Environmental and Social Monitoring Report

Project Number: 51051-001 July–September 2020 November 2020

THA: Natural Gas Power Project

Prepared by AFRY () Ltd.

The environmental and social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

REPORT

ASIAN DEVELOPMENT BANK JAPAN BANK FOR INTERNATIONAL COOPERATION MIZUHO BANK, LTD. BANK PUBLIC COMPANY LIMITED SUMITOMO MITSUI BANKING CORPORATION EXPORT-IMPORT BANK OF THAILAND

Gulf SRC 2,500 MW Combined Cycle Power Plant Project

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7 [July 1st 2020 to September 30th 2020]

127000407 10 November 2020 Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 1

Project Project No. Gulf SRC 2,500 MW Combined Cycle Power Plant 127000407 Project

Revision Date Revision 0 10 November 2020

Address AFRY (Thailand) Ltd. Vanit II Bldg., 22nd Floor, Room No. 2202-2204, 1126/2 New Petchburi Road, Makkasan, Rajchthewi, Bangkok 10400 THAILAND

Phone +66 2 108 1000 (THAILAND)

Contact

Mr.Mark Wilson

Mobile Click here to enter Mobile phone.

E-mail

[email protected]

Client

ASIAN DEVELOPMENT BANK JAPAN BANK FOR INTERNATIONAL COOPERATION MIZUHO BANK, LTD. BANGKOK BANK PUBLIC COMPANY LIMITED SUMITOMO MITSUI BANKING CORPORATION EXPORT-IMPORT BANK OF THAILAND

Report Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7 [July 1st 2020 to September 30th 2020]

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 2

NOTICE

It is the good faith and belief of AFRY (Thailand) Ltd (“AFRY” or the “LTA”) that the estimates and conclusions contained in this report are reliable. However, the LTA does not warrant or guarantee their accuracy. Use of the report and its estimates shall, therefore, be at the user’s sole risk. Such use shall constitute a release of the LTA from and against any liability in connection with such use, whether liable for special, indirect or consequential damages, whether such liability is asserted to arise in contract, negligence, strict liability or other theory of law. This document has been prepared for Asian Development Bank, Japan Bank for International Corporation and Bangkok Bank Public Company Limited in relation to the 2,500-megawatt combined cycle natural gas fired power plant project of Gulf SRC Company Limited in Hemaraj Eastern Seaboard Industrial Estate, Chonburi Province in Thailand (the “Project”). AFRY acknowledges and agrees that Asian Development Bank, Japan Bank for International Cooperation (the international arm of Japan Finance Corporation), and Bangkok Bank Public Company Limited, and certain other lenders of the Project accepted by the LTA from time to time (hereinafter jointly the “Lenders”) are entitled to and will rely on this report. The LTA consent to making this report available to the Lenders is subject to and on the understanding that before receiving and relying on this report, each Lender has as set out in the Engagement Agreement signed between the LTA, Gulf SRC Company Limited, Independent Power Development Company Limited and Bangkok Bank Public Company Limited on July 2018 concerning the LTA’s engagement (“Engagement Agreement”) either itself signed the Engagement Agreement or confirmed and accepted in writing that it is aware of, understands and agrees to the scope of the LTA’s engagement and the liability as well as other terms and conditions which may apply as set out in the Engagement Agreement and without limitation confirms that it unconditionally agrees to be bound by the terms of the said Engagement Agreement (including without limitation clauses 9.7 and 11) and any limitations of or exceptions to liability included for the benefit of the LTA, and subject to the below conditions. All the above-mentioned Lenders hereby entitled to rely on this report acknowledge and agree that, prior to any issue becoming litigious, all disputes arising out of or in connection with the report shall be channelled through one Lender only. The Lender may not use the contents of this report for any purpose other than: a) the provision of financial accommodation to Gulf SRC Company Limited in connection with the Project including disclosing it to external accountants, auditors or lawyers for said purpose on the basis that they do not rely on the report and keep it confidential; b) if required by mandatory law or in accordance with an official directive or request of a governmental authority or agency for its internal purposes which, if not having the force of law, compliance is in accordance with good practice of responsible banks or financial institutions on the basis that they do not rely on the report and keep it confidential; or c) in connection with any litigation or proposed litigation concerning the report. The opinions and forecasts contained in this report have been prepared in good faith, with reasonable care and due diligence based on reasonable assumptions. However, no opinion or forecast in this report is, or should be, relied upon as a promise or representation of the future. Actual results may be different from the opinion contained in this report, as anticipated events may not occur as expected and the variation may be significant. All the above mentioned Lenders hereby entitled to rely on this report acknowledge and agree that monetary damages may be an insufficient remedy for the LTA if the recipient or Lender breaches the conditions of disclosure listed in paragraphs a) to c) above and in addition to any other remedy which may be available in law or equity, the LTA may seek injunctive relief to prevent any actual or threatened breach of the conditions of disclosure and to compel specific performance of those conditions of disclosure.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 3

EXECUTIVE SUMMARY

Gulf SRC Company Limited (“GSRC” or the “Owner”) is developing Gulf SRC 2,500 megawatt (“MW”) Combined Cycle Power Plant (“CCPP”) project in Hemaraj Easter Seaboard Industrial Estate (“HESIE”), Sriracha District, Chonburi Province, approximately 140 km east of Bangkok. Natural Gas will be transported to GSRC through a new 2.5 km long gas pipeline (“Interconnecting Pipeline”). EGAT will build a new 10.9 km overhead transmission line to connect GSRC’s switchyard with EGAT’s Pluak Daeng Substation. Raw water to GSRC will be supplied by East Water via the Hemaraj Raw Water Pipeline. This is the seventh Quarterly Environmental & Social (“E&S”) Monitoring Report of AFRY (the Lenders Technical Advisor) and covers the period from July 1st, 2020 to September 30th, 2020. AFRY would like to thank the Owners and EPC Contractor for their valuable support during the site visit and for providing the documentation requested to prepare this report.

Health and Safety

The key OHS statistics for the construction monitoring period are 2,458,371 safe man hours accumulated for the Power Plant Area/Raw Water Pond Area and 109,107 safe man hours accumulated for the Interconnecting Pipeline. There were 6 HSE incidents for the Power Plant Area/ Raw Water Pond Area and 1 HSE incident for the Interconnecting Pipeline. A fatality did occur at the Project site on August 19th, 2020 during transformer assembly construction at Block#2. The fatality has not been reported as a Project fatality or as a Lost Time Incident due to the incident occurring to a 4th tier contractor of Sino-Thai. Contractors past the 2nd tier contractors to Sino-Thai are not covered under the requirements of the Project HSE Management Plan and therefore incident reporting. The fatality is regarded as a Significant Safeguard and Social Reporting Event according to the Common Terms Agreement (clause 18.44) and the Owner has carried out the appropriate actions required by the Common Terms Agreement. High risk activities are now being identified for all Contractors of Sino-Thai past the 2nd tier contractor and are subject to Job Safety Analysis (JSA) if the activity needs to be performed onsite. In response to the fatality the LTA recommends the following additional measures: • Accident/incident reporting procedure is also updated to reflect the findings of the fatality and to ensure all accident/incidents which occur to contractors past the 2nd tier contractor of Sino-Thai (based on the high risk activities identified) are now separately reported and included in the EPC Contractor monthly reports; and • The high risk activities are reviewed in the weekly EHS meetings and those activities are supervised by the EHS personnel of the EPC Contractor.

Labour and Working Conditions and Security

The number of workforce personnel as of September 25th, 2020 is 2,919. Welfare facilities at the Project site including rest shelters, toilet/bathroom facilities, drinking water stations and medical facilities which continue to be adequately managed. Hygiene/cleanliness and the welfare facilities at the workers camp also continue to be adequately managed. In general, the hygiene/cleanliness of the workers camp was observed to be adequate in Zones 1, 2 and 3 of the workers camp. However, in the workers zone a number of room doors were observed to be damaged.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 4

Stakeholder Engagement

During this construction monitoring period, two education activities were undertaken on September 16th, 2020 and September 24th, 2020 to pass on knowledge to local community members concerning the power plant commissioning activities. The activities were undertaken to comply with Project requirements of undertaking 2 education awareness events per year for local community members.

Environmental and Social Monitoring

The EHS capacity recorded for this construction monitoring period and the training undertaken is considered to be sufficient. The Owner and Contractor continue to implement specific HSE procedures and programs for the Power Plant and Interconnecting Pipeline, this includes implementing COVID-19 prevention methods. It is AFRY’s opinion that the Project was operating in compliance with most of the Project E&S requirements during the construction monitoring period. Corrective actions have been identified concerned with housekeeping/material storage, hazardous waste storage, repairing damage to room doors at the workers camp (Myanmar workers zone), updating HSE procedures for Accident/Incident Reporting, Lifting Rigging and Chemical Handling Safety and knowledge sharing to local communities concerned with the Projects operation.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 5

Contents

1 Introduction ...... 10 1.1 Project Description ...... 10 1.2 Role of AFRY ...... 14 1.3 Objectives of the Report ...... 14 1.4 Construction Monitoring Period ...... 15 1.5 Project Participants ...... 15 1.6 Site Visit Schedule ...... 15 1.6.1 Kick Off Meeting ...... 15 1.6.2 Physical Verification ...... 15 1.6.3 Onsite Discussions and Interviews ...... 17 1.7 Reports Reviewed ...... 18

2 Health And Safety ...... 20 2.1 Overview ...... 20 2.2 Health and Safety Statistics ...... 20 2.3 Fatalities ...... 22 2.4 Accident / Incident Reporting ...... 24 2.5 HSE Staff ...... 24 2.6 Low Risk Issues ...... 25

3 Labor And Working Conditions And Security ...... 26 3.1 Workforce Profile and Recruitment ...... 26 3.2 Welfare Facilities at Project Site ...... 27 3.3 Workers Grievance Mechanism ...... 28 3.4 Workers Camp and Transportation ...... 29 3.4.1 Workers Camp ...... 29 3.5 Transportation ...... 31 3.6 Security ...... 31 3.6.1 Project Site and Block Valve Station ...... 31 3.6.2 Workers Camp ...... 31

4 Stakeholder Engagement...... 32 4.1 Engagement Activities and CSR ...... 32 4.2 Stakeholder Grievance Mechanism ...... 32

5 Environmental And Social Monitoring ...... 33 5.1 EHS Capacity (Resources and Training) ...... 33 5.1.1 EHS Capacity (Resources) ...... 33 5.1.2 EHS Training ...... 33

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 6

5.2 EHS Licenses, Permits, Authorizations and Compliance Status ...... 34 5.3 EHS Management System and Implementation Status ...... 36 5.3.1 EHS Policies ...... 36 5.3.2 Organisational Structure and Staffing ...... 37 5.3.3 HSE Procedures and Programs ...... 37 5.3.4 Training Requirements ...... 39 5.3.5 EHS Monitoring and Reporting ...... 39 5.4 Compliance with EHS National Laws and Regulations ...... 40 5.4.1 Construction Environmental Monitoring ...... 40 5.4.2 Ambient Air Quality ...... 40 5.4.3 Noise...... 41 5.4.4 Wastewater from Workers ...... 44 5.4.5 Wastewater from Water Treatment Plant ...... 47 5.4.6 Wastewater from Hydrostatic Test (Interconnecting Pipeline) ...... 47 5.4.7 Waste...... 47 5.5 Compliance with ESIA/EMP, ADB Safeguards, IFC Performance Standards and IFC EHS Guidelines ...... 48 5.5.1 IFC EHS Guidelines ...... 82 5.5.2 Land Acquisition and Involuntary Resettlement ...... 84 5.6 Associated Facilities ...... 84 5.6.1 Hemaraj Raw Water Pipeline ...... 84 5.6.2 500 kV Overhead Transmission Line ...... 84

6 Corrective Action Plan ...... 86

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 7

Figures and tables

Figures

Figure 1-1 Location of GSRC Project Site ...... 10 Figure 1-2 Project Area within HESIE ...... 11 Figure 1-3 Interconnecting Pipeline Start Point and End Point ...... 12 Figure 1-4 Proposed Alignment of the 500 kV Overhead Transmission Line (Red Line) ...... 12 Figure 1-5 Alignment of Hemaraj Raw Water Pipeline(Yellow Line) ...... 13 Figure 1-6 Areas of Physical Verification During Site Visit – Power Plant Area and Raw Water Pond Area ...... 16 Figure 1-7 Location of Contractors Workers Camp in Relation to the Power Plant Area and Raw Water Pond Area ...... 17 Figure 1-8 Location of Proud Village in relation to Power Plant Area ...... 18 Figure 5-1 Location of Predicted Maximum NO2 Concentration ...... 41 Figure 5-2 Noise Monitoring Locations during Steam Blowing at Block#1 ...... 43

