HOUSING IMPLEMENTATION STRATEGY (September 2017)

Summary of position on Large and Medium Sites: Q2 2017/18 (Reflects progress on planning applications as at 30 September 2017) (Reflects completion data as at 30 September 2017

Site Deliverables Progress on Planning Permissions Timing Progress on Completio Suitability Availability Achievability (1 April 2017 Trajectory) HARD COMMITMENTS: LARGE Land north of 137 units 13/00783/REM Approved 17 August 2017. To be added to the 2018 As at 30 September 2017: 137 Site is acceptable Persimmon Homes Housebuilder is Peacock Lane, Submission of details of layout, scale, appearance, Trajectory n/s as permission & Redrow Homes involved. ( access and landscaping for the erection of 137no. granted. Phasing: phase start of Parish) dwellings accessed from Peacock Lane with associated development for access roads, pedestrian and cycle links, car parking, starting in 2018/19 (SALP SA2) landscaping (including drainage) and associated works (after rest of Jennetts pursuant to outline planning permission 98/00288/OUT Park development), at (623523). (October 50dpa (on the basis of 2015: amended plans received increasing the number of a single housebuilder, units from 106 to 137 dwellings). (August-October 2016: on a site less than 300 amended plans received). [Will be units). added to 2018 Commitments] For residual part of site see soft commitments below Amen Corner 377 units (inc 14/00315/OUT. Approved with s.106 13 March 2015. 38 completions expected in As at 30 September 2017: Site is acceptable Site is being Site is being marketed North, Binfield affordable) (Reserved Matters to be submitted within 5 years of 2017/18 127 u/c as allocated developed by on housebuilder permission, i.e. March 2020. Development to be begun 100 in 2018/19 250 units n/s. through SALP Bellway Homes & website - launched in (SALP SA6) OSPV and SANG no later than 2 years of approval of last reserved 100 in 2019/20 (Policy SA6), and Ashberry Homes. 2016 (May 2016). matters). 100 in 2020/21 has outline & Primary School Outline planning application for up to 380 residential 39 in 2021/22 reserved matters Market and cost units, a 1 form entry primary school and associated approval. factors were accesses, open space, landscaping and Suitable considered through Alternative Natural Greenspace (SANG) (means of discussions on the access to be considered, all other matters reserved). s.106.

Reserved matters 15/00872/REM. Approved 18 March The Council has been 2016. proactive in joint Submission of details of access, appearance, strategic transport landscaping, layout and scale for the erection of a one- work with Wokingham form entry primary school, with associated play space Borough which led to a and car parking, pursuant to outline planning permission successful bid to 14/00315/OUT. secure the full funding for a major Reserved matters 15/00873/REM. Approved 24 June improvement to the 2016. Coppid Beech Submission of details of layout, scale, appearance and Roundabout from the landscaping for the erection of 377 dwellings and the Government's Local laying out of open space and Suitable Alternative Natural Pinch Point Greenspace (SANG) pursuant to outline planning infrastructure fund. permission 14/00315/OUT. The delivery of this scheme helps unlock Applications for conditions: Wokingham's strategic - 15/00168/COND. Details acceptable 18 March 2016. sites and Amen Corner Condition 6(Masterplan) and 7 (Design Code) of Outline North and South. Planning Permission 14/00315/OUT. - 16/00154/COND. Pending consideration. Phasing: as a house 21(CEMP), 22 (energy demand), 30 (Acoustic builder is involved and assessment), 10 (Archaeological works) of planning discussions are permission 14/00315/OUT. underway on detailed - 16/00215/COND. Pending consideration. matters (reserved 04 (Construction Phasing), 12 (Landscape), 19 (Surface matters subsequently Water Drainage), 20 (Foul Water Drainage) and 27 approved), phase at (Biodiversity) pursuant to planning permission 100 dph (as site is over 14/00313/OUT. 300 units, with one 16/00239/COND - pending consideration housebuilder), with 38 13 (Topography and Trees) and condition 14 (Tree in first year 2017/18 protection) to planning permission 14/00315/OUT. 16/00273/COND pending consideration NB: residual balance of Non material amendment to application 15/00873/REM 20 units for Amen for amendment to the approved details of landscaping. Corner North is listed 16/00274/COND Approved 26.01.2017 under soft Details to pursuant to condition number 22 (Energy commitments. Demand Assessment) to planning permission Land at Blue 400 units (inc 16/00020/OUT. Approved with legal agreement 15 June 25 completions expected N/A at this stage, as reserved Site is acceptable Luff Developments Developer is involved. Mountain, Binfield affordable) 2016. Approval of reserved matters for first phase within 2018/19; matters approval required for as allocated Reserved matters and 3 years i.e. June 2019. Approval of reserved matters for 75 in 2019/20; housing. through SALP condition approval (SALP SA7) Primary School other phases within 8 years, i.e. by June 2024.) 75 in 2020/21; Learning village u/c (Policy SA7), and required before site Hybrid planning application seeking (a) outline planning 75 in 2021/22; has outline can be developed. Secondary School permission for 400 dwellings, a community facility of up 75 in 2022/23; & permission (for to 1,077 sq m, sports provision and open space (all 75 in 2023/24 housing). Information SEN matters reserved except for means of access) and (b) full accompanying planning permission for an all-through school (Learning planning application: Multi functional Village) providing nursery, primary, secondary, post 16 Environmental community hub and SEN facilities, approximately 13 ha of Suitable Statement (January Alternative Natural Greenspace (SANG) land, two 2016). Para. 5.6.28 Football ground vehicular accesses from Temple Way, a spine road sets out that it is through the development and a school drop-off/SANG expected that the first OSPV and SANG car park. residential units will be delivered in 2017 and - 16/00895/NMA. Approved 7 October 2016. the Development will Non-material amendment to planning permission be completed in 2025. 16/00020/OUT to change cladding of the courtyard at the upper stories, change the coping of the parapet, and Phasing: Given that omit the large sports hall rooflights which were reserved matters and previously visible above the parapets condition approval for 16/00952/FUL approved 23 February 2017 housing needed before Section 73 application for the variation of conditions 04 development can (approved plans) and 60 (sustainable drainage) of hybrid commence, planning permission 16/00020/OUT for (a) outline completions in 2017 planning permission for up to 400 additional dwellings, a may be optimistic. community facility of up to 1,077 sq m, sports provision Therefore, phase first and open space (all matters reserved except for means completions for of access) and (b) full planning permission for an all- 2018/19 (25 units), through school (Learning Village) providing nursery, then 75 dpa (on the primary, secondary, post 16 and SEN facilities, basis of a single approximately 13 ha of Suitable Alternative Natural housebuilder, on a site Greenspace (SANG) land, two vehicular accesses from more than 300 units). Temple Way, a spine road through the development and a school drop-off/SANG car park. (Note for clarification: this application seeks a revision to the drainage proposals for the Learning Village). 15/00007/SCO: response issued 2nd June 2015. Conditions applications: - 16/00144/COND. Approved 1 September 2016. Details pursuant to conditions 18 (archaeology) and 45 (part fencing materials Phase 1). - 16/00149/COND. Approved 27 March 2017. Details pursuant to condition 11 (CEMP). - 16/00184/COND. Approved 8 May 2017. Details pursuant to conditions 13 (Planting Landscaping) and part 54 (Landscaping). 16/00232/COND Approved 10 July 2017 Binfield Nursery, 24 units 13/00966/FUL. Approved with a s.106 1st April 2015. 20 completions expected in As at 30 September 2017: Site is acceptable The site is being Housebuilder is Terrace Road (Application to be implemented within 3 years) 2017/18, & 24 units u/c as allocated developed by involved. Site has North, Binfield Erection of 5 no. five bedroom, 7 no. four bedroom, 2 no. 4 in 2018/19 through SALP Spitfire Properties. reserved matters and three bedroom and 10 no. two bedroom dwellings with (Policy SA1), and condition approval. (SALP SA1) associated landscaping and vehicular access from Knox has planning Green following demolition of existing buildings, and permission. Phasing: as alterations to wall within the curtilage of a listed building. construction started, (24 in total). phase 20 completions in 2017/18 and 4 in 13/00967/LB. Granted 17th October 2014. 2018/19 Application for listed building consent for alterations.

15/00989/NMA. Agreed 26th October 2015. Non material amendment to planning permission 13/00966/FUL for the removal of requirement under conditions 25 and 26 of planning permission 13/00966/FUL.

16/00374/FUL. Approved 13 October 2016. Section 73 application for the variation of condition 2 (approved drawings) of planning permission 13/00966/FUL for the erection of 5 no. five bedroom, 7 no. four bedroom, 2 no. three bedroom and 10 no. two bedroom dwellings with associated landscaping and vehicular access from Knox Green following demolition of existing buildings, and alterations to wall within the curtilage of a listed building.

16/00734/NMA - Agreed 26 August 2016 Non material amendment to planning permission 13/00966/FUL for the following:- 1. Amendments to window size and locations. 2. Amendments to door sizes, types and locations 3. Addition of chimneys 4. Amendments and additional brick detailing elevations 5. Alteration to cill and header detailing to window and doors 6. Alteration to garage roofs.

Conditions applications: - 15/00095/COND. Details acceptable, 17th June 2015. Conditions 37 & 38 of 13/00966/FUL. - 15/00097/COND. Details acceptable, 6 July 2015. Condition 21 of 13/00966/FUL. - 15/00098/COND. Details acceptable, 3rd August 2015. Conditions 3, 4, 5 & 6 of 13/00967/LB. - 15/00099/COND. Details acceptable 17th December 2015. Conditions 5, 32 & 34 of 13/00966/FUL. - 15/00105/COND. Details acceptable 17th December 2015 Conditions 3 4 13 14 16 17 22 23 24 25 26 Jennetts Park 1,350 dwellings (inc Outline permission 98/00288/OUT granted May 2004. 28 completions expected in Primary School opened Site is acceptable The site is being Housebuilder involved, (Peacock Farm), affordable) 2017/18. September 2011. as has permission developed by and site is under Bracknell Reserved matters approved for all housing land parcels 22 in 2024/25. for 1,250-1,500 Persimmon/Redrow construction. 1,300 Neighbourhood south of Peacock Lane. Community Centre opened residential units. , and is already completions to date. Centre 2011. - Outline under construction. Neighbourhood centre Neighbourhood Centre shops (11/00878/REM) gained Completions during: application (11/00878/REM: 28 Primary School reserved matters approval May 2012. 2007/08: 153 98/00288/OUT units) is u/c. Land east Submission of details of siting, design, external 2008/09: 154 granted May of Sparrowhawk Way 37ha Country Park appearance, access and landscaping for the erection of 2009/10: 145 2004. (14/00488/REM) is (OSPV and SANG) retail accommodation (506 sq m) with 12no. 2 bedroom 2010/11: 168 - Most of the pending consideration. and 4no. one bedroom flats above, one flat over garage 2011/12: 136 housing parcels 0.5ha of land for (FOG) unit and 11 houses with associated parking and 2012/13: 179 have reserved Key infrastructure such small commercial servicing space pursuant to outline permission 2013/14: 235 matters approval. as roads and country units 98/00288/OUT (623523). (28 units) 2014/15: 93 park in place. Primary 2015/16: 37 school and community Public House 14/00488/REM (last east of Sparrowhawk Way), pending centre opened in consideration. Total completions to date: 1,300 September 2011. Park and Ride site Submission of details of layout, scale, appearance, access and landscaping for the erection of up to 4no. As at 30 September 2017: Phasing: commercial/community (A1, A2, A3, A4, A5, D1, D2) 12 complete (Q2) Neighbourhood centre units (420 sq m) with 10no. 2 bedroom and 4no. one 16 u/c is u/c (12 units of 28 bedroom flats above, 3no. flats over garage (FOG) units 22 n/s with permission and 6no. houses with associated parking and servicing completed), therefore space pursuant to outline permission 98/00288/OUT phase 28 units as per (623523) on site identified on masterplan for public availability proforma house. (23 units) during 2017/18. As (Adjacent to Parcel's H12 & H14) remainder of units are subject to a pending 13/00155/COND approved 20 July 2017. Amended application, phase masterplan to delete hotel/conference centre and B1/B2 remainder of floorspace, except for 0.5ha site for small commercial completions for units. 2024/25. (Also see SALP Policy SA2 in relation to land north of Peacock Lane, allocated for 182 dwellings with 137 approved in August 2017 under 13/00783/REM).

