3.2 must be regarded as non-conforming waste.

Upon unloading the operator must ensure that each waste type identified on the accompanying documentation, is weighed using calibrated platform scales and the weight is recorded. Where relevant, if the weight is different to that stated on the accompanying documentation then the documentation should be clearly amended without obscuring the

Page 32 of 47

Permit No: PPC/A/1180708

original value, and the amendment should be initialled by the staff member. A record of the platform scales calibration must be kept at the Permitted Installation.

The operator must record and maintain an up-to-date list of all tare weights for each type of cart, or container, used to store waste in, at the point of weighing on the platform scales.

The unloading of vehicles delivering waste, and inspection, must only take place within designated area(s), which is served by a sealed drainage system and impermeable surface.

8.4 Non-Conforming Wastes

Where the operator refuses any person permission to deposit waste at the permitted installation, the operator must take all reasonable steps to obtain and record, the following details: name and address of person, registration number of vehicle, quantity and type of waste, and date and time of refusal. The details of the refusal must be reported to SEPA as soon as practicable.

A designated area (the ‘quarantine area’) must be provided for the storage of any wastes found on the permitted installation that are not authorised by this permit.

Accepted wastes which are subsequently found not to conform to permit conditions must be immediately removed to the quarantine area required by Condition 8.4.2 pending their removal from the permitted installation. The six-figure EWC number, type and quantity of any waste sent elsewhere for disposal or recovery must be recorded.

Where waste is accepted and it is subsequently not possible to treat that waste due to failure of the plant, and where the operator removes that waste from the permitted installation, the six-figure EWC number, the type and quantity of the waste and the final destination of the waste must be recorded.

8.5 Waste Storage

No individual bags, boxes or small containers (e.g. small waste bins, tubs and sharps boxes) of waste must be stored loose.

All waste must be stored either:

a) In a lockable, rigid, leak proof bulk containers with a lid (e.g. 770 litre carts);

b) In a lockable leak proof refrigeration unit;

c) Or in the case of small rigid waste containers only (e.g. small waste bins, tubs and sharps boxes), on pallets, stacked no more than 1.8m high, where the waste does not extend beyond the sides of the pallet, and the containers are secured using clear, transparent shrink wrap.

All bulk containers (e.g. 770 litre carts), refrigeration units and pallets must be uniquely unidentified and, where relevant, must be kept closed at all times unless loading/unloading or being visually inspected.

All wastes must be stored on the Permitted Installation in accordance with the requirements of Columns I to V of Table 6.

Page 33 of 47

Permit No: PPC/A/1180708

Table 6: Waste Storage Requirements

Column I Column II Column III Column IV Column V

Waste Storage Waste Types Maximum quantity Maximum Waste Storage Location of waste stored Storage Time Arrangements within the Permitted Installation boundary at any time

Outside the Unprocessed 3 days The trailers must process hazardous and be on an building non-hazardous 8 sealed and impermeable waste awaiting secured trailers surface served by unloading and a sealed foul processing or drainage system. direct onward transfer

Waste which has 5 days The compactor been processed skips must be on and compacted 7 sealed impermeable at the Permitted compactor skips. surface served by Installation, and a sealed foul contained within drainage system. a sealed compactor skip.

Inside the Un-processed 5 days - process hazardous and building non-hazardous 150 tonnes waste awaiting processing (including quarantine area)

Hazardous and 10 days - non-hazardous wastes which 40 tonnes are being bulked on site but will be sent off site for treatment or disposal, including liquid wastes, and wastes which must be refrigerated.

The Operator must record, maintain and utilise waste storage procedures designed to comply with the conditions of this Permit to prevent the release of pollutants to the air, land, surface or ground water, or site drains from the storage of waste at the Permitted Installation.

All waste must be stored in clearly demarcated and labelled, waste storage areas, designed to physically segregate hazardous and non-hazardous waste, and wastes that

Page 34 of 47

Permit No: PPC/A/1180708

must be treated or disposed of differently. This segregation must extend to waste streams that share a European Waste Catalogue (EWC) code but must be treated or disposed of differently.

