Road Management Plan

Draft 2011

Draft Version 2.20 15 April 2011

Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

APPROVAL VERSION COUNCIL GOVERNMENT GAZETTE MEETING No. No. ISSUE DATE PAGE No. DATE 6 December 16 December 1 G51 3384 2004 2004

AMENDMENTS VERSION APPROVED DATE * DATE OF DETAILS No. BY APPROVED EFFECT Substantial revision of entire 2.2 document following discussion will RG 8 April 2011 relevant stakeholders

Page 2 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Table of Contents:

1. Executive Summary ...... 4

2. About the Mornington Peninsula ...... 5

3. Road Facts ...... 7 3.1. Purpose of Asset: ...... 7 3.2. Description: ...... 7 3.3. Works: ...... 7 3.4. Stakeholders: ...... 8 3.5. Funding: ...... 9 3.6. Relevance of Plan to Community Plan: ...... 9 4. Legislative Control ...... 11 4.1. Road Management Act: ...... 11 4.2. Road Safety Act: ...... 11 5. Assets to which this Plan Applies ...... 13 5.1. Classification: ...... 14 5.2. Register of Public : ...... 18 6. Demarcation ...... 19 6.1. State Roads: ...... 19 6.2. Boundary Roads: ...... 19 6.3. Public : ...... 19 6.4. : ...... 20 6.5. Lighting: ...... 20 6.6. Utilities: ...... 20 6.7. Vehicle Crossings: ...... 20 6.8. Paths: ...... 21 6.9. Equestrian Trails: ...... 21 6.10. Roadsides: ...... 21 7. Levels of service ...... 22 7.1. Specifications and Standards: ...... 22 7.2. Inspection and Maintenance: ...... 22 7.3. Standards of Maintenance and Repair: ...... 23 7.4. Reseal and Rehabilitation: ...... 24 7.5. Events Beyond Control of Council: ...... 24 8. Data Management System ...... 25

9. Plan Improvement and Monitoring ...... 27

10. Glossary ...... 28

11. Appendices ...... 30

Page 3 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

1. Executive Summary

In accordance with Division 5 of the Road Management Act 2004 the Mornington Peninsula Shire, as a road authority, has developed and published this Road Management Plan.

The Road Management Plan (referred to hereafter as the ‘Plan’) for Mornington Peninsula Shire roads and associated infrastructure assets and is a communication tool used to document current levels of service and management practices. The plan provides a transparent and a network wide approach to managing the roads.

This plan will be implemented to fulfil the Shire’s Community Plan objectives in regard to infrastructure assets and is in line with the Asset Management Policy and Strategy.

This plan will enable the Shire to fully comply with the requirements of the Road Management Act 2004, (referred to hereafter as the ‘Act’). The primary objective of the Act closely aligns with the Shire’s Asset Management Policy objective.

Section 4 of the Act states its objectives as:

“The primary object of this Act is to establish a coordinated management system that will promote safe and efficient road networks at State and local levels and the responsible use of road reserves for other legitimate purposes”. 1

The three main requirements to which the Shire needs to comply are the establishment of:

1. A Register of Roads

2. Levels of Service/Standards

3. A Management System

Page 4 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

2. About the Mornington Peninsula

Our Place

Mornington Peninsula Shire (MPS) is located at the fringe of Melbourne’s outer southern suburbs, between 40 and 80 kilometres south of the Melbourne CBD. Mornington Peninsula is bounded by Frankston City and the City of Casey in the north, Western Port in the east, Bass Strait in the south and Port Phillip Bay in the west.

The Shire encompasses a total land area of about 724 square kilometres, including over 190 kilometres of coastline, which is approximately 10% of Victoria’s coastline. The region is one of Melbourne’s premier holiday and retirement destinations and has magnificent landscapes, coasts and beaches that are of state significance and attract millions of visitors every year.

Our Community

The Shire has forty townships spread across the peninsula, with the majority of the residential population living along the coastline of Port Phillip Bay, between Mount Eliza and Dromana.

The Shire is a second home to many thousands of additional households from Melbourne and surrounds that make regular holiday and weekend visits seeking the health giving properties and recreational opportunities of the beautiful beaches, landscapes and natural environments. Many beach holiday houses are based along the Port Phillip coastline, with

Page 5 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

the population swelling by up to 30% in the summer months, mostly in the southern bayside towns from Dromana to Portsea.

Australian Bureau of Statistics (ABS) Estimated Resident Population data for the Mornington Peninsula 30 June 2008 was 145,356. The population is estimated to increase to more than 160,000 by 2021.

Almost 4 million people are recorded as visiting the Mornington Peninsula each year providing increased opportunities for tourism.

Our Environment

Approximately 70% of the Shire is retained as rural land within the Green Wedge planning zone, whilst the other 30% is taken up by towns and villages. Within the Green Wedge, there are areas of highly productive farm land as well as highly significant landscapes and ecosystems. The Mornington Peninsula and Western Port has become part of the world-wide network of biosphere reserves recognised by the United Nations. The region has been recognised for its: great biological diversity; many significant, rare native plants and vegetation; wetlands; sites of geomorphological significance; remnant indigenous vegetation; highly scenic landscape values; and sites of historic importance.

Our Economy

The Mornington Peninsula has a growing and diverse local economy that includes retail, manufacturing, construction and business services. The region also has a distinguished agricultural history, including dairy, viticulture (grapes) and horticulture (fruit, vegetables and flowers), with the existing food and wine producers being recognised as world class and industry leaders in their respective fields. Tourism is another significant contributor to the local economy, with the Peninsula being a popular weekend, recreation and holiday destination.

Page 6 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

3. Road Facts

3.1. Purpose of Asset:

The network of roads is provided primarily for travel and transport and the road reserves are available for other appropriate uses. 1 This might include for example provision for nature strips, remnant vegetation, native animal corridors, and utilities.

