Module 11: Operation & Maintenance

OPERATION & MAINTENANCE

Gerard van Bussel

section Wind Energy

Module 11: Operation & Maintenance

Typical contribution to energy cost

Investment & Decommissioning 3% O & M Decommissioning O & M Investment 25 - 30% 23% 74% ~ 75 %

Opti-OWECS study (1998) CA-OWEE (2001)

1 Module 11: Operation & Maintenance Maintenance Concepts maintenance

corrective preventive maintenance repairmaintenance service

batch wise corrective periodic condition corrective maintenance preventive based maintenance on demand maintenance maintenance

opportunity calendar condition condition based based judging monitoring

Module 11: Operation & Maintenance Failure frequencies 500kW class

Tacke TW600 40 V39/500

number of turbines 25 26 59

events/year events/year events/year Lightning 0 0.03 0 Blade 0.76 0.42 0.32 Rotor Brake 0 0 0 Pitch Mechanism 0 0.30 0.03 Brake 0.08 0 0 Shaft/Bearing 0.04 0.03 0 Gearbox 0.16 0 0.03 Generator 0 0.03 0.33 Hydraulic 0.32 0 0.27 0.32 0.23 0.08 Anemometry 0 0 0.01 Electronics 0.04 0.42 0.33 Electric 0.20 0.69 0.30 Inverter 0 0 0 Sensors 0.08 0.07 0.18 Other 0.20 0.38 0.37 Overall Total 2.2 2.6 2.25 Failure frequencies 2.2 2.6 2.25 For larger machines (onshore) => 2.2 /year

2 Module 11: Operation & Maintenance Failure frequencies multi MWW class

Component Failure frequency (failures/year) Shaft & Bearings 0.02 Brake 0.05 Generator 0.05 Parking Brake 0.05 Electric 0.14 Blade 0.16 Yaw System 0.23 Blade tips 0.28 Pitch Mechanism 0.28 Gearbox 0.30 Inverter 0.32 Control 0.34 Total 2.20

Total of all components: 2.20 failures/year

Module 11: Operation & Maintenance

Reliability, Availability, Maintainability, Serviceability

reliability maintainability serviceability (failures/year) (MTTR) (PM demand)

theoretical availability accessibility maintenance of the site strategy

actual availability

3 Module 11: Operation & Maintenance A measure for availability

state running

failed MTTR MTTF Mean Time To Repair Mean Time To Failure

time MTTF Availability = MTTR + MTTF

Module 11: Operation & Maintenance

Experienced Availability

TunoTuno KnobKnob availabavailabilityility Tuno Knob 100.00% (inshore, 100.00% ) 98.00% 97% 98.00% 96.00%96.00%

94.00%94.00%

92.00%92.00%

90.00%90.00% 19961996 1997 1997 1998 1998

4 Module 11: Operation & Maintenance Present maintenance demand

4 Visits per 3 turbine per 2 year 1

0 Unplanned Planned

Module 11: Operation & Maintenance Accessibility of site (Vessel)

Vindeby DK inshore

Oct Nov Dec Jan Feb Mar Apr May June July Total Nominal 23 21 20 22 20 22 19 19 21 23 210 Working Days Bad Weather 110245400017 (Days) Bad Weather 522413100018 (o.5 Day) Lack of 02001.54610014.5 Transport Inaccessible 3.5414610.510.510040.5 Days % Total Time 15.2 19 5 18.2 30 47.7 55.3 5.3 0 0 19.3

5 Module 11: Operation & Maintenance Accessibility of site (Vessel)

Horns Rev Vindeby (near shore, (inshore, ) Denmark) Horns Rev versus Vindeby Accessibility

120.00%

100.00%

80.00% 6 hours 12 hours 60.00% 24 hours 40.00% Vindeby Fraction of time 20.00%

0.00% jul jan feb jun apr oct nov dec aug sep mar may

Module 11: Operation & Maintenance Means of crew transport

• Helicopter • Tender vessel - fast - fairly slow - expensive - cheap - helipad - boat landing - large operational -medium window window

6 Module 11: Operation & Maintenance Means of crew transport 2 A tender vessel For crew transport

A “gol” boat Harbour pilots

Module 11: Operation & Maintenance Means of crew transport 3

A tender vessel For crew transport

With a Zodiac for landing

7 Module 11: Operation & Maintenance Means of crew transport 4

WithWith aa ZodiacZodiac forfor landinglanding ????

