Environmental Management Plan

Public Disclosure Authorized for

Hongya County Restructuring Component of Small Towns Development Project by World Bank Loans

Public Disclosure Authorized (EMP)

Public Disclosure Authorized

Public Disclosure Authorized Hongya County Housing and Urban-Rural Construction Bureau July 2015

Contents

1. PROJECT DESCRIPTION ...... 1 1.1. INTRODUCTION ...... 1 1.2. THE TARGET OF ENVIRONMENT MANAGEMENT PLAN ...... 7 2. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 9 2.1 LAWS, REGULATIONS AND DOCUMENTS RELEVANT TO ENVIRONMENTAL PROTECTION ...... 9 2.2 GUIDELINES AND TECHNICAL SPECIFICATIONS ...... 10 2.3 PROJECT RELATED DOCUMENTS ...... 11 2.4 SAFEGUARD POLICY FOR THE WORLD BANK ...... 12 2.5 ENVIRONMENTAL QUALITY STANDARD ...... 16 2.6POLLUTANT EMISSION STANDARD ...... 18 3.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 19 3.1 MAJOR ENVIRONMENTAL IMPACTS ...... 19 3.2 MITIGATION MEASURES ...... 35 4.0 ORGANIZATION FOR EMP IMPLEMENTATION ...... 38 4.1 ENVIRONMENTAL MANAGEMENT AND MONITORING ORGANIZATION ...... 38 4.2 TRAINING AND CAPABILITY BUILDING ...... 41 5.0 MONITORING PROGRAM ...... 42 5.1 MONITORING PROGRAM ...... 42 5.2 MANAGEMENT SYSTEM ...... 44 6.0 PUBLIC CONSULTATION ...... 46 6.1 PUBLIC CONSULTATION ...... 46 6.2 THE SPECIFIC WAYS OF PUBLIC CONSULTATION ...... 47 6.3 INFORMATION DISCLOSURE...... 48 7.0 INVESTMENT ESTIMATION ...... 49

Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

1. PROJECT DESCRIPTION

1.1. INTRODUCTION As early as 2009, Hongya County started implementing “water diversion” with World Bank financing. The project passed World Bank’s appraisal in August 2010. The county government undertakes the “water diversion” (diversion canal) project. The total length is 9200m and the estimated investment is RMB 104,816,600. The development unit is the planning and construction bureau of Hongya County. The construction organizations are Zhejiang Provincial No. 1 Water Conservancy & Electric Power Construction Group Holdings Co., Ltd and Hunan Lyulin Municipal Landscape Engineering Co., Ltd. The project is implemented smoothly. The preliminary work including land requisition, demolition and displacement and resettlement was completed. Currently, construction 9km diversion canal has been completed. Integrating with regulation of the south and the north moats, this project can promote reconstruction of old areas of Hongya. Landscape along the canal can be improved. Land-use pattern of the country can be optimized, and the environment quality can be improved. In 2013, Hongya County (Hongchuan Town) Environmental Improvement Subproject of Sichuan Small Towns Development Project by World Bank Loans was commenced, with the construction items including drainage works, river channel improvement works, and water diversion works. Currently, the Subproject has been basically completed, and the water quality and environmental benefits have been effectively improved. Hongchuan Town Subproject, located downstream from the Project, is the improvement and extension of Phase I Project. World Bank was granted to Hongya County Component of Sichuan Small Towns Development Project just based on the above background condition. The purpose is to improve and extend “water diversion” project of Hongya County. In addition, it aims at enhancing life quality of both Hongya residents and tourism population by improving municipal infrastructure of Liujiang Town. In June 2014, Hongya County Housing and Urban-Rural Construction Bureau filled out the

1

Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan screening schedule for Hongya County Component of Sichuan Small Towns Development Project By World Bank Loans. In August, Hongya County Housing and Urban-Rural Construction Bureau compiled Project Proposal for Hongya County Component of Sichuan Small Towns Development Project By World Bank Loans. Besides improvement and extension water conversion project of Hongya County, municipal infrastructure improvement project of Liujiang County, another key tourist county was included in the proposal.

2

Hongya County Restructuring Component of Sichuan Small Towns Environmental Management Plan Development Project by World Bank Loans

Hongchuan Town Project

Liujiang Town Project

Figure 1 Project Location Map

3 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan According to Feasibility Study Report of Hongya County Component of Sichuan Small Towns Development Project by World Bank Loans, the project financed by World Bank is divided into two subprojects. Hongchuan Town Subproject, including 1) river channel project: dredge waterway 2.2km and desilt 106,800m3; improve riverine wetland 6.37801ha (about 95.62mu); newly construct river embankment 2.2km, and improve and repair embankment 1.8km. 2) Sewage pipe: lay and embed sewage pipe 2.35km. Liujiang Town Subproject, including 1) road engineering: build 2.36km new road. According to the planned level, width of the road is 8-12m. Construct auxiliary underground pipe network, lighting and signs and marks; 2) bridge engineering: build 3 new bridges including one foot bridge and two vehicular bridges; 3) urban rainwater garden engineering: build 67312.17m2 public lawn, about 100mu. Adopt green infrastructure concept. Integrate with road rainwater regeneration system. Form an integrated urban rain-flood management system and public green space resources for recreation of residents and tourists; 4) Water treatment plant and supporting pipe network engineering: build one water treatment plant taking an area of 7.5mu. The current (by 2020) scale is 2500m 3/d. In the long term (by 2030), the scale is expected to reach 4500m3/d. build 12km new waterlines; 5) digital city engineering: establish geo-spatial data framework, element mesh data, management component data, geocoding data and other data resource platforms. Form an integrated, closed, interconnecting and interworking digital urban municipal supervision and management system; 6) Eco parking lot engineering. Build eco parking lot (one storey) with a total area of 7954m 2, 228 car parking spaces and 9 bus parking spaces, in total 237 motor vehicle parking spaces;60 public rental bicycle parking spaces. Project investment: RMB 118,073,200.

6 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Summary of Project Content

Project Name Content Proposed

Hongchuan Town Subproject: 1. River channel project: dredge waterway 2.2km and desilt 106,800m3; improve riverine wetland 6.37801ha (about 95.62mu); newly construct river embankment 2.2km, and improve and repair embankment 1.8km. 2. Sewage pipe: lay and embed sewage pipe 2.35km.

Liujiang Town Subproject: 1.Road engineering: build 2.36km new road. According to the planned Hongya County level, width of the road is 8-12m. Hereinto, lengths of A1 road, A2 road, Component of C1 road and C2 road to be built are 652.07m, 333.33m, 448.27m and Sichuan Small 26.8m respectively. Towns 2.Bridge engineering: build 3 new bridges including one foot bridge Development (Huaxi River Foot Bridge) and two vehicular bridges (Huaxi River Project By Bridge and Liujiang River Bridge); World Bank 3. Water supply engineering: build one water treatment plant taking an Loans area of 7.5mu. The current (by 2020) scale is 2500m3/d. In the long term (by 2030), the scale is expected to reach 4500m3/d. build 12km new waterlines; 4. Urban rainwater garden engineering: build 67312.17m2 public lawn, about 100mu. 5. Eco parking lot engineering. Build eco parking lot (one storey) with a total area of 7954m2, 228 car parking spaces and 9 bus parking spaces, in total 237 motor vehicle parking spaces;60 public rental bicycle parking spaces. 1.2. THE TARGET OF ENVIRONMENT MANAGEMENT

PLAN The Environmental Management Plan will adopt mitigation measures according to the identified environmental impacts, and supervise the effectiveness of the measures during the lifespan of the Project. The Environmental Management Plan based on the Environmental Impact Assessment, is compiled according to the Chinese environmental laws and guidelines, safeguard policies of World Bank, and optimal practices of similar projects. The purpose of Environmental Management Plan is to ensure the consistency between Environmental Impact Assessment and Environmental Management Plan, so as to satisfy the relevant standards of environmental protection. The Environmental Management Plan can effectively satisfy the supervisory requirements, instructing the Project owner on management of contractors and subcontractors. The Environmental Management Plan for Hongya County Subproject has been effectively implemented in the Phase I project, and the environmental mitigation

7 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan measures in the project construction process have all been put into practice. The implementation of the Environmental Management Plan has effectively eliminated or mitigated the adverse environmental impacts that might arise during the project construction and generally achieved the expected goals of the project.

