NUCA PRESENTS THE GREATER KANSAS CITY AREA CAPITAL IMPROVEMENT PROJECTS UPDATE FISCAL YEAR 2022
Program Book_2021.indd 1 4/26/21 6:57 PM TABLE OF Welcome ...... 3 CONTENTS City of Kansas City, Missouri KC Water......
Wastewater ...... 4 Water ...... 8 Public Works ...... 10 Aviation ...... 13 City of Kansas City, Kansas
Public Works ...... 14 Johnson County, Kansas
Wastewater ...... 15 City of Olathe, Kansas
Public Works ...... 16 U.S. Army Corps of Engineers
Flood Risk Management ...... 18 City of Grandview, Missouri
Public Works ...... 20
Kansas City District 2
Program Book_2021.indd 2 4/26/21 6:57 PM WELCOME
On behalf of NUCA KC, it is my honor to welcome you to the 9th Annual Greater Kansas City Area FY22 Capital Improvement Projects Update.
We understand that the ongoing COVID-19 situation is an unprecedented challenge for everyone, both personally and professionally. Our hearts and thoughts go out to all of our colleagues, families and, anyone affected by the virus.
The impact of COVID-19 is forcing organizations from all fields and industries to reconsider their all-important events in 2021, and ours is no exception. While we will miss seeing you in-person, we do look forward to the up- coming video conference. We are hopeful that next year we can once again meet together in the same space.
At this time, we would like to share with you some of the things that NUCA KC was involved with in 2020-2021. It is our hope that through our continued outreach we will grow in numbers and strength as we strive to work for the greater good of Kansas City.
• June 2020 - Kansas City’s Capital Improvement Projects Update FY22
• July 2020 - NUCA KC Scholarships
• July 2020 - NUCA Government Relations Meetings
• September 2020 - NUCA Washington, D.C. Summit
• November 2020 - Topgolf
• February 2021 - NUCA National Convention - Naples, FL
Thank you to all the local municipalities that have provided us with information on their upcoming projects. We have pulled together an amazing group that will be sharing this information with you.
Let us continue to work together as we strengthen the infrastructure of the Greater Kansas City area, and keep our cities and communities moving forward. Thank you for the attending the Greater Kansas City Area Capital Improvement Projects Update.
Tony Privitera President, NUCA KC
Capital Improvement Projects Update 3
Program Book_2021.indd 3 4/26/21 6:57 PM KC WATER
WASTEWATER PROJECT MANAGERS
BEN MCCABE KHOA NGUYEN WILLIE WILLIAMS
816.513.0434 816.513.0264 816.679.8995 [email protected] [email protected] [email protected]
PROJECT MANAGERS BLAKE ANDERSON KYLE TONJES
816.513.7258 816.601.2531 [email protected] [email protected]
BON GARDNER LAITH AFANA
816.513.0534 816.513.0433 [email protected] [email protected]
DEBRA SMITH MORRIS ROSS
816.513.0293 816.513.0361 [email protected] [email protected]
ISAAC GARLINGTON PAUL SOUTH
816.513.0436 816.513.0263 [email protected] [email protected]
KARINE PAPIKIAN PRIYA IYENGAR
816.513.0300 816.513.0579 [email protected] [email protected]