Module 11: Operation & Maintenance Means of crew transport 5

Crew transport by helicopter

8 Module 11: Operation & Maintenance Trends: Access methods

Catamaran landing vessel

SWATH@A&R / Abeking &Rasmussen

Module 11: Operation & Maintenance Trends: Access methods Flexible gangway:

OAS: P&R systems / Reinout Prins

9 Module 11: Operation & Maintenance Trends: Access methods

FlexibleFlexible gangwaygangway

OAS: P&R systems / Reinout Prins

Module 11: Operation & Maintenance

Trends: Access methods

AmpelmannAmpelmann

10 Module 11: Operation & Maintenance Cost comparison transport Vessel/Helicopter

2 MW farm

8000 7000 6000 5000 4000 3000 Vessel

Costs [euro] Costs 2000 Helicopter 1000 Vessel+Downtime Heli+Downtime 0 0 1020304050607080 Distance Mantenance base to offshore [km]

Module 11: Operation & Maintenance Experiences in the real world

Maintaining Horns Rev: – Access by boat: Winter 02/03: 5/7 days » Winter 03/04: 1/7 days – Helicopter: 6/7 days

– Vestas responsible for crew (60 people) Elsam for transport (6 people) – 75.000 transfers in 1.5 years (2 x /day/turbine)

11 Module 11: Operation & Maintenance Experiences in the real world

Maintaining Horns Rev:

Reasons: – Design not well adapted for offshore – Strategy not optimal – Onshore crew – Sophisticated alarms, but what does it mean?

Module 11: Operation & Maintenance Lifting equipment

• Jack-up barge • Crane vessels • Helicopter • Jack up vessel assisted with built-in facility (in wind turbine)

12 Module 11: Operation & Maintenance Installation & O&M lifting facilities

Jack up vessels

A2Sea Ocean Hanne at Horns Rev Denmark Utgrunden Wind farm, Sweden

Module 11: Operation & Maintenance Installation and O&M lifting facilities

Jack up vessels

A2Sea Ocean Hanne at Horns Rev and at Nysted Denmark

13 Module 11: Operation & Maintenance

Trends: Lifting at wind turbine

Hoisting outside

Picture: Enron (Utgrunden, Sweden)

Picture: N80 Offshore Internal cranes

Module 11: Operation & Maintenance Trends: Installation

Ballast-Nedam NEG-Micon Dowec project

14 Module 11: Operation & Maintenance Maintenance strategies

• PM and CM on demand (onshore practice) • Opportunity based maintenance (PM when CM is demanded) • Condition based maintenance (PM and CM only when demanded) • No maintenance/ batch maintenance

Module 11: Operation & Maintenance Maintenance strategies

• PM and CM on demand (reduced PM demand, increased reliability) • Opportunity based maintenance (flexible PM interval, increased reliability) • Condition based maintenance (extensive condition monitoring) • No maintenance/ batch maintenance (only feasible when failure freq. < 0.2 /year)

15 Module 11: Operation & Maintenance

Importance of Reliability and Accessibility

100%

90% Reliability

80% highly improved 70% improved Availability 60% onshore design 50% 100 % 80 % 60 % 40 % (remote (onshore) (nearshore) (offshore) offshore) Accessibility

Module 11: Operation & Maintenance Importance of (improved) Reliability

100%

90% Offshore 80% designed

70% Offshore adapted Availability 60%

50% 100 % 80 % 60 % 40 % (remote (onshore) (near shore) (offshore) offshore) Vessel accessibility