8 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

2. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

2.1 LAWS, REGULATIONS AND DOCUMENTS RELEVANT TO

ENVIRONMENTAL PROTECTION

(1) Environmental Protection Law of the People’s Republic of (taking effect on January 1, 2015); (2) Law on Environment Impact Assessment of the People’s Republic of China (taking effect on September 1, 2003); (3) Noise Pollution Abatement Law of the People’s Republic of China (taking effect on March 1, 1997); (4) Water Pollution Prevention Law of the People’s Republic of China (taking effect on June 1, 2008); (5) Air Pollution Prevention Law of the People’s Republic of China (revised on April 29, 2000 and taking effect on September 1, 2000); (6) Solid Waste Pollution Prevention Law of the People’s Republic of China (taking effect on April 1, 1996); (7) Soil and Water Conservation Law of the People’s Republic of China (taking effect on March 1, 2011); (8) Regulations on the Administration of Construction Project Environmental Protection (Decree No. 253 in 1998 of the State Council of the People’s Republic of China, taking effect on November 29, 1998); (9) Notice on Implementing ‘Regulations on the Administration of Construction Project Environmental Protection’ (Document [1999] 107 of State Environmental Protection Administration, taking effect on April 29, 1999); (10) Notice on Problems in Executing Environmental Impact Assessment on Construction Projects (Document [1999] 107 of State Environmental Protection Administration, taking effect on April 29, 1999); (11) Notice on Strengthening Environmental Projection in Construction Projects

9 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan (Document [2001] 19 of State Environmental Protection Administration, taking effect on February 21, 2001); (12) Catalogue of Environmental Impact Assessment for Construction Projects (taking effect on October 1, 2008); (13) Management Measures of Environmental Protection in Traffic Construction Projects ([1990] Decree No. 17 of Ministry of Communications, taking effect in 1990); (14) Notice on Printing and Issuing Regulation of Water and Soil Conservation in Road Construction Projects (Document No. 12 in 2001 of Ministry of Water Resources and Ministry of Communications, taking effect in 2001); (15) Notice on Further Standardizing Environment Impact Assessment ([2002] No. 88 of State Environmental Protection Administration, taking effect in 2002); (16) Environmental Protection Act of Sichuan Province (taking effect on September 24, 2004); (17) Urban and Rural Planning Law of the People’s Republic of China, taking effect on January 1, 2008; (18) Cultural Relics Protection Law of the People’s Republic of China (taking effect on October 28, 2002); Enforcement Regulations for Cultural Relics Protection Law of the People’s Republic of China; (19) Instruction for Constructing Innovative Transportation Industry (Ministry of Communications, July 24, 2006); (20) Notice on Environmental Protection Engineering Inspection and Acceptance of Construction Projects upon Completion (Environmental Protection Department of Sichuan (2003) No. 56); (21) Notice on Further Strengthening Environmental Protection Work in Distributed Drinking Water Sources (Ministry of Environmental Protection of the People's Republic of China (2010 No. 132); (22) Notice on Planning of Urban Centralized Drinking Water Source Protection Areas issued by General Office of the People’s Government of Sichuan Province 2.2 Guidelines and technical specifications (1) Guideline for Environmental Impact Assessment· General Principles (HJ 2.1-2011);

10 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan (2) Guideline for Environmental Impact Assessment· Atmospheric Environment (HJ 2.2-2008); (3) Guideline for Environmental Impact Assessment· Surface Water Environment (HJ/T 2.3-93); (4) Guideline for Environmental Impact Assessment· Acoustic Environment (HJ 2.4-2009); (5) Guideline for Environmental Impact Assessment· Groundwater Environment (HJ 610-2011); (6) Guideline for Environmental Impact Assessment· Ecological Impact (HJ 19-2011); (7) Technical Guideline for Environmental Risk Assessment of Construction Projects (HJ/T 169-2004);

(8) Technical Manual for Ecological Environment Condition Assessment on trial (HJ/T 192-2006); (9) Water and Soil Conservation and Comprehensive Treatment Technical Specifications (GB/T 16543.1~16453.6 - 2008); (10) Technical Manual for Water and Soil Conservation in Development and Construction Projects (GB 50433-2008); (11) World Bank Operations Manual——OP4.01 World Bank Program, Environmental Assessment; (12) World Bank Operations Manual——BP4.01 World Bank Program, Environmental Assessment; (13) World Bank Operations Manual——OP4.04 World Bank Policy, Natural Residence; (14) World Bank Operations Manual——OP4.11 World Bank Program, Cultural Properties; (15) World Bank Operations Manual——OP4.12 World Bank Program, Involuntary Immigration 2.3 Project Related Documents (1) World Bank Loan—Feasibility Study Report on Hongya County Component of

11 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Sichuan Small Towns Development Project (Apr. 2015) (2) Instructions on Applying for Hongya County Component of Sichuan Small Towns Development Project By World Bank Loans (HFG [2014] No. 107) by Hongya Development and Reform Bureau, Finance Bureau of Hongya, Hongya County Housing and Urban-Rural Construction Bureau (3) Reply on Executive Standard for Environmental Impact Assessment for Sichuan Small Towns Development Project By World Bank Loans of Housing and Urban and Rural Construction Bureau (MSHJH [2015] No. 47) by Environmental Protection Bureau (4) Descriptions on Planning And Construction Conditions of “Hongya County Component of Sichuan Small Towns Development Project By World Bank Loans” by Hongya County Housing and Urban-Rural Construction Bureau (5) Descriptions on Regional Drinking Water Source of “Hongya County Component of Sichuan Small Towns Development Project By World Bank Loans” by Environmental Protection Bureau of Hongya County 2.4 Safeguard policy of the World Bank

2.4.1 Ten safeguard policies of the World Bank and the compliance analysis

The World Bank has established ten safeguard business policies in social and environmental aspects. The screening is conducted to determine whether the project is involved with the ten policies as per the construction property, project layout and assessment scope determined by the environmental assessment and site investigation. The results are shown in Table 2-1 below:

Table2-1 Compliance Analysis for the Safeguard Policies of the World Bank Involved by

the Project Applicable S/N Safeguard policy Compliance condition (Yes/No) Class A project ; OP/BP4.01 Prepare the complete Environmental Impact Assessment and 1 Environmental Yes Environmental Management Plan; Assessment as a part of the environmental impact assessment procedure and conduct the two rounds public consultation; OP/BP4.04 This policy is not initiated. No natural habitats are involved in 2 No Natural Habitat the land area and waters of the project area.

12 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

The policy is not enabled. The project won’t subsidize the OP/BP4.36 significant change or degradation activities involved with the 3 No Forest important forests or relevant important natural habitats defined in the policy. OP/BP4.09 The policy is not enabled. The project won’t purchase any Management for insecticide nor lead to the increasing of the application amount 4 No Diseases and Insect of the application amount. As per the policy, no activity is Pests required to be adopted. OP/BP4.11 The project does not involve the damage of the physical 5 Physical Cultural No resources. Resources OP/BP4.37 The policy is not enabled. There is no dam within the project 6 No Dam Safety area. OP/BP4.10 The policy is not enabled. There is no native living in the 7 No The Native project area or impact on the native. OP/BP4.12 Applicable to resettlement of inhabitant and prepare the 8 Yes Involuntary Migrants Resettlement Action Plan; OP/BP7.50 The policy is not enabled. The project does not involve any 9 International No international waterway. Waterway Project OP/BP7.60 The policy is not enabled. The project doesn’t involve any 10 Project at the Dispute No dispute region. Region 2.4.2 Analysis on the compliance of the project with the provisions in the EHS Guidelines of the World Bank and relevant policies

The sewage treatment in the EHS Guidelines (general guidelines) and the Guidelines for Water, Hygienic Environment, Health and Safety, and the collection and transportation of the wastes in the Guidelines for Environment, Health and Safety of Toll Road and the Guidelines for Environment, Health and Safety of Management Facility for Wastes of the World Bank Group are also applicable to the project. The relieve measures included in the Environmental Management Plan of the project completely comply with the requirements of the above guidelines (especially the contents related to the construction management). It should be noted that the contents mentioned in the Guidelines basically comply with the Chinese laws, regulations, guide rules and construction management rules.

Table 2-2 Schedule of the Compliance of the Project Required by the EHS Guidelines of the

World Bank Compliance condition of the Environmental Impact EHS Guidelines of the World Bank Assessment/Environmental Management Plan

13 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

If the facilities or the project is near the identified ecological sensitive region (such as national park), then the increasing of the pollution level shall be declined as far as There is no ecological sensitive region near the project possible under the feasible premise. In area. addition, appropriate relieve measures also include application of the clean fuel or techniques or application of the comprehensive pollution control measures. Dust or particulate matter (PM) is the most The dust control method is adopted during the common contaminants among the unorganized construction period, e.g. covering or spraying water for emissions. Some operation (such as dust suppression or improving the water content of the transportation and open-air storage of the solid open-air material stacks, and adopting the spraying materials) and the bare soil surface (including water for suppression method to control the material the unpaved road) will release the particulate transportation on the paved or unpaved road surface. matter.