4
Program Book_2021.indd 4 4/26/21 6:57 PM KC WATER
WASTEWATER CONSTRUCTION PROJECTS WASTEWATER
WILLIE WILLIAMS WILLIE WILLIAMS 15th Street Pump Station Upgrade
816.679.8995 $5,500,000 | RFP/Bid: September 2021 [email protected]
DEBRA SMITH 4800 E. 63rd Street Wastewater ADA Compliance and Renovations $1,500,000 | RFP/Bid: September 2021
PAUL SOUTH ASR: City-Wide Sewer Rehabilitation $8,500,000 | RFP/Bid: May 2021
KHOA NGUYEN ASR: Large Diameter City-Wide Sewer Inspections $1,500,000 | RFP/Bid: April 2022
KHOA NGUYEN ASR: Large Diameter Sewer Rehabilitation $3,500,000 | RFP/Bid: April 2022
BEN MCCABE Baseline Improvements: Town Fork Creek $2,850,000 | RFP/Bid: September 2021
BEN MCCABE Dry Weather Sewer Line: Outfall 055 $2,500,000 | RFP/Bid: January 2022
PRIYA IYENGAR Green Infrastructure Project 1-1 Mill Creek Park $5,000,000 | RFP/Bid: April 2022
LAITH AFANA I/I Reduction: North of the River Phase 1 Buckeye Creek $8,500,000 | RFP/Bid: November 2021
Capital Improvement Projects Update 5
Program Book_2021.indd 5 4/26/21 6:57 PM KC WATER
WASTEWATER CONSTRUCTION PROJECTS
BEN MCCABE I/I Reduction: Northern Basins Project 2 $4,450,000 | RFP/Bid: November 2021
WASTEWATER BEN MCCABE Relief Sewer: Hardesty Ave and 31st Street $6,000,000 | RFP/Bid: November 2021
BEN MCCABE Relief Sewer: Vineyard and Lawn Street $4,500,000 | RFP/Bid: September 2021
KARINE PAPIKIAN Sanitary Sewer Assessment Program $1,000,000 | RFP/Bid: September 2021
KYLE TONJES Sewer Separation: 40th and Monroe $14,000,000 | RFP/Bid: March 2022
PRIYA IYENGAR Sewer Separation: Outfall 054 $3,900,000 | RFP/Bid: February 2022
WILLIE WILLIAMS Supplemental I/I Reduction Project: Round Grove $4,250,000 | RFP/Bid: December 2021
6
Program Book_2021.indd 6 4/26/21 6:57 PM KC WATER
WASTEWATER DESIGN PROJECTS WASTEWATER
BEN MCCABE I/I Reduction: Northern Basins Project 2 KHOA NGUYEN ASR: Force Main Inspection and Rehabilitation $4,450,000 | RFP/Bid: November 2021 $1,000,000 | RFP/Bid: February 2022
BEN MCCABE Relief Sewer: Hardesty Ave and 31st Street MORRIS ROSS Blue River Odor Control Phase II and III $6,000,000 | RFP/Bid: November 2021 $250,000 | RFP/Bid: February 2022
BEN MCCABE Relief Sewer: Vineyard and Lawn Street PRIYA IYENGAR Green Infrastructure Project 2-1 DMB Park $4,500,000 | RFP/Bid: September 2021 $3,000,000 | RFP/Bid: November 2022
KARINE PAPIKIAN Sanitary Sewer Assessment Program WASTEWATER DESIGN/BUILD PROJECTS
$1,000,000 | RFP/Bid: September 2021 ISAAC GARLINTON Blue River Pump Station Pump Station Screen Replacement $5,000,000 | RFP/Bid: October 2021
KYLE TONJES Sewer Separation: 40th and Monroe
$14,000,000 | RFP/Bid: March 2022 BLAKE ANDERSON Renewable Energy Public Private Partnership (P3) TBD | RFP/Bid: November 2021
PRIYA IYENGAR Sewer Separation: Outfall 054
$3,900,000 | RFP/Bid: February 2022 KHOA NGUYEN Sante Fe Sanitary Sewer Rehabilitation Phase 2 $5,500,000 | RFP/Bid: January 2022
WILLIE WILLIAMS Supplemental I/I Reduction Project: Round Grove $4,250,000 | RFP/Bid: December 2021 WASTEWATER STUDY PROJECTS