Tuno & Vindeby Horns Rev (DK inshore) (North Sea)

16 Module 11: Operation & Maintenance Assessing reliability, availability and O&M in the design process

RAMS targets Waiting time on system Design evaluation level analysis Feasibility study RAMS targets Expert system sub-system level approach Conceptual design

RAMS targets on Monte Carlo component level Simulations

Final design RAMS targets Full FMECA sub-component level analysis Systems specification

Module 11: Operation & Maintenance Probabilistic Waiting time analysis

Time To Repair IJmuiden Munitie Stortplaats

100% 90% 80% Chance 70% 60% T_mission: 24 h 50% [%] CDF 40% T_mission: 72 h 30%

20% T_mission: 168 h 10% 0% 0 100 200 300 400 500 600 700 800 900 1000 time [hrs] ECN/ Luc Rademakers Time [hrs]

17 Module 11: Operation & Maintenance Trend lines in expert system

Availability as Function of Maximum (onshore) Availability and Storm Percentage 120 100 80 Max.availability 99.0 % 98.0 % 60 97.0 %

40 Symbols: Availability [%] Availability simulations 20 0 0 50 100 150 No access percentage

Module 11: Operation & Maintenance

Monte Carlo simulations

• Analysis of complex stochastic processes • Failure simulation of wind turbines • Storm simulation for OWECS accessibility • Availability estimates for OWECS • O&M costs estimates for OWECS

18 Module 11: Operation & Maintenance FMECA: Failure Mode Effect and Criticality Analysis

• systematic brake down of: - functional components - hardware component • analysis of: - effects of all kinds of failures upon functioning - criticality of failure (how does failure affect costs/environment)

Module 11: Operation & Maintenance Reliability vs. turbine design

• Turbine design gets more complex: – Three bladed, variable speed pitch control – Doubly fed generators, Inverters BUT • Offshore environment demands a robust, lean design: – Two blades !? – Stall control !?? – Low speed or Direct drive generator !?

19 Module 11: Operation & Maintenance Recent wind turbine failures

NEG Micon Yttre Stengrunden

V 80 at Tjaereborg

Nordex N 80 Blyth offshore

Module 11: Operation & Maintenance

Context of the project

• Consortium of industries and institutes • Project: ~ 500 MW offshore wind farm • Location: North Sea > 12 mile zone • Concepts of 5 MW wind turbines • Turbine design for large scale wind farm

Assess wind turbine RAMS aspects in the context of the whole wind farm

20 Module 11: Operation & Maintenance Wind turbine’s reliability

Yearly failure freq. 2

1

0 Present Assumed DOWEC 500 kW 1.5 - 2 MW target (5 MW)

Module 11: Operation & Maintenance

Reduction of failure frequencies

Components factor events/year • Electric system 0.7 0.10 • Blades 0.7 0.07 / 0.11 • Yaw System 0.65 0.15 • blade tips 0.5 0.14 • Pitch Mechanism 0.5 0.13 / 0.14 • Gearbox 0.5 0.13 / 0.15 • Inverter 0.5 0.16 • Control system 0.5 0.15 / 0.19

21 Module 11: Operation & Maintenance DOWEC concepts Base line Advanced Robust Stall-teeter Smart stall Direct drive

Active Stall Pitch Stall Stall Stall pitch

3 blades 3 blades 2 blades 2 blades 3 blades 3 blades

2 speed Var. speed Fixed speed Var. speed Var. speed Var. speed (30%) (full) (full) (full) Tubular Tubular Tubular Truss Tubular Tubular tower tower tower tower tower tower

Piled Piled Monopile Gravity Piled Piled (tripod) (tripod) (tripod) (tripod) Up wind Up wind Up wind Down wind Up wind Up wind (teetered hub)

Module 11: Operation & Maintenance DOWEC concepts: reliability

basic control concepts: yearly failure frequencies

1.40

y 1.20

target 1.00 Control Inverter 0.80 Gearbox Pitch Mechanism blade tips 0.60 Yaw System Blade 0.40 Electric Brakes 0.20 Generator Cumulative failure frequenc Shaft & Bearings 0.00 Base Line Advanced Robust Stall- Smart- Direct teeter stall drive