3.2. Description:

The Shire’s road network has approximately 3,700 separate roadways with a total length of approximately 1,980 km. This is made up of:  1,330 km of local roads with a sealed surface  370 km of local roads with a unsealed or unformed surface  276 km of roads controlled and maintained by VicRoads

In addition to the above length of roads, the following road assets form a significant component of the road network that the Shire has responsibility for:  Kerbs approx 1,920 km  Shoulders: approx 500 km  : approx. 120 No.  Medians: approx 1,230 No.  Pathways: approx 580 km  Car parks: approx 500 No.  Road bridges: 7 No.  Major culverts: approx. 30 No.  Pits: approx. 47,000 No.  Drainage Pipes: approx. 1,200 km

3.3. Works:

 The maintenance of bitumen surface pavements and shoulders requires attention by service providers to repair corrugations, , depressions and scouring. Intervention levels have been specified for road failures and, when repaired, must comply with Shire standards.  Maintenance for unsealed pavements and shoulders is as above plus road and grading and dust suppression.  Service providers carry out regular inspections to identify failures that need to be repaired as well as responding to failures that have been identified by concerned members of the community.  The service provider also provides a street sweeping program.  Roads are resealed and rehabilitated annually in order to achieve the specified pavement performance outcomes of the Safer Local Roads contract. In order to identify and prioritise roads for treatment, a three-yearly cycle of independent road pavement inspections is undertaken. The resultant data is modelled through the service providers Pavement Management System in order to determine the annual works program. This program is subject to approval and

1 Road Management Act 2004, s. 20(1).

Page 7 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

sign-off by appropriate Shire representatives prior to commencement of annual works. If the required performance outcomes are not achieved and verified by subsequent condition assessments, an approved rectification program of works are undertaken to bring the network back to the specified standard.  Agreements for works have been established on municipal boundary roads between the Shire and the two abutting municipalities, Frankston City and the City of Casey.  Utilities will also do works on their own infrastructure which can involve Shire assets, such as having to dig up a section of road. The utilities are required to comply with the Road Management Act Code of Practice for Management of Infrastructure in Road Reserves.  New roads and other assets that are constructed by developers as part of new subdivisions do not become the responsibility of Council until assessed by Shire Officers as meeting required standards.

3.4. Stakeholders:

A stakeholder is any person or group having an interest in the service provided by the asset. The following key stakeholders have been identified:

 Mornington Peninsula Shire  State Road Authorities Council  Abutting municipalities  Shire residents  Utilities  Local community groups  Emergency and disaster services  Private road groups  Road developers and consultants  Bicycling groups  Civil contractors  Public transport operators  Foreshore committees of  Commerce and industry groups management  Tourism operators  Shire’s insurer

The management of the municipal road network requires extensive resources from the Shire. The following is a list of Shire staff, units or contractors that have involvement in various stages of road management.

 Councillors & Executive  Project Management  Safer Local Roads Contract  Design Coordinator  Development Engineering  Safer Local Roads Service  Construction and Asset Provider Protection  Infrastructure Maintenance  Renewable Resources Contract Coordinators  Geographic Information Systems – Parks & Roadsides  Finance – Signs & Street Furniture  Insurance & Risk Management – Cleansing  Recreation and Leisure  Infrastructure Maintenance  Community and Special Events Service Providers  Aged and Disabled Care – Parks & Roadsides  Social Planning and Community – Signs & Street Furniture Development – Cleansing  Environment Protection  Infrastructure Strategy  Property Services  Asset Management  Cemeteries  Infrastructure Planning & Policy

Page 8 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

& Road Safety  Customer Service  Special Charge Schemes  Records Management

All have the opportunity to provide input into the delivery of a safe and efficient road network. Apart from the commitment of these people the other resource that is required is adequate funding.

3.5. Funding:

Given the long term contracts with external service providers for the delivery of maintenance services on Shire controlled assets, the Council as part of their annual budget process provides operational funding to cover monthly contractual payments to the service providers. The monthly payments are primarily a lump sum with a small amount payable under Schedule of Rates arrangements for any minor discretionary works outside lump sum maintenance works.

Included in the annual operational budget is an allowance for growth to reflect additional assets being added to the contracts through subdivision and capital projects. In addition, included in the annual operational budget is an allowance for annual adjustment (variation) to the contract payments to allow for rise and fall in the cost of service delivery.

Council as part of the annual budget also provides funding towards ongoing annual programs involving asset renewal / rehabilitation. Annual programs include funding for such programs as crushed rock re-sheeting of unsealed roads, replacement of kerb & channel / kerbing, replacement and drainage rehabilitation. The level of funding is set by Council and programs delivered per annum are limited to the available funds.

In addition to the operational funds Council provides through its budget process, Council may receive grant funding from State or Federal Governments Programs (e.g. Roads to Recovery) for specific projects / works.

The functions required to be exercised by the Council, as a road authority, are limited by the financial and other resources that are reasonably available to the Council. The Council must also give consideration to the broad range of other services it provides to the community.

3.6. Relevance of Plan to Community Plan:

The Road Management Plan is consistent with the key elements of the Community Plan as the following points highlight:

3.6.1. Creating safe, healthy and engaged communities

Accessible, valued and well utilised community resources:

 to effectively manage and maintain our road and path network. Planning, developing and maintaining community assets:

 to effectively develop and manage our transport network to provide for access, mobility and community safety.  to develop and implement road safety.

Page 9 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

 to manage and renew existing infrastructure assets.

A safe and supportive community:

 to provide, protect and enhance Shire amenity for community enjoyment.

3.6.2. Being responsive, accountable and forward looking

We embrace the principles of continuous improvement and best practice to ensure that we deliver reliable, efficient and effective services to the community. We achieve this through responsible financial management, effective advocacy and engagement, and by highly valuing our people.

Quality service:

 to provide high-quality service outcomes by ensuring that Council processes and systems are effective and efficient.

Good governance:

 to monitor and minimise our risk exposure.

Effective leadership, advocacy & engagement:

 to encourage community engagement through communication, education and debate on key issues.  to engage with the community in diverse and different ways to capture and understand issues of community concern.

Responsible financial management:

 To sustainably manage the Council's finances and resources. To effectively develop and manage the capital works program.

Page 10 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

4. Legislative Control

4.1. Road Management Act:

The “Road Management Act” (referred to hereafter as the ‘Act’) was developed by the Victorian Government to establish improved road management legislation to provide a more efficient and safer road network for all Victorians. The need for this new legislation has also arisen as a result of a High Court decision that changed the common law governing civil liability for road management to make road authorities more accountable for the safety of their road networks”.

The Road Management Act places a statutory duty on a road authority to inspect, maintain and repair a public road to a standard specified in the road management plan. 2

The statutory duty does not create a duty to upgrade a road or to maintain the road to a higher standard than the standard to which the road is constructed.

The statutory duty to inspect applies to any part of a public road which is a roadway, pathway, shoulder or road infrastructure.