Notwithstanding Condition 8.5.6, where it is confirmed that the hazardous and non- hazardous waste will be treated and or disposed of in the same way, then they may be stored together.

The labelling of each waste storage area required by Condition 8.5.6 must identify:

a) the waste(s) permitted to be stored in the area with reference to the six digit EWC code;

b) where relevant the hazardous properties associated with the waste(s); and

c) the maximum number of carts (e.g. 770 litre carts) that the area can stored, and the maximum weight of waste that can be stored.

The labelling information must be legible from outwith the waste storage area.

The operator must ensure all waste is stored in a way that allows easy inspection, maintains safe access between rows of bulk containers or palletised waste and ensures that all labels and date markings are visible.

All anatomical waste (including that which is regarded as hazardous or non-hazardous, or animal or human e.g.18 01 02, 18 02 02) must be stored in refrigeration units maintained at -5oC or below at all times.

The Operator must continuously monitor and record the temperature of all refrigeration units used to store waste.

If the temperature of any refrigeration unit rises above -5oC the operator must take immediate action to bring the temperature back into compliance. If the immediate action does not work then the operator must treat this as an incident.

All pharmaceutical waste must be stored within a designated area within the process building.

All liquid wastes must be stored in appropriately bunded areas as required by conditions 4.2.6 and 4.2.7.

8.6 Cleaning

The operator must record, maintain and utilise cleansing and disinfection procedures for all storage areas, fixed storage containers (e.g. refrigeration units) and re-usable mobile containers (e.g. 770 litre carts and similar containers). The procedures must be designed to comply with the conditions of this permit and in particular must be designed to prevent the release of pollutants to the air, surface or groundwater, or to site drains from the cleansing and disinfection operations at the Permitted Installation.

All storage areas and associated infrastructure namely floors, walkways, railings, doors, walls, ductwork etc. must be cleared of all wastes at least once every three months and

Page 35 of 47

Permit No: PPC/A/1180708

the area thoroughly cleaned in accordance with the procedures required by Condition 8.6.1. The date and time, photographs and details of such cleaning must be recorded.

8.7 Contingency Plan

Within 2 months from the date of issues of this permit the Operator must develop, implement and maintain a Contingency Plan.

The Contingency Plan required by Condition 8.7.1 must as a minimum meet the requirements of Section 1.1 of EPR 5.07 and include ceasing the acceptance of waste

Page 36 of 47

Permit No: PPC/A/1180708

9 TRACKING OF WASTE THROUGH THE PERMITTED INSTALLATION

9.1 Electronic Tracking System

The Operator must develop, install, maintain and back-up an electronic tracking system capable of tracking all waste through the Permitted Installation, from the point of pre- acceptance, to acceptance onto the Permitted Installation, through each of the different stages of the process, and up-to and including the point of removal from the Permitted Installation.

The Operator must develop, record, maintain and implement written procedures detailing how to operate the electronic tracking system.

The electronic tracking system required by Condition 9.1.1 must operate as a waste inventory/stock control system, and as a minimum, must ensure the Operator is capable of:

a) Comparing, in real time, the total quantity of waste present at each waste storage location, against the permitted maximum and the current capacity (both in relation to the number of waste storage containers and weight);

b) Comparing, in real time, the time waste(s) have been on the Permitted Installation against the permitted limit;

c) Confirming, in real time, the quantity of each waste being stored at each waste storage location;

d) Confirm in real time, how much of each waste, is at each of the different stages of processing through the Permitted Installation including, but not limited to:

i. the amount being stored pending treatment on site,

ii. the amount being stored pending treatment and or disposal off-site,

iii. the amount of treated waste being stored pending movement off site, and

iv. the amount of refrigerated waste.

v. For all bulked waste, listing each Special Waste Consignment Note related to all waste which forms a portion of the bulked load.

Page 37 of 47

Permit No: PPC/A/1180708

10 WASTE TREATMENT OPERATIONS ON THE PERMITTED INSTALLATION

10.1 General

The Operator must prioritise the treatment, or off-site transfer, of waste based on the first- in, first-out principle, and in addition, prioritise wastes with a higher risk of causing odour, litter or pest problems.

