NUCA PRESENTS THE GREATER CITY AREA CAPITAL IMPROVEMENT PROJECTS UPDATE FISCAL YEAR 2022

Program Book_2021.indd 1 4/26/21 6:57 PM TABLE OF Welcome ...... 3 CONTENTS City of Kansas City, KC Water......

Wastewater ...... 4 Water ...... 8 Public Works ...... 10 Aviation ...... 13 City of Kansas City, Kansas

Public Works ...... 14 Johnson County, Kansas

Wastewater ...... 15 City of Olathe, Kansas

Public Works ...... 16 U.S. Army Corps of Engineers

Flood Risk Management ...... 18 City of Grandview, Missouri

Public Works ...... 20

Kansas City District 2

Program Book_2021.indd 2 4/26/21 6:57 PM WELCOME

On behalf of NUCA KC, it is my honor to welcome you to the 9th Annual Greater Kansas City Area FY22 Capital Improvement Projects Update.

We understand that the ongoing COVID-19 situation is an unprecedented challenge for everyone, both personally and professionally. Our hearts and thoughts go out to all of our colleagues, families and, anyone affected by the virus.

The impact of COVID-19 is forcing organizations from all fields and industries to reconsider their all-important events in 2021, and ours is no exception. While we will miss seeing you in-person, we do look forward to the up- coming video conference. We are hopeful that next year we can once again meet together in the same space.

At this time, we would like to share with you some of the things that NUCA KC was involved with in 2020-2021. It is our hope that through our continued outreach we will grow in numbers and strength as we strive to work for the greater good of Kansas City.

• June 2020 - Kansas City’s Capital Improvement Projects Update FY22

• July 2020 - NUCA KC Scholarships

• July 2020 - NUCA Government Relations Meetings

• September 2020 - NUCA Washington, D.C. Summit

• November 2020 - Topgolf

• February 2021 - NUCA National Convention - Naples, FL

Thank you to all the local municipalities that have provided us with information on their upcoming projects. We have pulled together an amazing group that will be sharing this information with you.

Let us continue to work together as we strengthen the infrastructure of the Greater Kansas City area, and keep our cities and communities moving forward. Thank you for the attending the Greater Kansas City Area Capital Improvement Projects Update.

Tony Privitera President, NUCA KC

Capital Improvement Projects Update 3

Program Book_2021.indd 3 4/26/21 6:57 PM KC WATER

WASTEWATER PROJECT MANAGERS

BEN MCCABE KHOA NGUYEN WILLIE WILLIAMS

816.513.0434 816.513.0264 816.679.8995 [email protected] [email protected] [email protected]

PROJECT MANAGERS BLAKE ANDERSON KYLE TONJES

816.513.7258 816.601.2531 [email protected] [email protected]

BON GARDNER LAITH AFANA

816.513.0534 816.513.0433 [email protected] [email protected]

DEBRA SMITH MORRIS ROSS

816.513.0293 816.513.0361 [email protected] [email protected]

ISAAC GARLINGTON PAUL SOUTH

816.513.0436 816.513.0263 [email protected] [email protected]

KARINE PAPIKIAN PRIYA IYENGAR

816.513.0300 816.513.0579 [email protected] [email protected]

4

Program Book_2021.indd 4 4/26/21 6:57 PM KC WATER

WASTEWATER CONSTRUCTION PROJECTS WASTEWATER

WILLIE WILLIAMS WILLIE WILLIAMS 15th Street Pump Station Upgrade

816.679.8995 $5,500,000 | RFP/Bid: September 2021 [email protected]

DEBRA SMITH 4800 E. 63rd Street Wastewater ADA Compliance and Renovations $1,500,000 | RFP/Bid: September 2021

PAUL SOUTH ASR: City-Wide Sewer Rehabilitation $8,500,000 | RFP/Bid: May 2021

KHOA NGUYEN ASR: Large Diameter City-Wide Sewer Inspections $1,500,000 | RFP/Bid: April 2022

KHOA NGUYEN ASR: Large Diameter Sewer Rehabilitation $3,500,000 | RFP/Bid: April 2022

