Washington Metropolitan Area Transit Authority Board Action/Information Summary
Resolution: Action Information MEAD Number: Yes No
TITLE:
Rail Service Adjustments for State of Good Repair
PURPOSE:
To inform the Customer Service and Operations Committee of 2012 service adjustments in support of achieving a state of good repair.
DESCRIPTION:
The quarterly update on scheduled service adjustments that support Metro’s goal to improve service reliability by maximizing rider satisfaction though convenient, comfortable services and facilities that are in a good condition and easy to navigate.
To accomplish the ambitious goals of bringing our infrastructure to a state of good repair, a very aggressive program of work on weekends and night is being implemented. To minimize inconvenience and maximize efficiencies, work is being accelerated and performed around the clock.
FUNDING IMPACT:
All projects are funded in the FY12 approved Capital Program.
RECOMMENDATION:
None Washington Metropolitan Area Transit Authority
2012 Rail Service Adjustments for State of Good Repair
Customer Service and Operations Committee April 12, 2012 Single Tracking 1st Quarter 2012
• 47 scheduled with continuous monitoring to minimize customer disruption o 23 completed as scheduled o 24 incorporated into other shutdowns/single tracking to maximize work occurring simultaneously Escalator/Elevator Shutdowns 1st Quarter 2012
• Eight escalator rehabs Escalators completed Station Unit Completed Date • Adjusted schedule to avoid Metro Center A01W07 1/11/12 negative impact on Cherry Dupont Circle A03N05 1/27/12 Blossom event Dupont Circle A03N01 1/27/12 Judiciary Square B02S07 2/3/12 • Implemented scheduled Wheaton B10X03 3/16/12 elevator shutdown at Arlington Cemetery C06X05 3/19/12 Cleveland Park Arlington Cemetery C0606 3/19/12 Gallery Place B01W06 3/20/12 Project Highlights 1st Quarter 2012
• All 11 Ra il sh utd owns occurred as sch ed ul ed
• Continued installation of No. 8 switches in the mainline – NTSB recommendation o Final eight to be installed May 2012
• Completed installation of: o 15,760 linear feet of running rail - GOAL 15,000 o 23,501 fasteners - GOAL 5,000 o 4,297 cross ties - GOAL 2,000 Customer Outreach Conducted
• As part of Metro Forward Campaign o Newspaper, radio advertisements o In station banners, signs, murals, take ones o In station announcements o Social media alerts , videos o Web site postings o Call Center recordings o Added personnel on -site o Community briefings, outreach o Outreach to local Departments of Transportation APPENDIX Single Tracking Operations
Start Finish Line Type Location
April 1, 2012 May 3, 2012 Red Fastener Friendship Heights ‐Medical Center
Blue/ April 1, 2012 June 28, 2012 Floating Slab Stadium Armory – Addison Road Orange
April 1, 2012 April 19, 2012 Orange Dulles East Falls Church –West Falls Church
Blue/ April 1, 2012 April 12, 2012 Station Dome Eastern Market – Stadium Armory Orange
April 2, 2012 April 12, 2012 Red ETS New York Ave – Rhode Island Ave
East Falls Church –West Falls Church April 8, 2012 April 12, 2012 Orange Dulles
April 15, 2012 April 26, 2012 Red ETS New York Ave – Rhode Island Ave Single Tracking Operations
