FINAL REPORT

APPLICATION CLOSE-RANGE OF TERRESTRIAL TO

STRUCTURES BRIDGE

by

Hilton Marvin H.

Research Scientist Senior

(Photogrammetry by Bales, F. B.

Engineer) Photogrammetric

(The findings, expressed opinions, conclusions this and in

necessarily of the author those and those of report

not

are

agencies.) sponsoring the

Highway Vir.ginia Transportation Council Research &

(A Sponsored by Cooperative Organization Jointly Virginia the

Highways Department Transportation of and &

Virginia) University the of

Cooperation with Transportation Department the of S. U. In

Highway Federal Administration

1985 June

85-R40 VHTRC

COMMITTEE RESEARCH ADVISORY BRIDGE

Bridge Engineer, MISENHEIMER, Chairman, VDH&T District L. L.

Bridge Supervisor, Engineer ANDREWS, Design VDH&T E. J.

Bridge Engineer, CHAMBERS, FHWA Division C. L.

Div., GARVER, Administrator Division VDH&T JR., D. Construction C.

HILTON, Research Scientist, Senior H. VH&TRC M.

Engineer, MCGEE, VDH&T G. G. Assistant Construction J.

Engineer, MENEFEE, Structural Steel JR., F. VDH&T M.

Bridge Engineer, MORECOCK, District H. VDH&T R.

Engineer, NASH, JR., A. District VDH&T C.

Bridge PREWOZNIK, Engineer, District VDH&T F. L.

Bridge •Engineer, SELLARS, VDH&T District W. L.

Bridge Engineer, SUTHERLAND, G. F. VDH&T

University Engineering, Old Prof. Civil Dominion WANG, of R. L. L.

Engineer, WILLIAMS, Materials P. District VDH&T C. ii

SUMMARY

photogrammetry close-range application terrestrial of field A to

displacements magnitude structural and of order small of the measurement

10/1318

conducted. A elevation Jena UMK differences in camera was was

photographs evaluations. used the in take the used to

bridges girders several steel deflections of of the Measurements on

i/8

achieved with be

of the in order that accuracies

suggest

can on

0MK

10/1318 close-range addition,

using the In normal

camera. care

applications bridge be other photogrammetry used for terrestrial

can

technique condi- using

for this By deck for condition such

surveys. as

preparing taking and hand need for the tion

measurements surveys,

provide photographs eliminated. The field sketches the is in perma- a

potential

evaluate reference be used

which

record to nent

as a can

structural

of deck changes the condition the in movements. to

gage or

desirable, of bridge the

evaluations records of Where permanent use

are

considered. should photogrammetry close-range be

10/1318 satisfactory during produced results the The UMK

camera

Highways of by Virginia purchased and Department the study has been and

applications. terrestrial close-range Transportation for It is

recom-

capabil- of bridge made the engineers highway be and that mended

aware

photogrammetry. close-range of ities iii

CONVERSION SI FACTORS

Multiply To To Convert By

Length:

2.54 in--- cm

0.025 in 4 m

0.304 8 ft m

yd 0.914 4 m

609 344 kin- ml

Ares

2 2

6.451 600 E+O0

in.

cm_-

z z

9.290 304 ft E-02

m

2 2

yd 8.361 274 E-01

m

9

2.589 988 E+O2 mi-: Hectares

(a) 4.046 856 E-Of •ectares------acre

3

353 E-05 2.957

oz m

3

4.731 765 E-04 pt

m

3

9.463 529 E-04 qt

m 3

706 1.638 E-05

m

3

ft 2.831 685 E-02

m

3 3

yd 549 7.645 E-Of m

3

1.,000 lm NOTE: L

Volume

Unit per

Time:

ft•31mln

3

m3/sec 4.719 E-04 474

m3/sec ft•/s 685 E-02 831 2.

m31

In•/ml. E-07 2.731 177

sec

/

E-02 258 1.274 •/rain

yd

s ec------

m

3

/s•c

E-05 gal/min-.------6.309 029 m

E-02 kg 2.834

952

oz

E-03 kg 174 1.555 dwt

4.535 924 E-01 kg ib

847 E+02. 9.071 kg Ib) (2000 ton

Mass per

Unit

Volume:

Ib/yd2•- 2

kg/m E+01 4.394 185

3

Ira3--

in• E+04 990 kg 2.767 / lb

kg/m lb/ft.• 846 E+OI 1.601

3

kglm E-Of 5.932 Iblyd•= 764

Velocity:

(Includes

Speed)

m/s E-01 3.048 000 ft/s

mls E-Of 4.470 400 .•.lh

m/s E-OI 144 444 5. knot

km/h E+O0 344 1.609 ml/h•-•------

Force Per

Unit Ares

2

E+03 757 lbf/In 6.894 Ps

2

E+OI 026 lbf/ft 788 4. Pa

Viscosity:

2/

E•06

1.000 000

cS s m

t E-Of Pa's l.O00 000 p

5/9

°F-32) °C Temperature

CLOSE-RANGE TERRESTRIAL PHOTOGRAMMETRY APPLICATION OF TO

BRIDGES TO HIGHWAY

by

Hilton Marvin H.

Research Scientist Senior

(Photogrammetry by Bales, F. B.

Engineer) Photogrammetric

INTRODUCTION

obtaining Photogrammetric information involves in

an

by photographs object. taking of from indirect measurements

an manner

usually procedures surveying where Unlike conventional measurements

are

object photogrammetry directly field, involves of the the in made

photographs required recording these the obtain using the and

to area on

photogrammetric office. the later When time in measurements at

a

general required. techniques operations used, These three

are are are

photography, photographs, taking and, planning, the processing the and

photographs finally, desired using the obtain The the measurements. to

products example, produce photographs, be such

for used other to as can

topographic maps.

photogrammetry. for broad number of

There

it In

are uses a a sense

(interpretative) qualitative quantitative well be for

used

as as can

(metric) diversity, photogrammetry has been work. of found this Because

beyond applications of fields useful number be

its in most to

common a

forestry, mapping. fields include surveying these of all and Some in

physics, biomedical, transportation engineering, and of astronomy, types

(I) planning. urban

photogrammetry aerial

be divided into and Metric two

areas: can

high photogrammetry precision

which terrestrial. aerial is In

camera, a

photograph airplane, plane the flies

used mounted

is in to

area an as an

photographs photogrammetry, taken terrestrial from fixed

For

over. are

earth's positions majority surface. either the While the of

or on near

photogrammetry highway transportation conducted work the the and in

presented work field been of the aerial this the has is in type, report

applications potential evaluation of concerned of with

terres-

an some

bridges. highway photogrammetry trial to

particular photogrammetry study The this of be further

in

can use

close-range photogrammetry. terrestrial defined these In type

as

object applications relatively the mounted close be the is to to camera

close-range the when Photogrammetry be considered photographed. is to

4 330 approximate of camera-to-object in the distance is in to range

(2) fields where direct Photogrammetry used this is in ft. in

many range

impractical,

costly, diffi-

object either of is measurement very or an

impossible obtain cult if otherwise. to not

of

number highway engineering be there transportation and In

may a

photogrammetry. These close-range applications for terrestrial

may

significant measuring historically documenting from structures to range

structural of deflections structural small distances such movements,

as

of structural positions changes relative other members, the in or

elements.

