Environmental Monitoring Report

Project Number: 42012 August 2012

PRC: Urban-Rural Infrastructure Development Demonstration Project

Prepared by Chongqing ADB Project Management Office Chongqing, PRC

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)

Semi-annual Report of Environmental Protection (the first half of 2012)

Chongqing Asian Development Bank Project Management Office

2012.08 Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Table of Contents

1 Project brief ...... 1 2 The semi-annual report description ...... 1 2.1 The environmental semi-annual report during the construction period of Gaoguan town water supply project and Longtan town Youyang county water supply project...... 1 2.1.1 General situation of the project ...... 1 2.1.2 Organization ...... 3 2.1.3 Project progress and environmentally sensitive and environmental standards ... 4 2.1.4 The implementation of mitigation measures ...... 8 2.1.5 monitoring results ...... 22 2.1.6 Training records and public information consultation ...... 27 2.1.7 conclusions ...... 31 2.2 The related environmental impact analysis report on design change of Wubai road in the Fuling ...... 33 2.2.1 The situation and the brief analysis of environmental impact about design change of Wubai road in the Fuling district ...... 33 2.2.2 Conclusions of environmental impact analysis about design change of Wubai road in the Fuling district ...... 38

Chongqing Asian Development Bank Project Management Office 1 Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) 1 Project brief

The range of the first period of “ADB loan in demonstration project of overall construction planning of Chongqing urban and rural infrastructure” include 8 impoverished counties of Chongqing city, the type of the project are the build or rebuild rural roads and drinking water supply system, mainly including 21 road project and 9 water supply project, the total length of the road is 362 km, the capacity of water supply is 72500 t/d. The sub project has been started are the water supply project of Longtan town Youyang county and the water supply project of Gaoguan town Chengkou county. 2 The semi-annual report description

The first half of 2012 semi-annual report main content into two parts: ① the environmental protection status report during the construction period of the two projects have been started: the water supply project of Longtan town Youyang county and the water supply project of Gaoguan town Chengkou county; ② the related environmental impact analysis report of Fuling District Wubai Road design changes. 2.1 The environmental semi-annual report during the construction period of Gaoguan town Chengkou county water supply project and Longtan town Youyang county water supply project. 2.1.1 General situation of the project The main contents of the construction engineering of Gaoguan town Chengkou county wanter supply project and Longtan town Youyang

Chongqing Asian Development Bank Project Management Office 1

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) county water supply project are shown in table 1.

Table 1. The construction engineering profile table of the started sub project Project Construction Construction name site and The main contents engineering Start date Construction design scale ofconstruction Engineering contract period investment Water supply project The The design of The length of the water 59980000 The 1.5 years water the water purification plant and water yuan construction supply supply distribution pipeline is project will sub capacity of about 28.3 km; the main be started project of 30000 m3/d building: water intake, at April 28, Longtan (built 6000 pumping station, match 2011 town m3/d );water wells, Grid flocculation Youyang purification inclined tube sedimentation county plant tank, non-valve filter, clean construction water tank, feeding room, site is located delivery and distribution on the six pipe network, power corner supply, and the retaining Pavilion in wall construction and the right drainage ditch closure bank of construction that can Longtan prevent and control soil Reservoir erosion; water supply for town residents in the range 11.21km2. The The design of The main construction 7683600 The 1.0 year water the water contents include yuan construction supply supply waterworks and water project will sub capacity of supply pipe network be started project of 2000 m3/d; engineering. The plant at March Gaoguan engineering engineering includes water 19, 2012. town water intake wells, water suction pump Chengkou point is room, variable power county located in the distribution room, water end of high pipelines, water distribution river weir, well, chlorination room, water dosing room, Sedimentation purification tank, non-valve filter, clear plant is water pool, factory road, located in the retaining wall, anchor, green mountainside and so on. Water behind distribution network Gaoguan engineering includes water town primary distribution main (branch) school pipe, pipe fittings, about 100 m; infrastructure, road repair, the length of water supply

Chongqing Asian Development Bank Project Management Office 2

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) pipeline is about 13.81 km, water supply for Gaoguanchang town, Gaoguan village, Puchi village, Shuangzhu village, Shili village and Bai village.

2.1.2 Organization The civil engineering of Gaoguan town Chengkou county and Longtan town Youyang county water supply project has formed a complete environmental management organization, responsible for the environmental management during the construction period of civil engineering. The environmental management organizations are shown in table 2. Environmental management plan documents have list in the special conditions of contract of bidding documents as component of the contract. Table 2 The environmental management organization and staff profile of sub project which have started construction Whether through Contact Name of environmental Office staff environmental Title or position telephone management organization name management number ( supervision) training Development and Management ADB office of Chongqing Qian Chen Reform Commission 023-63017266 qualification official Trained by the State Professor, Senior Environmental Consultation expert group Mingpu Hu 13594691447 Engineer Protection Administration External independent The manager of the Trained by the State monitoring organization: company, senior Xinzhong Environmental Chongqing Huijiang engineer of 13983207373 Zhu Protection Environmental Engineering environmental Administration Limited company monitoring Longtan town Youyang county water supply sub project, abbreviated YYLT. Youyang county Environmental Chuanqiang environmental protection Deputy director supervision and 13372791888 Yao bureau management

Chongqing Asian Development Bank Project Management Office 3

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Through the ADB Youyang county project Guangwei Section chief of expert environmental 13594906371 office project office management training Through the ADB Project site manager Chongqing Xinyou Water Yonghua expert environmental of owner unit, 18696977775 Supply Limited Company Shi management training engineer

Chongqing Longhui Construction and Project manager of construction limited Chao Liu environment 13983824969 construction unit company management Chongqing Huaxing engineering supervision Tianxue project director of Supervision Engineer 13272537102 company Youyang Longtan Lang Supervision unit Water Supply Project Office Gaoguan town Chengkou county water supply sub-project, abbreviated CKGG. Chengkou county Environmental Environmental Protection Wei Ju Director supervision and 023-59222621 Bureau management Through the ADB Development and Chengkou county project Xianglian expert environmental Reform Commission 023-59220695 office Guo management training Deputy director

Through the ADB Chongqing Chengkou Water Project site manager expert environmental Jiang Li 13709449100 Supply Company of owner unit management training

Jiangxi Hongfa Roads and Construction and Bridges Construction Wanshou Project manager of environmental 13709449763 Engineering Limited Song construction unit management Company Chongqing Jianghe Engineering Construction project director of Hui Guo Supervision Engineer 13098637655 Supervision Limited Supervision unit Company Wanzhou Branch

2.1.3 Project progress and environmentally sensitive and environmental standards The civil engineering progress, environment sensitive and standards of Gaoguan town Chengkou county and Longtan town Youyang county water supply project are shown in table 3.