Table 2-3 Schedule of the Compliance of the Project Required by the Guidelines for Water, Hygienic Environment, Health and Safety of the World Bank Guidelines for Water, Hygienic Environment, Compliance condition of the Environmental Health and Safety Impact Assessment/Environmental Management There is no production waste water discharged during the project construction period, and the Discharging industrial wastewater, domestic domestic waste water is treated with the existing wastewater, and the wastewater or rainwater sewage treatment facility in the rented house. produced by public works operation to the Part of the production waste water of the water public or private waste water treatment system purification plant during the project operational shall comply with the pretreatment and period shall be recycled, the sludge water shall be monitoring requirements of the sewage discharged and the supernatant liquid shall be treatment system in which above mentioned discharged after concentration treatment, and the water are discharged. domestic wastewater shall be transported to the sewage plant for treatment with sewage vehicles. Rainwater shall be separated from the industrial wastewater and the domestic wastewater to Rainwater and sewage shall be divided at the project reduce the waste water quantity that can be area. discharged only after being treated; Select the equipment with low sound power level; The noise prevention and control measures shall install the vibration isolating device for the be adopted, if at the most sensitive acceptance mechanical device; point, the noise caused by project facility or Limit the performance time of specific equipment or operation activity is estimated to be exceed operation, especially the mobile noise source moving relevant noise index. within the community;

14 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Table 2-4 Schedule of the Compliance of the Project Required by the Guidelines for Environment, Health and Safety of Toll Road of the World Bank Guidelines for Environment, Health and Compliance condition of the Environmental Safety of Toll Road Impact Assessment/Environmental Management Under appropriate conditions, the important land and hydrophytic habitat (such as mature old-growth forest, wet land and fish spawning The region where the project is located does not habitat) through selecting appropriate location belong to the important land and hydrophytic habitat of the road and the supporting facility and taking advantage of the existing traffic corridor; Cleaning of the local plant species shall be The water and soil conservation scheme is specially reduced as far as possible during the prepared, and the appropriate local herbaceous plant construction, and the local plant species shall be shall be planted as per the water and soil replanted at the disturbed areas. conservation scheme measures. During the construction period, the paving Conduct the paving for the road in dry weather construction is prohibited in strong wind weather, to prevent the pitch or cement material from and the construction site shall be determined loss; reasonably; The construction machine oily water collector shall The oil water separator shall be used in the be equipped for the construction site to collect the treatment work no matter whether it will generated oily water. The collected oily water shall generate a lot of grease; be sent to the unit which has the processing capacity for treatment, and direct discharging is prohibited. The following measures shall be adopted to The requirements are specially put forward in the avoid the pollution generated from cleaning the specifications of the Contractor for the “storage of pitch equipment, namely, using the vegetable oil the fuel, oil and dangerous toxic substance”, all fuels instead of diesel oil as the releasing agent and at eh construction site shall be stored within the rails; the cleaning agent; prevent the cleaning product the storage area shall be 110% of the fuel storage and the polluted pitch residual from leakage; container. The fuel storage area shall not be close to conduct the scraping prior to cleaning; and any water source (namely: within 100m from the conduct the cleaning activity far away from the water source); surface water or the water discharge facility. Adopt the acoustic measure for the surrounding During the road operational period, the function of architectural structure (normally is replacing the the region along the main trunk road, the roadside windows); structure shall be reasonably planned layout and the Use the road surface with low road surface/tyre acoustic design shall be optimized, and the speed friction noise, such as stone matrix asphalt limiting management shall be strengthened. mixture.

15 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Table 2-5 Schedule of the Compliance of the Project Required by the Guidelines for Environment, Health and Safety of Management Facility for Wastes of the World Bank Guidelines for Environment, Health and Compliance condition of the Environmental Safety of Management Facility for Wastes Impact Assessment/Environmental Management Delivered to the waste treatment plant of Hongya Collection and transportation of the wastes County for unified treatment. Encourage to use dustbin or garbage bag at the garbage collection point near each family and the buildings; collect the garbage on a regular basis with sufficient frequency to avoid the accumulation of the garbage; cover the garbage collection and transportation vehicles to prevent the garbage from blowing off during driving; Collect the garbage on a regular basis; Formulate the cleaning plan for the garbage Put the garbage on specified point, and the garbage collection vehicles and all garbage collection shall be transported by the sanitation department containers of the enterprise; uniformly to the waste treatment plant for treatment. Advocate using garbage bag to prevent the garbage collection equipment from pollution. Optimize the garbage collection line to reduce the transportation distance and reduce the total fuel consumption and discharge; Set the transfer station for the small size garbage collection vehicle to collect all collected garbage on the large size vehicle to transport the garbage to the waste treatment plant; 2.5 Environmental Quality Standard

2.5.1 Ambient air quality Class 2 in Ambient Air Quality Standard (GB3095-2012) is executed in the project areas. Table 2-6 Class 2 standard of ambient air quality (GB3095-2012) Concentration standard Pollutants Unit of concentration Annual mean Daily mean One-hour mean

PM10 0.10 0.15 / mg/m3 NO2 0.04 0.08 0.20 (standard state) SO2 0.06 0.15 0.50 2.5.2 Water environment quality The Class III standard in Environmental Quality Standards for Surface Water

16 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan (GB3838-2002) is executed for the surface water involved in the project. Table 2-7 Environmental quality standard value for surface water (unit: mg/l) Index Normal value( mg/L) Basis pH 6-9 Ammonia nitrogen ≤1.0 Volatile phenol ≤0.005 The Ⅲ water standard of Oils ≤0.05 (GB3838-2002) CODcr ≤20

BOD5 ≤4.0 Fecal coliforms ≤10000(No.) Third-grade criterion described in the Quality Standard for Underground Water (GB/T14848-93). Table 2-8 Environmental quality standard value for underground water (unit: mg/l) Index Normal value Basis pH 6.5-8.5 Permanganate index ≤3.0

Ammonia nitrogen ≤0.2 The Ⅲ water standard of (GB/T14848-93) Volatile phenol ≤0.002 Chlorides ≤250 Total coliforms ≤3.0 2.5.3 Acoustic environment quality Grade 4a and Grade 2 Standards in the national Acoustic Environmental Quality Standard (GB3096-2008) are implemented, and the standard values are shown in the following table: Table 3-4 Acoustic Environmental Quality Standard Standard Value (Leq: dB Applicable Area (A)) Basis Daytime Nighttime Mixed residential, commercial Grade 2 Standard in 60 50 and industrial area (GB3096-2008) Class 4a Standard in Both sides of main traffic arteries 70 55 (GB3096-2008)

17 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan 2.5.4 Soil environment quality

Environmental Quality Standard for Soils (GB15618-1995) - secondary standard Table 2-10 Environmental quality standard value for soil (unit: mg/Kg) Index pH Cu Zn Ni Pb Cd Basis

Normal The secondary standard <6.5 400 500 200 500 1.0 value of(GB15618-1995) 2.6 Pollutant Emission Standard

2.6.1 Wastewater Grade III Standard in Integrated Discharge Standard of Wastewater (GB8978-1996) is executed for wastewater. Table 3-5 Wastewater Discharge Standard Pollutant Standard Value (mg/L) Basis pH 6~9 CODcr 500 Grade III Standard in SS 400 (GB8978-1996) Animal and vegetable oil 100 BOD5 300 2.6.2 Waste Gas Grade II Standard in Integrated Emission Standard of Air Pollutants (GB16297-1996) is executed for waste gas. Table 3-6 Integrated Emission Standard of Air Pollutants Maximum Allowable Maximum Allowable Pollutant Emission Concentration Basis Emission Rate(kg/h) (mg/m3) Limits of Grade II SO2 50 4.3 Standard in Particle 120 5.9 (GB16297-1996) (20m-high exhaust NO 240 1.3 2 funnel) 2.6.3Noise Grade 2 Standard in Emission Standard for Environmental Noise at Boundary of Industrial Enterprises (GB12348-2008) is executed. Table 3-7 Emission Standard for Environmental Noise at Boundary of Industrial Enterprises Category Daytime Nighttime Basis Noise limits [Leq: dB (A)] 60 50 Grade 2 in (GB12348-2008) Relevant standards of Noise Limits at Boundary of Construction Site (GBl2523-2011) are executed during construction.