BEN MCCABE Baseline Improvements: Town Fork Creek $2,850,000 | RFP/Bid: September 2021

BEN MCCABE Dry Weather Sewer Line: Outfall 055 $2,500,000 | RFP/Bid: January 2022

PRIYA IYENGAR Green Infrastructure Project 1-1 Mill Creek Park $5,000,000 | RFP/Bid: April 2022

LAITH AFANA I/I Reduction: North of the River Phase 1 Buckeye Creek $8,500,000 | RFP/Bid: November 2021

Capital Improvement Projects Update 5

Program Book_2021.indd 5 4/26/21 6:57 PM KC WATER

WASTEWATER CONSTRUCTION PROJECTS

BEN MCCABE I/I Reduction: Northern Basins Project 2 $4,450,000 | RFP/Bid: November 2021

WASTEWATER BEN MCCABE Relief Sewer: Hardesty Ave and 31st Street $6,000,000 | RFP/Bid: November 2021

BEN MCCABE Relief Sewer: Vineyard and Lawn Street $4,500,000 | RFP/Bid: September 2021

KARINE PAPIKIAN Sanitary Sewer Assessment Program $1,000,000 | RFP/Bid: September 2021

KYLE TONJES Sewer Separation: 40th and Monroe $14,000,000 | RFP/Bid: March 2022

PRIYA IYENGAR Sewer Separation: Outfall 054 $3,900,000 | RFP/Bid: February 2022

WILLIE WILLIAMS Supplemental I/I Reduction Project: Round Grove $4,250,000 | RFP/Bid: December 2021

6

Program Book_2021.indd 6 4/26/21 6:57 PM KC WATER

WASTEWATER DESIGN PROJECTS WASTEWATER

BEN MCCABE I/I Reduction: Northern Basins Project 2 KHOA NGUYEN ASR: Force Main Inspection and Rehabilitation $4,450,000 | RFP/Bid: November 2021 $1,000,000 | RFP/Bid: February 2022

BEN MCCABE Relief Sewer: Hardesty Ave and 31st Street MORRIS ROSS Blue River Odor Control Phase II and III $6,000,000 | RFP/Bid: November 2021 $250,000 | RFP/Bid: February 2022

BEN MCCABE Relief Sewer: Vineyard and Lawn Street PRIYA IYENGAR Green Infrastructure Project 2-1 DMB Park $4,500,000 | RFP/Bid: September 2021 $3,000,000 | RFP/Bid: November 2022

KARINE PAPIKIAN Sanitary Sewer Assessment Program WASTEWATER DESIGN/BUILD PROJECTS

$1,000,000 | RFP/Bid: September 2021 ISAAC GARLINTON Blue River Pump Station Pump Station Screen Replacement $5,000,000 | RFP/Bid: October 2021

KYLE TONJES Sewer Separation: 40th and Monroe

$14,000,000 | RFP/Bid: March 2022 BLAKE ANDERSON Renewable Energy Public Private Partnership (P3) TBD | RFP/Bid: November 2021

PRIYA IYENGAR Sewer Separation: Outfall 054

$3,900,000 | RFP/Bid: February 2022 KHOA NGUYEN Sante Fe Sanitary Sewer Rehabilitation Phase 2 $5,500,000 | RFP/Bid: January 2022

WILLIE WILLIAMS Supplemental I/I Reduction Project: Round Grove $4,250,000 | RFP/Bid: December 2021 WASTEWATER STUDY PROJECTS

ISAAC GARLINTON Household Hazardous Waste Facility Study $200,000 | RFP/Bid: June 2021

BON GARDNER Pied Creek Pump Station Expansion and Rehabilitation $200,000 | RFP/Bid: June 2021

Capital Improvement Projects Update 7

Program Book_2021.indd 7 4/26/21 6:57 PM KC WATER

WATER PROJECT MANAGERS

BON GARDNER JOHN REDDY

816.513.0354 816.513.0377 [email protected] [email protected]

DAVIS MCDONALD KELLY FINN PROJECT MANAGERS 816.513.0171 816.513.0351 [email protected] [email protected]

JERRY STEVENS TERRY THOMAS

816.513.0446 816.513.0262 [email protected] [email protected]

