SELECT COMMITTEE ON HYDRO AFFAIRS

FINAL REPORT ON THESAFETYOF ONTARIO'S NUCLEAR REACTORS

THE LEGISLATIVE ASSEMBLY OF ONTARIO THIRD AND FOURTH SESSION: THIRTY-FIRST PARLIAMENT SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS

FINAL REPORT ON THE SAFETY OF ONTARIO NUCLEAR REACTORS

THE LEGISLATIVE ASSEMBLY OF ONTARIO THIRD AND FOURTH SESSION: THIRTY-FIRST PARLIAMENT

MEMBERS Donald C MacDonald, M.P.P., Chairman Jim Foulds, M.P.P., Vice Chairman Port Arthur George Ashe, M.P.P. 3. Albert Beianger, M.P.P. Prescott-Russell Sean G. Conway, M.P.P. Sam L. Cureatz, M.P.P. , M.P.P. Ray Haggerty, M.P.P. Erie Mickey Hennessy, M.P.P. Fort William Vince Kerrio, M.P.P. Niagara Falls Nicholas G. Leluk, M.P.P. York West Bob Mackenzie» M.P.P. Hamilton East Julian Reed, M.P.P. Halton-Burlington John Williams, M.P.P. Oriole

Alan M. Schwartz Siegal, Fogler - Barrister and Solicitors Consultant James D. Fisher - The Canada Consulting Group Clerk of the Committee Andrew Richardson Assistant to the Clerk James Stesky TO: THE HONOURABLE JOHN E. STOKES Speaker of the Legislative Assembly of the Province of Ontario

Sir: We, the undersigned members of the Committee appointed by the Legislative Assembly of the Province of Ontario on November 24, 1977* to inquire into various matters relating to Ontario Hydro, have the honour to submit the attached, final report on The Safety of Ontario's Nuclear Reactors.

Donald C. MacDonald, M.P.P. York South Chairman

I.P.P. Port Arthur } Chairman ^y

inway, Renfrew Nor

Evelyn Gigantes, MJP.P. Raj Durham East arleton East

Mickey HennessyV M.P.P. _ I Vince M.P.P. Nicholas G. Leluk, M.P.P: Fort William. >V Ni York West JL Bob Mackenzie, M.P.P. WiUiams, M.P.P. Hamilton East Oriole

* - Mr. Cureatz replaced Mr. MeNeü on April 17,1979; Mr. Conway replaced Mr. Kerrio on May 31,1979; Mr. Kerrio replaced Mr. Nixon on December 20,1979; Mr. Mackenzie replaced Mr. Di Santo on June 19,1979. FIN AL REPORT ON

THE SAFETY OF

ONTARIO'S NUCLEAR REACTORS

TABLE OF CONTENTS

INTRODUCTION 1

CHAPTER 1: THE FIRST FULLY PUBLIC HEARING , 3

CHAPTER 2: THE SAFETY OF ONTARIO'S NUCLEAR REACTORS. . . 5

ONTARIO'S NUCLEAR REACTORS 6

OPERATING REACTORS ARE 'ACCEPTABLY SAFE' . 13 Radiation Release Standards 13 Safety Analysis & Research IS Basic Design Features 21 Lessons From The Significant Events 26

WEAKNESSES IN HUMAN PROCESSES 27

SPECIAL REFERENCE TO NPD REACTOR '29

CHAPTER 3: THE REGULATION OF NUCLEAR POWER SAFETY ... 33

GOOD FEATURES WORTH STRENGTHENING .... 33 Onus on the Owner/Operator 34 Basic Standards Are Sound . . *. 34 Staff are Competent and Independent 37

REGULATORY PROCESS OCCASIONALLY FAILS . . 39 Bruce "A" Shutdown Systems 39 Early Licensing of Bruce "A" 40

MORE CHANGES NEEDED 40 Reducing Vagueness and Uncertainty 41 Change Board Composition & Functioning 43'

DISSENTS 45 FINAL REPORT ON THE SAFETY OF

ONTARIO'S NUCLEAR REACTORS

TABLE OF CONTENTS (continued)

APPENDICES

APPENDIX A: TERMS OF REFERENCE

APPENDIX B; CHRONOLOGY OF THE RECORD OF HEARINGS INTO THE SAFETY OF NUCLEAR REACTORS IN ONTARIO

APPENDIX C: LIST OF WITNESSES APPEARING BEFORE THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS

APPENDIX D: LIST OF EXHIBITS TABLED IN MEETINGS FROM APRIL 25, 1979 TO APRIL 10, 1980

APPENDIX E: INFORMATION PROVIDED BY ONTARIO HYDRO TO THE LEGISLATIVE LIBRARY FOR THE PURPOSES OF, AND USE BY, THE PUBLIC AND THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS (*36 Volumes)

APPENDIX F: CORRESPONDENCE BETWEEN AECL-AECB-ONTARIO HYDRO SUBMITTED TO THE LEGISLATIVE LIBRARY FOR THE PURPOSES OF, AND USE BY, THE PUBLIC AND THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS

APPENDIX G: LIST OF RECOMMENDATIONS INTRODUCTION INTRODUCTION

The Select Committee on Ontario Hydro Affairs was established by the Legislative Assembly of the Province of Ontario on November 2*, 1977 with Mr. Donald C. MacDonald, M.P.P. (York South) as Chairman, to examine and report on several matters relating to the activities of Ontario Hydro. The Committee's complete terms of reference are. Appendix A to this report. In March, 1978, the Committee tabled with the Legislature its report on Ontario Hydro's proposed uranium contracts with both Denison and Preston Mines. In October, 1978, it tabled its report on the construction of the heavy water plants at the Bruce nuclear site. During November, 1978, the Committee submitted an interim report dealing with Ontario's future commitment to nuclear power. This report contains the Committee's conclusions and recommendations on one aspect of its examination of Ontario's nuclear commitment, the safety of Ontario's nuclear reactors. Another report on a second aspect of the nuclear commitment,, the final disposal of nuclear fuel wastes is also being submitted this month. Later this year, the Committee will investigate a third aspect, safety in the mining, milling and refining of uranium. Throughout the reactor safety hearings, the Committee was aware of the motion passed by the Legislative Assembly on June 14, 1979, specifically directing it to consider "....the concerns expressed with respect to Rolphton (NPD) ...." Specific safety-related concerns about the small, demonstration reactor near Roiphton had first been raised before the Committee by a group of local citizens, banded together as the Renfrew County Citizens for Nuclear Responsibility. In order to meet the special directions of the Legislature, the Committee toured the facility, conducted a well publicized, open Committee session in the nearby community of Deep River and heard, on several separate occasions, both the detailed allegations of the citizens group and the responses of the plant operator - Ontario Hydro, the plant owner - Atomic Energy of Canada Limited (AECL) and the regulator - the Atomic Energy Control Board (AECB). The Committee considered that its major task was to determine whether the people of Ontario should continue to accept the risks involved in the operation of nuclear reactors. 'Essentially this involved consideration of the likelihood that a significant proportion of the extremely large quantities of radioactivity contained in the reactor core could be released under accident conditions. A major release of this radioactivity into the atmosphere would almost immediately result in deaths and injuries from direct radiation to persons near the faulty reactor; the development of disease, some fatal, over the longer term; and the contamination of the surrounding area to an extent which would render it unuseable for some period of time.

The Committee learned that it is impossible to assure absolute safety in the operation of Ontario's nuclear reactors. There are a broad range of possible accidents and subsequent consequences with varying likelihoods of occurrence. While the design, construction and operation of Ontario's nuclear reactors is permeated with attention to safety, all possibilities cannot be foreseen or totally eliminated. Even so, given the clear commitment of Ontario Hydro and AECL to safety, the past safety record of the existing reactors and the design mechanisms to limit the consequences of possible accidents, the Committee found that the chance of a very serious accident occurring in any single reactor is extremely small and, an the basis of the information considered to date, that the reactors are, therefore, 'acceptably safe'. In so doing, the Committee recognized fully that it was making a political/societal judgement that the benefits derived from nuclear reactors are worth the risks incurred. In order to complete its examination of the Provincial nuclear commitment, the Committee intends to inquire fully into all facets of the nuclear cycle from the mining of uranium ore through to the disposal of radioactive waste and to consider all aspects of the nuclear industry. Only at the conclusion of its continuing investigation will the Committee be able to arrive at a broad overall finding on the appropriateness of Ontario's commitment to nuclear power. Prior to its intensive examination of reactor safety, the Committee conducted a preliminary examination of the management of nuclear waste during seven days of hearings in October, 1978. As weli, in May, 1979, the Committee briefly touched upon Ontario's contingency planning in light of the confusion evident in implementing contingency plans in the area of Harrisburg, Pennsylvania after the accident at the Three Mile Island nuclear station. Finally, the Committee has received the major findings on nuclear power of the Royal Commission on Electric Power Planning in the form of an interim report on nuclear power in Ontario entitled A Race Against Time and a Final Report on all aspects of electric power planning. The Committee's continuing investigation will involve careful consideration of the health, environmental, safety and economic aspects of: * mining and milling of uranium ore and disposal of mill tailings; * refining of uranium and its fabrication into pellets and, disposal of waste products from refining; * Ontario Hydro's particular strategy for adopting large multi- unit stations; and * nuclear power in relation to other alternative energy sources. Under the circumstances outlined above, it is evident that this report is not intended, and should not be viewed as, a complete response to the Committee's very broad undertaking. Rather it is a report to the Legislative Assembly on only one component, albeit an extremely important one, of the provincial nuclear commitment. A second report on the final disposal of nuclear fuel wastes, a second component of the commitment, has recently been finalized. Mining, milling, refining and fabricating will be investigated in the Committee's next set of hearings. The report itself is set out in three chapters. Chapter 1 will outline the hearing format adopted by the Committee and the emphasis placed on ensuring full public disclosure of all information deemed relevant to the decision-making process. Chapter 2 will concentrate on the safety of Ontario's nuclear reactors outlining how the reactors operate, the risks they present, and the systems designed to reduce those risks before setting out the Committee's reasons for concluding that the reactors should be considered acceptably safe. Chapter 3 will deal with the process for regulating nuclear safety, explaining the Committee's views of both its strengths and weaknesses, leading to a series of recommended changes. CHAPTER 1 THE FIRST FULLY PUBUC HEARING CHAPTER 1

THE FIRST FULLY PUBLIC HEARING

The sixteen weeks of the hearings into the safety of Ontario's nuclear reactors stretched over a full calendar year including: two weeks in April, 1979 in the wake of the serious accident at the Three Mile Island nuclear power plant; one week in May to consider several significant events that had occurred at the Bruce Generating Station; another day later in May to consider a response to alleged safety-related problems at the Nuclear Power Demonstration (NPD) Station near Rolphton; seven weeks of hearings from July 4 to August 16 and three weeks from September 18 to October 4 to consider the main issues relating to the safety of Ontario's reactors; and three weeks in February, 1980 on specific topics still outstanding at the end of 1979. The main Committee hearings were organized around five basic topics: * safety criteria and philosophy; * basic design concepts; * licensing approaches * operating history and practices; and, * compliance and reassessment procedures. In each area the Committee identified several key concerns and centred its examination on these particular topics. It ensured that its schedule provided ample time for the nuclear industry, its regulators, its critics and others to express opinions in every area of controversy examined. Appendix B is a chronology of the hearings and sets out the Committee's activities on a daily basis. A list of the nearly 100 witnesses who appeared during the session is included as Appendix C. Appendix D describes the 150 exhibits tabled with the Committee. The exhibits contain extensive information on Ontario reactors as well conclusions and opinions on nuclear power from around the world. The Committee began its examination of the safety of Ontario's nuclear reactors in the knowledge that nuclear safety was already subject to extensive regulation by the Atomic Energy Control Board (AECB). The regulatory process, however, excluded, to a large extent, significant public involvement and has, to date, done little to unwrap the shroud of secrecy within which the Canadian nuclear industry appears to operate. The Committee was also aware of the lengthy review of reactor safety undertaken by the Royal Commission on Electric Power Planning. The Commission's Interim Report on Nuclear Power in Ontario was available to the Committee before its reactor safety hearings began and the Final Report was available before the Committee had settled on its own conclusions and recommendations. The Chairman, Or. Arthur Porter, and his staff opened the hearings with a two day discussion of Ontario's nuclear reactors. Unlike the regulatory process, the work of the Royal Commission involved the public to the greatest extent possible. The Committee shared the view of the Royal Commission that "....if an informed and reasonably sophisticated public involvement in the energy debate is to be achieved, then greater and freer public access to information is essential. This is particularly important in the case of nuclear power...." The Committee noted, however, that the Royal Commission hearings

A Race Against Time, p. 65; Interim Report on Nuclear Power in Ontario, Royal Commission on Electric Power Planning, September, 1978 themselves did not result in significantly increasing the availability of information historically treated as "confidential" by both the nuclear industry and the AECB. After carefully weighing the balance between the benefits of providing greater public access to information and any possible negative safety or commercial impact fwwhich; could jjfresult --jJErom >^the 5* release $ of ^ previously,, .unavailable documentation, the Committee Irëquested and received f rom Ontario Hydro^f or its examination cJid public scrutiny, an enormous amount of information^ [mucKjof it n^eryrnade public before?|A great deal of this preyipusly|unrèlèased information, suchiaiithe significant|èvent re^rj^and Jcorrêsponde^^ and :tte^AECB,5prove^inyaluabte helping ?it;ajriyeja| "its conclusions^ iJAppendixlEllists^he^JWf -^umes)|nade/alrailable|j^^ Libraryiand vthe .Ontario?Hyd^ro^ublic «REerejic'eiCentr^l1^ Por ts'^ürity;reasons "and to protetf";OTmmerciaï interests^22Ö. volumes .were controliëd vin the sense that reader identification is obtained and machine duplicat;on of pages is not allowed.

The Gommittee also requested of AECL the release of certain documents which the Committee felt were relevant: to its deliberations. In spite of some possible jurisdictional disputes, this documentation was provided voluntarily by AECL. AECL released the documentation after consultation with Both the Department of Justice and the Atomic Energy Control Board. AËCL made it dear, however, that, the documents^Lwere being made «available* without constituting a precedent f or other requests by this or any other provincial committee. Appendix F lists the four volumes provided by AECL. The Committee believes strongly that freer public access to previously unavailable docurr.entation1'.is;:an"'essential eiement in the ongoing process of informing and involving the public in the nuclear debate. All the evidence heard by the Committee and on which it reached its conclusions was, and still is, available to the public atthe ^Legislative - Library and the Ontario Hydro Public Reference Centre. TTiat information should be regularly updated and kept current. The Committee also believes that Members of the Legislative Assembly must be immediately informed of any decision, occurrence or design reanalysis, which might be of particular interest or concern to the public,

RECOMMENDATION I ONTARIO HYDRO SHOULD CONTINUE T0 PROVIDE PUBLIC ACCESS TO ALL OF THE INFORMATION MADE AVAILABLE TO THE COMMITTEE BY KEEPING THE REPORTS NOW AVAILABLE IN THE LEGISLATIVE LIBRARY REGULARLY UPDATED AND CURRENT.

RECOMMENDATION H ONTARIO HYDRO SHOULD IMMEDIATELY ADVISE THE LEGISLATIVE ASSEMBLY, THROUGH THE MINISTER OF ENERGY, OF ANY DECISION, OCCURRENCE OR DESIGN REANALYSIS WHICH MIGHT BE OF PARTICULAR INTEREST OR CONCERN TO THE PUBLIC. CHAPTER 2 THE SAFETY OF ONTARIO'S NUCLEAR REACTORS CHAPTER 2 THE SAFETY OF ONTARIO'S NUCLEAR REACTORS

The major task of the Committee was to determine for itself whether the nuclear reactors operated in Ontario by Ontario Hydro are 'acceptably safe' and report its conclusion to the Legislative Assembly and the people of Ontario. This task was part of the Committee's original terms of reference, was made explicit for the station near Rolphton, and was, in the wake of the accident at Three Mile Island, a task the public expected that this Committee would undertake.

This chapter will set out very simply the basic functioning of Ontario's nuclear reactors, the risks they present and the systems designed to reduce the risks. It then goes on to set out four reasons for concluding that the reactors are "acceptably safe",* the areas where Hydro must show some improvement and the Committee's response to its special reference on the station at Rolphton. Before getting into any of these details, however, the concept of 'safety' is discussed.

The Committee would like to be able to say, simply and directly.... 'Ontario's reactors are safe1, or — 'Ontario's reactors are not safe'. It would be desirable to be able to say to the public .... 'A catastrophic nuclear accident at an Ontario reactor is impossible'. Direct, simple statements cannot be made. It is not possible to say that a nuclear reactor is absolutely safe; there are risks associated with nuclear power. It is not right to say that a catastrophic accident is impossible; there is always some chance that the worst can happen.

In a situation where absolutes are misleading, the Committee is forced to make relative judgements. If there is some chance of a catastrophic accident, that chance must be suitably small. If it is not possible to say that Ontario's reactors are absolutely safe, then they must, if allowed to operate, be judged 'acceptably safe' for continued operation. There must be a political/societal judgement that the risks from a nuclear reactor are worth its benefits — competitively-priced, Ontario-based energy from power generating stations that are relatively non- polluting in normal operation.

Although this is a difficult judgement to make, society has always made judgements of this type. For example, motor vehicles are widely accepted in our society despite the fact that in Ontario alone about 2,000 people are killed and many more injured every year in accidents involving motor vehicles. Although few would deny that we should continue to try to make motor vehicles safer, motor vehicles are accepted as they are today. They are 'acceptably safe'.

The risks from nuclear power are much different from those involving motor vehicles. Although there are potential risks in the routine operation of nuclear reactors from the production and release of various radioactive materials, it is the threat of catastrophic accidents that is of concern to most people. The worst possible accident involving a nuclear reactor, such as the accident scenarios identified in -tudies of U.S. reactors, could involve the spread of radioactive poisons over large areas, killing thousands immediately, killing others through increasing susceptibility to cancer, risking genetic defects that could affect future generations and possibly contaminating large land areas for further habitation or cultivation.

2 dissent of Members Foulds, Gigantes and Mackenzie The nuclear industry and its regulator recognize the potential danger of atomic energy and have taken elaborate precautions to ensure that dangers are minimized as far as is considered reasonable. A key element in determining what is 'reasonable' is the technical concept of risk. To a layman, 'risk' is a relative term: a risky operation would be one in which there is a high probability ox an undesirable outcome. In the scientific community, risk is a precise term, defined mathematically as probability times consequence: probability being the chance of some kind of accident happening and consequence the effect on individuals or property of the accident. Thus every human action involves risk, even if the risk is something as improbable as colliding with a falling meteorite. The NPD station, for example, was licensed on the basis that the total risk to human life would never be greater than 1 chance in 100 that one person might die in any year from the operation of the plant. The scientific assessment of that level of risk (risk = probability x consequence) would equate that 1 chance in 100 for one person to a one in one thousand chance that 10 might die, a one in ten thousand chance that 100 might die, or a one in one million chance that 10,000 might die. Scientifically defined, the risk is constant.

The scie *if ic concept of risk underlies the Canadian and international approaches to nuclear safety. Thus the industry response to a potential accident of very high consequence is to design equipment and procedures that make it increasingly improbable. The earliest commercial reactor (NPD) was licensed on the basis of constant risk (i.e. the designer always tried to equate the risk of any accident — of high or low consequence — to the average of one chance in 100 of killing one person). In the later reactors, the concept of diminishing risk was introduced recognizing that people are more concerned about larger accidents than smaller ones. Thus the scientifically defined risk of the accident of higher consequence must be lower than the scientifically defined risk of the accident of lower consequences. The plant designer achieves this by changing the safety systems or equipment either to reduce the consequence of the larger accident or to make it more improbable.

The Committee understands the logic of the scientific approach and the need for designers to have specific safety targets to work toward. However, for its own evaluation of nuclear safety, the mathematical rigidity of the scientific approach was difficult to accept. The more familiar the Committee became with nuclear technology and the limitations of strict mathematical approaches, the more it realized that mathematical calculations of risk can only be a general guide. Ultimately the decision whether to consider nuclear reactors 'acceptably safe' is a subjectively judgemental one based on a large number of factors outlined in the sections below.

ONTARIO'S NUCLEAR REACTORS

All Ontario Hydro's nuclear reactors are CANDU-PHW design. (CANada Deuterium Uranium - Pressurized Heavy Water). CANDU is a totally Canadian technology, conceived~by AECL, then developed, implemented and refined in conjunction with Ontario Hydro and private sector component manufacturers. Ontario Hydro's current commitments call for 22 reactors in Ontario by the early 1990s. The ten commercial reactors currently operating in Ontario are the 22 megawatt Nuclear Power Demonstration reactor hear Rolphton (north of ), the 208 megawatt reactor at the Bruce Nuclear Power Development on Lake Huron at Douglas Point, four 516 megawatt reactors at Pickering, just east of , and four 750 megawatt reactors also at the Bruce Nuclear Power Development. A 'megawatt' is the unit that is used to measure the size of an electricity generating station; a 'kilowatt hour' is the unit normally used to bill a residential customer. If a one megawatt (1,000 kilowatts) station produced electricity continuously throughout the year (8,760 hours), it would produce 8,760,000 kilowatt hours. In Ontario in 1980, Ontario Hydro expects to be called upon by its customers to produce over 102 billion kilowatt hours of electricity throughout the year and be capable of meeting a peak demand of 17,100 megawatts.

Ontario Hydro has twelve further reactors at various stages of construction. Four reactors are being built f or a second station at Pickering that will come into service in stages from 1982 to 1983. Four reactors are being built for a third station at Bruce to come into service from 1983 to 1987. Another four reactors are being built at a new site near Newcastle called Darlington for planned in- service dates of 1988 to 1991. The entire Ontario nuclear program can be described in superlatives.

The stations are large:

The planned Darlington station will be among the largest nuclear stations in the world. The Bruce complex — 2 four-unit stations, Bruce "A" and Bruce "B", plus a one unit station, Douglas Point — is the largest nuclear - complex in the world.

The Pickering complex — 2 four-unit stations, Pickering A and Pickering B — is the largest nuclear complex in an urban setting in the world.

They have performed well:

Since the Pickering A station was commissioned, one or more units have operated over 90% of the time in every year except one, making that station one of the world leaders in dependability.

And the entire program is enormous:

When all stations currently under construction are completed, there will be nearly 14,000 megawatts of nuclear capacity — or theoretically enough to have met Ontario's total electric needs throughout most of the current year.

The heart of the CANDU nuclear reactor is the 'calandria' — a large, cylindrical tank set on its side and filled with heavy water. The calandria is pierced by 300 to 500 tubes running horizontally from one end to the other. (The Douglas Point reactor has 306 tubes, Pickering has 390 tubes, and Bruce has 480). Inside the calandria tubes and separated from them by an inert gas are the pressure tubes. Uranium, in the form of ceramic uranium dioxide pellets is sealed into small tubes made of 'Zircaloy', an alloy of zirconium. Zi.-caloy bearing pacts Zircaloy end cap spacars

"' Ovsr 90% ct the radioactive ISssion products are in the solid fuel. La» th«n 10% ol the radioactive fission products are Zircaloy structural end plate Graphite coating In the fuel sheath gap.

The tubes containing the fuel are assembled into a bundle, and the fuel bundle is placed inside the pressure tubes. (Douglas Point fuel bundles have 19 tubes, Pickering bundles have 28, and Bruce bundles have 37). When all the elements ~ tne uranium, the heavy water and various regulating and control mechanisms — are in the right position, same of the uranium atoms begin to "fission" or break apart. As the uranium atoms fission, heat is produced. Heavy water, at high pressure, is pumped through the pressure tubes to remove the heat and use it to produce steam in a completely separate circuit of ordinary water that turns a turbine to produce electricity. The simple chart below shows the basic CANDU process.

4. Turbine shaft turns S. Power lines take electric power to generator rotor to communities generate electricity 3. Steam Turbine pressure turns turbine

2. 'Heavy water'coolant transfers heat from fuel to boiler wh«re ordinary water is turned Into steam

6. Lake or river water coots used steam to condense it to water

7. Water pumped back to trie boiler Pump

1. Heat produced by fissioning uranium fuel in reactor- The amount of heat produced in this almost mysterious breaking apart of the uranium atom is enormous. The heavy water passes 20 feet through the calandria in one second and rises 50 C degrees. One fuel bundle contains as much heat energy as 500 tons or about 12 train car loads of coal. The continuous circulation of heavy water keeps the temperature of the pressure tubes at about 300 C degrees or well below the point at which the fuel might melt (2800 C degrees), the Zircaloy fuel bundle might melt (1700 C degrees) or the fuel bundle might be seriously weakened (1000 C degrees). Among the most serious safety concerns is the suppression or loss of flow of coolant due to a burst pipe. If active fuel is not cooled by one of the normal process systems or emergency systems, the fuel will melt and release its radioactivity into the reactor building. CANDU reactors have a number of safety systems designed to keep the fuel from approaching dangerously high temperatures.

As soon as sensors located throughout the reactor detect any sign of a safety problem with the reactor, special systems act to shut down the machine. At Pickering and Bruce, shutdown is achieved by dropping 'shut down rods1 into the reactor, and either dumping the heavy water moderator in the calandria (Pickering) or injecting a chemical "poison" into it (Bruce). Although the shutdown mechanisms act quickly to reduce reactor power, the nature of the fission reactor is such that heat continues to be produced by the fuel for many hours after the reactor is shut down. The amount of heat produced from the continuing decay of the fuel reduces very quickly to a small percentage of its full power — in one minute it f alls to *% of full power —then, gradually, over many hours, the decay process slows to a negligible level. Three hours after shutdown the power level will have fallen to 1%. This gradually declining decay heat, while small in relation to the full power produced under normal conditions, is still very significant. Cooling must be maintained for months after a shutdown before the decay heat becomes insignificant enough that it can be removed by the air surrounding the fuel. Thus, all CANDU reactors have emergency cooling systems to provide continuous cooling if an accident disrupts the normal cooling system.

There are also many systems and design features in a CANDU reactor to prevent poisonous radioactive gases from reaching the public in significant concentrations. Among the most important are what are referred to as the multiple barriers of defence — the five barriers between the radioactive poisons in the fuel and the public. These are:

(i) The fuel itself; (ii) The sheathing in the fuel bundle; (iii) The heat transport system and calandria; (iv) The containment structures; and (v) The exclusion zone.

Each is described briefly below:

(i) The uranium dioxide (UO2) fuel is the first barrier to the release of fission products. UO2 is a ceramic with a high melting point and is chemically inactive in water. Most of the radioactive fission products are permanently retained in the ceramic pellet at operating temperatures, and a small fraction (up to 10%) of the gaseous fission products are released into the gases within the tubes. 10

(ii) Each fuel element is sheathed with Zircaloy which forms the second barrier to fission product release. The sheath is designed to withstand the stresses resulting from DO-, expansion and fission gas pressures, external hydraulic pressures and the mechanical loads imposed by fuel handling as well as the stresses caused by small accidents.

(iii) The coolant is. contained in a closed heat transport system which forms the third barrier to fission product release. All the high-pressure piping is designed with a safety factor between the' working and ultimate stresses. In most conceivable accidents, this piping must fail before fission products in the coolant are released to the containment system. In addition, the pressure tubes are inside calandria tubes which are normally kept at about 150 F degrees by the relatively cool heavy water moderator that is cooled by a separate system, and held inside the stainless steel calandria vessel that is, itself, surrounded by a cooled shield.

(iv) The reactor and heat transport system are housed in a concrete containment system that is pierced by the piping and boiler systems necessary to produce usable energy and provide access for the safety systems and by airlocks and ventilation dampers. This safety system is the fourth barrier to fission product release. There are two basic containment systems used in Canada: the vacuum building system used on multi-unit'stations, and the single-building containment system adopted for single unit stations.

(v) No residences are allowed in a zone of 3,000 feet radius from the plant. This exclusion zone is the filtii barrier. The atmospheric dilution between the plant and the boundary of this zone reduces the concentration of any fission product release from the containment system by 100 to 1000 times.

Several other features of the CANDU design are conducive to enhanced safety. The combination of natural uranium fuel and heavy water moderator has significant safety advantages. Natural uranium fuel cannot become "critical" or begin to have its atoms continuously break apart or fission without the heavy water moderator. Therefore if the heavy water in the moderator is lost through a serious leak, the heat production from the fuel will eventually cease on its own. This is not the case in enriched fuel reactors that are being used and developed around the world. In these reactors, the fuel could theoretically continue to be "critical" after a very serious accident that left a molten mass of enriched fuel on the reactor floor. In light water reactors there is even a problem of a reactor becoming 'recritical' when emergency light water is pumped into the core following an accident involving the loss of normal coolant.

Other safety features of Ontario reactors include:

* The pressure tube concept (rather than the American pressure vessel) which keeps shutoff and control mechanisms in the low pressure parts of the system where they cannot be driven out by extreme pressure accident;

* The ability of the secondary heat transport systems — such as the boilers —to absorb up to 30 minutes of heat build-up before other action must be taken if the reactor is shut down and f eedwater is still available; 11

* And the general features of the control systems allow reactor power to build-up slowly, but be stopped quickly.