18 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

3.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

3.1 Major Environmental Impacts The project belongs to low pollution type municipal project and has obvious environmental benefit and social benefit, but it will also generate some local environmental problems inevitably during the construction and operation periods. I. Main impact analysis during construction period 1. Ecological environmental impact analysis (1) Impacts on plants during construction period ① Impacts on vegetation deterioration and land productivity The permanent land occupation for project construction will tie up and destroy the vegetation in the project area, and the construction activities will make the vegetation habitat destroyed and make the biological individual lose growing environment; the degree of impact is irreversible. It can be seen from the results of vegetation distribution status investigation, the vegetation affected by the project directly mainly includes shrub and grass. During the project construction process, the temporary construction sites mainly include construction workshop and temporary .silt stock yard. The type of temporary construction sites is dry land, and the temporary land use will have a short-term direct impact on the land and aboveground vegetation. The type of vegetation greatly affected is mainly vegetation. However, the temporary construction sites of the project will set up within the permanent land range, and the temporary occupation of Hongchuan subproject will be used as the green area of river landscape, thus the temporary constriction works of this project will not cause any impacts on the plants. Above all, the destruction on plants during project construction is mainly the permanent land occupation, and it is for a long term and unrecoverable. ② Impacts on ecological structure Human activities during construction period, such as paving of subgrade, excavation of commercial street pile foundation, rolling compaction of construction machineries,

19 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan trampling of constructors and so on, will have direct destructive effect on shrub and grass vegetation around the construction operation area, so as to make the biological diversity of the community reduced. The construction area has the relatively stable agricultural ecological system and shrub-grass ecological system formed in many years. According to the field investigation, within the project impact range, the plants affected by the project are the general and common species, with wide growth range and strong adaptability. The loss of aboveground vegetation will have a certain impact on the existing ecological system, but since the lost area is relatively small to the project area, the project will adopt the approach of vegetation greening and temporary construction land vegetation recovery to make up part of biomass loss. Therefore, the construction activities will not impact the stability and integrity of ecological system within the project area. (2) Impacts on landscape during construction period The impacts of project land occupation on landscape mainly show up as the impacts of project on regional vegetation and geomorphologic landscape. (1) Impacts of permanent project land occupation on landscape The destruction of permanent project land occupation (mainly refers to land occupation of road and water supply projects) on original aboveground vegetation is unrecoverable, so the construction has a significant impact on the vegetation landscape within the project area, which mainly shows up as surface excavation, vegetation destruction, terrain fragmentation of construction operation area, and will product an extreme vision contrast. (2) Impacts of temporary project land occupation on landscape The temporary project land occupation mainly refers to the land occupation of temporary soil heap yard and construction workshop. Because most of the temporary projects are project implementation services, which request for good terrain and traffic conditions, as well as good land and vegetation conditions; but the construction has a large disturbance on the aboveground vegetation and terrain within the operation area, mainly manifested as follows: industrial and domestic wastes polluting the environment, dust emissions polluting the air, too much dirt retention on plant branches and leaves likely to cause burns or mechanical injury and produce visual pollution. But because the

20 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan temporary project land has the soil layer with good fertility, it is easy to be reclaimed and utilized; after the project construction is completed, the temporary construction land area will be carried out the landscape green construction as the landscape project implementation area; therefore, the temporary construction land occupation has little impact on landscape along the line. 2. Atmospheric environmental impact analysis (1) Construction dust ① Pollutant source analysis The raising dust pollution generated by construction vehicles during construction period is relatively serious and the impact range is very large. The raising dust is a kind of falling dust with smaller particle size (10~20μm) and the particle size distribution of dust on the unpaved road surface (soil) is as follows: the dust with particle size less than 5μm accounts for 8%; the dust with particle size of 5~30μm accounts for 24% and that with particle size more than 30μm accounts for 68%. Therefore, the road under construction is easy to cause dust emission, but compared to the dust generated from lime-soil mixing, the harm of raising dust is smaller and its impact cycle is shorter. It is available to adopt the watering measures to reduce the raising dust pollution.

The excavation of earthwork and earth filling during construction period are the main engineering actions that generate the raising dust. The lime-soil mixing during road building process will generate a large amount of dust and it can be divided into two processes according to the mixing modes, namely road mixing and station mixing. Road mixing refers to mix at the construction site; station mixing refers to transport the finished product to the construction section by vehicles after centralized mixing. By contrast, the impact of station mixing is great and wide, and the pollution scope can reach up to 150m down the wind; while the pollution of road mixing is small and narrow, but the polluted line is long. Therefore, during construction period, it is required to select the appropriate lime-soil mixing mode according to the actual situations, to reduce TSP pollution. ② Control measures of raising dust pollution

21 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

1) When the wind speed is above Category-4 and it is easy to produce raising dust, it is suggested that the construction unit shall suspend the earth excavation and take the effective measures such as covering the windrow and wetting, to reduce the raising dust pollution; 2) The construction wastes shall be cleaned and transported in a timely manner and the wastes cannot be cleaned and transported temporarily shall be taken the measures such as covering; the vehicles for transporting the substances that are easy to produce dust, such as sand, stone, cement and earthwork, shall be covered tightly and it is strictly prohibited to sprinkle and leak. 3) After the project is completed, it is required to clean the construction site timely. For the construction site, except cleaning in a timely manner, it is also necessary to afforest or revert to cultivated land, to plant the crops. 4) It is required to select the lime-soil mixing mode reasonably according to the actual situations and water to reduce the raising dust pollution.

5) During the excavation, drilling and demolition processes, it is required to water to keep certain humidity for the operation: for the loose and dry surface soil in the construction site, it is also necessary to water to control the dust; when backfilling the earthwork, it is necessary to water appropriately if the surface layer soil is dry, to prevent dust flying.

6) It is required to strengthen the management of backfilling earthwork storage yard, to develop the earthwork surface compaction, regular water spraying and covering measures; the undesired soil and waste slag of building materials shall be carried away timely and shall not be stored for a long time. 7) The earth-moving trucks and building materials transport vehicles shall be equipped with the anti-spill devices according to the regulations and the loading shall not be too full, to guarantee that there is no scattering during transportation process; and the running route and time of transport vehicles shall be planned well, to avoid driving within

22 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan the sensitive areas such as downtown area, traffic concentration area and residential area as far as possible. 8) The transport vehicles shall be canopied and shall be washed out before doing out from the loading and unloading sites, to reduce the carried soil of vehicle wheels and chassis scattered on the road surface. 9) The soil scattered on the road surface during transportation process shall be swept out timely, to reduce the raising dust during running process. 10) During construction process, it is strictly prohibited to burn the waste building materials as the fuels. (2) Construction waste gas The waste gas during construction period of this project mainly comes from the oil-fired waste gas generated by construction machineries and transport vehicles; its quantity generated is small and it belongs to discontinuous and dispersive emission, so its impact cannot be considered basically. (3) Asphalt fume During the pavement construction stage of the proposed road for the subproject in Liujiang Town, the asphalt fume is mainly caused in the course of asphalt fission refining, stirring and road paving, and the asphalt fume discharge in the course of asphalt refining is largest. The main poisonous and harmful substances in the asphalt fume are THC, phenol and 3.4-benzopyrene. The impact range of asphalt fume pollution is 100m down the wind. The asphalts required for the project are commercial asphalts purchased at local and no asphalt mixing station is set up. For the requirements of environmental impact assessment, it must be loaded and transported by canned asphalt dedicated vehicles, to avoid sprinkling along the way and polluting the environment. Therefore, the emission concentration of asphalt fume is low and can meet the maximum acceptable emission concentration of asphalt fume in the Integrated Emission Standard of Air Pollutants (GB16297-1996), so it has little impact on the surrounding environment. (4) Silt foul smell The silt from desilting works during construction period of Hongya Town subproject will be stored temporarily, and the temporary storage of silt is likely to

23 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan produce foul smell and have impact on regional ambient air quality. So the requirements of this assessment are as follows: the temporarily stored silt shall be allocated and transported as soon as possible after treatment and the construction party shall spray the disinfectant and vegetation liquor for the temporary silt storage yard every day, to reduce the pollution impact of foul smell. In addition, the temporary silt storage yard shall select the zone far away from the residential areas, to avoid impact of foul smell on residents. 3. Environmental impact analysis of surface water (1) Impact of construction waste water Waste water in construction period of the Project is mainly from construction waste water and sanitary sewage. Among the waste water, construction waste water, which contains a certain amount of sediment, is from construction machinery cooling water and washing water, construction site cleaning, construction material cleaning, concrete pouring, maintenance, flushing, etc; sewage from construction workers mainly contains organic pollutant, ammonia nitrogen, SS, etc. Besides, surface runoff water on the construction site during raining season contains a certain amount of soil and suspended substances in high concentration. 1) Sanitary sewage and treatment measures As there are 100 persons, including construction workers and site management personnel, during the peak of construction period, water consumption rate would be 5m3/d on the basis of 50L/person •d, while sanitary sewage yield would be 4m 3/d on the basis of sanitary sewage rate of 0.8. Sanitary sewage during construction period of the Project can be treated by renting treatment facility in the local house. Therefore, sanitary sewage during construction period would not have obvious impact on local environment. 2) Construction waste water and treatment measure The main pollutant of construction waste water and surface runoff water in raining season is sediment; the concentration of suspended substances is comparatively high, and the pH value indicates alkalescency; the suspended substances would be separated by building sedimentation pool; the waste water would not be discharged but recycled after sedimentation treatment; the