WATER CONSTRUCTION PROJECTS

BON GARDNER ADA Compliance Building Renovations $400,000 | RFP/Bid: May 2022

DAVIS MCDONALD 131st Street Transmission Main from Holmes to Prospect $2,200,000 | RFP/Bid: October 2021

DAVIS MCDONALD Water Main at Hwy 150 and Botts Road $1,000,000 | RFP/Bid: July 2021

JOHN REDDY Prospect Road Elevated Water Storage Tank $10,000,000 | RFP/Bid: May 2021

KELLY FINN NE Shoal Creek Transmission Main from I-435 to MO Hwy 152 $3,000,000 | RFP/Bid: April 2022

8

Program Book_2021.indd 8 4/26/21 6:57 PM KC WATER

WATER CONSTRUCTION PROJECTS

KELLY FINN NE Shoal Creek Transmission Main from I-435 to MO Hwy 152 WATER $3,000,000 | RFP/Bid: April 2022

TERRY THOMAS Hardesty and 63rd Street Transmission Main Replacement $1,500,000 | RFP/Bid: June 2021

PM VARIES Water Main Replacements — 15 Projects $25,750,000 | RFP/Bid: TBD

WATER DESIGN PROJECTS

JERRY STEVENS Waukomis Transmission Main from NW 62nd to 68th Street $300,000 | RFP/Bid: September 2021

JOHN REDDY Water Master Plan Risk and Resilience Update $1,250,000 | RFP/Bid: August 2021

PM VARIES Water Main Replacements $3,500,000 | RFP/Bid: July 2021

PM VARIES SLBE-Water Main Replacements $1,00,000 | RFP/Bid: July 2021

WATER DESIGN/BUILD PROJECTS

TERRY THOMAS Water Main Replacement Design/Build $4,000,000 | RFP/Bid: September 2021 Capital Improvement Projects Update 9

Program Book_2021.indd 9 4/26/21 6:57 PM PUBLIC WORKS

PUBLIC WORKS PROJECT MANAGERS

KATY STEINBACHER MARIO VASQUEZ

816.513.2793 816.513.6984 [email protected] [email protected]

KIM PEMBERTON PATTY HILDERBRAND PROJECT MANAGERS 816.513.2741 816.513.2576 [email protected] [email protected]

PUBLIC WORKS CONSTRUCTION PROJECTS

KATY STEINBACHER N Green Hills Road from NW Barry Road to NW 78th Street $8,700,000 | RFP/Bid: Fall 2021

KATY STEINBACHER Swope Park Industrial Flyover Bridge $10,000,000 | RFP/Bid: Fall 2021

KATY STEINBACHER Raytown Road over Lumpkins Fork $3,500,000 | RFP/Bid: Summer 2021

KIM PEMBERTON N Stark Avenue Improvements $3,300,000 | RFP/Bid: Spring 2021

KIM PEMBERTON Lee’s Summit Road from Anderson Drive to Lakewood Blvd $9,300,000 | RFP/Bid: Summer 2021

KIM PEMBERTON NW Waukomis Drive from Englewood to NW 62nd Street $10,800,000 | RFP/Bid: Fall 2021

10

Program Book_2021.indd 10 4/26/21 6:57 PM PUBLIC WORKS

PUBLIC WORKS CONSTRUCTION PROJECTS PUBLIC WORKS

KIM PEMBERTON Gregory Boulevard Bridge over Blue River $8,400,000 | RFP/Bid: Spring 2022

KIM PEMBERTON Noland Rd and Hwy 350 - Street Improvements $6,300,000 | RFP/Bid: Spring 2022

KIM PEMBERTON Lee’s Summit Road Reconstruction - Lakewood Blvd to Gregory $9,500,000 | RFP/Bid: Spring/Summer 2022

KIM PEMBERTON 22nd/23rd Roadway improvements Phase III - Benton to Indiana $5,800,000 | RFP/Bid: Summer 2022

MARIO VASQUEZ 75th Street and Wornall Traffic Improvements $7,000,000 | RFP/Bid: Summer/Fall 2021