Tables

Table 2-1 HSE Statistics 1 ...... 20 Table 2-2 HSE Statistics 2 ...... 21 Table 2-3 HSE Incidents ...... 21 Table 2-4 CTA Requirements and Actions Undertaken by the Owners ...... 23 Table 2-5 HSE Staff for the Power Plant Area and Raw Water Pond Area ...... 24 Table 2-6 HSE Staff for the Interconnecting Pipeline ...... 25 Table 3-1 Workforce Number ...... 26 Table 3-2 Female Workers Roles and Grades ...... 26 Table 3-3 Labour Protection Act Requirements and Compliance for Welfare Facilities ...... 27 Table 3-4 Workers Camp Living Statistics ...... 29 Table 3-5 Owner Workers Camp Checklist...... 29 Table 5-1 EHS Training During the Construction Monitoring Period ...... 33 Table 5-2 EHS Training for October, November and December 2020 ...... 34 Table 5-3 Status of EHS Related Permits ...... 35 Table 5-4 Status Approval for Interconnecting Pipeline ...... 36 Table 5-5 Status of EHS Polices ...... 36 Table 5-6 Status of Existing HSE Procedures and Programs for the Power Plant ...... 37 Table 5-7 Status of Existing HSE Procedures and Programs for the Interconnecting Pipeline .... 38 Table 5-8 Noise Monitoring Results during Steam Blowing at Block#1 ...... 42 Table 5-9 Water Quality Monitoring Results at the Project Site ...... 45 Table 5-10 Water Quality Monitoring Results at the Workers Camp ...... 46

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 8

Table 5-11 Wastewater Monitoring Results from Hydrostatic Test (Interconnecting Pipeline) ... 47 Table 5-12 Waste Monitoring Results ...... 48 Table 5-13 Status of Project Against Project E&S Standards of the ESIA/EMP ...... 49 Table 5-14 Project Compliance with IFC EHS Guidelines ...... 82 Table 6-1 Corrective Action Plan for the Construction Monitoring Period (July to September 2020) ...... 87

Appendices

Appendix 1 – Site Photos ...... 90

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 9

GLOSSARY OF TERMS

ADB Asian Development Bank CSR Corporate Social Responsibility E&S Environmental and Safety EHS Environmental, Health and Safety EMP Environmental Management Plan EPC Engineering, Procurement and Construction ESIA Environmental and Social Impact Assessment GT Gas Turbine HESIE Hemaraj Easter Seaboard Industrial Estate HSE Health, Safety and Environment IFC International Finance Corporation JBIC Japan Bank for International Cooperation LTS Lenders’ Technical Advisor MHPS Mitsubishi Hitachi Power Systems Project (Thailand) MOI Ministry of Interior MW Megawatt OHS Occupation Health and Safety ONEP Office of Natural Resources and Environmental Policy and Planning PPA Power Purchase Agreement SCOD Schedule Commercial Operation Date SPS Safeguard Policy Statement WBG World Bank Group WHO World Health Organisation

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 10

1 Introduction

1.1 Project Description

Gulf SRC Company Limited (“GSRC” or the “Owner”) is developing Gulf SRC 2,500 megawatt (“MW”) Combined Cycle Power Plant (“CCPP”) project in Hemaraj Easter Seaboard Industrial Estate (“HESIE”), Sriracha District, Chonburi Province, approximately 140 km east of Bangkok. The site location is shown in Figure 1 1 and location within the HESIE is shown in Figure 1-2

Figure 1-1 Location of GSRC Project Site

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 11

Figure 1-2 Project Area within HESIE GSRC is being developed on an IPP basis and a 25-years Power Purchase Agreement (“PPA”) has been signed with EGAT. The Schedule Commercial Operation Date (“SCOD”) of Unit 1, Unit 2, Unit 3 and Unit 4 are March 31st, 2021, October 1st, 2021, March 31st, 2022 and October 1st, 2022 respectively. Natural Gas will be transported to GSRC through a new 2.5 km long 28 inches diameter gas pipeline (“Interconnecting Pipeline”). The Interconnecting Pipeline will connect to the power plant from PTT’s 5th pipeline. The Interconnecting Pipeline start point and end point is shown in Figure 1-3

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 12

Figure 1-3 Interconnecting Pipeline Start Point and End Point

EGAT will build a new 10.9 km long 500 kV double circuit 4 x 1272 MCM ACSR Overhead Transmission Line to connect GSRC’s switchyard with EGAT’s Pluak Daeng Substation. The 500 kV Overhead Transmission Line is considered an “associated facility” in accordance with Asian Development Bank (“ADB”) Safeguard Policy Statement (“SPS”) 2009 and the International Finance Corporation (“IFC”) Performance Standards 2012 as this facility will not be funded as part of the Project. The alignment of the 500 kV Overhead Transmission Line as from the GSRC’s switchyard to EGAT’s Pluak Daeng Substation is shown in Figure 1-4 (red line).

Figure 1-4 Proposed Alignment of the 500 kV Overhead Transmission Line (Red Line)

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 13

Raw water to GSRC will be supplied by East Water at a maximum flow rate of 63,000 m3/day. East Water is managing the raw water supply source within the eastern region area of Thailand. GSRC will have three raw water ponds located adjacent to the power plant area. The GSRC raw water ponds have a total capacity of 189,000 m3. The Hemaraj Raw Water Pipeline to supply the raw water during construction and operation is also considered an associated facility under ADB SPS 2009 and the IFC Performance Standards 2012. The alignment of the Hemaraj Raw Water Pipeline is shown by the yellow line in Figure 1-5

Figure 1-5 Alignment of Hemaraj Raw Water Pipeline(Yellow Line)

Wastewater from GSRC will be discharged back into the wastewater discharge of HESIE at an interface point located north west of the power plant. GSRC will consist of four separate power blocks, all consisting of one gas turbine, one steam turbine and one HRSG in a 1-1-1 single shaft arrangement. The gas turbine (“GT”) model selected for GSRC is MHPS M701JAC gas turbine. GSRC will be cooled through the user of an indirect “recirculating” wet cooling water system using mechanical draft cooling towers. GSRC will use natural gas as primary fuel with diesel oil used as back-up fuel. The Engineering, Procurement and Construction (“EPC”) arrangement for GSRC consists of the following contracts:

• The Supply Contract between Gulf SRC Company Limited (“GSRC” or the “Owner”) and Mitsubishi Hitachi Power System, Ltd, as Supplier, for design and engineering services performed outside of Thailand and for the supply of equipment and materials to be imported into Thailand date February 8th, 2018;

• The Construction Contract between Gulf SRC Company Limited (“GSRC” or the “Owner”) and the consortium of Mitsubishi Hitachi Power Systems Project (Thailand) Company Limited

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 14

(“MHPS-PTC”) and Sino-Thai Engineering and Construction Public Company Limited (the “Contractor”) dated February 8th, 2018; and

• The Coordination Agreement between the Owner, the Supplier and the Contractor (the Supplier and the Contractor are jointly referred to as the “EPC Contractor”) dated February 8th, 2018.

For design review and construction management purpose for the EPC contract, GSRC has entered into an Owner’s Engineer agreement with Black and Veatch. For construction site supervision (including environmental & safety), GSRC has entered into an Owner’s Engineer agreement with EGAT. The Notice to Process for the EPC contractor was issued on December 3rd, 2018, with the Limited Notice to Proceed issued in July 2018. The financial close for GSRC was achieved in Q4/2018.

1.2 Role of AFRY

AFRY (Thailand) Ltd. (“AFRY” or the “LTA”) has been appointed in the role of Lenders’ Technical Advisor for the construction and operating and maintenance phases of the Project up to the third year of the operational phases of all Units. During this time the LTA will monitor the progress of GSRC and advise the Lenders in all technical, management and environmental and social (“E&S”) issues that may have a material effect on the financial standing and success of GSRC. During the construction period the LTA will make quarterly site visits and meetings with the Owner and relevant parties.

1.3 Objectives of the Report

The objectives of the quarterly E&S monitoring are as follows: • To assess the Projects compliance with the following Project E&S standards during construction: − Applicable Thailand Laws, legislation and regulations; − ADB SPS (2009); − World Bank Group (“WBG”) General Environmental, Health and Safety (“EHS”) Guidelines (2007); − WBG EHS Guidelines for Thermal Plants (2008); − IFC Performance Standards (2012)1 , including: ▪ PS1: Assessment & Management of Environmental & Social Risks & Impacts; ▪ PS2: Labour and Working Conditions; ▪ PS3: Resource Efficiency and Pollution Prevention; ▪ PS4: Community Health, Safety, and Security; ▪ PS5: Land Acquisition and Involuntary Resettlement; ▪ PS6: Biodiversity Conservation and Sustainable Management of Living Natural Resources; ▪ PS8: Cultural Heritage.

1 FC PS7 (Indigenous Peoples) is not considered applicable to the Project

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 15

− Japan Bank for International Cooperation (JBIC) Guidelines for Confirmation of Environmental and Social Considerations, 2015. • To review the implementation of the mitigation and monitoring programmes specified in the Environmental Management Plan (“EMP”) developed as part of the Environmental and Social Impact Assessment (“ESIA”) for ADB dated October 2018; • To review the status of EHS management onsite, including the Company’s EHS Management System, procedures and training and to identify areas for improvement; • To review the Projects EHS records and compliance with respect to the site specific management system by the Owners, EPC Contractor and sub-contractors; • To provide objective reports to the Lenders confirming compliance and if not, recommend corrective actions, as appropriate to the Project during construction.

1.4 Construction Monitoring Period

This E&S Monitoring Report is the seventh Quarterly E&S Monitoring Report of the LTA and covers the period from July 1st, 2020 to September 30th, 2020. The report is based on inputs received from the Owner, the EPC Contractor and discussions held on site during the LTA’s site visit on September 20th, 2020.

1.5 Project Participants

This quarterly site visit was attended by the following LTA representatives: • Mr. Mark Wilson (LTA’s Senior Environmental Consultant); • Mr. Ilkka Lassila (LTA’s Project Manager); and • Mr. Pramual Numsong (LTA’s Senior Project Engineer).

1.6 Site Visit Schedule

1.6.1 Kick Off Meeting

A kick off meeting was held at the Owners site office to confirm the agenda. The meeting was attended by representatives of GSRC and the LTA.

1.6.2 Physical Verification

The LTA team accompanied by the representatives of the Project team undertook site visits of the construction area to assess the status and compliance with respect to EHS requirements. The LTA team made physical and visual inspections/verification of the construction phase activities and onsite management of EHS issues within the Power Plant Area and Raw Water Pond Area shown in the plot plan in Figure 1-6. Construction activities at transmission line towers currently undergoing stringing were also observed.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 16

Figure 1-6 Areas of Physical Verification During Site Visit – Power Plant Area and Raw Water Pond Area

Source: MHPS Thailand GSRC Power Plant Project Presentation, 24th October 2019.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 17

In addition, inspection of EHS issues was also undertaken at the Contractors workers camp located approximately 1 km east of the Project site. The location of the Contractors Workers Camp in relation to the Power Plant Area and Raw Water Pond Area is shown in Figure 1-7.

Figure 1-7 Location of Contractors Workers Camp in Relation to the Power Plant Area and Raw Water Pond Area

Photographs taken during the physical verification are provided in Appendix 1.

1.6.3 Onsite Discussions and Interviews

Onsite discussions and interviews were undertaken with representatives of GSRC, EGAT and the EPC Contractor. The following topics were discussed for the construction monitoring period and findings are presented in this report. • EHS management plans and procedures being developed and implemented; • EHS organizational structure; • EHS mitigation / management programs implemented; • EHS monitoring programs undertaken; • EHS incidents and corrective actions; • EHS training; • EHS meetings; • EHS initiatives; • Waste disposal procedures;

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 18

• Grievance records (workers and communities); • Stakeholder engagement/Corporate Social Responsibility (“CSR”) activities undertaken; • Status of land acquisition associated with the 500 kV Overhead Transmission Line. An interview with the Deputy Village Head of Moo 3 which includes the Proud Village immediately to the south of the Power Plant Area (location shown in Figure 1-8) was also undertaken to understand any construction related issues that may be impacting the village or any new concerns related to the operation phase.

Figure 1-8 Location of Proud Village in relation to Power Plant Area

1.7 Reports Reviewed

The relevant Project documents pertaining to E&S have also been reviewed. This was aimed at understanding the ongoing implementation, record maintenance, internal monitoring and reporting and mandatory regulatory compliances required for the Project. The following documents were reviewed by AFRY for this construction monitoring period: • GSRC Progress Technical Reports for July 2020, August 2020 and September 2020; • EGAT Progress Technical Report for NTF, July 2020, August 2020 and September 2020; • Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation (EHS), October 20th, 2020; • Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation (Site Progress), October 20th, 2020;

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 19

• GSRC Job Role and Grades for Females, October 2020; • GSRC Summary of Workers Camp Statistics, October 2020; and • Incident Report No. 2020/012 (Final Report) (Fatal Accident During Tire Maintenance at Block#2 Main Transformer Area).