22 Module 11: Operation & Maintenance DOWEC concepts: failure classes

basic control concepts: yearly failure frequencies

1.40 Cat. 4: Small or no parts, 24 hrs y 1.20

1.00 Cat. 3: Small target parts, 48 hrs 0.80 Cat. 2: Large 0.60 components internal crane 0.40 Cat. 1: Heavy components, 0.20 Cumulative failure frequenc external crane

0.00 Base Line Advanced Robust Stall- Smart- Direct teeter stall drive

Module 11: Operation & Maintenance Numerical Monte Carlo Simulation

Quantity of Spare Parts in Stock

25 • Site conditions 20 Spare Part 1 15 Spare Part 2 10 Spare Part 3 quantity (wind and waves) 5 Spare Part 4 0 1 1231 2461 3691 4921 6151 7381 8611 9841 11071 12301 13531 14761 15991 17221 •Failures time [hours]

components of turbine, Accumulative Availability of Wind Farm against Time

101.00% and wind farm 100.00% 99.00% 98.00% • Maintenance strategy 97.00% 96.00% 1 941 1881 2821 3761 4701 5641 6581 7521 8461 9401 - ships and crew 10341 11281 12221 13161 14101 15041 15981 16921 time [hours]

turbine 1 - immediate/batch repair Availability of Turbines turbine 2 turbine 3 101.00% - overhaul turbine 4 100.00% turbine 5 99.00% turbine 6 98.00% - stock keeping turbine 7 97.00% turbine 8 96.00% turbine 9 95.00% turbine 10 94.00% turbine 11 93.00% turbine 12

23 Module 11: Operation & Maintenance DOWEC 500 MW wind farm

100.00% Accessibility 80 % 2.10E+09

2.00E+09 target 95.00% 1.90E+09 90.00% 1.80E+09 85.00% 1.70E+09 Yearly yield [kWh] Yearly yield 80.00% 1.60E+09

ine Robust Base L Advanced Stall-teeterSmart-stallDirect drive

Module 11: Operation & Maintenance DOWEC 500 MW wind farm Accessibility 60 % 100.00% 2.10E+09

2.00E+09 target 95.00% 1.90E+09 90.00% 1.80E+09 85.00% 1.70E+09

80.00% 1.60E+09 [kWh] Yearly yield

ine Robust Base L Advanced Stall-teeterSmart-stallDirect drive

24 Module 11: Operation & Maintenance DOWEC 500 MW wind farm

Yearly O&M costs of wind farm [Euro]

€ 45,000,000 € 40,000,000 € 35,000,000 € 30,000,000 € 25,000,000

Euro € 20,000,000 Fixed costs € 15,000,000 Transport costs € 10,000,000 Crew costs € 5,000,000 € 0 Cat 4: No parts Cat 3: Small parts t r l e ine t Catrive 2: Large comp. L tee t-stal se Robus l- a l Cat 1: Heavy lift B Advanced a St Smar Direct d

Module 11: Operation & Maintenance

Context of the project

• Consortium of industries and institutes • Project: ~ 500 MW offshore wind farm • Location: North Sea > 12 mile zone • Concepts of 5 MW wind turbines • Turbine design for large scale wind farm

Develop optimal crew transport strategy

25 Module 11: Operation & Maintenance The Target

Develop an optimal O&M strategy for crew transport in the DOWEC offshore wind farm

• 80 * 6 MW wind turbines • 43 km off the Dutch coast (“NL7”) • 40 PM operations per year • 1.5 failure per year per turbine (120 (averaged) CM operations per year) • 1 shift (12h) per 24 hours

Module 11: Operation & Maintenance

Access systems considered

Significant Average (1-hour) No Access system wave height wind speed [m] [m/s]