4.2. Road Safety Act:

Obligations of road users:

All road users have a duty of care under the Road Management Act 2004, section 106, with particular obligations prescribed in Section 17A of the Road Safety Act 1986, which states:

17A Obligations of road users

(1) A person who drives a motor vehicle on a must drive in a safe manner having regard to all the relevant factors, including (without limiting the generality) the—

(a) physical characteristics of the road; (b) prevailing weather conditions; (c) level of visibility; (d) condition of the motor vehicle; (e) prevailing traffic conditions; (f) relevant road laws and advisory signs; (g) physical and mental condition of the driver.

(2) A road user other than a person driving a motor vehicle must use a highway in a safe manner having regard to all the relevant factors.

(3) A road user must—

(a) have regard to the rights of other road users and take reasonable care to avoid any conduct that may endanger the safety or welfare of other road users;

2 Road Management Act 2004, s. 40.

Page 11 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

(b) have regard to the rights of the community and infrastructure managers in relation to road infrastructure and non-road infrastructure on the road reserve and take reasonable care to avoid any conduct that may damage road infrastructure and non-road infrastructure on the road reserve; (c) have regard to the rights of the community in relation to the road reserve and take reasonable care to avoid conduct that may harm the environment of the road reserve.

(4) In subsection (3), infrastructure manager, non-road infrastructure, road infrastructure and road reserve have the same meanings as in section 3(1) of the Road Management Act 2004.

Page 12 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

5. Assets to which this Plan Applies

The plan will cover in detail roads, and car parks. To a lesser degree many other road assets are included as the Shire has a complete register of all other assets, grouping is shown below:

 Infrastructure Assets  Traffic Islands  Roadways  Traffic Control  Sealed  Signs  Local Area Traffic  Unsealed  Regulatory Signs Management  Warning Signs (LATM) Devices  Road Shoulders  Hazard Markers  Pavement  Sealed  Advisory Signs Marking and Line  Unsealed Marking  Bridges  Delineators  Car Parks  Road Bridges  Rumble Bars  Sealed  Footbridges  Pedestrian  Unsealed  Major Culverts crossings  Traffic signals  Kerb & Channel  Road Drainage  Barrier  Pits  Street Lighting  Mountable  Pipes  Shire controlled  Semi mountable  Culverts  Open inverts  Structures  Kerb only  Open Drains  Channel only  Soak Pits  Edge strips  Fences  Paths  Guard Fence  Footpaths  Pedestrian  Shared paths Fencing  Equestrian Trails  Median Fencing  Handrail  Roundabouts

 Medians

All assets have Minimum Inspection Frequencies (see Appendix 1), and standards for Maintenance and Repair (Compulsory Intervention Levels, Maximum response times: see Appendix 2)

Page 13 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

5.1. Classification:

5.1.1. :

The Shire engaged ARRB Transport Research to investigate the functional hierarchy and service levels for sealed and unsealed roads.3 Working closely with Shire staff, and building on the experience from the Safer Local Roads contract, the following road classifications have been developed.

The purpose of a road hierarchy is to ensure that appropriate management, risk management, engineering standards and planning practices are applied to a road based on its function. It also enables more efficient use of limited resources by allocating funding to those roads that are in greater need and on which expenditure is better justified. The functional local road classifications cover both urban and rural areas. Shire officers have reviewed the road network and reclassified the hierarchy based on these functional types:

Figure 1: Schematic Diagram of MPSC Road Classification System – Rural

Local

Arterial Road Access Road (VicRoads)

Limited Access Track

Access Road

3 ARRB. (G. Giummarra). Report for MPSC – Development of Roads Classifications, Design Standards, Maintenance/Intervention Levels and Access Provision Guidelines (2004).

Page 14 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Table 1: Road Classifications in Rural Areas

Road Service Function Brief Description Class Type Class Description RURAL AREAS Provides primarily for the main connection Two-way, two-, mainly 4A Rural Arterial from town centres and local areas to the wider sealed. State main road network. Provides for collecting and distributing traffic Two-way, two- lane sealed or 4B Rural Collector and acting as a feeder service to local arterial unsealed road. roads. Provides predominantly for direct access to Two-way, mainly two-lane 4C Rural Access properties, recreational areas and industries in sealed or unsealed road. rural zones. Rural Access 4CS Substandard Rural Access 4CN Not Maintainable Two-way, unformed, single lane Rural Limited Provides primarily for limited access and in track with limited geometry and 4D Access rural areas using four wheel-drive vehicles. possible access restrictions imposed. Rural Limited 4DS Access Substandard Rural Limited 4DN Access Not Maintainable Provides similar functions to rural access or Generally a two lane, two-way Rural rural limited access roads, however not 4S not constructed to Substandard constructed to Shire standards but to a Shire standards. maintainable standard. Generally a one lane, two-way, Provides similar functions to urban access or unformed or unsealed road of urban limited access roads, however not 4T Rural Track low construction standards that constructed to Shire standards and cannot be cannot be economically economically maintained. maintained.

Figure 2: Schematic Diagram of MPSC Road Classification System – Urban

access road

access road State arterial road

Page 15 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Road Service Function Brief Description Class Type Class Description URBAN AREAS Generally a four-lane, or two- Provides primarily for the main connection Local Arterial lane, two-way sealed road with 8A from urban centres and local areas to the Road parking provisions on both wider State arterial road network. sides. Provides for collecting and distributing traffic Mainly a two lane, two-way 8B Collector Road and acting as a feeder service to local arterial sealed road with commonly roads. parking on one side. Provides predominantly for direct access to Generally a two lane, two-way 8C Access Road properties, recreational areas and industries in sealed road, or unsealed road. urban zones. Provides similar functions to urban access Generally a sealed two-way Access Road 8 CS road, however not constructed to Shire road not constructed to Shire Substandard standards but to a maintainable standard. standards. Generally an unformed or Provides similar functions to urban access and unsealed two-way road of low Access Road urban limited access roads, however not 8 CN construction standards that Not maintainable constructed to Shire standards and cannot be cannot be economically economically maintained. maintained. Generally a one lane, two way Limited Access Provides primarily for limited access to rear of road at the rear of properties or 8D Lane properties or within recreational parks informal tracks within recreational parks. Generally a sealed one lane, Limited Access Provides similar functions to urban limited two-way road not constructed to 8 DS Lane access lane, however not constructed to Shire Shire standards at the rear of Substandard standards but to a maintainable standard. properties. Generally an unformed or Provides similar functions urban limited access Limited Access unsealed one lane, two-way lane, however not constructed to Shire 8 DN Lane road of low construction standards and cannot be economically Not maintainable standards that cannot be maintained. economically maintained. Generally a one lane, two-way, Provides similar functions to urban access and unformed or unsealed road of urban limited access roads, however not 8 T Urban Track low construction standards that constructed to Shire standards and cannot be cannot be economically economically maintained. maintained.