10.2 Shredding Operations

Only wastes defined as suitable for shredding in column IV of Table 5 must be subject to shredding operations.

When operational, all waste within the shredders must be fully enclosed, and under negative pressure as defined in Condition 10.2.4.

All air extracted from operational shredders must be passed through high efficiency particulate air (HEPA) filters and a carbon filter prior to being discharged to air.

For the purposes of Condition 10.2.2 ‘negative pressure’ must mean inward suction with a minimum velocity of 0.5 metres per second, or greater, around all areas of the shredder whilst the shredder is in operation. The velocity of negative pressure must be checked quarterly using a calibrated anemometer and recorded.

10.3 Heat Treatment Process

Only waste which has been shredded and defined as suitable in Column V of Table 5, must be treated via the heat treatment process at the Permitted Installation.

The heat treatment process must be operated such that the minimum temperature to which waste is exposed to is 122oC for 80 minutes.

The Operator must install and maintain an effective interlock whereby if the process fails to meet the required temperature and time no additional waste can be introduced to the process.

Failure to meet the required temperature and time stated in Condition 10.3.2 must be treated as an incident in accordance with section 2.8, and no more waste must be introduced into the process, and the waste within the auger must be managed as untreated waste.

The operator must continuously measure and record the temperature at multiple points along the auger at all time during operation.

All thermocouples used to monitor temperature of the Heat Treatment process must be calibrated in-situ annually. A record of the calibration must be kept.

The operator must continuously measure and record the speed of rotation of the auger at all times during operation.

The operator must ensure that when in operation the heat treatment process must be operated under negative pressure (as defined by Condition 10.2.4) and all air extracted

Page 38 of 47

Permit No: PPC/A/1180708

must be passed through a condenser, a coalescing filter and a carbon filter prior to release to atmosphere.

All waste effluent produced at the site including condensed emissions from the heat treatment process must be discharged to the public sewer under consent of Scottish Water.

10.4 Routine Efficacy Monitoring of the Heat Treatment Process

The operator must ensure that any heat treatment of waste will consistently achieve a minimum microbial reduction equal to STAATT Level III.

The operator must undertake routine efficacy monitoring of the heat treatment process in accordance with the requirements specified in Table 7, using the same methodology used for site commissioning. The results must be reported to SEPA within 14 days of the monitoring taking place.

Table 7: Routine efficacy monitoring frequency per thermal screw auger treatment unit

Test frequency Test frequency Minimum number Number of control Number of thermal of spore samples samples indicator strips (if (first 6 months of (operational, after or sub-samples used) operation) the first 6 months)

Weekly Monthly 3 1 1 per spore strip

In each round of routine efficacy monitoring spore strips and controls strips from the same manufacturer, and from the same batch code, must be used. Strips that exceed their stated expiry date must not be used.

The routine efficacy monitoring report required by Condition 10.4.2 must include as a minimum the information required by Conditions 6.1.5 a), b), c), d)

Where the quantitative results for the control spore strip indicate a viable population less than 104 colony forming units (cfu) the routine efficacy testing must be repeated immediately.

Where 5% of scheduled spore strips fail to comply with Condition 10.4.1 in any 12 month period, the operator must treat it as an incident and cease operation of the heat treatment process until such time as a full investigation has been completed and reported in accordance with Condition 2.8 of this permit.

Where any thermal treatment indicator strip or multi point thermal logger, used in the routine efficacy monitoring indicates that the stated temperature in Condition 10.3.2 has not been met, the operator must treat this as an incident in accordance with Condition 2.8

Page 39 of 47

Permit No: PPC/A/1180708

of this permit. The waste associated with that testing period must be managed as untreated Waste.

10.5 Drying System

The operator must install and maintain an effective fire detection system capable of detecting a fire within the drying system and process building. This must be connected to an audible and visual alarm system.

The operator must install and maintain an effective continuous monitoring system which continuously measure and record the temperature at multiple points within the drying process at all times during operation.

All thermocouples used to monitor temperature of the drying process must be calibrated in-situ annually. A record of the calibration must be kept.