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 20

2 Health And Safety

2.1 Overview

Occupational Health and Safety (“OHS”) for the Power Plant continues to be principally managed through the Health, Safety and Environment (“HSE”) Management Plan (GSRC-ST/MPS-HS-12- 0002) Revision C. OHS for the Interconnecting Pipeline is principally managed through the EHS Management Plan, Code F (PR-X-1605.01-6503-003). Other HSE Procedures implemented or under development are described in Section 5.3.3.

2.2 Health and Safety Statistics

The Health and Safety statistics from 1st July, 2020 to 30th September, 2020 for the Power Plant and Interconnecting Pipeline are shown in Table 2-1 and Table 2-2. A description of the HSE incidents are provided in Table 2-3

Table 2-1 HSE Statistics 1

Power Plant Interconnecting Pipeline

Man- Total Man-Hours Record 2,458,371 109,107 Power Data

Accident / TIRR Report table (0) (0) Incident (3 days or Records more absence from work)

Lost time (0) (0) (0.5 days or more absence from work)

First Aid (Medical Treatment at Site) 1 1

Property Damage 0 0

Potentially Serious Incident 5 0

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 21

Table 2-2 HSE Statistics 2

Item Power Plant Interconnecting Pipeline

A: Fatalities 0 0

B: Lost time incidents (including 0 0 vehicular)

C: Incidents and near-misses 6 1

D: Hazard observations 176 69

E: Total number of lost workdays 0 0 resulting from incidents

F: Total person-hours worked this 2,458,371 109,107 reporting period

G: Incident during this reporting 0 0 period

(Note: Incidence = total lost 0 0 workdays/total hours worked)

H: Lost Time Injury Frequency 0 0 Rate

(Number of lost time accidents x 0 0 1,000,000 total person-hours worked – lost workdays per million hours worked)

J: Lost Time Severity Rate 0 0

(Total Lost workdays x 1,000,00 0 0 hours/total person-hours worked – lost workdays per million hours worked).

K: Security Loss 0 0

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020

Table 2-3 HSE Incidents

HSE Incident Date Corrective Action Status

A truck fell into a 3rd July 2020 Safety talk to all drivers Closed gutter. Traffic and operators related to safety signage was transportation routes onsite not followed. and following traffic safety signs. Concrete protection barriers installed on corners close to gutters.

Fire caused by 3rd August 2020 Ensure fire blanket is in Closed welding activity place and checking working

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 22

HSE Incident Date Corrective Action Status coming into contact conditions below welding with oil drip tray. activities. No hot work within 15 metres of oil flushing areas. If required, permit is required and safety signage installed.

Oil leak during lube 13th August 2020 Increased the thickness of Closed oil flushing in the gasket. Power Block#1. Temporary plug changed to “hard type”.

Worker slipped into 16th August 2020 Ensure no gaps in the Closed a gutter at Block gutter where possible. Value Station. Barricade areas with warning signs. Inform all workers of the accident and prevention measures.

Release of 17th August 2020 Procedure for checking Closed Hydrochloric Acid equipment, transportation, (HCL) vapor during fume trap and pipe unloading of HCL in connecting point before the chemical unloading chemicals. storage area.

Chain block (5 ton) 31st August 2020 All ropes to be used for Closed fell from height at lifting materials or HRSG#1. equipment to be inspected for condition and colour coded based on inspection. Procedure for safe use of ropes for lifting materials and equipment.

2.3 Fatalities

A fatality occurred at the Project site on 19th August, 2020 during transformer assembly construction at Block#2. A 25 ton crane was being used for transformer assembly. During tire maintenance of the crane, the crane tire was being filled with air. During this process the tire ring blow out striking the maintenance person on the head. The cause of the incident is reported to be inappropriate installation of the lock ring on the tire or over pressure during filling the tire with air. The maintenance worker was taken to Pluak Daeng Hospital by Sino-Thai emergency vehicle, accompanied by the site nurse. On arrival at the hospital the worker was pronounced dead due to the head injuries sustained. The crane was supplied by a 3rd tier contractor to Sino-Thai and maintenance activities for the crane tire were being undertaken by a 4th tier contractor to Sino- Thai (the EPC Contractor). The deceased worker was the employee of the 4th tier contractor to Sino-Thai. Financial support to the deceased persons family was provided by the Owner, Sino- Thai and Sino-Thai’s 1st tier contractor in addition to the social security program under Thai Law. The fatality has not been reported as a Project fatality or as a Lost Time Incident due to the incident occurring to a 4th tier contractor of Sino-Thai. Contractors past the 2nd tier contractors to

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 23

Sino-Thai are not covered under the requirements of the Project HSE Management Plan and therefore incident reporting. The fatality is regarded as a Significant Safeguard and Social Reporting Event according to the Common Terms Agreement (clause 18.44). As such there are certain actions that the Owner is required to undertake in the event of such incidents. The requirements and summary of the actions undertaken by the Owner are presented in Table 2-4.

Table 2-4 CTA Requirements and Actions Undertaken by the Owners

CTA Requirements Action Undertaken by the Owner

Notify the Intercreditor Agent promptly and in any The Owner notified the incident to the event as soon as possible and in any event within 24 Intercreditor Agent (Mizuho) within 24 hours of its occurrence. hours if its occurrence.

Undertake such emergency action (if any) as are Initial actions were undertaken in appropriate in response to the Significant Safeguard response to the incident and were and Social Reporting Event and notify the notified to the Intercreditor Agent Intercreditor Agent of such emergency actions as (Mizuho). This included stopping work soon as possible. and barricading the incident area and prohibiting maintenance activities on all 25 ton cranes onsite.

Undertake all other actions (if any) as are required Prevention measures have been to be implemented without delay to remedy or developed by the Owner and Sino-Thai mitigate effects of the Significant Safeguard and for such incidents. This includes the Social Reporting Event, obtaining Intercreditor following: Agents agreement to such actions whenever • Tire maintenance is now reasonably practicable to obtain the same within the time available. prohibited onsite and can only be undertaken by the tire maintenance company at their own warehouse;

• High risk activities are now being identified for all Contractors of Sino-Thai past the 2nd tier contractor and are subject to Job Safety Analysis (JSA) if the activity needs to be performed onsite.

As soon as is reasonably practicable, provide the The Corrective Action Plan was provided Intercreditor Agent with a proposed Corrective in the Incident Report No. 2020/012 Action Plan in relation to all remaining corrective (Final Report) (Fatal Accident During measures. Tire Maintenance at Block#2 Main Transformer Area).

In response to the fatality the LTA recommends the following additional measures: • Accident/incident reporting procedure is also updated to reflect the findings of the fatality and to ensure all accident/incidents which occur to contractors past the 2nd tier contractor of Sino-Thai (based on the high risk activities identified) are now separately reported and included in the EPC Contractor monthly reports; • The high risk activities are reviewed in the weekly EHS meetings and those activities are supervised by the EHS personnel of the EPC Contractor.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 24

2.4 Accident / Incident Reporting

The accident / incident reporting procedure is specified in the HSE Management Plan (GSRC- ST/MPS-HS-12-0002) Revision C. It specifies that all accidents and incidents shall be reported to the HSE Managers of the EPC Contractor who will take the necessary steps in investigating and adopting corrective measures. Immediate reporting is required in the case of the following: − Personal Injuries; − Damage to Property or Equipment; − Near Miss Incident; and − Environmental – Non-conformance Report. The incidents / accidents which occurred during the construction monitoring period as described in Table 2-3 have been documented and recorded.

2.5 HSE Staff

The HSE staff of Sino-Thai and MHPS-PTC responsible for HSE management/supervision in the Power Plant Area and Raw Water Pond Area are shown in Table 2-5.

Table 2-5 HSE Staff for the Power Plant Area and Raw Water Pond Area

Position Number of Staff

Senior HSE Manager (MHPS-PTC) and Welfare 1 Officer

HSE Manager (MHPS-PTC) 1

Safety Officer (MHPS) 2

Field Safety Officer (Sino-Thai) 4

Field Safety Technical (Sino-Thai) 37

Training Safety Officer (Sino Thai) 1

Training Safety Document Control (Sino Thai) 2

Permit Control Safety Technical (Sino Thai) 2

Document Safety Officer (Sino Thai) 1

Document Safety Document Control (Sino Thai) 2

EIA Support Environmental Officer (Sino Thai) 1

EIA Support Environmental Document (Sino Thai) 1

First Aid Nurse (Sino Thai) 2

Inspectors (Sino Thai) 4

Welfare Officer (Sino Thai) 1

Myanmar Translator (Sino Thai) 1

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020. The HSE staff of Sino-Thai and their sub-contractors responsible for HSE management/supervision at the Interconnecting Pipeline is shown in Table 2-6. There is currently 6 safety officers for the 105 workers of the Interconnecting Pipeline which based on the construction activities is considered to be sufficient.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 25

Table 2-6 HSE Staff for the Interconnecting Pipeline

Position Number of Staff

Safety Officer Management Level 1

Safety Officer Professional Level 1

Safety Officer Technical Level 4

Environmental Specialist 1

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020. In addition, the Owner currently has an EHS Manager and EHS Officer. EGAT also has a dedicated HSE Manager.

2.6 Low Risk Issues

The following low risk issues concerning health and safety have been identified for this construction monitoring period: • The construction access road at the front of each Power Block is particularly congested with movement of vehicles and workers between each of the Power Blocks under construction. Heavy equipment is parked in this area which was not being used and some poor housekeeping was observed in terms of storage of materials which made the area more difficult to navigate for workers (Refer to Photo 1 in Appendix 1). • There was a lack of space in the hazardous waste storage area for further used oil storage. Used oil storage containers are being stored inappropriately which could result in spillages (Refer to Photo 2 in Appendix 1).

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 26

3 Labor And Working Conditions And Security

3.1 Workforce Profile and Recruitment

The number of male workers and female workers as of September 25th, 2020 is shown in Table 3-1The number of male workers comprise 84% of the workforce, while the number of female workers comprise 16% of the workforce. For the female workers a further breakdown of their roles and grades is provided in Table 3-2.

Table 3-1 Workforce Number

Company Number of Male Workers Number of Female Workers

Owner 63 7

Power Plant

EGAT 49 5

MHPS-PTC 128 12

Sino-Thai 2126 428

Interconnecting pipeline

Worley Parsons 4 0

STECON 9 2

SRPLC 12 5

SRPLC Subcon 52 17

Total 2443 476

Table 3-2 Female Workers Roles and Grades

Company Position Number of Female Workers

Owner HR & Admin Manager 1

Administration Officer 2

Purchase Officer 2

Chemist 2

EGAT Engineering 3

Electrician 1

Administration Officer 1

MHPS-PTC Administration Officer 12

STECON Nurse 2

Project Engineer 1

Engineer 7

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 27

Company Position Number of Female Workers

Administration Officer 83

Construction Worker 335

STECON Environmental Officer 1

Document Control 1

SRPLC Administration Officer 4

Environmental Officer 1

SRPLC Subcon Construction Worker 17

3.2 Welfare Facilities at Project Site

AFRY observed the following concerning the welfare facilities at the Project site:

• Toilet/bathroom facilities. There are 231 toilets installed in the Project site (181 male toilets and 50 female toilets). According to GSRC Progress Technical Report - EIA Checklist Report male workers comprise of 2,646 persons and female workers comprise of 653 persons as of September 25th, 2020. The ratio of toilet/bathroom to number of workers complies with the ESIA and The Ministry of Interior (“MOI”) ministerial law No. 63 (BE 2551) issued under the Building Control Act BE 2522 requirement of at least one (1) toilet for 15 workers or less, two (2) toilets for 40 workers or less, three (3) toilets for 80 workers or less, and additional one (1) toilet for additional 50 workers;

• There are sufficient number of drinking water tanks with water analysis complying to the Thailand drinking water standards; • Four (4) main rest shelters in the Power Plant Area and One (1) rest shelter in the Raw Water Pond Area; • Medical facilities including ambulance. Two (2) qualified nurses are employed by the Project and are based on site 7 days per week (8:00am to 5:00pm). The applicable requirements of the Labour Protection Act B.E. 2541 concerning welfare facilities and Project compliance during the construction monitoring period is shown in Table 3-3.

Table 3-3 Labour Protection Act Requirements and Compliance for Welfare Facilities

Requirement Project Compliance at the Project Site

Section 96 “In a place of The Project has established a Welfare Committee as of 1st business with fifty Employees June 2019 comprising of five (5) employee representatives or more, an Employer shall whose remit also covers the welfare facilities. arrange for the establishment MHPS has appointed two (2) designated representatives of a welfare committee at the (male and female) to monitor labor and welfare place of business, comprising requirements. The two welfare officers are identified in the of at least five Employee EPC Contractor organizational chart. representatives”. The welfare committee duties are Safety Induction material includes details of the welfare described in the Land officers and the methods of communication. Protection Act and the employer must hold a meeting with the welfare committee every 3 months and whenever

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 28

Requirement Project Compliance at the Project Site half of its members requests a meeting.