1 Fictitious 0.75 N.A. 2 Rubber boat, jump onto 1.5 10 ladder 3 Offshore Access System 2 11.5 (OAS) 4 Offshore Access System 3 15 + (optimistic assumption) 5 Helicopter NA 20

26 Module 11: Operation & Maintenance Wind & waves from the NESS/NEXT database

• North European Storm Study • consortium of oil companies ‘NL7’ location (“NL7“ data made available by Shell) • “hindcast“ data • wind fields based on pressure data • application of wave models • verification with measurements • 3- hours interval; 30*30 km grid • 30 years; 9 years complete + (long term correlation of wind and waves)

Module 11: Operation & Maintenance

Variables in the NESS/NEXT database

Characteristic values for each 3-hour period: • V (1-hour) mean wind speed (m/s) at 10 m height

• θV wind direction (degrees)

• Hs significant wave height (m)

• Tz mean zero upcrossing period (s)

• Θm wave direction (degrees)

9 years of consecutive data

27 Module 11: Operation & Maintenance From 3 D scatter plot → pdf

Vw →

→ • ? pdf • ⇒ Hs → →

pdf NEXT database: built-in (long term) correlation between wind and wave data Tz →

Module 11: Operation & Maintenance To 2 D relations

V

Hs

28 Module 11: Operation & Maintenance NESS/NEXT database relation for NL7

V 25

20 Helicopter 15 OAS+ 10

Zodiac 5 OAS

1 2 3 4 5 Hs

Module 11: Operation & Maintenance Weather windows 1

Example: • Uninterrupted time intervals Hs < 1.25 m

Windows: • 6 hours • 12 hours • 24 hours • ...... hours

29 Module 11: Operation & Maintenance Weather windows 2

120 Heli summer Heli winter OAS+ summer 100 OAS summer OAS+ winter 80 Zodiac summer OAS winter Zodiac winter % 60 Fictitious summer Fictitious winter Percentage 40

20

0 0 102030405060 Weather window Window [hours] [hours]

Module 11: Operation & Maintenance

Availability of the DOWEC wind farm

120.0 OAS+Heli 100.0 OAS

] Zodiac 80.0

60.0

40.0 Availability [% Availability

20.0 Availability [%] Availability

0.0 0 20406080100 AccessibilityAccessibility [%] [%]

30 Module 11: Operation & Maintenance

Immediate maintenance action

100 90 12 hours 80 24 hours 48 hours 70 168 hours 60 336 hours 50 12 hours 40 [%] 24 hours 30 48 hours 20 168 hours 10 336 hours Direct action and compltetion % 0 20 40 60 80 100 AccessibilityAccessibility [%] [%]

Module 11: Operation & Maintenance Average waiting time

336 s 288 12 hours 24 hours 240 48 hours 168 hours 192 336 hours 144

96 Waiting hours 48 Average nr of waiting hour 0 40 50 60 70 80 90 100 AccessibilityAccessibility [%] [%]

31 Module 11: Operation & Maintenance CONTOFAX overall results

DOWEC reference wind farm: one shift with two crews

No Access system Accessibility Availability [%] [%] 1 Fictitious 34 49 2 Rubber boat, jump onto 71 83 ladder 3 Offshore Access System 84 91 4 Offshore Access System+ 95 95 (optimistic assumption) 5 Helicopter 100 96

Module 11: Operation & Maintenance DOWEC crew transport conclusions

• Rubber boat landing strategy not feasible • OAS wind farm availability > 90% • OAS+ availability > 95% • OAS+ and heli comparable availability • Average waiting time for short maintenance actions (<48h) is limited (10 to 20 h)

32 Module 11: Operation & Maintenance O&M Conclusions • Present wind turbine reliability insufficient • Certainly for wind farms at remote sites • Different maintenance strategy needed • Opportunity based (flexible service intervals) • Condition based maintenance • High impact of heavy lifting operations on costs • Large offshore wind farms need integrated design • Wind turbines designed for marine maintenance (and installation !!) operations • Special purpose O&M hardware

33