The operator must install an interlock such that if the outlet screw stops or blocks, the gas fired burner system which provides the drying air is shut-down. The operator must record all such instances.

10.6 HEPA Filters

The Operator must ensure all HEPA filters are installed and maintained to ensure a minimal particle removal efficiency of 99.97% for all particles ≥0.3μm.

The Operator must carry out annual monitoring of the HEPA filters in accordance with BS EN ISO 14644-3-2005 to demonstrate compliance with condition 10.6.1.

The operator must install differential pressure monitors to continuously monitor the differential pressure across all HEPA filters. They must record the differential pressure twice per day.

The differential pressure monitors must be calibrated and maintained annually. Details of calibration and maintenance must be recorded.

The operator must define and record the range of differential pressure readings which represents compliant operation.

HEPA filters must be replaced when the differential pressure readings are outside the defined compliant range. Details of when HEPA filters are changed must be recorded.

The operator must record, maintain and utilise procedures for the installation, maintenance, safe removal and disposal of HEPA filters.

10.7 Carbon Filters

The operator must undertake and record the monitoring required in Table 8 at the frequency stated in Column II, for all carbon filters.

Page 40 of 47

Permit No: PPC/A/1180708

Table 8: Carbon Filter Monitoring Requirements

Column I Column II Parameter Monitoring frequency Inlet air temperature Continuously Inlet air moisture content Continuously

Carbon filter inlet air moisture content must not exceed 20% relative humidity, and inlet air temperature must not exceed 48oC.

If monitoring indicates that a parameter is outwith compliant range, the operator must investigate without undue delay. Details of the investigation must be recorded.

Page 41 of 47

Permit No: PPC/A/1180708

11 EMISSIONS MONITORING

11.1 Microbial Emissions Monitoring

The Operator must undertake and report on microbial emissions monitoring in accordance with the requirements of Table 9.

At least 28 days prior to undertaking the monitoring the operator must submit a microbial monitoring protocol to SEPA describing the proposed sampling and analytical methods to be used.

The microbial monitoring protocol must be agreed in writing with SEPA prior to undertaking the monitoring.

Table 9: Microbial emissions monitoring

Monitoring Location Method Frequency of Reporting of: monitoring frequency

Ambient air Internal adjacent to shredder(s) Tracer spore Annual During suspension commissioning Internal adjacent to bin washer(s) technique using and thereafter Bacillus spores annually. External to process building and downwind of HEPA filter emission point (s)

External and downwind of the Permitted Installation and not >10 metres from site boundary

Surfaces Internal adjacent to the shredder(s) Tracer spore Annual During suspension commissioning Internal adjacent to bin washer(s) technique using and thereafter Bacillus spores annually. External to process building and adjacent to HEPA filter emission point(s) External and downwind of the Permitted Installation

11.2 Emissions to Air

There must be no emissions to air from the installation other than those specified in Table 10, which must only be permitted from the emissions locations specified in Table 10 and must not exceed the limits specified in Table 10.

The operator must carry out spot sampling (SS) of emissions of the parameters specified in Table 11, at the sampling location specified in Table 10 and subject to the requirements for monitoring specified in Table 11.

The operator must record the date, time, duration and results of all monitoring carried out under Condition 11.2.2 and report said results. For each result, the report must include the operational mode of the Permitted Installation at the time of monitoring, the name of the person carrying out the monitoring, any deviations from the methods specified in Table 11 and the associated confidence interval.

Page 42 of 47

Permit No: PPC/A/1180708

Table 10: Emissions to Air ELVs

Emission point EP1 EP4 EP2 EP3 EP6 EP7 number on Site Plan Combined Combined Emission Backup Diesel Boiler 1 Boiler 2 Drier 1 Burner Shredder, Auger, Shredder and source Generator Drier Auger Source of Emission Stack height/ >3m above roof >3m above roof >3m above roof >3m above apex of >3m above apex of diameter (m) ridge ridge ridge roof roof - /0.3 /0.3 /0.35 /1.0 /1.0