SCOPE PURPOSE AND

applicability

the study

evaluate of primary this The to

purpose was

small of photogrammetry the close-range for of terrestrial measurement

Several bridge members. of deflection structural such the movements

as

study follows: secondary of the

purposes as were

background precedents for of the

and the i. Review

use some

obtaining close-range photogrammetry for terrestrial

bridges. engineering of measurements

used general of in the classification 2. Review

cameras

applications. terrestrial

accomplish particular the 3. used Evaluate the to

camera

study. primary of the purpose

photogrammetry close-range terrestrial 4. Evaluate of the

use

bridge recording deck condition for surveys.

technique ability small define Evaluate the of the 5. to

the associated with such that differences elevation in as

bridge decks. surface of texture

work office study field and limited the

of the The to

scope was

bridges, Several accomplish objectives. which the above to necessary

study. were-selected field An for later, detail described

in

more are

photogrammetry by resulting photography analysis the made of the

was

Transportation. Highways Virginia and of Department of the section

BACKGROUND

relatively long photogrammetry used Close-range has been

over a

beginning of period nineteenth the middle the time, of In in century.

by photographs

applications terrestrial used earliest the

surveyors were

point-by-point technique. develop

from

intersection It to maps

was

a

photographs. identify however, difficult, different point the

to

same on

by problem of resolved the the This invention comparator, stereo was

independent Pulfrich work 1901 of which resulted from the in

(3) possible the simultaneous 1903. made This device Fourcade and in

photograph

of different setting measuring marks identical of two

s

on

point-by-point by method, Succeeding calculations made the views.

were

subsequently work automated. been but this has

applied photogrammetry close-range architecture when 1885 In

to

was

(3) began photogrammetric Meydenbower Germany. archive the in monument

widely photogrammetry aid Architectural used reconstruction in is to now

damage related for other restoration efforts after and to

measurements

glaciers.

photogrammetry The used 1889 work. In to

survey pos-

was

technique changes sibility the and using observe of in size the to

recognized, glaciers velocity thus

dimension the and of time

was was

early analysis photogrammetric Other of added the measurements. to

close-range photogrammetry applications the of of the century at turn

images evaluation X-ray taken of for medical included the purposes.

1920's development photogrammetry dealt with the the of Up

to

Subsequently, photographs ground however, the taken from main stations.

photography development placed emphasis the of both the aerial

was on

stereoplotting produce instrume.nts useful that used data and the to

are

applica- photographs. given With from aerial attention recent to

more

photogrammetry of

variety technical of terrestrial it in tions

areas,

a

obtaining recognized being for be used again method that

is

can a as

legis- objects for Federal of documentation and measurements purposes.

example, placed

for the has

restrictions lation in recent years,

use on

engineering federal for that of funds and other activities construction

historically significant When

site affect

sites structures. may or •a or

eligible inclusion for the either

included is is structure

on, on, or

Places, be Register effort made of National Historic prevent to must an

only alternative demoli- where harm the

the is site. In to

cases some

required removal, often records of the

that it is tion structure

or

or

acquired. object of kind often require This could be documentation

subsequent field the laborious time-consuming and and measurements

bridge, drafting drawings. addition, inventory of of In structures

an

encouraged department transportation that within each

is

state so now

historically significant identified. be is It apparent structures

can

photogrammetry close-range could be used terrestrial in assist that to

applicability approach satisfying using of requirements. this The these

historically objects significant and associated document structures to.

Virginia

transportation evaluated in projects with in

recent

a was

by Spero.(4) work that by documentation this concluded in It report

was

sufficiently and photogrammetric is methods is cost- accurate

very

photo- by obtaining data field that effective. also noted It

was

of traditional labor-intensive,

the whereas is grammetry not

more use

recommended further normally

labor- It methods intensive. is

very was

photo- terrestrial close-range could be used that that

for

camera a

Subsequently, the purchased. used that

be the grammetry

was on

camera

presented this being study by

Spero work and the in report

was

on

Transportation. Highways purchased and by Virginia of Department the

later. described This is camera

photogrammetry and distortion

of terrestrial The to

measure use

deflection bridges precedent. and Distortion without in is not movement

by

monitoring

determined be function of of

time

structure

on as a can a

photogrammetry regular Accordingly, of of

the basis.

account

use an a

by presented

bridge girder in Scott

box

in movement

to was measure a

by

1978.(5) the caused arch of of The the distortion measurement

an

described.(3)

this bridge also In been railroad has of settlement

a

of develop the photogrammetry the used latter instance contour to

was

and fit constructed lining could be distorted that arch armored

to so

an

10/1318

UMK instance, another Jena it. In support

two recent cameras

of

bridge the Germany determine used in

measurements exact to

a were on

bearings could be bearings that

structural elements the the at

new so

required

rail- the would techniques have of fabricated. The other

use

would have unacceptable periods of and bridge time for be closed road

to

Williamsburg costly.(6) the

still

been

In

recent

case,

more a more

photo- surveyed

using City

York Bridge the East River in New

was across

corroded of techniques the condition grammetric the determine

.to suspen-

profile during

load bridge cables and sion tests. get to

accurate

an

First, bridge cited. technique

advantages this using of the Two

were on

only few bridge for

closed

considerable the and saved time

a was

was

required

techniques would have hours, the other whereas of many

use

be considerable that Secondly, data stereophotos days. the record can

information. additional reexamined obtain time to at any

CAMERAS PHOTOGRAMMETRIC CLOSE-RANGE

General Classification

photo- total the used initial in the instrument The is

camera

surveying function instruments grammetric similar is and in to system

object.