Appropriate geometric design guidelines for Class A, B and C roads have been established. The standards take into account road user requirements relating to operational comfort, convenience and safety and the funding resources available to Council.

Maintenance intervention levels for sealed and unsealed road pavements are provided based on an extensive review of the maintenance of its assets. This review involved input from the community to ensure maintenance service standards and service levels reflected the expectations of the community.

5.1.2. Off-Street Car Park Hierarchy:

 CP 1 – High Profile Commonly an off-street sealed car park in a major commercial area.

 CP 2 – Low Profile Commonly an off-street car park in other areas.

Page 16 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

5.1.3. Path Hierarchy:

The Shire keeps a register of all footpaths and their classification. All paths are categorised as either a Shared Path, Residential, Foreshore, Park or Other. There are also High Profile paths that attract a higher level of inspection and maintenance. The list below details the types of path that are typically included in each classification, although this is not a definitive list.

Residential, Commercial and Industrial Areas

P 1 – High Profile A footpath immediately adjacent to:  Large Township activity centres  Small Township activity centres  Local activity centres  Convenience centres  Schools  Child Care Centres  Kindergartens  Hospice & Palliative Care  Hospitals  Nursing Homes

P2 – Low Profile All other paths in a Residential, Commercial or Industrial area

Shared Paths (includes Boardwalks) P1 – High Profile  Any path that connects two townships  Any shared path that also fits the criteria for a high profile footpath.

P2 – Low profile  All other paths

Foreshore

P1 – High Profile During daylight savings the following paths are considered high profile:  Any path in a camping area  Bay trail  Hastings foreshore

P2 – Low Profile  All other paths during daylight savings time  All paths are considered low profile outside daylight savings time

Parks

P1 – High profile:  Typically any path in park of regional significance

P2 – Low profile Any other path in a Shire park or reserve

Page 17 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Council will not become the road authority for new subdivisions until all 5.2. Register of Public Roads: works are complete and are to Council’s standards.

As a road authority the Shire must keep a Register of Public Roads in The compilation of the register is an ongoing process of refinement accordance with the Road Management Act to record the details of the with new assets coming on line all the time, plus newly found areas Public Roads and Ancillary area for which it is responsible. Council and dispute resolution between other road authorities. must make a decision that the roads included in the Register are reasonably required for general public use. For further information A sample of the Register of Public Roads is shown below: refer to the Shire’s of Register of Public Roads Policy.

Roads for which Council is not the authority will either be the responsibility of other road authorities, e.g. VicRoads, Parks Victoria and Department of Sustainability & Environment. For a list of VicRoads roads refer to Appendix 3.

DATE DATE ROAD BLOCK ROAD ROAD LOCALITY ALTERNATIVE FROM TO LENGTH BECAME CEASED TO ROAD MAINT/CONTROL ANCILLARY AGREEMENTS, COMMENTS

PUBLIC BE A PUBLIC ID ID NAME TYPE ROAD NAME ROAD ROAD CLASS DESCRIPTION AREAS PLANS ETC.

URBAN 104827 1 SHAKTI PLACE HASTINGS TARA DVE TWAY END 124 1/7/2004 ACCESS LADY URBAN 304680 1 SHALIMAR COURT SORRENTO NELSON TWAY END 80 1/7/2004 ACCESS URBAN 211650 1 SHANDON STREET MORNINGTON HERBERT LUCERNE 170 1/7/2004 ACCESS URBAN 211650 2 SHANDON STREET MORNINGTON LUCERNE BELEURA HL 180 1/7/2004 ACCESS URBAN 211650 3 SHANDON STREET MORNINGTON BELEURA HL AMELIA 117 1/7/2004 ARTERIAL URBAN 211650 4 SHANDON STREET MORNINGTON AMELIA NEPEAN 242 1/7/2004 ARTERIAL MOUNT URBAN 204717 1 TANGERINE COURT MARTHA PAPERBARK TWAY END 99 1/7/2004 ACCESS OLD MERRICKS BITTERN- RURAL 118820 1 TANNENBAUM NORTH DROMANA TWAY END 472 1/7/2004 ACCESS JOHN URBAN 211100 1 BELEURA HILL ROAD MORNINGTON ROWEL ROTHESAY 145 1/7/2004 COLLECTOR URBAN 211100 2 BELEURA HILL ROAD MORNINGTON ROTHESAY CHANNEL 140 1/7/2004 COLLECTOR

Page 18 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

6. Demarcation

6.1. State Roads:

Guidance on the physical limits of operational responsibility between VicRoads and municipal councils for different parts or elements of the road reserve of a Freeway or Arterial Road is provided in the Road Management Act Code of Practice – Operational Responsibility for Public Roads, Part 1.

6.1.1. Car Parking Bays on Arterial Roads:

VicRoads is responsible for any part of the roadway that could be used by through traffic. Distances of less than 200 metres are considered to be of limited use for through traffic.

Therefore the Shire is responsible on Arterial Roads for maintaining isolated parking areas of lengths less than 200 metres between kerb outstands.4

6.2. Boundary Roads:

The Shire has entered into agreements with abutting municipalities where a municipal road defines the boundary between the two Councils.

6.2.1. City of Frankston:

The Shire has a letter of agreement, dated 30 June 2004, with the City of Frankston concerning municipal boundary road responsibilities.

6.2.2. City of Casey:

The Shire has entered into a Memorandum of Understanding, dated 24 December 2004, with the City of Casey concerning the management of boundary roads.

6.3. Public Transport:

6.3.1. Bus Passenger Facilities:

Council has a contract with the Department of Transport for the supply and maintenance of bus shelters and some DDA compliant bus shelter pads at specific locations throughout the Shire.

4 Road Management Act 2004, Code of Practice for Operational Responsibility for Public Roads (December 2004), p. 11.

Page 19 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

The service contract is for the full asset management of the shelters and pads, including routine maintenance along with cleaning and also periodic maintenance along with structural integrity maintenance.