Even with all these safety features and design concepts, it is still possible for a serious accident to take place. Among the most serious is the complete loss of cooling to the reactor caused by a break in the main heat transport piping. A major piping failure calls on the emergency coolant injection system to come into play as well as other safety features described above.

A major piping failure causes:

* an immediate surge in power due to a complex set of phenomena brought about by the cooling system depressurizing through the pipe break — requiring the shut down systems to act quickly.

* decreased cooling of the fuel — requiring the addition of water from the emergency coolant injection system to maintain cooling to the fuel, and

* the release of energy and radioactivity to the building via flashing coolant — bringing the "vacuum building" into action.

In order to reduce to an acceptable level the chance that this or any other believable accident sequence will seriously harm the public, many accident sequences are carefully analyzed. The Committee pressed the expert witnesses that appeared before it to outline one of the sequences of events which, though highly improbable, is conceivable, and could lead to an accident of very severe consequence. The sequence presented is highly unlikely because it requires several, simultaneous serious failures and, since there has never been a serious accident in one of the commercial CANDU. reactors, the scenario requires a number of assumptions that have never been proven. The sequence could involve:

* a pipe rupture causes a loss of coolant in the reactor. As the heat builds up, various instruments detect the changes occurring in the systems and activate control and shutdown systems to quickly bring the reactor power down,

* the pipe rupture is the worst kind and in the worst location, reducing the effectiveness of emergency cooling so that the heat build up causes the tubes that make up the fuel bundles to slump or sag and the pressure tubes to sag against the calandria tubes,

* ineffectiveness of emergency cooling and failure of the moderator cooling system allows the heat of the pressure tubes and fuel bundles to continue to rise, causing the fuel bundles to fall apart and the pressure tubes and then the calandria tubes, to sag and break,

* the broken distorted interior of the calandria is such that effective cooling cannot be brought to bear, 12

* as the decay heat builds up the Zircaloy tubes begin to melt. As the melting zirconium comes in contact with steam from the cooling water being poured into the reactor, small heat- producing explosions take place,

* the breaks in piping and pressure relief valves on the calandria opened by steam pressure- permit radioactive steam to flash into the reactor building and thus into the entire containment system,

* the containment system fails to function properly and the radioactive gases are released to the atmosphere where poor dispersion conditions carry them in a concentrated state over a populated area.

This accident sequence would be considered, at the least, to be a "triple failure" accident:

(1) failure of the regular cooling systems including the primary heat transport system and the moderator cooling system;

(2) failure of the emergency coolant injection system; and,

(3) failure of the containment system — compounded by the worst weather conditions.

Although there are many arguments among nuclear engineers over how hypothetical accident sequences could develop, there is no' question that if all the heat sinks are lost and there are holes in containment an accident with extremely serious public consequences will result.

Ontario Hydro is required to demonstrate to the nuclear regulatory agency, the AECB, that the performance and reliability of its process systems and safety systems are very high so that the chance of a serious accident occurring is very small. Each of the safety systems must be independent of the process systems and independent of each other to the greatest extent possible. Each safety system must be tested and maintained to be shown to be available to function 99.7% of the time at Pickering and 99.9% of the time at Bruce. In the event of a dual failure — and the worst design basis dual failure that is required to be analyzed is the worst possible failure of the process cooling system and a major impairment of containment — the consequences of the failure must be limited. A single failure ~ the cooling system pipe break — must be accommodated within the 500 millirem to the most exposed individual normal release limit of routine activity.

This section has described the way a CANOU reactor operates, the basic safety features and a very severe accident that could happen. In the next section it will outline the four reasons that the Committee considers Ontario's reactors 'acceptably safe'. 13

OPERATING REACTORS ARE 'ACCEPTABLY SAFE' The Committee concluded on the basis of evidence examined so far that the nuclear reactors operated by Ontario Hydro are 'acceptably safe'. The Committee reached this conclusion while being fully aware that there are real risks in the peaceful use of nuclear power and that absolute safety can never be totally assured. To reach the conclusion, the Committee had to satisfy itself in four areas: the effects of radiation; the safety analysis and research carried out by the industry; the basic design; and the lessons learned from examining the incidents at the station that are recorded in abnormal or significant event report.

Radiation Release Standards The Committee found that it had to reach its own conclusion on the probable effect of radiation on human health and the appropriateness of standards currently in effect. Actual and potential radiation releases are the main health hazard in the operation of nuclear reactors (as opposed to the actual and potential fire, explosion and atmospheric pollution dangers of fossil fuel energy sources). In the normal operation of nuclear plants, workers are exposed to small radiation leaks throughout the plant and the public is exposed to very small, but continuous releases of radioactive emissions into the water and air. In the event of a serious accident, the critical health consequences will come from the effect of the radioactive gases and particles that could be released to the atmosphere. Therefore, all conclusions on whether reactors are safe enough in normal operation and any assessment of the consequences of large scale accidents depend upon the effect that radiation might have on human health.

In a general sense, the effects of radiation on human health are well known. Alpha, beta and gamma radiation penetrate tissue to varying extents, disrupting the normal cellular structure. At very high levels of exposure, say 500 rem, radiation sickness is fatal within a few days. At more moderate levels, say 25 rem, the damage is manifest in noticeably increased risk of cancers that may occur in three years or after a latency period of ten to twenty years. As well, studies with non-human organisms indicate that radiation can cause genetic disorders that affect future generations.

The biological effects of radiation are said to have been more extensively studied than those of any other toxic material. And, the handling of irradiated materials is, generally, far more careful than that of other toxics. Nevertheless, there is some controversy about the effects of radiation on human health. The main area of dispute is about the effects of very low level exposures. Most of the reliable health effects data has been collected on populations who have received very high doses — such as the survivors of the atomic bomb explosions at Hiroshima and Nagasaki and patients who have received massive radiation treatments.

There are three schools of thought on the effects of very low levels of radiation.

* The majority of experts believe that the risks to human health decrease substantially at low levels. In addition to citing experimental evidence on threshold limits, they reason that the human (and other organisms) have developed a repair capability to ccpe with the 100 to 150 millirem of background radiation every year from natural sources such as cosmic rays, radium and radon in building materials, and potassium in our bodies, as well as from man-made sources such as X-rays, colour television sets, and the fall-out from early atomic weapon tests. In the minds of many experts, it is unlikely that very slight increases over the natural background levels or exposures that fall within the normal variation in background radiation could have a noticeable effect on human health.

* A second view, accepted by most bodies responsible for setting exposure standards is that the health effects of very low levels of radiation should be considered to be directly proportional to the effects at higher levels with no safe "threshold" dose. The "linear no-threshold hypothesis" is believed by nuclear regulators to be a conservative approach for setting standards in an area of continuing uncertainty, rather than a scientifically proven hypothesis.

* A third view, held by a very small number of researchers is that the "linear no-threshold hypothesis" understates the effects of very low levels of radiation. Several studies published in recent years claim to demonstrate that health effects of accumulating radiation at very low levels might be greater than is allowed for by the "linear hypothesis".

It is very difficult to prove conclusively that any of the views is entirely correct. In fact, even those who hold the view that the low level risk may be higher than previously estimated agree that the absolute number of additional cases is very, very small and the cases are unlikely to appear for as much as twenty years after the dose is received. The problem of proving or disproving one point of view then is to find a very large group of people who have received very small doses of radiation, track their medical records for twenty to thirty years and compare them to another large group similar in all respects except for the exposure to radiation. Since about 20% of the population will ultimately contract fatal cancer for reasons having nothing to do with the operation of nuclear power plants, anyone familiar with the problems of epidemiological studies will not be surprised that there are no conclusive long-term results.

In the light of this continuing uncertainty the Committee concluded that the "linear no-threshold hypothesis'* is appropriate for standard-setting. It is a standard accepted by international authorities, by North American authorities and by recent special scientific panels. The Committee was impressed, however, by the continuing attention that must be paid to questions of radiation health effects. There are suggestions that the exposure limits for workers should be related to the workers' age. Younger workers, according to one theory should have lower exposure than older workers. Another suggestion is that total exposures should be regulated — including both occupational exposures and exposures for medical or dental purposes. As well, studies that appear to show increased danger at low levels need continuous review. The routine emissions from nuclear reactors include a number of different elements. Two were of special interest to the Committee, carbon - 1* and tritium (or hydrogen -3). In 1978, the principal airborne releases of radioactivity from Pickering A were measured at 26,000 curies of tritium, 4,100 curies of noble gases and assumed to be 1,100 curies of carbon-14. (A curie is a common unit for measuring the radioactivity from different elements.) Although all releases are of concern and require emission standards, the noble gases are of somewhat less concern because their short half-life (a few hours to a few days) ensures that they cannot accumulate in the environment.

Carbon-1* and tritium are of comparable and special concern for similar reasons. First, they each have long half-lives: 5,730 years for carbon-14 and 12.3 years for tritium. Long half-lives allow them to accumulate in the environment around a reactor and in the global biosphere. Second, they are easily incorporated into human tissue. Carbon-14 is incorporated into the carbon that comprises about 18% of total body weight, including the fatty tissue, proteins and ON A. Tritium is incorporated into all parts of the body that contain water. Thus the radiological significance of both elements is not related to their inherent toxicity, as each is a very low energy form of radiation, but to their easy incorporation in the body.

The basis for regulatory emission standards is the 'safe limits' established by the International Council for Radiological Protection (ICRP). The ICRP is an international body drawn from experts in radiology from all over the world, and including many of the leading authorities in radiological protection. Some critics claim it is a self perpetuating body drawn from the nuclear establishment with no inclination to 'rock the boat' by imposing overly tight standards. Its supporters claim that it is made up of leading scientists and medical doctors whose reputation is beyond repute and who safeguard the independence of the Commission by not allowing membership selection by political bodies.

The ICRP has a Chairman and permanent Secretariat who call the Commission together when, in their opinion, there is a need to review overall or specific standards. The ICRP have established a 'safe limit' of 500 millirem per year for the most exposed individual from a nuclear facility and 5 rem or 5,000 millirem per year for workers. (Rem is the unit used to measure the exposure of man to radiation; mUlirem is 1/1,000 rem). The ICRP also emphasize the "ALARA' principle which means that despite the 'safe limit', radiation doses should be kept As Low As Reasonably Achievable, economic and social factors being taken into account.

The AECB, as a matter of explicit policy, accepts the ICRP approach and specific standards. In their view it provides the most authoritative basis for setting emissions standards for radioactive products. The AECB take responsibility for the next phase of regulatory control, reviewing and approving the specific allowable levels for the various categories of radioactive releases, including air and water borne tritium, iodine, noble gases, and particulates and establishing limits for normal operations and accident conditions. The AECB require the licencee to conduct a "pathways analysis", analyzing the various pathways by which the radioactivity can reach man and determining the resultant radiation dose to the most exposed individual. On the basis of this analysis, the AECB then set derived release limits that equate curies of radioactive releases to the ICRP limit of 500 millirem to the most exposed individual. 16

In the routine operation of nuclear reactors, emissions can be kept considerably lower than the derived limit. Designers and operators of Hydro stations set a release target of 1% from each category of radioactive release. In most cases the targets can be met. For example, Hydro's pathways analysis shows that they could release 10,400,000 curies of airborne tritium before the most exposed individual in the public would receive a dose of 500 millirem. The release target is set at 1% of that derived limit or 104,000 curies. In 1978 the Pickering release was 26,000 curies or 1/4 of 1% of the'derived limit resulting in a dose to the theoretically calculated "most exposed individual" of about 1 1/4 millirem. Dr. E. P. Radford, a Professor of Environmental Epidemiology at the University of Pittsburgh was critical of this approach when he appeared as a witness before the Committee. Dr. Radford is familiar with radiation protection as the Chairman of the National Academy of Science's Committee on the Biological Effects of Ionizing Radiation. Dr. Radford believes that regulatory authorities should set the regulatory limits at the low levels' that can be achieved by careful design and operation - the 1% level - rather than accepting the potential risks implicit in the ICRP's 'safe limit'.

At this time there is no derived release limit for carbon-14 for two reasons. First, the low energy level of carbon-14 and its very low concentration principally in the carbon dioxide and carbon monoxide gases released from the stations have made it very difficult to measure accurately the actual releases. Second, it has been assumed that releases were so far below any limits that might be set that it was not necessary to specify limits and require routine monitoring and reporting on them. Ontario Hydro's Health Physics Branch recently concluded some work on measuring releases and on tracing pathways to man that could result in a dose to the most exposed individual that is somewhere between a small fraction of a millirem and 2 1/2 millirem. At that potential dose level the AECB has become more interested in carbon-14 and is now awaiting a submission from Ontario Hydro on derived release limits and operating targets.

By focussing on carbon-14 at this preliminary stage of developing a derived release limit, the Committee was able to see clearly the range of assumptions that make up a pathways analysis and the consequent uncertainty in the very specific calculations that are made. At this time the uncertainties are in:

The actual emissions. Hydro has made theoretical calculations of the amount of car bon-14 produced in various parts of the station. Knowledge of the amount released is less certain. The carbon-14 content in vegetation surrounding the plant is not as high as it should be if the calculated release;, were correct.

The amoi.it taken up by man. Authorities are quite certain that the only significant pathway to man is through food grown in the vie!.*üty of the stations. Calculations of carbon-14 ingestion are based on a mix of foods of varying carbon content assumed to be grown at the plant boundary. Since different foods have different carbon content, the mix chosen for the calculation will result in widely varying doses of carbon-14. As well, assumptions have to be made of the proportion of the food that comes from the vicinity of the plant. 17

In addition to these admitted uncertainties, the Committee itself was concerned that neither Ontario Hydro nor AECB know enough about the propensity of carbon-14 to accumulate in the food chain and biosphere around a plant, and the rate at which it is dispersed as it moves further from the source.

Carbon-14 is not just a problem of the 'most exposed individual'. Its long half-life makes it a problem for the global environment. In 1977 a group of experts of the OECD's Nuclear Energy Agency identified four nudides that may be of greater global than of local concern. The four are krypton -85, iodine -129, tritium and carbon-14. The half-lives of these nudides vary from 10.8 years for krypton -85, to 12.3 years for tritium, 5,730 years for carbon-14 and 17 million years for iodine -129. Each of these elements occurs naturally in the environment as a result of the interaction of cosmic rays from the sun with the atmosphere. They are of concern in nuclear power programs because their artificial production is a significant proportion of the natural production which will result in an increase in the global inventory of each nudide. The large-scale atmospheric testing of nuclear weapons in the '50s did, in fact, result in large increases in the global inventory. Since atmospheric testing ended, global inventories in man's immediate environment have been dedining as these elements sink into the deep oceans.

As long as Canada does not reprocess its used fuel, krypton -85 and iodine -129 are of lesser importance to Canadian regulators. These nuclides remain bound up in the used fuel and will only be released in reprocessing or in a severe accident involving fuel melting. Tritium and carbon-14 are cf special concern to Canada.

In heavy water reactors, a relatively small proportion of the tritium is bound up in the fuel. Most is produced in the large quantities of heavy water moderator and coolant. Inevitably, significant amounts are released in the air and water.

CANOU reactors produce about 20 times as much carbon-14 as light water reactors. Only a negligible amount is bound up in the fuel.

The Committee is concerned that Canada - and Ontario in particular - may have a spedal global responsibility for controlling carbon-14 and tritium that goes beyond consideration of local effects. Although Ontario Hydro and AECL have programs ongoing to consider ways of further reducing tritium and carbon-14 releases, there is no national or regulatory framework for guiding their implementation.

The Committee also noted that radiation protection and the appropriateness of radiation standards is a health topic of great concern to people in Ontario — the workers in the industry and populations located near industry facilities. Legislative responsibility for nuclear safety rests with the Federal government and Ontario has deferred responsibility to the AECB.

The AECB, with its limited staff, accepts the recommendations of the ICRP. The major Canadian role in standard-setting has been to provide representatives ~ and in one case the chairman •— to the ICRP from AECL. Thus, the basic Canadian regulatory standards come from a body reputed to be dominated by those the critics call the nuclear establishment — manufacturers, utilities, regulators. 18

The AECB has recently established an advisory committee of experts in radiation including some people from outside the "nuclear establishment."

The Committee believes that there is an additional need to provide a body that can focus on Ontario problems, that can do so openly and with participation from the public, and that can relate directly to the federal body.

RECOMMENDATION III A COUNCIL SHOULD BE FORMED BY THE GOVERNMENT OF ONTARIO WITH GIVEN TERMS OF REFERENCE AND REPRESENTATION FROM WITHIN AND OUTSIDE THE NUCLEAR ESTABLISHMENT TO PROVIDE AN INSTITUTIONAL FORUM FOR PUBLIC PARTICIPATION AND A FOCUS FOR CONCERNS ABOUT RADIATION PROBLEMS IN ONTARIO, TO BUILD UP ONTARIO-BASED TECHNICAL KNOWLEDGE AND TO OVERSEE AS MUCH EPIDEMIOLOGICAL WORK AS IS NECESSARY TO DECIDE WHAT THE STANDARDS SHOULD BE FOR THE HEALTH AND SAFETY OF PEOPLE IN ONTARIO.

THE COUNCIL SHOULD REVIEW PARTICULAR PROBLEMS OF RADIATION ASSOCIATED WITH OPERATING OR PLANNED REACTORS, INDEPENDENT OF ONTARIO HYDRO AND THE GOVERNMENT. THE COUNCIL SHOULD WORK TOWARD THE ESTABLISHMENT OF A FEDERAL-PROVINCIAL WORKING GROUP TO CO-ORDINATE THE NATIONAL STANDARDS WITH THE WORK AND FINDINGS OF THE PROVINCIAL GROUP. THE POWERS OF THE COUNCIL SHOULD BE THAT OF MAKING INDEPENDENT AND PUBLIC RECOMMENDATIONS TO AN APPROPRIATE MINISTER.

RECOMMENDATION IV ONE OF THE FIRST TASKS THE COUNCIL SHOULD TAKE ON AND GIVE HIGH PRIORITY TO IS AN INDEPENDENT REVIEW OF THE ADEQUACY OF CURRENT PROPOSED RELEASE LIMITS FOR CARBON-14 AND TRITIUM, TAKING INTO ACCOUNT BOTH LOCAL AND GLOBAL CONCERNS.

Safety Analysis & Research

The operation of the nuclear power generating stations in Ontario is the end product of a great deal of applied research and development conducted in Canada over the past thirty-five years. One of the reasons that the Committee has concluded that the reactors operated by Ontario Hydro are "acceptably safe" is that the safety analysis and research carried out both before and after the reactors are built is very impressive.

Canada's first heavy water moderated research reactor - NRX - was built at Chalk River in 1947. Extensive research with this reactor and the experience gained with it — including the famous accident that President Carter, as a junior U.S. naval officer, helped clean up - led to the building of a second reactor - NRU - in 1957. The NRU reactor was the foundation for the development of a reactor capable of generating electricity at commercial scale. The first prototype 19

commercial reactor was the Nuclear Power Demonstration (NPD) reactor at Rolphton commissioned in 1962. Success with this reactor, in both safety and operational terms led to the development of the current massive nuclear program of Ontario Hydro. This program then was built upon a solid base of research, experimentation and experience with nuclear power. Many believe the development of the CANDU reactor is one of Canada's most outstanding technological achievements.

As each station is designed and built, a massive amount of analysis is completed and documented for every part of the station's operation. The shelves of documents made available to the public through this Committee constitute the most significant parts of this material. As each aspect of the analysis is completed, it is forwarded to the AECB staff. The correspondence among the AECB, AECL and Ontario Hydro in several volumes for the licensing of the Bruce A reactor which was released to the Committee, attests to the extensive scrutiny of the analysis and documentation before a reactor is licensed.

An important part of the pre-licensing analysis is the accident analysis that is carried out and documented in the Safety Report for each station. The idea of accident analysis is to assume that very serious accidents occur and then work out the consequences of the accident. The AECB has specified certain dose limits for the releases of radioactive emissions in the event of the postulated accidents. The dose limits are set out below:

-AECB Accident Condition Dose Limits- Type Individual Dose Population Dose

Single Failure 0.5 rem whole body 10 man rem whole body

3 rem thyroid 10 thyroid rem

Dual Failure 25 rem whole body 10 man rem whole body

250 rem thyroid 10 thyroid rem

i A single failure means that one of the important process systems fails and the safety systems have to cool down the reactor with minimal consequences to the public The single failure accidents analyzed in the Pickering A Safety Report are failures of the: * Reactor regulation system * Heat transport system (such as a pipe break) * Secondary system (such as loss of f eedwater) * Class IV power (requiring the use of emergency power supplies) * Fuel handling systems (leading to uncooled fuel channels) 20

The dual failure accidents are those in which the failure of a key process system is accompanied by a failure of one of the safety systems. Since each safety system is supposed to be available 99.7% or 99.9% of the time, the probability of a dual failure accident is considered to be sufficiently remote to justify higher release limits for dual failures. The dual failures analyzed for the Pickering A reactor are: * Loss of the reactor regulation system and a failure of the shutdown system:

* Loss of normal cooling of the reactor core and a failure of the shutdown system.

* Loss of normal cooling and a failure of emergency cooling.

* Loss of normal cooling and a failure of the containment system.

In conducting these accident analyses, the licensee is required to analyze various ways in which the accident might occur. For example, the loss of normal coolant accident analyses include failures of pumps, or misfunctioning valves or breaks of different sizes and different types. Further, the licensee is required to make a number of conservative assumptions about what might happen at the time of the accident. For example, in the event of a pipe break it is assumed that:

* The two most critical shutdown rods are r»ot available, making the power rise higher than it would be if all the shutdown rods worked

* None of the process systems help out, putting a greater load on the safety systems than might, in fact, be the case.

* The weather is the very worst possible for maximizing population dose, although this condition occurs less than 10% of the time.

* The individual receiving the dose is the most susceptible member of the population — an infant somehow lying at the plant boundary.

* The pipe breaks in the worst possible way even though extensive testing indicates that tubing used in CANDU reactors will probably leak before breaking and instrumentation should detect the leak.

It should be noted though that the assumptions are considered pessimistic but credible. The licensee is not required to analyze the "incredible". For example, the analysis of failure of containment is an analysis of the. failure of the various mechanical devices included in the containment system. It is not an analysis of an accident in which the containment system is somehow simply not there when it is needed. Nevertheless, the accident analysis approach to licensing does give a good deal of confidence that accident sequences such as the one at Three Mile Island can be handled by an Ontario reactor without serious public safety consequences. 21

Another source of confidence in the safety of Ontario reactors is that safety research continues after the reactor is built and operational, and that the results of that research — favourable and unfavourable — are made known to the regulator. One such area the Committee examined was the update of the loss of normal cooling accident analysis. Early analysis, using the best information and techniques available, had shown that the loss of cooling accidents could be handled by the emergency cooling systems without serious consequence. The key finding at that time was that emergency cooling would be effective in assuring that the fuel sheaths — the Zircaioy tubes in which the fuel pellets are sealed — would not fail. If the fuel sheaths do not fail then radioactive emissions remain trapped inside the fuel bundles and do not escape into containment. Subsequent analyses found that there was a particular kind of pipe break in a particular location that is potentially more difficult to cope with than others. In fact, analyses by AËCL safety researchers showed that the emergency cooling system might not be effective in preventing the failure of a significant number of fuel bundles. This analysis was made available to the AECB and led to a number of modifications being made to Ontario reactors. It is reassuring to find that the industry itself continues to probe for weak spots in its own defences.

Basic Design Features The CANDU reactor has been called ultra high technology. Some might consider that the only way to be satisfied that a CANDU reactor is safe enough for continued operation is to examine thoroughly each and every aspect of each and every station. If that approach were taken, the only individuals capable cf reaching a conclusion on the safety of the CANDU reactor would be a few of the senior designers at AECL and Hydro. This approach would effectively eliminate the public» and their representatives on this Committee and in the Legislature, from participating in the process of deciding whether nuclear reactors are acceptable in Ontario today. Therefore, this Committee, while it listened to a great deal of technical evidence on the performance of different aspects of the reactor, sought a more straightforward way of assessing the basic features of the design.

There are two aspects of the design that are important for safety: the process systems and the safety systems. The process systems must work in such a way that the public and workers are protected from unsafe levels of radiation emissions during the normal operation of the stations. Normal operation should include the regular and anticipated kinds of accidents and mistakes that do happen. The safety systems are poised to protect the public and plant workers from the consequences of more serious accidents.

The process systems include the various heat transport systems that carry heat from the core (thereby preventing the core from overheating) to produce useful electric energy, the systems for regulating and shutting down the reactor, and the numerous instrumentation and control systems that keep the reactor operating in a safe state. Since the process systems are continuously in use — and in the case of Pickering, Douglas Point and NPD have been for several years ~ the best test of process system performance is how well they have performed to date. 22

The Ontario public has been well protected by the operation of the process systems in conjunction with the special safety systems. Continuous monitoring of air and waterborne emissions show that, month after month, emissions are usually less than 1/100 of the required standard. Even when there was a serious spill of irradiated water from the Pickering reactor in'February of this year where the momentary concentration of tritium could have been 400 times the maximum permissible level, the total tritium emissions were still only 1.43% of the monthly emission limit. Also, the irradiated water was well diluted by the time it reached the municipal water supply.

Workers at the plant — especially mechanical maintainers — are exposed to radiation in the normal course of their work at the plant. Dosimeters are worn by all nuclear workers to measure their levels of exposure and provide a basis for continuous monitoring. There have been incidents where workers were exposed to radiation in excess of the AECB standard, the, most recent being the overexposure of two workers cleaning spilled fuel from ar pressure tube at Bruce. As well, significant numbers of workers receive annual doses that approach the maximum permissible dose of 5 rems in a year. This is in sharp contrast to Hydro's ability to keep emissions to the public below 1/100th of the required standard. Clearly, Hydro's record with workers is not as good as its record with the public. On the other hand, Hydro was able to demonstrate that ; c has a very high level of concern for employee safety and is vigilant in maintaining high safety standards. In fact, the total exposure of all Hydro employees peaked in 1975 at 3,145 man rem when faulty pressure tubes were being replaced at Pickering and by 1973 had fallen to 1,750 man rem despite the addition of three units at Bruce. Overall then the Committee has found that Ontario's plants operate safely under 'normal' circumstances and have been able to cope with the accidents, mistakes and malfunctions that have occurred to date.

It is not as easy to make a similar general statement about the performance of safety systems. The safety systems include the emergency cooling systems, the containment systems and back-up shutdown systems. The shutdown systems have been used a few times, but the other systems have never boen called upon in any of Ontario's reactors. We cannot, therefore, judge their adequacy by objective standard of performance. Instead the Committee had to find reassurance in the logic of the design concepts and the demonstrated reliability in test performance.

Several features of safety system design are reassuring:

* The defence-in-depth approach, exemplified by the multiple barriers to radiation releases that were outlined at the beginning of this chapter, is an appropriate way to handle sr-y toxic substance.

* Several important features of the plant have 'fail-safe' characteristics, (i.e., if the component fails, it is more likely to fail in a way that is safe rather than unsafe). For example, the shutdown rods are held poised above the reactor by electromagnetic clutches. If power fails, the rods will drop and shut the reactor down, whether this is necessary or not. The computer control systems will shut the reactor down if the operating and the standby computers malfunction and is programmed to shut the reactor down if any data is received that the computer does not "understand". 23

* Systems are separated as far as possible to reduce the chance that faults in the process equipment can damage the protective devices and containment provisions as well.

* Redundancy is built into many systems so that if one fails, the other is able to perform the necessary function. The important sensing instruments, for example, are all triplicated. Extra pumps are provided so that several can fail without affecting safety.

* Safety systems are designed so that they can be tested while the plant is operating. Since CANDU reactors have been able to operate, in some cases, for over 90% of the year, it is important that the 'unused' safety systems be regularly tested.

If the logic of the basic design concepts for safety systems is reassuring, then it is only necessary for Hydro to show that their systems test out to the reliability levels set by the AECB (availability 99.7% or 99.9% of the time). The record here is not as dear, not as good and not as reassuring. Hydro has a complex system of assessing availability of safety systems and reporting the availability to the AECB. The reporting system and the definition of underlying data have changed over the years making outside analysis very difficult. Overall though, it appears that important safety systems do not meet the target performance levels set by the AECB.

The Committee made a special investigation of safety system reliability and the ongoing debate between the AECB and Ontario Hydro on the adequacy of Hydro's past record and current performance. The overall impression from that special investigation is mixed: on the one hand, safety systems do not meet the reliability targets set out as a licencing condition, while on the other, the reported reliability does not necessarily indicate that the systems are inoperable and both Hydro and the AECB appear to be focussing greater attention on improving reliability.

As currently reported, safety systems do not meet the availability targets set out as conditions in the operating license. In 1973 and 1979, each operating station missed its targets.