Whereas

about used obtain information since is it

to a an

only for provide direction

information in theodolite

transit

one can or

virtually. yield

sighting, information photograph

in given

a can

a a

the point identified Therefore,

unlimited of number directions. any on

photograph

would different with direction the represent respect to

a

position.

The important good

thus is instrument since camera camera an

quality photographs

metric to necessary are accuracy. assure

should be that photo- noted the It used for terrestrial cameras

differ those from aerial used for Since grammetry in

surveys.

photogrammetry terrestrial the stationary used from positions, is

camera

design simpler than is its that of for

aerial used

surveys. a camera

(phototheodolite) The combined, effect,

is in theodolite with

camera a

photographs and used obtain object is of from fixed control to

an

overlapping points. photographs obtain phototheodolite order In the to

be from

another, moved

station mounted must to two at one or cameras a

rigid distance known of the ends base

could be used obtain apart

to

on a

photographs. the pairs of

hand, Aerial the other stereo

cameras,

on

being

during

good lens, in require motion fast shutter

exposure, a a

mechanism

short for high-speed times, film and with

emul- exposure

a a

photogrammetry, project sion. this Since concerned with terrestrial was

aerial will be further. discussed not cameras

close-range that The used photo-

for terrestrial cameras are

designated either

metric nonmetric. Nonmetric grammetry are as or

have

that interior unknown and orientation often is is

cameras

an

principal unstable; i.e., principal point the and illustrated distance

Figure unknown 1

in unstable. hand,

other the Metric cameras, are or on

fixed assumed have

With the interior orientation. to were once a

development having focusable of tolerable radial distortion and

cameras

stability, adequate longer only designate it

the

to

was no cameras

having being fixed suggested

orientation been has that metric. It

a as

simplest

classify being the by

the metric is to way

camera a as

(3) of existence fiducial marks.

normally designed specifically

Nonmetric for

not cameras are

photogrammetric

they calibrated work

and be if

in must to way

some are

be for such work. used combination Used appropriate with in data

an

reduction highly provide

nonmetric results system, accurate cameras can

costly less and

than Several metric reduction data schemes

are cameras.

Karara.(3)

by reported general have been

In nonmetric

sense, a camera a

obtained be for low

but expensive evaluation cost, system

can an

sophisticated requiring

required. would be The computer

program a

costly, photographs but metric the is taken with the instru-

camera more

analogue plotters. availability restituted be with The the of ments

can

plotters

logical would make the the

metric choice to appear

camera more

for projects require that that be from derived the most measurements photographs.

Fiducial

Marks Negative

Perspective

center

(Lens)

Principal

Point

Principal

Object

Distance

principal distance, showing Illustration Figure i.

(From fiducial principal marks. point, and

3.) Ref.

"cartographic"

and

called work used for metric Cameras

cameras are

geometric

for highly corrected by usually lenses characterized are

distortion.

10/1318 The UMK Camera

by reported study earlier study and the used this The in

camera

10/1318. Spero(4) single (Jena)

metric This model the UMK Zeiss was

the of UMK device. views Two mounted

its orientation in is

own camera

10/1318 tripod shown in

device mounted orientation its in are a on

3. Figures and 2

(Jena) Figure 2. Front of view the 10/1318 Zeiss UMK

Photogrammetric Universal Camera.

Figure

10/1318 3. UMK being

placed

tripod camera on

for field use.

10/1318 wide-angle efficiently where field used

The be UMK

a or can

taking large focusing required. Objective picture allows the size is

a

infinity. photographs between l.Sm of and The less than of distances

large objective

lens, focusing the

offers of continuous range

a camera

horizontal vertical

stop-settings, of of and choice

times exposure

or a

photographic format, The vertical horizontal and of

choice axis.

a or

handling separated facilitate and substructure be

and its to

can camera

high Angles degree precision operation. of with with be measured

can a

include of

the Other features the orientation system. an camera

electromagnetic illumination of the shutter electrical release and

10/1318 universal

fiducial of with marks. second the Use UMK

camera a

possible configuration of the double-mourrted where erection in is

two

a

10/1318 probably single tripods of difficult.. be would The is UMK one

close-range versatile available the of for the in

most

cameras use

photogrammetric applications. of features the of terrestrial main Some

I, either film Table the noted Table

in i. summarized in As

camera are

photographs.

plates taking of this the for used be

For

purpose or can

plates study, glass image that

distortion eliminate the used

to can were

shrinkage changes film. with with associated and temperature occur

being photogrammetric photographs be defined

the studies In

as

can

by horizontal, oblique of vertical, the the of orientation

nature or

optical Accordingly,

the

of the when is axis axis

camera camera.

and

horizontal, being photographs

horizontal be defined will the

so as

analyzed photographs with vertical be

Horizontal and stereo-

can on.

photogra- commonly plotting aerial for used scopic instruments that

are

photographs require phy Oblique study. available for and the

were

analytical stereoplotters for A restitution. universal accurate

or

only study. stereoplotter for this However, available universal

not was

accomplish photographs

the vertical horizontal and to necessary were

objectives work. of the main

Table i

10/1318 (Jena) Model of UMK Summary of the Main Features Zeiss

Single Terrestrial Camera

Photographic Principal Position Format Nominal Tilt Minimum Format

(ram) material of focal rotation distance

range

range

(deg) (m) principal length

(ram) P0,int

Central Plates 4 130x180 -30 I00 I. Yes Variable or

film in steps

to

+90

Source" 3. Ref.

•_ASUREMENTS FROM PHOTOGRAPHS

photogrammetry photographs normally the In taken that such

are

overlap 60% object there will be

the being in observed. Thus, if

a

area

adjacent photographs

pair of

objects from viewed positions,

two a are

lying overlapped the seen in

be three dimensions. in area can

develop overlapping the photographs of To stereoplotter geometry a

high-precision used. is is

It instrument that be used obtain

to a can

three-dimensional information photographed object. the about accurate

accomplished This overlapping photographs placed when is the in two are

relationship device the that such between field the stations is

camera

reproduced precisely.

Basically, photographs correctly the

very

are

aligned stereoplotter the when optical in the positioned

axes are as

they photographs when

optical the taken.