Chongqing Asian Development Bank Project Management Office 4

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Table 3 The civil engineering progress, environment sensitive and standards of sub project which have started construction

Civil engineering construction progress description Project The environment sensitive and name Before the semi-annual During the semi-annual report environment report standards The flat field of earth and stone works and the retaining wall has been completed. Since June 17, Sensitive point: 2011 the clean water tank Longtan reservoir, construction has begun; reservoir dam, Since August 12th, the spillway and non valve filter The construction stopped from downstream on the construction has begun; the 2012 Spring Festival to now, Longtan river; river, Longtan Since September 1th, the only in may 2012 the Longtan river town grid flocculation inclined excavation has started and the Longtan reservoir Youyang tube sedimentation tank drainage ditch of the plant belongs to Ⅲ class county construction has begun, started to build, and the earth waters; sound water the above works have excavation engineering environment supply sub basically completed in quantity of 250m3, is used for perform 2 class of project 2011. In addition, the leveling backfill of plant road environmental laying of Longtan town 2 and field. noise standards, air km long water distribution environment pipe network has perform two level completed. The laying of environmental air remaining 26.3 km long standard. pipe network is lagged because of the effect of Youyang county municipal road maintenance Water plant general Sensitive point: engineering, clean water tank from Gaoguan engineering, sedimentation Town Primary tank engineering, chlorine School to the dosing room engineering, water waterworks supply pipe network construction site Gaoguan construction; complete is about 200m and town excavation total volume of scattered residents Chengko 3845.16 m3, in addition to the around the u county nearest backfill, disposed construction area / water 419.42 m3; wherein, the clean field 100m; the supply water tank engineering tributary of Ren sub completed the earthwork river (Yudu river) project excavation volume of 145.72 belongs to Ⅲ class m3, disposed 16.82 m3, waters; sound sedimentation tank project environment completed the earthwork perform 2 class of excavation volume of environmental 326.24m3, disposed 125.8m3, noise standards, air chlorine dosing room environment

Chongqing Asian Development Bank Project Management Office 5

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) engineering completed the perform two level earthwork excavation volume environmental air of 326.2 m3, disposed 125.8 m3, standard. plant smooth engineering completed the earthwork excavation volume of 2760 m3, water supply pipe network engineering completed the earthwork excavation volume of 287 m3, disposed 151 m3.

The figure 1 to figure 3 are pictures of Gaoguan town Chengkou county water supply project and Longtan town Youyang county water supply project respectively.

高观镇 小学

Figure 1. The water purification plant construction site and adjacent environment of Gaoguan town Chengkou county water supply sub project.

Chongqing Asian Development Bank Project Management Office 6

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Figure 2. a corner of pipeline construction site of Gaoguan town Chengkou county water supply sub project.

Figure 3. the building overview of drainage ditch around the plant of Longtan water supply project.

Chongqing Asian Development Bank Project Management Office 7

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) 2.1.4 The implementation of mitigation measures The implementation of adverse environmental impact mitigation measures during the period of Gaoguan town Chengkou county water supply sub project and Longtan town Youyang county water supply sub project are shown in table 4.

Chongqing Asian Development Bank Project Management Office 8 Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Table 4. Potential and mitigation measures implementation summary (2012.1-2012.6) Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts YYLT: Because the construction site adjacent to the Longtan Reservoir, the plan of water pollution control and management has been developed and implemented by the contractor of Longhui company: developed operation plans, improve the corresponding management system and regulations, standardize operations, improve labor efficiency,

refine responsibility, achieve the purpose of system management, system constraint; The temporary toilets, septic Huaxing supervision company also pay attention to the daily supervision, to ensure the tank and the surrounding The illegal construction camp sewage enters the Longtan town sewage pipe network, the domestic ditch set up in all the emissions of life sewage of construction site enters the septic tank; before use the vacated site at the end of construction camp must clear sewage from the construction stage, all the garbage must be transferred to Youyang county sewage landfill off or get out of the construction camp site. construction site after A small amounts of hogwash produced by construction camp living facilities is given to transferred all the rubbish nearby villagers used as pig fee.

CKGG: Construction workers are all local residents, no construction camp and corresponding accommodation facility is constructed; the life waste water produced by construction workers put in toilet, using as farmyard manure, no sewage discharged, no impact to environment. YYLT: Because the construction site adjacent to the Longtan Reservoir, the management The impact of system and regulations system of machinery maintenance and repairmen is developed by waste water the contractor of Longhui company, normative operation, refine responsibility, washing Water produced by vehicle and cleaning equipment near the reservoir spillway side is strictly prohibited; construction Huaxing supervision company also took note of the daily supervision; the production excavation, car Build sedimentation tanks, wastewater in construction site should be treated by sand settlement and site percolation washing, grease traps to collect and up to standard before discharged; all the waste water is patrolled and monitored, so there maintenance of treat wastewater. is no adverse effects to the downstream receiving waters of Longtan River, the water can concrete and still meet the requirements of class III water quality standard. machinery repair CKGG: The construction residual water and waste water of site cleaning, pipeline laying, and so on to the concrete modulation, construction and installation engineering: a primary treatment pool receiving water. (the pool with a total length of about 4.5 m, width 1.5 m, the effective depth of sedimentation tank is 1.5 m) was set near the aggregate washing field, the wastewater is

Chongqing Asian Development Bank Project Management Office 9

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts collected into the primary treatment pond used the obvious ditch during the construction, sediment sand will be treated by artificial regularly. As a result, the day treatment of the primary treatment pool can meet requirements of concrete wastewater treatment, and the SS concentration in effluent is less than 70 mg/l. The emission of various kinds of wastewater can meet the first grade discharge standard of " integrated wastewater discharge standard " (GB8978-1996) after the environmental supervision personnel on-site investigation and monitoring.

YYLT: Vehicles of loading sand and stone are covered with tarpaulin; The vehicles should be decelerated at gale dry season; The import site vehicles of One side of the connecting band site of construction site and municipal road is covered loading transport oil, sand or with 50 m of gravel, avoiding the vehicle with mud on the road form dust to lead second other bulk materials are pollution; covered with tarpaulin; the Clean the channels at least two times a day in site; vehicles get out of the Keep the municipal road adjacent to conservation site clean and without dust; construction site with the Up to now, the environment of construction site and the surrounding area is clean, the air mud on the wheel will be is good, odorless and tasteless, the masses are satisfied. The generated washed; sprinkle in CKGG: ① Set the enclose or safety protection distance around the dust facilities such as Gasses dust construction site, clean the mortar mixer; ② Do hardening treatment for site road and material stacking sites; for the channel two times a day, keep powder materials such as yellow sand and cement, special storeroom is set to stack broken the transport vehicle of the package, clean the break package and cement drop to the ground in time, and avoid contractor, subcontractor or constructing in gale weather; ③ Strengthen management, civilized construction, building supplier, roads and walkways materials, light load and life the building materials; vehicles will be washed before leave clean, clean the vehicles, the site to remove the soil adhered in the surface; the vehicles that easy to produce dust of roads and walkways regularly; loading lime, sand stone materials, cement, fly ash should cover sheeting; ④ to reduce the dust of the construction site and construction road in time through the sprinkler and sweeping measures in time.

