What are YOU Doing to MY Roads?
And When are You going to be Done? Tampa Airport Interchanges & www.myTBI.com Interstate 275
Overview of Projects Projects
www.myTBI.com Tampa Airport Interchanges Project Limits
www.myTBI.com Why are we doing this?
www.myTBI.com ••PartPart of a decadedecade--longlong program to improve II--275275 and SR 60
••NotNot enough capacity for today’s traffic or future traffic demands Why are we doing this?
www.myTBI.com ••SeparateSeparate roadways to various destinations (SR 60, Veterans Expressway, Airport)
••BetterBetter access to Tampa International Airport and the Westshore Business District Benefits
www.myTBI.com ••AddedAdded Capacity through additional lanes
•• Free --flow limited access highway through removal of traffic signals Benefits
www.myTBI.com ••ImprovedImproved operations through redundant ramping
•• Readily adaptable to future improvements Project is Significant
www.myTBI.com Money ~ What does this project cost us? $214 million ••RepresentedRepresented 12 % of 55--yearyear District 7 construction work plan (2006) when project began •• Financial Incentives: $13 M Project is Significant
www.myTBI.com Time Start Date ••August 15, 2005 Projected End Date ••OctoberOctober 2009 ~ Based on achieving all bonus dates and early completion incentives. Project is Significant
www.myTBI.com Time May 2010 ~ End of authorized contract time. A Few Facts…
www.myTBI.com How large is this project? Earthwork ••EmbankmentEmbankment (fill dirt) = 145,000 truck loads Enough to fill the St. Pete Times Forum 8 times A Few Facts…
www.myTBI.com How large is this project? Pavement ••55 ½ lane miles Equivalent to building a single lane from Clearwater to Lakeland A Few Facts…
www.myTBI.com Lighting ••441441 new light poles
Structures ••2121 new bridges & 38 new MSE/ retaining walls A Few Facts…
www.myTBI.com
Drainage ••566566 new inlets & manholes About 10 ½ miles of pipe ranging in sizes from 15” up to 60” diameter A Few Facts…
www.myTBI.com
Drainage • 4 major box culverts with the largest culvert running approximately ¼ mile underground from Memorial Highway to Courtney Campbell Parkway Maintenance Of Traffic (MOT) www.myTBI.com Total of 18 Phases Significant MOT Investment ••$13.7 million of the construction bid cost or about 7% of the contract value Maintenance Of Traffic (MOT) www.myTBI.com Interruptions to Traffic
Lane Closures Rolling Roadblocks Detours Maintenance Of Traffic (MOT) www.myTBI.com Rolling Roadblocks (Pacing) Used to slow traffic with Police Officers Restricted to night time hours (12:00 midnight to 4:00 AM) Maintenance Of Traffic (MOT) www.myTBI.com Detours Night time Multi --day Phase duration Maintenance Of Traffic (MOT) www.myTBI.com
Spruce St.
Laurel St. Detours
Night time Cypress St. Blvd. Blvd. Westshore Westshore Westshore Westshore
Kennedy Blvd. Maintenance Of Traffic (MOT) www.myTBI.com Detours Spruce St . Multi-day
Laurel St .
Cypress St . Blvd. Blvd. Westshore Westshore Westshore Westshore
Kennedy Blvd . Maintenance Of Traffic (MOT) www.myTBI.com
Detours Phase duration
Courtney Campbell Causeway SR 60 North of Courtney
www.myTBI.com Campbell Parkway area
Pre-construction Completed Courtney Campbell
www.myTBI.com Parkway area
Pre-construction Completed Courtney Campbell
www.myTBI.com Parkway area
Pre-construction Completed South of Courtney
www.myTBI.com Campbell Parkway area
Existing Completed Cypress Street area
www.myTBI.com
Pre-construction Completed TIA entrance/exit area
www.myTBI.com
Pre-construction Completed South of TIA area
www.myTBI.com
Pre-construction Completed Spruce Street area
www.myTBI.com
Pre-construction Completed Spruce Street interchange
www.myTBI.com
Completed O’Brien Street area
www.myTBI.com
Pre-construction Completed Recent Construction
www.myTBI.com
January 16, 2009 SR 60 interchange at TPA, Spruce Street, & Cypress Street Recent Construction
www.myTBI.com
January 2, 2009
Under the heart of the TPA interchange Recent Construction
www.myTBI.com
January 9, 2009
Decorative irrigation pond at TPA Construction last year
www.myTBI.com
MSE Wall Construction Recent Construction
www.myTBI.com
January 9, 2009
New access roads at Bayport Drive Construction last year
www.myTBI.com
Seawall along Tampa Bay Recent Construction
www.myTBI.com
Looking south at Memorial Highway from Independence Parkway
January 16, 2009 Recent Construction
www.myTBI.com
SR 60 on the Courtney Campbell next to Dana Shores
January 16, 2009 Recent Construction
www.myTBI.com
SR 60 at the Courtney Campbell / Memorial Hwy / Veterans Expressway interchange
January 16, 2009 Recent Construction
www.myTBI.com
Looking from I-275 towards Cypress Street
January 16, 2009 Recent De struction
www.myTBI.com
January 16, 2009 Demolishing bridge at TPA interchange Construction Challenges
www.myTBI.com
Traffic Environmental TPA Work Zone Access Other Development Neighborhoods Businesses Construction Challenges
www.myTBI.com
Traffic Construction Challenges
www.myTBI.com
TPA Construction Challenges
www.myTBI.com
TPA Notifying HCAA Crane Restrictions Imaginary Glide Path Work Lighting Operations w/in TPA ROW FAA Regulations Personnel Security Clearance I-275 Projects
www.myTBI.com
Current: Northbound II--275275 from Himes Avenue to downtown Started ----August 13, 2007 Finish --––earlyearly 2010
Current: Box Culvert from Lois Avenue to the Bay Started ----January 7, 2008 Finish --––SpringSpring 2009 Projects
www.myTBI.com
I-275 West Tampa Himes Avenue to downtown Tampa Construction Last Year
www.myTBI.com
Bridge Widening over the Hillsborough River
February 15, 2008 Construction last year
www.myTBI.com
Bridge Widening over the Hillsborough River
January 18, 2008 Recent Construction
www.myTBI.com
North Blvd. to Ashley Drive
January 16, 2009 Recent Construction
www.myTBI.com
Looking south at Howard / Armenia interchange
January 16, 2009 Recent Construction
www.myTBI.com
Decorative bridge treatments at Armenia Avenue
February 22, 2009 Recent Construction
www.myTBI.com
New concrete pavement west of Armenia / Howard exit
February 27, 2009 Recent Construction
www.myTBI.com
Concrete paving west of Mac Dill Avenue
February 22, 2009 Public Information
www.myTBI.com Publics Motorists Local Visitors Businesses Groups and associations Residents Adjacent Affected in other ways Media Public Information
www.myTBI.com myTBI.com web site ••WebWeb site ee--mailmail list Q & A
www.myTBI.com Thank you for your attention!
Questions? Comments?