Council also has and extensive network of DDA compliant bus stop pads and bus shelters that are not part of the abovementioned service contract. Council directly manages these pads and shelters with respect to asset management incorporating routine and periodic maintenance along with asset renewal.

6.3.2. Bus Bays:

Responsibilities for bus bays are described in RMA Code of Practice, Operational Responsibility for Public Roads, dated 17 December 2004.

6.3.3. Rail Tracks (Railway Level Crossings):

Responsibilities of public transport operators and the road authority for roads with rail crossings are set out in a Safety Interface Agreement (SIA) between the two parties. The SIA clearly defines which authority is responsible for maintenance and renewal of assets relating to rail crossings, both level and grade-separated.

6.4. Bridges:

See Definitions: Road infrastructure

The MPSC is responsible for inspecting, maintaining and repairing all road bridges, including pathways, on Municipal Roads within the Shire on its Register of Public Roads

6.5. Street Lighting:

Standard street lighting is generally the responsibility of the electrical distribution business.

The Shire is responsible for the maintenance of non-standard lighting in specific areas such as subdivisions.

The Shire works with the relevant electrical authority to ensure the regular inspection and repair or replacement of such lights and poles as required.

6.6. Utilities:

The Shire and utilities work together cooperatively to facilitate the installation, maintenance and operation of road and non-road infrastructure within road reserves. This work is undertaken in accordance with the Road Management Act 2004, Code of Practice for Management of Infrastructure in Road Reserves.

6.7. Vehicle Crossings:

The Road Management Act provides that a road authority is not liable for private vehicle crossings (driveways). This applies in both urban and rural areas.

Page 20 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

This is consistent with the general principle in the Road Management Act that the owner of an asset is responsible for the condition and maintenance of that asset. This does not, however, prevent the Council from imposing conditions on the construction of a .

The adjacent property owner is responsible for the construction and maintenance of their vehicle crossing, including the pathway section and the adjacent kerb and channel. The property owner is also responsible for pathways on road reserves that provide access to land adjoining a road.

The adjacent property owner is responsible for a culvert crossing including end walls.

Vehicle crossings must comply with the relevant Shire Policy

For further details refer to the Shires’ Register of Public Roads Policy.5

6.8. Paths:

The Shire is responsible for all paths on its reserves and road reserves that appear on its asset register.

For a definition of Foot trodden track refer to the Road Management Act

6.9. Equestrian Trails:

The Shire will only be responsible for Designated Equestrian Trails constructed or developed by the Shire for use by members of the public with horses.

A horse trodden track over roadside land is not an Equestrian Trail.

6.10. Roadsides:

The statutory duty imposed by the Road Management Act to inspect does not apply to any roadside that has not been developed by a road authority for use by the public as a roadway or pathway. A road authority is not under a duty to maintain roadside bushland.6

At its discretion, the Shire has included some parks and roadsides standards in this Road Management Plan as it is considered that they may affect the safety of road users.

5 Mornington Peninsula Shire Council. Register of Public Roads Policy – Background Paper (adopted by Council 24 March 2008), p. 8. 6 Road Management Act 2004, s. 40(4)(b), s. 107.

Page 21 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

7. Levels of service

7.1. Specifications and Standards:

The Shire has specifications and standards for constructed assets that are the Shire’s responsibility, or will become so. The standards cover all areas of construction, OH&S, traffic management and quality systems. The Development Engineer and Construction and Asset Protection Unit work together to ensure that new assets are constructed to these specifications and standards and after the assigned maintenance period make sure the assets at handover are serviceable. The specifications and standards can be viewed at our web site - http://www.mornpen.vic.gov.au .

7.2. Inspection and Maintenance:

The Shire has a process in place for inspection frequencies, intervention levels and time to complete works. Higher risk areas have a higher inspection frequency, tighter intervention levels and quicker response times, e.g. footpaths around schools or shopping centres are inspected more frequently than footpaths in residential areas. The response times have been developed giving consideration to matters such as the type of infrastructure, public usage, community expectations, risk analysis, and the resources available. Nominated inspection and audit regimes are an integral part of pro-active service delivery and risk management.

The nominated response times have been developed as a maximum response time that will be achieved at all times in all circumstances within the control of the Shire. It is not the desirable level of service but a level of service that it is intended to achieve in all circumstances. In most circumstances it is expected that a higher level of service will be achieved. Refer to Events Beyond Control of Council: on page 24.

The Shire’s service providers must plan and implement programs of inspections of the road network which:

 are undertaken at an agreed minimum frequency,  identifies defects,  prioritises defects giving consideration to potential risk,  are responsive to reports or complaints,  are carried out at intervals designed to establish programs of periodic maintenance.

The Shire’s service providers respond to three types of inspections:

7.2.1. Programmed Inspections

Where each asset type is inspected at a specified minimum frequency, the minimum frequency of inspection for all road infrastructure assets can be viewed in Appendix 1

Page 22 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

7.2.2. Ad-hoc Inspections

Inspections of individual assets are undertaken in response to reports, complaints, notifications or other representations made to the Shire or inspections by work crews.

7.2.3. Triggered Inspections

Inspections of certain assets following defined events notified to the Shire or of which the Shire is aware. These could include events such as the movement of an abnormally heavy load, a road opening, special event, or events likely to cause defects in an asset.

7.3. Standards of Maintenance and Repair:

A table of Standards of Maintenance and Repair, including compulsory intervention levels and maximum response times can be viewed in Appendix 2.

7.3.1. Tracks

Standards for Maintenance and Repair for Tracks (Type T roads) will be as follows:

 Only a minimal standard of maintenance will be delivered.

 An attempt will be made to make a road passable by a standard model two- wheel drive vehicle (e.g. Falcon, Holden Commodore) at very low speed in the following circumstances:

 Primary access to a property where people reside.

 Dry weather access only.

 Work can be undertaken economically within available road maintenance resources.

 The road will not be upgraded or maintained to a higher standard than the standard to which the road is constructed.

 Response time for reactive inspections: 7 days.

 Response time for repairs or making safe: 28 days.

7.3.2. Car Parks

Standards for Maintenance and Repair for Car Parks will be as follows:

 High Profile Off-Street Car parks ( CP 1) are the same as Type B roads.

 Other Off-Street Car parks (CP 2) are the same as Type C roads.

 On-street car parks are the same as Type C roads, unless nominated as a CP 1 classification in the Register of Public Roads.