Winchester House Residential (inc Outline permission granted (10/00434/EXT) for the 100 completions expected in As at 30 September 2017: Site is acceptable Site is being House builder involved, Bracknell Town affordable) redevelopment of the Town Centre September 2010 2019/20, 311 units u/c as outline and developed by and demolition of Centre 100 in 2020/21, & reserved matters Comer Homes, and Winchester House Retail Section 73 application (12/00476/OUT) to amend 111 in 2021/22. approval. is under completed. Site is planning permission 10/00434/EXT granted May 2013. construction. listed under 'future Leisure facilities Note: time to submit reserved matters is now time sites' part of expired (condition 02 of 12/00476/OUT refers to reserved housebuilder website matters no later than 21 December 2014). Therefore, (April 2016). only Winchester House has reserved matters approval for residential development. All other town centre Phasing: Demolition of residential taken out of trajectory. Any sites which come site is complete. Plans forward will be treated as windfalls. show 9 towers, built as one structure rather Reserved Matters than separate blocks, 13/01068/REM. Approved with legal agreement 7th July but could be built out in 2014. sub-phases, at c. 100 Submission of details of design, access, appearance, pa. Therefore, phase landscaping, layout and scale for redevelopment of first completions Winchester House identified as Blocks NW3.1, NW3.2, 2019/20. NW3.3. Demolition of Winchester House and redevelopment to provide retail A1-A3 Class, D2 gym and 311 residential units, car parking, new public realm, landscaping and highway works. This reserved matters application is submitted pursuant to outline planning permission 12/00476/OUT.

Applications for conditions: 15/00250/COND. Part approved, 3 June 2016. Details pursuant to conditions 2 (materials and external surface) and 5 (car park management) of planning permission 13/01068/REM. 16/00014/COND. Approved, 2 June 2016. Discharge of conditions 3 (Lighting), 4 (Public Realm) and 6 (Levels) of planning permission 13/01068/REM. Garth Hill School, 65 units (net 64 as Site divided into two parts. For residual part of site, see Demolition of 1 unit in 2017/18. Completions during 2015/16: 65 Site is acceptable Site developed by September 2017: Sandy Lane, demolition of a soft commitments. as allocated apartments completed, Bracknell caretakers As 30 September 2017: through SALP Homes. but demolition of (Clement House) bungalow) 13/00074/FUL Approved with Legal Agreement June Demolition 1 unit n/s (Policy SA1), and existing caretakers 2013. has planning bungalow not started. (Part of SALP SA1) (This is a C3 Erection of 65no. elderly extra care apartments with permission. specialised use). associated access, facilities, landscaping and parking, following demolition of caretakers house on Sandy Lane

Land at Bowman's 36 dwellings 15/00366/FUL. Approved with legal agreement 29 June 5 completions expected in As at 30 September 2017: Site is acceptable Site is owned by Phasing: phase 5 Court, Dukes Ride, 2016. (Expires June 2019). 2017/18; 36 u/c as allocated Wellington College. completions for Erection of 36 dwellings (9no open market houses and 15 in 2018/19 & through SALP 2017/18; 15 for 27no dwellings to be retained by Wellington College to 16 in 2019/20 (Policy SA3) and 2018/19 and 16 for (SALP SA3) accommodate teachers) with associated vehicle access has permission. 2019/20 (including formation of a new access onto Dukes Ride), parking, landscaping and open space.

16/00788/NMA. Approved 31 August 2016. Application for non-material amendment to planning permission 15/00366/FUL for the following:- - Site plan updated to show that plots 2, 3, 7 and 8 are 3 bedroom properties - Plot 6: utility room window replaced by door - Plot 9: chimney added

Conditions: - 16/00163/COND. Approved 16 August 2016. Condition 28 (archaeology). - 16/00272/COND Pending Consideration Details pursuant to conditions 13 (Tree Protection), 15 (Arboricultural Protection Measures), 16 (Construction Method Statement) and 17 (Hard Surface Removal) of planning permission 15/00366/FUL.

Land at Transport 1,000 dwellings (inc 13/00575/OUT, approved with s.106 30 Jan 2015. (8 10 completions expected in As at 30 September 2017: 1000 Site is acceptable Site is owned by Requires reserved Research affordable) years to submit reserved matters, i.e. by Jan 2023). 2018/19, n/s as allocated Legal & General matters and condition Laboratory (TRL), Outline application (including details of access from Nine 75 in 2019/20, through SALP (L&G) approval before Crowthorne Neighbourhood Mile Ride and Old Wokingham Road) for the 100 in 2020/21, (Policy SA5), and development can Centre comprehensive redevelopment of the former Transport 100 in 2021/22, has outline commence. (SALP SA5) Research Laboratory (TRL), comprising demolition of 100 in 2022/23, approval. Primary School existing buildings (excluding the new TRL headquarters 125 in 2023/24, Market and cost building), the erection of up to 1000 dwellings, 125 in 2024/25, factors were Multi functional neighbourhood centre (comprising use classes A1, A2 150 in 2025/26 & 215 in the next considered through Community Hub and A3), retail unit (A1 / A2 / A3), primary school and Plan Period discussions on the associated playing fields, community centre, care home, s.106. Care Home/Nursing and municipal depot, together with public open space, Home Suitable Alternative Natural Greenspace (SANG), The Council has surface water attenuation areas, landscaping, formation successfully secured Replacement of public highways, vehicular access and parking. funding from the Enterprise Centre Thames Valley Local Non-material amendments: Economic Partnership Depot Site - 15/00944/NMA agreed 21 October 2015. to deliver a major Amendment to various pre commencement conditions to junction improvement OSPV and SANG confirm what information needs to be submitted to and for the Coral Reef approved by the LPA prior to the commencement of Roundabout. This demolition and clearance works. improvement is - 16/00521/NMA agreed 2 August 2016. required to support the Change the wording of conditions 06, 25 and 30 to allow delivery of the TRL site work on the SANG to commence prior to the approval of and considerably helps design codes, the foul water drainage strategy and the with the overall viability provision of a temporary access. of the TRL - 16/00698/NMA. Agreed 24 November 2016. development by Application for non material amendment to planning removing an permission 13/00575/OUT to amend condition 16. infrastructure obstacle - 16/00825/NMA. Pending consideration. to the sites delivery. Non material amendment for an amendment to condition 5 (approved drawings) of planning permission Phasing: Taking 13/00575/OUT. account of the need to demolish existing Reserved Matters: buildings, and taking 16/01075/REM Pending consideration. Submission of account of the latest details of scale, layout, appearance, access and information from landscaping relating to the Suitable Alternative Natural Developer, put first Greenspace (SANG) pursuant to outline planning completions at 2018/19 permission 13/00575/OUT. (10 units) then 17/00401/REM Approved 17 August 2017. Submission of remainder at 100- details of scale, layout, appearance, access and 150dpa (as the site is landscaping relating to the Phase 1 residential phase, more than 300 units). comprising 207 dwellings, pursuant to outline planning permission 13/00575/OUT.