* At NPD, the Injection Water System missed the target by 26 times in 197S and the boiler room containment system missed by 3.1 times in 1979

* At Douglas Point, the Emergency Coolant Injection System missed by 15.8 times in 1978 and 9.6 times in 1979 while the Dousing System missed one of its targets by 5 times in 1979

* At Pickering the Emergency Coolant Injection target was missed on units 2 and 4 in 1973 and units 1, 2 and » in 1979 while the containment system missed its target by 6 times in 1979

* At Bruce the Emergency Coolant Injection targets on units 1, 2 and 3 were missed in 1978 and in 1979 were missed by about 200 times on all four units. In 1979 Shutdown System 2 missed its target by two times Problems in safety system reliability are not just a recent occurrence. Each of Hydro's stations has had one or more key process or safety system with chronic problems that eventually required extensive modification. The exhibit at the conclusion of this chapter shows for a selected systems that unavailability problems do appear and take several years to resolve. For example:

* When Pickering first began to operate the system for regulating power in the reactor was unreliable. A very detailed, component-by-component assessment of the system was necessary to make the modifications that eventually made the regulation system highly reliable.

* From 1962 to 1970, NPD had continuing problems with the reliability of the mechanical parts of its containment system, such as isolating dampers and dousing valves. Again, extensive modifications were made that have resulted in a decade of high reliability. Ironically, there are now indications that modifications to other parts of the station have reduced the effectiveness of the now reliable containment system.

Safety system reliability is taken very seriously by the AECB and by Ontario Hydro and AECL. An explicit condition of the operating licence is that safety systems shall be tested and maintained to substantiate and assure the reliability and effectiveness claimed in the station Safety Report. Ontario Hydro report availability statistics at least quarterly for all the major stations. AECB on-site inspectors are available to audit test procedures, frequency and results. The Committee has some concern that attention to safety system reliability may be more procedural than actual. In the light of continuing failure to meet targets, the AECB response could be seen to be primarily exhortations and strongly worded letters while tacitly accepting that the targets will always be difficult to meet.

There are though a number of factors that make the unavailability statistics less concerning than they appear on the surface to be. Two factors are important: the overstatement of the statistical measures and the continuing effort to improve.

Nuclear power station safety systems are large and complex. An Emergency Coolant Injection System is made up of hundreds of metres of pipes with valves, headers, sensing instruments and computer controls. Numerous tests of the various subsystems are carried out while the reactor is in operation to substantiate reliability claims. Maintenance procedures involve the regular checking of each part of the system. Some parts are tested and checked frequently; others less so. Out of all the tests and checks of complex systems one statistical measure of "unavailability" is recorded in Quarterly Technical Reports.

Over the years there have been many attempts to define various classes of 'unavailability' for regular reporting. These changes make it difficult to analyze station statistics over time. They are also indicative of the difficulty in reducing complexity to a few meaningful phrases. As currently defined, it appears that 'unavailability' does not mean 'inoperability'. For example: 25

* In the summer of 1979, a valve in the emergency cooling system at NPO was found to be not fully open - even though the instrumentation showed it to be fully open. The Station Technical Report labelled the Emergency Cooling System 'unavailable' for one-half the period over which it was presumed to have become defective. And the valve was defective. At the same time however, there is no indication that the effectiveness of emergency cooling would have been impaired by the position of the valve. The bare 'unavailability' measure understates the reliability of the system.

* At Bruce A Generating Station, the Emergency Coolant Injection System shows a chronic unreliability. In report after report, target reliability levels are not met. It turns out though that for much of the time there have been no problems with the system itself. The problem is that certain isolating valves must be dosed in order to test the system. When these valves are dosed, the system is 'unavailable' for immediate use. The more often the system is tested, the worse the apparent reliability of the system appears to be. Changes to the testing procedure (specifically a contemplated increase in the speed of operation of the test valve) will improve the apparent reliability of the system, even though the system itself is not changed.

Thus the unavailability information on its own would not compel the Committee to label the stations 'not safe enough' because the raw unavailability data is not directly meaningful. In the future, as the public receives safety system reliability information on a regular basis, the information must be improved.

Another reason the Committee has enough confidence to justify continuing operation at the plant is that it appears that reliability is improving . In terms of the plant hardware, station statistics show that, over time, system reliability does improve. Each station has problems in the years following start up. Over time, the problems are solved and the statistics become more encouraging. In terms of regulatory vigilance, it appears that the AECB is paying increasing attention to compliance. A recent top-level review of safety system reliability was forced on Hydro. The on-site inspection system is being strengthened and formalized. And the AECB is paying attention to the reporting problem. Finally, Ontario Hydro has taken the extremely promising initiative of creating a Nuclear Integrity Review Panel, with membership from the senior level of the Design and Operations groups of Ontario Hydro and AECL. This panel will provide a focus, at a senior level, for a more organized and thorough approach to the review of the performance of nudear plants. As its terms of reference state, it will aim to "ensure there is adequate reliability, effectiveness, and independence of all the nudear systems." Among the important work this panel has sponsored is a thorough examination of the lessons to be learned from the acddent at Three Mile Island and a component- by-component assessment of the reliability of the Bruce safety systems.

Although the inadequacies in the availability statistics are frustrating, they do, on balance, appear to overstate the real problems of safety system reliability. And, recent action by Hydro and the AECB give some assurance that the performance of safety systems should improve. Beyond the life of this Committee, 26

the public should continue to be fully informed of the reliability of safety systems and the efforts of regulators and licencees. Informed vigilance will ensure that the high level of attention is maintained. Accordingly the Committee recommends that • RECOMMENDATION V ONTARIO HYDRO SHOULD ENSURE THAT THE NUCLEAR INTEGRITY REVIEW PANEL REPORTS ANNUALLY ON ITS ACTIVITIES TO IMPROVE THE RELIABILITY, EFFECTIVENESS AND INDEPENDENCE OF NUCLEAR SYSTEMS, HIGHLIGHTING CONCLUSIONS OF COMPLETED PROJECTS AND PROBLEMS UNDER ACTIVE STUDY. SUCH A REPORT SHOULD BE MADE AVAILABLE TO THE PUBLIC FROM ONTARIO HYDRO AND AT ALL INFORMATION CENTRES AND SHOULD BE TABLED IN THE LEGISLATIVE ASSEMBLY BY THE MINISTER RESPONSIBLE FOR ONTARIO HYDRO.

RECOMMENDATION VI THE AECB IN ITS ANNUAL REPORT SHOULD REVIEW AND COMMENT ON REPORTED UNAVAILABILITY OF SYSTEMS IN NUCLEAR POWER PLANTS AND SHOULD SUMMARIZE THE ACTIVITIES OF ITS COMPLIANCE BRANCH. Lessons From The Significant Events

One of the important contributions this Committee made to opening up the nuclear debate in Ontario and Canada was to bring into the open all the incidents of varying degrees of seriousness that have taken place in Ontario reactors. All the reports of abnormal or significant events in ail Ontario Hydro reactors are now made available for public scrutiny.

Out of the hundreds of incidents that have been reported on in Ontario reactors, the Committee examined six that had been referred to it by a shift operator at the Bruce plant, and another twelve selected by Committee members and staff. Due to the complexity of nuclear reactors, each event required a significant amount of background explanation.

Several general conclusions emerged. The most important was the recognition that accidents, mistakes and malfunctions do occur in nuclear plants: equipment fails; instrumentation gives improper readings; operators and maintainers make errors and fai.' to follow instructions; designs are inadequate; events that are considered ' incredible' happen. It is a sobering reality, but one we must accept, that no matter how careful we are, we must expect accidents; we must anticipate the unexpected. On the other hand the incidents themselves do give some assurance that CANDU reactors are properly designed and operated. When incidents happen, the reactor does shut down safely, and there is enough redundancy that, in the incidents that have happened, the public has not been at risk. In fact, if there were no 'incidents', then we would have no basis for verifying that the reactor is able to cope with problems. 27

WEAKNESSES IN HUMAN PROCESSES A good deal of the Ontario Hydro evidence concerned their programs to ensure the most effective functioning of the organizations responsible for nuclear generation, from design through to operations and maintenance. In fact, Hydro considers "competent operators" and effective systems to "detect and correct failures" to be two of their five major public safety thrusts (along with "reliable process systems", "reliable safety systems", and "multiple barriers'"). It was dear from the evidence that Hydro does devote a good deal of attention to the human factors of nuclear operations. The quality and competence of Hydro's staff was apparent in the many people who appeared before the Committee as was the care and thoughtf ulness that went into the back-up documentation and analysis in the information presented to the Committee and made available to the public through the Legislative Library.

Clearly the human back-up to the physical equipment is vital to the continuing safe operation of nuclear plants. It is in this area that the Committee found evidence that Hydro needs to strengthen and improve.

* The significant events often showed instances of operator or maintainer error. Seven of the twelve events singled out for special examination involved operator error as a major contributor toward initiating, prolonging or increasing the severity of the event. Of course, the twelve events singled out were not a random sample but were specifically selected to illustrate the range of problems that occur. To that extent, the raw number of operator errors may be overstated. Nevertheless, the point is irrefutable: operators do make errors.

* There is pressure of some kind on plant operators to get or keep a unit going that leads operators to take improper actions. This pressure exists despite Hydro management's assurance that no pressure is deliberately applied, despite the station manager's assurance that no pressure should be felt, despite procedures written into operating manuals, and despite the fact that disciplinary action is taken against operators who act improperly. The pressure is apparent; its source remains unexplained.

* Another kind of breakdown in the human processes was Hydro's failure to demonstrate a comprehensive follow-up to significant events at Bruce. Hydro could demonstrate that each event is documented and reported in a very timely way, but could not, at that time or later in the inquiry, demonstrate that the i.ollow-up is adequate and comprehensive. The organization appears to break down between the plant and head office and between Design and Operations. The Committee found, as one specific, that a significant event report in 1970 pointed to problems in emergency cooling at NPD. The early insight was not accepted and later studies —in 1976 — showed that it had been correct. 28

At the beginning of this set of hearings, Dr. Porter advised the Committee of his concern that the human factors were the weak link in Hydro's nuclear operation. As the hearing progressed, the Committee became increasingly concerned about weaknesses in the human back-up to the engineering, construction and equipment that made up a CANOU reactor. As the hearing was drawing to a close» the Hydro Chairman, «appearing before the Committee, conceded that "empire building" was, very likely, a problem in the organization. Mr. Taves, a recent shift operator at the Bruce "A" Generating Station confirmed that the plant operators are unable to communicate their ideas and concerns to the rest of the organization. Drs. Senders and Foley, human factors engineers from the University of Toronto, along with one of their former students, and, for a short time, a Hydro employee, Mr. Kaponeridis, also gave evidence of shortcomings in Hydro's handling of the human dimension.

The substantiation of concerns that the Committee was gathering in questioning Hydro witnesses, gives the Committee additional confidence in concluding that Hydro must rethink the way it handles the human resources involved in nuclear operations and must substantially improve its follow-up of significant events. In its interim report, the Committee made specific recommendations to effect these conclusions. As this Final Report was being prepared, Hydro reported to the Committee through Committee staff, on the actions it had taken to implement these recommendations. A comprehensive new system for reporting significant events has been tested and recently implemented. An important feature of that system is the collection of information on the direct effect of 'human factors' during an incident. A computer backed system for classifying and analyzing incidents is being developed to improve follow-up and ensure that lessons are learned. Hydra is also trying to learn how to improve the effectiveness of the human resources in its nuclear facilities. The heavy water plants have been singled out for various pilot programs accompanied by in-depth attitude surveys and recording of overall plant performance.

The Committee commends Hydro for these initiatives and repeats the recommendations from its Interim Report to emphasize their importance and the need for ensuring that the work is carried to a satisfactory conclusion.

RECOMMENDATION VII HYDRO SHOULD UNDERTAKE A COMPREHENSIVE REVIEW OF PROCESSES FOR DEALING WITH HUMAN RESOURCES TO IMPROVE THE ORGANIZATIONAL CLIMATE AND THE FUNCTIONING OF THOSE PARTS OF THE ORGANIZATION THAT DEAL WITH THE SPECIAL PROBLEMS OF NUCLEAR POWER.

RECOMMENDATION VDJ HYDRO SHOULD TIGHTEN ITS SYSTEM FOR MANAGING THE FOLLOW-UP TO SIGNIFICANT EVENTS IN ORDER TO ENSURE THAT APPROPRIATE REMEDIAL ACTION RESULTS, THAT EVENTS ARE CLASSIFIED BY TYPE AND/OR COMPONENT AND THAT EVENTS ARE CROSS-REFERENCED TO OTHER PLANTS IN A MANNER WHICH CAN BE TRACED THROUGH THE REPORTING SYSTEM. 29

SPECIAL REFERENCE TO NPD REACTOR Although the NPD Reactor at Rolphton is, at 22 megawatts, the smallest of Hydro's operating reactors, it received more attention than any other reactor. In fact, the Committee was specially directed to study and report back to the Legislature on the continuing operation of the station.

Several factors accounted for this special attention. First, a group of citizens living in Renfrew County expressed their concerns about the station to the Committee. Second, the station is the oldest in the system and there were special concerns that it may not be as safe as the newer ones. Finally, over the course of the hearings the station was plagued by a number of operating problems that kept attention focussed on it.

To help fulfill its special obligation, the Committee travelled to the plant for a tour of the facility and an open meeting in the nearby community of Deep River. At several points in the hearing, the Committee heard the detailed concerns of the Renfrew County Citizens for Nuclear Responsibility (RCCNR) and the responses of Ontario Hydro, AECL (the owner of the plant) and the AECB. The Committee acknowledges the extensive background work that went into the submissions of the RCCNR. Their participation was extemely important to the Committee process. They helped the Committee gain valuable insights into the recent history of the station and into the regulatory process as it has applied to the NPD reactor. Finally, the Committee received from AECL copies of the correspondence between Ontario Hydro, AECL and the AECB that related to emergency core cooling. That correspondence formed the basis for a final set of hearings on NPD in February of this year.

The NPD Reactor wai originally licenced in 1963. The reactor was the first commercial scale reactor in Canada and was built to demonstrate the feasibility of the CANDU system. On the basis of the early operation of NPD, the 200 megawatt station at Douglas Point and two 540 megawatt units at Pickering were built to launch the Canadian nuclear program.

As the first reactor of its kind, NPD required original regulatory criteria. Licencing criteria for a nuclear reactor include many specifications for certain qualities of materials and equipment and for specified levels of control and instrumentation. An important class of criteria are those that relate directly to the public safety risk raised by the operation of the reactor. In the case of NPD, the public risk criteria were set to show that the risk from a nuclear reactor are less than from a coal-fired reactor. The specific risk level was that the chance of one individual dying as the direct result of the operation of the reactor should not exceed 10- (one death per 100 years of station operation). Many of the criteria have been changed for subsequent reactors that are much larger, more complex and operate with fuel that is far more powerful. Equipment specifications have been changed. New engineering codes have developed for assessing material quality. The overall risk concept (10- ) has been changed to single and dual failure criteria. The single and dual failure approach is used en all the reactors built after Douglas Point. It establishes limits to the amount of radioactivity that can be released in any single failure accident for which the AECB requires analysis (such as the worst possible failure of the normal cooling system but proper action from the safety systems) or in any dual failure accident for which analysis is required (such as the worst possible failure of the normal cooling system coupled with an inoperative safety system). 30

When various postulated accidents -vere analyzed at NPD prior to 1963, the best analytical techniques showed that the public was protected from significant radiation danger by the integrity of the Zircaloy fuel bundle. The fuel bundles would not fail, and therefore significant quantities of radiation could not be released. By 1976 new analytical techniques had been developed which showed that fuel bundles could fail in CANDU reactors under certain conditions. The new analyses were relayed to the AECB and each station was required to show how the new information should affect its continued operation. AECL replied for NPD by showing that the plant, if allowed to operate without any changes, would continue to meet its original public risk licencing criteria, even though there could be fuel shèath failures under certain accident conditions and even though, under those conditions, the plant could not meet either the single or dual failure criteria applied to most of the newer reactors. The AECL also showed, however, that certain modifications could reduce the probability and level of emissions in potential accident situations. Single and dual failure criteria could be met.

All equipment and procedures necessary to activate the proposed modifications are now in place. Most have been accepted by the AECB and are implemented. Among the most important were those that enable the calandria spray system to continue in operation following a loss of coolant accident (LOCA). This modification was in place and accepted in i 977 and brought the plant within the dual failure limit. All of the additional modifications designed to bring the regular emergency cooling system back to its original effectiveness have not been accepted by tha AECB. For one of the two modifications not yet accepted, boiler crash cooldown, extensive and time-consuming stress analysis has been requested. That modification must he approved and implemented before the. station wil! meet the single failure criteria. In fact, recent analysis has shown that the impact of the other modifications caused the single failure criteria to be exceeded by a factor of two - considerably more than had been originally estimated.

In its Interim Report, the Committee was critical of the AECB for allowing the plant to operate while the modifications to bring the releases in a dual failure within limits were installed. The Committee believes that the plant can be allowed to operate while modifications that will bring it within the single failure limit are being analyzed.* Several factors influenced this very critical decision. First, the plant is, and has always, operated, within its original licencing criteria. Although these criteria are not as stringent as the single and dual failure limits applied to later reactors, the Committee considers them adequate for a reactor of the size and location of NPD. Second, NPD operates with fuel that is not as powerful as the fuel used in other reactors. The importance of the low fuel rating is that there are no significant quantities of gaseous fission products that would release from the fuel immediately if the fuel bundles were to fail. When the performance of the Douglas Point reactor's emergency cooling system was shown to be not as good as had been presumed in its original Safety Report, the AECB reduced the reactor's power to that of NPD. The third factor considered by the Committee is that failure to meet the singie failure results in a lower release of radioactivity than the inability to meet the dual failure criteria. The release for the worst single failure accident is 150 curies; for the dual failure acciden*, it was 6,800 curies.

•See dissent of Members Foulds, Gigantes and Mackenzie 31

There is, however, another concern about NPD. The Committee found that the documentation concerning NPD is far from adequate. The key safety document, originally called the Final Hazards Report, is no longer accurate but has not been replaced. Various analyses and descriptions of proposed modifications are now just appended without being cross referenced to„the safety^report or to each other. Incomplete^ss^fs^ety analysis^ that an earlier modification had inadvertently incréasëf pressure irT the c«tainmentSfyste^ tritium to tiw control room and atmosphere during "certain /accident situations. There have been many advances in the art of analyzing the capability of materials and components in nucbar power plants since NPD was designed some 20 years ago. The latest analytical techniques should be applied to NPD to see if there are any other problems that might appear.

NPD requires a major engineering review. Completion and full documentation.of the review would place the AECB and the public in a much better position to judge the acceptability of the reactor. Such a judgement will become increasingly important as the reactor continues to age. -3 _ ^ 1

The Committee recommends that: -';.• -~;^::j-r^-.^-^,-r.-r-.-i'.i'^-\^r4-X-i. .;,-...• RECOMMENDATION IX ONTARIO HYDRO SHOULD ENSURE THAT A COMPLETE ENGINEERING REVIEW OF THE NPD STATION IN ITSMODIFIED STATE IS UNDERTAKEN AS A BASIS FOR A ISIEW FINAL HAZARDS REPORTTHAT REFLECTS BOTH THE PLANT MODIFICATIONS AND THE MOST CURRENT RESEARCH INFORMATION. AFTER AECB REVIEW AND APPROVAL THE REPORT SHOULD BE PRINTED WITHIN TWELVE MONTHS AS A NEW SAFETY REPORT AVAILABLE FOR PUBLIC SCRUTINY, 32

EXHIBIT

UNAVAILABILITY OF SELECTED SAFETY SYSTEMS AT THREE STATIONS

Unavailability as a Multiple of Target 200.. Pickering ECI, Unit 3

V«-Pickering ECI, Unit 2

100-

Oouglas Point ECZ

1962 1979 CHAPTERS THE REGULATION OF NUCLEAR POWER SAFETY 33

CHAPTER 3 THE REGULATION OF NUCLEAR POWER SAFETY

The safety of the nuclear power industry has been regulated in Canada by the Atomic Energy Control Board (AECB) since 1946. At that time, the Atomic Energy Control Act set up the Board and gave it exclusive authority to regulate, license and monitor the health, safety and security of all works that involve atomic energy. This gives the AECB effective control over the full nuclear cycle — mining, milling, fuel fabrication, reactor operation, waste management — as well as the use of radioactive materials in other products, such as smoke detectors or medical equipment. The AECB in 1979-80 had a staff of 17S plus 7 temporary staff members and a budget of $7 million per year. In contrast, the Nuclear Regulatory Commission (NRC) in the U.S.A. had 2,700 employees, 600 consultants and a budge, of $330 million in the same year. Canada has 12 operating reactors; the U.S.A. has 75 to 80. The AECB operates by granting licenses and giving permission at important stages. In sequence the important milestones are: site approval construction licence permission to load fuel permission to go critical graded set of permissions to increase power full operating licence operating licence renewal At each stage the Board requires the pre-filing of appropriate documentation which is analyzed and verified by the Board staff. Often extensive dialogue ensues between the AECB staff and the licensee before the licence is issued or permission granted. In the course of coming to its own conclusions on the acceptability of Ontario's reactors, the Committee became thoroughly familiar with the Canadian nuclear regulatory process. The Committee found that while there are several good features in the regulatory process as it exists, the public has not always been protected by the process as effectively as it could be. Changes of a substantial nature are required. The balance of this chapter will deal with each of these points in turn.

GOOD FEATURES WORTH STRENGTHENING The regulatory approach has evolved considerably over the 33 years the AECB has treen in operation and, perhaps most critically, over the approximately 20 years that it has been regulating commercial sized reactors. Several features of the process are very good. In some cases they need strengthening, but in concept they are worth retaining. Onus en the Owner/Operator In the U.S., the NRC has developed a specific set of technical design criteria that each reactor must meet in order to be licensed. In Canada, the AECB has defined a set of general output standards for reliability of systems and permissible radiation emissions under normal or accident conditions. The owner/operator of the plant is responsible for design, engineering, construction and operating procedures to ensure that the plant meets the standards. (In Ontario, Ontario Hydro operates all the nuclear generating stations but AECL owns the nuclear portions of the NPD station at Rolphton and the Douglas Point station.) The AECB checks the analysis and documentation, and monitors plant operations through resident inspectors.

The Committee is satisfied that the Canadian approach is sound and appropriate. The Canadian approach encourages the owner/operator to develop a capability for safety research and analysis. Specifically, Ontario Hydro has groups concerned solely with nuclear safety within its Design and Development Division and its Nuclear Generation Division. AECL has a separate Safety Engineering Group within its Engineering Company. These groups are involved in all aspects of the design, participate in all design reviews, audit the quality of operation of safety-related systems, and are available for follow-up of significant events as they occur. This built-in responsibility for safety is the best assurance that safety decisions are appropriately integrated with operating practices and procedures. And, by making the owner/operator initially responsible for safety, there is always the possibility that better safety systems are designed and implemented than the regulator would have required or even considered possible.

Basic Standards Are Sound The basic safety standards have evolved over the past twenty years from the licensing of NPD to the current approach to Darlington. There is, in the minds of the Committee, considerable unproductive and unsatisfying vagueness about the detailed definition and application of the standards. However, the basic approach has, in each case, been quite straightforward. The NPD reactor was licensed on the basis that it must be safer than an equivalent coal-fired facility. Specifically, probable releases from possible accidents must be shown to fall within limits that would result in no more than one fatality every 100 years from the operation of the plant.

The Douglas Point reactor was licensed on the basis that the most exposed member of the public would not have more than one chance in a million per year of being killed by the operation of the station. The Pickering, Bruce and Darlington plants are licensed to meet reference dose limits and reliability standards calibrated to ensure that the risk to the public is acceptable in relation to the risks from other industries. 35

Although the reference dose limits are expressed in fairly technical terms, they can be expressed in three plain statements. 1. A single failure accident should be a very infrequent event (say once every three years) and its consequences should fall within the 500 miilirem to the most exposed individual "safe limit" set for releases during normal operation. 2. A dual failure accident should be expected to occur very rarely (no more than about once in every 3,000 reactor years) and its consequences should be well below radiation levels that are certain to cause an immediate fatality. 3. A triple failure, or catastrophic accident should be expected to be a highly improbable event. It is important to note that while these three statements seem to define the basic Canadian standards, they are not expressed in these terms anywhere in any of the material provided the Committet >/ Hydro, AECL or the AECB. In fact, Hydro witnesses stated their conviction that the only standards applicable are the first two. On the other hand, we found that a good deal of the debate between Hydro and the AECB centred on AECB requirements that Hydro believes are aimed at meeting the third. One problem of failing to recognize the third basic principle is that the industry has never fully analyzed the consequences of the more improbable accidents. As well, there are instances where the AECB has granted an exemption to a particular standard. At the Bruce "A" reactor, the dual failure release limit is not met for an accident that includes the worst possible loss of coolant and each of two particular failures of the containment system. The exemption is granted because it is presumed that the two failures are highly improbable.

Despite the soundness of the basic regulatory approach, there are difficulties in applying them, as indicated by the exemptions and the lack of clear articulation. The AECB set up a group called the Inter-Organizational Working Group (IOWG) made up of representatives of the industry and the regulator and chaired by Or. Paskievici of the University of Montreal. This group was given the responsibility of reviewing and updating the general principles as a first step in the current work of the AECB to develop a more comprehensive set of regulatory guidelines.

The approach recommended by the IOWG is conceptually more consistent than the current approach and does toughen up some of the release limit standards. Release limits are set by the probability of occurrence rather than single and dual failure, recognizing that some accidents are more likely to occur than others, and they are set for some of the more improbable accidents including some that may fall into our category 3 above. Release limits for normal operation and for some of the accidents that correspond to the reference single and dual failure accidents are lowered. Each of these features contributes to the attractiveness of the IOWG approach.

The IOWG approach does, however, have certain drawbacks that are, in the minds of ':he Committee, sufficient to cause it to be rejected in favour of strengthening the current system. One drawback of the IOWG proposal is that, as it was written, it appears to offer the theoretical loophole of allowing accident 36

sequences to be subdivided into small discrete elements that are each highly improbable,, thereby increasing the allowed release limits. This is a specific aspect of the general concern of the Committee that probabilities should be used only as a guide and not as the exclusive licensing tool. Second, the IOWG approach has the drawback of taking the regulation of nuclear safety even further away from the understanding of even the most well informed layman, by stating the criteria in a way that can only be understood in very technical terms. As well, by allowing designers to work through 'fault trees' in assessing probabilities, credit can be taken for the operation of process systems that in current accident analysis are assumed to be completely inoperative. Finally, 4he Committee noted the personal view of the President of the AECB that at least two of the 10WG recommendations can be interpreted as a loosening of current standards. The Committee believes, on the basis of its knowledge of nuclear safety, that it is entirely inappropriate to loosen any nuclear safety standard.

The Committee believes then that the AECB should continue with is current' basic approach to standard-setting. But the approach must be strengthened. One concern is that there has been no study of the likelihood and possible consequences of the highly improbable worst set of accidents possible in a CANDU reactor. The AECB has contracted with Dr. Rogers of Carleton University to study what can happen in a physical sense if a core melt does occur when, one after another, each of the reactor's cooling systems or heat sinks is lost. His study will take information available around the world and apply it to the CANDU reactor. The Committee supports this initiative. Until this study was commissioned, the AECB has stood with AECL and Ontario Hydro in their conviction that a much more detailed study is unnecessary. Their argument is that the probability of catastrophic accidents is very low and resources are better devoted to ensuring that accidents do not happen. The AECB joins the industry in arguing that no study can be definitive. Studies of potential catastrophies, it is argued, will always be subject to intense academic criticism that will confuse the public and make it unnecessarily skeptical of nuclear power. They cite the $5 million study completed in the U.S.A. under the chairmanship of Dr. Rasmussen of the Massachusetts Institute of Technology that was soundly criticized as soon as it was published, , even though the credentials of Dr. Rasmussen and many of his colleagues are impeccable. The basis of the technical criticism is that confidence in predicting events that cannot be demonstrated in relevant experience is not very high. There will always be unanticipated human actions or missed cross-links that render the prediction invalid - either significantly too high or significantly too low.

In the end the study can only show what is already known: a catastrophic accident is possible but unlikely. The Royal Commission on Electric Power Planning supported the industry on this issue. In fact, this was the only Committee conclusion with which the Royal Commission failed to agree. The Committee believes, however, that the industry and the Commission are underestimating the public's need to know the risk it is accepting in allowing nuclear power plants to operate in Ontario. As well, the Committee is aware that the Rasmussen study is acknowledged to have been extremely valuable in developing the capability to analyze nuclear accidents, in identifying potential accident sequences, and in alerting public authorities to the nature of the required civil response to a catastrophic nuclear accident. It should not be necessary for a Canadian study to duplicate each and every aspect of the massive Rasmussen project: some things can be learned from that experience and the extensive debate 37 that followed publication of the report and summary. A study for a CANDU reactor would cover the likelihood of a range of the accidents through fault tree analyses that incorporate the effect of human actions and the consequences identified by Dr. Rogers. The slowdown in new reactor orders should have made a good number of design analysts available to complete the work. With guidance and direction from outside the industry, the study could draw on all recognized experts. The several million dollar cost of the study may appear high, but it is insignificant in comparison to the billions of dollars spent in the construction of each Ontario Hydro station.