Chongqing Asian Development Bank Project Management Office 10

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts To ensure the normal running of the vehicle to reduce exhaust emissions; Maintain YYLT: The inspection and maintenance of construction machinery such as vehicles and the machinery and equipment tower crane inspection should be institutionalized, in order to ensure the vehicles and to energy saving and high mechanical equipment running safely and high efficiency, the vehicles will be inspected Air pollution from efficient operate, large yearly, the tower crane will be maintained, inspected and certificated regularly vehicles and horsepower equipment will CKGG: Strengthen the use management and maintenance repair of the construction equipment be installed in exhaust gas machinery, reduce the exhaust emissions from fuel mechanical, and reduce its adverse purifier to ensure compliance effects to a minimum; the living stove of construction workers use natural gas or liquefied with the emission standard; gas as fuel, in order to reduce the adverse effect on the environment. the processing equipment will be check and authenticate regularly; Ensure the noise level of the YYLT: The following measures are adopted equipment conform to the 1) The construction machinery such as tower crane and so on are low noise equipment; noise limits for construction 2) The construction site is far away from the sensitive points of sound environment such as site (PRC-GB12523-90);Noise hospital, school, centralized residential areas and so on; equipment should be far away 3) All construction activities of noise are stopped between 22:00 to 6:00; the noise sensitive area such 4) The retaining wall that have been completed and the other side of the barrier are used as schools, hospitals and to limited noise; The vehicles and residential areas as far as 5) The transport vehicles will slow down and whistle as little as possible when go through Noise construction possible, if it could not be the residents point; machinery noise avoided, sound insulation 6) The vehicles are maintained effectively, and do not take risks when go out. facilities such as temporary CKGG: (1) The scientific construction plan is formulated, avoid high noise equipment used tailgate and retaining wall at the same time; the construction schedule of equipment with large noise, shock should be set up; if there is resistance and accompanied by strong vibration is arranged in the daytime, the noise of residential area around the construction equipment near the Gaoguan Town Primary School avoiding school hours as construction site 200m, all the far as possible; if it needs continuous 24-hour operation because of the process, the noise construction activities construction unit should apply approval formalities to the local environmental protection will be stopped between bureau in advance, and post notices at conspicuous place of the site, do the propaganda

Chongqing Asian Development Bank Project Management Office 11

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts 22:00 to 6:00. and explanation work, ensure that the public has avoidance or prevention time, and seek public understanding; (2) The low noise equipments are used as far as possible, for example, hydraulic machinery can be substituted for fuel machinery, high frequency vibrator is used, insulation facilities are set at concrete mixing station; (3) Reduce anthropogenic noise: construction workers operate machinery and equipment according to the rules strictly, comply with the operating rules in the process of dismantling the baffle and trestle, reducing the impact noise.

YYLT: There are Longtan reservoir management room and staff quarters of original water plant around the construction site, especially drinking water source protection: Longtan Reservoir and it’s dam, therefore, the construction units strictly limit the operation of The excessive vibration heavy vehicles and equipment; there is no vibration operation such as blasting and so on, operation of heavy vehicles Vibration and not only protect the reservoir management room and water plant staff quarters, but more and equipment will be blasting important, protect Longtan reservoir and reservoir dam form the effect of vibration, to Limited in sensitive building preserve and protect the reservoir and dam safety. and near the residential area. CKGG: There will be no major vibration operations such as blasting and so on, in order to ensure the safety of Gaoguan town primary school and scattered residents around construction field. The contractor provide proper waste storage YYLT: There are garbage collecting barrel and garbage can in construction site provided container; spraying with by construction units, and sprayed with pesticides regularly, to reduce flies, mosquitoes insecticides to the garbage and mouse harm, and the number of summer spraying insecticide will be increased; collecting box regularly, to Solid Construction Trash, garbage box are far from the Longtan Reservoir spillway; reduce the flies, mouse harm; waste camp trash And the garbage will be transported to Youyang county landfill by vehicles to disposal; the waste is stored away from CKGG: There are garbage collecting barrel and garbage can in construction site, the water, and will be transported domestic garbage send to Gaoguan town garbage disposal field about 5km after unified to the municipal or collection. environmental protection administrative department

Chongqing Asian Development Bank Project Management Office 12

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts designated location to be filled; According to the garbage disposal, make sure the dump site of administrative permission clearly.

YYLT: There is no other building garbage except the earth and stone during Longtan water supply civil engineering construction period, the civil construction would achieve the The construction waste which digging and filling balance as far as possible, earth excavation would be used synthetically Waste of could not re-use is as far as possible, and disposal on the spot, in order to fill the depression of purification Construction and transported and treated water plant main facilities near the Longtan reservoir spillway side, and to form a new

demolition waste regularly, it is not allowed to smooth site, this can be used as construction land of dosing room and other auxiliary products long-term cumulative stack in facilities, saving land resources; the field; CKGG: According to a reasonable, economic principle, the stopped slag dam is constructed on spot and low-lying land is used to stack waste slag, the excavated materials are used as construction backfill material as far as possible, to reduce remote exploitation.

YYLT: The earthwork excavation would be used synthetically as far as possible, the using for ground leveling embankment: the civil engineering excavation with a total volume of The storage field or discarded The erosion 10651.97m3, retaining wall embankment with a volume of 4045.81m3 , the rest 6606.16m3 Soil soil field is build before dump produced by is used for ground leveling soil of public facilities; erosion waste slag; protect the waste residue, Construction units and supervision units are forbid to fell and damage the surrounding and vegetation around the quarry, borrow forest vegetation, the vegetation surrounding construction site is retained in a good ecological construction site; soil field condition;

CKGG: Construction waste soil, waste slag: stack in the low-lying place of 200m of the plant, the capacity the discarded soil field is about 20000m3.