Start Finish Line Type Location
April 16, 2012 May 4, 2012 Blue Insulator Van Dorn –Franconia Springfield
Blue/ April 16, 2012 April 20, 2012 Fastener Stadium Armory ‐ Cheverly Orange
April 20, 2012 April 23, 2012 Orange Dulles East Falls Church –West Falls Church
Yellow/ April 22, 2012 May 24, 2012 Tie Renewal Prince George’s Plaza ‐ Greenbelt Green
Blue/ April 23, 2012 May 24, 2012 Station Dome Eastern Market – Stadium Armory Orange
April 23, 2012 April 26, 2012 Red Fastener Dupont Circle –Van Ness UDC
Blue/ April 23, 2012 May 11, 2012 Fastener Federal Center – Eastern Market Orange Single Tracking Operations
Start Finish Line Type Location
April 27, 2012 April 30, 2012 Red Platform Takoma –ForestGlen
Blue / April 27, 2012 April 30, 2012 Neutral Host Farragut North –Van Ness UDC Orange
April 30, 2012 August 9, 2012 Red Cable Takoma –ForestGlen
May 4, 2012 May 7, 2012 Red Platform Takoma –ForestGlen
May 4, 2012 May 7, 2012 Red Fastener Dupont Circle – Van Ness UDC
May 4, 2012 May 7, 2012 Red Cable Takoma –ForestGlen
Blue/ May 4, 2012 May 7, 2012 Bearing Eastern Market – Stadium Armory Orange Single Tracking Operations
Start Finish Line Type Location
May 4, 2012 May 7, 2012 Orange Dulles East Falls Church –West Falls Church
May 7, 2012 May 10, 2012 Blue Tie Renewal Arlington Cemetery – Pentagon City
May 7, 2012 May 17, 2012 Red Fastener Van Ness UDC – Friendship Heights
May 7, 2012 May 25, 2012 Red Insulator Twinbrook – Shady Grove
May 7, 2012 May 24, 2012 Red Platform Takoma – Forest Glen
May 11, 2012 May 14, 2012 Red Platform Takoma –ForestGlen
May 11, 2012 May 14, 2012 Red Cable Takoma –ForestGlen Single Tracking Operations
Start Finish Line Type Location
May 11, 2012 May 14, 3012 Red Fastener Dupont Circle – Van Ness UDC
May 11, 2012 May 14, 3012 Blue Grout Pad Eastern Market – Addison Road
May 14, 2012 May 17, 2012 Blue Tie Renewal Arlington Cemetery – Pentagon City
May 14, 2012 June 1, 2012 Orange Insulator West Falls Church ‐ Vienna
May 16, 2012 May 16, 2012 Red Sign Install New York Ave – Rhode Island
May 17, 2012 May 17, 2012 Red Sign Install New York Ave – Rhode Island
May 18, 2012 May 21, 2012 Red Platform Takoma –ForestGlen Single Tracking Operations
Start Finish Line Type Location
May 18, 2012 May 21, 2012 Red Cable Takoma –ForestGlen
May 18, 2012 May 21, 2012 Red Fastener Van Ness UDC – Friendship Heights
May 18, 2012 May 21, 2012 Green Tie Renewal College Park ‐ Greenbelt
Ma y 21, 2012 May 23, 2012 Blue Sign Install Morgan Blvd ‐ Largo
Ma y 21, 2012 May 23, 2012 OrangeSign Install West Falls Church ‐ Vienna
May 21, 2012 May 24, 2012 Red Track Circuit Friendship Heights –Medical Center
Ma y 22, 2012 May 24, 2012 Orange Sign Install West Falls Church ‐ Vienna Single Tracking Operations
Start Finish Line Type Location
Ma y 22, 2012 May 29, 2012 Blue Sign Install Morgan Blvd ‐ Largo
May 25, 2012 May 28, 2012 Red Platform Takoma – Forest Glen
May 29, 2012 May 29, 2012 Orange Sign Install Ballston –East Falls Church
May 29, 2012 June 7, 2012 Green Tie Renewal College Park – Greenbelt
May 29, 2012 June 21, 2012 Red Track Circuit Grosvenor ‐ Twinbrook
May 30, 2012 May 30, 2012 Orange Sign Install Ballston –East Falls Church