A special concern of the Committee is that this type of study should be the responsibility of the AECB and through it, the Federal Government. However, the study itself is of major concern to the people of Ontario. The Government of Canada should be given an opportunity to accept its responsibility. If it does not act, the Province must be prepared to do so. RECOMMENDATION X THE AECB SHOULD COMMISSION A STUDY TO ANALYZE THE LIKELIHOOD AND CONSEQUENCES OF A CATASTROPHIC ACCIDENT IN A CANDU REACTOR. THE STUDY SHOULD BE DIRECTED BY RECOGNIZED EXPERTS OUTSIDE THE AECB, AECL AND ONTARIO HYDRO. IT SHOULD BE FUNDED BY A SPECIAL GRANT FROM THE FEDERAL GOVERNMENT. IF THIS STUDY IS NOT COMMISSIONED BY JULY 31, 1980, THE PROVINCE OF ONTARIO SHOULD ENSURE THAT IT IS UNDERTAKEN.• In general, the Committee believes that the Board should continue with its current approach to standard-setting: aiming at outcomes and reliability levels rather than specific equipment specifications and building on the simple, understandable, three-step approach. RECOMMENDATION XI THE AECB SHOULD MAKE SIGNIFICANTLY MORE SPECIFIC ITS OWN CURRENT CRITERIA FOR BOTH SINGLE AND DUAL FAILURE ACCIDENTS AS WELL AS FOR MINIMIZING THE PROBABILITY OF A CATASTROPHIC ACCIDENT, INCORPORATING WHERE APPROPRIATE, THE TIGHTENING IMPLICIT IN THE REPORT OF THE INTER- ORGANIZATIONAL WORKING GROUP (IOWG). Staff are Competent and Independent In requesting and receiving from Ontario Hydro, letters and internal memorandums between the corporation and the AECB, the Committee gave itself and the public a unique insight into the complex, formerly secret, often confusing process for regulating the safety of nuclear reactors in Ontario. The Committee found that lengthy discussions and arguments go on between regulator and licensee on many, many aspects of the licence. Many of the conclusions drawn by the Committee on the strengths and weaknesses of the regulatory process came from its examination of that correspondence. Much of the Committee's confidence that the reactors operating in Ontario are 'acceptably safe' came from observing the depth of analysis and questioning that goes into the design of an operating reactor.

•See dissent of Members Ashe, Belanger, Hennessy, Leluk and Williams 38

One specific concern the Committee examined in some detail relates to the boilers in the Bruce A Generating Station. In any generating station producing electricity from thermal power (heat) the boiler is the critical component thai turns the heat from the thermal source into steam that turns the turbines of the electricity generators. In a CANDU station the heavy water coolant, heated in passing through' the calandria, flows through thousands of small tubes inside the huge steel boilers. The boilers and their adjoining steam drums are normally filled with ordinary or light water that boils into steam in.the top half of the steam drum, *team in the top of the steam drum is piped to the turbines, condensed and coolea, and returned as water to the boilers to be converted into steam again.

The boilers at Bruce A are a unique design that has caused some problems. In addition, Hydro made a critical decision to put a good portion of the boilers outside containment as part of a general design philosophy at Bruce of putting as much equipment as possible outside containment. The objective of this philosophy is to reduce the exposure of plant personnel to radioactive tritium while carrying out maintenance and upkeep duties during normal reactor operation. In Pickering the boilers are entirely within containment and were designed to a Class III engineering standard. The location of the Bruce boilers in the containment wall made them, in the opinion of the AECB, a part of the containment boundary. In 1971, the AECB imposed a requirement for a more stringent, Class I engineering standard for the Bruce boiler shells. Hydro contacted its supplier, Babcock 4 Wilcox, and amended the contract to provide for the necessary upgrading. This included a higher level of inspection of the material and fabrication, more in-service inspection and more detailed stress analysis. The stress analysis had to show how the boiler shell would accommodate the worst forces that could be imparted by the piping during any operation.

Babcock & Wilcox performed the upgrading tasks required of them and their work was reviewed and approved by the AECB. During the plant's commissioning and before there was any power coming from its reactors, it was discovered that the unique boiler design was creating unusual stresses at the intersection of the boiler and the steam drum. Since the fall of 1975 when this phenomena was discovered, the boilers have been subject to unceasing scrutiny and analysis. From the Committee's point of view, several aspects of the long history of the Bruce A boilers were important in demonstrating that the Canadian regulatory process is working to ensure that high standards of safety are maintained in Canadian reactors. Oespite the limited numbers of staff, the AECB was able to:

identify the critical design change that required the Bruce boilers to be of a higher standard than Pickering boilers follow the details of the commissioning tests to pinpoint critical operating factors not considered in the original stress analysis. recognize the need for greater expertise and get it by contracting out the stress analysis review and then adding staff expertise. And, the Committee was able to see that Ontario Hydro has operated the station very cautiously while the problems continue to be analyzed. For example, in 1976 the analysis showed that the cool-down rate should be limited to 2°F per 39 minute from the specification value of 5 F per minute. Hydro proposed and AECB accepted an operating limit of IF per minute. Questions about the boilers continue today and problems have continued to appear. The boilers are being operated within restrictive limits to reduce the possibility of inadvertent excursions beyond allowable stress limits. Innovative strain gauges are being installed to provide data for further analysis. It could be well into 1981 before a 'definitive' analysis will lead toward some final resolution of the problem. So long as the vigilance of the AECB continues, and that vigilance is backed by an open information policy to ensure that the final decision is publicly justifiable, the Committee is satisfied that the problem can be left to Ontario Hydro and the Control Board.

One of the great strengths of the Canadian system is, it seems, the individuals involved in it. The Bruce correspondence show that the AECB staff is competent and independent. They ask many, many questions on the documents submitted. They ask for a great deal of information. The staff seem totally unconcerned by Hydro's complaints that too many questions are being asked and that the process costs too much money. At this time, with three stations incorporating 12 reactors at various stages of construction, the Federal Government should not be looking to the AECB staff as a source of quick 'cutback' economies. RECOMMENDATION XII THE GOVERNMENT OF ONTARIO SHOULD PUBLICLY URGE THE FEDERAL GOVERNMENT TO ENSURE THAT THE AECB IS ADEQUATELY FUNDED, PARTICULARLY IN LIGHT OF THE SIGNIFICANCE OF ITS CURRENT AND ONGOING WORK AND THE PUBLIC TRUST IT MUST FULFILL.

REGULATORY PROCESS OCCASIONALLY FAILS Although the Canadian regulatory system has its strengths, as outlined in the preceding sections, it also has some significant weaknesses. In the next section, the report will set out the areas of weaknesses and recommend specific corrective actions. In this section we will set out two instances the Committee discovered where the regulatory process did not do what the Committee believes the public would have expected it to do. Bruce "A" Shutdown Systems The Bruce "A" Station was designed and is operating with two independent, fast shutdown systems. The first involves shutdown rods dropping into the calandria to absorb the excess neutrons that cause continuous "fissioning". The second is the injection of a chemical 'poison' into the moderator to accomplish the same function. At Pickering the shutdown system is insertion of the rods and dumping the moderator.

The correspondence indicates that there was continuing confusion whether the second fast shutdown at Bruce was an AECB requirement, or an added feature put forward by Ontario Hydro. One result of the confusion is that the second shutdown system designed and installed by Hydro at the Bruce "A" plant is not able to react as quickly to certain kinds of accident possibilities as the first. The AECB believe both should have the same characteristics but have now conceded that it could be counter productive to 'backfit' a new design' that would offer the same capabilities for both systems. The Committee believes that the public does not expect that a critical safety system would be given 'de facto' approval while not meeting the requirements of the AECB merely because of loose communications.

Early Licensing of Bruce "A" The Bruce correspondence indicates that the licensing process at that station was extremely difficult. The AECB seemed to ask more questions and require more analysis on Bruce than had been the case with Pickering. Documentation fell behind. Construction was nearly completed and the reactor was ready to operate but the AECB staff did not yet have documents that they had expected to receive one year before the Board issues an operating licence. The example cited earlier of the analysis and checking required on the boiler shells indicates the reason the documentation is required for such a long time. The Chairman of Ontario Hydro visited the President of the AECB in Ottawa to impress upon the Board the economic significance of avoiding delay in starting- up the reactor. The President of the AECB expressed in a letter to the Chairman of Ontario Hydro his concern that the regulatory process was coming under increasing public scrutiny, requiring extra vigilance from the AECB. However, the AECB relented and issued a licence to operate at 63% of full power. Ontario Hydro, in turn, gave a corporate commitment to complete certain documentations in six months. The reactor began to operate at the reduced power level. The documentation was not ready in six months. When finally complete, the documentation showed that for some dual failure accidents with significantly impaired containment, the criteria are not met at power levels over 63%. A licence to operate at S8% cf full power was issued- wnUe the AECB pressed Hydro to design and implement an emergency coolant injection system that will keep dual failure releases within limits. Hydro does not accept the fact that they have been granted an exception. Hydro and the AECB continue to disagree whether the critical accidents are credible enough to be required for the dual failure release limits. The Committee is confident that the public has the right to expect that the process of licensing the largest nuclear complex in the world would be carried out with far more precision and adherence to the regulatory requirements that has been the case.

MORE CHANGES NEEDED The Committee is aware that the responsibility for regulation of nuclear safety is a federal rather than a provincial responsibility. Therefore, any change recommended by this Committee can be construed as being outside its jurisdiction. However, the Committee has devoted a good deal of time to studying the current regulatory proces and is convinced that the process must change if the public is to have confidence in the system, and consequently, in the acceptability of nuclear power. Two areas require change. First, the Board must make its judgements clearly and ensure they are enforced. In addition to improving public confidence, this will also have the beneficial effect of improving the interaction between the Board and the regulated nuclear operator. Second, the composition and apparent functioning of the Board itself must change to improve public confidence in the safety of nuclear reactors. Reducing Vagueness and Uncertainty The Bruce correspondence revealed that there was considerable uncertainty between Hydro and the AECB on exactly what was required in the licensing process. In many of the appearances of Hydro and the AECB, the Committee was able to confirm that the differences in opinion still exist. In fact, in the very last appearances of Hydro and AECB witnesses, it became apparent that a critical question still unresolved is whether the failure of Bruce "A" to meet the dual failure criteria for certain postulated accidents is an exception f or that plant or not really a requirement. •Uncertainties that continue today include the: Timetable The AECB has said that documents in support of an operating licence must be available one year before the licence is issued. The last plant was licensed before the documents were finished. It is unclear whether the one year rule still applies. In other instances the Board has requested certain action. The requests lead to long arguments and the transfer of great volumes of paper. It is unclear whether there are any end points to debate over Board requirements. Criteria & Standards Many uncertainties in the definition and application of criteria and the standards that do exist, continue to confuse. The Canadian approach is to focus its regulation on outputs —reliability and expected performance of systems — rather than inputs — the technical specifications necessary to achieve these outputs. This focus should continue. But a great deal of uncertainty remains about what the output targets are and how they are proved. Arguments continue over which accidents must be analyzed. There were contradictory statements from AECB staff over the reliability target for process systems. There are continuing debates over the definition of availability. It is disconcerting for laymen to observe so much confusion in the regulatory process. The confusion is dearly frustrating to the participants as well.

Ongoing Enforcement The AECB posts resident inspectors at each station except NPD. And, it requires regular reports from the operator on the performance of the various safety systems as evidenced by their use and testing. Over the years the reporting of availability information has changed almost continuously as Hydro and the Board have sought a definition of 'unavailability1 that is both simple and yet able to cope with the complexity of nuclear technology. The current system is still not satisfactory. It shows unavailability levels for certain systems that fail to meet targets. But Hydro responds that the information is not meaningful because unavailability does not mean inoperability in an emergency. The implications of failure to meet targets remain unclear. Powers of Board & Staff

The correspondence 'revealed to the Committee considerable uncertainty over the powers of the Board and of its staff. It is deac that the Board itself has the ultimate power to grant.or withhold a licence. It is also dear that Ontario Hydro has no question about that authority. However, below that ultimate power lies a great sea of uncertainty about what the Board can request of a licensee, when that request becomes an order, whether the request or order can be made by a staff member, and, given this uncertainty, under what circumstances Hydro staff can refuse to comply with a request from AECB staff. This uncertainty gives rise to long arguments between Hydro and AECB staffs. The arguments may not in themselves be improper, but they do lead to concern that delay can become a tactic for failing to act.

This confusion and uncertainty must be overcome. The system as it operates today depends too much on the strength of individuals.

RECOMMENDATION XIII THE AECB SHOULD SET OUT A SPECIFIC TIMETABLE FOR THE RECEIPT AND APPROVAL OF DOCUMENTS AT EACH STEP IN THE LICENSING PROCESS.

RECOMMENDATION XIV THE AECB SHOULD DEFINE AS CLEARLY AS POSSIBLE THE KEY PHRASES, SUCH AS "REQUEST" OR 'ORDER" THAT FORM PART OF THE ON-GOING COMMUNICATION WITH THE LICENSEE AND SHOULD TELL THE LICENSEE EXACTLY WHAT AUTHORITIES HAVE BEEN GRANTED TO STAFF MEMBERS.

RECOMMENDATION XV THE AECB SHOULD, AS A MATTER OF ROUTINE, BRING DEBATES WITH A LICENSEE TO A FIRM CONCLUSION BY INDICATING, AT THE APPROPRIATE TIME, THE BOARD'S DECISION AND THE REASONS THEREFORE. WHERE THE BOARD IS NOT YET IN A POSITION TO MAKE A DECISION IT SHOULD PLACE AN APPROPRIATE TIME CONSTRAINT ON THE DURATION OF UNRESOLVED DISAGREEMENTS RELATING TO VITAL SAFETY MATTERS.

RECOMMENDATION XVI THE BOARD SHOULD SET OUT THE FUNDAMENTAL REQUIREMENTS FOR THE CRITICAL SYSTEMS IN A NUCLEAR PLANT - PROCESS SYSTEMS, EMERGENCY COOLING SYSTEMS AND CONTAINMENT SYSTEMS - AND THE WAYS IN WHICH ACCIDENT ANALYSIS MUST BE DONE TO SATISFY THE REQUIREMENTS.

RECOMMENDATION XVII THE BOARD SHOULD SPECIFY THE ROUTINE REQUIREMENTS OF ITS OWN ON-SITE INSPECTORS, DEVELOP APPROPRIATE DAY-TO-DAY OPERATIONAL AUDITING ROUTINES AND BEGIN A REGULAR SYSTEM OF INSPECTION REPORTS. Change Board Composition & Functioning . • The Atomic Energy Control Board itself, as opposed to its staff and the processes that surround it, is, in the end, the critical element in public confidence in the adequacy of safety regulation of nuclear plants. Even though the Committee itself has been able to conclude that, at this time, and based on the information it has examined, Ontario's nuclear plants can be considered safe enough for continued operation, it recognizes that the ongoing confidence of the public rests with the Board. In the view of the Committee,' the Board must recognize that this is one of its most important functions. The Board must not only satisfy itself that nuclear operations are safe enough, it must, through its composition and functioning satisfy the public. The existence of this Committee is proof that the Board has not satisfied the public. There are five aspects of the Board's current operation that do not lend themselves to improved public confidence. 1. Board membership is from the technical community including the National Research Council, the university community and the medical profession. If one of the key jobs of the Board is to balance technical considerations with public needs, this technical membership should be supplemented by members drawn from the general public. 2. Board role as evidenced by the Bruce correspondence is very limited. The Board meets infrequently and there was no evidence that the Board itself pushes the staff to take a tougher stand or to try to further tighten a particular approach.

3. Board secrecy about its proceedings and decision making makes the public almost completely unaware that the Board is performing any function at all. Without public awareness, there can be no public confidence. *. Board powers appear to limit the Board to issuing or withdrawing a license, allowing full or reduced power operation. There is some concern that this is such an extreme action that the Board may sometimes be reluctant to take it. 5. Board staffing relies too heavily on in-house expertise, reducing the breadth of the technical community informed about nuclear power and raising the critic's concern that the Board is receiving opinions from too narrow and too limited a group. The Committee is aware that the Board is operating under some constraints because new legislation that would have moved the Board into a more desirable open direction did not get passed before the last Federal election. The Board may be required to work for several more years under the current legislation. The Committee urges the Board to take ail the steps it can to increase public awareness and public confidence in its proceedings by holding public hearings and, by making its decisions, and reasons for decision, public. The Committee notes that as this report was being prepared the AECB did develop a new public information policy that will significantly increase public access to and awareness of Board decisions. If fully implemented it will also ensure public access to information about each plant. The Committee endorses this new direction and further supports it by recommending that: , 5

- RECOMMENDATION XVIII THE AECB SHOULD STRIVE TO ADOPT^THE MOST-OPEN AND PUBI.IC POSITION POSSIBLE BY BROADLY INTERPRETING ITS CURRENT LEGISLATION.

RECOMMENDATION XIX THE AECB SHOJULD BROADEN ITS T MEMBERSHIP TO INCLUDE REPRESENTATION FROM THE GENERAL PUBLIC AS WELL AS THE INFORMED TECHNICAL < COMMUNITY.

RECOMMENDATION XX' THE AECB SHOULD SEEK AN INCREASE IN ITS FUNDING TO ENABLE IT TO INCREASE ITS CONTRACTING FOR INDEPENDENT OUTSIDE RESEARCH INTO I-]"'-- MATTERSOF NUCLEAR SAFETY. _ f

RECOMMENDATION XXI THE AECB SHOULD REPORT TO THE HOUSE OF COMMONS THROUGH A MINISTER OTHER THAN THE MINISTER RESPONSIBLE FOR AECL.

RECOMMENDATION XXH THE AECB SHOULD MAKE ITS PROCEEDINGS OF DECISION MORE WIDELY KNOWN. ITS MEETINGS SHOULD BE OPEN TQ THE PUBLIC UNLESS THERE IS A REASON FOR KEEPING ONE CLOSED.

RECOMMENDATION XXIII THE AECB SHOULD WORK WITH ITS LICENSEES TO ENSURE THAT DOCUMENTS MADE AVAILABLE TO THE PUBLIC ARE, TO THE GREATEST EXTENT POSSIBLE, ACCURATE, COMPLETE AND COMPREHENSIBLE.

RECOMMENDATION XXIV THE RULES UNDER WHICH THE BOARD OPERATES, INCLUDING SPECIFIC LICENSING CRITERIA, SHOULD BE THE SUBJECT OF PUBLIC HEARINGS WHEN FORMULATED OR CHANGED. THE AECB SHOULD HAVE GENERAL POWERS OF INTERPRETATION AND THE POWER TO GRANT EXEMPTIONS. INTERPRETATIONS AND EXEMPTIONS MUST, HOWEVER, BE PUBLICLY EXPLAINED IN A TIMELY MANNER IN THE BOARD'S REASONS FOR A PARTICULAR DECISION. DISSENTS DISSENT OF THE FOLLOWING MEMBERS: JIM FOULDS, EVELYN GIGANTES, BOB MACKENZIE

Following the Three Mile Island accident and the leak of then-secret documents concerning "incidents" at the Bruce nuclear reactors, the Select Committee was forced to acknowledge public concern in Ontario by changing its work agenda and spending several months of hearings in examination of the safety of Ontario's CANDU reactors. The difficulty of reaching an objective judgement on the "acceptability" of risk associated with Hydro reactors is extreme. The judgement is made in circumstances which mean that a negative judgement would have enormous economic implications for the province. The operation of the Pickering reactors and the Bruce reactors has become an integral part of the electricity supply in Ontario, and it is inconceivable that this dependence could be phased out quickly or without severe financial consequences. Given this framework of circumstances, it is inevitable that any reasonable person would conclude that the risk associated with the operation of Pickering and Bruce must be accepted. But a judgement of this kind should not be taken as absolute - it is a judgement based on dependence, and a judgement which relates risk to the virtual impossibility of identifying an immediate alternative. The public of Ontario looks to the Select Committee for a judgement of whether Hydro's reactors are "acceptably safe". V the conclusion of the Committee is conditioned by supply and financial considerations, it is vital that the public be given a clear understanding of the relativity of the Committee conclusion. In spite of the numerous indications of dissatisfaction with safety matters which are outlined in thé Committee report, the report in no way addresses the element of relativity which must so strongly condition any current judgement of the "acceptability" which the Committee had to take into account.

This is a serious failing in the Committee report. We find this particularly regrettable in view of the thorough evaluation that the Committee gave to this question and the sincerity with which all members have approached the problem. Nevertheless, the interested reader of the report is not informed that supply and economic considerations have formed the context, the very atmosphere, in which the Committee was forced to evaluate "acceptable safety". In its most extreme form, the logic of the existing evaluation can lead to a judgement which is based on the following circular reasoning: The public asks the Committee to judge if existing reactors are "acceptably safe". The Committee notes that the public has historically accepted the operation of these reactors. Therefore, the public has accepted the safety of the reactors. Therefore, the reactors are acceptably safe.

The examination of the tautology contained in this kind of reasoning points to the necessity of ensuring that the public be given an explicit explanation of the factors which lead the Committee to recommend that the public be willing to accept current risk from the operation of Pickering A and Bruce A. The failure of the report is that the omission of this information suggests that the acceptability of current reactors is an absolute judgement, and that it can therefore be extended to endorsation of constructing more reactors. In fact, the current dependence on Pickering A and Bruce A should not be the grounds for 46 extending supply and economic dependence on nuclear-generated electricity. Nor should the current dependence on these facilities be confused with the questions of whether the public should accept the additional risk associated with additional reactors. And because the report is limited to examining the question of reactor safety, it does not explore fully the inadvisability of an electrical system as large as Ontario Hydro's becoming only dependent on one source of power for electricity. We hope in the Committee's future work the question of a balanced mix for the system will be fully addressed. But the present report of the Committee at least allows the confusion between dependence and acceptability, if it does not actively promote it.

The failure of the Committee report on this count is most clearly demonstrated by the recommendation that the NPD reactor at Rolphton be permitted to continue in operation. The report outlines a series of major concerns about NPD which were examined by the Committee: The original licence criteria do not meet current licence standards; design inadequacies have been identified and are not yet corrected; equipment failures make operation sporadic (38% capacity in 1979). In addition trie Committee learned that what power is produced by NPD is not either a significant source of supply for the grid or an economic source of electricity. Despite its specific findings about safety concerns associated with NPD, the Committee report states that "the plant should be allowed to operate while modifications that will bring it within the single failure limit are being analyzed." The report cites no reason of supply or economics for this conclusion, but instead gives stress to the fact that the total consequences of an accident at the NPD reactor would be lower than at larger reactors. While this is obviously correct it does not mitigate the relative risk to those smaller number of people who might be exposed to radiation'in the event of a serious accident at NPD. Nor does it answer the question of why risk beyond the levels of current criteria should be accepted, especially when the reactor is not one on which Ontario depends for supply or economic reasons.

While the conclusions of the report concerning the NPD reactor are the clearest sign that the majority of the Committee has failed in its attempt to define "acceptable risk", the fact that the report does not recommend the closing of the Douglas Point reactor has to be taken as further evidence of confused judgement. Like the NPD, the Douglas Point reactor was an early prototype in commercial CANDU design. It too has been found to have design inadequacies, and has been allowed to operate by the AECB on condition that it is not operated at full power. Neither reactor has a vacuum building containment system, and neither provides a significant or economic source of electricity for the grid.

To sum up: The Committee report, while it provides a useful account of the findings of many months of work and reflection, and advances a number of constructive proposals for improving the procedures of reactor safety regulation in Ontario, is a report which fails to identify the elements of safety, supply dependence and economic considerations which interrelate in the judgement of "acceptable safer/".. This failure, in turn, means that the interested public which looks to the re : for a clarification of the issues involved in deciding whether Ontario reactors are "acceptably safe" will find the report a confusing document. It offers much less than it should in terms of logical consistency and definition of issues, and it falls regrettably short of reflecting the quality of work which the Committee accomplished as we attempted to answer public questions about the safety of Ontario's reactors. DISSENT OF THE FOLLOWING MEMBERS: GEORGE ASHE, ALBERT BELANGER, MICKEY HENNESSY, NICK LELUK AND JOHN WILLIAMS

The above Progressive Conservative members submit the following dissent on the report of the Select Committee's examination of the safety of Ontario's nuclear reactors. We generally support the Committee's report with the exception of Recommendation X. RECOMMENDATION X: THE AECB SHOULD COMMISSION A STUDY TO ANALYZE THE LIKELIHOOD AND CONSEQUENCES OF A CATASTROPHIC ACCIDENT IN A CANDU REACTOR. THE STUDY SHOULD BE DIRECTED BY RECOGNIZED EXPERTS OUTSIDE THE AECB, AECL AND ONTARIO HYDRO. IT SHOUDL BE FUNDED BY A SPECIAL GRANT FROM THE FEDERAL GOVERNMENT. IF THIS STUDY IS NOT COMMISSIONED BY JULY 31, 1980, THE PROVINCE OF ONTARIO SHOULD ENSURE THAT IS IS UNDERTAKEN.

We share the opinion of the majority of Members of the Committee based on the extensive testimony of the expert witnesses who appeared before us, that the nuclear reactors operating in Ontario are "acceptably safe". We also share, with all Members of the Committee, a wish that every effort be made to ensure that the design, construction and operation of reactors in Ontario be made as safe as is reasonably possible. In our view, based on the extensive, knowledgeable testimony heard by the Committee, the undertaking of a substantive and expensive study would probably serve little purpose but to identify the fact that a catastrophic type of accident is possible but highly improbable. The results would, as in the Rasmussen study undertaken in the United States, be widely debated and challenged and would in the end serve little practical purpose except to confirm the consensus of this Committee that the reactors are "acceptably safe". In any event, it is our feeling that further studies deemed necessary by the regulatory authority should be commissioned by that authority. It would in our view be wrong to suggest that the Ontario Government should assume responsibility far a study which is clearly within the proper jurisdiction of the federal government and/or its agency. During the course of the Committe's hearings, the President of the Atomic _ Energy Control Board indicated that the Board had recognized the need to study further the possible consequences of severe reactor malfunctions and had already taken steps to evaluate same through studies at Carleton University. We also heard testimony from Atomic Energy Control Board, Atomic Energy of Canada Limited, Ontario Hydro staff and others, that to undertake an even more comprehensive study, similar to the Rasmussen study in the United States, would likely take a number of years to complete and would represent a very major research undertaking. In conclusion we do not believe it to be reasonable, or perhaps even practical, to have anyone other than the responsible federal regulatory agency undertake such a study and to assume, thereby, the apparent responsibility for taking any subsequent action on the basis of the results of the study.

The laws of the Government of Canada provide that the AECB be the sole regulatory agency with respect to nuclear reactor safety in Canada. APPENDIX A TERMS OF - APPENDIX A

TERMS OF REFERENCE On motion by Mr. Welch, seconded by Mr. Kerr, ORDERED, That a Select Committee of the Legislature be appointed: First, to inquire into the cost of construction of the two heavy-water plants being built by Ontario Hydro at the Bruce Nuclear Power Development, and report to the Legislature on all factors affecting cost, such examination to include but not be limited to: (a) The requirements for heavy water, the original estimates of the cost of the plants and the contract signed with the Lummus Company of Canada for the construction of the plants and the conditions placed on the contracts for Canadian content; (b) The change in the scope of the work required due to changes in plant design after the original estimates were completed; (c) The effect on the total cost of the plants and their construction schedule due to the cancellation of the fourth plant known as plant "C";

(d) The factors affecting any additional costs incurred by the contractor and Hydro for the supply of major equipment, structural components or other supply items; (e) The factors affecting escalation of sub-contracts placed by the contractor, or Hydro for work related to the construction of the plants; (f) The factor affecting labour costs for construction of the plant including escalation of labour rates, work stoppages, union jurisdictional disputes, and the shortage of any labour skills required for construction; (g) The effect of interest rates, and foreign exchange rates on the overall costs of construction; (h) The administration of the contract by Hydro and the control methods used to monitor and minimize the cost, and to prepare and submit a report for the Legislature upon the conclusions of this inquiry. Second, to review the implementation of the recommendations of the Select Committee of the 30th Parliament which examined Ontario Hydro's proposal for bulk power rate increases for 1976; such review to include consideration of Ontario Hydro's status reports tabled by the Ministry of Energy. Third, to examine Ontario's nuclear commitment, taking into account the report and recommendations of the Royal Commission on Electrical Power -A/2-

Planning and Ontario's Energy Future, such examination to include but not be limited to: (a) Ontario Hydro's system planning strategy for adopting nuclear power and, in particular: o Large v. small generating stations; o Remote stations v. sites close to urban areas; o The ratio of nuclear-fuelled generating stations that should be built in comparison to fossil fuelled stations, keeping in mind security of supply and cost differentials; (b) The economics of nuclear power v. generation from other primary fuels; (c) The performance and reliability of nuclear generating stations; (d) The responsibility for, and the standards relative to the safety of nuclear generation stations; (e) Environmental impact and health considerations related to nuclear power. And that the Select Committee may prepare and submit interim reports for the Legislature and shall prepare and submit a final report before the end of December, 1978, and that the Select Committee may request such coverage of its proceedings by Hansard and the printing of such papers as the Committee deems appropriate; and the Committee shall have authority to sit during the interval between sessions and have full power and authority to employ counsel and such other personnel as may be deemed advisable and to call for persons, papers and things, and to examine witnesses under oath and the Assembly doth command and compel attendance before the said Select Committee of such persons and the production of such papers and things as the Committee may deem necessary for any of its proceedings and deliberations, for which the Honourable Speaker may issue his warrant or warrants; and the Committee shall be composed of 14 members as follows: Mr. MacDonald (Chairman), Ashe, Foulds, Gigantes, Haggerty, Handleman, Jones, Kerrio, Lane, Leluk, Nixon, Reed (Halton-Buriington), Samis, and Williams*.