24 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan sedimentation sludge would be regularly cleaned out, then transported to construction waste disposal site and buried. (2) Impact of construction method ① Hongchuan Town – River Regulation Works The impact of river regulation works of the Project on water environment is mainly from dredging waterway and river bank construction. Dredging waterway of moat in Hongchuan Town will cause turbulence in the water; as a result, it will cause suspended substances and influence water quality of water body. However, because the Project adopts dredging waterway section by section and the construction time is relatively short, the impact will be temporary and fade away as the works is finished. Moreover, cofferdam construction technology will be used in dredging works, all the construction processes will be preceded inside cofferdam except that building cofferdam will cause disturbance to the river bed; thus, the construction processes are basically separated from the water body. Besides, the function of water body of waterway is flood discharge and irrigation, so construction works would have little impact on water quality of water body. The river bank construction works will be built section by section; construction materials will be piled away from waterway; separated board will be built between riverside and waterway in section under construction to prevent impact on water quality and function of water body caused by slipping materials. Therefore, after the above measures have been taken, the methods of dredging waterway and river bank construction are rational, which won’t change function of body of moat in Hongchuan Town and have little impact on water environment. ② Liujiang Town – Bridge Construction There is no water contact pier in bridge construction of the Project, so no water contact construction involves in the whole bridge pier construction. Bridge piers of this construction adopt pile foundation, where drill construction will be employed for pile foundation of bridge piers. Since bearing platform and body of pier will be built through cast in place, certain of suspended substances may be brought in surface water body when the raining water flushes. But such impact is comparatively temporary. The assessment recommends avoiding bridge pier construction in rainy

25 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan days as far as possible to reduce suspended substances in surface water caused by raining water flushing. Moreover, the upper structure of main bridge will be installed by hoisting precast concrete unit, and the construction of upper structure of main bridge in the Project will cause no pollution to water environment. The upper structure of the approach bridge will introduce precast concrete unit, so that construction will have little impact on water body. 4.Environmental impact analysis of noise ① Noise source Noise in construction period mainly points to noise generated by various construction machines, equipments and construction transportation vehicles during operation. Construction of the Project needs various types of machine. According to the survey, frequently used machines at present mainly include excavator, loader, agitator, etc. The value of noises generated by various types of construction equipment during operation is showed in Table 3-1. Table 3-1 Intensity Sheet of Construction Equipment Noise Source Characteristics of noise Noise value in 5m distance S/N Type of machine source to noise source 1 Loader Unstable source 90 2 Compactor Moving and unstable source 90 3 Vibratory road roller Moving and unstable source 86 4 Birotary turbine Moving and unstable source 81 5 Tri-wheel road roller Moving and unstable source 81 6 Pneumatic tire roller Moving and unstable source 76 7 Bulldozer Moving and unstable source 86 Tire hydraulic 8 Unstable source 84 excavator 9 Paver Moving and unstable source 87 10 Truck Moving and unstable source 92 Fixed source in construction 11 Concrete blender 91 site Fixed source in construction 12 Concrete pump 85 site ② Impact estimation of noise during construction period Construction noise source can be deemed as point acoustic source. Based on noise attenuation mode of point acoustic source, noise value during construction period in different distance to noise source can be estimated. Estimation mode as followed:

26 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Lp = Lpo - 20lg(r/r0) - ΔL In the formula: Lp – sound pressure level in r (m) distance to noise source, in dB (A); Lpo - sound pressure level in r0 (m) distance to noise source, in dB (A); r – distance to noise source, in m; r0 – 1m distance to noise source; ΔL – different decrement (except for divergence attenuation), in dB (A). ΔL of outdoor noise is deemed as 0. According to the estimation formula, noise value in different distance to noise source during various types of construction machines in full operation is calculated. The results are showed in Table 3-2.

Table 3-2 Estimated noise value in different distance to various types of construction machines Noise value in different distance, in dB (A) S/N Type of machine 5 40 50 60 100 150 200 300 500 1 Wheel loader 90 71.94 70 68.42 63.98 60.46 57.96 54.44 50 2 Compactor 90 71.94 70 68.42 63.98 60.46 57.96 54.44 50 3 Vibratory road roller 86 67.94 66 64.42 59.98 56.46 53.96 50.44 46 4 Birotary turbine 81 62.94 61 59.42 54.98 51.46 48.96 45.44 41 5 Tri-wheel road roller 81 62.94 61 59.42 54.98 51.46 48.96 45.44 41 6 Pneumatic tire roller 76 57.94 56 54.42 49.98 46.46 43.96 40.44 36 7 Bulldozer 86 67.94 66 64.42 59.98 56.46 53.96 50.44 46 Tire hydraulic 8 84 65.94 64 62.42 57.98 54.46 51.96 48.44 44 excavator 9 Paver 87 68.94 67 65.42 60.98 57.46 54.96 51.44 47 10 Concrete blender 91 72.94 71 69.42 64.98 61.46 58.96 55.44 51 11 Concrete pump 85 66.94 65 63.42 58.98 55.46 52.96 49.44 45

27 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

(1) Noise from single construction machine in daytime conforms to standard limited value in 30m distance at most to source, while in 300m distance at most in nighttime.

(2) Noise from multiple construction machines in daytime conforms to standard limited value in 60m distance at most to source, while in 350m distance at most in nighttime.

(3) Environmental protection targets within assessment area of proposal project are mainly 6 residential areas, 1 nursing homes and 1 health center. Construction in daytime will cause interruption to residents and patients, especially the noise impact in nighttime will be much greater. The significant factors to be considered during construction period are noise pollution to the residents within 60m distance to construction area and protection management measures. Therefore, the assessment considers that certain protection measures should be taken to reduce impact on sensitive spots around construction area during construction period, for example, using wooden acoustic board and building construction wall to insulate noise. Requirements of assessment: construction in nighttime is prohibited; construction block fence must be strictly set in construction section around sensitive spots to insulate noise effectively.

5. Impact analysis of solid waste Solid waste during construction period mainly involves two parts. One part is garbage from construction area, including waste construction materials, package materials, household garbage, which mainly contain waste plastics, sand and soil, vegetable leaves, vegetable stems, glass, etc. Such solid waste usually exists around structures like storage yard and construction site. The other part is sludge from dredging waterway works in Hongchuan Town. Such solid waste usually exists in temporary storage yard. According to the result of sludge survey, all specifications of bottom soil meets the requirements of Secondary Standard stipulated in Soil Environment Quality Standard (GB15618-1995) and no metal content exceeds the standard. Thus, a part of drained sludge would be used to repave in wet land of project area for planting and landscape modeling; the rest will be packed in woven bags and transported to Hongya

28 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan County by airtight vehicles for landscape planting of municipal road construction. If solid waste is stored or treated in an inappropriate way, it will directly affect crops and vegetation, and interfere with agricultural production; if solid waste is covered with dust after long-term storage, the raised dust blown by the wind will cause impact on nearby residents. Garbage placing along the construction area will help mass propagation of germs, mosquitoes and flies, causing potential risk of local contagion diseases happening and spreading. Stink smell from garbage will affect residents’ life and landscape environment. Since the Project involves in construction along the river, assessment requires: solid waste during construction period should not be stored in places contacting water body, not mention abandoning in the river. Therefore, during construction period, such impact could be reduced or prevented through enhancing construction management and timely cleaning, transferring and disposal after construction is completed. Meanwhile, inappropriate transfer method for solid waste during construction period will also cause negative impact on surrounding environment. Requirements of assessment: in transferring construction garbage, vehicles must be capped with dust screen to prevent spattering and raise dust during the trip and flushed when they are driven out of waste loading site. When the vehicles arrive at the unloading site, the waste must be emptied. Construction units should carefully study transportation route for waste soil and waste slag with traffic authorities and environmental protection authorities to bypass environmental sensitive spots like mass residential area. The transfer should be done in nighttime as much as possible. Solid waste during construction period would cause little impact on surrounding environment as above measures are taken. Ⅱ. Main impact analysis during operation period 1.Environmental impact analysis of atmosphere After the implementation of the Project, raise dust pollution along the road and bridge will be reduced. But during operation period, raise dust caused by running vehicles and exhaust will still cause certain air pollution. The main pollutant includes CO, NOX and PM10. The amount of pollutant discharged will increase proportionately along with traffic volume and involve with type and condition of

29 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan vehicles. As traffic volume increases, the impact of pollutant NO 2 of vehicle emission will grow. Compared with similar roads, the estimated average daily concentration value of NO2 or PM10 at a distance of 20m away from the road centerline could meet requirements of secondary standard value of Environmental Air Quality Standard under the circumstance of maximum forward traffic volume in the Project. Treatment measures for road and bridge works of Liujiang subproject to reduce air pollution are recommended as follow: 1. Enhance greening measures and specifically optimize greening tree species, greening structure and layer to improve control effect and reduce impact of gaseous pollutant on surrounding environment. 2. Enhance traffic administration and stipulate speed range to reduce accident. 3. Water regularly and clean to reduce raise dust. 4. Restrain vehicle speed and strictly carry out pursuant to stipulated speed of the Project. 5. Strictly prohibit dangerous chemicals transportation vehicle pass through. Besides, main waste gas source during operation period of newly built eco-parking site of Liujiang subproject is vehicle emission from surface parking lot.