TRL - Conditions Approval of conditions: - 15/00234/COND: approved 5th January 2016. Condition 4 & 19. - 16/00118/COND. Approved 5 August 2016. Conditions 4 & 19. - 16/00119/COND. Details acceptable 13 June 2016. Condition 18. - 16/00127/COND. Approved 27 July 2016. Part (b) of condition 28. - 16/00177/COND. Approved 31 August 2016. Condition 18 (Archaeological Work). - 16/00187/COND. Pending consideration. Condition 6 (master plan and design code). - 16/00195/COND. Approved 19 September 2016. Condition 31 (private hydrant scheme). - 16/00198/COND. Pending consideration. Condition 25 (foul water drainage). - 16/00200/COND. Approved 22 November 2016 Condition 19 (construction and environmental plan). - 16/00201/COND. Approved 29 September 2016. Condition 26 (remediation strategy). - 16/00213/COND. Approved 29 September 2016. Condition 18 (programme of archaeological works) - 16/00222/COND. Approved 12 October 2016. Condition 11 (tree retention). - 16/00257/COND. - Approved 06 Jan 2017. Condition 11 (tree strategy) - 16/00241/COND - Pending consideration. Conditions 23 (Surface Water Drainage Strategy), 24 ( Soakaways) and 33 (Level 3 Flood Risk ) Land west of Alford 106 units (net) 15/00026/SCR, decision issued 26 November 2015. 10 completions expected in As at 30 September 2017: 106 Site is acceptable Bloor Homes House builder is Close, Sandhurst Request for screening opinion under Regulation 5 of The 2018/19; n/s as permission involved (SALP SA3) Town and Country Planning (Environment Impact 50 in 2019/20, & granted. Assessment) Regulations 2011. 48 in 2020/21, Information 16/00372/FUL, Approved 7 August 2017. Phased (full) accompanying the application for erection of 108 dwellings, creation of new current planning access off High Street, Sandhurst, the construction of a application states community facility and provision of public open space (Planning Statement, with associated infrastructure following demolition of two April 2016, para. 5.16) existing dwellings. [Will be added to 2018 that the site could Hard Commitments] make a contribution towards the 5 year housing land supply, but no further information is provided. See: http://www.alfordclose. co.uk/ Phasing: as a housebuilder is involved phase first completions for 2018/19, then remainder at 50dpa (on the basis of a single housebuilder, on a site less than 300 Area 1 211 units - 16/01195/FUL Land East Of Avery Lane and North Of To be added to the 2018 As at 30 September 2017: 211 Site is acceptable Various Variousi) land owners. (part of CSDPD Watersplash Lane - Approved 20 July 2017. Erection of Trajectory n/s as allocated Western There is a need to CS5/SALP SA9) 116 dwellings with associated landscaping, infrastructure through SALP Consortium: Newell address delivery of (see soft works and open space of public value served by (Policy SA5), and Green Area infrastructure across commitments for vehicular access from north-south link road and has permission (Millgate, Harrow the site. A consortium residual) pedestrian/cycle link to Watersplash Lane. - Estates, and is established for 16/01253/FUL Land South Of Fairclough Farm - Kitewood Newell Green Area. Approved 20 July 2017. Erection of 52 no. dwellings with Investments) associated parking, landscaping and open space and Masterplan for Central vehicular access onto Newell Green. - Area published 16/01274/FUL Land At Watersplash Lane -approved 20 February 2015: July 2017. Demolition of existing buildings and erection http://consult.bracknell- of 43 dwellings with associated accesses (to land to west forest.gov.uk/file/33447 and to Watersplash Lane), parking and landscaping. 10. Page 42. Also sets [Sites to be added to 2018 Commitments as hard out development will commitments] be progressed in 3 phases, on the basis of 3 developers operating (Phase 1: 325 dwellings, Phase 2: 241 dwellings, Phase 3: 248 dwellings) in the following phases (814 total): 2015-16: 50 2016-17: 150 2017-18: 150 2018-19: 150 2019-20: 150 2020-21: 164 Development of the Warfield site requires a new north/south link road through the site. This has received investment through the ‘local growth’ funding pot from the Thames Valley Local Enterprise Partnership. Phasing: delivery timings set out within masterplan are considered to now be outdated. However, on- going work with HCA/ATLAS and landowners/developers to bring forward Warfield Area 2 750 dwellings (inc 13/01007/OUT (hybrid application). Approved with legal 3 completions in 2015/16; Completions during: Site is acceptable Site being Housebuilder involved, (part of) affordable) agreement 28 October 2014. (6 years to submit 85 completions in 2016/17; 2015/16: 3 units (Phase 1) as allocated developed by and site is under (Woodhurst Park) (65 units are C3 reserved matters, i.e. by October 2020. Development to 215 in 2017/18; through SALP Berkeley, and is construction. Phases specialised use). be begun no later than 3 years of approval of last 73 in 2018/19; Completions during 2016/17: (Policy SA5), and under construction. 1 and 3 being (CSDPD CS5/SALP reserved matters). 72 in 2019/20; Phase 1: 84 (phase complete) has outline marketed through SA9) Primary School Hybrid application for residential development of up to 72 in 2020/21; Phase 3: 1 approval (part of housebuilder website 750 dwellings including 60 senior living units (minimum 72 in 2021/22;; Total complete: 88 which is full), plus (May 2016). North/South link of 675 dwellings). New two form entry Primary School; 72 in 2022/23; Total u/c: 215 some reserved road Formal and Informal open space; Two new access points 72 in 2023/24 & Other phases: 377 n/s matters [Application off Harvest Ride, and SANG (outline element - all 14 in 2024/25 applications. 13/00575/OUT. matters reserved except means of access to the As at 30 September 2017: Condition 05, min 675 development). Phase 1 residential development of 87 Phase 3: 17 complete (Q1) dwellings. If min built dwellings and provision of a link road between Harvest 10 complete (Q2) 66 u/c out, would not affect Ride and Forest Road. Phase 4a (senior living): 65 u/c current 5 year HLS, but Phase 4a (residential): 58 u/c may affect longer term Phase 1 (The Maples): details approved under outline for Phase 4b: 49 u/c trajectory towards the 87 units. Phase 5: 13 u/c end of the plan period.] Phase 2: 14/01275/REM. Approved March 2015. 108 n/s Reserved matters for the erection of a new two-form Total complete: 114 Total Market and cost entry primary school (including nursery), with associated u/c: 251 Other factors were playing field and car parking. phases: 385 n/s considered through Phase 3: 15/00163/REM. Approved 14 September discussions on the 2015. s.106. Reserved matters for Phase 3 (comprising 93 dwellings and public open space). Development of the - 16/00515/REM. Approved 18 October 2016. Warfield site requires a Submission of details of landscaping for Phase 3 of the new north/south link development at land north of Harvest Ride, Warfield, road through the site. comprising 93 dwellings and public open space, This has received pursuant to outline planning permission 13/01007/OUT. investment through the Phase 4a: 15/00646/REM. Approved 25 February 2016 ‘local growth’ funding Erection of 65 Senior Living dwellings with associated pot from the Thames access, car parking and landscaping Valley Local Enterprise - 15/00647/REM. Approved 8 January 2016. Access, Partnership. appearance, landscaping, layout and scale for phase 4A comprising the erection of 58no.apartments (36 x 2 Clause in s.106: no bedroom and 22 x 1 bedroom) more than 110 - 16/01041/REM Pendin Consideration - Submission of practical completions details of landscaping for Phase 4A pursuant to outline until primary school planning permission 13/01007/OUT. conditions fulfilled - Phase 4b: 16/01123/REM Approved 3 April 2017. primary school opened Submission of details of access, appearance, in September 2017 landscaping, layout and scale for Phase 4B of the development at land north of Harvest Ride, Warfield Previous comprising 49 dwellings with associated parking, roads correspondence from and temporary turning facilities pursuant to outline (August 2015) advising planning permission 13/01007/OUT. depending on market Phase 5; 17/00054/REM pending consideration. conditions 4-8 S b i i f dt il f completions per month Warfield Area 2 - Approval of conditions: Conditions 13/01007/REM (Phase 1): 10, 18, 21, 28, 30, 32, 34, 35, 38, 42, 43, 46 - 16/00102/COND. Pending consideration. Details pursuant to conditions 28 (Flood Plain Modelling) and 30 (Bridge 3) of planning permission 13/01007/OUT

14/01275/REM Phase 2 (School). Approved 13 March 2015 - Submission of details of scale, layout, appearance, access and landscaping for the erection of a new two-form entry primary school (including nursery), with associated playing field and car parking accessed from link road from Harvest Ride, together with a landscape hub on the east-west greenway, pursuant to outline planning permission 13/01007/OUT. 16/00172/COND pending consideration - Details pursuant to condition 16 (hard and soft landscaping) of Planning Permission 14/01275/REM (Revised scheme).

15/00163/REM (Phase 3): 3, 4, 6, 16, 18, 21, 25, 26, 29, 32, 34 - 16/00003/COND. Approved 10 March 2016. Condition 2(materials). - 16/00075/COND Approved August 2016. Conditions 03 (external lighting), 04 (noise mitigation along Harvest Ride) and 06 (cycle parking) - 16/00206/COND Pending Consideration. Condition 32 (Surface Water Drainage Scheme) and 34 (Foul Water Drainage Scheme)

15/00646/REM (Phase 4a Senior Living): - 16/00099/COND. Pending consideration. Conditions 16 (Design and Access Statement), 18 (Site Organisation Working Method Statement), 21 (Finished Floor Levels), 25 (Access Details), 26 (Construction Access), 29 (Compensatory Flood Plain Storage), 32 (Surface Water Drainage Scheme) and 34 (Foul Water Drainage Scheme) of planning permission 13/01007/OUT. - 16/00204/COND. Pending consideration. Conditions 32 (sustainable drainage scheme) and 34 (foul water drainage scheme). - 16/000053/COND. Approved 28 April 2016. Condition 3 (materials). - 16/00081/COND. Approved Nov.2016. Condition 06 (noise mitigation), 08 (parking facilities), 10 (disabled pedestrian access scheme) and 12 (ventilation and extract system details) 16/00082/COND A d A t 2016 C diti Cranbourne net = 0 (as 09/00605/FUL approved 10 December 2009. 1 completion expected during As at 30 September 2017: Site is acceptable Site is being Site is under Corner, Forest replacement Erection of 1 no. detached dwelling and garage, following 2017/18 1 unit u/c as permission developed by construction. Road, dwelling) demolition of existing dwelling and outbuildings and (demolition counted in 2009) granted. Donford Ltd insertion of underground mineral water storage tank Phasing: as site is (Included in large room (Amendment to 07/00583/FUL). under construction, sites, as site area phase completion for over 1ha). 2017/18. Orchard Lea, 14 flats 17/00251/FUL Approved 18 August 2017. Part 14 completions expected in As at 30 September 2017: Site is acceptable Danescroft Infrastructure provision Winkfield Lane, redevelopment of existing office buildings to provide 14 2018/19. 14 u/c as permission (Orchard Lea) Ltd, secured through s.106. Winkfield residential units (Class 3) together with garages, granted. sitework Site was marketed by balconies, hard and soft landscaping, entrance gates, undwerway. Savills following issue open space and reconfiguration of car park and closure of planning permission of entrance off Winkfield Lane. 15/00547/FUL. Approved 17 September 2015 (expires Phasing: phase 14 September 2018) units in 2018/19. Part redevelopment of existing office buildings to provide 14 residential units (Class C3) together with garages, balconies, hard and soft landscaping, open space and reconfiguration of car park and closure of entrance off Winkfield Lane.

Conditions: - 16/00178/COND. Approved 31 August 2016. Condition 17 (demolition method statement). - 16/00218/COND. Approved Nov 2016. Conditions 10 (site organisation), 11 (working method statement) & 20 (energy demand assessment).

16/01280/FUL - pending consideration. Section 73 application to vary condition 02 (approved plans) of planning permission 15/00547/FUL for the part redevelopment of existing office buildings to provide 14 residential units with associated works. [For clarity the changes sought comprise internal and external alterations to buildings, new entrance gates, revised parking layout and the location of bin and cycle store].S

Kingswood, Kings 59 flats 16/00732/FUL. Approved at committee 19 January 8 completions expected in As at 30 September 2017: Site is acceptable Millgate Infrastructure provision Ride, Ascot Ancillary gym & 2017, subject to s106. 2017/18; 16 units u/c as permission Developments Ltd. secured through s.106. swimming pool. Demolition of existing office buildings and redevelopment 24 in 2018/19; 43 n/s granted. Site was marketed by to provide 59 residential units (Class C3), together with 20 in 2019/20 & Savills following issue detached garages, associated internal estate road, car 7 in 2020/21 of planning permission parking, landscaping and open space. Phasing: as site under 13/00858/FUL approved with legal agreement, 12 August construction phase 8 2014. (Application expires August 2017). units in 2017/18, 24 in Demolition of existing office buildings and redevelopment 2018/19, 20 in 2019/20 to provide 38no. residential units (Class C3) together and 7 in 2020/21. with garages, associated internal estate road, car parking, landscaping, open space and ancillary gym and swimming pool.

16/00028/SCR. EIA not required. 25 May 2016. Request for screening opinion under Regulation 5 of The Town and Country Planning (Environmental Impact Assessment) Regulations 2011 (relates to redevelopment with 59 units)

Conditions applications: - 14/00120/COND. Details acceptable September 2014. Condition 16 (land phase 1 desk top study). - 16/00168/COND. Approved Jan 2017. Conditions 8 (site clearance), 21 (biodiversity mitigation) & 23 (reptiles). - 16/00242/COND. Approved Nov 2016. Condition 19 (Site Clearance - bat survey) 16/00732/FUL Approved 3 April 2017. Demolition of existing office buildings and redevelopment to provide 59 residential units (Class C3), associated internal estate road, car parking, landscaping and open space. (38 units counted under Hard Commitment 13/00858/FUL, additional units will be added to 2018 Commitments) The Brackens, 56 units 16/00171/PAC. Granted 14 April 2016 32 completions expected in As at 30 September 2017: Site is acceptable c/o Brooks Murray London Road, Application for prior approval for the change of use of 2018/19 56 units n/s as permission Winkfield existing office (Class B1) to residential use (Class C3) [Additional dwellings permitted granted (allowed comprising 32 apartments. under 16/01266/FUL to be added on appeal). NB: Class O, of Part 3 (Changes of Use) of Schedule 2 to 2018 Trajectory) of the General Permitted Development Order (see SI 2015 No. 596, amended by SI 2016 No. 332) sets out that development is permitted, subject to the condition that it must be completed within a period of 3 years starting with the prior approval date. Therefore, this application needs to be completed by April 2019.