ISAAC GARLINTON Household Hazardous Waste Facility Study $200,000 | RFP/Bid: June 2021
BON GARDNER Pied Creek Pump Station Expansion and Rehabilitation $200,000 | RFP/Bid: June 2021
Capital Improvement Projects Update 7
Program Book_2021.indd 7 4/26/21 6:57 PM KC WATER
WATER PROJECT MANAGERS
BON GARDNER JOHN REDDY
816.513.0354 816.513.0377 [email protected] [email protected]
DAVIS MCDONALD KELLY FINN PROJECT MANAGERS 816.513.0171 816.513.0351 [email protected] [email protected]
JERRY STEVENS TERRY THOMAS
816.513.0446 816.513.0262 [email protected] [email protected]
WATER CONSTRUCTION PROJECTS
BON GARDNER ADA Compliance Building Renovations $400,000 | RFP/Bid: May 2022
DAVIS MCDONALD 131st Street Transmission Main from Holmes to Prospect $2,200,000 | RFP/Bid: October 2021
DAVIS MCDONALD Water Main at Hwy 150 and Botts Road $1,000,000 | RFP/Bid: July 2021
JOHN REDDY Prospect Road Elevated Water Storage Tank $10,000,000 | RFP/Bid: May 2021
KELLY FINN NE Shoal Creek Transmission Main from I-435 to MO Hwy 152 $3,000,000 | RFP/Bid: April 2022
8
Program Book_2021.indd 8 4/26/21 6:57 PM KC WATER
WATER CONSTRUCTION PROJECTS
KELLY FINN NE Shoal Creek Transmission Main from I-435 to MO Hwy 152 WATER $3,000,000 | RFP/Bid: April 2022
TERRY THOMAS Hardesty and 63rd Street Transmission Main Replacement $1,500,000 | RFP/Bid: June 2021
PM VARIES Water Main Replacements — 15 Projects $25,750,000 | RFP/Bid: TBD
WATER DESIGN PROJECTS
JERRY STEVENS Waukomis Transmission Main from NW 62nd to 68th Street $300,000 | RFP/Bid: September 2021
JOHN REDDY Water Master Plan Risk and Resilience Update $1,250,000 | RFP/Bid: August 2021
PM VARIES Water Main Replacements $3,500,000 | RFP/Bid: July 2021
PM VARIES SLBE-Water Main Replacements $1,00,000 | RFP/Bid: July 2021
WATER DESIGN/BUILD PROJECTS
TERRY THOMAS Water Main Replacement Design/Build $4,000,000 | RFP/Bid: September 2021 Capital Improvement Projects Update 9
Program Book_2021.indd 9 4/26/21 6:57 PM PUBLIC WORKS
PUBLIC WORKS PROJECT MANAGERS
KATY STEINBACHER MARIO VASQUEZ
816.513.2793 816.513.6984 [email protected] [email protected]
KIM PEMBERTON PATTY HILDERBRAND PROJECT MANAGERS 816.513.2741 816.513.2576 [email protected] [email protected]
PUBLIC WORKS CONSTRUCTION PROJECTS
KATY STEINBACHER N Green Hills Road from NW Barry Road to NW 78th Street $8,700,000 | RFP/Bid: Fall 2021
KATY STEINBACHER Swope Park Industrial Flyover Bridge $10,000,000 | RFP/Bid: Fall 2021
KATY STEINBACHER Raytown Road over Lumpkins Fork $3,500,000 | RFP/Bid: Summer 2021
KIM PEMBERTON N Stark Avenue Improvements $3,300,000 | RFP/Bid: Spring 2021
KIM PEMBERTON Lee’s Summit Road from Anderson Drive to Lakewood Blvd $9,300,000 | RFP/Bid: Summer 2021
KIM PEMBERTON NW Waukomis Drive from Englewood to NW 62nd Street $10,800,000 | RFP/Bid: Fall 2021
10
Program Book_2021.indd 10 4/26/21 6:57 PM PUBLIC WORKS
PUBLIC WORKS CONSTRUCTION PROJECTS PUBLIC WORKS
KIM PEMBERTON Gregory Boulevard Bridge over Blue River $8,400,000 | RFP/Bid: Spring 2022