Chongqing Asian Development Bank Project Management Office 13

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts The culverts with sufficient size are constructed on the foundation drainage line which calculated in the catchment area; the YYLT: The intercepting drainage drains that can withstand floods are constructed on both intercepting ditch is sides of the retaining wall, the length of intercepting drain that has been constructed is constructed beside the 170m; the intercepting drainage drain outside the retaining wall can collect and discharge permanent road of the the surface runoff of water catchment area; the upstream surface of permanent drainage mountain to collect and outlet is build by erosion resistant stone, to fight against the scour of discharge surface discharge the surface runoff; runoff to channel, preventing burst and form erosion of large bodies of water; Drainage control The permanent drainage

outlet of the road is CKGG: In the temporary dumping area, the surface soil that easily to produce erosion is constructed in the area that placed in the middle of the site, the stone generated from the excavation piled up around the excess water will not it, this can play temporary blocking role, and the temporary dumping area is treated by damage the environment of slope protection and surrounding drainage, to prevent soil erosion of soil side slope as far the bottom of the slope, the as possible. upstream face material of the drainage outlet and the construction quality are strengthened;

The topsoil of temporary YYLT: The topsoil of the site is stored temporarily as the future green covering soil of the storage in all sites is removed; site; the new retaining wall and water intake, diversion canal play intercepting ditches and construct intercepting ditches drains, the surface runoff collected on hillside could not enter the site, the surface runoff is and drains, to prevent runoff discharged into Longtan River in the downstream after guide and shunt, because there is The erosion of flow into the construction no pollutants enter the surface runoff after guide discharge, it won't create pollution to construction site site, and diverted the runoff Longtan River on the downstream; to the drainage system or At the same time, strengthen the construction site supervision at rainy season; clean the temporary storage pool; site sand and the gravel in the construction walkway pad timely, slowing down soil erosion; The construction site is Because the project has not yet completed, the recovery and green of the construction site

Chongqing Asian Development Bank Project Management Office 14

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts restored to grassland, will be implement in the later stage of the construction of Longtan water supply sub woodland or farmland, project; farmland after completed; CKGG: Avoid construct in the storm in waterworks site leveling project area, remove the waste soil and prompt timely, the backfill earth and stone treated by measures of layered compaction; try to excavate a section and backfill a section when excavate the pipeline trench, and clean the timely excess soil timely;

According to the state forest law, the project implementation agencies will be in charge of forest vegetation compensation with an equal or greater area; select the local species of YYLT: The project has not yet completed, the recovery and green of the construction site survival adaptation to restore will be implement in the later stage of the construction of Longtan water supply sub the vegetation; project; maintain the growth of plant But measures will be taken to strengthen protection of the surrounding affected The affected area during the operation period; vegetation; vegetation according the principle of CKGG: The project has not yet completed, the greening work around the waterworks and restoration plant growth cycle from short water distribution pipe overburden will be carried out after the construction is completed to length to restore the as soon as possible, restore and reconstruct the vegetation timely, to make sure the slope vegetation, the green is stable, and the rock, soil is not exposed; prohibit to cut or damage the surrounding coverage following the vegetation during the construction period. combining point principle, the herbs with short growth cycle and large coverage area should be planted priority, then the proper planting shrubs or trees are planted

Chongqing Asian Development Bank Project Management Office 15

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts appropriately; the road which take the noise control measures during the operation period, will be restored to a sound proof belt composed of trees and shrubs. society YYLT: Longtan water supply construction units and supervision units pay more attention to cultivated land protection, and survey the construction site with design departments and proprietor (technical staff of Xinyou company) before enter the construction site, the area of construction is approved by the homeland department and Longtan town administrative Control the green belt width department before construct, at the same time, make the control of area as a system and Cultivated land strictly if it is farmland one of important assessment and rewards and punishment indexes, so as not to cause protection surrounding the construction social disputes. site. CKGG: The water purification plant construction field should be confirmed by Chengkou county or Gaoguan town land departments and the adjacent village primary school, confirmation before construct, not only can protect the farmland, but also avoid social disputes. According to the resettlement plan, compensate all the affected residents timely and effectively, and pay particular YYLT: There is no immigrant in the area of Longtan water supply projects, so it will not be attention to the improvement completed; Immigration of effect for vulnerable groups CKGG: There is no immigrant in the area of Gaoguan water supply projects, so it will not be and the females; completed; environmental protection measures after emigrating: garbage treatment, drinking water, air, noise monitoring

Chongqing Asian Development Bank Project Management Office 16

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts and health

YYLT: Construction units and supervision units will make the safe production institutionalization and standardization, and responsibility to the post; set temporary traffic management in vehicle entrance of construction site; guide the construction vehicle Select and manage the entry, do not impede the municipal road vehicles or pedestrians society as far as possible, temporary road or walkways at the same time ensure safety production; to reduce traffic problems; In the period of morning, noon or night, with more vehicles and pedestrians, organize Traffic control shunt or limit construction personnel to inspect and guide the road adjacent to the construction site, separate the traffics during the peak people and vehicles as far as possible, while maintaining the municipal road is open to period; traffic, and guarantee the construction vehicles entry construction site safely; CKGG: Construction vehicle do not transport at night, the vehicles would slow down and reduce whistle via Gaoguan town primary school and neighborhood of scattered residential. The contractor is required to YYLT: Strengthened sanitation supervision and management of the construction site and ensure the sanitation of camp, seal the boiling water bucket tightly to prevent dust, mosquitoes and flies pollution; construction camp, including The workers are equipped with uniforms, helmets, canvas gloves, masks and other basic The health and the quality of water supply; labor health and safety supplies; tower crane operated according to rules strictly, the staff hygiene of work Ensure personal protective cannot stay in area of tower crane construction; area equipment and other health All equipment, raw materials in the construction site are orderly storage, prohibit to stack resources in all the debris in construction site channel, in order to ensure the safety of construction personnel; construction sites in order to There is no labor health and safety accident happened up to now; create a safe working The HIV / AIDS prevention campaign is being prepared actively under the support of city

Chongqing Asian Development Bank Project Management Office 17

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts environment; project office; Require the construction site CKGG: Strengthened sanitation supervision and management of the construction site and accord with national safety camp, seal the boiling water bucket tightly to prevent dust, mosquitoes and flies pollution; regulations; The workers are equipped with uniforms, helmets, canvas gloves, masks and other basic According to the strategy of labor health and safety supplies; Safety warning is set between waterworks construction “prevention first, publicity area and Gaoguan Town Primary School and Sending someone on duty to prevent students and education, mobilize the Straying construction area. whole society to participate, to carry out integrated management” to prevent and control the AIDS;

YYLT: Under the guidance of Chongqing City PMO and Youyang County Project Office, the suspected artifacts protection regulations have been drafted before the construction team Protect cultural heritage of enter the site: whenever the unidentified objects were found during the earthwork valuable is determined, it construction process (excavation, embankment, waste disposal), should immediately stop does not allow anyone to the construction, maintenance field, immediately report to the Construction Project Office, disrupt, fouling, concealed or organized protection immediately by the project office, and reported to Youyang County, damage antiquities with other the construction would be continued when it is allowed to after the unidentified objects ways according to state are identified by Cultural Relics Administration, during the period of cultural relics Cultural heritage regulations; protection, construction unit can arrange other works without affecting the protection

protection If important sites have been and identification of suspected artifacts; excavated, the construction So far, there is no suspected artifact has been found in the construction site. must be stopped immediately CKGG: The suspected artifacts protection regulations have been drafted before the and report to district, county construction team enter the site: when the unidentified objects were found during the or city and consult reasonable earthwork construction process, should immediately stop the construction, maintenance solution; field, immediately report to the Construction Project Office, organized protection immediately by the project office, and reported to Youyang County, the construction would be continued when it is allowed to after the unidentified objects are identified by Cultural Relics Administration, during the period of cultural relics protection, construction unit can

Chongqing Asian Development Bank Project Management Office 18

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Youyang Longtan water supply (abbreviated YYLT), Chengkou Gaoguan water supply Water supply sub project Influence (abbreviated CKGG) factors Environmental Mitigation measures Implementation impacts arrange other works without affecting the protection and identification of suspected artifacts; So far, there is no suspected artifact has been found in the construction site.