16/01242/OUT withdrawn. Hybrid planning application for a residential development comprising: DETAILED application for partial demolition of existing buildings. Retention and conversion of Brackens House to provide 5 no. apartments with associated parking, tree removal and improvements to existing access. 16/01266/FUL Appeal allowed 28 July 2017. Residential development comprising partial demolition of existing buildings, retention and conversion of Brackens House to provide 5 no apartments and construction of 51 new dwellings, with associated parking, tree removal and landscaping and improvements to existing access to London Road. 32 units counted under 16/00171/PAC (soft commitment) [Will be added to hard commitments in 2018 Commitments]

2015/16 completions: 242 (net) 2016/17 completions: 201 2017/18 completions to date: 39 U/C September 2017: 669 net (Large sites/hard commitments)

HARD COMMITMENTS: MEDIUM LandSITES to rear of 5 units 16/00049/FUL Approved 21 April 2016. Section 73 SITE COMPLETE 2017/18. Completions during 2016/17: 1 Site is acceptable Site developed by Site complete. Murrell Cottage, application for the variation of conditions 02 (approved As at 30 September 2017: 2 as permission JPP Land Ltd Murrell Hill Lane plans) and 28 (Sustainable Drainage Scheme) of completions (Q1) 2 granted. (Fitzgerald Park) planning permission 15/00209/FUL (for the erection of completions (Q2) 5no. 5 bedroom dwellings with associated works) to Site complete provide a revised drainage strategy and for minor internal and external amendments to the design of the proposed buildings including changes to fenestration and the addition of a single-storey element to the house on Plot 5 Land adj 7 units 09/00141/FUL 12/00492/EXT Erection of 2no. 2bed 7 completions expected in As at 30 September 2017: 7 n/s Site is acceptable Site is being Housebuilder involved. Medical Centre, flats and 5no. 1bed flats. 2020/21 and has planning developed by Phasing: 7 expected Leppington permission Kingfisher 2020/21. Residential Brackworth, Broad 7 units (net) 16/00230/FUL Erection of 6 no 2 bedroom and 2 no 1 7 completions expected in As at 30 September 2017: 7 n/s Site is acceptable Site is being Phasing: 7 completions Lane bedroom flats with associated parking, cycle shed, 2019/20 and has planning developed by Mr M expected in 2019/20 amenity space, bin store and access following demolition permission Goyal of existing dwelling. Blythe House, 5 units 15/00023/FUL Conversion of existing common room and 4 completions expected in Completions during 2015/16: 1 Site is acceptable Site is being Housebuilder involved. kitchen on ground floor to 5 no. apartments (3 no. studio 2017/18 As at 30 September 2017: 4 u/c and has planning developed by 1st unit completed Square apartments and 2 no. 1 bed flats) - part retrospective. permission Blythe House 2015/16; phase (Bracknell) remainder for 2017/18. Discussions on-going with developer.

Avoncrop, Eastern 14 houses 15/00456/FUL. Approved with legal agreement 30 June 14 completions expected (March 2015 site preparation Site is acceptable Belgrave Homes Housebuilder involved. Road, Bracknell 2016. (Application expires June 2019). 2019/20. works) as allocated Site is on housebuilder Erection of 3 no. 3 bedroom houses and 11 no. 4 through SALP website, as coming (Part of SALP SA1 - bedroom houses with associated garages and access As at 30 September 2017: (part of Policy soon, Spring 2018 Eastern Road) from Eastern Road. 14 units n/s SA1, Eastern (September 2017). Road), and has Conditions applications: planning Phasing: Given - 14/00129/CON. Details acceptable 7th April 2015. permission. housebuilder involved, Conditions 3, 4, 5, 6, 9, 10, 11, 14, 15, 16, 19, 20, 21, on-site preparation 22, 23, 27, 29, 30 & 31 of planning permission works needed; 12/00483/FUL. completions expected - 16/00157/COND. Approved No 2016. Condition 03 for 2019/20. (material samples), 04 (FFL), 13 (access road), 14 (visibility splays), 15 (access to dwellings), 16 (retention of visibility splays), 19 (visitor car parking), 21 (link to east) and 22 (drainage strategy) of planning permission 15/00456/FUL.

Other applications: 15/00039/NMA, agreed 12 March 2015 Application for a non-material amendment to planning permission 12/00483/FUL to remove chimneys from the houses on all plots, rearrangement of the parking spaces in front of plot 12 and alterations to the road alignment from the access westward to plot 14. Foundation House, 123 flats. 13/00441/OUT Approved with legal agreement, 14 May 58 completions expected As at 30 September 2017: Site is acceptable Site is being Housebuilder involved, London Road, 2014. 2017/18, & 24 complete (Q1) as allocated developed by and site is under Bracknell. Outline application, with all matters reserved, for erection 65 in 2018/19. 27 complete (Q2) through SALP Redrow Homes, construction. Site is (The Quarters) of 123 residential apartments with associated access, 72 u/c (part of Policy and is under being marketed car parking, landscaping and related works. SA1, Eastern construction. through housebuilder (Part of SALP SA1 - Road), and has website (September Eastern Road) 14/00933/FUL. Approved with legal agreement 17th outline planning 2017). April 2015. permission. (Block A = 27 flats; Application under S73 of the Town and Country Planning Block B = 31 flats; Act for a minor material amendment to Outline Planning Block C = 41 flats and Permission Ref: 13/00441/OUT, dated 14th May 2014, Block D = 24 flats) for the erection of 123 residential apartments with associated access, car parking, landscaping and related Phasing: as site under works to seek:- construction, 58 a) variation to condition 04 to amend the parameter completions expected plans and associated supporting documents in 2017/18 and 65 in (amendments include minor alterations to proposed 2018/19. scale of built-development and broad location of uses on the site); b) variation to wording of conditions 06 (accessibility), 09 (car parking provision), 13 (off-site highway works), 15 (car park strategy), 17 (timing of landscape works) and 23 (communal amenity space) so that they correspond with the changes proposed in (a) above, and c) deletion of conditions 08 (closure of existing access) - covered by amended condition 13 - and 30 (Code Level 3 Post Construction Review Report) - Code for Sustainable Homes now withdrawn.

15/00362/REM. Approved 17th September 2015. Submission of details of access, appearance, landscaping, layout and scale for a residential development comprising 123 residential apartments with associated access, car parking, landscaping and other associated works pursuant to outline planning permission 13/00441/OUT (as varied by 14/00933/FUL).

16/00087/FUL. Approved 9 June 2016. Section 73 application for the variation of condition 01 (approved plans) of reserved matters approval 15/00362/REM (for a residential development comprising 123 residential apartments and related works pursuant to outline planning permission 13/00441/OUT (as varied by 14/00933/FUL)) to provide for the addition of 3no. external water booster tank housings with associated changes to detailed design of apartment blocks and bin/cycle stores.

Conditions applications: Eagle House, The 84 flats 15/00212/FUL: Approved with legal agreement 17th July 60 completions expected 2018/19 As at 30 September 2017: Site is acceptable Bracknell Applicant is BRP who Ring 2015, application expires July 2018. & 24 84 units u/c as permission Regeneration are leading on Town Change of use from Office (B1) to residential (C3) to in 2019/20 granted, and Partnership Centre regeneration. provide 92 dwellings. s.106 completed. February 2016 14/00270/FUL. Approved 21 May 2014. availability proforma: Removal of mezzanine floorspace to increase the height no response received. of the existing underpass, and external alterations to podium and roof plant room. Phasing: 60 completions expected 14/00271/FUL. Approved May 2014. 2018/19, 24 in Alterations to external appearance of floors 1-7 of the 2019/20. building by the formation of "pop-outs" and recladding.

16/00749/FUL. Approved 15 September 2016. Alterations to external appearance of building (no change to existing floorspace)

[13/00938/PAC. Prior approval not required (19th December 2013). s.106 completed 13th March 2015. Prior approval relating to change of use of office to residential (90 flats).]

Conditions applications: - 15/00136/COND. Details acceptable 3rd December 2015. Details pursuant to condition 3 (Materials) of planning permission 14/00270/FUL. - 15/00137/COND. Details acceptable 9th December 2015. Details pursuant to condition 3 (Materials) of planning permission 14/00271/FUL. - 15/00139/COND. Details acceptable 9th December 2015. Details pursuant to condition 4 (Vehicle Access) of planning permission 14/00270/FUL. 17/00635/NMA Approved 26 July 2017. Application for non material amendment to 15/00212/FUL to change the number of dwellings proposed from 92 to 84.

Barnett Court, 0 overall (as 15/00284/FUL. Approved 5 November 2015 (expires 28 completions expected Completions during 2016/17: - Site is acceptable Bracknell Forest Registered provider Larges Lane, replacement) November 2018). 2018/19. 28 as permission Homes involved. Bracknell Demolition of existing buildings (27 self-contained units As at 30 September 2017 (zero granted. (23 bedsits and 4no. 1-bed dwellings) and caretakers net): February 2016 bungalow) and erection of 28 flats (9 no. 1 bed and 28 units u/c availability proforma: 19no. 2-bed flats) with associated access, parking, and Bracknell Forest landscaping. Homes (09.02.16): 28 completions in Conditions: 2017/18. - 16/00152/COND. Approved 12 September 2016. Conditions 09 (site management), 12 (method Phasing: completions statement), 13 (tree construction), 14 (sustainability during 2018/19. statement) and 21 (tree protection) - 16/00174/COND. Approved 17 Nov 2016 Conditions 3 (materials), 7 (parking), 11 (external lighting), 15 (drainage), 17 (floor levels) and 20 (landscaping). - 16/00188/COND. Approved 30 September 2016. Condition 05 (parking bay alterations) Bridgewell Centre, loss of 7 overall 15/00618/FUL. Approved 24 December 2015 (expires -27 completions expected in As at 30 September 2017: Site is acceptable Bracknell Forest Registered provider 10A Ladybank, (demolition of 27 & December 2018). 2018/19; n/s (-7 net) as permission Homes involved. Bracknell erection 20 new) Erection of 6no. 1 bedroom and 14no. 2 bedroom flats 20 in 2020/21 granted. with associated access, parking, and landscaping February 2016 following demolition of existing building (27 elderly care availability proforma: units in C3 use). no response received.

Phasing: demolition expected 2018/19, completions expected 2020/21. Photon 72 units 14/01095/FUL. Approved with a s.106 12 October 2015. 72 completions expected in As at 30 September 2017: Site is acceptable Site is being Housebuilder involved. House/Blueprint (Expires March 2018). 2017/18. 12 complete (Q1) 46 as allocated developed by Site is under House, Old Redevelopment of site to provide 19no. 1 bedroom, complete (Q2) through SALP Hodson construction. Bracknell Lane 44no. 2 bedroom and 2no. 3 bedroom flats with 14 units u/c. (part of Policy Developments, and West, Bracknell associated car parking. (65 in total). SA1, Old is under Market and cost Bracknell Lane construction. factors were The Fitzroy 15/01273/FUL. Approved 11 March 2016. West), and has considered through Collection, Old Section 73 application for variation of condition 02 permission. discussions on the Bracknell Lane (approved plans) of Planning Permission 14/01095/FUL s.106. West to substitute the list of approved drawings. [Note for clarification: this application seeks approval of internal Phasing: As site is (Part of SALP SA1 - and external alterations (including enlargement of under construction, Old Bracknell Lane basement area). These changes are also sought under phase all completions West) application 15/01281/NMA] 2017/18.

15/01281/NMA. Withdrawn January 2016. Application for a non-material amendment to planning permission 14/01095/FUL involving internal and external alterations (including enlargement of basement area). [Note for clarification: these changes are also sought under application 15/01273/FUL]

16/00494/FUL. Approved 27 January 2017 Erection of 72no. apartments with associated basement parking (amendment to planning permission 15/01273/FUL).