Messrs. Handleman, Jones, Kerrio, Lane, Samis and Nixon were subsequently replaced by Messrs. Belanger, Cureatz, Conway, Hennessy, Mackenzie and Kerrio. APPENDIX B CHRONOLOGY OF THE RECORD OF HEARINGS iNTO THE SAFETY OF NUCLEAR REACTORS IN ONTARIO APPENDIX B CHRONOLOGY OF THE RECORD OF HEARINGS INTO THE SAFETY OF NUCLEAR REACTORS IN

ONTARIO

Date of Meeting Name of Organization and Personnel Representatives

April 19,1979 Royal Commission on Electric Power Planning Porter, Dr. A., Chairman Smith, Ronald, Executive Director Mueller, Mr. Peter, Senior Advisor Choudhury, Mr. Sushil, Researcher

April 20,1979 Royal Commission on Electric Power Planning Porter, Dr. A., Chairman Smith, Ronald, Executive Director Mueller, Mr. Peter, Senior Advisor Choudhury, Mr. Sushil, Researcher

April 25,1979 Ministry of Labour Armstrong, T.E., Deputy Minister Fitch, Dr. Max, Director, Special Studies and Services Branch Aitken, Dr. Harry, Chief, Radiation Protection Services

Atomic Energy Control Board Jennekens, Jon, President

Ontario Hydro McConnell, Lome, General Manager, Operations Morison, W.G., Director, Design and Development Division Woodhead, L.W., Director, Nuclear Generation Division Wilson, R., Director of Health and Safety Watson, D., Manager, Safety Services Department -B/2-

Date of Meeting Name of Organization and Personnel Representatives j

AprU 26, 1979 Ontario Hydro McConnell, Lome, General Manager, Operations Morison, W.G., Director, Design and Development Division Woodhead, L.W., Director, Nuclear Generation Division Wilson, R., Director of Health and Safety Watson, D., Manager, Safety Services Department

Ministry of Labour Fitch, Dr. Max, Director, Special Studies and Services Branch Aitken, Dr. Harry, Chief, Radiation Protection Services

Ontario Provincial Police Lidstone, J.S., Assistant Commissioner

AprU 27,1979 Ontario Hydro Watson, D., Manager, Safety Services Department Kelly, R.J., Reactor Safety Engineer, Radioactivity Management and Environmental Protection Department (Member of Ontario Scientific Assessment Team)

Ministry of Labour Aitken, Dr. J.H., Chief, Radiation Protection Service Fitch, Dr. Max, Director, Special Studies and Services Branch ; Johnson, Dr. A., Consultant on Energy Research (Member of Ontario Scientific Assessment Team) Wong, Dr. K.Y., Supervisor, Central Health and Safety Division (Member of Ontario Scientific Assessment Team)

May 3,1979 Ontario Hydro

McConnell, Lorne, General Manager, Operations Morison, W.G., Director, Design and Development Division -e/3-

Date of Meeting Name of Organization and Personnel Representatives May 3,1979 (continued) Woodhead, L.W., Director, Nuclear Generation Division Watson, D., Manager, Safety Services Department Austman, H.L., Station Manager, Bruce "A" Nuclear Generating Station

May 4,1979 Ontario Hydro •McConnell, Lome, General Manager, Operations Morison, W.G., Director, Design and Development Division Woodhead, L.W., Director, Nuclear Generation Division Wilson, R., Director of Health and Safety Watson, D., Manager, Safety Services Department Austman, H.L., Station Manager, Bruce "A" Nuclear Generating Station

May 24,1979 Committee Meeting with Staff and Members

June 15, 1979 Ontario Hydro Morison, W.G., Director, Design and Development Division

June 20,1979 Ontario Hydro Morison, W.G., Director, Design and Development Division

July »,1979 Ontario Hydro Morison, W.G., Director, Design and Development Division Irvine, H.S., Group Manager, Nuclear Design and Development Division

July 5,1979 Canadian Coalition for Nuclear Responsibility Edwards, Dr. G., National Chairman -B/4-

Date'.I Meeting Name of Organization and Personnel Representatives

July 6, 1979 Atomic Energy Control Board Jennekens, Jon, President Bush, W.R., Manager, Radiation Protection Division

July 9, 1979 Atomic Energy Control Board Bush, W.R., Manager, Radiation Protection Division

Atomic Energy of Canada Limited Blackstein, F., Assistant to the Vice-president, Chalk River Nuclear Laboratories Myers, Dr., D., Director, Biology Branch, Chalk River Newcombe, Dr. H., Director, Population Research Branch, Chalk River

Ontario Coalition for Nuclear Responsibility Torrie, Mr. R.

July 10, 1979 University of Pittsburgh, Pittsburgh, Pent. Radford, Dr. E.P., Professor of Environmental Epidemiology, Graduate School of Public Health

Roswell Park Memorial Institute for Cancer Research Buffalo, N.Y. Brass, Dr. I.D.J., Director of Biostatistics

July U, 1979 Harvard University, Cambridge, Mass. Rothman, Dr. K. Associate Professor of Epidemiology, School of Public Health

Ontario Hydro Wilson, R., Director, Health and Safety Division -B/5-

Date of Meeting Name of Organization and Personnel Representatives July 12, 1979 Renfrew Cotaity Citizens for Nuclear Responsibility (held in Deep River, Ontario) Schultz, Mr. N., Counsel Cowan, Mr., Spokesman

Municipality of Deep River Smith, LyaJl, Acting Mayor

Township of Rolph Dumanoir, Mr. Guy, Reeve

Village of Chalk River Sequin, Mr. Bob, Reeve

Townships of Head, Clara, & Maria Horricks, Mr. Grant. Reeve

County of Renfrew Sadler, Mr. Jack

Renfrew County Travel Association Hocking, Mr. Brian

Township of Alice and Fraser Donahue, Mr. Al, Clerk-Treasurer

Serdula Systems Serdula, Mr. Kenneth, President

Deep River Area Business Association Fairfield, Mr. Paul -B/6-

Date of Meeting Name of Organization and Personnel Representatives July 12,1979 (cont'd) Society for Professional Employees, Chalk River Laboratories Cassidy, Mr. Richard

Atomic Energy Allied Coiaicil St. John, Mr. Clarence, President

Society for Hydro Management and Professional Staff Sutton, Mr. Glenn, Delegate in Rolphton

Private Citizens Mr. Zadow Mr. Bob Walker Mr. John Snider Mrs. Catherine Dalrymple Mr. J. Pachner Mr. Lionel Ritter Mr. E.J. Craig Mr. Al Link Mr. McLeod Mr. Philip Simpson Mr. David Wylie Mr. Jacques Rubacha Mr. Andrew Stirling Mr. Ken Burkhart Mr. Donald Sutherland

July 13, 1979 Atomic Energy Control Board Domaratzki, Z., Director, Reactor and Accelerator Branch

Atomic Energy of Canada limited Axford, D., Head, Reactor Technology Branch Morrison, L, Director, Special Projects Division Chalk River Nuclear Laboratories

July 13, 1979 Ontario Hydro Kelly, R.J., Reactor Safety Engineer, Nuclear Generation Division -B/7-

Date of Meeting Name of Organization and Personnel Representatives

July 13, 1979 (cont'd) Müley, D.C., Station Manager, NPD Generating Station

3uly 17, 1979 Atomic Energy of Canada Limited Blackstein, F.P., Assistant to the Vice-President, Chalk River Nuclear Laboratories Krishnan, S., Branch Manager, Safety Branch, , Ontario Snell, V., Section Head, Safety Branch, Mississauga, Ontario

University of Montreal

Paskievici, Or. W.f Chairman, Interorganizational Working Group

July 18, 1979 Atomic Energy Control Board Atchison, R.J., Director, Assessment Branch

July 19, 1979 Atomic Energy of Canada Limited Axford, O., Head, Reactor Technology Branch

Ontario Hydro Kelly, R.J., Reactor Safety Engineer, Nuclear Generation Division Milley, D.C., Station Manager, NPD Generating Station

July 23, 1979 Carleton University, Ottawa, Ont. Rogers, Dr. J.T.

July 24,1979 Atomic Energy Control Board Domaratzki, Z., Director, Reactor and Accelerator Branch -B/8-

Date qdc Meeting Name of Organization and Personnel Representatives July 25, 1979 Energy Pathways Foster, D.

Canadian Coalition for Nuclear Responsibility Edwards, Dr. C, National Chairman

July 26,1979 Ontario Hydro Irvine, H.S., Group Manager, Nuclear Design and Development Division Morison, W.G., Director, Design and Development Division

July 31, 1979 Ontario Hydro McConnell, L.G., Vice-President, Production and Transmission Popple, R.T., Assistant to the Director, Nuclear Generation Division Ryder, 3., Station Manager, Pickering Generating Station Voodhead, L, Director, Nuclear Generation Division

August 1,1979 Edwards, Dr. G., National Chairman Private Citizens Mr* G» Newby Mr.W.Taves

August 2,1979 Royal Commisston on Electric Power Planning Porter, Dr. A., Chairman Mueller, P.G., Senior Adviser

university ox Toronto, Toronto, unt. Foley, Dr. P.J., Professor of Industrial Engineering Senders, Dr. J.W., Professor of Industrial Engineering Kaponeridis, A., Human Factors Engineer -B/9-

Date of Meeting Name of Organization and Personnel Representatives AugMSt 7, 1979 Ontario Hydro Kelly, R.J., Reactor Safety Engineer, Nuclear Generation Division Owens, A.H., Location Technical Transmission Systems Division Ryder, 3., Station Manager, Pickering Generating Station Woodhead, L., Director, Nuclear Generation Division

August 3, 1979 Atomic Energy Control Board Domaratzki, Z., Director, Reactor and Accelerator Branch

August 9, 1979 Ontario Coalition for Nuclear Responsibility Torrie, R.D.

August 14,1979 Ontario Hydro Horton, E.P., Operations Manager, Bruce Nuclear Power Development Austman, H.L., Station Manager, Bruce Nuclear Power Development Ryder, J., Production Manager, Pickering Generating Station

August 15, 1979 Atomic Energy Control Board Jennekens, Jon, President

Ministry of Energy ft Natural Resources Auld, Hon. J.A.C., Minister

August 16, 1979 Ontario Hydro Macaulay, H.L., Chairman of the Board

September 18,1979 The Renfrew County Churns for Nudear Responsibility Schultz, N.J., Counsel -B/10-

Date ol Meeting Name of Organization and Personnel Representatives September 19, 1979 Atomic Energy of Canada Limited Morrison, I.W., Director, Special Projects Division Axford, DJ., Head, Reactor Technology Branch Hancox, W.T., Ph.D., Director, Applied Science Division, Whitesheil Nuclear Research Establishment, Pinawa, Manitoba Nieman, Dr. R.W., Head, Thermalhydraulics Research Branch, Whiteshell Nuclear Research Establishment, Pinawa, Manitoba Blackstein, F.P., Assistant to the Vice-President, Chalk River Nuclear Laboratories

Ontario Hydro Popple, R.T., Assistant to Director, Nuclear Generation Division Kelly, R.J., Reactor Safety Engineer, Nuclear Generation Division Milley, D.C., Station Manager, NPD Generating Station

September 20, 1979 Canatom (Ontario) Limited Siddall, E., President

Energy Probe Rubin, N., Nuclear Power Researcher

September 25,1979 Ontario Hydro Morison, W.G., Director Design and Development Division Irvine, H.S., Group Manager, Nuclear Design and Development Division

September 26,1979 Canadian Coalition for Nuclear Responsibility Edwards, Dr. G., National Chairman

Federation of Engineering and Scientific Associations Bailey, Chris, Executive Member of the Board Shalaby, Amin, Executive Member of the Board -B/ll-

Date of Meeting Name of Organization and Personnel Representatives September 26, 1979(cont'd) Atomic Energy of Canada Limited Blackstein, F.P., Assistant to the Vice-President Chalk River Nuclear Laboratories

September 27, 1979 Atomic Energy Control Board Domaratzki, Z., Director, Reactor and Accelerator Branch Jennekens, Jon, President

October 2,1979 Ontario Hydro Morison, W.G., Director, Design and Development Division Wilson, R., Director, Health and Safety Division Popple, R.T., Assistant to Director, Nuclear Generation Division

October 3,1979 Committee Meeting with Staff and Members

October *, 1979 Committed Meeting with Staff and Members

October 24, 1979 Committee Meeting with Staff and Members

November 15,1979 Committee Meeting with Staff and Members

February 12,1980 Atomic Energy of Canada limited Axford, D., Head, Reactor Technology Branch, Nuclear Laboratories, Chalk River Blackstein, F.P., Assistant to Vice-President, Chalk River Martin, M.P., Manager, Public Information Programs, Corporate Office, Ottawa

Ontario Hydro Childerhose, Manager, Radioactivity Management and Environmental Protection Department Kelly, RJ., Reactor Safety Engineer, Nuclear Generation Division -B/12-

Date of Meeting Name

Ontario Hydro Parry, O.A., Technical Superintendent, Douglas Point

February 14,1980 Atomic Energy Control Board Oomaratzki, Dr. Z., Director, Reactor and Accelerator Branch

February 19,1980 Ontario Hydro Richman, Dr. Jack W., Nuclear Equipment and Processes Engineer, Nuclear Systems Department, Design and Development Division Morison, W.G., Director, Design and Development Division

February 20,1980 Ontario Hydro Morison, W.G., Director, Design and Development Division Kelly, R.J., Reactor Safety Engineer, Nuclear ' Generation Division

February 26,1980 Ontario Hydro Vivian , Gary A., Assessment, Safety and Program Engineer, Nuclear Materials Management Department Wilson, R., Director, Health and Safety Division -B/13-

Date of Meeting Namcof Organization; February 27, 1980 Ediger, N.M., Immediate Past Chairman, President, Eldorado Nuclear Ltd. Foster, Or. J.S., First Vice-Chairman, Vice- President, Monenco (Ontario) MacOwan, W., Chairman of the Board, Vice- Chairman, Howden Group Canada Aspin, Dr. Norman, President McNicol, W.J., Director, Vice-President Power Systems Group, Westinghouse Canada Ltd.

February 28, 1980 Ontario Hydro Irvine, H.S., Group Manager, (Nuclear), Design and Development Division

April 10, 1980 Committee Meeting with Staff and Members

April 17, 1980 Committee Meeting with Staff and Members

May 28, 1980 Committee Meeting with Staff and Members

June 4, 1980 Committee Meeting with Staff and Members APPENDIX C UST OF WITNESSES APPEARWG BEFORE THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS APPENDIX C

LIST OF WITNESSES APPEARING BEFORE THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS

Government of Ontario Minister, HON J.A.C. AULD Ministry of Energy and Natural Resources Deputy Minister, T.E. ARMSTRONG Ministry of Labour Director, DR. MAX FITCH Special Studies and Sevices Branch Ministry of Labour DR. HARRY AITKliN Chief, Radiation Protection Services Ministry of Labour J.W.LIDSTONE Assistant Commissioner, Ontario Provincial Police

DR. A. JOHNSON Ontario Scientific Assessment Team, Ministry of Energy DR. KAM WONG Ontario Scientific Assessment Team, Ministry of Labour

Ontario Hydra

H.L. MACAULAY Chairman of the Board

LORNEMcCONNELL General Manager, Operations Division

W.G. MORISON Director, Design and Development Division H.S. IRVINE Group Manager (Nuclear), Design and Development Division L.W.WOODHEAD Director, Nuclear Generation Division R. WILSON Director, Health and Safety Division D. WATSON Manager, Safety Services Department -C/2-

Ontario Hydro (continued) GARY A. VIVIAN Assessment Safety and Program Engineer, Nuclear Materials Management Department

E.P. HORTON Operations Manager, . Bruce Nuclear Power Development H.S. AUSTMAN Station Manager, Bruce "A" Nuclear Generating Station G. CHILDERHOSE Manager, Radioactivity Management and Environmental Protection Department

R J. KELLY Reactor Safety Engineer, Nuclear Generation Division D.C. MILLEY Station Manager, NPD Generating Station A.H. OWENS Location Technician, Transmission Systems Division D.A. PARRY Technical Superintendent, Douglas Point

R.T. POPPLE Assistant to the Director, Nuclear Generation Division DR. JACK W. RICHMAN Nuclear Equipment and Processes Engineer, Nuclear Systems Department Design and Development Division

J. RYDER Station Manager, Pickering Generating Station

Atomic Energy of Canada Limited (AECL) F.P. BLACKSTEIN Assistant to the Vice-President, Chalk River Nuclear Laboratories D. AXFORD Head, Reactor Technology Branch Chalk River Nuclear Laboratories R,D. GADSBY Senior Licensing Co-ordinator, Engineering Company, Sheridan Park DR. W.T. HANCOX Director, Applied Science Division,, WhitesheU Nuclear Research Establishment -C/3-

Atomic Energy of Canada Limited (AECL) (continued) 1. HOPWOOD Section Head, Safety Analysis, Engineering Company Sheridan Park • • S. KIRSHNAN Branch Manager, Safety Branch Sheridan Park M.P. MARTIN Manager, Public Information Programs Corporate Office I. MORRISON Director, Special Projects Division Chalk River Nuclear Laboratories

DR. O. MYERS Director, Biology Branch Chalk River Nuclear Laboratories DR. H. NEWCOMBE Director, Population Research Branch Chalk River Nuclear Laboratories DR. R.W. NIEMAN Head, Thermaihydraulics Research Branch Whitesheil Nuclear Research Establishment D.A. SIMMONDS Senior Project Engineer Engineering Company Sheridan Park V. SNELL Section Head, Safety Branch Engineering Company Sheridan Park

Atomic Energy Control Board (AECB) JOHN 3ENNEKENS President

DR. Z. DOMARATZKI Director, Reactor and Accelerator Branch R J. ATCWSON Director, Assessment Branch W.R.BUSH Manager, Radiation Protection Division -c/*-

Royal Commission on Electric Power Planning DR. A. PORTER Chairman RONALD SMITH Executive Director PETER MUELLER Senior Advisor SUSHIL CHOUDHl'RY Researcher

Canadian Nuclear Association W. MacOWAN Chairman of the Board, (Vice-Chairman, Howden Group Canada)

NJVl. EDIGER Immediate Past Chairman, (President, Eldorado Nuclear Ltd.)

DR. 3.S. FOSTER First Vice-Chairman, (Vice-President, Monenco (Ontario)) W.J. McNICOL Director, (Vice-President of Power Systems Group for westinghouse Canada Ltd.)

DR. NORMAN ASPIN President

Other Witnesses—in alphabetical order MR. CHRIS BAILEY Executive Member of the Board, Federation of Engineering and Scientific Associations DR. LD J. BROSS Director of Biostatistics, Roswell Park Memorial Institute for Cancer Research, Buffalo, New York MR. RICHARD CASSIDY Society for Professional Employees, Chalk River Nuclear Laboratories MR. COWAN Renfrew County Citizens f or Nuclear Responsibility MR. AL DONAHUE Clerk-Treasurer, Township of Alice and Fraser MR. GUY DUMANOIR Reeve, Township of Rolph - C/5 -

Other Witnesses — in alphabetical order (continued)

DR. GORDON EDWARDS National Chairman, Canadian Coalition for Nuclear Responsibility MR..PAUL FAIRFIELD Spokesman, Deep River Area Business Association DR. P.J. FOLEY Professor of Industrial Engineering, University of Toronto

MR. D. FOSTER Energy Pathways MR. BRIAN HOCKING Renfrew County Travel Association MR. GRANT HORRICKS Reeve, Village of Chalk River MR. A. KAPONERIDIS Human Factors Engineer, University of Toronto

DR.W. PASKIEVICI Chairman, Interorganiz2tional Working Group, EcoJe Polytechnique, University of Montreal DR. E.P. RADFORD Professor of Environmental Epidemiology, Graduate School of Public Health University of Pittsburgh, Pittsburgh, Pennsylvania DR. J.T. ROGERS Carleton University, Ottawa, Ontario

DR. K. ROTHMAN Associate Professor of Epidemiology, School of Public Health, Harvard University, Cambridge, Massachusetts MR. N. RUBIN Nuclear Power Researchar, Energy Probe MR. JACK SADLER Spokesman, County of Renfrew MR. N. SCHULTZ Counsel, Renfrew County Citizens for Nuc'ear Responsibility MR. BOB SEGUIN Reeve, Township of Rolph DR. J.W. SENDERS Professor of Industrial Engineering, University of Toronto -C/6-

Other Witnesses—in alphabetical order (continued) MR. AM IN SHALABY Executive Member of the Board, Federation of Engineering and Scientific Associations MR. E. SIDDALL President, Canatom (Ontario) Limited MR. LYALL SMITH Acting Mayor, Municipality of Deep River MR. CLARENCE ST. JOHN President, Atomic Energy Allied Council MR. GLEN SUTTON Delegate in Rolphton, Society for Hydro Management and Professional Staff MR. R. TORRIE Ontario Coalition for Nuclear Responsibility

Private Citizens Appearing as Witnesses—in alphabetical order

MR. KEN BURKHART

MR. E.J. CRAIG

MRS. CATHERINE DALRYMPLE

MR. AL LINK

MR. McLEOO

MR. G. NEW BY

MR. J. PACHNER

MR. LIONEL RITTER

MR. JACQUES RUBACHA

MR. KENNETH SERDULA

MR. PHILIP SIMPSON

MR. JOHN SNIDER

MR. ANDREW STIRLING

MR. DONALD SUTHERLAND

MR. W. TAVES -C/7-

Private Citizens Appearing as Witnesses — in alphabetical order (continued) MR. BOB WALKER MR. DAVID WYLIE MR. ZADOW APPENDIX D LIST OF EXHIBITS TABLED IN MEETINGS FROM APRIL 25,1979 TO APRIL 10,1980 APPENDIX D LIST OF EXHIBITS TABLED IN MEETINGS FROM APRIL 25, 1979 to APRIL 10,1980

Exhibit # . Title Date Tabled

E-l Presentation to The Select Committee April 25, 1979 ol the Ontario Legislature on Nuclear Safety & Emergency Procedures for Nuclear Generation Stations. E-2 AECB - 1139 - The Licensing April 25, 1979 Process for Nuclear Power Reactors, by M. Joyce, Atomic Energy Control Board, Ottawa. E-3 Letter dated April 17, 1979 from April 25, 1979 Thomas L. Wells, Minister, Ministry of Intergovernmental Affairs to The Honourable Don Jamieson, Re: Accident at Three Mile Island Plant at Middletown, Pennsylvania.

. E-4 Presentation to The Select Committee April 26, 1979 on Ontario Hydro Affairs concerning Off-Site Contingency Plans. E-5 Notice to public from Medical April 26, 1979 Officer of Health Regional Municipality of Durham and Chief Physician/Manager Health Services, Ontario Hydro, Re: Radioactive material in air.

E-6 Statement by Leader of the Opposition, April 27, 1979 to Hydro Affairs Committee, Re: Nuclear Reactor Safety. E-7 Ontario Hydro 1979 Review of April 27, 1979 Generation Expansion Program E-7A Supplement to 1979 Review of April 27, 1979 Generation Expansion Program Comparison of the Recommended Alternative with Alternatives 3 and 5 -D/2-

Title Date Tabled

Report of The Scientific Assessment April 27, 1979 Team to the Ontario Interministeriai Agency Coordinating Committee, Re: Three Mile Island Nuclear Generating Station Accident of March 28, 1979. E-9 Presentation to The Select Committee May *, 1979 of the Ontario Legislature on Nuclear Safety & Emergency Procedures for Nuclear Generating Stations. E-10 Reporting of Abnormal Events May 23, 1979 Dated, May », 1979 E-ll Royal Commission on Environmental May 23, 1979 Pollution. Chairman, Sir Brian Flowers. Sixth Report. Nuclear Power and the Environment. Presented to Parliament by Command of Her Majesty, September 1978. E-ll A Nuclear Power and the Environment. May 23, 1979 The Government's Response to the Sixth Report of the Royal Commission on Environmental Pollution (Comnd). Presented to Parliament by the Secretary of State for the Environment by Command of Her Majesty, May 1977.

E-12 The Cluff Lake Board of Inquiry May 23, 1979 Final Report, May 31, 1978. E-12A The Saskatchewan Government May 23, 1979 Response to The Cluff Lake Board of Inquiry Report, June 1978. E-13 Summary Argument to the Royal May 23, 1979 Commission on Electric Power Planning (Porter Commission), by Ralph Torrie and Gordon Edwards, Canadian Coalition on Nuclear Responsibility, 2030 Mackay, Montreal, 1978. -D/3-.

Title Date Tabled

The Atomic Energy Control Board May 23, 1979 In the Matter of the Atomic Energy Control Act, R.S.C. 1970 c. A-19. In the Matter of an Application by James Croy, Valerie Croy, Charles Myers, Sharon Myers, Henry Venema, Mary Anne Venema, and The Renfrew County Citizens for Nuclear Responsibility for a Public Hearing into the Safety of the Nuclear Reactor at Rolphton on the Ottawa River in the County of Renfrew. E-15 Letter dated June 20, 1979 June 20, 1979 From Robert B. Taylor, Chairman and Hugh L. Macaulay, Vice Chairman to Donald MacDonald, Chairman, Ontario Select Committee on Hydro Affairs, Re: Controlled access to nuclear safety documents. E-16 Letter dated June 27, 1979 juiy *, 1979 From N.J. Schultz, Counsel for the Renfrew County Citizens for Nuclear Responsibility to Donald MacDonald, Chairman, Select Committee on Ontario Hydro Affairs Re: Nuclear Reactor Safety. E-17 Letter from J.E. Wilson, Public July *, 1979 Hearings Officer, Public Hearings Department to Donald MacDonald, Chairman, Select Committee on Ontario Hydro Affairs, Re: Attached list of information forwarded to Legislative Library. E-17A Reports requested by the Select July 10,1979 Committee on Ontario Hydro Affairs, Re: Controlled Access. E-17B Reports requested by the Select July 10, 1979 Committee on Ontario Hydro Affairs, Re: No Restriction. -D/4-

Exhibttf Title Date Tabled

E-17C Letter dated August 3, 1979 from August 7, 1979 J.E. Wilson, Public Hearings Officer, Ontario Hydro to Donald MacOonald, MPP, Chairman, Select Committee on Ontario Hydro Affairs, Re: Documents forwarded to Legislative Library. E-18 Select Committee on Ontario July 4, 1979 Hydro Affairs. Examination of Ontario's Nuclear Commitment — Staff Introduction to Summer Hearing into The Safety of Ontario Reactors, July», 1979. E-19 Presentation to The Select Committee July *, 1979 of the Ontario Legislature on Nuclear Power, July 1979, Re: Introduction, Safety Philosophy and Criteria, Design, Licensing, Operation, Safety Administration and Control, Summary and Conclusions

E-20A ' "Do Nuclear Engineering Educators July 5: 1979 have a Special Responsibility?". Alvin M. Weinberg, Institute for Energy Analysis, Oak Ridge Associated Universities, Oak Ridge, Tennessee, U.S.A. E-20B Canadian Coalition for Nuclear July 5, 1979 Responsibility Excerpts from Estimating Lung Cancers or, "It's Perfectly Safe, But Don't Breathe Too Deeply" Summary presented by Gordon Edwards, to Elliott Lake Environmental Assessment Board, March 1973 (revised May, 1973) c-20C Letter dated February 2,1979, July 5,1979 from Victor E. Archer, M.D., Medical Director, Department of Health, Education, and Welfare, Public Health Service, Health Services and Mental Health Administration, Salt Lake City, Utah, to Mr. Frank Palmay, Re: Risk Estimates. -D/5-

Exhibitf Title Date Tabbed E-20D Letter datf.d March 2, 1979, July 5, J*79 from Gordon Edwards, Canadian Coalition for Nuclear Responsibility, to Mr. P,J. Dyne, Director, Office of Energy Research and Development, Ottawc, Re: Reactor Grade Plutonium for Bombs E-20E Could Britain be Energy Self. July 5, 1979 Sufficient by 2000? Nev? Report Stresses Efficiency Gains, Better Forecasting, Reduced Nuclear. E-20F Letter dated March 6, 1979, from July 5, 1979 Gordon Edwards, Canadian Coalition for Nuclear Responsibility to Mr. Jon Jennekins, President, Atomic Energy Control Board (AECB), Ottawa. E-20G Letter dated January 13, 1979, July 5, 1979 from Gordon Edwards, Canadian Coalition for Nuclear Responsibility to Bob Blackburn, Secretary, Atomic Energy Control Board (AECB), Ottawa, Re: CANDU Safety and Canadian Radiation Standards.