NGR NS 7256 6096 NS 7256 6097 NS 7253 6092 NS 72515 60901 NS 72514 60901

Type of SS SS - SS SS - Monitoring Monitoring Details Sampling In flue In flue - In flue In flue - Location Particulate ------mg/Nm3 Oxides of nitrogen 100 100 - - - - Limits for (NOx) mg/m3 Parameters Ringlemann Shade 1 Ringlemann Shade 1 from Emission Smoke to BS 2742 (as to BS 2742 (as - - - Source amended) amended) Visible No persistent mist, No persistent mist, No persistent mist, No visible plume of No visible plume of No persistent mist, Plume fume or droplets. fume or droplets. fume or droplets. steam. steam. fume or droplets Odour 3 ------(OUE/m )

Page 43 of 47

Permit No: PPC/A/1180708

Table 11: Emissions to Air Monitoring Requirements

Spot Sampling (SS) Emission point Reference Parameter Operational number Standard Frequency Conditions Mode

Once within 4 months of 273,15 K, Oxides of As agreed in writing EP1 commencing operation of nitrogen with SEPA at least 14 Normal 101.3 kPa, EP4 the boiler thereafter every 3 (NOx) days prior to monitoring 3% O2 years. Once within 4 months of 273,15 K, As agreed in writing Carbon EP1 commencing operation of with SEPA at least 14 Normal 101.3 kPa, Monoxide EP4 the boiler thereafter every 3 days prior to monitoring 3% O2 years. Once within 2 months of As per standard EP3 commencing Waste Dust EN 13284-1 Normal EP6 Treatment Operations thereafter every 6 months. Quarterly for 1 year from As per standard. commencement of the EP3 Odour BS EN13725 Waste treatment Normal EP6 operations thereafter annually. Once within 2 months of As per standard. EP3 commencing Waste TVOC EN 12619 Normal EP6 Treatment Operations thereafter every 6 months

Page 44 of 47

EXPLANATORY NOTES

(These Explanatory Notes do not form part of the Permit)

1. BAT

It should be noted that Regulation 22 of the Regulations specifies that it is a Condition of a permit that the operator must use the best available techniques (BAT) for preventing or, where that is not practicable, reducing emissions from the installation. This is referred to as the ‘general’ BAT Condition.

This does not apply to the extent that any other Condition of the permit, or a standard rule which has effect as a standard rules Condition, has the same effect.

Examples of aspects of the operation that have not been regulated by specific Conditions are management and supervision systems, training and qualification and maintenance in general.

BAT is defined in Regulation 4 of the Regulations as follows:

"Best available techniques" means the most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing the basis for emission limit values and other permit Conditions designed to prevent and, where that is not practicable, to reduce emissions and the impact on the environment as a whole.

"available techniques" means those techniques which have been developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable Conditions, taking into consideration the cost and advantages, whether or not the techniques are used or produced inside the UK, as long as they are reasonably accessible to the operator.

"best" means in relation to techniques, the most effective in achieving a high general level of protection of the environment as a whole.

"techniques" includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned.

“BAT conclusions” means a document containing the parts of a BAT reference document laying down the conclusions on best available techniques, their description, information to assess their applicability, the emission levels associated with the best available techniques, associated monitoring, associated consumption levels and, where appropriate, relevant site remediation measures.

“emerging technique” means a novel technique for an industrial activity that, if commercially developed, could, when compared to existing best available techniques provide a higher level of protection of the environment, or at least the same level of protection of the environment and higher cost savings.

“emission levels associated with best available techniques” means the range of emission levels obtained under normal operating Conditions using a best available technique, or combination of best available techniques, as described

in BAT conclusions, expressed as an average over a given period of time, under specified reference Conditions.

Schedule 3 of the Regulations specifies the matters to be taken into account in determining BAT.

In considering BAT, SEPA would expect the operator to have regard to all relevant PPC sectoral or other technical guidance, including BAT Reference Documents published by the European Commission and UK technical guidance published by the Environment Agency.

2. GENERAL STATUTORY REQUIREMENTS

The permit does not detract from any other statutory requirements applicable to you in respect of the Permitted Installation, such as any need to obtain planning permission or building regulations approval or any responsibilities under legislation for health, safety and welfare in the workplace.