MARIO VASQUEZ NE Vivion Road — Streetscape Improvements $5,000,000 | RFP/Bid: Summer 2022

MARIO VASQUEZ Front Street Improvements - Universal Ave to Chouteau $12,000,000 | RFP/Bid: Spring 2021

PATTY HILDERBRAND Grand Blvd Bridge Bike/Ped Accommodations (3rd Street to Riverfront) $5,300,000 | RFP/Bid: Fall 2021

PATTY HILDERBRAND Benton Blvd Bridge over Brush Creek $4,000,000 | RFP/Bid: Summer 2022

Capital Improvement Projects Update 11

Program Book_2021.indd 11 4/26/21 6:57 PM PUBLIC WORKS

PUBLIC WORKS CONSTRUCTION PROJECTS

PATTY HILDERBRAND Byrams Ford Road Bridge over Round Grove Creek $1,400,000 | RFP/Bid: Spring 2023

PATTY HILDERBRAND Holmes Road from Blue Ridge Blvd to 137th Street PUBLIC WORKS $11,000,000 | RFP/Bid: Fall 2023

PUBLIC WORKS DESIGN/BUILD PROJECTS

PATTY HILDERBRAND 63rd Street Reconstruction - Woodland Avenue to Prospect Avenue $7,100,000 | RFP/Bid: Fall 2021

PATTY HILDERBRAND N Oak Trafficway Reconstruction - 42nd Street to 46th Street $8,500,000 | RFP/Bid: Winter 2021

PATTY HILDERBRAND Wornall Rd Reconstruction - Gregory Blvd to 75th Street $5,200,000 | RFP/Bid: Fall 2022

12

Program Book_2021.indd 12 4/26/21 6:57 PM PUBLIC WORKS AVIATION

AVIATION PROJECT MANAGERS

JADE LISKA MALLIE KOEHLER AVIATION

816.243.3045 816.243.3037 [email protected] [email protected]

JOEL TAYLOR

816.243.3042 [email protected]

AVIATION CONSTRUCTION PROJECTS

JADE LISKA Post Gate 1

& JOEL TAYLOR $2,500,000 | March 2022

JADE LISKA Post Gate 6

& JOEL TAYLOR $800,000 | July 2021

JADE LISKA Roadway Improvements

& MALLIE KOHLER $3,000,000 | August 2022

JADE LISKA KCI Bridge Repairs

& MALLIE KOHLER $2,000,000 | June 2022

Capital Improvement Projects Update 13

Program Book_2021.indd 13 4/26/21 6:57 PM PUBLIC WORKS

PUBLIC WORKS PROJECT MANAGERS

DAVE CLARK TRENTON FOGLESONG

913.573.5400 913.573.1300 [email protected] [email protected] PUBLIC WORKS

BRANDON GROVER

913.573.5400 [email protected]

PUBLIC WORKS DESIGN/BID/BUILD PROJECTS

PARTNER W/ WESTWOOD 47th Street Complete Street Improvements, Rainbow to Mission $1,800,000 | RFP/Bid: 2022

BRANDON GROVER Annual Pavement Preservation $7,300,000 | RFP/Bid: January 2022

TRENTON FOGLESONG Annual Sanitary Sewer Rehab $2,555,000 | RFP/Bid: January 2022

TRENTON FOGLESONG Annual Stream Crossing Repairs

$735,000 | RFP/Bid: January 2022

DAVE CLARK Hutton & Leavenworth Road Intersection Reconstruction $6,000,000 | Design 2021, Construction 2022-2023

TRENTON FOGLESONG Kaw Point Biosolids Digestion $75,000,000 | RFP/Bid: 2022

14

Program Book_2021.indd 14 4/26/21 6:57 PM PUBLIC WORKS JOHNSON COUNTY WASTEWATER

WASTEWATER PROJECT MANAGERS

ISAAC CRABTREE ALEX SZERWINSKI SEWER

913.715.8544 913.715.8549 [email protected] [email protected]

ANDY WENDEL

913.715.8540 [email protected]

SEWER DESIGN/BID/BUILD PROJECTS

ISAAC CRABTREE Cedar Mill Forcemain Replacement $1,100,000 | RFP/Bid: June 2021

ISAAC CRABTREE 103rd and Metcalf Interceptor Improvements $5,000,000 | RFP/Bid: June 2021