Chongqing Asian Development Bank Project Management Office 19 Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one) Semi-annual Report of Environmental Protection (2012.08)

From the table 4 it can be known that, every mitigation measure for the environmental effect is being implemented effectively in the construction site of Longtan, Gaoguan water supply project, the effects of environment management and water source protection of construction site are remarkable. The domestic wastewater of Longtan water supply construction site is disposal uniformly after use the drainage pipe network of the original waterworks (6000t/d) to access to Longtan town sewage pipe network, there is no construction wastewater or solid waste emissions on site; the small amount of domestic sewage in Chengkou Gaoguan water supply construction site is discharged trough the municipal sewer ditch nearby; the impact of construction noise and exhaust on the adjacent environmental is low, the building materials temporary storage and safety protection measures are in place, achieved safe and civilized construction. Longtan water supply use the waste rock of drainage ditch construction excavation to construct nearby plant area road, the waste rock of the Chengkou Gaoguan water supply purification plant construction and laying water supply pipeline excavation is backfilled nearby or disposal and use, in this way, the waste rock and concave ground can be fully utilized, and the environmental effect and ecological destruction which caused by chose other spoil ground are also prevented, reduced the load of existing spoil ground of town. Compliant with the requirement of soil and water conservation "suit one's measures to local conditions, comprehensive prevention and control, practical and beautiful", "water and soil conservation technical specification of development and construction project" (GB50433-2008)

Chongqing Asian Development Bank Project Management Office 20

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) As shown in table 4, various environmental impact mitigation measures are implemented effectively in the construction site of the water sub-project of Longtan and Gaoguan, the environmental effect environment management and water source protection and so on is remarkable. The life sewage in the construction site of Longtan water is treated together by taking drainage pipelines of the original water plant(6000 t/d) connection with the sewage pipe network of Longtan town . There is no construction waste water and solid waste to be discharged in the construction site; A little sewage of in the construction site of Gaoguan in Chengkou water is discharged through municipal sewage ditches; The influence of construction noise and waste gas on the environment is very small, and temporary storage of building materials and safety protection measures are taken in place, so the safety and civilization construction is done. It build factory road using the abandoned soil and stone of drainage ditch excavation in the Longtan water engineering. In the Gaoguan water engineering, the abandoned soil and stone of the construction of water and laying pipelines excavation are disposed or near to backfill, make full use of the abandoned brick and concave ground , and prevent the effect on the environment and ecological destruction from alternating abandoned clay, reduce the load of abandoned clay of the town. It meets requirements of " adjust measures to local conditions, comprehensive prevention and control, practical beautiful " in the《the soil and water conservation technical rules of the development and construction project》(GB50433-2008) .

Chongqing Asian Development Bank Project Management Office 21

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) 2.1.5 monitoring results

2.1.5.1 external monitoring On March 28, 2012, the contract of the first period of external environment monitoring of chongqing urban and rural infrastructure construction demonstration projects from ADB loans was signed. External independent environmental monitoring unit is chongqing Huijiang environmental protection engineering Co., LTD. Because the construction of drainage ditch in the Longtan water engineering is on and off since it was stepped in May this year, external monitoring of it is not synchronized, it has not been monitoring. So the half-annals only submitted external environment monitoring near the construction site of Gaoguan water engineering. The adjacent external environment monitoring results and its brief analysis of the sub-project are shown in table 5 ~ table 7.

Table 5 External environment monitoring reports for surface water of water project in the construction phase Monitoring unit: Chengkou environmental monitoring stations

Monitoring Monitoring details values (unit Baseline Engineer :mg/L) or ing Standard situation, Monito Projec backgro activities overweight ratio, ring Stand t Monitorin rang und during further mitigation sampli time ard name g e valuesof monitori measures and cost ng and average parameter value environ ng estimates sites frequen s ment cy

pH(note) Sectio / 7.51 6~9 8.26

Gaog NH3-N n of May 20, / 0.08 ≤1.0 0.57 civil Meet the Ⅲ water uan BOD5 downs 2012, / 0.22 ≤4.0 3.3 construc quality standard of water CODcr tream once, / 10 ≤20 2.62 tion of 《the surface water engin petroleum in each ≤0.0 water environment quality / 0.05 0.045 eering type 200m one 5 plant standards》

Chongqing Asian Development Bank Project Management Office 22

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) in away sample and (GB3838-2002) , Cheng from water the water kou discha pipeline environment rge of network quality is better. constr uction waste water into Yudu rivers note:pH is dimensionless.

Table 6 External environment monitoring reports for noise of water project in the construction phase Monitoring unit: Chengkou environmental monitoring stations

Monitoring Baseli Monitoring details values (unit ne or Enginee :dB,A) backg Standard ring Monit roun situation, activitie Project oring rang standar d overweight ratio, Monit s during name time e d value further mitigation oring samplin avera monito and valu sof measures and cost param g sites ge ring freque e envir estimates eters ncy onme nt constru Meet 51.1~ ction theⅡstandards of day / 55.6 ≤60 56.3 peak of 《the standards

civil for acoustic Gaogua May constru environmental n water Gaguan 20, ction quality》 engineer primary 2012, and (GB3096-2008) , ing in school once 40.2~ pipe the sound Chengko night / 43.2 ≤50 45.5 laying environment u of quality of the water project is good. plant

Table 7 External environment monitoring reports for health and disease of water project in the construction phase Monitoring unit: Chengkou sanitation and antiepidemic station

Chongqing Asian Development Bank Project Management Office 23

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Monitoring values (unit: Project Monitoring details a number of name infectious diseases ) Engineering Health and disease status , Monit activities during further mitigation measures oring rang Monit monitoring and cost estimates time e oring samplin avera and valu param g sites ge freque e eters ncy

Constru Health ction No emigrant; Inspect , clean site, environmental hygiene of water Gaogua construction camp regularly,and ensure supply n protective equipment and Gaoguan , primary construction May other health resources of water medic school peak of civil 20, construction personal; engineer al and / 0 construction Prevent and control AIDS 2012, ing in consul scattere and pipe laying according to the strategy of once "prevention first, publicity Chengko tation, d of water plant education priority, the whole u AIDS residen society participation by aware ts of mobilizing, and ness adjacen comprehensive t management" in the project.