Conditions applications: - 15/00206/COND. Details acceptable, 24 November 2015. Condition 7 of 14/01095/FUL. - 15/00228/COND. Withdrawn July 2016. Conditions 3, 5, 13, 19 & 22 of 14/01095/FUL. - 15/00239/COND. Withdrawn July 2016. Conditions 8, 10, 11, 14, 15, 16 & 21 of 14/01095/FUL. - 16/00085/COND. Approved 01 Sept 2016. Condition 5 (Landscaping) of 15/01273/FUL. - 16/00190/COND. Approved 05 Sept 2016. Condition 03 (materials) of 15/01273/FUL. Post Office, 6 High 14 flats 15/00536/FUL. Approved with legal agreement 18 April 14 completions expected in As at 30 September 2017: Site is acceptable Bradiston Real Phasing: taking Street, Bracknell 2016. (Expires April 2019). 2019/20. 14 units n/s as permission Estate Inc account of the need to Erection of 7 storey building (with undercroft for granted, and obtain condition parking/storage) accommodating A1 (retail) use at s.106 completed. approval, and site ground floor (170 sq m) and 14 residential units over clearance, phase 14 following demolition of Post Office building - completions for resubmission of 14/01015/FUL. 2019/20 (before application expires). Discussions with developer on-going Edenfield Larges 48 flats 15/00004/FUL. Approved with legal agreement 30th 48 completions expected in Offices being demolished. Site is acceptable, Stonewater (Raglan Phasing: as demolition Lane, Bracknell June 2016. (Expires June 2019). 2019/20 As at 30 September 2017: and has a Housing) of existing building on- Erection of 48 no. dwellings (41 no. apartments and 7 48 units n/s completed s106 going, and approval of no. terraced houses) with associated parking and conditions required, vehicular access from Larges Lane following demolition phase 48 units in of existing office building. 2019/20.

16/01233/FUL Approved 6 April 2017. Section 73 application for the variation of condition 12 of planning permission 15/00004/FUL (for the erection of 48 no. dwellings with associated parking and vehicular access from Larges Lane following demolition of existing office building) to extend permitted demolition/construction hours from between 09:00 and 17:00 hours Mon-Fri and 09:00 and 13:00 hours on Saturday, to between 08:00 and 18:00 hours Mon-Fri and 08:00 and 13:00 hours on Saturday. No demolition/construction to take place on Sundays or Public Holidays.

Bracknell Town 14 units 16/00102/FUL. Approved with s.106 27 September 14 completions expected in As at 30 September 2017: Site is acceptable, Bracknell Town Phasing: 14 expected Football Club 2016. (Application to be implemented within 3 years). 2018/19 14 units u/c as permission Football Club 2018/19. Larges Lane, Change of use of land from D2 to C3 and erection of granted, and Bracknell 6No. dwellinghouses and 8No. flats with parking and s.106 completed. access. (NB: this falls within the boundary of the allocation at the Football Club, SALP Policy SA2)

Alston House 12 units 16/00962/FUL Erection of 4 storey building comprising 12 completions expected in As at 30 September 2017: 12 Site is acceptable Mr E Goodwin Phasing: 12 Market Street 10 no. self contained units for shop (Class A1), financial 2018/19 u/c and has planning completions expected and professional services (Class A2), restaurant and permission in 2018/19. café (Class A3), hot food takeaway (Class A5) and night club (sui generis) use (1148 sq m) at ground and first- floor level with 12 no 2 bedroom apartments on the second and third floors with associated car parking, bin storage and landscaping.

Racal House 60 units 16/00626/FUL Approved 23 February 2017. 31 completions expected in As at 30 September 2017: 60 Site is acceptable Glenmore Housebuilder involved. Eastern Road Redevelopment of site to provide 60 residential units 2020/21 & n/s and has planning Residential Limited Phasing: 31 expected within a part-three, four and five storey building (plus 29 in 2021/22 permission 2020/21, 29 in basement car parking) with associated amenity space, 2021/22. landscaping, car parking, refuse stores and foot/cycle path link following demolition of existing buildings.

Amber House & 193 units 15/01035/FUL. Approved with s.106 03 February 2017. 35 completions expected in As at 30 September 2017: Site is acceptable Thames Valley Phasing: 35 expected Northgate House, Erection of building accommodating 193no. residential 2020/21 & 193 units n/s and has planning Housing 2020/21, 158 in Market Street, apartments (use class C3) with flexible commercial use 158 in 2021/22 permission Association 2021/22. Bracknell at ground level within use classes A1 (shops), A2 (financial and professional services), A3 (restaurants and cafes), B1 (business), D1 (non-residential institutions) and D2 (assembly and leisure) and associated car parking, amenity space, landscaping, servicing and access following the demolition of Amber House and Northgate House.

1-9 High Street 10 units (net) 15/01261/FUL Allowed on Appeal. Erection of two -3 completions expected in As at 30 September 2017: -3 Site is acceptable Mr K Dickens Demolition complete. buildings accommodating 2no. shop/financial and 2017/18 & complete (Q1) and has planning Phasing: 13 professional services units (use classes A1/A2: total 13 in 2018/19 13 u/c permission completions expected floorspace 136 sq m), 6no. one bedroom and 7 no. two 2018/19. bedroom flats (use class C3) with access from High Street 69 - 77 Church 9 units 16/00331/FUL Erection of 2 no 4 bed, 5 no 3 bed and 2 4 completions expected in As at 30 September 2017: 9 u/c Site is acceptable Aquinna Homes Housebuilder involved. Street no 2 bed dwellings with associated access and parking. 2017/18 & and has planning Phasing: 4 expected 5 in 2018/19 permission 2017/18, 5 in 2018/19.

48-50 Dukes Ride, 32 units (30 net) 15/01082/FUL. Approved with s.106 23 June 2016. -2 completed in 2016/17 & Completions during 2016/17: -2 Site is acceptable, Renaissance Market and cost Crowthorne (C3 specialised use) (Application to be implemented within 3 years). 32 expected in 2018/19 As at 30 September 2017: as permission Retirement Ltd factors were Erection of a block of 32 sheltered apartments for the 32 units u/c granted and s.106 considered through elderly with detached binstore/cycle store; modification of completed. discussions on the existing access (to No.50) and closure of existing access s.106. to No.48; construction of basement parking and other associated parking, following the demolition of existing Phasing: as demolition buildings. (Re-submission of 14/01073/FUL with complete, phase 32 in amendments). 2018/19

319 Yorktown Road 6 units (net) 15/00731/FUL The erection of 7 apartments (4 no. 1 bed SITE COMPLETE 2017/18. Completions during 2016/17: -1 Site is acceptable Mr A Atkinson Site complete. flats and 3 no. 2 bed flats) with 10 car parking spaces, As at 30 June 2017: 7 complete and has planning 14 cycle spaces, secure waste storage and private Site complete permission residential amenity space. 92 High Street 6 units (net) 15/00082/FUL Erection of 3no two-storey terraced -3 completed during 2016/17 Completions during 2016/17: -3 Site is acceptable Mr A Shenton, Mr P Demolition complete. houses and a three-storey building containing 6no flats, 9 completions expected during As at 30 September 2017: 9 u/c and has planning Shenton & Mrs A Phasing: as provision of vehicle parking and circulation areas; cycle 2017/18 permission Simpson constuction on-going, and bin storage, private gardens and communal amenity phase 9 in 2017/18. space following the demolition of existing buildings.

Former Harts Leap 8 units 15/01258/FUL Erection of 7 no. 4 bed and 1 no. 3 bed 8 completions expected during As at 30 September 2017: 8 n/s Site is acceptable Halebourne Housebuilder involved. Nursing Home, 5 detached houses and garages following demolition of all 2018/19 and has planning Developments Ltd Phasing: 8 expected Windrush Heights existing buildings. permission 2018/19.

Jolly Farmer, 41 units (net) 15/00403/FUL Erection of building comprising 42no. -1 completions expected during As at 30 September 2017: -1 Site is acceptable Renaissance Housebuilder involved. Yorktown Road sheltered apartments for the elderly with a retail unit/tea 2017/18 & complete and has planning Retirement Ltd Demolition complete. shop (use class A3) and associated parking, following 42 in 2018/19 42 u/c permission Phasing: all units demolition of existing building. expected 2018/19.

152 New Road, 14 houses (net 13) - 12/00593/FUL. Approved with legal agreement 30th Demolition (-1) completed in Completions during 2016/17: -1 Site is acceptable Site is being Phasing: demolition Ascot September 2013. (Expires September 2016). 2016/17 As at 30 September 2017: as allocated developed by Regis complete, completions Erection of 8no. 3 bedroom and 6no. 4 bedroom houses 14 completions expected in 2 complete (Q1) 3 through SALP Homes, and is expected for 2017/18. (SALP SA2) with associated amenity space, parking & landscaping 2017/18. complete (Q2) 9 u/c (Policy SA2), and under construction. following demolition of existing dwelling. Total completions: 4 (net) has planning - 16/00043/FUL. Granted 23 May 2016. permission. Section 73 application for the variation of condition 02 (approved plans) of planning permission 12/00593/FUL (for the erection of 14no. houses with associated works) to provide for minor internal and external amendments to the design of the proposed houses. - 16/00836/NMA. Agree 26 October 2016 Non material amendment for variation to wording of condition 07 (Sustainability Statement) and removal of condition 08 (Post Construction Review Report) to planning permission 12/00593/FUL. Conditions applications: - 15/00134/COND. Details acceptable, 4th September 2015. Details pursuant to condition 22 (archaeology). - 15/00141/COND. Details acceptable, 4th November 2015. Details pursuant to conditions 15 (Tree Protection) and 16 (Ground Preparation Works). - 15/00150/COND. Details acceptable, 4th September 2015. Details pursuant to condition 18 (Flood Plain) of planning permission 12/00593/FUL. - 16/00022/COND Approved 23 Feb 2016 Details pursuant to condition 11 (Ecology Mitigation) of planning permission 12/00593/FUL - 16/00049/COND. Approved 24 Nov. 2016 Details pursuant to conditions 3 (materials), 4 (levels), 5 (access), 6 (parking), 7 (sustainability statement), 8 (post construction review report), 9 (energy demand assessment), 10 (working method statement), 14 (hard and soft landscaping), 21 (surface water), 26 (gradient of drive), 27 (visitor parking), 28 (parking areas), 31 (off site highway works), 32 (site management) of planning permission 12/00593/FUL. - 16//0182/COND pending consideration Details pursuant to condition 17 (Flooding) of planning permission 12/00593/FUL.

2015/16 completions: 14 (net) 2016/17 completions: 156 2017/18 completions to date: 121 (net) 2017/18 u/c June 2017: 342 (net) (Medium Sites/hard commitments)

SOFT COMMITMENTS - Large sites subject to a s 106 Amen Corner 550 units (inc 12/00993/OUT (outline application covering part of the 550 units: As at 30 September 2017: Site is acceptable To be added once Requires completion of South, Binfield affordable) site), resolution to approve, subject to completion of a 25 completions expected in 550 units n/s as allocated permission is s.106, reserved Neighbourhood s.106 agreement. (i.e. redline area does not relate to 2019/20; through SALP granted. matters and conditions (CSDPD CS4/SALP Centre whole allocation, and now excludes school). 75 completions in 2020/21; (Policy SA8), and approval before SA8) 75 completions in 2021/22; has a resolution commencement of Primary School 550 dwellings 75 completions in 2022/23; to approve development. new spine road 75 completions in 2023/24; (subject to OSPV and SANG neighbourhood centre 75 completions in 2024/25; completion of a Market and cost 75 completions in 2025/26; and s.106). factors being Extension of time to determine application: agreed to 29 75 completions in 2026/27 considered through July 2016 s.106 process.

14/00472/OUT, resolution to approve (August 2014 Phasing: as s.106 yet Committee), subject to completion of a s.106 agreement. to be completed, and Outline application for erection of two-form entry primary taking account of the school and associated playing fields with access from need to obtain Beehive Road. reserved matters and condition approval, together with clearance of the site, put first completions in 2019/20 at 25 units, then build out rate of 75dpa (as site is over 300 units, on the assumption that one housebuilder involved).

NB: residual balance of 175 units for Amen Corner South is listed under soft commitments.