KIM PEMBERTON Noland Rd and Hwy 350 - Street Improvements $6,300,000 | RFP/Bid: Spring 2022
KIM PEMBERTON Lee’s Summit Road Reconstruction - Lakewood Blvd to Gregory $9,500,000 | RFP/Bid: Spring/Summer 2022
KIM PEMBERTON 22nd/23rd Roadway improvements Phase III - Benton to Indiana $5,800,000 | RFP/Bid: Summer 2022
MARIO VASQUEZ 75th Street and Wornall Traffic Improvements $7,000,000 | RFP/Bid: Summer/Fall 2021
MARIO VASQUEZ NE Vivion Road — Streetscape Improvements $5,000,000 | RFP/Bid: Summer 2022
MARIO VASQUEZ Front Street Improvements - Universal Ave to Chouteau $12,000,000 | RFP/Bid: Spring 2021
PATTY HILDERBRAND Grand Blvd Bridge Bike/Ped Accommodations (3rd Street to Riverfront) $5,300,000 | RFP/Bid: Fall 2021
PATTY HILDERBRAND Benton Blvd Bridge over Brush Creek $4,000,000 | RFP/Bid: Summer 2022
Capital Improvement Projects Update 11
Program Book_2021.indd 11 4/26/21 6:57 PM PUBLIC WORKS
PUBLIC WORKS CONSTRUCTION PROJECTS
PATTY HILDERBRAND Byrams Ford Road Bridge over Round Grove Creek $1,400,000 | RFP/Bid: Spring 2023
PATTY HILDERBRAND Holmes Road from Blue Ridge Blvd to 137th Street PUBLIC WORKS $11,000,000 | RFP/Bid: Fall 2023
PUBLIC WORKS DESIGN/BUILD PROJECTS
PATTY HILDERBRAND 63rd Street Reconstruction - Woodland Avenue to Prospect Avenue $7,100,000 | RFP/Bid: Fall 2021
PATTY HILDERBRAND N Oak Trafficway Reconstruction - 42nd Street to 46th Street $8,500,000 | RFP/Bid: Winter 2021
PATTY HILDERBRAND Wornall Rd Reconstruction - Gregory Blvd to 75th Street $5,200,000 | RFP/Bid: Fall 2022
12
Program Book_2021.indd 12 4/26/21 6:57 PM PUBLIC WORKS AVIATION
AVIATION PROJECT MANAGERS
JADE LISKA MALLIE KOEHLER AVIATION
816.243.3045 816.243.3037 [email protected] [email protected]
JOEL TAYLOR
816.243.3042 [email protected]
AVIATION CONSTRUCTION PROJECTS
JADE LISKA Post Gate 1
& JOEL TAYLOR $2,500,000 | March 2022
JADE LISKA Post Gate 6
& JOEL TAYLOR $800,000 | July 2021
JADE LISKA Roadway Improvements
& MALLIE KOHLER $3,000,000 | August 2022
JADE LISKA KCI Bridge Repairs
& MALLIE KOHLER $2,000,000 | June 2022
Capital Improvement Projects Update 13
Program Book_2021.indd 13 4/26/21 6:57 PM PUBLIC WORKS
PUBLIC WORKS PROJECT MANAGERS
DAVE CLARK TRENTON FOGLESONG
913.573.5400 913.573.1300 [email protected] [email protected] PUBLIC WORKS
BRANDON GROVER
913.573.5400 [email protected]
PUBLIC WORKS DESIGN/BID/BUILD PROJECTS
PARTNER W/ WESTWOOD 47th Street Complete Street Improvements, Rainbow to Mission $1,800,000 | RFP/Bid: 2022
BRANDON GROVER Annual Pavement Preservation $7,300,000 | RFP/Bid: January 2022
TRENTON FOGLESONG Annual Sanitary Sewer Rehab $2,555,000 | RFP/Bid: January 2022
TRENTON FOGLESONG Annual Stream Crossing Repairs
$735,000 | RFP/Bid: January 2022
DAVE CLARK Hutton & Leavenworth Road Intersection Reconstruction $6,000,000 | Design 2021, Construction 2022-2023
TRENTON FOGLESONG Kaw Point Biosolids Digestion $75,000,000 | RFP/Bid: 2022
14
Program Book_2021.indd 14 4/26/21 6:57 PM PUBLIC WORKS JOHNSON COUNTY WASTEWATER
WASTEWATER PROJECT MANAGERS
ISAAC CRABTREE ALEX SZERWINSKI SEWER
913.715.8544 913.715.8549 [email protected] [email protected]