E-20H Article from The Sunday Times, July 5, 1979 London, Re: Nuclear plant in 'Quake Zone' Act of Madness - -Geologist says. E-20I News Article, Re: Quebec's July 5, 1979 Reactor: How Safe Is It? Plant Having problems says Hydro Engineer. E-203 The Incident at Browns Ferry July 5, 1979 —Alabama's Nightmare in Candlelight, by David Dinsmore Comey. E-20K Press Release and background July 5, 1979 information for April 3, 1979, Canadian Coalition for Nuclear Responsibility Re: The Harrisburg Nuclear Accident Could Happen Here.

E-21 Nuclear Safety or Nuclear Unsafety? July 5, 1979 — The Limits to Prediction and Control. Outline for presentation of Dr. Gordon Edwards. -D/6-

Title Date Tabled

Introductory Statement to July 6, 1979 Select Committee on Ontario Hydro Affairs, by Jon. H.F. Jennekens, President, Atomic Energy Control Board, (AECB), Ottawa, July 6, 1979. £-23 Atomic Energy Control Board — July 6, 1979 Annual Report 1977-78. E-2» Basis for Limiting Exposure to July 9, 1979 Ionizing Radiation. Presented to The Select Committee on Ontario Hydro, Toronto, July 6,1979, by w.R. Bush, Manager, Radiation Protection Division, Atomic Energy Control Board.

E-25 Memorandum dated December 5, 1978, July 9, 1979 from W.R. Bush, to J.H. Jennekens, Re: New Environmental Radiation Protection Standards for Nuclear Power Operations in the U.S.A. (25 mrem) E-26 Published Estimates of Health July 9, 1979 Risks from Coal and from Nuclear Energy (data cited from Newcombe, 1977 and Myers & Newcombe 1978). E-26A Curriculum Vitae—Howard B. July 9, 1979 Newcombe. E-26B Curriculum Vitae—David K. Myers. July 9, 1979 E-27 Letter dated June 28, 1979 to July 10, 1979 the Clerk of the Legislature, from D.B. Kelly, Deputy City Clerk, City of Sarnia, Re: Atomic Energy Control Board — Recent Accidents at Douglas Point Nuclear Station.

E-28 Testimony before The Select July 10, 1979 Committee on Ontario Hydro Affairs, July 10, 1979, by Edward P.Radford, M.E., Professor of Environmental Epidemiology, Graduate School of Public Health, University of Pittsburgh. -D/7-

Exhibitf Title . Date Tabled

E-29 A Reassessment of the Health July 10, 1979 Hazards of Low-Level Ionizing Radiation: The Limiting Factor in the Nuclear Power Cycle, by Irwin D.J. Brass, PhD, Director of Biostatistics, Rosweli Park Memorial Institute, Buffalo, New York. E-30 Review of Dr. Irwin Bross1 July 11, 1979 Presentation on Radiation Exposure and Cancer Risk, Kenneth J. Rathman, April 7, 1978. E-31 Presentation to The Select July 11, 1979 Committee of the Ontario Legislature on Safety and Nuclear Power by Ontario Hydro. E-32 Submission of the Renfrew County July 13, 1979 Citizens for Nuclear Responsibility on the Nuclear Power Demonstration Generating Station at Roiphton on the Ottawa River in the County of Renfrew.

E-33 Magazine article. "Low Level July 13, 1979 Radiation: A High-Level Concern". E-34 "Risk Assessment Review Group July 13, 1979 Report to the Nuclear Regulatory Commission". Prepared for U.S. Nuclear Regulatory Commission. E-35 Press release from A.E.C.B. Dated July 13, 1979 June 1, 1979, Re: Statement on Application for Hearing re: N.P.D. Nuclear Generating Station. E-36 Presentation by Ontario Hydro July 13, 1979 and A.E.C.L. to the Select Committee on Hydro Affairs regarding the NPD (Nuclear Power Demonstration) Nuclear Generating Station, July 13, 1979 E-37 I3W - CV2 Valve Failure at NPD July 13, 1979 E-38 Introductory remarks, by Dr. W. July 17, 1979 Paskievici before The Select Committee on Ontario Hydro Affairs. -D/8-

Title Date Tabled Report of the Interagency Task July 17, 1979 Force on the Health Effects of Ionizing Radiation, June 1979. E-39A Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Report of the Work Group on Science, June 1979. F.-39B Interagency Task Force on Health July 17, 1979 Effects of Ionizing Radiation: Report of the Work-Group on Records and Privacy, June 1979.

E-39C Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Report of the Work Group on Care and Benefits, June 1979. E-39D Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Report of the Work Group on Exposure Reduction, June 1979. E-39E Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Report of the Work Group on Public Information, June 1979. E-39F Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Report of Institutional Arrangements, June 1979. E-39G Interagency Task Force on the July 17, 1979 Health Effects of Ionizing Radiation: Public comments on the Work Group Reports, June 1979.

E-40 Briefs presented to Committee at July 17, 1979 Rolphton. Meeting, July 12, 1979. E-»l Petition: We, the undersigned July 17, 1979 living in the immediate vicinity of the Nuclear Power Demonstration (N.P.D.), wish to record our confidence in the overall operation. For seventeen years it has made a major contribution to both our electrical supply and training of staff: it has done so with no injury to any member of the public. -D/9- Exhibitf Title Date Tabled E-42 Cancer and low level ionizing July 17, 1979 radiation. Karl Z. Morgan. The Bulletin, 1973. E-*3 Memo to Select Committee on July 17, 1979 Hydro Affairs from D.K. Myers, Head, Biology Branch, Chalk River Nuclear Laboratories, July 11, 1979. E-44 Abstract Discussions of early July 17, 1979 safety considerations E-45 Transparencies (copies) re: July 17, 1979 ' presentation by Dr. Snell, AECL. E-*6 International Atomic Energy Agency July 17, 1979 Safety Standards. E-47 Safety of CANDU Nuclear Power July 17, 1979 Stations by V.G. Snell. E-*8 CANDU Reactor Safety Design July 17, 1979 Proceedings of a symposium. Canadian Nuclear Association. November 1978. E-49 Nuclear Reactor Philosophy and July 18, 1979 Criteria presented on July 18, 1979 to the Select Committee on Ontario Hydro Affairs Summer Schedule on the Safety of Nuclear Reactors, Session 3, July 17-19, 1979. AECB Participant - R.J. Atchison, Director, Assessment Branch, Atomic Energy Control Board

E-50 Letter from the Public Interest July 19, 1979 Advocacy Centre, dated July 17, 1979 to Donald MacDonald, M.P.P., Chairman, Select Committee on Hydro Affairs Re: Derived Release Limits for NPO Reactor.

E-51 Letter dated June 5, 1979 from July 23, 1979 J.F.D. Vtaclsaac, Q.C., Director of Legal Services, Atomic Energy Control Board to N.J. Schultz, Counsel for the Renfrew County Citizens for Nuclear Responsibility Re: question of disclosure of information respecting atomic energy. -D-10-

Exhibit» Title Date Tabled

E-51-A Letter dated July 20, 1979 from July 23, 1979 N.J. Schultz, Counsel for the Renfrew County Citizens for Nuclear Responsibility to Z. Domaratzki, Director, Reactor and Accelerator Branch, Atomic Energy Control : Board Re: fUe 21-5-10. % E-51-B Letter dated July 20, 1979 from July 23, 1979 N.J. Schultz, Counsel for the . : Renfrew County Citizens for Nuclear Responsibility to Donald MacOonald, : M.P.P., Chairman, Select Committee ./:__ : r : on Ontario Hydro Affairs, re: ~ . --:- - -; : : NPD Reactor. "^ E-52 CANOU Moderator Provides Ultimate July 23, 1979 Heat Sink in a LOC A by J.T. Rogers. . .. _. . Paper Published in Nuclear Engineering International, January 1979. E-52-A Figures to accompany testimony August 15, 1979 of J.T. Rogers to Select Committee, July 23, 1979. E-53 No Significnt Fuel Failures (NSFF). July 2», 1979 Presented to the Ontario Select Committee on Hydro Affairs by ,. Z. Domaratzki, Atomic Energy Control Board. E-54 Brief by Ronald S. Davis, July 2*, 197? Deep River, Ontario. E-54-A Letter dated July 30, 1979 from August 7, 1979 Ronald S. Davis to Donald MacDonald, M.P.P., Chairman, Select Committee on Hydro Affairs, Re: Responses to Mr. Schultz's comment of July 25, 1979.

E-55 Letter dated July 18, 1979 to July 2*, 1979 Select Committee on Hydro Affairs from Henry V. Brown, Mayor, City of Pembroke. -D/n-

Exhibitf Title Date Tabled E-56 Canadian Nuclear Association, July 25, 1979 Nineteenth Annual International Conference, Toronto, Canada, June 10-13, 1979 - President's Address, CNA Committee Reports. E-56-A ^Canadian Nuclear Association, July 25, 1979 Nineteenth Annual International Conference, Toronto, Canada, June 10-13, 1979- Proceedings. E-57 Radiation Protection Training, July 25, 1979 Health and Safety Division, Ontario Hydro, 481.1 Course 3 Revised 1978. E-58 Radiation Protection Training, July 25, 1979 Health and Safety Division, Ontario Hydro, 481.2 Revised 1978. E-59 Rasmussen's Numbers Game, Taken from July 25, 1979 Nuclear Power - The Unviabie Option by John J. Berger. Pages 58-59 Inc. E-59-A Program Outline, Energy Pathways July 25, 1979 Policy Research Group. E-59-B Program and Policy Outline on July 25, 1979 Nuclear Waste Management in Canada, Energy Pathways, Killaloe, Ontario. E-60 Risk Assessment and Public July 25, 1979 Confidence. An outline of testimony by Dr. Gordon Edwards to the Select Committee on Ontario Hydro Affairs, July 25, 1979.

E-60-A Curriculum Vitae. Dr. Gordon Edwards. July 25, 1979 E-60-B Excerpts from the testimony of July 25, 1979 Mr. Liberty Pease, Manager, Safety Analysis Division, Power Projects (AECL), to the Porter Commission (July 12-13, 1977)

E-60-C Nuclear Fuel Melting as seen by July 25, 1979 The Rasmussen Report (WASH- 1400) with some additional comments re the CANDU Reactor. -D/12-

Title Date Tabled

Excerpts from the book "The Accident . July 25, 1979 Hazard of Nuclear Power Plants" by Richard E. Webb, University of Massachusetts Press, 1976.

E-60-E Untersuchungen Zum Vergieich July 25, 1979 Grosstmoglicher Storfallfolgen In Einer Wiederaufarbeitungsanlage Und In Einem Kernkraftwerk Or. 0. Bachner, D. Holm, A. Meltzer, G. Morlock, Dr. P. NeuBer und Or. H. Urbahn

E-60-F Letter from the Comptroller General July 25, 1979 of the United States to the Honourable Mike Gravel, United States Senate.

E-60-G Letter from R.W. Blackburn, Atomic July 25, 1979 Energy Control Board dated May 11, 1979 to Dr. Gordon Edwards.

E-60-H Unedited Transcript of Testimony July 25, 1979 of Or. William Bryan before Sub- committee on State Energy Policy, Committee on Planning, Land Use and Energy - California State Assembly - Hon. Charles Warren, Subcommittee Chairman, February 1, 197».

E-60-I Health Physics, Volume 33, No.3 July 25, 1979 September 1977. E-60-J Conference on Faith, Science, and July 25, 1979 the Future. July 12-2*, 1979, Cambridge, Massachusetts. Document/123. E-61 Week 3 - Design July 26, 1979 1. Derivation of Design Basis Release Limits 2. Def ence-in-Depth Approach (Ontario Hydro).

E-62 Week * - Licensing July 26, 1979 (Ontario Hydro).

E-62-A Condition: Normal Operation August 7, 1979 Fuel. Cooling: PHT Coolant Circulation. -D/13-

Exhibitf Title Date Tabled E-63 The Need for a Cost-Benefit July 26, 1979 Perspective in Nuclear Regulatory Policy by Edward P. O'Donnell, Chief Nuclear Licensing Engineer, Ebasco Services Incorporated. Operation of Nuclear Stations July 31, 1979 prepared by Ontario Hydro.

E-65 Letter dated July 25, 1979 from July 31, 1979 R.W. Blackburn, A.E.C.B. to W.E. Raney, Q.C., Secretary and General Counsel, Ontario Hydro re: certain documents requested by Select Committee.

E-66 Letter dated July 31, 1979 from July 31, 1979 Tilley, Carson & Findlay to AJan M. Schwartz re: Select Committee on Hydro Affairs Request for Correspondence. E-67 Pickering G.S.A., LOCA Reanalysis July 31, 1979 Correspondence. E-6S Preliminary Evaluation of the July 31, 1979 Safety Features of Pickering N.G.S. - "A" Relative to the Three Mile Island Accident. E-6S-A Preliminary Evaluation of the July 31, 1979 Safety Features of Pickering G.S. "B" Relative to the Three Mile Island Accident.

E-6S-B Preliminary Evaluation of the July 31, 1979 Safety Features of Bruce N.G.S "A" Relative to the Three Mile Island Accident.'

E-6S-C Preliminary Evaluation of the July 31, 1979 Safety Features of Bruce N.G.S "B" Relative to the Three Mile Island Accident.

E-6S-D Atomic Energy of Canada Limited, July 31, 1979 Engineering Company, Sheridan Park, Mississauga, Preliminary Evaluation of the Safety Features of Douglas Point G.S. Relative to the Three Mile Island Accident 1979 April 12. Eahibittf Tttle Date Tabled E-68-E Preliminary Evaluation of the July 31, 1979 Safety Features of N.P.O. Relative to the Three Mile Island Accident.

E-68-F News Release: Atomic Energy Control July 31, 1979 Board May 23, 1979. A.E.C.B. Completes Preliminary Staff Assessment of CANDU Design Review Relative to U.S. Nuclear Reactor Accident.

E-69 Opening Statement by Mr. L.G. July 31, 1979 McConnell, July 31, 1979. E-70 Statement to the Select Committee August 1, 1979 on Ontario Hydro Affairs by Gordon Edwards, Chairman of the Canadian Coalition for Nuclear responsibility

E-70-A Quotations about Nuclear Energy. August 1, 1979 E-70-B Nuclear Power: The Canadian Issues. August 1, 1979 A Submission from Atomic Energy of Canada Limited to the Royal Commission on Electric Power Planning in response to the Commission's Issue paper No.l "Nuclear Power in Ontario".

E-70-C Correspondence between Alastair. August 1, 1979 Gillespie and Gordon Edwards on the subject of CANDU Nuclear Safety, April 1979. E-70-D Excerpt from WASH-1*00, Appendix VII, August 1, 1979 Pages 6 & 7. E-70-E Canadian Coalition for Nuclear August 1, 1979 Responsibility. Excerpt from the Burns Report (New Zealand) March 1977. E-70-F Investigations to Compare Maximum August 1, 1979 Possible Consequences of Accidents in a Reprocessing Plant and in a Nuclear Power Plant. An English precis by G. Edwards of the German Study entitled Untersuchungen Zum Vergleich Grosstmoglicher Storfalifolgen In Einer Wiederaufarbeitungsanlage Und In Einem Kernkraf twerk by Dr. D. Bachner, D. Holm, A. Meltzer, G. Morlock, Dr. P. Neusser, and Dr. H. Urbahn, of the Institute for Reactor Safety, Federal Republic of Germany - August 1976. -D/15-

Exhibit f Title Date Tabled

E-70-G "Three Mile Island - Four Months August 1, 1979 Later". Item from Business Week, July 30, 1979. E-70-H Figure 10: A destructive nuclear August 1, 1979 runaway (power excursion) test conducted in 1954 of a small nuclear reactor.

E-70-I Text of anonymous letter on the August 1, 1979 Rolphton Plant received by M. Bein. E-70-J World Council of Churches, Conference August 1, 1979 on Faith, Science, and the Future July 12-24,1979. Resolution on Disarmament. E-70-K Canadian Coalition for Nuclear August 1, 1979 Responsibility. Radiation Exposures to Cargo Handlers at Dorval Airport. E-70-L Exchange of Correspondence between August 1, 1979 an Ottawa Doctor and The Atomic Energy Control Board - Re: Inadequate Containment of Low Level Radioactive Waste near an Ottawa Suburban Community - April 1977.

E-70-M Radiation and Man. August 1, 1979 E-71 Letter dated June 15,1979 from August 2, 1979 T.J. Molloy, Manager, Power Reactor Division, Atomic Energy Control Board to L.W. Woodhead, Director, Nuclear Generation Division, Ontario Hydro Re: Safety System Availability at Operating Stations.

E-72 Letter dated July 31, 1979 from August 2, 1979 L.W. Woodhead, Director of Nuclear Generation, Ontario Hydro to T.J. Molloy, Manager, Power Reactor Division, A.E.C.B. Operations Directorate Re: Safety System Availability at Operating Stations. -D/16-

Exhibit# Title Date Tabled E-73 Royal Commission on Electric Power August 2, 1979 Power Planning "Human Factors*in Power Plant Design, Operation, and Safety" by 3ohn W. Senders, Patrick 3. Foley, Consultants, September 1978. E-7» Letter to Alan Schwartz, Committee August 7, 1979 Counsel, from J.E. Wilson, Public - Hearings Department, Ontario Hydro Re: Ontario Hydro Mortality Studies.

E-75 Letter to Alan Schwartz, Committee August 7, 1979 Counsel, from J.E. Wilson, Public Hearings Department, Ontario Hydro Re: Questions Raised in Dr. Radford's Testimony in Regard to Tritium Releases and Their Effect on Female Oocytes.

E-76 Letter to Donald MacDonald, M.P.P., August 7, 1979 Chairman of the Select Committee on Ontario Hydro Affairs, from Nikol James Schultz, Counsel for the Renfrew County Citizens for Nuclear Responsibility, Re: Reactor Safety Inquiry. E-77 The process of Risk Assessment in August 7, 1979 National, Provincial and Local Policy Decisions on Nuclear Power, AECB-1127 Report prepared by Ian Burton and Anne Whyte, Institute for Environmental Studies, University of Toronto, November 25, 1977. E-77-A Environmental and Health Effects August 7, 1979 of Fossil Fuel and Nuclear Power Generation, by Syed 3. Naqvi, D. Bruce Black and Colin R. Phillips, Department of Chemical Engineering and Applied Chemistry, University of Toronto, Toronto, Ontario. E-77-B "An Approach for Determining August 7, 1979 the Acceptable Levels of Nuclear Risk" AECB-H30, Report Prepared for the Directorate of Research and Coordination, Atomic Energy Control Board by the Bureau of Management Consulting, AECB Project 34-0-2-0, BMC Project 3-199$, March 1978. -D/17-

Exhibiti Title Date Tabled E-77-C Evaluation of Report AEC8-11Ï9, August 7, 1979 Risk of Energy Production AECB- 1131, by Lemberg Consultants Ltd.

E-77-D Material Irradiation and Down August 7, 1979 Syndrome: A Study Based on Record Linkage. D.L. Gibson, S.H. Uh, and J.R. Miller, April 1978.

E-78 Population Doses and Health Con- August 7, 1979 sequences following a Nuclear Accident. Excerpts from WASH-1*00 -Appendix VI.

E-78-A An Epidemiological Evaluation of August 7, 1979 Health Effects in a General Population Residing in an Area Contaminated with Plutonium: A Preliminary Report by Carl J. Johnson, M.O., M.P.H.

E-78-B The Zirconium Connection by August 7, 1979 Daniel M. Pisello, 1979.

E-79 Operation of Nuclear Stations, August 7, 1979 Ontario Hydro.

E-80 Response of Ontario Hydro and August 7, 1979 Atomic Energy of Canada Limited, joint licensees, to the submissions of the Renfrew County Citizens for Nuclear Responsibility with respect to the safety of the Nuclear Power Demonstration Generating Station August 7, 1979.

E-81 AECB Compliance Procedures August 8, 1979 for Nuclear Power Plants by Z. Domaratzki, Atomic Energy Control Board, August 8, 1979.

E-82 Notes for Testimony of Ralph August 9, 1979 D. Torrie, August 9, 1979.

E-S2-A Referenced Version of Exhibit September 19, 1979 E-82 by Ralph Torrie.

E-82-B Letter dated August 16, 1979 from September 27, 1979 Ralph Torrie to James Fisher, Consultant, Select Committee on Ontario Hydro Affairs - Re: Pickering N.G.S. "A" ECCS unavailability. -D/1S-

Titlc Date Tabled • Letter dated August 3, 1979 from August 1», 1979 3.E. Wilson, Public Hearings Officer, to Alan M. Schwartz, Committee Counsel, Re: Clarification of statement cited by Or. Gordon Edwards. E-8* Declaration by Patrick D. O'Brien, August 1*, 1979 Re: Bruce G.S. "A". E-85 Review of Twelve Selected Abnormal August 14, 1979 Event Reports, August 14, 1979. E-86 "1 was the only victim of Three- August 15, 1979 Mile Island" by Dr. Edward Teller. E-87 Closing statement to the Select August 15, 1979 Committee of the Ontario Legislature on Ontario Hydro Affairs by J.H.F. Jennekens. President, Atomic Energy Control Board, Ottawa, Canada. August 15, 1979. E-88 Nuclear Power Reactor Safety August 15, 1979 in Illinois. A Report to the Honourable James Thomson, Governor of the State of Illinois. By the Ad-Hoc Nuclear Power Reactor Safety Review Committee, Illinois Commission on Atomic Energy. July 1979.

E-S9 Press Release dated September September 18, 1979 18, 1979 from Ontario Hydro: "NPD Repairs Completed". E-90 The Legislative Assembly of Ontario September 18, 1979 "Reply Submissions of the Renfrew County Citizens for Nuclear responsibility with Respect to the Safety of the Nuclear Power Demonstration Generating Station at Rolphton on the Ottawa River in the County of Renfrew", dated August 21,1979.

E-90-A "Short Summary of the Position September 18, 1979 of the Renfrew County Citizens for Nuclear Responsibility.11 -D/19-

Exhibit* Title Date Tabled

E-91 "Coming to Some Conclusions September 18, 1979 on Nuclear Safety". Schedule for Last Three Weeks on the Summer Hearings of the Select Committee on Hydro Affairs, September 18, 1979. E-92 Letter dated August 20, 1979 September 19, 1979 to Mr. Donald MacDonald, M.P.P., Chairman, Select Committee on Hydro Affairs, from Hugh L. Macaulay, Chairman of the Board, Ontario Hydro, re: Globe and Mail article on interview with Jon Jennekens, President A.E.C.L.

E-93 The Perils of Probabilities Energy September 19, 1979 Probe's response to AECB-1149, "Proposed Safety Requirements for Licensing of CANDU Nuclear Power Plants" (IOWG Report). A brief to the Atomic Energy Control Board by Norman Rubin, September 1979.

E-94 A.E.C.L. Description of Dispersion September 19, 1979 of Radioactive Emissions from N.P.D. presented by Mr. Blackstein, September 19, 1979.

E-95 Report - Nuclear Safety in September 19, 1979 Perspective, E.S. Siddall, Canatom, Canada. E-96 Ontario Hydro Appearance, September September 19, 1979 19, 1979, Nuclear Power Demonstration Reactor. E-97 Ontario Hydro/A.E.C.L., Position September 19, 1979 on N.P.D.G.S. with respect to Select Committee on Hydro Affairs. E-98 Letter dated September 25, 1979 September 25, 1979 from J. E. Wilson, P.Eng., Public Hearings Officer, Public Hearings Department, Ontario Hydro, to Alan Schwartz, Committee Counsel, re: information promised by Mr. R. Wilson before Select Committee on July 11, 1979. -D/2Q-

Exhibitf Title Date Tabled

E-99 Table 1, Sample of Accident Analysis September 25, 1979 Results, Comparisons of Pickering and Bruce. E-100 Cosmetic Solutions are Not Enough, September 26, 1979 G. Edwards, September 26, 1979.

E-100-A Energy Policy and Public Acceptance September 26, 1979 Lecture given at the IAEA Conference in Saltzburg, Austria, May 9, 1977 by Hannes Alf ven, Nobel Laureate in Physics, 1979.

E-100-B "What is Radiation?" Ontario Hydro. September 26, 1979 E-100-C C.C.N.R. Transitions, Reprinted, 1979. September 26, 1979 E-100-D Estimating Lung Cancers or "It's September 26, 1979 Perfectly Safe, But Don't Breathe Too Deeply" A summary of testimony presented by Gordon Edwards to the Elliott Lake Environmental Assessment Board dealing with the problem of radon gas in buildings, March 197S. (see Exhibit E-20-8, Tabled, July 5, 1979)

E-100-E "Step out of the Nuclear Shadow", September 26, 1979 C.C.N.R. Newsletter, September- October, 1979. C.C.N.R. Transi- tions.

E-101 CANDU Reactor Safety Research September 27, 1979 Program, Atomic Energy of Canada Ltd. Whiteshell Nuclear Research Establishment, Pinawa, Manitoba.

E-102 "Rating the Risks" by Paul Slovic, September 27, 1979 Buruch Fischhof f and Sarah Lichtenstein

E-103 Letter dated May 17,1979 (with October 2, 1979 attachments) from Roger J. Mattson, Director, Division of Systems Safety Office of Nuclear Reactor Regulations United States Nuclear Regulatory Commission, Washington, D.C. to Evelyn Gigantes, M.P.P. Re: "Post-Accident Hydrogen Production in Nuclear Power Plants". -D/21-

Exhibitg Title Date Tahled

E-10* Renewable Energy in Developing October 2, 1979 • Countries - An Overview by Ralph Torrie and Miles Goldstick, March 1979. E-105 Browns Ferry - The Regulatory October 2, 1979 Failure -Daniel F. Ford, Henry E. Kendall, Lawrence S. Tye, Union of Concerned Scientists, Cambridge, Mass. June 10, 1976. E-106 United States of America Before September 27, 1979 the Nuclear Regulatory Commission - Union of Concerned Scientists' Petition for Emergency and Remedial Action. E-107 Submission to the Select Committee September 26, 1979 on Ontario Hydro Affairs by the Federation of Engineering and Scientific Associations (FESA), September 26, 1979. E-10S Letter dated September 25, 1979 September 27, 1979 from Z. Domaratzki, Director, Reactor and Accelerator Branch, Atomic Energy Control Board to Mr. A. Schwartz, Committee Counsel Re: Mr. Domaratzki's response to actions placed on him at previous appearances before the Committee. E-109 Ontario Hydro Summary Statement October 2, 1979 -Select Committee on Hydro Affairs Reactor Safety Hearings, October 2, 1979. E-110 Scintillating Staff Summary on October 3,1979 Safety of Ontario's Nuclear Reactors. E-Ul The Need f or Electrical Capacity October 2*, 1979 -Review and update of material presented to Committee January to March, 1979 -Select Committee on Ontario Hydro Affairs, October 1979. Now listed as D-105 -D/22-

Title Date Tabled

Notes on the Kemeny Report - November 15, 1979 President's Commission on Three Mile Island.

E-112 Rough Draft Report - Select Committee November 15, 1979 on Ontario Hydro Affairs on its Examination of the Safety of Ontario's Nuclear Reactors, prepared by Alan Schwartz, Counsel and James Fisher, Consultant.

E-113 Letter dated November 5, 1979 November 15, 1979 from M.P. Martin, Media Relations Coordinator, Atomic Energy Canada Ltd., to Alan M. Schwartz, Committee Counsel, Select Committee on Ontario Hydro Affairs Re: documentation concerning; "copies of all correspondence between AECL-AECB —Ontario Hydro with respect to NSFF/LOCA/ECC Studies and Reports relating to design power ratings for the Douglas Point and Rolphton reactors".

E-11» Letter dated November 7, 1979 November 15, 1979 from Canadian Coalition for Nuclear Responsibility to Donald C. MacDonald, Chairman, Select Committee on Ontario Hydro Affairs Re: "Cases of Misinformation and Attempted Suppression by Canadian nuclear Institutions and Representatives."

E-U5 Letter to Donald C. MacDonald, November 20, 1979 Chairman from Norman Rubin, Nuclear Power Researcher outlining two statements regarding IOWG in the Rough Draft Report (E-112) which Mr. Rubin contends are wrong. The two points underlined in the letter are: 1. "Release limits are set for the most improbable accidents (our category 3 above)." and, 2. Release limits for normal operation and for accidents that correspond to the reference single and dual accidents are lowered. -D/23-

Exhibit# Title Date Tabled E-116 Letter to Mr. L.W. woodhead, November 20, 1979 Director of the Nuclear Generation Division of Ontario Hydro, from Mr. T.J. Molloy, Manager, Power Reactor Operational Division of the Atomic Energy Control Board (Ottawa); which outlines their approval of Ontario Hydro improving the availability of safety systems at the operating nuclear stations.