ANDY WENDEL Dyke’s Branch Pump Station Improvements $4,800,000 | RFP/Bid: December 2022

ALEX SZERWINSKI Middle Basin WWTF Solids Thickening System Upgrades $5,000,000 | RFP/Bid: February 2022

ALEX SZERWINSKI Turkey Creek WWTF Structural Repairs $2,100,000 | RFP/Bid: December 2021

Capital Improvement Projects Update 15

Program Book_2021.indd 15 4/26/21 6:57 PM OLATHE

PUBLIC WORKS, WATER & SEWER PROJECT MANAGERS

MATT KAPFER NICO ESTRADA-STEPHEN

913.971.9004 913.971.9245 [email protected] [email protected]

THERESE VINK AUSTIN LAMPARTER PROJECT MANAGERS 913.971.9032 913.971.9057 [email protected] [email protected]

CHAD JONES AARON WASKO

913.971.9066 913.971.9108 [email protected] [email protected]

SCOTT WARD NICOLE WOODS

913.971.9020 913.971.9119 [email protected] [email protected]

SEWER CONSTRUCTION PROJECTS

AARON WASKO Cedar Lake Lift Station $1,600,000 | RFP/Bid: July 2021

NICOLE WOODS 103rd Lift Station and Force Main Improvements $3,500,000 | RFP/Bid: November 2021

PUBLIC WORKS DESIGN PROJECTS

THERESE VINK 167th & Ridgeview Geometric Improvements $3,000,000 | RFP/Bid: October 2021

MATT KAPFER Indian Creek-Lindenwood, Jamestown to Arrowhead, Stormwater Improvements $6,200,000 | RFP/Bid: November 2021 16

Program Book_2021.indd 16 4/26/21 6:57 PM OLATHE

PUBLIC WORKS CONSTRUCTION PROJECTS PUBLIC WORKS

CHAD JONES Mill Creek, Prairie to Cedar, Stormwater Improvements $10,000,000 | RFP/Bid: May 2021

MATT KAPFER Stagecoach and Sleepy Hollow Stormwater Improvements $2,375,000 | RFP/Bid: May 2022

SCOTT WARD 135th & Pflumm Geometric Improvements $3,870,000 | RFP/Bid: May 2022

MATT KAPFER Cedar Creek Parkway South of College Improvements $9,400,000 | RFP/Bid: June 2021

SCOTT WARD Pflumm Road, 143rd to 151st, Improvements $18,700,000 | RFP/Bid: March 2022 SEWER CONSTRUCTION PROJECTS

AARON WASKO Cedar Lake Lift Station NICO ESTRADA-STEPHEN Highland Park Neighborhood Street Improvements $1,600,000 | RFP/Bid: July 2021 $1,800,000 | RFP/Bid: April 2022

NICOLE WOODS 103rd Lift Station and Force Main Improvements AUSTIN LAMPARTER Ridgeview West Neighborhood Street Improvements $3,500,000 | RFP/Bid: November 2021 $1,400,000 | RFP/Bid: March 2022

PUBLIC WORKS DESIGN PROJECTS CHAD JONES Provence Village Street Improvements

THERESE VINK 167th & Ridgeview Geometric Improvements $1,200,000 | RFP/Bid: April 2022 $3,000,000 | RFP/Bid: October 2021 WATER DESIGN PROJECTS

NICOLE WOODS Remote Facilities Improvements MATT KAPFER Indian Creek-Lindenwood, Jamestown to Arrowhead, Stormwater Improvements $6,200,000 | RFP/Bid: November 2021 $5,800,000 | RFP/Bid: June 2021 Capital Improvement Projects Update 17

Program Book_2021.indd 17 4/26/21 6:57 PM U.S. ARMY CORPS OF ENGINEERS Kansas City District KC LEVEES U.S. ARMY CORPS OF ENGINEERS PROJECT MANAGERS

BRAD PETTIJOHN KENT MYERS

816.389.3823 816.389.3399 [email protected] [email protected] FLOOD RISK

CRAIG WELTIG SCOTT MENSING MANAGEMENT 816.389.3091 816.389.2321 [email protected] [email protected]