ANDY WENDEL
913.715.8540 [email protected]
SEWER DESIGN/BID/BUILD PROJECTS
ISAAC CRABTREE Cedar Mill Forcemain Replacement $1,100,000 | RFP/Bid: June 2021
ISAAC CRABTREE 103rd and Metcalf Interceptor Improvements $5,000,000 | RFP/Bid: June 2021
ANDY WENDEL Dyke’s Branch Pump Station Improvements $4,800,000 | RFP/Bid: December 2022
ALEX SZERWINSKI Middle Basin WWTF Solids Thickening System Upgrades $5,000,000 | RFP/Bid: February 2022
ALEX SZERWINSKI Turkey Creek WWTF Structural Repairs $2,100,000 | RFP/Bid: December 2021
Capital Improvement Projects Update 15
Program Book_2021.indd 15 4/26/21 6:57 PM OLATHE
PUBLIC WORKS, WATER & SEWER PROJECT MANAGERS
MATT KAPFER NICO ESTRADA-STEPHEN
913.971.9004 913.971.9245 [email protected] [email protected]
THERESE VINK AUSTIN LAMPARTER PROJECT MANAGERS 913.971.9032 913.971.9057 [email protected] [email protected]
CHAD JONES AARON WASKO
913.971.9066 913.971.9108 [email protected] [email protected]
SCOTT WARD NICOLE WOODS
913.971.9020 913.971.9119 [email protected] [email protected]
SEWER CONSTRUCTION PROJECTS
AARON WASKO Cedar Lake Lift Station $1,600,000 | RFP/Bid: July 2021
NICOLE WOODS 103rd Lift Station and Force Main Improvements $3,500,000 | RFP/Bid: November 2021
PUBLIC WORKS DESIGN PROJECTS
THERESE VINK 167th & Ridgeview Geometric Improvements $3,000,000 | RFP/Bid: October 2021
MATT KAPFER Indian Creek-Lindenwood, Jamestown to Arrowhead, Stormwater Improvements $6,200,000 | RFP/Bid: November 2021 16
Program Book_2021.indd 16 4/26/21 6:57 PM OLATHE
PUBLIC WORKS CONSTRUCTION PROJECTS PUBLIC WORKS
CHAD JONES Mill Creek, Prairie to Cedar, Stormwater Improvements $10,000,000 | RFP/Bid: May 2021
MATT KAPFER Stagecoach and Sleepy Hollow Stormwater Improvements $2,375,000 | RFP/Bid: May 2022
SCOTT WARD 135th & Pflumm Geometric Improvements $3,870,000 | RFP/Bid: May 2022
MATT KAPFER Cedar Creek Parkway South of College Improvements $9,400,000 | RFP/Bid: June 2021
SCOTT WARD Pflumm Road, 143rd to 151st, Improvements $18,700,000 | RFP/Bid: March 2022 SEWER CONSTRUCTION PROJECTS
AARON WASKO Cedar Lake Lift Station NICO ESTRADA-STEPHEN Highland Park Neighborhood Street Improvements $1,600,000 | RFP/Bid: July 2021 $1,800,000 | RFP/Bid: April 2022
NICOLE WOODS 103rd Lift Station and Force Main Improvements AUSTIN LAMPARTER Ridgeview West Neighborhood Street Improvements $3,500,000 | RFP/Bid: November 2021 $1,400,000 | RFP/Bid: March 2022
PUBLIC WORKS DESIGN PROJECTS CHAD JONES Provence Village Street Improvements
THERESE VINK 167th & Ridgeview Geometric Improvements $1,200,000 | RFP/Bid: April 2022 $3,000,000 | RFP/Bid: October 2021 WATER DESIGN PROJECTS
NICOLE WOODS Remote Facilities Improvements MATT KAPFER Indian Creek-Lindenwood, Jamestown to Arrowhead, Stormwater Improvements $6,200,000 | RFP/Bid: November 2021 $5,800,000 | RFP/Bid: June 2021 Capital Improvement Projects Update 17
Program Book_2021.indd 17 4/26/21 6:57 PM U.S. ARMY CORPS OF ENGINEERS Kansas City District KC LEVEES U.S. ARMY CORPS OF ENGINEERS PROJECT MANAGERS