Main pollutant of automobile emission includes CO, NO2 and HC. Emission volume is related to quantity and parking frequency of vehicles. The surface parking lot of eco-parking site has open topography that helps vehicle emission spread, along with large portion of greening in eco-parking site making vehicle emission have little impact on environment. 2. Environmental impact analysis of surface water (1) Road and bridge works Waste water during operation period of proposed road of Liujiang subproject is mainly from rainfall, surface runoff caused by road surface flushing. After road and bridge enter into operation, impact of surface rainfall runoff, as major pollutant, on water environment mainly reflects on vehicle emission, tire friction particles, raise dust on the surface and oil drops flowing into or crossing river along with surface rainfall to pollute water body. The concentration of surface runoff pollutant depends on multiple factors,

30 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan such as rainfall capacity and rainfall duration, traffic volume and atmosphere pollution degree, interval between tow rainfall, width of road, etc. Such factors are with the characteristics of high randomness and chance, thus it is hard to summarize general rule or recognized assessing method for calculating rainfall runoff pollutant concentration. Based on the statistic of domestic study data and assessment data, pollution to water body by surface runoff usually occurs in the beginning of rainfall; as rainfall time prolongs, concentration of pollutant in runoff will decrease. As a result, pollution to water body will reduce, and no obvious impact will fall on water body. Besides, the wastewater collected in the new sewage pipe network of the Project in Hongchuan Town can be discharged into the sewage treatment plant of Hongya County. The sewage treatment plant abovementioned is with the Phase I capacity of 10,000m3/d and Phase II design capacity of 20,000m3/d, which is located at the closing dam at northern side of Qingyi River. In the Project, a d800 reinforced concrete sewage intercepting main is laid along the closing dam corners at the northern side, by which the sewage collected is discharged into the sewage treatment plant for treatment and up-to-standard discharge. (2) Water supply project Production waste water during operation period of newly built water treatment plant of Liujiang subproject is mainly from sludge water in sediment pool and back flushing waste water in filter pool. Back flushing water will not be drained, but recycled through recycle pool; sludge water will be drained to nearby flood discharging channel as upper clear liquid meets requirements of discharge standard after treatment through sludge concentration pool. After the Project enters into operation, labour capacity needs 11 employees to implement three shifts in duty among four shifts. There is no canteen in plant area, so just a little sanitary sewage is generated from office area. Daily sewage from life and office is 1.1m 3/d, which would be transported by tank truck to local sewage treatment plant for treatment and drained. After above measurements are taken, water supply project of Liujiang subproject will not have obvious impact on regional surface water environment. 3. Analysis of Impact on Acoustic environment

31 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan ①Road works of Liujiangzi Project (1) Reasonable planning and layout of buildings and control of land along road sides Based on the spirit of “the Urban Planning Department shall determine the layout of buildings in compliance with national standards for acoustic environment quality and design specifications for civil buildings, reasonably specify the distance between buildings and the traffic artery to prevent noise, and propose corresponding planning and design requirements” as stated in Clause XI, Chapter II of Law of the People’s Republic of China on Prevention and Control of Pollution from Environmental Noise, the land on both sides of the road shall be properly planned and the use of the land along the route shall be strictly controlled. In principle, new construction or extension of school, hospital, residential buildings or other sensitive buildings is not allowed within the noise defending distance. On the basis of proper functional planning of the land along road sides, it is recommended that building layout and sound insulation design be designed to ensure the indoor environment of sensitive buildings can meet the requirements of using functions. According to the overall planning of Liujiang Town, construction around roadways of the Project mainly involves business areas and a small number of commercial and residential quarters. So requirements are proposed through assessment that influence of traffic noise on residents should be minimized after construction of shopping mall, dinning places and other commercial buildings along road sides. Meanwhile, the layout of environmentally sensitive buildings shall be optimized, with the noise-sensitive functional zone to be located far away from the road. Therefore, according to noise prediction of this environmental assessment, it is recommended that school, hospital, nursing home, residential quarter or other sensitive buildings not be constructed within 20m from both sides of the road axis. Any environmental sensitive site in the above-mentioned area must be provided with noise reduction measures during construction and can only be put into use after being approved by an environmental authority and reaching the corresponding functional standards. (2) Noise pollution control measures All the predicated noise values of in both day and night at 3 sensitive points of the Project in short, medium and long-term operation (up to 2016, 2023 and 2030

32 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan respectively) fall within Class II standard limits as stated in Environmental Quality Standard for Noise. Therefore, the following management requirements are proposed through environmental assessment that traffic control be strengthened after the road is built and put into operation to avoid excessive noise caused by traffic jam and vehicle noise monitoring be enhanced to prevent vehicles making excessive noise or speeding. ②Water supply (water purification plant) works of Liujiangzi Project After the water purification plant for water supply works of Liujiangzi Project is put into operation, the noise mainly comes from pumping house, pump equipment and blower. See Table 3-3 below for noise generation and control. Table 3-3 Noise generation and control Sound pressure Equipment Operating Sound pressure Control measures level after control, name conditions level, dB (A) dB (A) Reasonable layout, Water pump Continuous 85 sound-proof doors and ≤70 windows Reasonable layout, Blower Continuous 80 ≤65 vibration mitigation According to predication, equipment noise values at the plant boundary during operation of the water purification plant fall within Class II standard limits as stated in Standards of Noise at Boundary of Industrial Enterprises (GB12348-2008). The predicted values at sensitive points of the Project are 51.2dB (A) in daytime and 43.4dB (A) at night, falling within the Class II standard limits as stated in Environmental Quality Standard for Noise (GB3096-2008). That is to say this Project has little influence on environmental sensitive sites. 4. Impact Analysis of Solid Wastes During the operation period of road and bridge works of the Project, solid wastes mainly refer to domestic garbage of management and maintenance personnel with a point shape distribution, which has little impact on environment compared with that during the construction period. As the solid wastes are generated near the road during the operation period, they may affect the landscape, pollute the air, spread disease and harm human health if not properly disposed. During the operation period of the Project, domestic garbage shall be collected, dumped, disposed and transported in such a manner as not to affect environmental health. Solid wastes generated during the operation period of road

33 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan and bridge works of the Project shall be collected and transported to the local garbage disposal area by the sanitation department. Solid wastes from the production area of the water purification plant include dry sludge, office garbage and domestic garbage. The output of dry sludge from the Project is approximately 1.4t/d. There are 11 production workers in the plant with office garbage of 5.5kg/d (0.5kg/d per capita). Disposal measures: Dry sludge will be transported to the landfill; office and domestic garbage will be collected and sent to the local sanitation department for disposal.

34 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

3.2 Mitigation Measures

Summary of Impacts and Mitigation Measures (Hongchuan Town)

Stage Field Impacts Mitigation Measures Comments A small quantity of domestic sewage generated by working personnel Wastewater during construction will be generated at the discharged after being treated in the Impact is construction site existing environment sanitation minor. and the workers’ facilities nearby; wastewater Water domestic sewage generated during mixing of sand gravel materials will be recycled after sedimentation. Impact is Impacts during Excavation in the sludge is prohibited minor. raining season in raining season.

Construction dust generated during earth rock excavation, transportation Construction and Impact is and concrete mixing will be Air transportation dust minor. eliminated by watering and residues

remaining on the road surface will be cleared away in time. During Equipment with high noise will be construction arranged in a proper manner and provided with fencing during Construction construction to make noise at the equipments and Impact is boundary fall within the standard Noise transportation minor. limits. Construction is forbidden vehicle from 22:00 p.m. to 6:00 a.m.;

equipment with low noise will be used and maintenance of construction machineries will be strengthened. Domestic garbage generated by Solid waste construction personnel of the Project Impact is generated at the will be collected and sent to the minor. construction site garbage disposal area at regular intervals. Solid waste Lots of spoil in Earth and stone will be allocated Impact is initial period of and transported within the plant area, minor. construction no waste to be generated. Mud will be used for earthing in Impact is River mud landscape engineering after minor. temporary pile-up and dewatering.

35 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Summary of Impacts and Mitigation Measures (Hongchuan Town)

Stage Field Impacts Mitigation Measures Comments Without new occupation of land, the Impact is Removal of trees by project construction has little impact minor. construction on vegetation. Ecology Permanent or temporary occupation Impact is Soil erosion of land during construction may minor. cause local water and soil loss. Compensation will be made Impact is During Land acquisition according to the scheme for minor. construction and resettlement resettlement of affected residents. Social Existing roads will mainly be used Impact is Traffic impacts during the construction to provide minor. access for project personnel. Construction Environmental activities going N/A / risk across rivers and railways During Impact is Ecology Greening impacts N/A operation positive.