2017/18 u/c to date: none. (Large sites/soft commitments with s.106) SOFT COMMITMENTS - Medium sites subject to a s 106 Apex House, 28 flats 16/00639/PAC. Approved 20 July 2016 (s.106 required 28 completions expected As at 30 September 2017: Prior approval Requires completion of London Road, in relation to SPA). 2019/20. 28 units n/s granted, but s.106 s.106 before Bracknell Application for prior approval for the change of use of required in development can existing office (Class B1a) to residential use (Class C3) relation to commence. (Part of SALP SA1 - comprising 28 apartments. mitigation of the Eastern Road) Thames Basin Phasing: put Heaths Special completions in Protection Area 2019/20. before permission can be implemented Century Court 71 units 17/00136/PAC Prior approval for the change of use from 71 completions expected in As at 30 September 2017: 71 Prior approval Mason Property Ltd Requires completion of Millennium Way offices (B1) to 65 no. 1 bedroom, and 6 no. studio 2019/20 n/s granted, but s.106 s.106 before apartments (C3). required in development can relation to commence. mitigation of the Phasing: completions Thames Basin expected 2019/20. Heaths Special Protection Area, before permission can be implemented. The Braccans, 36 units 16/00299/PAC. Granted 11 May 2016. 36 completions expected in As at 30 September 2017: Prior approval Northprop Ltd Requires completion of London Road, Prior approval notification for the change of use of offices 2019/20 36 units n/s granted, but s.106 s.106 before Bracknell (B1a) to 33 apartments (C3). required in development can relation to commence. 16/00995/PAC Approved 16 November 2016. Prior mitigation of the Phasing: completions approval notification for the change of use of offices Thames Basin expected 2019/20. (B1a) to 36 apartments (C3). Heaths Special 17/00170/PAC Approved 23 March 2017. Prior approval Protection Area, change of use application for offices (Class B1a) to form before permission 36 apartments. can be implemented 77-79 Deepfield 8 units 15/01283/FUL Erection of 10 houses comprising 7no 3 -2 completions expected in As at 30 September 2017: 8 n/s Permission Requires completion of Road bed and 2no 4 bed houses and 1 no 3 bed chalet 2018/19 & granted but s.106 s.106 before bungalow at 77-79 Deepfield Road and land to the rear 10 completions expected 2019/20 required in development can of 73-75 and 81-87 Deepfield Road and the creation of a relation to commence. new access road following demolition of 77 and 79. mitigation of the Phasing: demolition Thames Basin expected 2018/19, Heaths Special completions expected Protection Area, 2019/20. before permission can be implemented Tamar House, 79 units 16/01293/PAC Prior approval for the change of use of 79 completions expected in As at 30 September 2017: 79 Prior approval Requires completion of Forth House and Tamar House, Forth House and Clifton House from office 2019/20 n/s granted, but s.106 s.106 before Clifton House, buildings (Use Class B1a) to residential (Use Class C3) required in development can Brants Bridge comprising 79 units. relation to commence. mitigation of the Phasing: completions Thames Basin expected 2019/20. Heaths Special Protection Area, before permission can be implemented 32 Wellington 8 units 16/00735/PAC Prior Approval for the change of use from 8 completions expected in As at 30 September 2017: 8 n/s Prior approval Requires completion of Business Park, B1(a) offices to 8no. C3 dwellings 2017/18 granted, but s.106 s.106 before Dukes Ride required in development can relation to commence. mitigation of the Phasing: completions Thames Basin expected 2017/18. Heaths Special Protection Area, before permission can be implemented 34 Wellington 5 units 16/01202/PAC Prior Approval for the change of use from 5 completions expected in As at 30 September 2017: 5 n/s Prior approval Requires completion of Business Park, B1(a) (Office) to C3 (Residential) to form 2 no. 2 bed and 2017/18 granted, but s.106 s.106 before Dukes Ride 3 no. 1 bed dwellings. required in development can relation to commence. mitigation of the Phasing: completions Thames Basin expected 2017/18. Heaths Special Protection Area, before permission can be implemented Crossways 5 units 16/00221/FUL Change of use from 9 bed carehome (C2) 5 completions expected in As at 30 September 2017: 5 n/s Permission Requires completion of Residential Care to 5 flats (C3), with associated single storey rear 2019/20 granted but s.106 s.106 before Home, 306 extensions and alterations to the existing building, required in development can Yorktown Road parking, and access. relation to commence. mitigation of the Phasing: completions Thames Basin expected 2019/20. Heaths Special Protection Area, before permission can be implemented

2017/18 u/c to date: none 2017/18 completions to date (Q2): none (Medium sites/soft commitments with s.106)

SOFT COMMITMENTS: Site Allocations Local Plan Land north of 45 units No current applications on residual part of site. 137 units Trajectory relates to whole As at 30 September 2017: 182 Site is acceptable Persimmon Homes Permission required Peacock Lane, permitted under 13/00783/REM. allocation, part permitted under n/s as allocated & Redrow Homes before site can be Bracknell (Binfield 13/00783/REM. 14 completions through SALP developed. Parish) (residual expected in 2018/19, (Policy SA2). Phasing: As no current balance) 35 in 2019/20, discussions phase in 48 in 2020/21, later years of plan (SALP SA2) 32 in 2021/22, period. 30 in 2022/23 & 23 in 2023/24

Land north of Cain 75 units (inc No current applications. 30 completions expected N/A at this stage, as no Site is acceptable Hewlett Packard Permission required Road, Binfield affordable) 2024/25, & application approved. as allocated before site can be [09/00792/OUT & 10/00310/REM: for the erection of a 2 45 in 2025/26. through SALP developed. (SALP SA2) storey office building and associated car parking and (Policy SA2). landscaping on the Island Site and 2no. linked 4 storey Developer response to office buildings, and a 4 level multi-storey car park. This SALP consultations, a permission has been part implemented as covers a covenant currently larger site than the SALP allocation, and therefore the affects the short term SALP site has extent permission for commercial development of the site redevelopment (see plan 2714/1110D on application for housing. 09/00792/OUT).] Phasing: As no current discussions and restrictive covenant, phase over last 2 years of plan period. Amen Corner 175 units No current applications on residual part of site. 25 completions expected in N/A at this stage, as no Site is acceptable Various Permission required South, Binfield 2022/23 application approved. as allocated before site can be (residual balance) 50 in 2023/24 through SALP developed. 50 in 2024/25 & (Policy SA8). (CSDPD CS4/SALP 50 in 2025/26 Phasing: As no SA8) discussions have yet to taken place on the residual 175 units, added later in plan period (towards end of completions on main site), completions starting 2022/23), at 50dpa (on the basis of a single housebuilder, on a site less than 300 units).

Amen Corner 23 units (inc 16/00717/OUT. Popes Farm - Refused 26 Oct 2016 23 completions expected in N/A at this stage, as no Site is acceptable Shanly Homes Permission required North, Binfield affordable) Outline planning application for the erection of 54 2024/25 application approved as allocated before site can be (residual balance) dwellings, associated vehicular and pedestrian access, through SALP developed. car parking, drainage works and landscaping, including (Policy SA6). (SALP SA6) provision of open space, following removal of existing Phasing: As no dwelling and outbuildings (access, appearance, layout discussions have yet to and scale to be considered, landscaping reserved for taken place on the future consideration) residual 23 units, 17/00337/OUT Pending consideration. Outline planning added outside of the 5 application for the erection of 53 dwellings, associated year period (after vehicular and pedestrian access, car parking, drainage completion of main works and landscaping, including provision of open Amen Corner North space, and alterations to existing outbuilding to provide a site) around 2024/25. car barn and cycle store following removal of existing dwelling (means of access, appearance, layout and scale to be considered, landscaping reserved for future consideration) [NB: relates to a larger site area than residual allocation].

Garth Hill School, 36 units (residual No current applications on residual part of site. 36 completions expected N/A at this stage, as no Site is acceptable Cala Homes Housebuilder currently Sandy Lane, balance from 100 2020/21. application approved. as allocated involved. Discussions Bracknell estimated in Site through SALP on-going with (SALP SA1) Allocations). (Policy SA1). developer. (residual balance) Phasing: Requires approval (including conditions), and demolition of existing buildings before development can commence. Therefore, phase 36 completions for 2020/21.

The Depot 115 units (inc No current applications. 50 completions expected N/A at this stage, as no Site is acceptable BFC Site is reliant upon (Commercial affordable) 2023/24, application approved. as allocated TRL for relocation of Centre), Bracknell 50 in 2024/25, & through SALP depot. Permission Lane West, 15 in 2025/26. (Policy SA1). required before site Bracknell can be developed. BFC published a (Part of SALP SA1 - planning brief for Phasing: given Old Bracknell Lane the wider Old dependence on TRL, West) Bracknell Lane allowing time to West site March decommission existing 2015: site and gain planning http://consult.brac permission, assume knell- delivery of housing on forest.gov.uk/file/3 this site starting 350746. 2023/24, at 50dpa (on the basis of a single housebuilder, on a site less than 300 units).

Land to the north of Total estimated in Apex House: 100 completions expected N/A at this stage as no Site is acceptable Various Multiple land owners, Eastern Road, Site Allocations is 28 units: Soft commitment subject to s.106, application 2022/23, applications on residual part of as allocated no current applications. Bracknell 432 units (inc 16/00639/PAC. 100 in 2023/24, & site. through SALP Permission required (residual balance) affordable) 7 in 2024/25. (Policy SA1). before site can be Hayley House: developed. (SALP SA1 - Residual balance No current application, 16/00079/PAC expired 2017. BFC published a Eastern Road) (taking account of planning brief for To achieve the hard & soft Foundation House: the wider Eastern remaining 207 unit commitments at 123 units: Hard commitment application 13/00441/OUT, Road site June allocation, a more Avon Crop (14 14/00933/FUL & 15/00362/REM (see above). 2014: cautious density of units), Foundation http://consult.brac 120dph has been House (123 units), Avoncrop: knell- applied to the Racal House (60 14 units: Hard commitment, applications 12/00483/FUL forest.gov.uk/file/3 outstanding sites, to units) and Apex & 15/00039/NMA (see above), plus 15/00456/FUL. 215124 derive an indicative House (28 units) = capacity for the 207 remaining. Greenwood House: trajectory (instead of a No application at present. density of 160dph across the site as Racal House: assumed in SALP), 60 units: Hard commitment, application 16/00626/FUL. which gives the following estimates: Radius Court: Radius Court: c. 72 No application at present. units (based on approximate site area of 0.6ha); Greenwood House: c. 120 units (based on approximate site area of 1ha); Hayley House: c. 15 units

Phasing: Greenwood House: given refurbishment to office, phase 120 units in 2022/23-2023/24 Radius Court: given no current discussions, phase 72 units outside of 5 year period (2023/24). Hayley House: given no current discussions phase in 2023/24- 2024/25. Land at Old 138 units (inc Blueprint House (Photon House): 50 completions expected in N/A at this stage, as no Site is acceptable Various Multiple land owners, Bracknell Lane affordable) (residual 65 units: Hard commitment application 14/01095/FUL 2022/23, application approved. as allocated no current applications West, Bracknell balance from 203 (see above). 50 in 2023/24, & through SALP on residual. (residual balance) estimated in Site 31 in 2024/25 (Policy SA1). Permission required Allocations) No current applications on other parts of site. before site can be (SALP SA1 - Old BFC published a developed. Bracknell Lane planning brief for Discussions on-going West) the wider Old with developer. Bracknell Lane West site March SALP divides site in 2015: two: Area 1: west of http://consult.brac the depot (BRISA, knell- Photon House & forest.gov.uk/file/3 Hyperion House) and 350746. Area 2: east of the depot (the Beeches). SALP assumes 88 units for Area 1 and 115 for Area 2. Photon House (Area 1) 65 units approved October 2015, therefore residual balance is 138 units (203-65).

Phasing: as no current applications on other parts of site, phase at 50dpa (31 in final year), starting in 2022/23 (on the basis of a single housebuilder, on a site less than 300 units).