The for axis

were were a

photograph by (shown located is of four the fiducial marks earlier

use

i)

Figure in that recorded image the

the of time at

are exposure. on

through The lines of intersection opposite drawn the fiducial marks will

(Figure principal I). locate the point principal the When point is

directly optical

the of axis of each projectors the of the

two

over

stereoplotter overlapping the interior photograph orientation for •each

is recovered. With the light recovered, interior orientation the

rays

through plates passing replica the be will those that of entered the

a

photographs when

the taken. The position relative and camera were

duplicate will orientation the existing situation the of time not

at

photography, however, the until exterior elements orientation have. been

photographs recovered. Each of stereoplot?.. the in the be posi- must

with tioned the X, Y, result, degrees and

As Z six respect to axes.

a

freedom, of which include three translations three and rotations, have

overlapping be photograph. for recovered each accomplish order In to

to

this adequate orientation,

number of points control be must survey an

provided.

Relative orientation solves for five elements orientation and

can

accomplished by manipulating be the such model that estab- is it stereo

arbitrary lished

effect, scale. It, pair in each of at

an

causes

corresponding by point intersect recovering relative the to at rays

a

other.

tilts projectors the of with Absolute each respect two to

solves orientation for by accomplished elements orientation and is

seven

scaling leveling scaling, and model. the horizontal For control

two

plotted points drawing the

scale the be used. The at to are map on or

points control make used the horizontal between distance the

to

are

corresponding

photographic equal points model the distance the

to on

drawing by

changing This done is model the base the in instru- map. or

leveling, least three For points control vertical needed ment. at

are

plane.

establish

The four of the models quite often to stereo a corners

used, however, front back and side and

side rotations to to are are

scaling operations model conducted make the level. of The

stereo to two

leveling alternately repeated and

refine the

to

necessary are re- as

sults, adjustment

affect the other. since may one

recovered, resulting the When the exterior orientation is stereo-

by scopic be model table which tracing be moved measured

can a can

through

all All model three three the directions. motions in

space can

automatically. manually be monitored When either and recorded

or

stereoscopically through viewing spectacles model colored attached the

table, tracing, the circular the model within the

operator to a sees

floating white which differences ele- dot be used determine in to

can

accomplished by floating vertical- This moving the white dot vation. is

ly object. Thus,

point until be the with it

in to contact appears a on

sloping if the wanted elevation terrain, the elevation of

to

trace a one

floating continuously changed of the dot would have be maintain to to

plot line with of surface. the

To apparent contour, contact

a a con-

floating elevation, question fixed the the elevation dot in is at stant

stereoplotter tracing table horizontal and of the the the moved in

keeping plane. By surface, line the dot the with terrain in contact

a

model points elevation of the

be traced.

Discrete constant can can on

time-dependent of be elevation. determine measured the their In to case

photographs distortion of of

deflection structures, measurement are or

photographs object, taken additional of the latter and

time

at

are a

durinK Changes taken occurring the locations. the elevation in at same

photogra- interval thus before and after from the be time measured can

phy.

ACCURACY

the engineers of

Accuracy of in the

is main measure-

one concerns

structural distances, elevation, differences of in movements. ment or

particularly structural of This of the is the in

measurement true

case

magnitude. only expected of deflections of small order that be

to a are

techniques photogrammetric from

that obtained The be

accuracy can

quality depends of

of the factors number and such the

nature

upon

a as

camera-to-object quality photographic materials, of the the the camera,

distance, disposition few. points, just and the of control

the to

name a

Consequently, possible will that be accuracies it is

not to state

Generally, applicable directly however, all is situations. to

accuracy

having photograph. given related of the the scale

For

to

camera a a

length, photo camera-to-object focal of the scale the function is

a

usually expressed function distance. of the Hence,

is

accuracy as a

photo-taklng conditions, _+0.01%

of of distance. For

accuracy average an

Accordingly, camera-to-object the achieved. distance be

at a can i0

1/16

ft, within 50 could obtain of distance in. to

accuracy an one

only technique, Normally, of order the the the minimize in to

cost

sought. degree has been of that indicated is is accuracy It

necessary

applications photogrammetry

for industrial of that aim

most accuracy an

(3) photo-taking _+0.02% of of about the is distance. At it rate, any

close-range remarkable obtained with that be accuracies apparent

can

techniques. photogrammetric measuring

APPLICATIONS RESULTS OF FIELD

Bridge Condition Survey Deck

photogrammetry application possible close-range terrestrial of One

photo•raphically recording bridge deck These condition is in surveys.

bridge repaired,

decks be conducted that recondi-

to surveys are are on

replaced.

degree repair the of tioned, determine order

In to or or

bridge

decks of the rehabilitation on-site examinations necessary, are

mapping involve the conducted.

The the examinations on-site areas on

surface where located. of deck Areas distress various types

are

by usually example, of delamination, for detected the chain

of

a use

are

drag, sounding hammer, of delamination both. the The

is extent

or a

scaling, Patches, sketches. deck off recorded and marked the also

on on

of also located recorded and other evidences deterioration and

are on

addition, sketches. taken from locations the

certain In cores are on

laboratory decks and the determine chloride examined in to contents.

information, be regions the deck Using all this the distressed of

on can

along calculated, results using information the the of this with and

replacing analyses, rehabilitating bridge the chloride decision

or on a

deck be made. can

close-range photogrammetry bridge of for the deck evaluate To use

bridge

evaluation that scheduled for condition

surveys, a was was

bridge study. 33 located selected for The of is Harrison- Rte. east

on

simple composed burg of 81. four and is Interstate It

spans overpasses

spans), (two approach 6 68 ft ft 7 and and has 52 in in

center two spans

regular bridge roadway ft deck 39.5 curbs. between width of The a

laying fashion,

the work usual conducted condition in its

survey crew

marking grid delaminated off the off deck and and dis- .in pattern a

they several of detected. the

tressed After

spans

areas as were were

photography begun, surveyed traffic marked that the the

and

was so

by photogrammetry well deck control used could be the the

party as as

bridge deck of the established

line the such base

A survey

crew. was on

width

photograph. that each could Targets the be covered entire in were

26-ft for the laid deck intervals based needs the the

at

out

on on

length. height mounting of focal Three lines of the and its

camera

placed bridge deck, each of the the side and

targets were on one on ii

closed that lanes approximately of the the to in another two center were

operation. during the traffic

bucket of the attached plywood frame

mounted in

The to

a camera was

he±ght 36 operated of ft (Figure 4).