As shown in table 5 ~ table 7, the environmental quality of surface

water and noise near the construction site is consistent with baseline

values, and can meet the requirements of environmental standards of

the relevant function area. The performance of the pollution slowdown

measures from environmental management plan laying down is good,

and the influence of construction of water sub-project on environment is

very small. In addition, prevention measures of health and disease of

construction site from the environmental management plan are

Chongqing Asian Development Bank Project Management Office 24

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) implemented basically, and construction workers and the public of

surrounding are in good health. 2.1.5.2 internal monitoring

According to the content of the construction unit providing, the

internal monitoring on implementation and effect of slowdown

measures is shown in table 8. Table 8 The brief of the internal monitoring on implementation and effect of slowdown measures

The main Potential The brief of the internal Responsibility project stage project environmental monitoring on institutions content impact implementation and effect of slowdown measures soil-rock Influence on the Ecological protection was YYLT: Chongqing excavation ecological payed special attention in Longhui environment the soil-rock excavation, it construction Co., around the took the engineering LTD.; construction measures of building CKGG: site gravity retaining wall, hongfa which can ensure the construction safety in construction and engineering of ecological environment road and bridge such as surrounding Co., LTD vegetation, soil and so on. construction Civil structure The influence of YYLT: Using the concrete Ditto stage construction construction products; with a few dust self-stirring mortar, no self-stirring concrete, and almost no dust in the construction site; CKGG:Reducing dust in the construction site by covering and blocking ; Mechanical The influence of YYLT: There is no sound Ditto construction construction environment sensitive and vehicles noise point such as hospitals, transportatio schools, residential area

Chongqing Asian Development Bank Project Management Office 25

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) n and so on in the adjacent of construction site ; Machinery equipment is low noise equipment in the Longtan water civil engineering , and being blocked with slope of two sides, so there is no noise nuisance phenomenon. There is not any complaints so far; CKGG:Machinery equipment is low noise equipment in the Gaoguan water civil engineering, and don't work for noise during schooling and residents having a rest, so there is no noise nuisance phenomenon. There is not any complaints so far; Construction The influence of Setting desilter for Ditto waste water rivers construction waste water, downstream very few drainage infiltration into the land and into the downstream river after filtration. So there is no obvious influence on the water quality of downstream river with no pollution; Abandoned Soil and water Abandoned soil and stone Ditto debris loss from are disposed in the site as disposal abandoned clay far as possible, the remaining soil and stone are all for Exalting site , almost no bad ecological influence; Pay attention social influence There are some staff of Ditto to minorities minority(tujia and miao) and women's in the construction site. employment YYLT:21, CKGG:20; women workers are used in their abilities YYLT:8,

Chongqing Asian Development Bank Project Management Office 26

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) CKGG:12; These reflect national unity and social harmony; vibrate Reservoir, the Heavy vehicles and Ditto dam or civil equipment are strictly building limited into the site; No blasting vibration work, YYLT: No adverse effects on the safety of Longtan reservoir and dam ; CKGG: No adverse effects on the safety of civil building .

2.1.6 Training records and public information consultation

(1) Improvement of capability and training

The CPMO have some trainings to personnel of the construction units and supervision unit by explaining and information communication in the construction site, in order to improve the environmental protection consciousness and practical ability. The first ability enhancement and training for environmental protection and future arrangement of

Gaoguan water in Cengkou are shown in table 9 and figure 4.

Chongqing Asian Development Bank Project Management Office 27

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

Figure 4 Consulting experts have a training for the sub-project of Gaoguan water in Chengkou

Table 9 The first ability enhancement and training for environmental protection and future arrangement Organizer Time Place Participants Training content s project 16 persons constructi office of from consulting Consulting experts from CPMO explain that it on Hongfa experts of should execute in the regulations of ADB and 2012.6. supervisio company CPMO, environmental management plan in the 4 n office of and Hongfa construction period of sub-project. Gaoguan Jianghe company and

water company Jianghe company Environmental experts from CPMO explain it about The following the water source protection; Discussion about

is to do HIV/AIDS prevention of construction sites and construction camps. The project manager of construction unit explain the function of main body system and supporting system of water plant, and the matters needing attention about environmental protection in the construction; Invite technical personnel from supervision unit to explain the environmental supervision requirements in the construction.

Chongqing Asian Development Bank Project Management Office 28

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08)

(2) public information consultation

According to the requirement of ADB public information consultation

on informing major construction activities in advance , at the same time

of project construction, The construction unit of the sub-project of

Gaoguan water engineering (Hongfa company) often makes the publicity

of construction information in the place where the public often goes to

go, and promises to do well in the environmental protection work in the

construction period by being closely cooperate with local village

committee and Gaoguan primary school .

The brief of public consultation activities since the sub-project of

Gaoguan water engineering started is shown in table 10.

Table10 The summary of public consultation

Public Consultation Treatment and consultation Sub-project questionnaire or forum Practical visit and discussion reply of public range of the public opinion

Chongqing Asian Development Bank Project Management Office 29

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) the the public of the development period The project is under sub-project influence of the project: construction, and the of Gaoguan scope of The public of eia and telephone hotline water Gaoguan the public consultation (023-59220695)has been engineering water were taken from January setted up, the public opinion in Chengkou engineering 15 to March 1, 2009; is listening from phone at

in the Conclusion: present.

construction Support the For the potential effects of Xinyou company period construction and water pipe network on is negotiating and and operation of the project. highway (from Longtan to consulting with operation Zhongduo in Youyang city ), it traffic

period requires that the pipe management network lays away from the department in highway. Youyang.

the Youyang The sub-project is not to operation period. When it is in sub-project traffic the running period, then it invite relevant public of Longtan managemen discussion and communication. water t engineering department in Youyang

As far as the date of this report, there is no public information

feedback about Gaoguan water engineering in Chengkou, therefore

there is no results of treatment and reply.

The pipe laying of Longtan water engineering in Youyang has been

completed, and the main pipe is 6 km. Youyang traffic management

department considers that the potential effects of water pipe network

on highway (from Longtan to Zhongduo in Youyang city ) , and requires

that the pipe network lays away from the highway. At present, Xinyou

company is consulting with traffic management department in Youyang,

Chongqing Asian Development Bank Project Management Office 30

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) and the reply of relevant public information consultation will be reported in the next half annals report.