E-U7 Carbon 14 January 8, 1980 Candu - PHW Generating Stations T.R. Clarke Radioactivity Management and Environmental Protection Department. October 1979. E-11S Carbon 14 Control January 8, 1980 A Presentation to Staff of the Atomic Energy Control Board, November 19, 1979. G.A. Vivian, Nuclear Materials Management Department, Design, and Development Division, Ontario Hydro. E-119 Health Physics Aspects of Carbon-14 January 8, 1980 Dr. K. Y. Wong. Safety Services Department, Health and Safety Division, Ontario Hydro. November 1979. E-120 Letter to Mr. S. Conway, M.P.P. January 29, 1980 from Jacques Rubacha, Petawawa, Ontario regarding the NPD reactor. E-121 Letter from The Public Interest February 12, 1980 Advocacy Centre dated February 8, 1980 concerning the NPD generating station and defining the Public Interest Advocacy Centre's position. (Tabled originally as F-55) E-122 Presentation by Ontario Hydro to the February 12, 1980 Select Committee on Ontario Hydro Affairs on deposits of NPD NGS boiler tubes by Ontario Hydro, dated February 12, 1980. (Tabled originally as F-56) -D/2*-

Title Date Tabled

Presentation to The Select Committee February 12, 1980 of the Ontario Legislature on NPD Injection Water System and Containment System Modifications by Ontario Hydro/AECL February 1930. (Tabled originally as F-S7)

E-12* Douglas Point Station Data. February 13, 1980 (Tabled originally as F-58). E-125 Presentation to the Select Committee February 13, 1980 on Ontario Hydro Affairs by Atomic Energy of Canada Limited entitled "Emergency Coolant Injection System at Douglas Point (A review of the background to the correspondence between AECL-AECB-Ontario Hydro)" presented February 13,1980. (Tabled originally as F-59).

E-126 Letter addressed to Mr. 3. Fisher February 14, 1980 from J.E. Wilson of Ontario Hydro, the enclosure of which is a copy of a chronology of correspondence between T.G. Molloy (AECB) and L.W. Woodhead (Ontario Hydro). (Tabled originally as F-61).

E-127 Ontario Hydro response to letter from February If, 1980 Mr. R. Torrie to the Select Committee dated August 16, 1979 regarding Pickering NGS "A1* ECCS. Unavailability. (Tabled originally as F-62). E-128 "Environmental Effects: Scenarios of February 19, 1980 C-14 Releases from the World Nuclear Power Industry from 1975 to 2020 and the Estimated Radiological Impact", from the September- October, 1978 edition of Nuclear Safety. (Tabled originally as F-63).

E-129 "Nuclear Power Stations as Sources of February 19, 1980 Carbon-14 Discharge", translation from a Russian article from the Institute of Biophysics of the Ministry of Health of the USSR in Moscow by V.P. Rublevsky, A.D. Zykova and A.D. Turkin. (Tabled originally as F-6*) -D/25-

Exhibit# Title Date Tabled

E-130 Presentation by Mr. Kelly to the • February 20, 1980 Select Committee of the Ontario Legislature on AECB/Ontario Hydro correspondence regarding Safety System Availability at Operating Stations, dated February 1980. E-131 Letter to Mr. Domaratzki dated February 20, 1980 November 7, 1979 and signed by D.A. Watson, Manager of Safety Services Department, Ontario Hydro regarding Carbon 1ft.

E-131-A Information Summary on Carbon February 20, 1980 14 Studies at Ontario Hydro. E-131-B Carbon 14 Control February 20, 1980 A Presentation to Staff of the Atomic Energy Control Board, November 19, 1979. G.A. Vivian, Nuclear Materials Management Department Design, Development Division. Ontario Hydro. (Also tabled as E-118)

E-131-C Health Physics Aspects of Carbon 14 February 20, 1980 Dr. K. Y.Wong Safety Services Department Health and Safety Division Ontario Hydro November 1979 (Also tabled as E-119) E-131-D Carbon 14 February 20, 1980 Candu - PHW Generating Stations T.R. Clarke Radioactivity Management and Environmental Protection Department, October 1979. (Also tabled as E-117) E-132 Information Summary on Carbon February 20, 1980 14 Studies at Ontario Hydro. (Also tabled as E-131-A) -D/26-

Exhibitf Title Date Tabled E-133 Bruce 'A' Boilers, presentation February 21, 1980 on February 21,1930 to The Select Committee on Ontario Hydro Affairs prepared by RJ. Atchison, Director of Assessment Branch and B. Jarman, Assoc. Scientific Advisor, both of Atomic Energy Control Board. ,

E-13* . Memorandum from W .R. Bush February 21, 1980 to R.J. Atchison, entitled, 'Carbon 1* Information for Select Committee', dated February 18,1980. E-135 Document entitled 'Transportation February 21, 1980 Incidents Involving Canadian Shipments of Radioactive Material, 1947 to 1978", by 3M. Jardine. E-136 Document entitled "Atomic Energy February 21, 1980 Control Board Radioactive Material Transport", by Michael C. White, dated October 1, 1979.

E-137 Presentation to Select Committee February 26, 1980 of the Ontario Legislature on Ontario Hydro. Engineering Studies for Carbon 14 Control, February 26, 1980. E-138 Presentation to the Select Committee February 26, 1980 of the Ontario Legislature on Carbon 14. Production and Releases from Ontario Hydro Reactors, dated February 16, 1980. E-138-A Carbon 14 Distribution after Injection February 26, 1980 into the Tropospere. E-138-B Four Compartment Models for February 26, 1980 Distribution of Carbon 14. E-139 Document entitled Transportation February 26, 1980 of radioactive materials. E-140 A list of people on the panel. February 27, 1980 On the letterhead of the CNA, Canadian Nuclear Association Delegation to the Ontario Select Committee, dated February 27, 1980. -D/27-

Exhibitf Title Date Tabled

E-1W-A Document on the Canadian Nuclear February 27, 1980 Association letterhead, entitled "Introductory Remarks to Ontario Select Committee Hearing, dated February 27, 1980", by William MacOwan, Chairman of the CNA. E-1W-B Hard-cover series of the slides *" February 27, 1980 which were seen later in the morning. The first page has a slide entitled Electrical Energy in Ontario - - Ontario Imports Approximately 80 Per Cent of Its Energy Requirements, Mostly as Fossil Fuels. E-141 A letter dated February 29, 1980 March 13, 1980 and addressed to, Jim Fisher, Consultant to the Select Committee on Ontario Hydro Affairs from 3.E. Wilson, Manager, Public Hearings Department, Ontario Hydro with attachments including a Memorandum to Mr. G.R. Chiiderhose, Manager, RMEP the subject of which is entitled NPD NGS -IJW Valve Cycling, dated February 27, 1980. E-l*2 A letter dated March 12, 1980 March 13, 1980 and addressed to, Jim Fisher, Consultant to the Select Committee on Ontario Hydro Affairs from 3.E. Wilson, Manager, Public Hearings Department, Ontario Hydro the letter is entitled "Additional Information on Carbon 14" documents attached to the letter are entitled: 1. "The Carbon Content of Food Crops and Consideration of the Biological Effects of the Transmutation on Carbon 1* and Tritium" - written by D.K. Myers of the Chalk River lab. 2. "Radionuclide metabolism and dosimetry". -D/28-

Exhibitf Title Date Tabled E-1*3 Comments from Dr.. Gordon Edwards April 10, 1980 dated March 19,1980 entitled "Ontario Legislature Investigates . Nuclear Safety". A response to the Select Committee on Ontario Hydro Affairs' Interim Report entitled "The Safety of Ontario's Nuclear Reactors'". E-144 Comments by the Atomic Energy April 10, 1980 Control Board Staff on the December, 1979, Interim Report of the Ontario Select Committee on Ontario Hydro Affairs on "The Safety of Ontario's Nuclear Reactors", received under covering letter from R.W. Blackburn, Secretary to The Atomic Energy Control Board dated February 27, 1980 and directed to Mr. Donald C. MacDonald, Chairman, Select Committee on Ontario Hydro Affairs.

E-l*5 Letter addressed to Mr. J.D. Fisher, April 10, 1980 Canada Consulting Group on April 8, 1980, from Mr. J.E. Wilson, Manager, Public Hearings, Ontario Hydro, the subject of which is headlined as "Airborne Radionudides". Three attachments to this letter are entitled: 1) Table 1: Airborne Releases from Pickering NGS- 1978. 2) Table 2: Typical Ranges of Noble Gas Composit- ion Measured in Pickering NGS Stack Effluent. 3) Table 3: Airborne Radionuclides E-146 Staff Summary for Select Committee April 10, 1980 on Ontario Hydro Affairs entitled "Reaching Final Conclusions on the Safety of Ontario's Nuclear Reactors" dated April 10, 1980. APPENDIX E INFORMATION PROVIDED BY ONTARIO HYDRO TO THE LEGISLATIVE LIBRARY FOR THE PUKPOSES OF, AND USE BY, THE PUBLIC AND THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS (436 Volumes) APPENDIX E INFORMATION PROVIDED BY ONTARIO HYDRO TO THE LEGISLATIVE LIBRARY FOR THE PURPOSES OF, AND USE BY, THE PUBLIC AND THE SELECT COMITTEE ON ONTARIO HYDRO AFFAIRS

(436 Volumes)

UNRESTRICTED ACCESS Documents provided to Select Committee members, staff, Party research offices and the Hydro Public Reference Centre, Friday June 8 and Monday June 11,1979. Vol. 1 Applications to Operate (Bruce Unit 4, Pickering Unit 1, Douglas Point and NPD). Operating Licences (Bruce, Pickering, Douglas Point and NPD). Bruce "A" Operating Policies and Principles. Vol. 2 Sample of Significant Abnormal Event Reports. Vol. 3 4th Quarter 1978 Quarterly Technical Reports (Bruce, Pickering and Douglas Point) and the 1978 Annual Report for NPD.

Documents provided to the Select Committee office and to the Hydro Public Reference Centre Wednesday, June 13,1979.

Vol. 4 Bruce N.G.S. "A" Application to Operate Units 1 to 4.

Vol. 5 Pickering N.G.S. "A" Application to Operate, Units 1 to 4.

Vol. 6 Douglas Point N.G.S. Application to Operate.

Vol. 7 NPD G.S. Application to Operate.

Vol. 8 Bruce N.G.S. "A" Application Policies and Principles and Radiation Protection Procedures.

Vol. 9 Pickering N.G.S. "A" Operating Policies and Procedures.

t Vol. 10 Douglas Point N.G.S. Operating Policies and Principles and Radiation Protection Procedures.

Vol. 11 NPD G.S. Operating Policies and Principles and Radiation Protection Procedures. Vok 12 Bruce N.G.S. "A" Quarterly Technical Reports 3rd Qtr. 1976 to »th Qtr. 1977. -E/2-

Vol. 13 Bruce N.G.S. "A" Quarterly Technical Reports 1st Qtr. 1978 to 4th Qtr. 1978. Vol. 14 Pickering N.G.S. "A" Quarterly Technical Reports 1971 to 4th Qtr. 1973. Vol. 15 Pickering N.G.S. "A" Quarterly Technical Reports 1st Qtr. 197» to 4th Qtr. 1975. Vol. 16 Pickering N.G.S. "A" Quarterly Technical Reports 1st Qtr. 1976 to 4th Qtr. 1977. Vol. 17 Pickering N.G.S. "A" Quarterly Technical Reports 1st Qtr. 1978 to 4th Qtr. 1978. Vol. 18 Douglas Point N.G.S. "A" Annual Technical Reports 1969 to 1973. Vol. 19 Douglas Point N.G.S. 1974 Quarterly Technical Reports. Vol. 20 Douglas Point N.G.S. 1975 Quarterly Technical Reports. Vol. 21 Douglas Point N.G.S. 1976 Quarterly Technical Reports. Vol. 22 Douglas Point N.G.S. 1977 Quarterly Technical Reports. Vol. 23 Douglas Point N.G.S. 1978 Quarterly Technical Reports. Vol. 24 NPD G.S. Annual Reports 1962-1969. Vol. 25 NPD G.S. Annual Reports 1970-1978. Vol. 26 Bruce Abnormal Events Reports to the AECB Vol. 27 Design and Development Report List. Health Physics Report List. Nuclear Generation Division Index Vol. 1. Vol. 28 Nuclear Generation Division Index Vol. 2. Nuclear Generation Division Index Vol. 3.

Documents provided to the Select Committee office and to the Hydro Public Reference Centre on June 18,1979. Vol. 29 Health Physics Investigation Reports of Excess Doses. Vol. 29A Sample of Lifetime Occupational Dose Report records. -E/3-

Documents provided June 28,1979 to the Legislative Library and to the Hydro Public Reference Centre. Vol. 30 Douglas Point N.G.S. Monthly Technical Reports 1963 and 1964. Vol. 31 Douglas Point N.G.S. Monthly Technical Reports 1965 and 1966. Vol. 32 Douglas Point N.G.S. Monthly Technical Reports 1967 and 1968. Vol. 33 Douglas Point N.G.S. Monthly Technical Reports 1969. Vol. 34 Douglas Point N.G.S. Monthly Technical Reports 1970. Vol. 35 Douglas Point N.G.S. Monthly Technical Reports 1971. Vol. 36 Douglas Point N.G.S. Monthly Technical Reports 1972. Vol. 37 Douglas Point N.G.S. Monthly Technical Reports 1973 to 1979. Vol. 38 NPD G.S. Monthly Technical Reports 1960. Vol. 39 NPD G.S. Monthly Technical Reports 1961. (January to June) Vol.40 NPD G.S. Monthly Technical Reports 1961. (July to December) Vol. 41 NPD G.S. Monthly Technical Reports 1?S2. Vol. 42 NPD G.S. Monthly Technical Reports 1963 and 1964. Vol. 43 NPD G.S. Monthly Technical Reports 1965 and 1966. Vol. 44 NPD G.S. Monthly Technical Reports 1967 and 1968. Vol. 45 NPD G.S. Monthly Technical Reports 1969. Vol. 46 NPD G.S. Monthly Technical Reports 1970 and 1971. Vol. 47 NPD G.S. Monthly Technical Reports 1972 to 1979. Vol. 48 Bruce N.G.S. "A". 1974 SER 1 to 12. 1975 SER 1 to 27. Vol. 49 Bruce N.G.S. "A". 1976 SER 1 to 56. Vol. 50 Bruce N.G.S. "A". 1977 SER 1 to 30. -E/4-

Vol. 51 Bruce N.G.S. "A". 1977 SER 31 to 55. Vol. 52 Bruce N.G.S. "A". 1977 SER 56 to 9*. Vol. 53 Bruce N.G.S. "A". 1973 SER 1 to 50. Vol. 5* Bruce N.G.S. "A". 1978 SER 51 to 99. Vol. 55 Bruce N.G.S. "A". 1979 SER 1 to 54. Vol. 55A Bruce N.G.S. "A". Significant Event Reports, SER 55 to 64 inclusive, 66. Vol. 56 Bruce N.G.S. "A". Unusual Occurrence Reports, (UOR) 1976 to 1979. Vol. 57 Pickering N.G.S. "A". 1970 SER 1 to 15. 1971 SER 1 to 72. Vol. 58 Pickering N.G.S. "A". 1972 SER 1 to 97. Vol. 59 Pickering N.G.S. "A". 1973 SER 1 to 3 Vol. 60 Pickering N.G.S. "A". 1974 SER 1 to 141. Vol. 61 Pickering N.G.S. "A". 1975 SER 1 to 157. Vol. 62 Pickering N.G.S. "A". 1976 SER 1 to 184. Vol. 63 Pickering N.G.S. "A". 1977 SER 1 to 189. Vol. 64 Pickering N.G.S. "A". 1978 SER 1 to 248. Vol. 65 Pickering N.G.S. MA". 1979 SER 1 to 62. Vol. 65A Pickering N.G.S. "A" Significant Event Reports SER 63 to 69 inclusive, 74. Vol.66 PickeringN.G.S. "A" Unusual Occurrence Reports (UOR) 1971 to 1979. -E/5-

Vol. 67 Douglas Point N.G.S. 1968 and 1969 Significant Event Reports (SER). Vol. 68 Douglas Point N.G.S. 1970 and 1971 Significant Event Reports (SER). Vol. 69 Douglas Point N.G.S. 1972 to 1975 Significant Event Reports (SER). Vol. 70 Douglas Point N.G.S. 1976 to 1979 Significant Event Reports (SER). Vol. 71 Douglas Point N.G.S. Unusual Occurrence Reports (UOR) 1969 to Present. Vol. 72 NPD G.S. Unusual Occurrence Reports (UOR) 1961 to 1964. Vol. 73 NPD G.S. Unusual Occurrence Reports (UOR) 1965 to 1979. Vol. 7* NPD G.S. Significant Event Reports (SER) 1967 to 1971. VoL 75 NPD G.S. Significant Event Reports (SER) 1972 to 1975. Vol. 76 NPD G.S. Significant Event Reports (SER) 1976 to 1979. Vol.77 Bruce N.G.S. "A", Monthly Technical Reports October 1973 to December 197*. Vol. 78 Bruce N.G.S. "A", Monthly Technical Reports 1975. Vol. 79 Bruce N.G.S. "A", Monthly Technical Reports 1976 to 1979. Vol. 80 Pickering N.G.S. "A", Monthly Technical Reports. Vol. 31 Pickering N.G.S. "A", Monthly Technical Reports January 1971 to July 1971. Vol. 82 Pickering N.G.S. "A", Monthly Technical Reports August 1971 to December 1971. Vol. 83 Pickering N.G.S. "A", Monthly Technical Reports 1972. Vol. 84 Pickering N.G.S. "A", Monthly Technical Reports 1973 to 1979. Vol. 85 Bruce N.G.S. "A" Station Instructions. -E/6-

Vol. 86 Bruce N.G.5. "A" Station Instructions. Vol. 87 Bruce N.G.S. "A" Station Instructions.

Vol.88 Pickering N.G.S. "A" Station Instructions.

Vol.89 Douglas Point N.G.S. Station Instructions.

Vol.90 NPO G.S. Station Instructions.

Vol. 91 Nuclear Generation Division. Station Instructions.

Vol. 92 Nuclear Training Syllabus. Vol. 93 Pickerina N.G.S. "A". Production Unit Standards and Procedures Vol. 94A Bruce N.G.S. "A". Computer Summary of Deficiency Reports to Year End 1978.

Vol. 94B Bruce N.G.S. "A". Computer Summary of Deficiency Reports during 1979. Vol. 95A Pickering N.G.S. "A". Computer Summary of Deficiency Reports to Year End 1978. Vol. 95B Pickering N.G.S. "A". Computer Summary of Deficiency Reports during 1979. Vol. 96 Pickering N.G.S. "A". Jumper Records. Vol.97 Pickering N.G.S. "A". Jumper Records. Vol. 98 Pickering N.G.S. "A". Work and Test Permits. July 1978 - Unit 0, 012, 03*. Vol. 99 Pickering N.G.S. "A". Work and Test Permits. August 1978 - Unit 0, 012, 034. Vol. 100 Pickering N.G.S. "A". Work and Test Permits. September 1978 - Unit 0, 012, 034. -E/7-

Vol. 101 Pickering N.G.S. "A". Work and Test Permits. July 1978 - Unit 1. Voi. 102 Pickering N.G.S. "A". Work and Test Permits. August 1978 - Unit 1. Vol. 103 Pickering N.G.S. "A". Work and Test Permits. September 1978 - Unit 1. Vol. 10* Pickering N.G.5. "A". Work and Test Fsrmits. July and August 1978 - Unit 2. Vol. 105 Pickering N.G.S. "A". Work and Test Permits. September 1978 - Unit 2. Voi. 106 Pickering N.G.S. "A". Work and Test Permits. July and August 1978 - Unit 3. Vol. 107 Pickering N.G.S. "A". Work and Test Permits. September 1978- Unit 3. Vol. 108 Pickering N.G.S. "A". Work and Test Permits. July and August 1978 - Unit 4. Vol. 109 Pickering N.G.S. "A". Work and Test Permits. September 1978 - Unit 4. Vol. 110 Pickering N.G.S. "A". Descriptive Logs. Units 0, 1 and 2 July 1978. Vol. Ill Pickering N.G.S. "A". Descriptive Logs. Units 3 and *' July 1978. Vol. 112 Pickering N.G.S. "A". Descriptive Logs. Units 0, 1 and 2 August 1978. Vol. 113 Pickering N.G.S. "A". Descriptive Logs. Units 3 and 4 August 1978. -E/8-

Vol. 11* Pickering N.G.S. "A". Descriptive Logs. Units 0, I and 2 September 1978. Vol. 115 Pickering N.G.S. "A". Descriptive Logs. Units 3 and * September 1978.

Vol. 116 Pickering N.G.S. "A". Work Control Area Logs. 3rd Quarter 1978. Vol. 117 Pickering N.G.S. "A". Fuelling Logs. Unit 1. 3rd Quarter 1978. Vol. 118 Pickering N.G.S. "A". Fuelling Logs. Unit 2. 3rd Quarter 1978. Vol. 119 Pickering N.G.S. "A". Fuelling Logs. Unit 3. 3rd Quarter 1978. Vol. 120 Pickering N.G.S. "A". Fuelling Logs. Unit«. 3rd Quarter 1978. Vol. 121 Pickering N.G.S. "A". Deficiency Reports. Units 012 and 034. Vol. 122 Pickering N.G.S. "A". Deficiency Reports. UnitO. USI 0000 to 5*60. 3rd Quarter 1978. Vol. 123 Pickering N.G.S. "A". Deficiency Reports. Unit 0. USI 5510 to 71600. 3rd Quarter 1978. Vol. 12* Pickering N.G.S. "A". Deficiency Reports. UnitO. USI 7160 to 98309. 3rd Quarter 1978. -E/9-

Vol. 125 Pickering N.G.S. "A". Deficiency Reports. Unit 1. USI 0000 to 4531. Vol. 126 Pickering N.G.S. "A". Deficiency Reports. Unit 1. USI 50000 to 7611. 3rd Quarter 1978.

Vol. 127 Pickering N.G.S. "A". Deficiency Reports. Unit 2. USI 0000 to 32305. 3rd Quarter 1978. Vol. 128 Pickering N.G.S. "A". Deficiency Reports. Unit 3. USI 0000 to 4121. 3rd Quarter 1978. Vol. 129 Pickering N.G.S. "A". Deficiency Reports. Unit 3. USI 42122 to 78700. 3rd Quarter 1978. Vol. 130 Pickering N.G.S. "A". Deficiency Reports. Unit 4. USI 0000 to 4323. 3rd Quarter 1978. Vol. 131 Pickering N.G.S. "A". Deficiency Reports. Unit 4. USI 43230 to 78700. 3rd Quarter 1978. Vol. 132 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 1 to 7. Vol. 133 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 7 to 8. Vol. 134 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 9 to 12. - E/10 -

Vol. 133 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 14 to 18. Vol. 136 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 19 to 23. Vol. 137 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 24 to 41. Vol. 138 Pickering N.G.S. "A". Safety System Test Reports. July 1978. Tests 45 to 48. Vol. 139 Pickering N.G.S. "A". Safety System Test Reports. August 1978. Tests 1 to 7. Vol. 140 Pickering N.G.S. "A". Safety System Test Reports. August 1978. Tests 7 to 8. Vol. 1*1 Pickering N.G.S. "A". Safety System Test Reports. August 1978. Tests 9 to 12. Vol. 142 Pickering N.G.S. "A". Safety System Test Reports. August 1978. Tests 13 to 18. Vol. 143 Pickering N.G.S. "A". Safety System Test Reports. August 1978. Tests 19 to 36. Vol. 144 Pickering N.G.5. "A". Safety System Test Reports. August 1978. Tests 41 to 48. Vol. 145 Pickering N.G.S. "A". Safety System Test Reports. September 1978. Tests 1 to 7. -E/U-

Vol. 1*6 Pickering N.G.S. "A". Safety System Test Reports. September 1978. Tests 8 to 14. Vol, 1*7 Pickering N.G.S. "A". Safety System Test Reports. September 1978. Tests 15 to 23. Vol. 148 Pickering N.G.S. "A". Safety System Test Reports. September 1978. Tests 24 to 47.

Vol. 149 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 0 - 3rd Quarter 1978. US1 00570 to 67877. Vol. 150 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 0 - 3rd Quarter 1978. USI 7110 to 90185. Vol. X51 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 1/2 and 3/4 -3rd Quarter 1978. USI 4511 to 7513.

Vol. 152 Pickering N.G.S. "A11. Control Maintenance Work Reports. Unit 1 - 3rd Quarter 1978. USI 09070 to 7313. Vol. 153 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 2 - 3rd Quarter 1978. USI 21102 to 7611. Vol. 154 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 3 - 3rd Quarter 1978. USI 09071 to 4511. Vol. 155 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 3 - 3rd Quarter 1978. USI 4521 to 7711. Vol. 156 Pickering N.G.S. "A". Control Maintenance Work Reports. Unit 4 - 3rd Quarter 1978. USI 09015 to 7711. -E/12-

Vol. 157 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 0 - 3rd Quarter 1978. USI 09015 to 71513. Vol. 158 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 0 - 3rd Quarter 1978. USI 71600 to 90180. Vol. 159 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 1 - 3rd Quarter 1978. USI 09070 to 79150. Vol. 160 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 2 - 3rd Quarter 1978. USI 09070 to 7711.

Vol. 161 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 3 > 3rd Quarter 1978. USI 09015 to 32512. Vol. 162 Pickering N.G.S. "A". Mechanical Maintenance Work Reports. Unit 3 - 3rd Quarter 1978. USI 33000 to 77110.

Vol. 163 Pickering N.G.S. "A" Mechanical Maintenance Work Reports. Unit * - 3rd Quarter 1978. USI 09070 to 76730. Vol. 16* Pickering N.G.S. "A". Water Quality and Daily Water Data. Vol. 165 Pickering N.G.S. "A". 1978 Monthly Fish Sample Reports. Vol. 166 Pickering N.G.S. "A". Routine Radiological Survey. Vol. 167 Pickering N.G.S. "A". External Work Requests. 3rd Quarter 1978. Vol. 168 Pickering N.G.S. "A". Operating Memoranda. 3rd Quarter 1978. Vol. 169 Pickering N.G.S. "A". Operating Memoranda. 3rd Quarter 1978. - E/13 -

Vol. 170 Pickering N.G.S. "A". Orders to Operate. 148501 to 183199.

Vol. 171 Pickering N.G.S. "A". Orders to Operate. 183301 to 185100.

Vol. 172 Pickering N.G.S. "A". Orders to Operate. 722501 to 722950.

Vol. 173 Pickering N.G.5. "A". Orders to Operate. 722951 to 72*850. Vol. 17* Pickering N.G.S. "A". Orders to Operate. 725052 to 7267*8. Vol. 175 Pickering N.G.S. "A". Orders to Operate. 726758 to 7610*9.