BRAD PETTIJOHN KENT MYERS
816.389.3823 816.389.3399 [email protected] [email protected] FLOOD RISK
CRAIG WELTIG SCOTT MENSING MANAGEMENT 816.389.3091 816.389.2321 [email protected] [email protected]
ERIC BRANDT THARETH CASEY
816.389.3109 816.389.2216 [email protected] [email protected]
JOE SCIARRA ZACK PARSONS
816.389.3121 816.389.2352 [email protected] [email protected]
U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION PROJECTS
BRAD PETTIJOHN Manhattan, KS Levee Raise $10,000,000+ |RFP/Bid: May 2021
CRAIG WELTIG MRLS 471-460-R - Levee Raise North of 36 Hwy $10,000,000+ | RFP/Bid: January 2022
CRAIG WELTIG MRLS 455-L - Swing Gate $1,000,000 - $5,000,000 | RFP/Bid: March 2022
18
Program Book_2021.indd 18 4/26/21 6:57 PM U.S. ARMY CORPS OF ENGINEERS KC LEVEES MANAGEMENT U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION PROJECTS FLOOD RISK ERIC BRANDT Harry S. Truman Dam - Station Drainage Pump Replacement $500,000 - $1,000,000 | RFP/Bid: May 2021
JOE SCIARRA Smithville Dam - Stilling Basin Wall Drain $500,000 - $1,000,000 | RFP/Bid: June 2021
KENT MYERS Kanopolis Lake - Admin Building Repair $100,000 - $500,000 | RFP/Bid: September 2021
SCOTT MENSING Kansas City Levees $250,000,000 - $500,000,000 | RFP/Bid: May 2021
THARETH CASEY Hillsdale Dam - Rip Rap Placement $100,000 - $500,000 | RFP/Bid: August 2021
THARETH CASEY Harlan County Dam - CMP & Culvert Replacement $100,000 - $500,000 | RFP/Bid: August 2021
THARETH CASEY Wilson Dam - Relief Well Replacement $500,000 - $1,000,000 | RFP/Bid: September 2021
ZACK PARSONS Roadwork Multiple Award Task Order Contract & Seed Task Order $20,000,000 (Individual task orders vary)| RFP/Bid: June 2021
Kansas City District
Capital Improvement Projects Update 19
Program Book_2021.indd 19 4/26/21 6:57 PM GRANDVIEW
PUBLIC WORKS & SEWER PROJECT MANAGER
DOUG WESSELSCHMIDT
816.316.4857 [email protected] & SEWER
PUBLIC WORKS PUBLIC WORKS DESIGN/CONSTRUCTION PROJECTS
DOUG WESSELSCHMIDT KCS Railroad Bridge over Blue Ridge Blvd $7,500,000 | RFP/Bid: August 2021
DOUG WESSELSCHMIDT Raytown Road Bridge over Longview Lake Tributary $2,454,000 | RFP/Bid: April 2022
DOUG WESSELSCHMIDT MO-150 Highway Enhancements/Turnlanes $3,800,000 | RFP/Bid: January 2022
DOUG WESSELSCHMIDT KCS Railroad Bridge over Grandview Road $7,500,000 | RFP/Bid: March 2024
DOUG WESSELSCHMIDT 135th Street Multi-use Path
$200,000 | RFP/Bid: March 2022
SEWER DESIGN/CONSTRUCTION PROJECTS
DOUG WESSELSCHMIDT 120th Terrace Sanitary Sewer Replacement $700,000 | RFP/Bid: October 2021
DOUG WESSELSCHMIDT 140th Street & Falkirk Drive $250,000 | RFP/Bid: October 2021 20
Program Book_2021.indd 20 4/26/21 6:57 PM GRANDVIEW
NOTES NOTES
Capital Improvement Projects Update 21
Program Book_2021.indd 21 4/26/21 6:57 PM THANK YOU TO OUR SPONSORS
PLATINUM SPONSORS
22
Program Book_2021.indd 22 4/26/21 6:57 PM THANK YOU TO OUR SPONSORS
GOLD SPONSORS
SILVER SPONSORS
FRONT TOP CENTER (Velure: 2-color blue and black) OLATHE
FRONT TOP CENTER (Velure: white) OLATHE
Capital Improvement Projects Update 23