Page 23 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

7.4. Reseal and Rehabilitation:

The Safer Local Roads service provider’s Pavement Management System is utilised to determine the annual local sealed roads reseal and rehabilitation program (see 3.3 Works:). Factors taken into account when optimising expenditure to achieve SLR pavement performance outcomes are roughness, rutting, surface texture depth, crocodile cracking, pavement defects, flushing, stripping, surface age and traffic loading. Various surface and pavement treatment options are considered in order to achieve best performance outcomes.

The current status of the local sealed road network within SLR is indicated by the (PCI), an index that takes into account condition related data. The PCI is a useful method for comparison of the network condition during three year assessment cycles, however it cannot be used as a ‘universal’ scale of comparison between other municipalities.

7.5. Events Beyond Control of Council:

Council will make every endeavour to meet all aspects of its Road Management Plan. However in the event of natural disasters and events but not limited to fires, wind storms and floods, as well as human factors, but not limited to lack of Council staff or suitably qualified contractors, because of Section 83 of the Victorian Wrongs Act, 1958, as amended, Council reserves the right to suspend compliance with its Road Management Plan.

In the event that the Chief Executive Officer of Council, has to, pursuant to Section 83 of the said Act, consider the limited financial resources of Council and its other conflicting priorities, meaning Council’s Road Management Plan cannot be met, they will write to Council’s Officer in charge of its Road Management Plan and inform them that some, or all of the timeframes and responses in Council’s Road Management Plan, are to be suspended.

Once the events beyond the control of Council have abated, or if the events have partly abated, Council’s Chief Executive Officer will write to Council’s Officer responsible for Council’s Road Management Plan and inform them which parts of Council’s Road Management Plan are to be reactivated and when.

Page 24 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

8. Data Management System

Service Providers are responsible for the maintenance of roads, footpaths, kerb & channels, bridges, major culverts and other infrastructure assets. To achieve the contract standards and inspection frequencies the service providers have implemented various systems. The Safer Local Roads contractor runs a maintenance management system that follows works from inception to completion. Inspectors have Global Positioning System (GPS) handheld technology in the field so that each defect for roads, footpaths and kerb & channels is mapped and prioritised. This is an effective way of logging a defect to a point on the asset. For example, a pot hole is located by GPS and thereby linking the defect to the road block, so that each defect is logged against an asset. This means it is there for future reference, such as supervisor audit, customer inquiry or, if it is a failure that happens repeatedly, then further investigation can be carried out.

Once inspections are complete the inspectors upload their data directly into the system which produces work schedules based on compliance with intervention levels and response times. A completion date is entered into the system when works are complete. This can then be archived and will be used for the supervisors to audit and for future use to use in road modelling.

The Parks and Roadsides team maintain and update a historical reference of identified trees (trees inspected). The trees are individually identified via a unique barcode number. Information includes details such as tree species, tree height, GPS location and previous maintenance, to name a few. This database is known as the Tree Risk Database.

Page 25 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Following is the flowchart of maintenance works as provided by a Service Provider.

In the case of customer request or staff initiated activities; they will be generated by the Shire’s customer service software Merit. The Safer Local Roads service provider will tag all works generated via Merit with a customer request ID so that the activity is tracked from inception to completion. Giving a full history as described earlier for feedback to customers if required. This data can also be used by the contracts supervisor for auditing quality of works, response times and customer relations.

Page 26 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

9. Plan Improvement and Monitoring

The area of roads and asset management has been rapidly changing over several years and will continue to do so in the future. Therefore there is a need to continually improve the Shire’s Road Management Plan and to update amendments as required by the Road Management Act. Improvement will come from monitoring changes in:

 Legislation  Technology  Community needs  Methodology  Resources  Liability claims  Dispute resolution and  Agreement finalisation.

The Plan will be reviewed in compliance with legislation and any changes or amendments made will be put forward for public review and gazettal as required

Page 27 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

10. Glossary

The following terms are used in this Road Management Plan.

TERM MEANING AS USED IN THIS PLAN

Day Refers to all calendar days

Week Refers to 7-day week

Month Refers to calendar month.

Year Refers to calendar year.

Bridge Includes all structures, including culverts, on, over or under a road that have a single span or diameter of 1.8 metres or greater, or have a waterway area of 3 m2 or greater and includes all structural components (e.g. abutments, retaining walls, traffic safety barriers), and associated pathways, within the limits of the structure, but excludes approach embankments.

Public Road A road that the Council decides is reasonably required for general public use and is then registered on the Shire’s Register of Public Roads.

Repair The taking of any action to remove or reduce a risk arising from a defect, including – (a) reinstating a road to its former standard. (b) providing a warning to road users of a defect.

Road Any public highway; Any ancillary area; Any land declared to be a road under section 11 of the RMA or forming part of a public highway or ancillary area.

Road Reserve All the area of land that is within the boundaries of a road.

Roadside Any land that is within the boundaries of a road (other than the shoulders of the road) which is not a roadway or a pathway and includes the land on which any vehicle crossing or pathway which connects from a roadway or pathway on a road to other land has been constructed; Example: Any nature strip, forest, bushland, grassland or landscaped area within the road reserve would be roadside.

Roadway (a) In the case of a public road, the area of the public road that is open to or used by members of the public and is developed by a road authority for the driving or riding of motor vehicles; (b) In the case of any other road, the area of the road within the meaning of road in section 3(1) of the Road Safety Act 1986 —

Page 28 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

but does not include a driveway providing access to the public road or other road from adjoining land;

Vehicle Crossing An improved area between the carriageway of any Road to the adjacent property line of private property and includes culverts, kerb and channel laybacks and pavement thickening of footways, that provides safe, all weather access to properties and prevents damage to services and other assets located within the Road Reserve.7

7 • Mornington Peninsula Shire Council. Local Law No. 5 – and Roads (2005).