Yellow/ May 30, 2012 June 7, 2012 Sign Install Mount Vernon –L‐Enfant Green Single Tracking Operations
Start Finish Line Type Location
May 31, 2012 May 31, 2012 Blue Sign Install McPherson Square –Foggy Bottom
June 1, 2012 June 4, 2012 Red Platform Takoma –ForestGlen
June 8, 2012 June 11, 2012 Red Platform Takoma – Forest Glen
June 15, 2012 June 18, 2012 Red Platform Takoma –ForestGlen
June 22, 2012 June 25, 2012 Red Platform Takoma –ForestGlen
June 29, 2012 July 2, 2012 Red Platform Takoma –ForestGlen Escalator Shutdowns
Start Finish Unit TpeType Station
January 12, 2012 April 4, 2012 D06X04 Rehab Eastern Market
January 16, 2012 April 11, 2012 C05X08 Rehab Potomac Avenue
January 26, 2012 April 5, 2012 A01W05 Rehab Metro Center
February 2, 2012 October 19, 2012 A03S01 Replace Dupont Circle
February 2, 2012 October 19, 2012 A03S02 Replace Dupont Circle
February 2, 2012 October 19, 2012 A03S03 Replace Dupont Circle
February 8, 2012 April 18, 2012 B02S05 Rehab Judiciary Square
FbFebruary 23, 2012 May 17, 2012 C07S13 RhbRehab PtPentagon
March 22, 2012 May 31, 2012 B01W03 Rehab Gallery Place
March 22, 2012 May 31, 2012 C08X05 Rehab Pentagon City
March 22, 2012 May 31, 2012 D08N04 Rehab Stadium Armory Escalator Shutdowns
Start Fini sh UitUnit Type Stati on
April 2, 2012 May 28, 2012 C05X06 Rehab Rosslyn April 19, 2012 June 28, 2012 C01S04 Rehab Metro Center
April 19, 2012 June 28, 2012 A01W04 Rehab Metro Center
May 2, 2012 July 11, 2012 B02S06 Rehab Judiciary Square
May 31, 2012 August 23, 2012 C07S12 Rehab Pentagon
June 11, 2012 August 6, 2012 C05X07 Rehab Rosslyn
June 14, 2012 August 23, 2012 B01W04 Rehab Gallery Place
June 14, 2012 August 23, 2012 C08X06 Rehab Pentagon City June 14, 2012 August 23, 2012 D08N05 Rehab Stadium‐Armory
July 12, 2012 September 20, 2012 C01S06 Rehab Metro Center
JlJuly 12, 2012 StSeptem ber 20, 2012 A01E06 RhbRehab MtMetro CtCenter Escalator Shutdowns
Start Finish Unit Type Station
July 25, 2012 October 3, 2012 B02S04 Rehab Judiciary Square
August 20, 2012 October 15, 2012 C05X05 Rehab Rosslyn
September 6, 2012 November 15, 2012 B01W05 Rehab Gallery Place
September 6, 2012 November 15, 2012 C07N10 Rehab Pentagon
September 6, 2012 November 15, 2012 C08X07 Rehab Pentagon City
September 6, 2012 November 15, 2012 D08N06 Rehab Stadium‐Armory
October 15, 2012 December 23, 2012 A03N06 Rehab Dupont Circle
OtbOctober 15, 2012 DbDecember 23, 2012 A02W05 RhbRehab FtFarragut NthNorth
November 15, 2012 July 31, 2013 C07S07 Replace Pentagon
November 15, 2012 July 31, 2013 C07S08 Replace Pentagon
November 15, 2012 July 31, 2013 C07S09 Replace Pentagon Elevator Shutdowns
Start Finish Unit Type Station
January 9, 2012 April 24, 2012 A05X01 Rehab Cleveland Park
February 16, 2012 April 24, 2012 A05X02 Rehab Cleveland Park
April 15, 2012 June 4, 2012 D05X01 Rehab Capitol South
April 15, 2012 June 4, 2012 D05X02 Rehab Capitol South
May 8, 2012 August 21, 2012 A09X01 Rehab Bethesda
June 12, 2012 August 21, 2012 A09X02 Rehab Bethesda
June 18, 2012 August 7, 2012 F03N01 Rehab L’Enfant Plaza
June 18, 2012 August 7, 2012 F03N02 Rehab L’Enfant Plaza
August 20, 2012 December 21, 2012 K01X01 Rehab Courthouse
AtAugust 21, 2012 OtbOctober 10, 2012 D08S01 RhbRehab Sta dium Armory