Summary of Impacts and Mitigation Measures (Liujiang Town)

Stage Field Impacts Mitigation Measures Comments Road and pipeline works are constructed according to the planning Impact is Line selection of the cities or towns where they are minor. Project located. There is no line comparison location and selection. Environmental The site of the water supply plant is impacts selected based on the planning of related to the Liujiang No. 2 Water Plant, and Impact is construction Site selection relevant comparison and selection minor. site scheme shall be proposed. Crop Before compensation is used as a mitigation construction measure for land acquisition. Other alternative analysis Pipeline routing The water supply network will be laid Selection of Impact is Layout scheme for along the road and constructed by other minor. water distribution section to sustain water demand of programs with network the residents. a greater impact on the environment

36 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Summary of Impacts and Mitigation Measures (Liujiang Town)

Stage Field Impacts Mitigation Measures Comments

A small quantity of domestic sewage Wastewater generated by working personnel during generated at the construction will be discharged after being Impact is construction site treated in the existing environment sanitation minor. and the workers’ facilities nearby; wastewater generated during Water domestic sewage mixing of sand gravel materials will be recycled after sedimentation. Excavation construction in raining season will Impact is Impacts during be avoided to the greatest extent and, if any, minor. raining season provided with shielding. Construction dust generated during earth rock excavation, transportation and concrete Construction and Impact is mixing will be eliminated by watering and Air transportation dust minor. residues remaining on the road surface will be

cleared away in time. Mixed asphalt will be purchased and used for road paving. Equipment with high noise will be arranged in a proper manner and provided with fencing during construction to make noise at the boundary fall within the standard limits. Construction is forbidden from 22:00 p.m. to During 6:00 a.m.; equipment with low noise will be Construction construction used and maintenance of construction equipments and Impact is machineries will be strengthened. Noise transportation minor. If any sensitive point such as nursing home vehicle and health center is involved in the newly

constructed road section, a temporary noise barrier will be set according to the environmental assessment to reduce influence of construction noise; influence of construction noise on school teaching will be avoided. Domestic garbage generated by Impact is SW from construction personnel of the Project will be minor. construction site collected and sent to the garbage disposal area Solid at regular intervals. waste Earth and stone will be allocated and Impact is Spoiled soil transported within the plant area, no waste to minor. be generated. Without new occupation of land, and Impact is Removal of trees occupying a small occupation area, the project minor. by construction construction has little impact on vegetation. Ecology Permanent or temporary occupation of land Impact is Soil erosion during construction may cause local water and minor. soil loss.

37 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

4.0 ORGANIZATION FOR EMP IMPLEMENTATION

4.1 Environmental Management And Monitoring Organization

4.1.1 Management requirements for Contractor The Contractor and the construction organization play a key role in environmental management, implementation of pollution control and prevention measures, etc. during construction. So the following requirements are proposed for the Contractor: (1) The Contractor must have relevant strength and financial capacity to ensure effective EMP implementation; (2) Environmental impact mitigation measures during the construction period shall be included in the Contractor’s tender documents and the construction contract as well as a part of contract requirements for the Contractor. (3) The Contractor shall assign 1 full-time environmental worker to make monitoring record of environmental activities during construction and submit environmental records to the Owner and the environmental protection and supervisory organization weekly or as required for supervision and review. (4) The contractor together with the assigned environmental worker and the construction supervisor must receive training on environmental protection and management before commencement of construction work so as to be competent for their jobs. (5) During construction, the Contractor shall keep communication and consultation with people in the region where the Project is located, with a bulletin board set at each construction site to inform the public of the specific construction activities and time. In addition, a contact person and his telephone number shall be provided to receive the public’s complaints and suggestions on construction activities.

4.1.2Environmental management organization The environmental management organization mainly consists of two levels, i.e.

38 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

Hongya County Housing and Urban-Rural Construction Bureau and Sichuan Urban Environment Project Office (hereinafter referred to as PMO). (1) Hongya County Housing and Urban-Rural Construction Bureau, the Owner of the Project, will assign a full-time worker to be responsible for the environmental protection and management of the Project. Besides, the Owner will assign a full or part-time worker to take charge of a supervision and complaint hotline for the Project. (2) PMO is a coordination agency for preparation and implementation of the Project. During the entire project implementation, SUEPO will assign a special person to be responsible for environmental management of the Project, supervise EMP implementation and provide necessary monitoring report to the World Bank and relevant national sectors.

4.1.3Environmental management responsibility 1. Construction period Environmental management personnel shall develop a detailed EMP according to the construction plan of the Project, conduct monthly inspection in reference to the EMP and make necessary revisions. Environmental management personnel shall also carry out perambulation inspection of implementation of environmental protection measures according to the plan, ensure the monitoring work to be conducted at a fixed time and location as per the plan, report inspection and monitoring results, on-site treatment suggestions as well as environmental management inspection results to the project leader on a monthly basis, and propose solutions specific to potential problems found during inspection. Working personnel in charge of the hotline shall record and handle complaints over the phone and report solutions to the environmental management personnel as well as to the public. 2. Operation period (1) Propagandizing national polices, laws and regulations related to environmental protection and organizing their implementation; (2) Implementing various environmental management systems developed by the superior competent department; (3) Putting into practice environmental protection measures for the operation period

39 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan as stated in the environmental assessment report and the EMP; (4) Directing and organizing environmental monitoring during the operation period and establishing monitoring files; (5) Entrusting Hongya County Environmental Protection Bureau to record and register the quantity and quality of wastewater from all pollutant discharging units to the sewage pipe network of this Project and monitor the running conditions of their wastewater pretreatment facilities, or directly transferring such work to Hongya County Environmental Protection Bureau, according to coordination among various functional departments of the local government; (6) Reporting environmental monitoring and management inspection results to the PMO as required on a yearly basis and proposing solutions specific to potential problems found during inspection.

4.1.4Supervision organization and responsibilities The environmental supervision organization of this Project is mainly composed of the World Bank delegation, Sichuan Urban Environment Project Office (hereinafter referred to as PMO), Sichuan Environmental Protection Department, Meishan Municipal Environmental Protection Bureau, Hongya County Environmental Protection Bureau and Hongya County Housing and Urban-Rural Construction Bureau.

4.1.5Monitoring organization and responsibilities Hongya County Environmental Monitoring Station is responsible for quality monitoring of water, air and acoustic environment. Responsible departments for environmental management during the construction/operation period Project Construction Environment Compliance Level Management Supervision Management Monitoring During Construction Sichuan Sichuan Environmental Environmental Provincial Protection Department Protection Department Hongya County Entrusting Southwest Housing and Hongya County Hongya County Jiaotong University and Local Urban-Rural Environmental Environmental other external related Construction Protection Bureau Monitoring Station entities Bureau

40 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

Project Construction Environment Compliance Level Management Supervision Management Monitoring During Operation Sichuan SUEPMO Environmental Hongya County Protection Hongya County Housing and / Department Environmental Urban-Rural Hongya County Monitoring Station Construction Environmental Bureau Protection Bureau 4.2 Training and Capability Building Objects of the environmental protection training for this Project include executive and technical staff from PMO, the Owner, the construction organization, the supervision organization, etc. The Owner is responsible for organizing a training class with duration of 2 – 3 days for Hongya County Component of Sichuan Small Towns Development Project by World Bank Loans after the determination of the construction and supervision units for this Project and before the commencement of construction. The training may be located in colleges, universities or scientific research institutes of Hongya County, Meishan City or City. At least one technical manager and one environmental manager from the Owner, the construction unit and the supervision unit are required to participate in the training. The training content includes: (1) National and provincial laws and regulations, documents and relevant requirements on environmental protection, water and soil conservation, etc. in construction project management; (2) Environmental protection measures proposed in the project design and environmental protection requirements during the construction/operation period; (3) Environmental protection guidelines for the construction/operation period of this Project. Any responsible person for environmental protection design from Sichuan Environmental Protection Department, Meishan Environmental Protection Bureau and China Railway Eryuan Engineering Group Co., Ltd. or relevant expert from the environmental assessment unit may be selected as the instructor of the training class.

41 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

5.0 MONITORING PROGRAM

5.1 Monitoring Program 5.1.1 Monitoring during Construction Monitoring Program during Construction (Hongchuan Town) Projec Environment Monitoring Monitoring Monitoring Applicable Monitorin t al Element Location Item Frequency Standard g Institute Name Construction Monitoring site and 3 twice, each time Class II Air sensitive PM10 for 3 day; standard of points along sampling during GB3095-2012 the line construction Monitoring 3 sensitive monthly, each Standard of Noise points along LAeq time for 1 day GB12523-201 the line (once both day 1 and night) River Cross pH, COD, works Monitoring sections at ammonia twice, each time Class III the starting nitrogen, Surface water for 2 days; standard of and finishing BOD , 5 sampling during GB3838-2002 points of suspended construction Hongya river works solids County Monitoring once The Class III Environm and sampling Sediment finishing standard of ental once at the end of point of river GB15618-199 Monitorin the construction works 5 g Station period

Monitoring twice, each for 3 Class II Construction Air PM day; sampling standard of site 10 during GB3095-2012 construction Monitoring Pipeli monthly, each Standard of Construction ne Noise L time for 1 day GB12523-201 site Aeq works (once both day 1 and night) pH, COD, Monitoring Construction ammonia twice, each time Class III Ground water site, nitrogen, for 2 days; standard of residential BOD , sampling during GB14848-93 area nearby 5 chloride construction