Page 29 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

11. Appendices

Page 30 of 30 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Appendix 1 – Standards for Inspection ...... 2 Appendix 2 – Standards for Maintenance and Repair ...... 4 Appendix 3 – VicRoads Roads ...... 10

Draft Version 2.20 15 April 2011

Page A-1 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Appendix 1 – Standards for Inspection

Page A-2 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Standards for Inspection

Minimum Asset Classification Inspection Frequency

A 1 month B 1 month Roadway, kerb & channel, road shoulders, roundabouts, medians, traffic C 1 year islands, open drains D 1 year S 1 year T 1 year

CP1 3 months Car Parks CP2 1 year

High Profile 6 months Residential 2 years Foreshore 1 year Paths Parks 1 year Shared Paths 1 year Other Reactive only

Designated Trails 1 year Equestrian Trails Other Reactive only

A 6 months B 6 months Signs, Delineators, Pavement Marking, Electrical Hardware [e.g. traffic C 2 years signals (Shire controlled)], Street Lighting (Shire controlled) D 2 years

S 2 years

T 2 years Day Parks & Open 1 year Space

A 2 years B 2 years Night C 5 years D 5 years

A 6 months B 6 months Street Furniture , Guard Rails, Fencing and Handrails C 2 years D 2 years S 2 years

Level 1 18 months Bridges Level 2 As determined by  Road Bridges Level 1 inspections  Footbridges

 Major Culverts Level 3 As determined by Level 2 inspections

Drainage (located within roads) – culverts, pits, piped drains, structures. All 5 years (Underground drains located within easements will be inspected by reactive methods only.)

Soak Pits (located within roads) All 1 year

Page A-3 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Appendix 2 – Standards for Maintenance and Repair

Page A-4 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Standards for Maintenance and Repair

Maximum Response Compulsory Intervention Level Classification Time proposed OBSTRUCTIONS AND SUBSTANCES IN TRAFFIC

LANES Materials fallen from vehicles. A 24 hours Dead animals. B 24 hours Wet clay and other slippery substances C 7 days Hazardous materials D 7 days Ponding of water > 300mm deep A 24 hours Fallen trees. B 24 hours Oil spills C 2 days Stray livestock D 7 days

SEALED PAVEMENT – POTHOLES depth > 35 mm and diameter > 150 mm; or A 7 days on bicycle , depth > 20 mm and diameter > 500 mm. Pothole depth > 50 mm and diameter > 200 mm; B 14 days or C 8 weeks on bicycle lanes, depth > 20 mm and diameter > 200 mm. D 8 weeks

SEALED PAVEMENT – DEFORMATION Any distressed pavement up to 25 m2 in area and deformation A 8 weeks > 75 mm depth under a 1.2 m straight edge. (except at abutments and culverts where deformation > 40 mm B 6 months depth) C 6 months D 6 months

Where any distressed pavement > 25 m2 in area and deformation > 75 mm depth under a 1.2 m straight edge (except at bridge abutments and culverts where deformation > 40 mm All depth): Place on road pavement renewal program for prioritisation.

SEALED PAVEMENT – EDGE BREAK Horizontal fretting > 75 mm A 8 weeks Horizontal fretting > 100 mm B 6 months Horizontal fretting > 150 mm C 6 months Horizontal fretting > 300 mm D 6 months

SEALED PAVEMENT – SWEEPING Any area where accumulated debris > 5 m2 within the common A 28 days travelled path and is hazardous to vehicles or pedestrians. Any area where accumulated debris > 10 m2 within the common B 8 weeks travelled path and is hazardous to vehicles or pedestrians.

Page A-5 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Any area where accumulated debris > 40 m2 within the common C 8 weeks travelled path and is hazardous to vehicles or pedestrians. D 8 weeks

UNSEALED ROADS – GRADING Corrugations, scouring, depressions and potholes on unsealed roads A / must not exceed 50 mm in depth for > 30% of area of roadway in road 8 weeks C (rural area) block; or B 8 weeks

C (residential Any scour occurrence length > 5 m and mean scour depth > 150 mm. 6 months area)

D 6 months Where lack of crushed rock remaining makes grading unviable:Place All on crushed rock road resheeting renewal program for prioritisation.

UNSEALED SHOULDERS Corrugations, scouring, depressions and potholes on unsealed shoulders must not exceed 50 mm in depth for a length of 20 m or A 14 days more. Corrugations, scouring, depressions and potholes on unsealed shoulders must not exceed 50 mm in depth for a length of 40 m or B 8 weeks more. Corrugations, scouring, depressions and potholes on unsealed shoulders must not exceed 50 mm in depth for a length of 50 m or C 6 months more. D 6 months Where lack of crushed rock remaining makes grading unviable: Place on crushed rock shoulder resheeting renewal program for All prioritisation.

KERB & CHANNEL Step or misalignment > 50mm A 12 weeks B 12 weeks C 12 weeks D 12 weeks

TRAFFIC ISLANDS Step or misalignment in island kerbing or paving > 50mm A 12 weeks B 12 weeks C 12 weeks D 12 weeks

OPEN DRAINS DOD Drain cross sectional area reduced by > 50%, or A 8 weeks drainage diverted out of drain path. B 8 weeks C 8 weeks D 8 weeks Where total length of open drains in Shire requiring cleaning exceeds 50 km / annum: All Place on open drain cleaning program for prioritisation.

Page A-6 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

PITS AND DRAINAGE STRUCTURES DPR Repair is required or drainage structure is non-functional. All 8 weeks Pit lintel, surround or lid repair required. All 8 weeks Pit lid missing. All 7 days

CULVERTS, PIPES AND PITS Low point completely blocked and flooding of road could result. A 7 days B 7 days C 14 days D 14 days Waterway area restricted by more than 50% A 8 weeks and flooding of road could result. B 8 weeks C 8 weeks D 3 months

SOAK PITS NSP Soak Pit has failed to operate and all water is bypassing the pit or not A 8 weeks soaking away and flooding of road is occurring. B 8 weeks C 8 weeks D 3 months

BRIDGES & MAJOR CULVERTS Structure unsafe for traffic or pedestrians. All 3 days

REGULATORY AND WARNING SIGNS > 50% sign legend illegible at 150 m under low beam or in daylight, or A 28 days B 28 days C 12 weeks D 12 weeks Sign missing A 3 days B 3 days C 3 days D 14 days

DELINEATORS > 10% on straights or 5% on curves of delineator installations per block missing or defective, relative to original installation and design A 28 days standards and a risk to public safety. (Refer AS1742.2)

> 20% on straights or 5% on curves of delineator installations per block missing or defective, relative to original installation and design B 28 days standards and a risk to public safety. (Refer AS1742.2) > 30% on straights or 5% on curves of delineator installations per block missing or defective, relative to original installation and design C 12 weeks standards and a risk to public safety. D 12 weeks (Refer AS1742.2)

Page A-7 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

PAVEMENT MARKINGS Pavement markings missing or illegible and constituting a traffic A 28 days hazard. B 28 days C 12 weeks

D 12 weeks

GUARD FENCE FGF Guard fence damaged constituting a traffic hazard. A 28 days B 28 days C 28 days D 28 days

FENCE AND HANDRAIL Defect constituting hazard to motorists or pedestrians A 8 weeks B 8 weeks C 3 months D 3 months

ELECTRICAL HARDWARE Traffic signals, pedestrian signals or other electrical devices which are All 3 days inoperative or defective and could present a danger to the public. Evidence of short circuit, bare wires, arcing or other similar unsafe All 24 hours situation.