The boom llft at a

was camera a

allow moved bucket the truck bridge and deck. The the above to were

total

A reference the above of the positioning targets. center

camera

taken. bridge deck A photographs overlapping the of of eleven

were

gives through 8, which photographs Figures 5 shown in these of is mosaic

end. bridge from beginning the

complete deck of the of the view west

a

marked distressed

f±gures,

the these from be noted As were areas can

which determ±ne used chalk white blue

dark and A with to

were crayon. a

Probably darker is

the photos. the

the

easiest to see on was

acceptable. either best, but is

boom for lift of bucket

mounting the 4. Figure Camera

a on

bridge deck. photographing of close-range a 12 13

edges of of the All the delaminated by

measured the areas were

deck information this and

recorded sketches. their Thus, survey crew on

the data recorded could be later used calculate the of dis- to

area

tressed that would material require deck the removal if be

to

were

rehabilitated. photographed,

deck If the however,

these

were measure-

would be field, have taken the in the of the since not ments to

area

distressed could material photographs. be determined 9, from the Figure

example, (Figure for shows 7) distressed the regions plotted of 3 span

photographs. scale from the

The of feet in each dis- to

square

area

region

plat. tressed shown the interesting is is It that the

to note

on

lighter

patches colored deck the Figure

shown 7 in had that spots

on are

repaired been earlier rehabilitation Although of the in deck. these

an

patches deck, outlined they the easily plotted

shown not

were on were

as

by patches marked broken the lines with Figure 9. in Several of these

patches their and measured

calculated compared and the w•th were areas

photographs. the determined from values

The close in areas very were

likely but photo- that the it determined is from the agreement,

areas

graphs

precise than

those calculated the from direct more are measure-

because deck level it is difficult sometimes define ments, at

to more

edges patches the photographs. of of than the from the is it some

close-range photogrammetry The bridge of for deck condition use

developing eliminate the for need sketches of deck the surveys can

taking

for and linear addition, of

In type. measurements any perma- a

of deck surface record the available future for reference is and nent

information Visual

that such

described above be obtained use. as

can

photographs from the needed, possible if and future structural settle-

changes other elevation

position in relative

be measured ment

or

or can

making by

photographic of the initial

Having record. permanent

use a

might for record future be primary close-range the

using for

use reason

photogrammetry bridge for

deck

condition While the of survey. a

use

technique

could reduce of the work thus the and required

some manpower

for the by photogrammetry would be this offset the for need survey,

personnel lift bucket and truck and operator. a 17

• o

• o

o •, o

Surface in.Elevation Irregularities C.rscks Differences of and

bridge points Several the described the deck of above

on were

determining selected of the for differences small elevation. in purpose

photogrammetric locations depth the At three engineer the of measured

highest joint filler the surface of relative deck level the the

to

(Figure i0). immediately adjacent joint the points, four other At to

depth made similar pitting he the of of small the in measurements

some

Finally, deck cracks surface. widest of he the widths three measured

bridge joints. deck several of the

of All these

measurements

near were

1/16

by straightedge taken field using the the in and in

to nearest

a

photogrammetric independently The engineer rule. the determined dis-

subsequently 0.01 the ft. field The tances to nearest measurements were

compared 0.01 the converted ft with those determined from and to nearest

photographs the selected Table shown 2. the Of in ten measurement

as

by comparisons, four ft,

0.01 differed the five

and same, were one

by 0.02 differed ft. the All of vertical comparisons

measurement

were

1/8

photogrammetric less. only within The

taken in

measurements or were

I/8 (i.e. in), approximately 0.01 ft but the is it to nearest apparent

exacting close-range that obtained be with the

measurements

very can

I/8 photogrammetric technique. of within the Measurement actual in

sufficiently highway value bridge for and

accurate most are applications.

depression Figure i0. joint Relative filler. of 19

Table 2

and Comparison Selected Field of Some

Photogrammetric Measurements

Measurements

Difference, Description Field, tric, of Pho togramme

Ft Ft Location Ft

depth 0.00 0.06 0.06 I Joint

depth .01 .06 2 .05 Joint

depth .00 .05 3 .05 Joint

.01 .02 pit .03 Surface 1

.00 .03 .03 pit Surface 2

.01 .02 3 Surface .03 pit

.01 4 pit .02 .03 Surface

.02 .07 Crack .05 width 1

.01 .06 Crack .05 width 2

0.08 0.00 3 Crack 0.08 width

developed irregularities bridge surface deck also be The of

can a

photographs. showing the from small deviations of the in One

very way

spaced bridge develop

close surface of deck is at contours to

a a

bridge 64 technique, interval. this the the of Rte. Rte. For test

over

Allegheny study. 0.05-ft County 639 for selected in A contour was

defining for surface interval used evaluate of

the contours to

was use

roughness photographs, Figure Ii. shown from the results in the and

are

rightward pointing by of The of deck shown the the the is contours

crown

perfectly Ideally, figure.

of smooth the the at trans- center

upper a

slope bridge by straight represented

deck would

be

contour a verse a on

edge deck. Furthermore, line horizon- the from the the the of to

crown

for spacing would be the all tal between lines the the contour same

Thus, and the shown. the in nonlinear lines variation contours contour

roughness, adjacent between the width surface, show contours or 20

irregularities, the surface in of deck. linearity the Deviations from

along the lines show degree relative the roughness of these contour

at

points.

spacing wider between A

in of the certain deck contours

a

area

indicates low closer high

spacing

high Adjacent spot;

and spot.

a a a

relatively low bumpy reveal region. spots a

The cracks of extensive the bridge deck the 64

Rte. mapped

on

were

photographs from taken from help above deck. the define cracks the To

they readily that

be could photographs, identified the in so two

proce-

dures used. first The involved wetting the deck with down

were

water.

the evaporated

As it longer remained cracks the in than the water

on

surface, clearly thereby

and defined cracks period the for of time

a

that prevailing with varied the ambient conditions. procedure This did

entirely satisfactory be

the since not of in the to

prove

water

some

cracks evaporated photography before the could be and initiated

completed. The procedure chalking second involved they cracks the

so

readily could be photographs. the in procedure This well, worked

seen

people

could mark the

cracks photographing ahead well of the two

as

so

that there delay.

Considerable effort additional and manual

was no

labor, however,

required

mark cracks. the plan Figure 12 is to

are

a

of the view cracking of network the close-range that by be shown

can

photogrammetry. terrestrial particular this lengths deck On the total

of the cracks 2,625 measured 1,344 total, ft. this Of ft cracks

were

measuring less than 1 width. in

kind this While mapping of would

not

mm

ordinarily bridge be done deck,

results close-range the show that

on a

photogrammetry

be extremely used conduct intricate to can surveys.