The Football 88 units (inc 16/01282/FUL Approved 26th May 2017. Erection of 14 36 completions expected N/A at this stage, as no Site is acceptable Not known Site is reliant upon Ground, Larges affordable) (residual dwellings with parking and access. 2023/24, & application approved. as allocated Blue Mountain for Lane, Bracknell balance from 102 Alternative app: 16/00102/FUL. Approved with s.106 52 in 2024/25 through SALP relocation of football estimated in Site agreement 27 September 2016 (Policy SA2). club. Permission (SALP SA2) Allocations) required before site No current applications on other parts of site. can be developed.

Phasing: as no current discussions, and given reliance on relocating elsewhere, phase at end of plan period, i.e. 2023/24, at approx. 50dpa (on the basis of a single housebuilder, on a site less than 300 units).

Land at Cricket 145 units (inc 16/00008/SCO - decision issued 19 May 2016. 60 completions expected in N/A at this stage, as no Site is acceptable Barratt David This site is linked with Field Grove, affordable) Request for scoping opinion under Regulation 13 of The 2019/20, application approved. as allocated Wilson Homes wider Broadmoor (i.e. Crowthorne Town and Country Planning (Environment Impact 60 in 2020/21, & through SALP SANG provisions and Assessment) 2011 (for 145 dwellings, made on behalf of 25 in 2021/22 (Policy SA2). reprovision of lost (SALP SA2) West London Mental Health Trust and Barratt Homes). OSPV at CFG). BFC published a Permission required 16/00914/FUL. Pending consideration. planning brief for before site can be Erection of 141 dwellings with associated car parking, the site developed. garaging, landscaping, informal open space and the September 2014: formation of two new access points off the existing http://consult.brac Phasing: Discussions Cricket Field Grove. In addition, the creation of a knell- are taking place publically accessible SANG facility and the provision of forest.gov.uk/file/3 (decision pending on two Sports Pitches with associated parking and changing 215121 application). Given room facilities on land off Lower Broadmoor Road. there is a need to reprovide existing recreation ground and provide SPA mitigation, phase start within 2019/20, at 60dpa (on the basis of a single housebuilder, on a site less than 300 units).

Land at Redeveloped Planning Performance Agreement in place 60 residential completions N/A at this stage as no Site is acceptable West London Permission required Broadmoor, Replacement expected in 2022/23 (relating to application approved. as allocated Mental Health Trust before site can be Crowthorne hospital Permission granted for replacement secure mental care home). through SALP developed. hospital and new access road off Foresters Road [Access road from Foresters (Policy SA4). (SALP SA4) Maximum of 210 (11/00743/FUL) May 2012 Housing within kitchen garden Way is now complete]. Phasing: No residential units expected: discussions as yet so (inc affordable) Applications for enabling works currently under 70 in 2023/24 added outside of the 5 consideration. These include the Energy Centre 70 in 2024/25 year supply period - 60 retirement units (discharge of condition). 70 in 2025/26 and phased in the later (C3 specialised use) years due to the need 12/00276/FUL Demolition of existing 'Silver Birches' to take account of Small Research building and construction of new two-storey building to setting of Listed Park provide a hospital training facility ancillary to the main Building & Historic hospital use, together with associated external works. Park and Garden Re-use of existing No current applications for residential development. 60 during 2022/23 hospital building equates to retirement apartments. Care Home/Nursing 210 during 2023/24- Home 2025/26 equates to housing in kitchen OSPV and SANG garden (at around 70dpa, on the basis of a single housebuilder, on a site less than 300 units). Land west of Alford 12 units No current application for residual. 2 completions expected in N/A at this stage, as no Site is acceptable Bloor Homes. House builder is Close, Sandhurst 2020/21, & application approved. as allocated involved (residual balance) 10 in 2021/22 through SALP (Policy SA3). Phasing: as no current (SALP SA3) application phase in BFC published a 2020/21 - 2021/22. planning brief for site June 2014: http://consult.brac knell- forest.gov.uk/file/3 215118 Warfield Area 1 814 units (inc Applications on parts of the site: Trajectory including recently N/A at this stage as no Site is acceptable Various Various land owners. affordable) permitted sites: 10 completions application approved. as allocated Permission required (CSDPD CS5/SALP (residuall balance - 13/00027/OUT - Fairclough Farm. Refused & expected in 2018/19, through SALP Western before site can be SA9) from based on dismissed on appeal (2 May 2014). 55 in 2019/20, (Policy SA9). Consortium: Newell developed. There is a emerging - 13/00423/OUT - Land Rear of Warfield Priory, 100 in 2020/21, Green Area need to address masterplan figure of Warfield Street, Warfield. Withdrawn. 55 in 2021/22, Masterplan for (Millgate, Harrow delivery of 814) - 14/00980/FUL - 1 Old Farmhouse Row, Warfield. 50 in 2022/23, Central Area Estates, Bovis and infrastructure across Dismissed on appeal (30th January 2016). 100 in 2023/24, published Kitewood the site. A consortium Primary School - 14/01029/FUL - West View, Watersplash Lane, 150 in 2024/25, February 2015: Investments) is established for Warfield. Refused January 2015. 150 in 2025/26, & http://consult.brac Newell Green Area. Neighbourhood - 16/00115/FUL - Land to rear of Warfield Garage, 144 in 2026/27 knell- Centre Forest Road. Refused 29 July 2016. forest.gov.uk/file/3 Masterplan for Central 16/01195/FUL Land East Of Avery Lane and North Of 344710 Area published Watersplash Lane - Approved 20 July 2017. February 2015: 16/01253/FUL Land South Of Fairclough Farm - http://consult.bracknell- Approved 20 July 2017. forest.gov.uk/file/33447 16/01274/FUL Land At Watersplash Lane -approved 20 10. Page 42. Also sets July 2017. out development will be progressed in 3 Council is currently undertaking discussions with phases, on the basis of HCA/ATLAS and landowners/developers. 3 developers operating Newell Green Area: (Phase 1: 325 - Planning Performance agreement in place with dwellings, Phase 2: 'Western Consortium' in relation to bringing forward of 241 dwellings, Phase 270 dwellings. 3: 248 dwellings) in the - 15/00027/SCR. Decision issued 25 January 2016. following phases (814 Request for screening opinion under Regulation 5 of The total): Town and Country Planning (Environment Impact 2015-16: 50 Assessment) Regulations 2011 (as amended) for 307 2016-17: 150 units (Harrow Estates Land: up to 150 units; Bovis 2017-18: 150 Homes land: up to 64 units; Kitewood Land: up to 55 2018-19: 150 units; Millgate land: up to 38 units) 2019-20: 150 No current applications on residual parts of Area 1. 2020-21: 164 Development of the Warfield site requires a new north/south link road through the site. This has received investment through the ‘local growth’ funding pot from the Thames Valley Local Enterprise Partnership. Phasing: whilst masterplan has been published, still no applications relating to the whole of this area, therefore delivery Warfield Area 2 100 units (inc Parcel 22A & 22B Land Opposite 50 completions expected in N/A at this stage as no Site is acceptable Various Various land owners. (residual area) affordable) Roundabout Binfield Road 2024/25, & application approved. as allocated Permission required No current applications on residual parts of area 2 50 in 2025/26. through SALP before site can be (CSDPD CS5/SALP (Area 'h', part of (Policy SA9). developed. There is a SA9) area 'c' (West End For main Area 2, see application 13/01007/OUT, and need to address Stables) and part of associated reserved matters applications. delivery of area 'f' (Park Farm) infrastructure across the site.

Development of the Warfield site requires a new north/south link road through the site. This has received investment through the ‘local growth’ funding pot from the Thames Valley Local Enterprise Partnership.

Areas of land not part of Berkeley Scheme (letters refer to land parcels contained in Warfield SPD): Area 'h': 25 dwellings (as per SPD) Part of area 'c' (West End Stables): site area c. 113ha@35dph = 40 dwellings (gross) (38 net), but adjusted to 35 net to take account of setting of Listed Building Part of area 'f' (Park Farm): site area c. 1.2ha@35dph = 42 dwellings (gross), 40 net.

Phasing: Added outside of the 5 year supply period as no discussions as yet on this sites (total 100 units) at end of plan period. Warfield Area 3 454 units (inc Applications on parts of the site: 50 completions expected in N/A at this stage, as no Site is acceptable Various Various land owners. affordable) 2021/22, application approved. as allocated Permission required (CSDPD CS5/SALP (as per SPD, Fig 5) 14/01262/FUL - land East of Jigs Lane & Strawberry Hill. 100 completions in 2022/23, through SALP before site can be SA9) Refused 25th August 2015. 100 completions in 2023/24, (Policy SA9). developed. There is a Erection of 90 dwellings comprising of 68 houses and 22 100 completions in 2024/25, & need to address flats, creation of vehicular access from Jigs Lane North 104 completions in 2025/26. delivery of with upgrading works to existing highway, associated car infrastructure across parking and amenity space, formation of open space, the site. creation of east-west greenway and footpaths within the site and connection points for provision of two bridges on Development of the eastern boundary to provide link to Westmorland Park Warfield site requires a and Edmunds Lane following demolition of existing new north/south link dwelling. road through the site. This has received 15/00221/OUT - land at Grove Gardens, Forest Road, investment through the Hayley Green. Application withdrawn. ‘local growth’ funding Outline application for the erection of 28 dwellings, with pot from the Thames new access off Bracknell Road, open space with Valley Local Enterprise associated cycle and public footpaths, landscaping and Partnership. facilitation of future Bracknell Road/Forest Road junction improvements following the demolition of Grove Phasing: On-going Gardens. work with HCA/ATLAS and Council is currently undertaking discussions with landowners/developers HCA/ATLAS and landowners/developers. to bring forward development across this area (workshops have taken place). There is a need address delivery of infrastructure across the site. As no applications relating to the whole of the site, phase outside of 5 year period to total 454 (as per numbers envisaged in the Warfield SPD see Fig 5 & 6 relating to parcels v-z & aa-dd). SPD (Appendix 3) also sets out that area 3 will be the final sequence. The site is more than 300 units. As the site is in multiple ownership, there is likely to be more than one housebuilder Sandbanks, 49 units (inc 14/0569/FUL - refused 19 December 2014 25 completions expected in N/A at this stage as no Site is acceptable Shanly Homes Multiple land Longhill Road and affordable) Erection of 62 dwellings comprising 5no. 1 bedroom 2020/21, & application approved. as allocated ownership, Dolyhir, Fern flats, 10no. 2 bedroom flats, 29no. 4 bedroom houses 24 in 2021/22 through SALP housebuilder is Bungalow and and 18 no. 5 bedroom houses, including the demolition (Policy SA3). involved. Permission Palm Hills Estate, of two existing residential dwellings (C3 use) and two required before site London Road, building associated with guest house/hotel (C1 use), can be developed. Bracknell landscaping. vehicular access from London Road, Discussions with parking, open space and pedestrian/cycle link to Long developer on-going. (SALP SA3) Hill Road. Phasing: As a 16/00395/FUL. Resolution to approve at 13 October housebuilder in 2016 Planning Committee. involved, taking Change of use of part of building from C1 (Guesthouse) account of the need to and C3 (Residential dwelling) to C3 (Residential) to obtain approval create six bedroom dwelling. (including conditions), and site clearance, 16/00396/FUL. Refused at 13 October 2016 Planning phase first completions Committee. Appeal pending. (25 units) in 2020/21. Temporary change of use of 2no. existing outbuildings to B1(a) office space and change of use of 1no. outbuilding to D2 childrens indoor recreational use (personal permission).