SEALED PATHS Tripping hazard > 30 mm High Profile 14 days

Defect constitutes a hazard to pedestrians, and Shared Paths 8 weeks

Tripping hazard > 50 mm; or Residential 8 weeks Cracks > 30 mm wide and 1.0 m long Foreshore 8 weeks Parks 8 weeks Other 8 weeks Where > 3 bays of path segment in need of replacement; or Total area of footpath replacement in Shire exceeds 3,000 sq m / All annum: Place on path renewal program for prioritisation.

UNSEALED PATHS

(crushed rock or granitic sand) Deformation under a 1.2 m straight edge > 100 mm depth – footpaths. High Profile 14 days

Shared Paths 8 weeks

Defect constitutes a hazard to pedestrians; and Residential 8 weeks Tripping point > 60 mm – footpaths; or Foreshore 8 weeks Parks 8 weeks Other 8 weeks Where > 25% of path area in road block in need of replacement: All Place on path renewal program for prioritisation.

Page A-8 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

STREET LIGHTING (Shire controlled) Defective or missing luminaire affecting usage, safety A 28 days and passage of road or park users. B 28 days C 8 weeks D 8 weeks Evidence of short circuit, bare wires, arcing and other unsafe situation. All 24 hours

Page A-9 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

Appendix 3 – VicRoads Roads

Page A-10 Council Meeting - Item 2.2 Attachment 1 Monday, 9 May, 2011

Road Management Plan

VicRoads Roads

Demarcation of roads and other assets are based on the Code of Practice “Operational Responsibility for Public Roads”. For specific areas where this code does not provide a definitive answer and for areas that Council wants to maintain to a higher standard than VicRoads there will be individual agreements made.

DECLARED ROADS (VIC ROADS CONTROLLED) – as at 1st July 2004

ROAD ROAD NAME FROM - TO No. TYPE TYPE 405715 COOLART ROAD KL Fston/Flinders Rd - KL Fston/Flinders Rd 17km Sealed 405750 BONEO ROAD KL Pt Nepean Rd - KL Cook St 22km Sealed 405751 NEPEAN HIGHWAY KL Fway Off-Ramp - CL White Hill Rd 4km Sealed 405751 WHITE HILL ROAD CL Nepean Hwy - HL Arthurs Seat Rd 5km Sealed 405751 ARTHURS SEAT ROAD HL White Hill Rd - CL Arthurs Seat Rd 1km Sealed 405751 MORNINGTON-FLINDERS ROAD CL Arthurs Seat Rd - CL Cook St 13km Sealed 405754 BITTERN-DROMANA ROAD KL Fston/Flinders Rd - CL Red Hill Rd 9km Sealed 405754 DUNNS CREEK ROAD CL Red Hill Rd - KL White Hill Rd 6km Sealed 405754 NEPEAN HIGHWAY CL White Hill Rd - CL Marine Pde 3km Sealed 405756 KL Main St - CL Ellerina Rd 12km Sealed 405756 MARINE DRIVE CL Ellerina Rd - KL Pt Nepean Rd 4km Sealed 405757 FRANKSTON-FLINDERS ROAD CL Baxter/Tooradin Rd - CL Western Port Hwy 10km Sealed 405757 GRAYDENS ROAD CL Marine Pde - KL Graydens Rd 0.4km Sealed 405757 WATTS ROAD KL Graydens Rd - CL High St 3km Sealed 405757 FRANKSTON-FLINDERS ROAD CL High St - CL Boyds Rd 24km Sealed 405757 WOOD STREET CL Boyds Rd - CL Cook St 1km Sealed 405757 COOK STREET CL Wood St - CL Mton/Flinders Rd 2km Sealed 405758 STONY POINT ROAD KL Fston/Flinders Rd - CL Gatehouse Hump 6km Sealed 405759 ELIZABETH AVENUE KL Pt Nepean Rd - CL Elizabeth Ave 0.2km Sealed 405759 EASTBOURNE ROAD CL Elizabeth Ave - KL Boneo Rd 1.8km Sealed 405760 MAIN STREET CL Esplanade - KL Nepean Hwy 2km Sealed 405760 MORNINGTON-TYABB ROAD KL Nepean Hwy - KL Fston/Flinders Rd 13km Sealed 405761 OLD MOOROODUC ROAD KL MP Freeway - CL Old Moorooduc Rd 2km Sealed 405761 BALNARRING ROAD CL Old Moorooduc Rd - KL Fston/Flinders Rd 11km Sealed 405764 SAGES ROAD HL Moorooduc Hwy - HL Fston/Flinders Rd 1km Sealed 405764 BAXTER-TOORADIN ROAD HL Fston/Flinders Rd - HL Western Port Hwy 6km Sealed 406397 McCULLOCH STREET HL Pt Nepean Rd - HL Arthurs Seat Rd 0.8km Sealed 406396 ARTHURS SEAT ROAD CL McCulloch St - CL Mton/Flinders Rd 8km Sealed 406450 MOOROODUC HIGHWAY CL Balnarring Rd - CL Baxter/Tooradin Rd 10km Sealed 406451 406500 406501 NEPEAN HIGHWAY CL Fway Off-Ramp - CL Humphries Rd 18km Sealed 406502 406600 406601 POINT NEPEAN ROAD KL National Pk Ent - CL Nepean Hwy 27km Sealed 406602 406603 406700 MORNINGTON PENINSULA FREEWAY CL Balnarring Rd - KL Boneo Rd 20km Sealed 406701 LONSDALE STREET KL Pt Nepean Rd - HL Bayview Rd 0.8km Sealed 406702 JETTY ROAD KL Eastbourne Rd - KL Freeway Exit 0.3km Sealed 406869 WESTERN PORT HIGHWAY HL Baxter/Tooradin Rd - CL Marine Pde 10km Sealed Note: CL = Centre Line, KL = Kerb Line, HL = Hold Line