The public consultation shows that the public support the implementation of the project, and hope to be built as soon as possible, in order to enlarge the benefit scope of safety drinking water. In addition, the degree about public consultation of Longtan water engineering in the earlier stage is not enough, it should be improved in the future.

2.1.7 conclusions

Since it started to construct in April 28, 2011, Only PE pipes are acute shortages of market supplies, the civil construction schedule of water plant is normal and to be completed in the civil engineering of Longtan water engineering; The construction schemes and progress of pipe network laying is to adjust.

Since it started to construct in March 19, 2012, the civil construction schedule of water plant and water pipe network laying is normal.

Environmental management plan is implemented basically in the civil construction of Longtan water engineering and Gaoguan water engineering, the main performances are as follows:

There is a complete environment management institutions to follow the tracks of environmental management in the whole process;

The special terms of the environment management plan and

Chongqing Asian Development Bank Project Management Office 31

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) slowdown measures about the adverse environmental impact are efficiently implemented in the contract, and get good results. There are no waste water and solid waste to be disposed disorderly or discharge, and no construction dust, smoke and noise interference phenomenon in the construction camps and construction site, The overall quality of environment is better in the construction site and its surrounding; The abandoned soil and stone of construction are comprehensive used as the fill of exalting concave ground as far as possible, and improving the use efficiency of land resources. It meet the requirement of water and soil conservation" adjust measures to local conditions, comprehensive prevention and control, practical beautiful " in the《technical rules of soil and water conservation in the development and construction project》

(GB50433-2008) ;

Construction unit made the interior monitoring of the construction site within the range of its ability, supervision unit made the relevant environmental supervision report in its monthly supervision report;

The public investigation about the water sub-project was taken in a certain range at the earlier stage of the project, the results show that the public support the implementation of Longtan and Gaoguan water engineering and hope that the benefit of sub-project is realized as soon as possible; The traffic management department of Youyang requires that the pipe network lays away from the highway. Xinyou company is

Chongqing Asian Development Bank Project Management Office 32

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) negotiating and consulting with the related departments .

The construction units, supervision unit and owners of the project shall lay down following system and implement programs to the slowdown measures needing to be improved, in order to take the environmental protection smoothly and develope further in the next stage of Longtan and Gaoguan water engineering .

2.2 The related environmental impact analysis report on design change of Wubai road in the Fuling district

2.2.1 The situation and the brief analysis of environmental impact about design change of Wubai road in the Fuling district

The main engineering content of design changes related to the environment includes the road level, length change and roadbed width change in the chongqing urban and rural infrastructure construction demonstration project from ADB loans—Wubai road in the Fuling district project. The main change and comprehensive analysis of related environmental impact are shown in table 11; Soil and water conservation and the setting of related abandoned clay are shown in table 12 and table13 .

Table11 The main change and comprehensive analysis of related environmental impact about Wubai road

Chongqing Asian Development Bank Project Management Office 33

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Road Original Analysis of Comparison design comprehensive analysis of expansion change items after environmental impact after change design quantity change Road level of Level 2 Level 3 investment For the old road can meet the expansion saving, demand of plane curve and vertical technical slope, reduce a large of excavation and and backfilling, decrease the number economic of new land. The adverse effect of feasible road along and around on social environment and ecological environment is small. Design speed 60km/h 30km/h Improved The transportation and the villagers' road safety production and life both are satisfied at the same time,which will be helpful for the social harmony and stability. Roadbed width 8.5m 10.0m Widen local The width of Existing roadbed is 8 to roadbed 12m; Can make full use of the existing road. Length of road 14.210km 15.997km For road The extending change of the three extending, sections (k0 +280 ~ 840, k8+ 020 ~ the road 380 and k14 + 880 ~k15 + 996) are grew 540m , 360m and 1080m respectively; 1.787km There is no environment sensitive after point such as residents , water source change site and so on along and surrounding the extending. Make full use the Can make The main The negative influence on ecological of existing roadbed full use body of the environment and landscape roadbed, of the project environment along the existing road is reduce existing reduced small, reduce the damage to engineering road new land vegetation and the loss of soil and permanent cannot be water, and avoid the secondary covers used. disasters such as landslides and debris flows from local high slope easily inducing.

New land area cultivated Cultivated Reduced The treatment to part of excavation land land 5.85 cultivated slope changed from natural slope to 43.22 mu; land and add the retaining wall and slope mu ; barren forest land governance. After the change, the forest hills 39.94 of being overall new requisitioned land was land 73 mu occupied reduced from 116.22mu to 45.79mu, mu and the influence on ecological

Chongqing Asian Development Bank Project Management Office 34

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Road Original Analysis of Comparison design comprehensive analysis of expansion change items after environmental impact after change design quantity change environmental along the existing road was decreased; For cultivated land and forest land of being requisitioned reducing, adverse social environment and the cost of corresponding mitigation measures is small. Temporary Fail to 10 places The main The total area of abandoned clay covers of consider of wasteland along the road is 5.14 hm2. Setting a abandoned abandone used gravity dam of blocking slag with dry clay (shown d clay by stone, covering and greening in the in table 3) rolling up later construction. Excavation 307800 505400m3 The The extending excavation quantity of quantity of soil m3 comprehen the three sections (k0 +280 ~ 840, k8+ and stone (without sive 020 ~ 380 and k14 + 880 ~k15 + 996) consideri quantity of are 56900m3, 7900m3 and 7100m3 ng the excavation respectively. excavatio was n of high reduced cut after slopes) change. Filled quantity Fail to 218100m3 / The extending filled quantity of the of soil and consider three sections (k0 +280 ~ 840, k8+ stone 020 ~ 380 and k14 + 880 ~k15 + 996) are 12000m3, 9700m3 and 2700m3 respectively. Green seedling Fail to 6600 Both sides Strengthen the soil and water consider along the conservation, enhancing the road landscape quality Social Does not According Help to Moderate widening road and reducing environment consider to 《the improve the design speed , which can make full that the technical service level use of existing 8 to 12 m roadbed flow of standards of Shijiagou width, improve passenger cars traffic large of highway scenic spot capacity, and then be convenient to cars is engineerin and the villagers of Wulingshan village and accounte g 》, roads Wulingshan along it for the production ,living and d for 61% can be forest park travel, and be helpful for the social in the moderate in the harmony and stability. overall broadened Fuling flow of . district.