The Company shall arrange Based on the number of toilet/bathroom facilities described the following: in Section 3.2 the Project is complying with these requirements. Clean drinking water and restrooms as follows: Raw water supplied by HESIE and drinking water supplied in tankers. Drinking water analysis report provided on each ≤ 15 employees: 1 restroom, tanker to show compliance with Thailand drinking water 1 toilet, 1 drinking point; standards. ≤ 40 employees; 1 restroom, 2 toilers, 1 drinking point; ≤ 80 employees; 1 restroom, 3 toilets, 2 drinking point. Over 80 employees: for every additional 50 employees; additionally, 1 restroom, 1 toilet, 1 drinking point.

First aid service and medical Two (2) permanent nurses are employed by the Project and supplies for employees injuries adequate first aid facilities are still located at the medical or sickness. facilities and within the first aid kits provided in the construction areas. Ambulances to transport workers to If the company has more than hospital are located onsite. 10 employees it must have a first-aid kit (including e.g. scissors, cotton, alcohol 70%, medicines, etc.) available at the work place. In case of industrial work place, the following additional facilities have to be provided: For the place with more than 100 employees, a ward with one bed, 1 permanent nurse and 1 doctor who visits occasionally; For the place with more than 1,000 employees, a ward with 2 beds, 2 permanent nurses, 1 doctor who is scheduled to visit regularly at least for 2 hours, and transportation to a hospital.

3.3 Workers Grievance Mechanism

There were no workers grievances / suggestions recorded during the construction monitoring period.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 29

3.4 Workers Camp and Transportation

3.4.1 Workers Camp

The workers camp living statistics as of October 20th, 2020 is shown in Table 3-4. The statistics show that there are currently sufficient rooms (1,564) for the current total number of persons (2,216) i.e. no more than 2 adults to a room.

Table 3-4 Workers Camp Living Statistics

Item Number

Total Room 1,564

Empty Room 186

Thai Males Adults 1,311

Thai Females Adults 552

Myanmar National Adults 280

Children 73

Total Persons 2,216

Sources: GSRC Summary of Workers Camp Statistics, September 2020

Workers Camp Living Conditions

In general, the hygiene/cleanliness of the workers camp was observed to be adequate in Zones 1, 2 and 3 of the workers camp. However, in the Myanmar workers zone a number of room doors were observed to be damaged (Refer to Photo 10 in Appendix 1). The Owner and Contractor continues to undertake monthly inspections at the workers camp and no non-compliances against the Owners Camp Checklist shown in Table 3-5have been reported during the construction monitoring period.

Table 3-5 Owner Workers Camp Checklist

Item Action

1 Dimension of the room, total area should be not less than 9 m2 (width greater than 2 metre and height greater than 2.4 metre), with personal space not less than 3 m2 /person.

2 If the building is longer than 45 m in width, then there need to be a 2.5 m gap between buildings, along the building depth.

3 Natural ventilation. Room is equipped with door or ventilation with total area of not less than 10% of the room area, excluding the door and window.

4 Number of toilets are sufficient for the total residents residing at the camp.

5 Separate bathing area and toilet. Separated male and female toilets.

6 The waste generated shall be managed in accordance to the law. Wastewater discharge shall not impact persons surrounding the workers camp.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 30

Item Action

7 When areas of the camp area are occupied by more than 10 people, basic medical kits shall be made available. Emergency contact number of the nearest health care centre needs to be displayed.

8 Electrical wire and equipment should be in good condition and a protection system in place. The installation needs to follow the standard code for outdoor (THW, MEA TYPE A) and indoor (300V 70oC VAF).

9 An appropriate number of fire extinguishers should be installed and of the correct type.

10. An appropriate emergency alarm system should be installed, covering all of the workers camp.

11. There should be sign placed at the workers camp entrance to inform that the workers camp is a residential area.

12 Fencing should be in place to secure the workers camp with a designated entrance and exit.

13. There should be warning signs prohibiting drug usage.

14. For every 10 persons residing at the workers camp one camp watchman needs to be allocated to ensure the camp operates in accordance with the site rules.

Workers Camp Welfare Facilities and Amenities

AFRY observed the following concerning the welfare facilities at the workers camp: • 154 toilets are now installed in the workers camp (118 male toilets and 56 female toilets) and number of males residing comprises of 1,311 persons and number of female workers residing comprises of 552 persons. Ratio of toilet/bathroom to number of workers complies with the ESIA and The MOI ministerial law No. 63 (BE 2551) issued under the Building Control Act BE 2522 requirement of at least one (1) toilet for 15 workers or less, two (2) toilets for 40 workers or less, three (3) toilets for 80 workers or less, and additional one (1) toilet for additional 50 workers; • Bathrooms and toilets were found to be of good hygiene with privacy. Regular inspections/cleaning of the facilities continues; • Medical facilities. Adequate medical/first aid facilities were observed. The Project site nurses are still used to attend any medical matters at the workers camp; • As part of the COVID-19 preventative measures the workers camp continues to have dedicated area for new workers and area of quarantine in case any of the residents are found to have symptoms of COVID-19.

Wastewater Treatment System

Wastewater from the workers camp continues to be discharged to an onsite wastewater treatment system comprising of an aerated pond and sedimentation pond. The wastewater treatment system remains at a capacity based on a maximum number of 3,200 persons residing at the workers camp during the construction period and wastewater rate of 200 litres/person/day. The wastewater treatment system was observed to be in good condition.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 31

Water quality monitoring continues to be undertaken at a sampling location adjacent to the sedimentation pond prior to discharge on a monthly basis and the results are provided in Section 5.

3.5 Transportation

The Contractors continue to be transported to site by shuttle buses. The shuttle buses are able to accommodate up to 25 persons. The location of the pickup point for the transportation remains an approximate 5 to 10 minute walk from the workers camp.

3.6 Security

3.6.1 Project Site and Block Valve Station

Security continues to be provided by the security contactor GIANT. Site Security Plan Rev A has been approved by the Owner and is still considered to be appropriate. The security contractor continues to monitor the control points and the Project site 24 hours per day. The security guards work 12 hours per day on a shift basis. The security guards continue to be positioned at the following locations: • Main entrance gate at Power Plant Area. Dayshift is two (2) security guards and nightshift is (two) 2 security guards. • Emergency gate at Power Plant. • Main office area: No Security guard for dayshift and one (1) security guard positioned at night shift; • Raw Water Pond area: One (1) security guard positioned at day shift and one (1) for night shift. • Block Valve Station: Two (2) security guards. The number of security guards required continues to be reviewed periodically and shall be increased if necessary.

3.6.2 Workers Camp

The Site Security Plan also includes security rules and regulations for the workers camp. Security is provided 24 hours per day at the workers camp entrance. Security guards continue to monitor the incoming/ outgoing of people and vehicles at the main entrance gate.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 32

4 Stakeholder Engagement

4.1 Engagement Activities and CSR

During this construction monitoring period, two education activities were undertaken on September 16th, 2020 and September 24th 2020 to pass on knowledge to local community members concerning the power plant commissioning activities. The activities were undertaken to comply with Project requirements of undertaking 2 education awareness events per year for local community members. There was no Environmental Impact Monitoring Committee during the construction monitoring period. However, the Environmental Impact Monitoring Committee did meet on the October 19th, 2020. The Minutes of Meeting were still in preparation at the time of preparing this report and therefore a summary of the Minutes of Meeting be provided in the next LTA monitoring report to cover the period October 2020 to December 2020.

4.2 Stakeholder Grievance Mechanism

The Owner informed no further stakeholder grievances were received during the construction monitoring period. During the LTAs site visit, the LTA also interviewed the Deputy Village Head of Moo 3 which includes the Proud Village immediately to the south of the Power Plant Area. The key findings from the interview were as follows: • Steam blowing from Block#1 was observed but no noise complaint was reported; • An issue was raised concerned with truck movements in the area and damage being caused to roads. However, there is also an understanding that the trucks are not associated with the Project; • Knowledge within in the community is lacking as some believe the Project to be coal fired; • For the Projects operation there is a concern about odour due to current experience with the nearby Sugar Mill Plant and the rubber/tire plant; • For operation they are also concerned about light pollution during night-time as the power plant is located at higher elevation than the communities. To address these concerns the LTA has provided recommendations in the Corrective Action in Table 6-1

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 33

5 Environmental And Social Monitoring

5.1 EHS Capacity (Resources and Training)

5.1.1 EHS Capacity (Resources)

The EHS staff employed for the construction monitoring period are described in Section 2.5. The EHS capacity observed at site for this construction monitoring period is considered to be appropriate. The HSE Committee continues to meet every month to review the overall safety at site and develop guidelines to improve E&S.

5.1.2 EHS Training

The EHS training undertaken during the construction monitoring period is shown in Table 5-1. The LTA considers the training to be appropriate based on the construction activities. The gender based violence training continues to be incorporated into the safety induction and re- inductions.

Table 5-1 EHS Training During the Construction Monitoring Period

No. July 2020 August 2020 September 2020

Safety 747 686 610 Induction Training

Safety 629 125 114 Induction Training (Re- Induction)

PTW Worker 747 686 610

Working at 721 676 589 Height

Rigger 23 9 0

Hot Working 52 34 25

Fire Watch 70 43 35

Job Safety 0 0 0 Analysis

Supervisor 0 0 0 Training

Scaffolding 1 0 0 12

Scaffolding 2 0 0 0

First Aid 0 0 0

Basic Fire 58 88 151 Fighting

Lifting 5 3 0 Supervisor

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 34

No. July 2020 August 2020 September 2020

Banks Man 0 0 0

Confined 0 14 86 Space

Hazard 747 686 610 Observation

Commissioning 402 405 443 Training

Source: 2020-07, 2020-08, 2020-09 GSRC Progress Technical Report_CC

The EHS training scheduled for October 2020, November 2020 and December 2020 during the construction monitoring period is shown in Table 5-2

Table 5-2 EHS Training for October, November and December 2020

Training Program Frequency Month

July August September

Lifting Works Required X X X (check/test rope capacity)

FO Required X X - Flushing/Receiving

Hot Work With Permit to X X - Work

PTW & LOTO for As Required X X X Commissioning

Safety Induction Persons who X X X Training (Re- undertook the Induction) safety induction 1 year previously

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020. During this construction monitoring period there was a basic fire fighting training emergency drill on 11th September 2020. The following EHS training also continued as reported in the previous construction monitoring period: • Contractor provides Safety Talks two times per week for all workers; and • Daily tool box talks for all workers.

5.2 EHS Licenses, Permits, Authorizations and Compliance Status

The status of the EHS related permits are provided in Table 5-3

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 35

Table 5-3 Status of EHS Related Permits

No. Permits Authorization Authority Status

1 EIA Power Plant Office of Natural Approved December Resources and 2nd, 2015 Environmental Policy and Planning (ONEP)

2. EIA Gas Pipeline Office of Natural Approved October 5th, Resources and 2017 Environmental Policy and Planning (ONEP)

3. EIA Power Plant Office of Natural Approved August 23rd, (Amendment) Resources and 2018 Environmental Policy and Planning (ONEP)

4. Report of Environmental Office of Natural Ongoing. Owner Mitigation Measures and Resources and required to submit Monitoring Programs Environmental Policy and mitigation and during construction and Planning (ONEP) monitoring reports to commissioning. ONEP every 6 months during construction. The next report for July 2020 to December 2020 will be submitted to ONEP in January 2021.

5. Registration of Plant Industrial Works To be submitted – Pollution Control System Department (IWD) planned September 1st, Supervisor prior to 2020, but still pending. commissioning date of block 1,2, 3 and 4

6. Registration to be an Industrial Works To be submitted – Operator for Supervision Department (IWD) planned September 1st, and Operation of 2020, but still pending. Environmental Pollution Prevention Equipment for commissioning phase.

7. Dangerous Substance Industrial Works To be submitted – was License Department (IWD) planned for November 15th, 2019 but still pending. Hazardous substance list has been submitted to Owner.

8. Permit for Transportation Department of Highways Under Department of of Heavy Equipment Highways application/approval process. Approved on December 2nd, 2019.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 36

No. Permits Authorization Authority Status

9. Permit for Liquid Fuel Department of Energy Phase 1 submitted Storage Tank: and Business (DOEB) November 14th, 2018 and approved. Phase 1: Construction Drawing Approval Phase 2:Updated drawings for Phase 2 Phase 2: Permit Approval permission was submitted to Owner on May 25th, 2020.

Sources: 2020-09 GSRC Progress Technical Report_CC The specific approvals concerning land acquisition for the Interconnecting Pipeline are provided in Table 5-4There is no change from the previous construction monitoring period

Table 5-4 Status Approval for Interconnecting Pipeline

Approval Issuing Agency Date of Issue

Use of Land Agreement WHA Eastern Seaboard October 4th, 2018 Industrial Estate 1

Right of Way of Gas Pipeline Route EGAT June 19th, 2018

Right of Way of Gas Pipeline Route TAO February 23rd, 2017

Right of Way of Gas Pipeline Route Sub-district Municipality February 27th, 2017

Energy Network Announcement ERC March 1st, 2019

5.3 EHS Management System and Implementation Status

AFRY has reviewed the following components of the EHS Management System for this construction monitoring period: • EHS Policies; • Organisational Structure and Staffing; • HSE Procedures and Programs; • Training Requirements; and • EHS Monitoring and Reporting.

