HS2: the opportunity Kate Allen, Supply Chain Manager HS2 Ltd

www.gov.uk/hs2 HS2: the new backbone of Britain’s rail network

HS2 vision: To be a catalyst for growth across Britain More than double the seats

12,10 3,490 1,720 2017 0 evening rush hour total seated capacity

2033 with 31,200 8,620 4,860 HS2

London Euston Manchester Piccadilly Leeds (Crewe/Stoke Corridor) (Doncaster Corridor)

Phase One statistics

216km 49.5km 74km 128 mt EXCAVATED MATERIAL ROUTE LENGTH TUNNELS CUTTINGS (90% TO BE RE USED)

145 152 31 299 STRUCTURES STRUCTURES UNDER MAIN COMPOUNDS FOR SATELLITE COMPOUNDS OVER BRIDGES BRIDGES CONSTRUCTION HS2’s strategic goals

Catalyst Capacity & Value for Passenger for growth connectivity money experience

Skills and World class Sustainable & a employment standards good neighbour When we are buying

Tier 1 Tier 1 Supply chain ITT issue award opportunities

Enabling works Complete Complete 2017+

Main works civils Complete Summer 2017 2017/18+

Design Q2 2017 Q1 2018 2018+ Stations North Q2 2019 Q2 2020 2020+ Construction South Q1 2018 Q3 2018 2018/19+

Railway systems Q3 2018 Q4 2019 2019/20+

Rolling stock Q2 2018 Q4 2019 2019/20+ Phase One enabling works contracts

• Laing O’Rourke Construction Ltd NORTH LM JV • J. Murphy & Sons Ltd

• Morgan Sindall Construction & Infrastructure Ltd CENTRAL Fusion JV • BAM Nuttall Ltd • Ferrovial Agroman (UK) Ltd

Plc SOUTH CS JV • Skanska Construction UK Ltd Enabling Works

11 Main works civils contracts

7 Packages 2 in area 4 Contractors north £6.6bn 3 in area central

2 Phase One, plus in area Phase 2a option south Main works civils contractors

Group Limited 2 • Vinci Construction UK Limited in area BBV JV • Vinci Construction Terrassement north • BeMo Tunnelling GmBH

• Bouygues Travaux Publics Align JV • Sir Robert McAlpine Limited 3 • Volker Fitzpatrick Limited in area central • Construction Limited CEK JV • Eiffage Genie Civil • Kier Infrastructure and Overseas Limited

2 • Skanska Construction UK Limited in area SCS JV • Costain Limited south • Strabag AG Our culture National College for High Speed Rail

DONCASTER BIRMINGHAM HS2 BIM upskilling platform

www.bimupskilling.com [email protected] How to engage with HS2

Resource Question Register s s

gov.uk/hs2 [email protected] [email protected]

Supplier Guide gov.uk/contracts‐finder Supply Chain FAQs competefor.com Contract Opportunities Table bimupskilling.com