ERIC BRANDT THARETH CASEY

816.389.3109 816.389.2216 [email protected] [email protected]

JOE SCIARRA ZACK PARSONS

816.389.3121 816.389.2352 [email protected] [email protected]

U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION PROJECTS

BRAD PETTIJOHN Manhattan, KS Levee Raise $10,000,000+ |RFP/Bid: May 2021

CRAIG WELTIG MRLS 471-460-R - Levee Raise North of 36 Hwy $10,000,000+ | RFP/Bid: January 2022

CRAIG WELTIG MRLS 455-L - Swing Gate $1,000,000 - $5,000,000 | RFP/Bid: March 2022

18

Program Book_2021.indd 18 4/26/21 6:57 PM U.S. ARMY CORPS OF ENGINEERS KC LEVEES MANAGEMENT U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION PROJECTS FLOOD RISK ERIC BRANDT Harry S. Truman Dam - Station Drainage Pump Replacement $500,000 - $1,000,000 | RFP/Bid: May 2021

JOE SCIARRA Smithville Dam - Stilling Basin Wall Drain $500,000 - $1,000,000 | RFP/Bid: June 2021

KENT MYERS Kanopolis Lake - Admin Building Repair $100,000 - $500,000 | RFP/Bid: September 2021

SCOTT MENSING Kansas City Levees $250,000,000 - $500,000,000 | RFP/Bid: May 2021

THARETH CASEY Hillsdale Dam - Rip Rap Placement $100,000 - $500,000 | RFP/Bid: August 2021

THARETH CASEY Harlan County Dam - CMP & Culvert Replacement $100,000 - $500,000 | RFP/Bid: August 2021

THARETH CASEY Wilson Dam - Relief Well Replacement $500,000 - $1,000,000 | RFP/Bid: September 2021

ZACK PARSONS Roadwork Multiple Award Task Order Contract & Seed Task Order $20,000,000 (Individual task orders vary)| RFP/Bid: June 2021

Kansas City District

Capital Improvement Projects Update 19

Program Book_2021.indd 19 4/26/21 6:57 PM GRANDVIEW

PUBLIC WORKS & SEWER PROJECT MANAGER

DOUG WESSELSCHMIDT

816.316.4857 [email protected] & SEWER

PUBLIC WORKS PUBLIC WORKS DESIGN/CONSTRUCTION PROJECTS

DOUG WESSELSCHMIDT KCS Railroad Bridge over Blue Ridge Blvd $7,500,000 | RFP/Bid: August 2021

DOUG WESSELSCHMIDT Raytown Road Bridge over Longview Lake Tributary $2,454,000 | RFP/Bid: April 2022

DOUG WESSELSCHMIDT MO-150 Highway Enhancements/Turnlanes $3,800,000 | RFP/Bid: January 2022

DOUG WESSELSCHMIDT KCS Railroad Bridge over Grandview Road $7,500,000 | RFP/Bid: March 2024

DOUG WESSELSCHMIDT 135th Street Multi-use Path

$200,000 | RFP/Bid: March 2022

SEWER DESIGN/CONSTRUCTION PROJECTS

DOUG WESSELSCHMIDT 120th Terrace Sanitary Sewer Replacement $700,000 | RFP/Bid: October 2021

DOUG WESSELSCHMIDT 140th Street & Falkirk Drive $250,000 | RFP/Bid: October 2021 20

Program Book_2021.indd 20 4/26/21 6:57 PM GRANDVIEW

NOTES NOTES

Capital Improvement Projects Update 21

Program Book_2021.indd 21 4/26/21 6:57 PM THANK YOU TO OUR SPONSORS

PLATINUM SPONSORS

22

Program Book_2021.indd 22 4/26/21 6:57 PM THANK YOU TO OUR SPONSORS

GOLD SPONSORS

SILVER SPONSORS

FRONT TOP CENTER (Velure: 2-color blue and black) OLATHE

FRONT TOP CENTER (Velure: white) OLATHE

Capital Improvement Projects Update 23