Shanly Homes undertook public consultation on a h f t 58 h i A il/M 2016 Land at Bog Lane, 40 units (inc No current applications. 40 completions expected N/A at this stage as no Site is acceptable Permission required Bracknell affordable) 2025/26. application approved. as allocated before site can be through SALP developed. (SALP SA3) (Policy SA3). Phasing: No current discussions, therefore, phase outside of 5 year supply around 2025/26.

SOFT COMMITMENTS: Site Allocations Local Plan Land at Wood 20 units (inc No current applications. 20 completions expected in N/A at this stage as no Site is acceptable Permission required Lane, Binfield affordable) 2024/25. application approved. as allocated before site can be through SALP developed. (SALP SA3) (Policy SA3). Phasing: No current discussions, therefore, phase outside of 5 year supply around 2024/25.

Albert Road Car 40 units (inc No current applications. 40 completions expected 2025/26 N/A at this stage, as no Site is acceptable BFC Permission required Park, Bracknell affordable) application approved. as allocated before site can be through SALP developed. (SALP SA1) (Policy SA1). Phasing: As no discussions, phase completions for 2025/26. Chiltern House and 71 units 17/00434/FUL Pending consideration. Erection of 99 19 completions expected N/A at this stage, as no Site is acceptable Bellway Homes Phasing: application the Redwood apartments (including affordable dwellings), provision of 2019/20, application approved. as allocated pending consideration; Building, Broad car parking and communal amenity space following 44 in 2020/21, & through SALP phase first completions Lane, Bracknell demolition of existing office buildings. (Resubmission of 8 in 2021/22 (Policy SA1). in 2019/20. application 16/00889/FUL with updated parking survey) (SALP SA1) 16/00889/FUL. Refused. Erection of 100 apartments (including affordable dwellings), provision of car parking and communal amenity space following demolition of existing office buildings.

14/01217/OUT. Withdrawn. 24th March 2016. Outline planning application for the erection of 71 no. apartments (18no. 1 bed, 47 no. 2 bed and 6no. 3 bed) following demolition of Chiltern House and The Redwood Building (including 18 No. affordable apartments). Outline application to consider means of access and layout. (All matters reserved). Downside, 18 units (inc No current applications. 18 completions expected N/A at this stage, as no Site is acceptable Thames Valley Permission required Road, affordable) 2020/21. application approved. as allocated Housing before site can be Bracknell through SALP developed. (Policy SA1). Discussions on-going (SALP SA1) with developer.

Phasing: As discussions on-going phase in 2020/21.

White Cairn, Dukes 16 units (inc No current applications. 16 completions expected N/A at this stage, as no Site is acceptable Wellington College. Permission required Ride, Crowthorne affordable) 2022/23. application approved. as allocated before site can be BFC have prepared non-statutory planning brief for the through SALP developed. (SALP SA3) site (dated October 2014), available to view: (Policy SA3). http://www.bracknell- Phasing: as no current forest.gov.uk/planningbriefsforcertainsiteallocationslocal BFC published a application, phase plansites planning brief for outside of 5 year the site October supply, in 2022/23. 2014: http://consult.brac knell- forest.gov.uk/file/3 215117

Land at Battle 10 units Part of application: 10 completions expected N/A at this stage, as no Site is acceptable Permission required Bridge House and - 16/00115/FUL - Land to rear of Warfield Garage, 2021/22. application approved. as allocated before site can be garage, Forest Forest Road. Refused (see Warfield Area 1, above). through SALP developed. Road, Warfield Residential development of 56 dwellings with associated (Policy SA1). access, open space and infrastructure on land off Forest Phasing: current (SALP SA1) Road, and change of use from agricultural land to SANG application relating to off Moss End. Warfield Area 1, could be achieved within 5 years (2021/22).

New Large & Medium Sites Granted Permission, or a resolution to approve (subject to completion of a s.106) during the 2017/18 Monitoring Year (Whilst these sites do not form part of the 2017/18 housing commitment data/Housing Trajectory they are included for information)

New permissions: Large Sites

Land Adjoining 82 units 15/00383/FUL Allowed on Appeal 27 September 2017. To be added to the April 2018 As at 30 September 2017: 82 Site is acceptable Warfield Homes Housebuilder is Warfield Park, Change of Use of land adjoining Warfield Park for the Trajectory n/s and has planning involved. Long Hill Drive siting of up to 82 mobile homes (according with the permission. definition of a caravan), suitable alternative natural green space (SANGS) and informal open space, together with access improvements, landscaping and biodiversity measures. [Will be added to 2018 Commitments]

New permissions: Medium Sites

Land R/O 5 units 16/01153/FUL Approved 22 May 2017. Erection of 5no. 5 To be added to the April 2018 As at 30 September 2017: 5 n/s Site is acceptable Neuchatel, Chavey bed detached dwellings with new access off Chavey Trajectory with permission Down Road Down Road. [Will and signed s106 be added to 2018 Commitments] Land At The Yard, 1 units (4 already 16/00707/FUL Allowed on Appeal 10 August 2017. To be added to the April 2018 As at 30 September 2017: 1 n/s Site is acceptable Howard Park Housebuilder is Road counted under Change of use of the land for the siting of six two bed Trajectory and has planning Homes involved. (Brickfield) 15/00200, with the residential mobile park homes. permission units permitted here [Will be added to 2018 Commitments] (allowed on on 1 plot of 2015 appeal) permission) Baileys Garage and 5 units 16/01181/FUL Approved 28 August 2017. Erection of 5 To be added to the April 2018 As at 30 September 2017: 5 n/s Site is acceptable Jordan Housebuilder is The Haven dwellings following demolition of existing buildings. Trajectory and has planning Construction Ltd involved. [Will be added to 2018 Commitments] permission.

The Blue Lion, 5 units 16/00159/FUL Allowed on Appeal 27 September 2017. To be added to the April 2018 As at 30 September 2017: 5 n/s Site is acceptable FPC (Bracknell) Broad Lane, Mixed use redevelopment comprising a retail unit (A1) Trajectory and has planning LLP and five flats (C3) (comprising five 2 bedroom units), permission together with associated plant, cycle and vehicle parking, (allowed on refuse storage and landscaping following demolition of appeal) existing public house and outbuildings. [Will be added to 2018 Commitments]

9 Albert Road, 5 units (net) 16/00321/FUL Allowed on Appeal 24 May 2017. Erection To be added to the April 2018 As at 30 September 2017: 5 n/s Site is acceptable Bancroft Housebuilder is Bracknell of 6no. flats with associated parking and bin and cycle Trajectory and has planning Developments Ltd involved. store, following demolition of existing dwelling. permission [Will be added to 2018 Commitments] (allowed on appeal)

New sites with a resolution to approve, subject to completion of a s.106 agreement: Large Sites

Building 2 60 units 17/00222/PAC Approved 21 June 2017. Application for To be added to the April 2018 As at 30 September 2017: 60 Site is acceptable Requires completion of Technology Houe, Prior Approval for the change of use of 1st, 2nd and 3rd Trajectory. n/s and has planning s.106 before The Boulevard, floor from Office (B1) use to Residential (C3) to form 60 permission, development can Cain Road no. flats. (Re-submission of 16/01062/PAC and subject to s106. commence. 17/00041/PAC). [Will be added to 2018 Commitments] Building 2 20 units 17/00442/PAC Approved 21 June 2017. Application for To be added to the April 2018 As at 30 September 2017: 20 Site is acceptable Requires completion of Technology Houe, Prior Approval for the change of use of ground floor from Trajectory. n/s and has planning s.106 before The Boulevard, Office (B1) use to Residential (C3), forming 20 no. (14 x permission, development can Cain Road one bed and 6 x two bed) units. [Will be subject to s106. commence. added to 2018 Commitments] Aspect 1-3,, 146 units 17/00408/PAC Approved 24 May 2017. Application for To be added to the April 2018 As at 30 September 2017: 146 Site is acceptable Requires completion of Wokingham Road prior approval for the change of use of the building from Trajectory. n/s and has planning s.106 before offices (B1) to residential (C3) use forming 109 no. permission, development can studios and 23 no. 1 bedroom, and 14 no. 2 bedroom, subject to s106. commence. apartments. Alternative app: 17/00407/PAC Approved 25 May 2017. Application for prior approval for the change of use of the building from offices (B1) to residential (C3) use forming 48 no. studios and 46 no. 1 bedroom, 34 no. 2 bedroom and 2 no. 3 bedroom apartments. [Will be added to 2018 Commitments]

OTV House, 130 units 17/00262/PAC Approved 13 April 2017. Application for To be added to the April 2018 As at 30 September 2017: 130 Site is acceptable Requires completion of Wokingham Road Prior Approval for change of use of existing building from Trajectory. n/s and has planning s.106 before office (B1) to residential (C3) to provide 101 no. studio permission, development can apartments and 29 no. one bedroom flats (total 130 subject to s106. commence. units) with parking for 156 no. cars and 156 no. cycles. [Will be added to 2018 Commitments]

New sites with a resolution to approve, subject to completion of a s.106 agreement: Medium Sites

Lavenir, Opladen 69 units 17/00457/PAC Approved 21 June 2017. Application for To be added to the April 2018 As at 30 September 2017: 69 Site is acceptable Requires completion of Way Prior Approval for the change of use of offices (Class Trajectory. n/s and has planning s.106 before B1a) to residential (Class C3) to form 69 no. apartments. permission, development can [Will be added to 2018 Commitments] subject to s106. commence.

Circa House, 2A 68 units 17/00315/PAC Approved 10 May 2017. Prior approval To be added to the April 2018 As at 30 September 2017: 68 Site is acceptable Stonegate Homes Requires completion of High Street change of use from B1 (office) to C3 (dwelling house) Trajectory. n/s and has planning s.106 before forming 68no. 1 bed flats. permission, development can Alternative app: 17/00295/PAC Approved 20 April 2017. subject to s106. commence. Prior approval change of use from B1 (office) to C3 (dwelling house) forming 64no. 1 bed flats. [Will be added to 2018 Commitments] Building B, 46 units 17/00264/PAC Approved 8 May 2017. Notification for To be added to the April 2018 As at 30 September 2017: 46 Site is acceptable Requires completion of Court, Prior Approval for the change of use of Ground, First and Trajectory. n/s and has planning s.106 before Western Road Second floors of Building B from Office use (B1) to permission, development can residential (C3) to provide 46 no. flats. [Will subject to s106. commence. be added to 2018 Commitments] Building A, 28 units 17/00201/PAC Approved 20 April 2017. Notification for To be added to the April 2018 As at 30 September 2017: 28 Site is acceptable Requires completion of Berkshire Court, Prior Approval for the change of use of the ground and Trajectory. n/s and has planning s.106 before Western Road first floors from Office (B1) to Residential (C3) use to permission, development can provide 28 flats (re-submission of 17/00060/PAC). subject to s106. commence. [Will be added to 2018 Commitments]

Building A, 11 units 17/00263/PAC Approved 20 April 2017. Notification for To be added to the April 2018 As at 30 September 2017: 11 Site is acceptable Requires completion of Berkshire Court, Prior Approval for the change of use of the roof space in Trajectory. n/s and has planning s.106 before Western Road Building A from Office use (B1) to residential (C3) to permission, development can provide 11 no. flats. subject to s106. commence. [Will be added to 2018 Commitments] Abbey House, 40 units 17/00562/PAC Approved 18 July 2017. Application for To be added to the April 2018 As at 30 September 2017: 40 Site is acceptable Requires completion of Grenville Place Prior Approval for the change of use of from offices Trajectory. n/s and has planning s.106 before (Class B1) to 40 no. residential units (Class C3) permission, development can comprising 34no. 1 bedroom, 5 no. 2 bedroom and 1no. subject to s106. commence. studio apartments. [Will be added to 2018 Commitments]