3. APPEALS

If you are aggrieved by any of the Conditions of the permit, you should initially contact the local SEPA office at the address or telephone number below. Further information on your right of appeal and the appeals procedure is contained regulation 58 and Schedule 8 of the Regulations.

4. SUBSISTENCE CHARGES

An annual subsistence charge will be payable in respect of the permit in terms of the Pollution Prevention and Control (Scotland) Charging Scheme or any relevant charging scheme made under Section 41 of the Environment Act 1995, copies of which are available from SEPA.

5. ADDRESS AND TELEPHONE NUMBERS

The contact address and telephone number for all information to be reported in terms of the permit, is as follows:

Scottish Environment Protection Agency Angus Smith Building 6 Parklands Avenue Eurocentral Holytown North Lanarkshire ML1 4WQ Tel No: 0800 80 70 60

6. REVIEW OF CONDITIONS

The Conditions of the permit will be periodically reviewed by SEPA.

7. PROPOSED CHANGE IN OPERATION OF INSTALLATION

It is a requirement of Regulation 45 of the Regulations that if you propose to make a change in the operation of the installation, you must notify SEPA at least 14 days before making the change. The requirement under Regulation 45 does not apply if you have already made an application to SEPA for the variation of the Conditions of the permit containing a description of the proposed change.

N.B. the requirements of Regulation 45 are in addition to any obligations you may have under the permit itself to only operate the Permitted Installation in the manner set out in the permit and to notify SEPA of proposed changes to the Permitted Installation.

Regulation 46 and Schedule 7 of the Regulations provide details on applications for variation of the permit in respect of proposed changes and substantial changes in operation.

“Change in operation” and “substantial change in operation” are defined in Regulation 2 of the Regulations.

8. ENFORCEMENT & OFFENCES

If SEPA is of the opinion that you have contravened, or are contravening or are likely to contravene a Condition of the permit, or an incident or accident significantly affecting the environment has occurred as a result of the operation of the installation it may serve an enforcement notice. Further details on enforcement notices are provided in Regulation 55 of the Regulations.

If SEPA is of the opinion that the operation of an installation poses an immediate danger to human health, threatens to create an immediate significant adverse effect upon the environment or involves a risk of serious pollution it must, in certain circumstances, serve a suspension notice on you. Further details on suspension notices are provided in Regulation 56 of the Regulations.

It is an offence to operate an installation covered by the Regulations without a Permit or in breach of the Conditions of the permit. It is an offence to fail to comply with the requirements of an enforcement or suspension notice. It is an offence to intentionally make a false entry in any record required to be kept under a Condition of a permit. Further details on offences and on penalties liable to be imposed upon conviction of an offence are provided in Regulation 67 of the Regulations.

Directors, managers and other individuals within a company may be held personally liable for offences under the Regulations.

All personnel who are responsible for fulfilling any Condition of the permit should be made aware of these facts.

9. BREACH OF A PERMIT CONDITION

Regulation 52 of the Regulations specifies that the operator of an installation must immediately give notice to SEPA of any breach of a Condition of the permit. It is an offence to fail, without reasonable excuse to comply with Regulation 52.

Any statement made by an operator to SEPA for the purposes of complying with regulation 52 may only be used in a prosecution for an offence where in giving evidence the operator makes a statement inconsistent with the initial notification.

All personnel who are responsible for fulfilling any Condition of the permit should be made aware of these facts.

10. RECORDED SYSTEMS, PROCEDURES OR INFORMATION RECORDING/ RETURN REQUIREMENTS

Where a Condition requires any system, procedure or information record/return, the operator may demonstrate compliance by making use of any relevant existing written system used for any other purpose and which meets the requirements of the relevant Condition.

11. SYSTEMATIC ASSESSMENT (AND REVIEW)

Where a Condition of the permit requires a “systematic assessment (and review)” the assessment should be undertaken in a methodical and arranged manner. If you require guidance on the scope or extent of any assessment (and review) required to be undertaken, you should contact your local SEPA office at the address or telephone number given above.