Figure ii. spaced Contours 0.05-ft intervals reveal deck surface at

irregularities. 21

bridge 64 Rte. deck of cracks Rte. Plan of Figure 12. in view over

639.

Bridges of Deflection

photo- terrestrial close-range applicability of evaluate the To

bridges structural measuring small for movements, two grammetry

were

could be and the bridges time under construction Both studied. at

were

placement of the subsequent photographed the prior and concrete to

to

steel

of the deflection girders. Thus, load dead the deck steel the

on

measured. The could be weight deck girders of the the under concrete

495 bridge

in 66

bridges Rte. the Metro first of the Rte.

two over

was

29) (alternate the Rte. 5th County; the Fairfax. second Street

was

Lynchburg. railroads in Southern Norfolk and crossing of the and Western

be could that

land bridges

has least of Each these at

open span over

one

opposed

Thus,

the under position the used to structure. to as camera

earlier, the described the

of the the above

structure,

as camera use

photographs being of taken with beneath the used

structure, camera was

bridge of underside the the superstructure. 22

Bridge 495 Metro Rte. over

bridge simply composed 495 supported of The ii Rte. is

spsns.

Deflection 7,

long tsken ft which 107

is measurements

span.

were

on

bearing composed between points and, like remaining all of the is spans,

girders. box steel The vertical each webs box of connected two

two are

by

plste, flsnge bottom the but steel hss esch

web similar top st

to

a

a

regular plste bridge, that girder. of effect, The deck for the in s

completes box the for The rails outbound the inbound section. snd Metro

tracks girder.

centered each box are over

positions, bridge, Three located

the transverse to

camera were

ground established

beneath the mld-span that 7 such its maximum

span

on

deflection could approximately be positions measured. The

camera were

ft below girders. 21 bottom the of mid-span, the box 12 Near

paper.

glued plates girders. bottom the the steel of box From targets to

were

each of overlapping positions, photographs the

taken

to

camera were

photograph typical pairs. the taken from A the create stereo center

position beneath the Figure 13. shown be is noted As in structure

can

photograph, forming place. from the wood for the deck the is in concrete

triangulation approach A used establish hor±zontal the and to was

positions vertical the of of each the

end From targets structure.

on a

65-ft ground, located baseline both horizontal the and vertical on

angles turned the of elevations for each the Two targets. to were

calculated--one baseline. of from each end the Good targets were

between these elevations indicated the control for that the agreement

close-range photogrammetry subsequent making adequate. the In was

triangulation deflection

used than rather

measurements,

program a was

photographic setting stereoplotter. the models The in

measurements

a

original plates glass made from 422F

the using Mann

were

a mono-

principal digitizer and the point located the and rotated comparator,

analysis, the coordinates. positions the the established In target

ground from

the be assumed and fixed the measurements to perspec- were

actually tive assumed The

but the is center true, to was move. reverse

vertical of the this determined be

in movement structure

can manner

displacement bridge the computed of the since

be from apparent can an

perspective of the movement center.

field, by the elevation the the of In base determined

camera was

leveling. differential adding this By elevation the the distance to to

perspective the elevations perspective of the center, true

centers at

the analytical three triangu- determined.

the stations From camera were

lation the elevation perspective of the apparent program, center

was

calculated for each of positions. the difference The between

camera

the the and elevations perspective of the each true apparent

at center

position bridge resulting of the of the from amount movement

gave camera

load girders the subjected. which the to were 23

girder Figure 66 13. Underside of box 7 of Rte. Metro

span

bridge placement. deck prior Twelve for targets to

photogrammetry the shown. are 24

photography.was during conducted

the The when solar

summer, ra-

substantial differential girder diation steel in temperatures can

cause

bridges. girders results of shown The have other steel studies that

flanges during day upward deflect will the the when hotter than top

are

lower.(8,9)

objectives study the of this the of

Since to

one was

photogrammetry close-range measuring for evaluate the of small use

photographed structural several the under times movements, at span was

placed, condition, the unloaded deck before the i.e. the

to

was measure

thermally deflection. induced

photographs bridge eight-day of taken All of the the

were over an

period, photographs period during During the latter of this June. part

placed before taken three the deck

and times times at at two were was

two-day afterwards. taken initial three of The

data

sets

over were a

thermally period provide of reference and the

induced to measurement

a a

period occurring of hours. deflection The last

several

two sets

over a

(after

single during day of data the deck recorded had

concrete were a

used

placed), load deflection been and

of the the dead to

were measure

photographs

approxi- The of these last of taken two sets at span. were

mately day initial the data that the time of the

to same as ensure

reasonably environmental would be conditions the same.

given 3 4. Tables obtained The 3 and Table in measurements are

gives deflection station, the taken from each and measurements camera

photographs taken these listed with reference initial the

June to

are on

A, three positions 23. ground the and the Points

C

B

camera were on

position points beneath the

the and Point A B center span. was camera

approximately 4 located Table 7 side. ft shows the and either C to

were

photography of occurring between deflection the times. span 25

23 and 2:00 June between that indicate The

measurements p.m.

on

by mid-span downward

deflected morning, the the 8:10 at next

span

a.m.

4). order, (Table be result in This

0.011 ft of to

appears average an

higher 2:00 due expected be would have been the since to

at

to p.m.

span

24), (June

morning thermally the 8:10 By induced the next moment.

a.m.

girders would the flanges would, and cooler of be the top

course,

of the 2:00 position downward their with deflect at respect to p.m.

differential

10:08 8:10 and previous afternoon. Between

a.m., a.m.

develop

the would flanges lower and between the temperatures

as upper

girders deflect began flanges the heat, would and to top to

cause

girders the that indicate 4, the upward. Table shown As in measurements

strongly results upward

0.016 These ft. of suggest deflected

average an

only direction showing the technique capable of that the is correct not

magnitude well. of order but their structural small of movements, as

4 the Table shown in of The series

measurements two next

are

weight resulting of the the mid-span from the deflections of span

10:40

24

June and 10:08 deck.

June Between concrete

on a.m.

on a.m.