5.3.1 EHS Policies

The status of EHS Policies is provided in Table 5-5. There is no change from the previous construction monitoring period.

Table 5-5 Status of EHS Polices

No. EHS Policy Status

1. Owner ES is visible at the Project Site. Signed 25th December, 2017

1. MHPS and Contractor OHS and Environment Signed 3rd December, 2018 Policy is visible at the Project Site.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 37

5.3.2 Organisational Structure and Staffing

The organisational structure of the current HSE staff concerned with the Project is provided in Section 2.5

5.3.3 HSE Procedures and Programs

The status of the existing HSE procedures and programs concerned with the EHS management system of the Power Plant is shown in Table 5-6

Table 5-6 Status of Existing HSE Procedures and Programs for the Power Plant

No. HSE Procedure / Revision Status Target Closed LTA Comments Program Date

1. HSE Management C Approved - - Plan

2. Security Plan A Approved - -

3. Site Emergency B Approved - - Procedure

4. Fire Prevention B Approved - - Plan

5. Confined Space B Approved - - Procedure

6. Lifting Rigging B Approved - The corrective Procedure actions identified concerned with the chain block (5 ton) fall incident at HRSG#1 should be included in the Lifting Rigging Procedure.

7. Permit to Work B Approved - - Procedure

8. Excavation Work B Approved - - Procedure

9. Radiography - Approved - - Work Procedure

10. Scaffolding A Approved - - Inspection and Tag Plan

11. Working at Height A Approved - - Plan

12. Incident and A Approved - - Accident Procedure

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 38

No. HSE Procedure / Revision Status Target Closed LTA Comments Program Date

13. Chemical - Submitted for - The corrective Handling Safety Approval actions Procedure identified concerned with the incident involving the release of Hydrochloric Acid (HCL) vapor during unloading of HCL in the chemical storage area should be included in the Chemical Handling Safety Procedure.

14. Pre- - Approved - - commissioning and Commissioning HSE Management Plan

15. Permit to Work - Approved - - Procedure during Commissioning

16. Commissioning - Approved - - Lock Out and Tag Out Procedure

17. Commissioning - Approved - - Team Emergency Response Procedure

The existing and approved HSE procedures and programs concerned with the EHS management system of the Interconnecting Pipeline are shown in Table 5-7

Table 5-7 Status of Existing HSE Procedures and Programs for the Interconnecting Pipeline

No. HSE Procedure / Program Code Number

1. Job safety and environment - PR-X-1605.01-6503-001 analysis procedure

2. EHS Management Plan F PR-X-1605.01-6503-003

3. Excavation work Procedure E PR-C-1605.01-6503-003

4. Emergency Plan F PR-X-1605.01-6503-002

5. Traffic management F PL-X-1605.01-6503-001

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 39

No. HSE Procedure / Program Code Number

6. Non destructive testing H TRZ-1605.01-6503-001 procedure

7. Security Plan F PR-X-1605.01-6503-004

8. Fire Prevention Plan F PR-X-1605.01-6503-005

9. Confined space entry work - PR-X-1605.01-6503-006 Procedure

10. Lifting work Procedure F PR-X-1605.01-6503-007

11. Permit to work Procedure F PR-X-1605.01-6503-008

12. Scaffolding inspection and tag - PR-X-1605.01-6503-009 Procedure

The Owner and Contractor continues to implement the following COVID-19 prevention measures: • Body temperature checks at the Project site for workers and visitors; • Body temperature checks at the workers camp; • PPE (face masks) mandatory for workers and visitors; • Disinfecting areas of the site offices and workers camp on a weekly basis; • Providing alcohol gel and hand soap at the Project site and workers camp; • Symptoms and prevention measure communicated to workers including foreign workers through talk box talks and in the site induction.; • Symptoms and prevention measures signage installed at the Project site and workers camp; • Dedicated area for new workers and area of quarantine at the workers camp in case any of the residents are observed to have symptoms of COVID-19; and • Specific prevention measures for overseas visitors. The Owners COVID-19 committee continues to monitor the implementation of the prevention measures. Body temperature results are provided to the Owner on a weekly basis. In addition to body temperature checks the Contractor has developed a heath questionnaire for new workers and visitors to determine any other symptoms of COVID-19. Symptoms of COVD- 19 are also being monitored at the workers camp through observation by the camp management. The COVID-19 emergency plan remains in place to cover the actions to be undertaken in case body temperature is found to be greater than 37.5 DegC, a person becomes infected with COVID- 19 and in case of site lock down.

5.3.4 Training Requirements

The EHS training undertaken during the construction monitoring period is shown in Section 5.1.2. The Contractor continues to implement the Training Action Plan included in the HSE Annual Plan for 2020.

5.3.5 EHS Monitoring and Reporting

To monitor HSE performance, the following audit program continues to be implemented by the Contractor: • Daily audit;

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 40

• Weekly Audit; • Monthly audit (by Management Team). HSE performance continues to be raised in the following meetings: • Weekly EHS meetings attended by the Owner, MHPS-PTC, EGAT and the Contactor; • Weekly progress meetings the Owner, MHPS-PTC, EGAT and the Contactor; • Monthly HSE Committee meeting comprising of Owner, MHPS-PTC, Contractor and another personal involved in the Project. • Quarterly Environmental Impact Monitoring Committee comprising of representatives of Sriracha district, Plukdang district, Municipality of Chomphol Chao Phraya and Tasit subdistric Moo 3 Headman. The following HSE reporting continues to be undertaken by the Contractor: • Weekly audit summary & safety report; • Monthly HSE report • Weekly EIA Activity Report; • Monthly EIA Activity Report; • Six month EIA Report to Owner; • Workers Camp Checklist.

5.4 Compliance with EHS National Laws and Regulations

The Projects compliance with the EHS National Laws and Regulations specified in the ESIA/EMP dated October 2018 are provided in this section.

5.4.1 Construction Environmental Monitoring

The Project continues to implement the environmental monitoring program as per the requirements of the ESIA/EMP dated October 2018. The environmental monitoring undertaken by the Owner is predominately for the 6 monthly report of environmental monitoring required by ONEP. The draft report for January to June 2020 was submitted to ONEP on July 15th, 2020 and final report on the July 21st, 2020.

5.4.2 Ambient Air Quality

During construction, the Project is required to undertake ambient air quality monitoring at 5 locations every 6 months (twice per year) for a period of 7 consecutive days. Parameters monitored are Total Suspended Particulates (TSP), Particulate Mater 10 (PM10), Nitrogen Dioxide (NO2) and Sulphur Dioxide (SO2). There was no ambient air quality monitoring required for ONEP during July to September 2020, and the next round of ambient air quality monitoring for ONEP is scheduled for November 2020. The Owner engaged Geo-Informatics and Space Technology Development Agency (GISTDA) to provide data to support the study to monitor the potential impacts at the location of the predicted maximum NO2 ambient air quality concentration (refer to Figure 5-1) from the Projects operation as determined by the environmental impact studies. This initial data was collected prior to the commissioning of Block#1 in order for the existing conditions at the location to be understood in order for changes to be monitored during the Project operation.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 41

Figure 5-1 Location of Predicted Maximum NO2 Concentration

This initial study comprised of obtaining satellite imagery and undertaking a land use survey which covered an area of 5 x 5 km2 from the location of the predicted maximum ambient air quality concentration. From the data obtained the location of concern is classified as forest habitat comprising of dry evergreen forest and mixed deciduous forest. The forest canopy density was to be found in the range of 70-80%. The Project plans to review satellite imagery on an annual basis for any change to the land use classification and forest canopy density. The LTA notes that any change could also be due to external influences and not directly from the Project and as such will require consideration alongside the Projects actual emissions to be monitored by the Projects continuous emissions monitoring system. 5.4.3 Noise

During construction, the Project is required to undertake noise monitoring at 3 locations every 6 months for a period of 7 consecutive days. There was no noise monitoring required for ONEP during July to September 2020, and the next round of noise monitoring for ONEP is scheduled for November 2020. However, during steam blowing at Block#1, STECON have undertaken spot noise measurements using a hand held noise meter to record noise levels at different locations at the Project site and at sensitive receptors to provide an indication of noise levels during steam blowing. The results of the noise monitoring for the steam blowing activities undertaken on October 14th, 2020 and October 15th, 2020 are shown in Table 5-8and monitoring locations are shown in Figure 5-2. A background noise level was also recorded at the sensitive receptor locations before steam blowing commenced in order for a comparison to be made. The noise monitoring results show no exceedances of the Community Noise National Standard at the sensitive receptors and no significant difference compared to the background noise measurement before steam blowing. Based on these results it can be concluded that the installed noise barriers are performing effectively to date but this is based on spot noise measurements only and further monitoring is expected during steam blowing.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 42

Table 5-8 Noise Monitoring Results during Steam Blowing at Block#1

Location Description Result (dBA) – Result (dBA) – Noise Background October 14th, October 15th, before Steam 2020 2020 Blow (dBA)

1. Steam Blow at 79.3 98.9 - Block#1

2. 16 m in front of 63.6 61.6 - noise barrier

3. 16 m behind 52.2 48.7 51.8 noise barrier

4. South east from 60.9 62.6 - steam blow at Block 1

5. South side from 56.8 55.2 - steam blow at Block 1

6. West side from 63.6 62.7 - steam blow at Block 1

7. North east from 62.0 63.9 - steam blow at Block 1

8. Chumchon 54.7 55.6 54.2 Borisat Namtan Tawan-aok School

9. Wat Chompon 54.8 50.5 54.4 Chaophraya

10. Proud Village 55.3 53.4 55.6

Community Noise National Maximum Lmax is less than 115 dB(A). Standard: Notified by the National Environment Board NO.15 (B.E.2540)

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 43

Figure 5-2 Noise Monitoring Locations during Steam Blowing at Block#1

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 44

5.4.4 Wastewater from Workers

During construction, the Project is required to undertake monthly wastewater quality monitoring at the following 2 locations:

• Project Site (Temporary Office);

• Construction Workers Camp

The results of the water quality monitoring at the Project site and workers camp during the construction monitoring period are in compliance with the national standards shown in Table 5 9 and Table 5 10.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 45

Table 5-9 Water Quality Monitoring Results at the Project Site

Sampling Measured (mg/l) Most Date Probable Number (MPN) / 100 ml

Total Total Biochemical Suspended Settleable Oil & Fecal pH Dissolved Sulphide Kjeldahl Oxygen Demand Solids Solids Grease Coliform Solids Nitrogen

July 2020 7.0 <1.0 172 <5 ND <0.1 ND 5.0 <1.8

August 2020 7.2 1.2 114 <5 ND <0.1 ND ND 35,000

September 7.1 <1.0 104 <5 ND <0.1 ND ND 21 2020

MENR Notification - Prescribing Standards for 5.0- effluent from <40 <500 <50 <3.0 <0.5 <20 <40 - 9.0 Building Type C Prior to Draining Outside 2005

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 46

Table 5-10 Water Quality Monitoring Results at the Workers Camp

Most Probable Measured (mg/l) Number / Sampling 100 ml Date Total Total Biochemical Suspended Settleable Oil & Fecal pH Dissolved Sulphide Kjeldahl Oxygen Demand Solids Solids Grease Coliform Solids Nitrogen

July 2020 7.7 <0.1 172 <5 ND <0.1 ND 1.2 <1.8

August 2020 7.6 0.80 136 5 ND <0.1 ND 0.80 1,700

September 7.2 1.8 <50 <5 ND <0.1 ND 0.4 3,500 2020

MENR 5.0- <40 <500 <50 <3.0 <0.5 <20 <40 - Notification - 9.0 Prescribing Standards for effluent from Building Type C Prior to Draining Outside 2005

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 47

5.4.5 Wastewater from Water Treatment Plant

The Owners are undertaking monthly wastewater quality monitoring for the wastewater generated in the Water Treatment Plant from the commissioning activities before the wastewater is discharged into the Hemaraj ESIE central wastewater treatment system. The LTA has observed that the monitoring results for July 2020 and these are shown to comply with the Notification of the Industrial Estate Authority of Thailand No.76, B.E. 2560 : Criteria of Wastewater Characteristic from Factory Discharge to Central Wastewater Treatment Plant.