Chongqing Asian Development Bank Project Management Office 35

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) Road Original Analysis of Comparison design comprehensive analysis of expansion change items after environmental impact after change design quantity change the road. Table 12 The analysis form about soil and water conservation scheme of Wubai road

scheme Analysis about soil and water conservation 一、The main body of the project The route of the road is The route of the road does not exist restrictive factors, reasonable and the expansion of feasible. existing road (1) The project area is not in areas of easy taking debris , land-collapsing , easy cause serious soil and water loss , ecological deteriorating area, water and soil conservation monitoring site in the national water and soil conservation monitoring network, key testing area and long-term positioning observatory of soil and water conservation designated by the state. (2) The existing road avoid the ecological fragile area, the key prevention reserve area of soil and water loss and the key results area of treatment ; (3) Minimize the cultivated land occupied, be maximum to protect the existing vegetation and the soil and water conservation function; Settinng 10 abandoned (1) Abandoned clay is not setted in areas of land-collapsing and debris clays near and along flow landslide with the people's government above the county the road (shown in noticing; table 3) (2) The distance is short, the loss is small in the transportation of abandoned soil and stone; (3) Both using depression nearby and not affecting drainage of slope surface. From the comprehensive analysis of terrain, type of covers, whether impact the flood , the location and scale of abandoned clay is reasonable. Don't set a yard; Use (1) Don't set a yard, the excavation can meet the needs of filled; the expansion road and (2) Not build new construction transportation roads. The design the existing villages scheme reduces the disturbance from source surface, and controls the road as the new quantity and area of soil and water loss . construction pavement. Slope protection of (1) The slope of roadbeds side takes the constant heavy type retaining roadbed wall to protect; (2)The slope of excavation takes the jet concrete of hang nets to protect. All are effective and mature control technology of soil and water loss of the slope . Surface drainage of (1) Set 51 culverts ; (2) Set side ditch, drainage ditch and cut ditch in roadbed two sides of the highway , and all these ditches are setted according to defense standards of heavy rain amount once 50 years in a 24 h, meet

Chongqing Asian Development Bank Project Management Office 36

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) scheme Analysis about soil and water conservation the defense standard requirements of rain amount once10 years in a 24 h in the《soil and water conservation technical rules of development and construction project》(GB50433-2008). The designs of tunnels and drainage all take effective and mature drainage technology by using roadbed drainage to protect the roadbed from hydraulic flushing. The green on both sides At the slope toe and top within the land scope, 6600 plants of of roadbed evergreen broadleaved tree with strong absorbent for harmful gases

such as CO2, SO2, NOX and so on are planted on both sides of the road every 10m spacing, and hold the soil and water conservation function of roadbed. 二、the new plan Temporary protection (1) Set the temporary cut ditch at the top of high and excavation slope measures in the outside 5m; construction area (2) to prevent excavation of construction from being washed out by the rains, temporary drainage ditches with about 2800m are built surrounding the engineering area, and set 14 temporary desilters at the export of drainage ditches, the water can drain into the natural channel after the water is in the pool and stable. Add dams for blocking Accord with mandatory provisions in the principle of" first block, after slag in the abandoned abandon " in the《soil and water conservation technical rules of clay development and construction project》(GB50433-2008) . Plant grass in the Protect by plant measures abandoned clay

Table 13 The analysis form about soil and water conservation scheme of abandoned clay in the Wubai road

Numbers Drainage ditches of Pile Area of Type of Capacity surrounding the abandoned numbers covers(m2) covers (m3) clay abandoned clay (m) 1 K1+290 2928 wasteland 30000 180 2 K2+360 2620 wasteland 24388 192 3 K3+280 4650 wasteland 14418 269 4 K4+100 7000 wasteland 33736 330 5 K5+320 5560 wasteland 29690 246 6 K6+720 5640 wasteland 18225 270 7 K8+530 5320 wasteland 18033 156 8 K9+620 5880 wasteland 33592 168 9 K10+540 6870 Dry land 55482 280 10 K13+460 4840 shrubs 29755 196 Total 51308 / 287319 2287 Every abandoned clay implements the principle of" first block, after abandon " , and protect the

Chongqing Asian Development Bank Project Management Office 37

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) foundation with dam for blocking slag of dry stone, the blocking slag dam is 2 m high; Abandoned slag in the abandoned clay piles up by rolling, and the ratio of the slope for piling up slag is 1: 2.5 ~ 3.0 to ensure the stability of slope; Build a drainage ditch along the surrounding of each abandoned clay according to the terrain and direction to intercept water from slopes and guide to drain the runoff formed in the abandoned clay; Renew vegetation by growing grass on the surface of abandoned slag after completing the abandoned soil, strip available part of corrosion surface soil before abandoning slag, cover the surface of abandoned clay with the original stripped soil after completing the abandoned clay, and transform it into grass land and forest land with water conservation, make it to meet the state can be recovered to use, in order to make full use of land resources.

2.2.2 Conclusions of environmental impact analysis about design change of Wubai road in the Fuling district

The grade of highway changed from level 2 to level3, which made it possible to build the road by using the old road and existing roadbed, and largely reduced the ecological destruction and the risk of secondary geological disaster from the high cut slopes.

The length of roads increased 1.787 km, mainly due to the need of three local sections extending. In the digging and filling engineering of new extending road, the digging is 71900 m3, the filling is 24400 m3, which is accounted for 14.23% in the total digging and 11.19% in the total filling respectively. The extra soil and stone of the three extending roads were discarded in 1, 2, 7 and 10 abandoned clay ( the setting of abandoned clay was shown in table12 and table13). According to practical investigation and inspection, the new extending sections mainly takes up wasteland, and no environmental sensitivity such as water sources, farmers and so on surrounding it, therefore, the environmental

Chongqing Asian Development Bank Project Management Office 38

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) protection measures of original environmental management plans approval from ADB are still apply to all engineering phases of the extending roads. The adverse impact of the new extending sections on the environment and ecology is small and controllable after taking the related measures of soil and water conservation, and environment function and ecological function remains the same in the neighboring areas surrounding the extending sections.

The width of roadbed changed from 8.5 m to 10.0 m, improved the capacity of the large-scale passenger car passing, improved road safety, satisfied the need of economic development, and also considered that the width of the old roadbed is 8 to 12m before the expansion, so the roadbed width of the expansion is not broaden in the all range, and only in the local road, the amount of digging and filling is little, and the broaden of local sections mainly takes up wasteland and slopes, and there is no environment sensitive point and soil conservation target neighboring areas of the sections for broadening the roadbed, therefore, the environmental protection measures of original environmental management plans approval from ADB are still apply to all engineering phases of the local sections for broadening the roadbed. After taking the related measures of soil and water conservation, environment function and ecological function remains the same in the old roadbed and neighboring areas surrounding the old sections.

Chongqing Asian Development Bank Project Management Office 39

Asian development bank loan on Chongqing urban-rural planning infrastructure construction demonstration project(one)Semi-annual Report of Environmental Protection (2012.08) The comprehensive analysis from the angle of environmental protection showed that the design change of Wubai road project did not exist environment factors, In addition the engineering quantity have changed, all the environmental protection measures and monitoring plans are the same with the environmental management plans approval from ADB, the engineering design change of Wubai road is reasonable and feasible.

Chongqing Asian Development Bank Project Management Office 40