10:40 0.252 ft. mid-span

30, deflection Between the

a.m. average

was

upward ft by 0.011 deflected 30, however, the

2:22 and June

span p.m. on

3),

(Table 2 about

0.236 ft yield

of deflection final

to or average

a

13/16 once differential again upward indicates deflection This in.

a

lower. being the flanges than effect, with the top temperature warmer

girders steel of the

plan deflection for the calculated value The

6here

1/16

While is weight given in. 2

of the under the

concrete as was

values, 3/4-in be plan it measured and between the difference cannot

a

Slight varia-

photogrammetric results in the that assumed error. are

explain of could

of steel the the dimensions tions in concrete

some or

developed of each from photogrammetric difference. The the measurements

showing differ- reasonably consistent, positions

the three camera are

i/8 but

all for less the order of

in

measurements one

or

ences on

i/4 could be difference this of by less than differed Some in. which

during occurring the bridge the small in thermal attributed movements

to

another.

position from required

the

timed to to one camera move 26

3 Table

(Span Photogrammetric Mid-span Deflection 7, Measurements

at

495) Bridge 66 Rte. Metro Rte. over

Deflection, Relative Ft*

Time Condition Average Point Date Point A Point B C

6-23 00 Unloaded 2- Reference Reference Reference p.m.

6-24 8"10 Unloaded 0.018 0.001 0.011 0.015 a.m.

6-24 10:08 0.001 Unloaded 0.014 0.002 0.005 + + + a.m.

6-30 10"40 0.259 Loaded 0.239 0.242 0.247 a.m.

6-30 22 0.246 2- 0.230 Loaded 0.236 0.232 p.m.

Downward deflection with the reference respect to measurement

Upward deflection reference with the respect to measurement

4 Table

Mid-span Photography Deflection Occurring Between Times

(Span 495) 7, Bridge 66 Rte. Metro Rte. over

Deflection, Ft*

Poin fl Point, B..P.o.in.t. .A.verage Period Time C t

6/23 6/24 2:00

8:10 0.001 0.018 0.0015 0.011 p.m. a.m.

6/24 6/24 8"10 10"08 0.015

0.017 0.016 0.017 + + + + a.m. a.m.

6/24 6/30 -10:40 10-08

0.253 0.244 0.258 0.252 a.m. a.m.

6/30-

6/30

10-40 0.013 0.009 0.010 2"22 0.011 + + + + p.m. a.m.

Downward deflection

Upward deflection 27

Bridge Railroads 5th and Southern Street & W N over

plate bridge three-span, 5th steel of The continuous Street is

a

girder design. study, during under the Since it construction it

was

close-range photogrammetry provided the opportunity

to to

measure an use

deflection

girders weight resulting deck. of of from the concrete a

long

bridge 147 The 5th of ft end and the the Street two

spans are

long.

bridge 170 of the ft continuous is is Because center

span a

design, by girders deflection the of of influenced the is steel

any span

loading bridge the unlike the 5th other therefore Street is

span; any on

simple availability bridge the earlier. the discussed Metro Due to span

bridge, Figure of shown beneath the 170 ft land the in center

open span,

placed 14, targeted being study. Figure for shows

the 15 targets was on

composed of the the of haunched steel five underside which is

span, girders.

procedures photogrammetric taken for used The the

measurements on

bridge bridge. this those the similar used

Three

Metro to

rows were on

right applied angles of girders centerline the the targets to to at

were

before,

portion and the middle of the three

As

span. camera near

positions ground of established

beneath the the

center

row were on

bridge. right angles Elevations and the determined targets at to

were

girders mid-span. the addition points all the and In

target to at at on

engineer's

photogrammetric level take the used

measurements, to

was an

girders points elevations before after all the both the and target at

photogrammetric check loaded the with the deck

concrete were as a on

photographs All of the elevation and measurements. measurements

were

placed September deck before taken occasions; the

and

in two

was on one

completed. April following another

of the deck the after in year was

Finally, the before used after elevation and to measurements were

girders calculate of the the deflection each of the steel target at

o

placed bridge points. skewed 27 but the Since the is targets at at

are

angles right bridge, additional the deflection

measurements at to

mid-span photographs. taken from the were

leveling by taken comparison with deflection of the A

measurements

•from photogrammetry presented those Table deflections The 5. in is at

according the 5 from from i listed 15 numbered and

targets to to are row

of each the deflection measured side the the The of to

east

west

span.

leveling by by given photogrammetry point determined that

and

are as

along points difference with the of there the 7 15 the between For two.

of 15 the differed difference

the between Five measurements. two

was

no

by by ft, Therefore, 0.01 by of 0.02 0.03 ft. 15 12 the ft and

two

one

I/8

by

ft, points The 0.01 about differed

than in.

average or no more

difference techniques 0.01 between ft. the less than two was 28

steel

continuous

three-span,

the of the of

span 14. center View Figure

bridge. girder 5th Street

5th

of Street

the placed

center being span Targets 15. on Figure

bridge. 29

girder the determined from mid-span of each The deflection

at

as

slight upward noted, photographs 6. be given

Table As in is a can

0.07.

ft downward the With measured which did deflection not

agree was

from either

plans. values provided bridge The deflection the average on

mid-span resulted deflection

6 little Table Table that 5 suggest

very

or

investigat±on, placement Upon it deck. of the the from concrete was

for continuous calculation of deflections for the found that

span

bridge placed the bridges entire that the assumed is is it concrete

on

The br±dge

this constructed in

the However, not at manner.

was once.

placed of end the positive

the in two

moment spans concrete

areas was

region of placed positive date, first; the later in

it moment at

a was

regions later, negative still the and the in moment

center over span,

that entirely from of different actual piers. The situation the was

plastic

the all the deck assuming that at structure concrete

one was on

example,

for the placed end the When is time. two concrete spans,

on

end the upward. the will deflect After sets concrete center on span

with composite the action due of the inertia increases to moment spans

of the deflection downward increased the steel. This resistance to

pos•tlon placed deck

its the when moment concrete

center span

on was

placed subsequent the weight Thus, of the region. the to

concrete

only girders back placement the deflected have initial center span

may

Consequently, deflection the position. approximate unloaded their to

leveling

by

checked by photogrammetric and obtained data

very

are means

interesting

actually likely occurred. is It what of accurate

measures

plan calculations deflection the which assumption that the

note to up.on

engineer photo.grammetric when the known the based

not to

was were

made. leveling photogra•metric and measurements were 30

Table 5

by Photogrammetric Comparison the Deflections the of Measured

Engineer's Technique those Using with Obtained Level

an

(Span Virginia) Lynchburg, Bridge, 2, 5th Street

Deflection, Ft* Measured

Leveling Photogrammetry ,,T.arg,et Difference No.