5.4.6 Wastewater from Hydrostatic Test (Interconnecting Pipeline)

Wastewater from the hydrostatic test of the Interconnecting Pipeline was undertaken on 31st July, 2020 to ensure compliance with the standard of the Hemaraj ESIE. The results are provided in Table 5-11

Table 5-11 Wastewater Monitoring Results from Hydrostatic Test (Interconnecting Pipeline)

Parameter Unit Result Standard

pH - 7.8 5.5-9.0

Temperature DegC 37.4 45

Total mg/l <5 <200 Suspended Solid

Oil & Grease mg/l <3 <10

5.4.7 Waste

The Project continues to actively monitor solid waste production. The amount of non-hazardous and hazardous waste generated during the construction monitoring period is presented in Table 5-12 Hazardous waste continues to be stored in the hazardous waste storage area, however the LTA has identified that there is a lack of space in the hazardous waste storage area for further used oil storage and used oil storage containers are being stored inappropriately which could result in spillages (Refer to Photo 2 in Appendix 1).

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 48

Table 5-12 Waste Monitoring Results

Item Non-Hazardous Waste Hazardous Waste

Generated Recycled Disposed Recycling Generated Recycled Disposed Recycling (ton) (ton) (ton) (ratio %) (ton) (ton) (ton) (ratio %)

A B C=A-B D=B/A*100 E F G=E-F H=F/E*100

July 2020 38.93 0.00 38.93 0.00 5.92 0.00 5.92 0.00

August 62.22 51.23 10.99 82 3.91 0.00 3.91 0.00 2020

September 64.00 0.00 64.00 0.00 5.02 0.00 5.02 0.00 2020

Source: Lenders Technical Advisor, Quarterly Construction Monitoring Site Visit Presentation, 20th October 2020.

5.5 Compliance with ESIA/EMP, ADB Safeguards, IFC Performance Standards and IFC EHS Guidelines

To avoid repetition when determining compliance with the Project E&S standards the findings are based on compliance against the requirements of the ESIA/EMP dated October 2018. Status of compliance is provided in Table 5-13

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 49

Table 5-13 Status of Project Against Project E&S Standards of the ESIA/EMP

Risk Rating

No Risk Identified Requirement as Topic Reference No. Findings / Observations Specified in EMP Low

Medium

High

EMP 1.1 Trucks carrying construction materials must be covered and Compliant – observed during have items being carried site visit and on review of GSRC tied up to prevent the No Risk Identified Progress Technical Report EIA materials from falling Checklists information. and to reduce the amount of dispersion of suspended particulate.

EMP 1.2 Spray water in the Air Quality construction area, the soil mounds or where project construction activities causes the Compliant – observed during dispersion of suspended site visit and on review of particulate, such as the GSRC Progress Technical No Risk Identified road, the area Report EIA Checklists undergoing filling and information. grading, etc. to reduce the dispersion of the suspended particulate, at least two times/day Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 50

(morning and afternoon) and more as necessary.

EMP 1.3 Inspect and maintain condition of Compliant – observed on engines/machines used review of GSRC Progress in the construction to No Risk Identified Technical Report EIA Checklists reduce the emission of information. air pollutants regularly, each month.

EMP 1.4 Install shading nets or fences with the height of Compliant – observed during 3 meters from the site visit and on review of ground around the GSRC Progress Technical No Risk Identified project construction site Report EIA Checklists to prevent suspended information. particulate from the construction.

EMP 1.5 Assign workers to clean Compliant – observed during up traffic surface in the site visit and on review of area in front of the GSRC Progress Technical No Risk Identified project area after the Report EIA Checklists entry or exit of the information. delivery trucks.

EMP 1.6 Wash tires of the delivery trucks leaving Compliant – observed during the construction area or site visit and on review of area related to the GSRC Progress Technical No Risk Identified construction activities to Report EIA Checklists prevent the debris of information. earth and sand from falling on the road

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 51

surfaces both inside and outside the project area.

EMP 1.7 Prohibit the burning of Compliant – observed on scrap materials or review of GSRC Progress No Risk Identified garbage in the Technical Report EIA Checklists construction area. information.

EMP 1.8 Limit the speed of vehicles in the construction area not to exceed 20 Compliant – observed during kilometers/hour. not site visit and on review of exceeding 40 GSRC Progress Technical No Risk Identified kilometers/hour in the Report EIA Checklists urban area and no more information. not exceeding 80 kilometers/hour on highway.

EMP 1.9 Limit the use of the Compliant – observed during construction area to the site visit and on review of absolute necessities and GSRC Progress Technical No Risk Identified to proceed with the Report EIA Checklists construction promptly. information.

EMP 1.10 The project will conduct quantification and monitoring of greenhouse gas The project will complete the emission annually in No Risk Identified study by the end of 2020. accordance with internationally recognition methodologies.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 52

EMP 1.11 During construction activities, in case project fine cultural heritage resources in Compliant - No cultural finds in the area the project No Risk Identified the project area. have to stop activity and report to relevant agencies according to the law.

EMP 2.1 Use construction equipment that produce loud noise only during the day time from 08.00-17.00. If it is necessary to operate Compliant – observed on after working hours, the review of GSRC Progress Project must obtain No Risk Identified Technical Report EIA Checklists approvals from the information. related agencies and must notify the communities and Noise factories in the vicinity, at least two weeks prior to the operation.

EMP 2.2 Publicize the construction plan that will generate noise and Compliant – observed on the measures to control review of GSRC Progress No Risk Identified noise from the Technical Report EIA Checklists construction to the information. people of the communities in the vicinity at least two

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 53

weeks prior to the construction.

EMP 2.3 Inspection, maintain and repair equipment and tools in good Compliant – observed on condition at all time and review of GSRC Progress No Risk Identified follow the maintenance Technical Report EIA Checklists manual for the information. equipment and tools continuously.

EMP 2.4 Install warning sign boards in the area of loud noise and provide protective equipment such as ear plugs and Compliant – observed during ear muffs for site visit and on review of construction workers GSRC Progress Technical No Risk Identified working in the area of Report EIA Checklists noise exceeding 85 dB information. (A) and require workers to use the silencers when working in the area of loud noise.

EMP 2.5 Ensure that the construction contractor strictly comply with the Compliant – observed on review of GSRC Progress prevention and No Risk Identified mitigation measures for Technical Report EIA Checklists noise impacts and information. require that they use equipment and

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 54

machines which produce low level of noise.

EMP 2.6 Install temporary noise barrier along the fence in the northeast of the project site which is adjacent to the Chumchon Borisat Namtan Tawan-aok School and Child Compliant – observed during Development Center of site visit and on review of Chomphon Chao Phraya GSRC Progress Technical No Risk Identified Sub-district Municipality. Report EIA Checklists information. Install temporary noise barrier in the south side of the project site which is adjacent to Wat Chompon Chaophraya and Proud Housing Estate.

EMP 3.1 Prepare gutters and temporary sedimentation pond within the project area to collect rainwater and Compliant – observed during allow it to precipitate. site visit and on review of Water Quality Solid sediments are GSRC Progress Technical No Risk Identified separated from Report EIA Checklists rainwater while the information. remaining clear water will be reused for spraying of the project area to reduce the

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 55

dispersion of the suspended particulate. The remaining water will be drained into the Estate's Rain Gutters.

EMP 3.2 If any scrap materials is found falling into the Compliant – observed during gutters and blocking or site visit and on review of obstructing the flow of GSRC Progress Technical No Risk Identified the water, it must be Report EIA Checklists removed to allow water information. to flow freely.

EMP 3.3 Compliant – observed during Forbid discarding of site visit and on review of scrap material or dirt GSRC Progress Technical No Risk Identified into the gutters. Report EIA Checklists information.

EMP 3.4 Project site - Provide sufficient toilets under proper hygienic principle for the construction workers as required by Compliant – observed during law and provide septic site visit and on review of tank or ready-made GSRC Progress Technical No Risk Identified wastewater treatment Report EIA Checklists tanks to treat information. Refer to Section 3 wastewater from daily for further details. consumption of the construction workers. Allocate wastewater holding pond with holding capacity for at

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 56

least one day in order to inspect the quality of the discharged water to ensure that it meets the requirement for Building Type C according to the standards prescribed in Ministry of Natural Resources and Environment's Notification re: Prescribing Standards for Discharged Water from Building of Certain Types and Sizes Prior to Draining Outside.

EMP 3.5 Provide drainage gutter in the construction area and wastewater holding pond to hold uncontaminated discharged water from Compliant – observed during the construction site visit and on review of activities for inspection GSRC Progress Technical No Risk Identified of the quality in Report EIA Checklists accordance with the information. requirement of Hamaraj Eastern Seaboard Industrial Estate, before draining to the estate's central wastewater treatment system.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 57

EMP 3.6 Control the management the contaminated wastewater such as Compliant – observed on collective wastewater review of GSRC Progress No Risk Identified from the engine oil Technical Report EIA Checklists changes in tanks for information. delivery to a company licensed by the government to dispose.

EMP 3.7 Repair and maintain vehicles and machines regularly to prevent leakage of fuel provided Compliant – observed on that it is carried out in review of GSRC Progress the designated area on No Risk Identified Technical Report EIA Checklists solid surface with information. materials for prevention of leakage from flowing into Map Kradon Swamp.

EMP 3.8 Workers Camp - Provide sufficient toilets under proper hygienic principle for the construction Compliant – observed during workers as required by site visit and on review of GSRC Progress Technical law and provide septic No Risk Identified tank or ready-made Report EIA Checklists wastewater treatment information. Refer to Section 3 tanks to treat for further details. wastewater from daily consumption of the construction workers.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 58

Allocate wastewater holding pond with holding capacity for at least one day in order to inspect the quality of the discharged water to ensure that it meets the requirement for Building Type C according to the standards prescribed in Ministry of Natural Resources and Environment's Notification re: Prescribing Standards for Discharged Water from Building of Certain Types and Sizes Prior to Draining Outside.

EMP 3.9 Measures for Management of wastewater from Hydrostatic Test Compliant – observed on Install grilles or fine review of GSRC Progress No Risk Identified mesh to trap debris Technical Report EIA Checklists solid contaminants information. mixed in the water at the end of the drain of the wastewater from the hydrostatic test.

EMP 3.10 Inspect the Compliant – observed on characteristics of the No Risk Identified review of GSRC Progress wastewater from the

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 59

hydrostatic test, such Technical Report EIA Checklists as, pH, temperature, information. suspended solid, oil and grease to ensure that the values are within the standard of Hemaraj Eastern Seaboard Industrial Estate.

EMP 3.11 In case the wastewater quality is not within the standard of the estate, Compliant – observed on the project will deliver review of GSRC Progress such wastewater to be No Risk Identified Technical Report EIA Checklists disposed by the information. company licensed by the government for disposal.

EMP 4.1 Plan for the routes to be used for transportation Compliant – observed on of construction materials review of GSRC Progress No Risk Identified and equipment of the Technical Report EIA Checklists project to avoid traffic information. problems.

Transportation EMP 4.2 Review and adjust the route plans for the transportation of Compliant – observed on construction materials review of GSRC Progress No Risk Identified and equipment of the Technical Report EIA Checklists project regularly to information. adapt to the current situation.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 60

EMP 4.3 Avoid transporting construction materials during the rush hours, such as between 07.30 to 08.30 hrs. And between 16.00-17.00 hrs. To alleviate Compliant – observed on problems of traffic review of GSRC Progress congestion. If No Risk Identified Technical Report EIA Checklists transporting during information. those hours is necessary, seek approval from the relevant agencies and notify the community at least two weeks in advance.

EMP 4.4 Cover up all trucks Compliant – observed during completely with canvas site visit and on review of to prevent materials GSRC Progress Technical No Risk Identified from falling on road Report EIA Checklists surface. information.

EMP 4.5 Ensure that all Compliant – observed on contractors order their review of GSRC Progress No Risk Identified drivers to strictly comply Technical Report EIA Checklists with the traffic rules. information.

EMP 4.6 Compliant – observed on Control of the trucks' review of GSRC Progress weight not to exceed No Risk Identified Technical Report EIA Checklists the legal limits. information.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 61

EMP 4.7 Provide training to and Compliant – observed on control drivers to review of GSRC Progress No Risk Identified comply with traffic rules Technical Report EIA Checklists strictly. information.

EMP 4.8 Compliant – observed on Inspect and maintain review of GSRC Progress the vehicles used in the No Risk Identified Technical Report EIA Checklists project, regularly. information.

EMP 4.9 Coordinate with traffic Compliant – observed on police in the area of the review of GSRC Progress transportation of various No Risk Identified Technical Report EIA Checklists materials and information. equipment.

EMP 4.10 Limit the truck's speed on the highway not to exceeding 80 kilometers/hour in accordance with the Compliant – observed on Land Transportation Act review of GSRC Progress No Risk Identified B.E. 2522 and the Technical Report EIA Checklists Highway Act No. 2 and information. No. 3 B.E. 2542. Limit the speed at 40 kilometers/hour in the community zone.

EMP 4.11 Install speed limit sign Compliant – observed on displaying the limit review of GSRC Progress within the construction No Risk Identified Technical Report EIA Checklists area not to exceeding information. 20 kilometers/hour.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 62

EMP 4.12 Display the telephone number of the person in Compliant – observed on charge of the delivery review of GSRC Progress No Risk Identified vehicles as a channel to Technical Report EIA Checklists notify or complain to the information. project.