August 21, 2012 October 10, 2012 D08S02 Rehab Stadium Armory Elevator Shutdowns
Start Finish Unit Type Station
September 7, 2012 December 28, 2012 A06X01 Rehab Van Ness‐UDC
October 19, 2012 December 28, 2012 A06X02 Rehab Van Ness‐UDC
October 20, 2012 December 29, 2012 A02S01 Rehab Farragut North
October 20, 2012 December 29, 2012 A02S02 Rehab Farragut North
October 24, 2012 December 13, 2012 D02S01 Rehab Smithsonian
October 24, 2012 December 13, 2012 D02S02 Rehab Smithsonian Total Shutdowns
Start Finish Line Location
April 20, 2012 April 23, 2012 Red Rhode Island – Silver Spring
April 20, 2012 April 23, 2012 Blue Rosslyn ‐ Pentagon
April 27, 2012 April 30, 2012 Blue Rosslyn ‐ Pentagon
May 4, 2012 May 7, 2012 Green Prince George’s Plaza ‐ Greenbelt
May 18, 2012 May 21, 2012 Orange East Falls Church ‐ West Falls Church
May 25, 2012 May 29, 2012 Green West Hyattsville ‐ Greenbelt Total Shutdowns
Start Finish Line Location
June 1, 2012 June 4, 2012 Orange East Falls Church ‐ West Falls Church
June 8, 2012 June 11, 2012 Orange East Falls Church ‐ West Falls Church
June 22, 2012 June 25, 2012 Orange East Falls Church ‐ West Falls Church
June 29, 2012 July 2, 2012 Orange Stadium Armory ‐ Landover
July 6, 2012 July 9, 2012 Orange Stadium Armory ‐ Landover
July 6, 2012 July 9, 2012 Red Silver Spring ‐ Brookland
July 13, 2012 July 16, 2012 Blue Pentagon ‐ Braddock Road Total Shutdowns
Start Finish Line Location
July 20, 2012 July 2, 2012 Red Friendship Heights ‐ Grosvenor
Friendship Heights ‐ Grosvenor July 27, 2012 July 30, 2012 Red
August 3, 2012 August 6, 2012 Orange East Falls Church ‐ Vienna
August 3, 2012 August 6, 2012 Red Fort Totten –Union Station
August 10, 2012 August 13, 2012 Red Friendship Heights ‐ Grosvenor
August 17, 2012 August 20, 2012 Red Brookland – Silver Spring
August 24, 2012 August 27, 2012 Orange East Falls Church ‐ Vienna Total Shutdowns
Start Finish Line Location
August 31, 2012 September 4, 2012 Green Waterfront ‐ Archives ‐ Pentagon
September 7, 2012 September 10, 2012 Red Dupont Circle ‐New York Ave.
September 14, 2012 September 17, 2012 Green College Park ‐ Greenbelt
September 14, 2012 September 10, 2012 Orange East Falls Church ‐ Vienna
September 21, 2012 September 24, 2012 Red Friendship Heights ‐ Grosvenor
September 28, 2012 October 1, 2012 Orange East Falls Church ‐ Vienna
October 5, 2012 October 9, 2012 Blue Stadium Armory –Largo Total Shutdowns
Start Finish Line Location
October 12, 2012 October 15, 2012 Blue Farragut West ‐ Smithsonian
October 19, 2012 October 22, 2012 Red Friendship Heights ‐ Grosvenor
October 19, 2012 October 22, 2012 Orange Ballston ‐West Falls Church
November 2, 2012 November 5, 2012 Blue Court House Rd ‐ Pentagon ‐ Foggy Bottom
November 9, 2012 November 13, 2012 OrangeVirginia Square ‐ East Falls Church
November 9, 2012 November 13, 2012 Red Friendship Heights ‐ Grosvenor
November 16, 2012 November 19, 2012 Green Mount Vernon –L’Enfant Plaza Total Shutdowns
Start Finish Line Location
November 30, 2012 December 3, 2012 Red Fort Totten ‐ Forest Glenn
DbDecember 7, 2012 DbDecember 10, 2012 RdRed TkTakoma ‐ FtForest Glenn
No Shutdowns during Thanksgiving week or the Christmas holidays