42 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan Monitoring Program during (Liujiang Town) Projec Environment Monitoring Monitoring Monitoring Applicable Monitorin t al Element Location Item Frequency Standard g Institute Name Monitoring Construction twice, each for site and 4 3 day; Class II standard Air sensitive PM 10 sampling of GB3095-2012 points along during the line construction Monitoring Road 4 sensitive monthly, each Standard of and Noise points along L time for 1 day Aeq GB12523-2011 bridge the line (once both day works and night) 200m pH, COD, Monitoring downstream ammonia twice, each from the nitrogen, time for 2 days; Class III standard Surface water bridges over BOD , sampling of GB3838-2002 Huaxi River 5 suspended during and Yangliu solids construction River Monitoring Construction once for 3 site of water Class II standard Air PM days; sampling purification 10 of GB3095-2012 Hongya during plant County construction Environme Monitoring Construction ntal Water monthly, each site of water Standard of Monitorin supply Noise L time for 1 day purification Aeq GB12523-2011 g Station works (once both day plant and night) pH, COD, Monitoring Construction ammonia once for 2 Ground water site of water Class III standard nitrogen, days; sampling purification of GB14848-93 BOD , during plant 5 chloride construction Monitoring once for 3 Construction Class II standard Air PM days; sampling City site 10 of GB3095-2012 during Rain construction Garde Monitoring n monthly, each works Construction Standard of Noise L time for 1 day site Aeq GB12523-2011 (once both day and night) Ecolog Monitoring ical once for 3 Construction Class II standard parkin Air PM days; sampling site 10 of GB3095-2012 g lot during works construction

43 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

Construction site and Monitoring residential monthly, each Standard of Noise area of L time for 1 day Aeq GB12523-2011 Shuanghe (once both day Village and night) nearby

5.1.2 Monitoring during Operation Monitoring Program during Operation (Liujiang Town) Projec Environment Monitoring Monitorin Monitoring Applicable Monitorin t al Element Location g Item Frequency Standard g Institute Name 4 sensitive Monitoring Class II NO2, Air points along yearly, each time standard of PM10, CO Road the line for 3 days GB3095-2012 and Monitoring twice bridge 2 sensitive every year, each Acoustic Standard of works points along L time for 1 day environment Aeq GB12523-2011 the line (once both day and night) Hongya Water Monitoring Class II NO2, PM10, County Air purification yearly, each time standard of Environm plant site CO GB3095-2012 Water for 3 days ental supply Monitoring twice Monitorin Water every year, each g Station works Acoustic Standard of purification L time for 1 day environment Aeq GB12523-2011 plant site (once both day and night) Monitoring twice Ecolo every year, each gical Acoustic Parking lot Standard of parkin environment site LAeq time for 1 day GB3096-2009 g lot (once both day and night) 5.2 Management System 5.2.1 Records For effective operation of the environmental management system, the Owner must organize and establish a complete recording system to keep records of the following items: (1) Requirements of laws and regulations; (2) Relevant review and approval of the Project; (3) Environmental factors and relevant environmental impact; (4) Training;

44 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan (5) Inspection, review and maintenance activities; (6) Monitoring data; (7) Problems found in environmental management and protection; (8) Effectiveness of mitigation measures; (9) Information related to the Project. In addition, various records mentioned above shall also be subject to necessary control, including identification, collection, cataloguing, archiving, storage, management, maintenance, inquiry, expiry and disposal.

5.2.2 Reports During project implementation, PMO, the Owner, the Contractor and the supervision unit shall record the project progress, EMP implementation, environmental quality monitoring results, etc. and report timely to relevant departments. Specifically, (1) The supervision unit and the Contractor shall record the EMP implementation in details and report to the Owner and PMO; (2) PMO must complete and submit the project progress reports (e.g. semiyearly rep ort and yearly report etc.) as required by World Bank. The reports shall include the follo wing contents: 1) Implementation of environmental protection measures, environmental management and training plan as stated in EMP; 2) The project progress, including the length of completed road, the length of installed pipe network of water drainage works, etc. 3) Records of public complaints, if any, including main content, solution and public satisfaction index; 4) EMP implementation plan for the next year.

45 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

6.0 PUBLIC CONSULTATION

6.1 Public Consultation Public consultation has been widely carried out during the preparation of EIA, so the public concerns have been reflected in the EIA/Environmental Management Plan. In order to minimize the impact of the Project, exchange with the project affected people (PAP) will be conducted throughout the Project. The purpose of such exchange is to provide a two-way information channel, where the information of project progress and implementation of the Environmental Management Plan can be publicized to the affected people, and their feedback on the impact of the Project under construction can be conveyed to the Contractor and the Owner in a timely manner. Public consultation and complaint mechanism is a two-way exchange between the Project Owner and the public, serving as an important mechanism for reducing the project risks and social impact, and an important way for publication of the project information and public consultation. A transparent and simple public consultation and complaint mechanism is established to objectively, justly and efficiently deal with the problems of the public, so as to ensure the smooth progress of the Project. Public visit and opinion survey is an important way to communicate with the surrounding people during the construction of the Project; the survey objects are mainly the surrounding people affected by the Project. Public visit and opinion survey for the surrounding people affected by the Project shall be carried out 1-2 months before the completion of the Project to know whether the Project causes environmental impacts to them during construction.

46 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan 6.2 The Specific Ways of Public Consultation Methods used Project Organized Key No. for public Date Location Comments Name by participants consultation

According to the Project investigation, Hongchua owner, 100% of the n Town Questionnaire , EIA respondents consultants Affected and Site publication people within Apr. support the project 1 Owner, Liujiang Conversazione the project 2015 construction. This environmen area Town, tal shows an absolute Hongya assessment local support to the unit County project construction. Hongya County During project Compon implementation, a public consultation ent of Hongchua and complaint Sichuan Jun, n Town 2015 Affected point will be set up Small public Project – and people within in Hongchuan 2 consultation owner, proje Towns the project Liujiang and complaint ct Town and Liujiang Develop area Town, comp Town respectively ment Hongya letion to receive public County Project consultation and by complaints on a World regular basis. Bank Interview and Loans 1–2 mont investigation of hs Hongchua nearby residents Project befor n Town will be made 1–2 owner,, e Affected external comp and months before Interview and people within 3 environmen letion investigation the project Liujiang completion of tal of area Town, project monitoring proje unit ct Hongya construction to see const County if construction has ructio impact on n environment.

47 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan 6.3 Information Disclosure Name of Project Project Name Date Location (Website or newspaper name) Documents

First Disclosure of Hongya County Official website of Hongya County Component of Sichuan Mar. 16, Government: Hongya County 2015 Small Towns http://www.schy.gov.cn/ Component of Development Project By Sichuan Small World Bank Loans Towns Second Disclosure of Development Hongya County Project By World Official website of Hongya County Component of Sichuan Bank Loans Apr. 4, Government: 2015 Small Towns http://www.schy.gov.cn/ Development Project By World Bank Loans

48 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

7.0 INVESTMENT ESTIMATION

A budget has been made for Environmental Management Plan during construction a nd operation, refer to Table 7-1 for details. Total budget of environmental investment incl udes environmental mitigation measures, environmental protection monitoring and mana gement and main works, as well as mitigation and elimination of negative impacts on env ironment. Many mitigation measures are management practices, and the budge are includ ed in the whole contract and not indicated specifically. The estimated total project construction investment is RMB 118,073,200, of which the one-time environmental protection investment reaches RMB 3,550,900, accounting for3.01% of the total project investment. Table 7-1 Investment Estimation of Environmental Protection Measures for the Project Amount Time Item Control Measures QTY (RMB in Remarks 10,000s) Construction site temporary 6 3.0 Constru Domestic tank ction sewage (Oil removal) Separation tank 6 3.0 period treatment Silt leachate sedimentation 1 2.0 tank Tarpaulin, construction fence / 15.0 Atmospheri Renting of sprinkler sprinkling c prevention 2 4.0 for dust prevention and control Silt stench prevention (plant measures 1 0.5 liquid, disinfectant) Low noise equipment, Prevention strengthening of equipment / 1.5 and control maintenance of noise Construction fence (3 / 3.0 temporary sound barriers,) Domestic rubbish collection / 3.0 Solid waste and disposal treatment Silt bagging temporary storage 5.0 and utilization Additional Engineering measures, soil and measures of the vegetation, / 154.45 water temporary measures, etc.

49 Hongya County Restructuring Component of Sichuan Small Towns Development Project by World Bank Loans Environmental Management Plan

Amount Time Item Control Measures QTY (RMB in Remarks 10,000s) conservatio n measures Environmen Environmental monitoring tal / 115.9 during the construction period monitoring Prevention and control Impervious membrane for silt of 5.0 stacking yard groundwate r Provision of non-honking / 2.0 Prevention signs and speed reducer and control Reserved noise cost / 8.0 of noise Shock absorption, sound 1 3.0 insulation of equipment Waste gas Strengthening of vehicle / treatment management Waste water Tanker transport of domestic / 1.0 treatment sewage Operati Trash can 4 1.0 on Solid waste period treatment Rubbish collection facilities 4 2.0 Environmen Completion acceptance of tal environmental protection / / protection works acceptance Ecological Greening / / measures Environmen Environmental monitoring tal / 22.74 during the operation period monitoring Total investment 355.09

50