EMP 4.13 Compliant – observed during Provide security site visit and on review of personnel to facilitate GSRC Progress Technical No Risk Identified the entry into and exit Report EIA Checklists from the project. information.

EMP 5.1 Require contractors to Compliant – observed on supply adequate water review of GSRC Progress No Risk Identified for use in the Technical Report EIA Checklists construction activities information.

EMP 5.2 Require the contractors Compliant – observed during to provide adequate and site visit and on review of hygienic drinking water GSRC Progress Technical No Risk Identified for construction Report EIA Checklists workers. information. Water Use EMP 5.3 Require the contractors Compliant – observed on to coordinate with the review of GSRC Progress No Risk Identified estate to allocate water Technical Report EIA Checklists for hydrostatic test. information.

EMP 5.4 Storm water from storm Compliant – observed during water holding pond will site visit and on review of be used as the spray GSRC Progress Technical No Risk Identified waster for dust Report EIA Checklists suppression purpose. information.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 63

EMP 6.1 Compliant – observed on Assign workers to collect review of GSRC Progress refuse in the designated No Risk Identified Technical Report EIA Checklists area at least once a day. information.

EMP 6.2 Sanitary toilets shall be adequately provided for construction workers as required by Thai law. Additionally, a septic tank or a prefabricated wastewater treatment plant shall be constructed to treat wastewater from water used by construction Compliant – observed during worker so that treated site visit and on review of Waste Management GSRC Progress Technical No Risk Identified effluent standard. The Report EIA Checklists sewage in the information. prefabricated wastewater treatment plant shall be pump out for further disposal. The prefabricated wastewater treatment plant will be always maintained to ensure its efficiency throughout the construction phase

EMP 6.3 Deliver hazardous waste to the company licensed Compliant – observed on No Risk Identified by the government for review of GSRC Progress disposal as prescribed in Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 64

Ministry of Industry's Technical Report EIA Checklists Notification re: Disposal information. of Refuse or Discarded Materials, B.E. 2548 (2005).

EMP 6.4 Provide refuse bins for collection of refuse with Compliant – observed during well covered lids and site visit and on review of coordinate with the GSRC Progress Technical No Risk Identified company licensed by the Report EIA Checklists government to collect information. refuse for disposal.

EMP 6.5 Collect, store, and Partially Compliant – Some dispose of scrap poor housekeeping in terms of materials, earth debris storage of materials was Low Risk Identified and refuse from observed in the areas in front construction by of each Power Block (Refer to appropriate means. Photo 1 in Appendix 1).

EMP 6.6 Control management of Partially Compliant – There was oil from the project such a lack of space in the as the engine oil hazardous waste storage area changes and for further used oil storage. construction equipment. Used oil storage containers are Low Risk Identified Collect the oil in the being stored inappropriately tanks for delivery to the which could result in spillages company licensed by the (Refer to Photo 2 in government for Appendix 1). disposal.

EMP 6.7 Ensure that construction Compliant – observed during workers dispose solid site visit and on review of No Risk Identified waste in the bins and GSRC Progress Technical

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 65

empty the bins Report EIA Checklists regularly. information.

EMP 6.8 Compliant – observed during site visit and on review of Allocate appropriate GSRC Progress Technical No Risk Identified areas for stock yard. Report EIA Checklists information.

EMP 6.9 Compliant – observed on Strictly prohibit the review of GSRC Progress No Risk Identified burning of refuses. Technical Report EIA Checklists information.

EMP 6.10 Sort refuses and reusable scrap materials such as, wooden scraps, Compliant – observed during scrap iron, bricks, paint site visit and on review of tins, paint brushes, GSRC Progress Technical No Risk Identified spray cans and recycle Report EIA Checklists them or reuse or sell information. them to the buying companies.

EMP 6.11 The contractors must coordinate with the local municipality government agency to collect the Compliant – observed on refuse in order to review of GSRC Progress No Risk Identified prevent the refuse from Technical Report EIA Checklists accumulating in the information. project area which will be a source of disease and foul smells.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 66

EMP 7.1 Collect and sort scrap materials and refuse from construction activities and send them Compliant – observed during to the company licensed site visit and on review of by the government for GSRC Progress Technical No Risk Identified disposal in order to Report EIA Checklists prevent them from information. clogging the water draining route of the project.

EMP 7.2 Design an appropriate Compliant – observed during rainwater drainage site visit and on review of Water Drainage and system to prevent GSRC Progress Technical No Risk Identified Flood Control obstruction to existing Report EIA Checklists waterways and flooding information. in the vicinity.

EMP 7.3 Compliant – observed during Prohibit discarding of site visit and on review of refuse and scrap GSRC Progress Technical No Risk Identified materials in the water Report EIA Checklists drainage gutters. information.

EMP 7.4 Compliant – observed during Keep checking the water site visit and on review of drainage gutters GSRC Progress Technical No Risk Identified regularly to prevent Report EIA Checklists clogging. information.

EMP 8.1 Establish a “Complaint Socio-economics Receiving Center “in Compliant – observed on No Risk Identified order to publicize the review of GSRC Progress project and to listen to Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 67

opinions, suggestions Technical Report EIA Checklists and complaints. Those information. affected by the project about the impacts or the problems through in any manners or as deem appropriate, e.g. verbal complaints, telephone , memorandum, letter, Email, Fax., etc.

EMP 8.2 Comply with the environmental impact Partially Compliant – Refer to prevention and EMP 6.5 and EMP 6.6 for Low Risk Identified mitigation measures details. strictly.

EMP 8.3 Receive complaints regarding matters troubling people in the Compliant – observed on communities affected by review of GSRC Progress No Risk Identified the construction Technical Report EIA Checklists activities and take information. correction action on such impacts urgently.

EMP 8.4 Compliant – observed on Give priority of hiring review of GSRC Progress No Risk Identified qualified local residents. Technical Report EIA Checklists information.

EMP 8.5 Compliant – observed on Keep records of non- review of GSRC Progress local and foreign No Risk Identified Technical Report EIA Checklists worker. information.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 68

EMP 8.6 Assign the head of the project to supervise Compliant – observed on worker. Assign review of GSRC Progress No Risk Identified employees to monitor Technical Report EIA Checklists entry into and exit from information. the project strictly

EMP 8.7 Control construction Compliant – observed on activities and worker review of GSRC Progress behaviours to prevent No Risk Identified Technical Report EIA Checklists impacts on people in the information. vicinity

EMP 8.8 Provide the rest area for Compliant – observed during No Risk Identified the construction worker. site visit and on review of The rest area should be GSRC Progress Technical sited is safe location and Report EIA Checklists away the work in information. progress area.

EMP 8.9 Issue work regulation Compliant – observed on and ensure that review of GSRC Progress construction worker No Risk Identified Technical Report EIA Checklists strictly comply with the information. regulations.

EMP 8.10 Monitor and control workers’ behaviours Compliant – observed on closely if their living review of GSRC Progress quarters are near local No Risk Identified Technical Report EIA Checklists communities so as not information. to disturb the nearby communities.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 69

EMP 8.11 Publicize and clarify facts to the public urgently, in case of misunderstanding between the power plant, and the Compliant – observed on community through review of GSRC Progress various channels or No Risk Identified Technical Report EIA Checklists media so people receive information. factual information. Be prepared to demonstrate that the project will take responsibility and care about people’s feeling.

EMP 8.12 Take corrective action urgently where it is proved that the power plant is the cause of Compliant – observed on such impacts. Set up a review of GSRC Progress register of individuals or No Risk Identified Technical Report EIA Checklists groups being affected information. and use the data to implement stricter measures to prevent the problems.

EMP 8.13 Prepare a register of people effected, Compliant – observed on recording issues from review of GSRC Progress No Risk Identified the complaints or from Technical Report EIA Checklists the event as evidence. information. Record information related to proof of facts,

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 70

solutions, negotiations, and arrangements as evidence of the power plant operation.

EMP 10.1 Provide a first-aid unit, basic medication, and transporting vehicle in Compliant – observed during case of emergency in site visit and on review of the construction area in GSRC Progress Technical No Risk Identified accordance with Ministry Report EIA Checklists of Labour's Notification information. re: Provision for Welfare in the Business Premises, B.E.2548.

EMP 10.2 Compliant – observed during site visit and on review of Provide clean drinking GSRC Progress Technical No Risk Identified Public water for workers. Health/Occupational Report EIA Checklists Health and Safety information.

EMP 10.3 Compliant – observed during Provide toilets that meet site visit and on review of the public hygiene GSRC Progress Technical No Risk Identified principle with the ratio Report EIA Checklists of 15 workers per toilet. information. Refer to Section 3 for further details.

EMP 10.4 Before hiring worker, Contractor has the Compliant – observed on review of GSRC Progress process to interview and No Risk Identified carry out health & Technical Report EIA Checklists physical check-up and information. request for medical

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 71

check certificate to confirm that the person has incurable disease and congenital disease which obstruct to work. Contractor will provide first aid facility at Project site and worker’s accommodation. Local hospitals are used in case of emergency. All medical record will be maintained by Contractor at the project.

EMP 10.5 Train workers on health Compliant – observed on and hygiene, disease review of GSRC Progress prevention, behaviour to No Risk Identified Technical Report EIA Checklists avoid causing information. disturbance, drugs.

EMP 10.6 Two health awareness raising events per year Compliant – GSRC to are held for local undertake by the end of 2020. community member, Health awareness events including, if possible No Risk Identified expected to be undertaken targeted measures for remotely with training material girl’s education in WASH provided by leaflet form. practices, HIV/AIDS and safety.

EMP 10.7 Ensure the contractors Compliant – observed on comply with labour laws No Risk Identified review of GSRC Progress regarding physical

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 72

health check and risk- Technical Report EIA Checklists based health check. information.

EMP 10.8 Prepare a list of construction workers, Compliant – observed on report the number and review of GSRC Progress their chronic diseases to No Risk Identified Technical Report EIA Checklists the public health station information. responsible for the area prior to coming to work.

EMP 10.9 Provide training to workers and employees Complaint – Undertaken during on the knowledge of site induction, refer to EHS health and action in training records for the No Risk Identified case of serious or construction monitoring period emergency prior to in Section 5. commencement of the construction.

EMP 10.10 Provide hygienic Compliant – observed during sanitary environment in site visit and on review of the construction GSRC Progress Technical No Risk Identified workers' living quarters Report EIA Checklists and the construction information. Refer to Section 3 site. for details

EMP 10.11 Compliant – observed during Use strict security site visit and on review of system in the GSRC Progress Technical No Risk Identified construction workers' Report EIA Checklists living quarters. information.

EMP 10.12 Monitor contagious Compliant – observed on No Risk Identified disease jointly with the review of GSRC Progress

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 73

local public health Technical Report EIA Checklists agencies. information.

EMP 10.13 Prepare a list of construction worker, Compliant – observed on report the number and review of GSRC Progress their chronic diseases to No Risk Identified Technical Report EIA Checklists the public health station information. responsible for the area prior to coming to work.

EMP 10.14 Supervise and ensure that the contractors comply with the contract such as monitoring Compliant – observed during workers' living quarters, site visit and on review of random drug test, GSRC Progress Technical No Risk Identified garbage sorting in the Report EIA Checklists workers' living quarters information. in accordance with the principle and methods of for garbage management.

EMP 10.15 Provide channel of Compliant – observed on complaints through the review of GSRC Progress No Risk Identified Environmental Impacts Technical Report EIA Checklists Monitoring Committee. information.

EMP 10.16 Ensure that the contractors coordinate Compliant – observed on review of GSRC Progress with schools especially No Risk Identified kindergarten to primary Technical Report EIA Checklists education level at least information. 6 months prior to the

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 74

project construction in the case some workers need to enrol their children in the local schools.

EMP 10.17 Specify occupational health and safety measures in the agreement, requiring the contractors to do as follow. - The project specifies in the contract that the contractors and the operation team working Compliant – observed on review of GSRC Progress within the power plant No Risk Identified under the contracts shall Technical Report EIA Checklists implement occupational information.. health, safety and environment measures in their design, construction and operation to comply with the occupational health and safety standards, rules and regulation.

EMP 10.18 Compliant – observed during The project shall provide site visit and on review of competent personnel to GSRC Progress Technical No Risk Identified be in charge of Report EIA Checklists occupational health, information.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 75

safety and the environment.

EMP 10.19 The project and the main contractors shall establish an Occupational Health, Safety and Environment Committee (OHS Committee) that also consists of heads of Compliant – observed on subcontractors. The review of GSRC Progress Chairman of the OHS No Risk Identified Technical Report EIA Checklists Committee will report information. directly to the project manager. The OHS Committee shall hold a meeting at least once a month to assess the results and make suggestions for corrective actions.

EMP 10.20 The project shall provide a first-aid unit, basic medication, and transporting vehicle in Compliant – observed during case of emergency in site visit and on review of the construction area in GSRC Progress Technical No Risk Identified accordance with Ministry Report EIA Checklists of Labour’s Notification information. re: Provision for Welfare in the Business Premises, B.E.2548.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 76

EMP 10.21 The project shall require Compliant – observed on inspection of personal review of GSRC Progress protective equipment No Risk Identified Technical Report EIA Checklists regularly or as specified information. in the Safety Procedure.