0.00 0.02 0.02

0.01 0.02 0.01 + +

0.02 0.02 0 + +

0.03 0.02 0.01 + +

0.01 0.02 0.03 +

O.O3 O.O3 0

0.01 0.01 0

0.01 0.02 0.01 + +

0.01 0.00 0.01 +

0.00 0.00 0

0.02 0.01 0.03 +

0.01 0.01 0

0.00 0.00 0

0.01 0.01 0

,,0,..03

0.01 0.02 .-

Average -0.002 0.009 -0.001

deflection Downward

Upward deflection 31

Table 6

Photogrammetric Mid-Span Deflection Measurements

at

(Span Virginia) 2, Lynchburg, Bridge, 5th Street

Deflection, Girder Number Ft

0.002 1 +

0.015 2 +

0.024 3 +

4 0.005 +

0.00 5

Average 0.009 +

CONCLUSIONS

following study The conclusions from be this close- of drawn

can

applied

photogrammetry

highway terrestrial of

to measurements range as bridges.

pho£ogrammetry developments I.

50 60 last the Over in

years,

or

photography stereoplotting. mainly been have aerial and in

During close-range however, few the last terrestrial

years,

photogrammetry being has been rediscovered for used and is

applications disciplines.

of various wide in Some

range a

applications highway bridges have demonstrated the

recent to

ability technique of difficult this otherwise to meet

measure-

and evaluation requirements using less lower cost, ment at

time, causing disruption less traffic be and would the than to

with methods. other many case

close-range 2. study The results of that the terrestrial show

photogrammetry be the of for used small measurement

can

magnitude displacements of order structural and

differences elevation. deflection the of The in measurements

girders of loading steel under that suggest concrete

i/8 accuracies achieved the be of with order

in

on can

10/1318 normal using that

utilized the

UMK

care camera was

study. field technique the thus The in could used be

to

indirectly general magnitude determine of the of order loads

imposed

structural members whenever their deflections upon

can

be measured.

10/1318

3. The satisfactory UMK results for the gave

camera

during taken study. the within Accuracies measurements

were

the desirable being for of the types

measurements range

taken. preferred This

because others

of

camera was over some

large, Consequently, 5 its format. 7 in, in be could it

x

used distances closer object required the and fewer

at to

photographs having than smaller formats.. cameras

Close-range photogrammetry 4. bridge be useful

deck

can on

by eliminating condition the for need sketches field

surveys

by reducing and the of field required.

amount measurements

addition, photographs the In be obtain used additional to can

information if needed

used be reference

to

gauge or

a as

potential changes future condition, elevation, in relative

or

advantages position. might These primary the be

reason

close-range

photogrammetry using for bridge for deck

a

condition savings the since field in work and

survey,

by photogrammetry offset the is personnel for need manpower

llft and bucket truck and operator. a

5. of small elevation,-such Measurements differences in those

as

bridge irregularities, associated with deck surface be

can

i/8 accomplished within using accuracies normal in to care.

probably could Greater accuracies obtained be if

necessary.

irregularities Surface by developing also be shown

can

close-interval photographs. from the contours

Extremely 6. bridge intricate

deck condition such

surveys, as

cracks, the mapping accomplished of be with close- can

photogrammetry. While this of would type range

not survey

ordinarily

conducted, study be this did in it

to serve

capabilities demonstrate technique. the of the of some 33

RECOMMENDATIONS

preliminary results by the Spero, work results of the the Based

on

engineer, photogrammetric it study, of the opinion the and of this

was

Transportation Highways of Virginia & Department the recommended that

Subsequently, 10/1318 study. the the purchase used in the UMK

camera

making capability

of

purchased, the giving Department the

use

was camera

the need in arises the photogrammetry when close-range terrestrial of

Recently, disciplines.

other transportation well in field

an

as as

Department's

the purchased, adds which analytical stereoplotter to

was

photogrammetry terrestrial Close-range capabilities. photogrammetric

might problems that

solving difficult approach offers measurement

to

an

rehabilitation. It repair, and bridge maintenance, with associated be

of the engineers made be bridge highway and that recommended is

aware

technique. capability availability of this and 34

ACKNOWLEDGEMENTS

study could This have been conducted without the of services F. not

photogrsmmetry Habel, Bales snd of the of G. W. the section B. Jr.

Highways Virginis Department Transportation. of snd cooperation The of

Misenheimer, Prewoznik, bridge Sellars and W. rL. district F. L. L. L.

Lynchburg, Culpeper engineers the districts, Staunton, and in

respec-

tively, indispensable conducting French, the field studies. in J.W. was

supervisor, technician assisted work with 66 the field the Rte. Metro

on

gratefully acknowledges bridge. by The suthor the rendered assistance

individuals. all of these 35

REFERENCES

Raymond I Davis, E., Foote, Anderson, Francis S. James J. and Edward

Mikhail, Theory Surveying M. Practice, ed., and 6th McGraw-Hill,

1981.

Moffitt, Mikhail, H., Photogrammetry, and F. E. M. Harper Row, and

York, 1980, 648 New pp.

Atkinson, Dev.e.lopment .Close Photogrammetry..-•..l, ..R.an•e B., K. in

Applied Publ•shers, Ltd., Science London, 1980.

"The Spero, Photogrammetric Paul A.C., Recording

of Historic

Transportation

.VHTRC 83-R35, Sites, " Highway Virginia and

Council,'

Transportation Charlottesville, Research Virginia, June

1983.

"S

Scott, P.J., tructural Deformation Measurement of Model Box

a

Brldge," Photogrammetric

Girder

9, Record, Vol. 51, 361-76, No. pp.

1978.

.phot.o.g.raphy, ! F.unct.i0.n.a Publishing Company, 18, PTN 2, Vol.

No.

March/April 1983, 41. p.

"Mapping Eng..i.neering. Record Test," Speeds Bridge New April 19, s

1984, 27. p.

"Factors Hilton, Affecting H., M.

Deflections Girder During Bridge

Highwa

Deck 40.0, Construction, h

"

Re Record 55-68 • .rc

s pp. ea

Washington, C., 1972. D.

"Deflections Camber and in Loss Heat-Curved

Girders,"

Transportation.

950, Research Record Bridge No. Second

'•o'l'.'

'D. Engineering Conference, Washington, 2, 1984. C., 37