EMP 10.22 Ensure the contractors comply with labor laws regarding physical health check and risk- Compliant – observed on based heath check. This review of GSRC Progress law is in accordance No Risk Identified Technical Report EIA Checklists with Ministerial information. Regulation on the Results of Health Check Up to Labor Inspector B.E. 2547 (A.D.2004).

EMP 10.23 A steel structure shall be installed for the Heat Compliant – observed during Recovery Steam site visit and on review of Generator. Also, a GSRC Progress Technical No Risk Identified walkway and a ladder Report EIA Checklists shall be provided for information. stability and safety.

EMP 10.24 Install insulation on the steam and hot water Not Applicable for Construction No Risk Identified pipes for the safety in Monitoring Period. careening out work.

EMP 10.25 Installation of Not Applicable for Construction equipment and No Risk Identified construction will be Monitoring Period. carried out by reliable Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 77

and experienced contractors with the safety officer supervising the safe conducts. Inspect and test the equipment and the construction by the engineer to ensure they meet the standard.

EMP 10.26 Inspect safety of the steam producing unit and to test the safety valves under the supervision of the Not Applicable for Construction engineer licensed for No Risk Identified Monitoring Period. inspection of the boilers in accordance with the Engineering Profession Act, B.E. 2505, before commissioning.

EMP 10.27 The main contractors must provide sufficient fire equipment for the persons working in the dangerous area or Compliant – observed during working with heat and site visit and on review of exposed to fire. For GSRC Progress Technical No Risk Identified example, in welding Report EIA Checklists work, welding team information. must have a dry chemical fire extinguisher near the place of work. For

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 78

welding at height, insulation lining must be placed underneath to prevent sparks from welding from catching fire underneath otherwise it is unsafe for persons working underneath the place of welding.

EMP 10.28 The main contractors Compliant – observed on must establish plans to review of GSRC Progress coordinate with the local No Risk Identified Technical Report EIA Checklists fire department in case information. of emergency.

EMP 10.29 Control of the entrance and exit of the dangerous zone where Compliant – observed during the construction works site visit and on review of are performed, control GSRC Progress Technical No Risk Identified of the traffic, install Report EIA Checklists warning clear signs by information. the supervisor in charge or by the safety officer.

EMP 10.30 Inspect function and condition of equipment Compliant – observed on to be used in the review of GSRC Progress No Risk Identified construction, especially Technical Report EIA Checklists at the places exposing information. to danger on fire.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 79

EMP 10.31 Inspect the working of Compliant – observed on the fire equipment review of GSRC Progress No Risk Identified regularly as specified in Technical Report EIA Checklists the Safety Procedure. information.

EMP 11.1 Designate the areas for welding of natural gas and diesel oil pipelines as "restricted areas”, in which working related to heat and sparking is Compliant – observed on prohibited. Signs of review of GSRC Progress No Risk Identified danger warning will be Technical Report EIA Checklists placed around the information. areas. In case it is necessary to work in the areas, permit must be obtained before accessing the areas. Major Hazard EMP 11.2 Fence the welding areas Compliant – observed on and put danger warning review of GSRC Progress signs, including No Risk Identified Technical Report EIA Checklists establishment of work information. permit system.

EMP 11.3 Before construction, the contractor must prepare and submit occupational health and safety action Compliant – HSE Action Plan No Risk Identified plan to Gulf SRC Co., for 2020 observed. Ltd., to approve and control implementation as planned.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 80

EMP 11.4 Compliant – observed during Provision of sufficient site visit and on review of personal protection GSRC Progress Technical No Risk Identified equipment, suitable for Report EIA Checklists nature of work to staffs. information.

EMP 11.5 Provision of safety personnel to watch and Compliant – observed during examine working, site visit and on review of including to control the GSRC Progress Technical No Risk Identified wearing of personal Report EIA Checklists protection equipment information. suitable for nature of works, as necessary.

EMP 11.6 Provision of suitable numbers of portable Compliant – observed during chemical fire site visit and on review of extinguishers and place GSRC Progress Technical No Risk Identified them in the construction Report EIA Checklists areas that may have information. firing.

EMP 11.7 Provision of first aid equipment and Compliant – observed during Emergency transport in site visit and on review of construction areas. As GSRC Progress Technical No Risk Identified required by the Ministry Report EIA Checklists of Labour's Regulations information. Welfare in Workplace (B.E. 2548).

EMP 11.8 Placing warning signs in Compliant – observed during the risk areas. No site visit and on review of No Risk Identified permission to work long GSRC Progress Technical Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 81

in this area, if no Report EIA Checklists personal protection information. equipment.

EMP 11.9 Coordinate with Compliant – observed on hospitals close to the review of GSRC Progress No Risk Identified project site for the case Technical Report EIA Checklists of emergency. information.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 82

5.5.1 IFC EHS Guidelines

The Projects compliance with the IFC EHS Guidelines during the construction monitoring period is shown in Table 5-14

Table 5-14 Project Compliance with IFC EHS Guidelines

IFC EHS Requirements Findings/Observations LTA Comment Guidelines

General EHS Air Emissions and Compliant - Guidelines: Ambient Air Quality. Environmental Energy Compliant - Conservation.

Wastewater and Compliant - Ambient Water Quality.

Water Conservation. Compliant -

Hazardous Materials Compliant - Management.

Waste Management. Partially Compliant Some poor housekeeping in terms of storage of materials was observed in the areas in front of each Power Block (Refer to Photo 1 in Appendix 1). There was a lack of space in the hazardous waste storage area for further used oil storage. Used oil storage containers are being stored inappropriately which could result in spillages (Refer to Photo 2 in Appendix 1).

Noise Compliant

Contaminated Land. Compliant -

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 83

IFC EHS Requirements Findings/Observations LTA Comment Guidelines

General EHS General Facility Compliant - Guidelines: Design and Occupational Operation. Health and Safety Communication and Compliant - Training.

Physical Hazards. Compliant -

Chemical Hazards. Compliant -

Biological Hazards. Compliant -

Radiological Compliant - Hazards.

Personal Protective Compliant - Equipment (PPE).

Special Hazard Compliant - Environment.

Monitoring. Compliant -

Community Water Quality and Compliant - Health & Safety Availability.

Structural Safety of Compliant - Project Infrastructure.

Life and Fire Safety Compliant - (L&FS).

Traffic Safety. Compliant -

Transport of Compliant - Hazardous Materials.

Disease prevention. Compliant -

Emergency Compliant - Preparedness and Response.

Construction and Environment. Partially Compliant Some poor Decommissioning housekeeping in terms of storage of materials was observed in the areas in front of

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 84

IFC EHS Requirements Findings/Observations LTA Comment Guidelines each Power Block (Refer to Photo 1 in Appendix 1). There is a lack of space in the hazardous waste storage area for further used oil storage and used oil storage containers are being stored inappropriately which could result in spillages (Refer to Photo 2 in Appendix 1).

Occupation Health & Compliant - Safety.

Community Health Compliant - & Safety.

5.5.2 Land Acquisition and Involuntary Resettlement

The Owner has acquired all necessary right of way and authorisations for the construction of the Interconnecting Pipeline as detailed in Section 5.2.

5.6 Associated Facilities

5.6.1 Hemaraj Raw Water Pipeline

Construction of the Hemaraj Raw Water Pipeline is complete and the LTA observed no E&S issues of concern.

5.6.2 500 kV Overhead Transmission Line

EGAT is responsible for constructing, testing and commissioning of the NTF required to connect the Power Plant to the EGAT Transmission Network. The progress as of September 2020 is reported as follows: • Foundation Work – completed 96.88% (completed 28 out of 29 transmission towers); • Tower Erection Work – completed 93.75% (completed 27 out of 29 transmission towers); • Stringing Work – completed 55.78% (completed 6.080 km out of 10.9 km); The latest land acquisition data made available to the LTA is as follows: • Land plots total 112 for the transmission line route. Compensation has been paid for 27 out of the 41 plots which are entitled to compensation. 47 plots are land areas under

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 85

agricultural land reform and 24 plots are public land which are not entitled to receive compensation but paid as rental fee. • Land plots total 20 for the transmission line towers. Compensation has been paid for 3 out of the 20 plots which are entitled to compensation The LTA will continue to seek support from the Owner to obtain up to date information from EGAT on the compensation payment status for the remaining landowners. The LTA understands that there are no issues of concern with the landowners and documentation is being processed to complete the compensation payments.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 86

6 Corrective Action Plan

The updated corrective action plan (CAP) following the monitoring results of this construction monitoring period is provided in Table 6-1

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 87

Table 6-1 Corrective Action Plan for the Construction Monitoring Period (July to September 2020)

# Date added Status Topic Description of action Responsibility Completion Timeframe evidence/KPI

1. 6th November Open Health and Update the accident/incident Owner and Updated 30th 2020 Safety reporting procedure to ensure all EPC accident/incident November accident/incidents which occur to Contractor reporting 2020 contractors past the 2nd tier procedure. contractor of Sino-Thai (based on the

high risk activities identified) are now separately reported and included in the EPC Contractor monthly reports. Ensure high risk activities are reviewed in the weekly EHS meetings and those activities are supervised by the EHS personnel of the EPC Contractor.

2. 6th November Open Health and Improve housekeeping/material Owner and Documentation 30th 2020 Safety storage. Ensure vehicles not being EPC showing improved November used are removed to avoid Contractor housekeeping 2020 congestion and do not cause an measures in place. unnecessary obstacle for workers.

3. 6th November Open Waste Ensure sufficient space in the Owner and Documentation 30th 2020 Management hazardous waste storage area to EPC showing sufficient November ensure materials/containers are Contractor capacity at the 2020 being stored appropriately. hazardous waste storage area for the expected amount of hazardous waste to be generated.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 88

# Date added Status Topic Description of action Responsibility Completion Timeframe evidence/KPI

4. 6th November Open Workers Investigate damage to room doors at Owner and Photographs 30th 2020 Camp Living the workers camp (Myanmar workers EPC showing doors November Conditions zone) and repair. Contractor repaired. 2020

5. 6th November Open Health and Ensure the corrective actions Owner and Updated Lifting 30th 2020 Safety identified concerned with the chain EPC Rigging Procedure. November block (5 ton) fall incident at HRSG#1 Contractor 2020 are included in the Lifting Rigging Procedure.

6. 6th November Open Health and Ensure the corrective actions Owner and Updated Chemical 30th 2020 Safety identified concerned with the incident EPC Handling November involving the release of Hydrochloric Contractor Procedure. 2020 Acid (HCL) vapor during unloading of HCL in the chemical storage area are included in the Chemical Handling Safety Procedure.

7. 6th November Open Information As part of the next Environmental Owner Environmental 18th 2020 Disclosure Impact Monitoring Committee Impact Monitoring December meeting identify through discussions Committee Minutes 2020 with the community representatives of Meeting and any lack of knowledge or Knowledge Sharing understanding in the communities Material. concerned with the following aspects: • Project technology i.e. gas fired not coal fired;

• Odours produced from the Projects operation;

• Light pollution.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 89

# Date added Status Topic Description of action Responsibility Completion Timeframe evidence/KPI Propose additional knowledge sharing material e.g. leaflets that could be distributed within the communities to improve knowledge for such aspects.

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 90

APPENDICES

APPENDIX 1 – SITE PHOTOS

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 91

Photo 1 - Example of Inappropriate Material Storage in Power Block Area

Photo 2 - Example of Inappropriate Storage of Used Oil Containers in Hazardous Waste Storage Area

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 92

Photo 3 – Working Conditions Inside Gas Turbine Building (Block#1)

Photo 4 – Example of Chemical Storage at the Water Treatment Plant

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 93

Photo 5 – Fuel Unloading in Fuel Oil Storage Area

Photo 6 - Example of Conditions at Raw Water Pond Area

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 94

Photo 7 - Example of Conditions at Workers Accommodation (1)

Photo 8 - Example of Conditions at Workers Accommodation (2)

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 95

Photo 9 - Example of Conditions at Wastewater Treatment Pond at Workers Camp

Photo 10 – Example of Damaged Doors at Workers Camp

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 96

Photo 11 – Example of Wash Facilities at Worker Camp

Photo 12 – Medical Room at Workers Camp

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 97

Photo 13 – Example of Construction Activities (Stringing) at the 500 kV Overhead Transmission Line

Photo 14 – Example of Workers Rest Area at Project Site

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0

Lenders’ Technical Advisor Quarterly Environmental and Social (E&S) Monitoring Report No. 7

Page 98

Photo 15 – Example of Conditions within the Medical Room at the Project Site

Photo 16 – Example of Conditions at Materials Storage Area in Power Plant Area

Gulf SRC 2,500 MW Combined Cycle Power Plant Project 127000407 copyright©AFRY

Date 10 November 2020, Revision 0