Reports Requested By The Select Committee - No Restriction

Vol. Report No. Number Title 176 78252 AECL Research and Development in Engineering 70181 AECL Symposium on Reliability 77132 Approach to Prevention of Massive Failure of Heat Transport Piping Bruce B 78326 Assessment of Radiation Risks in the Case of Accidents with Truck Transportation of Tritiated Water in Drums 76258 Boiler Feed Pumps Study Darlington GS 78070 Boiler Level Control Study - Phase I 78223 Bruce GS A Main Steam Piping Steam Hammer Problem

177 79038 Bruce GS B Design of Energy Absorbing Barrier System for Turbine Missiles 78262 Bruce GS B Dynamic Effects of Pipe Impact Loads on Reactor Building Structure 78121 Bruce GS B Shutdown System (SDS 1 and SDS 2) Reliability Targets for Loss of Production - E/14 -

75155 Bruce NPO Radioactive Wast Storage Site No. 2 Stage 4 79013 Bruce Nuclear Power Development Radioactive Waste Storage Site No. 2 Stage 3 Extension Foundation Construction Documentation 75046 BNPD Radioactive Waste Storage Site 2 - Stage 3 Geotechnical Investigations 75194 Canadian Nuclear Industry Study 74022 Community Impact - Bruce Nuclear Power Development - 2 vols. 178 76275 Complete retubing of a CANDU Reactor 72260 Conceptual Design Studies of a 4 x 1200 MWe LWR Type Nuclear GS 77067 Conceptual and Preliminary Engineering of Vacuum Bldg. .Darlington GS 76136 Cooling Water Discharge Duct Study Darlington GS 75156 Cooling Water Systems Supplementary Report Darlington GS 76299 Core Iodine and Noble Gases to Reactor Building Dose Rates Following Release 7532S Crack Investigation Unit 4 Fuel Channels Pickering GS

179 77021 Darlington GS Reliability Study of Computer Configurations 76172 Delayed Hydrogen Cracking in ZR 2-1/2% NB Pressure Tubes Appraisal Draft 76351 Delayed Hydrogen Cracking of Zirconium Alloy Pressure Tubes 76173 Delayed Hydrogen Cracking ZR-2 and Half % NB and Zircaloy - 2 Pressure Tubes 77075 Design Accident Analysis BNPD Rad Waste Storage Site 2 Stage 3 76168 Deuterium Buildup in CANDU Pressure Tubes Examination Results 73037 Economic and Financial Impact of Bruce Nuclear Power Development -E/15- 78160 Economic Evaluation on Alternative Vertical Shaft Arrangements for Deep Cavern Nuclear Power Station 78004 Economics of Advanced Fuel Cycles in CANDU Reactors 77156 Economics of Plutonium Recycle

180 77176 Economics of Thorium Fuel Cycles ; 71242 Emergency Procedure for H_S Release Bruce GS 76158 Emergency Response Study for Spent Fuel Shipments in Canada 78075 Evaluation Factors for Assessing Design Variations in Chats Falls GS B - 4 x 600 MVe Nuclear Generating Station 76330 Examination of Results of Deuterium Buildup in CANDU Pressure Tubes 75064 Fuel Bundle Temperature Distribution History Following A LOCA-Hotspot 75294 Fuel Channel Pressure Tubes Status of Crack Invest. Recommendation for Reactor 75160 Geotechnical and Environmental Study on Disposal of Radioactive Solid Wastes 181 78035 Hydrogeological Assessment of Spillage of Tritiated Water along Transportation Routes in Ontario 78144 Implications of Using Alternate Fuel Cycles to Meet Ontario's Nuclear Power Demand 78310 Influence of Extreme Natural Phenomena on Darlington GSA 74328 Liquid Waste Storage Pickering Radioactive Waste Management Study 76129 Long Term Temperature Changes in the Great Lakes 79093 Long Term Outlook for Nuclear Capacity in Ontario - A Strategy-Analysis Approach 78112 Mortality and Morbidity Impacts of the Fuel Cycles Associated with Nuclear and Fossil Fuel Electrical Generation Draft 77157 Nuclear Weapons and Nuclear Reactors - E/16 -

79109 Pickering GS A Creeping Pressure Tubes May Require Replacement 132 79077 Pickering GS A Large Scale Fuel Channel Replacement Study Phase II and Appendices 133 7902* Pickering GS A Vacuum Building Stress Analysis 74042 Pickering Heavy Water Upgrading Plant - Tritium Release in Waste Streams 78057 Postulated Pipe Failure Effect on Containment Bruce GS B 76195 Power Transient During LOCA Pickering GS A 78296 Preliminary Examination of Nuclear Safety Factors - Eastern Ontario Site Selection Study 76385 Pressure Drop Tests on Pickering and Bruce Fuel and Channels 77087 Pressure Tube Fretting Summary 78220 Probabilistic Evaluation of the Design Basis Seismic Ground Motion for Chats Falls GS B Site 76066 Project Performance Specification for 4 x 1250 MWe CANDU GS NK54 733 IJ Radiation Exposure Reduction Economics 75070 Radioactive Waste Storage BNPD Site 1 Geotechnical Investigations 75061 Radioactive Waste Storage BNPD Site 2 Stage 3 Geotechnical Investigations 73216 Radioactive Waste Transportation Alternatives Until the Year 2000 75167 Radioactive Wastes from Fuel Reprocessing and Fabrication 78241 Reactivity Balance in a Pressure/Calandria Tube Rupture Accident in Darlington GS A 77073 Retubing a CANDU Reactor 79048 Social and Economic Factors Vol. 2 Nuclear Waste Management Centre 72099 Sternglass Phenomenon and the Gofman-Tamplin Controversy - Radiation Doses -E/17-

77264 Study for the Export of Electric Power Min. Industry and Tourism

185 78170 System Expansion Program Review (SEPR) Environmental Effects - Nuclear 79011 The Low Enriched Uranium Fuel Cycle in Ontario: A Resource Utilization Study 78224 Tritium Control Working Party Report 78045 Underground Nuclear Power Station Interim Report 79092 Underground Nuclear Power Station Study Radionudide Migration in Geologic Media 186 78333 United States Utility Experience in Public Participation HPD 78-1 Gorman An Assessment of the Relative Hazards of T- i and T20 HPO 78-2 Gorman Environmental Aspects of Tritium from Wong CANDU Station Releases CNS-61 Central Nuclear Services 1979 Program CNS-IR-OOQ-2 CNS Mission and Stakeholders CNS-IR-012-26 Assessment of Present Integrity of Zirconium Alloy Components at Douglas Point CNS-IR-015-2 Expected Radioactive Emissions from Pickering GS CNS-K-017-5 Nuclear Generation Division 1978 Budget Summary CNS-IR-017-11 Cost Standards for Nuclear Generating Stations Based on Costs of US Nuclear Plants CNS-K-311-29 Status of Information on Pressure Tubes and Calandria Tubes Obtained from CANDU-PHw Reactors CNS-IR-381-33 BHWP Utilization - Operating Strategy

187 CNS-IR-312-1 An Assessment of Corrosion Damage in the Calandria Vault at Douglas Point CNS-IR-330-10 Bruce NGS A - Total Loss of Transport Feed - E/18 -

CNS-1R-330-19 Bruce NGS A - Effects of Overpressure Transient with One HT Relief Valve Capped CNS-IR-330-20 Two HT Relief Valves Failing Open in a Bruce NGS A Unit Operating at Power CNS-IR-330-21 Bruce NGS A Heat Transport Circuit One Pump Seizure at 100% FP CNS-R-331-14 Heat Transport Thermosyphoning Following Total Loss of Class IV at Pickering NGS CNS-IR-364-1 Boiler Blowdown Modifications for Pickering GS A CNS-IR-379-17 Nuclear Fuelling Unit Energy Cost Forecast CN5-IR-790-6 Active Effluents from Pickering GS RMEP-IR-015-* Effectiveness of Automatic Poison Addition System following Pressure Tube Failures into Moderator for Bruce GS A Reactor RMEP-1R-015-7 Number of SCRs Needed for Loss of Regulation Accident from Low Power at Pickering NGS A RMEP-IR-790-* A General Procedure for the Immobilization of Aqueous Radioactive Liquid Waste to Allow Storage at the NGD Waste Storage Site

Additional documents provided to the Legislative Library and to the Hydro Public Reference Centre during the Term of the Committee Vol. 188 Significant Event and Unusual Occurrence Reports for Bruce, Pickering, Douglas Point and NPD Bruce 79-65, 79-67 snf 79-68 Pickering 79-71 to 79-81 and 79-87 Douglas Point 79-8 NPD 79-18 Vol. 189 Nuclear Generation Division Management Review 197» to 1976

Vol. 190 Nuclear Generation Division Management Review 1977 and 1978 Vol. 191 Health Physics Department EnvironmetaL-Quarterly 1st Qtr. 1977 to 1st Qtr. 1979 -E/19-

Vol. 192 Radiation Protection Training Yellow and Green Manuals Vol. 193 Significant Event Reports for Bruce, Pickering, Douglas Pt. andNPD Bruce 78-100, 79-69 to 79-7*, 79-79 Pickering 79-82 to 79-86 and 79-88 to 79-92 Pickering UORs 79-3 to 79-5 Douglas Point 79-9 NPD 79-19 to 79-23

Vol. 19* Pickering N.G.S. "A" LOCA Reanalysis Correspondence Vol.195 Bruce N.G.S. "A" Correspondence 1970-1973 Vol. 196 Bruce N.G.S. "A" Correspondence 197*-1977 Vol. 197 Bruce N.G.S. "A11 Correspondence 1978-1979 Vol. 198 Bruce N.G.S. "A" AECB Staff Report on the Safety Review of the Bruce Generating Station "A" Unit 2 as of June 1976 and the AECL/Ontario Hydro Response Vol. 199 Bruce N.G.S. "A" AI Reports Vol. 200 Bruce N.G.S. "A" and "B" Conceptual Study on ECI Systems Vol. 201 Bruce N.G.S. "A" and "B" Design Review Package on ECI System Vol. 202 Significant Event Reports and Unusual Occurrence Reports for Bruce A, Pickering A, Douglas Pt. & NPD Nuclear Gnerating Stations Bruce SERs 79-75 to 79-9* UORs 79-2 to 79-3 Pickering SERs 79-93 to 79-127 Douglas Pt. SERs 79-10 to 79-11 NPD SERs 79-2* to 79-32 UORs 79-2 Vol. 203 Significant Event and Unusual Occurrence Reports for Bruce A, Pickering A, Douglas Pt. & NPD Nuclear Generating Stations Bruce SERs 79-91 and 79-95 to 79-125 Pickering SERs 79-128 to 79-162 Douglas Pt. SERs 79-13 NPD SERs 79-33 to 79-*5 - E/20 -

Vol. 20* Quarterly Technical Reports for Bruce: 79-1,2 Sc 3 Vol. 205 Quarterly Technical Reports for Pickering (79-1, 2 & 3) & Douglas point (79-1 & 2) Vol. 206 Significant Event and Unusual Occurrence Reports for Bruce A, Pickering A, Douglas Pt. and NPD Generating Stations Bruce 79-126 to 79-153 Pickering 79-163 to 79-189 (without 79-186) Douglas Pt. 79-12 and 79-15 NPD 79-»6 to 79-49 Vol. 207 Douglas Pt. NCS Quarterly Technical Report 79-3 Vol. 208 Significant Event and Unusual Occurrence Reports for Bruce A, Pickering A, Douglas Pt. and NPD Generating Stations Bruce 79-15» to 79-155 Pickering 79-186 to 79-190 to 77-193 Douglas Pt. Generating Station 79-1», 79-16 to 79-1S NPD 79-1» to 79-17 and 79-50 to 79-5»

Vol. 209 Bruce NGS "A" 1980 SERs Vol. 210 Bruce NGS "A" Quarterly Technical Report 79-» Vol. 211 NPD 1979 Annual Report Vol. 212 Pickering NGS "A" Quarterly Technical Report 79-» Vol. 213 Douglas Point Quarterly Technical Report 79-» Vol. 21» Pickering NGS "A" 1980 SERs Vol. 215 Douglas Point and NPD 1980 SERs Vol. 216 Bruce NGS "A" Follow-up & General SERs - E/21 -

CONTROLLED ACCESS

Documents provided to the Legislative Library and The Hydro Public Reference Centre Sine 22,1979.

Vol. C-l Bruce Reactor Safety (B.R.S.) Notes Category A - Superseded

Vol. C-2 Bruce Reactor Safety (B.R.5.) Notes Category A - Superseded

Vol. C-3 Bruce Reactor Safety (B.R.S.) Notes Category A - Superseded

Vol. C-* Bruce Reactor Safety (B.R.S.) Notes Category B - Reference Material

Vol. C-5 Bruce Reactor Safety (B.R.S.) Notes Category C - Design Information

Vol. C-6 Bruce Reactor Safety (B.R.S.) Notes Category D - Assessment of Hypothetical Accidents. (Not required to demonstrate conformity with AECB criteria)

Vol. C-7 Bruce N.G.S. "A" Safety Report (Vol. 1 &. 2)

Vol. C-8 Bruce N.G.S. "A" Safety Report (Vol. 3)

Vol. C-9 • Pickering N.G.S. "A" Safety Report (Vol. I)

Vol. C-10 Pickering N.G.S. "A" Safety Report (Vol. 2 & 3) Vol. c-n Douglas Point N.G.S. "A" Safety Report Vol. C-12 NPD G.S. Safety Report (Parts 1 and 2)

Vol. C-13 NPD G.S. Safety Report Addendum Material

Vol. C-13A NPD G.S. Safety Report Addendum Material Report on Emergency Core Cooling at NPD (CRNL 1768)

Vol. C-l* Bruce N.G.S. "A" Loss of Regulation Study

Vol. C-15 Pickering N.G.S. "A" Loss of Regulation Study Vol. C-16 Bruce N.G.S. "A" Overpressure Protection Report Vol. C-17 NPD G.S. In-Service Reports 01010-1 to 015-5 Vol. C-18 NPD G.S. In-Service Reports 015-6 to 016-6 Vol. C-19 NPD G.S. In-Service Reports 01700 to 300-15 - E/22 -

Vol. C-20 NPD G.S. In-Service Reports 3Q0-16 to 312-I Vol. C-21 NPD C.S. In-Service Reports 313-1 to 3313-6 Vol. C-22 NPD G.S. In-Service Reports 332.0-1 to 3522-18 Vol. C-23 NPD G.S. In-Service Reports 3*4.0-1 to 3522-18 Vol. C-24 NPD G.S. In-Service Reports 3522-19 to 372-1* Vol. C-25 NPD G.S. In-Service Reports 380-1 to 4111-4 Vol. C-26 NPD G.S. In-Service c oorts * 112-1 to 5234-3 Vol. C-27 NPD G.S. In-Service Reports 600.0-1 to 637.2-4 Vol. C-28 NPD G.S. In-Service Reports 6372-5 to 675.1 Vol. C-29 NPD G.S. In-Service Reports 711-1 to 7922-2 Vol. C-30 NPD G.S. In-Service Reports 09002 Outage Reports 1967 to 1971 Vol. C-31 NPD G.S. In-Service Reports 09002 to 09004 Outage Reports 1962 to 1966 Derating Losses 1966 to 1967

ContraUed Access documents provided the Legislative Library and the Hydro Public Reference Centre June 26,1979 Vol. C-32 Douglas Point N.G.S. In-Service Reports 010-1 to 0f01S-67-36 Vol. C-33 Douglas Point N.G.S. In-Service Reports 09013-67-37 to 09018-0-70-43

Vol. C-34 Douglas Point N.G.S. In-Service Reports 090-0-71-1 to 252-1

Vol. C-35 Douglas Point N.G.S. In-Service Reports 310-1 to 313-6 Vol. C-36 Douglas Point N.G.S. In-Service Reports 321-1 to 337-1 Vol. C-37 Douglas Point N.G.S. In-Service Reports 338000-4 to 34 - E/23 -

Vol. C-38 Douglas Point N.G.S. In-Service Reports 3*3-1 to 370-2 Vol. C-39 Douglas Point N.G.S. In-Service Reports 370-3 to * 12-1 Vol. C-40 Douglas Point N.G.S. In-Service Reports 412-2 to 523-11 Vol. C-41 Douglas Point N.G.S. In-Service Reports 600-1 to 678-1. Vol. C-42 Douglas Point N.G.S. In-Service Reports 711-1 to 761-1 Vol. C-43 Pickering N.G.S. "A" In-Service Reports - Unit 0 01100-1 to 33110-1

Controlled access documents provided to the Legislative Library and the Hydro Public Reference Centre June 25,1979. Vol. C-44 Pickering N.G.S. "A" In-Service Reports - Unit 0 33200-1 to 3611-1 Vol. C-45 Pickering N.G.S. "A" In-Service Reports - Unit 0 37000-1 to 5*700-1 Vol. C-*6 Pickering N.G.S. "A" In-Service Reports - Unit 0 6317* -79100 Vol. C-*7 . Pickering N.G.S. "A" In-Service Reports - Unit 1 2110-1 to 37000 Vol. C-48 Pickering N.G.S. "A" In-Service Reports - Unit 1 4001-1 to 41220-1 Vol. C-49 Pickering N.G.S. "A" In-Service Reports - Unit 1 41200-2 to 66*00-4 - E/24 -

Vol. C-50 Pickering N.G.S. "A" In-Service Reports - Unit 1 66400-5 to 72200 Vol. C-51 Pickering N.G.S. "A" In-Service Reports - Unit 2 2-21130-2 to 2-36000-2

Vol. C-52 Pickering N.G.S. "A" In-Service Reports - Unit 2 2-41000-1 to 2-71330-1 Vol. C-53 Pickering N.G.S. "A" In-Service Reports - Unit 3 21000 to 3301 Vol. C-54 Pickering N.G.S. "A" In-Service Reports - Unit 3 35200-1 to 71200 Vol. C-55 Pickering N.G.S. "A" . In-Service Reports - Unit 4 4-31100-2 to 4-63536-1 Vol. C-56 Bruce N.G.S. "A" In-Service Reports 01500-1 to 09053-4 Vol. C-57 Bruce N.G.S. "A" In-Service Reports 31U0-1 to 38300 Vol. C-58 Bruce N.G.S. "A" In-Service Reports 41240-1 to 98600 Vol. C-59 Bruce N.G.S. "A" Design Manual 00000 to 16000 Vol. C-60 Bruce N.G.S. "A" Design Manual 21000 to 30000 Vol. C-61 Bruce N.G.S. "A" Design Manual 31000 to 33000 Vol. C-62 Bruce N.G.S. "A" Design Manual 33000 to 34000 - E/25 -

Vol. C-63 Bruce N.G.S. "A" Design Manual 34000 to 34500 Vol. C-64 Bruce N.G.S. "A" Design Manual 34500 to 35000 Vol. C-65 Bruce N.G.S. "A" Design Manual 35000 to 35250 Vol. C-66 Bruce N.G.S. "A" Design Manual 35250 to 35630 Vol. C-67 Bruce N.G.S. "A" Design Manual 35630 to 35700 Vol. C-68 Bruce N.G.S. "A" Design Manual 35700 to 37000 Vol. C-69 Bruce N.G.S. "A" Design Manual 37001 to 40000 Vol. C-70 Bruce N.G.S. "A" Design Manual 40001 to 49999 Vol. C-71 Bruce N.G.S. "A" Design Manual 50000 to 59999 Vol. C-72 Bruce N.G.S. "A" Design Manual 60000 to 63399 Vol. C-73 Bruce N.G.S. "A" Design Manual 63400 to 63530 Vol. C-74 Bruce N.G.S. "A" Design Manual 63531 to 63590 Vol. C-75 Bruce N.G.S. "A" Design Manual 63591 to 63593 (Vol. 1) - E/26 -

Vol. C-76 Bruce N.G.S. "A" Design Manual 63593 (Vol. 2) Vol. C-77 , Bruce N.G.S. "A" Design Manual 63593 (Vol. 3) Vol. C-78 Bruce N.G.S. "A" Design Manual 6359* Vol. C-79 Bruce N.G.S. "A" Design Manual 63595 to 63710.9

Vol. C-80 Bruce N.G.S. "A" Design Manual 63720.1 to 6385* Vol. C-81 Bruce N.G.S. "A" Design Manual 65000 to 65060 Vol. C-82 Bruce N.G.S. "A" Design Manual 65100 to 66600 Vol. C-83 Bruce N.G.S. "A" Design Manual 66700.1 to 66700.6 Vol. C-8* Bruce N.G.S. "A" Design Manual 6713* to 71*10 Vol. C-85 Bruce N.G.S. "A" Design Manual 71*20 to 73220 Vol. C-86 Bruce N.G.S. "A" Design Manual 732*2-1 to 73**0-7 Vol. C-87 Bruce N.G.S. "A" Design Manual 73*40-8 to 73*60 Vol. C-88 Bruce N.G.S. "A" Design Manual 73*70-2 to 76112 - E/27 -

Vol. C-89 Bruce N.G.S. "A" Design Manual 76121 to 79320

Voi. C-90 Pickering N.G.S. "A" Design Manual 00000 to 20300

Vol. C-91 Pickering N.G.S. "A" Design Manual 21000 to 28000 Vol. C-92 Pickering N.G.S. "A" Design Manual 31100 to 32029

Vol. C-93 Pickering N.G.S. "A" Design Manual 32110 to 33200

Vol. C-94 Pickering N.G.S. "A" Design Manual 33300 to 34610 Vol. C-95 Pickering N.G.S. "A" Design Manual 34620 to 35290.3

Vol. C-% Pickering N.G.S. "A" Design Manual 35310 to 37000 Vol.C-97 Pickering N.G.S. "A" Design Manual 40010 to 45310 Vol. C-98 Pickering N.G.S. "A" Design Manual 50000 to 60300

Vol. C-99 Pickering N.G.S. "A" Design Manual 60436 to 63524 Vol. C-100 Pickering N.G.S. "A" Design Manual 63534 to 63812

Vol. C-101 Pickering N.G.S. "A" Design Manual 65000 to 67870 - E/28 -

Vol. C-102 Pickering N.G.S. "A" Design Manual 71200 to 73110 Vol. C-103 Pickering N.G.S. "A" Design Manual 73130 to 79210 Vol. C-104 Douglas Point N.G.S. Design Manual 00000 to 29300 Vol. C-10.J Douglas Point N.G.S. Design Manual 31100 to 32114 Vol. C-106 Douglas Point N.G.S. Design Manual 32300 to 3*510 Vol. C-107 Douglas Point N.G.S. Design Manual 3*520 to 37000 Vol. C-108 Douglas Point N.G.S. Design Manual 40000 to 53*10

Vol. C-109 Douglas Point N.G.S. Design Manual 601*0 to 63520.1 Vol. C-110 Douglas Point N.G.S. Design Manual 63520.2 to 63812.2 Vol. C-111 Douglas Point N.G.S. Design Manual 64210 to 67921 Vol. C-112 Douglas Point N.G.S. Design Manual 71114 to'79300 Vol.C-113 NPDG.S. Design Manual 000 to 320 Vol. C-ll* NPD G.S. Design Manual 321 to 411 - E/29 -

Vol. C-115 NPDG.S. Design Manual 412 to 633 Vol. C-U6 NPD G.S. Design Manual to 637

Vol. C-117 NPDG.S. Design Manual 638 to 7S5

Vol. C-118 Bruce N.G.S. "A" Operating Manual 00000 to 09053 Vol. C-119 Bruce N.G.S. "A" Operating Manual 09071 to 09092 Vol. C-120 Bruce N.G.S. "A" Operating Manual 20120 to 32710 Vol. C-121 Bruce N.G.S. "A" Operating Manual 33000 Vol. C-122 Bruce N.G.S. "A" Operating Manual 33130 to 34980 Vol. C-123 Bruce N.G.S. "A" Operating Manual 35100 to 38100 Vol. C-124 Bruce N.G.S. "A" Operating Manual 38220 to 38910 Vol. C-125 Bruce N.G.S. "A" Operating Manual 41000 to 41220 Vol. C-126 Bruce N.G.S. "A" Operating Manual 41230 to 43240 Vol. C-127 Bruce N.G.S. "A" Operating Manual 45210 to 53300 - E/30 -

Vol. C-128 Bruce N.G.S. "A" Operating Manual 53320 to 60040.4 Vol. C-129 Bruce N.G.S. "A" Operating Manual 60040.5 to 63720 Vol. C-130 Bruce N.G.S. "A" Operating Manual 63730 to 71420 Vol. C-131 Bruce N.G.5. "A" Operating Manual 71460-1 to 73600.10 Vol. C-132 Bruce N.G.S. "A" Operating Manual 73700.1 to 79320.8 Vol. C-133 Pickering N.G.5. "A" Operating Manual 00000 to 32710 Vol. C-134 Pickering N.G.S. "A" Operating Manual 33000 to 34200 Vol. C-135 Pickering N.G.S. HA" Operating Manual 34400 to 34600 Vol. C-136 Pickering N.G.S. "A" Operating Manual 34810 to 35200 Vol. C-137 Pickering N.G.S. "A" Operating Manual 35300 to 36900 Vol. C-138 Pickering N.G.S. "A" Operating Manual 37000 to 45310 Vol. C-139 Pickering N.G.S. "A" Operating Manual 51000 to 63815 Vol. C-140 Pickering N.G.S. "A" Operating Manual 65020 to 71730 - E/31 -

Vol. C- Pickering N.G.S. "A" Operating Manual 72110 to 8*1*0 Vol. C-l*2 Douglas Point N.G.S. Operating Manual 09000 to 09671.4

Vol. C-1*3 Douglas Point N.G.S. Operating Manual 0971.5 to 2915 vol. c-i** Douglas Point N.G.S. Operating Manual 3100 to 3372 Vol. C-l*5 Douglas Point N.G.S. Operating Manual 3*11 to 3**0

Vol. C-l*6 Douglas Point N.G.S. Operating Manual 3*50 to 35*1 Vol. C-l*7 Douglas Point N.G.S. Operating Manual 3611 to 3920 Vol. C-l*8 Douglas Point N.G.S. Operating Manual *100 to *520 Vol. C-l*9 Douglas Point N.G.S. Operating Manual 5000 to 5130 Vol. C-150 Douglas Point N.G.S. Operating Manual 5200 to 52*3 Vol. C-151 Douglas Point N.G.S. Operating Manual 53*0 to 6030

Vol. C-152 Douglas Point N.G.S. Operating Manual 6110 to 6510 Vol. C-153 Douglas Point N.G.S. Operating Manual 66*0 to 6789 -E/32-

Voi. C-154 Douglas Point N.G.S. Operating Manual 7101 to 7191 Vol. C-155 DouglasPointN.CS. Operating Manual 7300 to 7930

Vol. C-156 NPDC.S. Operating Manual 090.7.1.0 to 090.7.1.3 Vol. C-157 NPDG.S. Operating Manual 090.7.18-6.0 to 338.0-4.0 Vol. C-158 NPDG.S. Operating Manual 34L0-0 to 352.3-1.10 Vol. C-159 NPDG.S. Operating Manual 35331 to 452.0-7.3 Vol. C-160 NPDG.S. Operating Manual 510.0 to 623.2-5.0 Vol. C-161 NPD G.S. Operating Manual 633.1-0 to 672.1.1-13 Vol. C-162 NPDC.S. Operating Manual 711.1-0 to 789.1-4

Controlled access documents provided to the Legislative Library and the Hydro Public Reference Centre June 26,1979. Vol. C-163 liruce N.G.S. "A" Periodic Inspection Program Vol. C-164 Pickering N.G.S. "A" Periodic Inspection Program Vol. C-165 Douglas Point N.G.5. Periodic Inspection Program Vol. C-166 NPD G.S. Periodic Inspection Program - E/33 -

Vol. C-167 Bruce N.G.S. "A" Commissioning Reports 0913.3 to 3*3* Vol. C-163 Bruce N.G.S. "A" Commissioning Reports 3*51.1 to 60250 Vol. C-169 Bruce N.G.S. "A" Commissioning Reports 6359.1 to 79320 Vol. C-170 Bruce N.G.S. "A" Commissioning Reports - Unit 0 0913.3 to 3*3» Vol. C-171 Bruce N.G.S. "A" Commissioning Reports 3300.1 to 77110 Vol. C-172 Bruce N.G.S. "A" Commissioning Reports - Unit 2 00915.2 to 241O.4(A) Vol. C-173 Bruce N.G.S. "A" Commissioning Reports - Unit 2 3100 to 31760 Vol. C-174 Bruce N.G.S. "A" Commissioning Reports - Unit 2 3177 to 3300.5 Report #2 Vol. C-175 Bruce N.G.S. "A" Commissioning Reports 3300.5 Report // 3 to 3300.10 Vol. C-176 Bruce N.G.S. "A" Commissioning Reports - Unit 2 34810 to 38910 Vol. C-177 Bruce N.G.S. "A" Commissioning Reports - Unit 2 41000 to 94000 Vol. C-178 Bruce N.G.S. "A" Commissioning Reports - Unit 3 2100.1Ato77U Vol. C-179 Bruce N.G.S. "A" Commissioning Reports - Unit 4 03550 to 75140 - E/3* -

Vol. C-180 Bruce N.G.S. "A" Commissioning Reports - Unit 0 3*200.3(A) to 7522.4(A)

Vol. C-131 Bruce N.G.5. "A" Commissioning Reports - Unit 1 00000 to 3540.1

Vol. C-1S2 Pickering N.G.S. "A" Commissioning Reports - Unit 1 3700.1(A)to5822.1(A)

Vol. C-183 Pickering N.G.S. "A" Commissioning Reports - Unit 1 60000.KA) to 7920.1 (A)

Vol. C-18* Pickering N.G.S. "A" Commissioning Reports - Unit 2 31710.KA) to 3700.KA)

Vol. C-185 Pickering N.G.S. "A" Commissioning Reports - Unit 2 4110.8(C)to716*.l(A)

Vol. C-186 Pickering N.G.S. "A" Commissioning Reports - Unit 3 OOOOO.KC) to 75130.KA)

Vol. C-1S7 Pickering N.G.S. "A" Commissioning Reports - Unit 4 06070.1(A)to77ll.2(A)

Vol. C-138 Douglas Point N.G.S. Commissioning Reports 000.1Ato3110

Vol. C-1S9 Douglas Point N.G.S. Commissioning Reports 3131 to 33000.8(A7)

Vol. C-190 Douglas Point N.G.S. Commissioning Reports 3331(Al)to3810.1(Cl)

Vol. C-191 Douglas Point N.G.S. Commissioning Reports *U0.1(Al)to4300.2(A2)

Vol. C-192 Douglas Point N.G.S. Commissioning Reports 5200.KA1) to 5131.3 -E/35- •

Vol. C-193 Douglas Point N.G.S. Commissioning Reports 5200.KA) to 5233.2(A2) Vol. C-194 Douglas Point N.G.S. Commissioning Reports 52

Vol. C-196 Douglas Point N.G.S. Commissioning Reports 7173.1(Al)to7920.1(Al) Vol. C-197 NPD G.S. Commissioning Reports 100.1(Al)to331.8(Cl) Vol. C-198 NPD G.S. Commissioning Reports 331.9(A1) to 380.KA1) Vol. C-199 NPD G.S. Commissioning Reports 410.5 to 623.3 Vol. C-200 NPD G.S. Commissioning Reports 630.2 to 660 Vol. C-201 NPD G.S. Commissioning Reports 711.1 to 733.1 Vol. C-202 NPD w.S. Commissioning Reports 733.1 to 787.2(A1) Vol. C-203 Bruce N.G.S. "A" System Training Manual Vol. C-20« Bruce N.G.S. "A" System Training Manual Vol. C-205 Bruce N.G.S. "A" System Training Manual Vol. C-206 Bruce N.G.S. "A" System Training Manual - E/36 -

Vol. C-207 Bruce N.G.S. "A" System Training Manual Vol. C-208 Pickering N.G.S. "A" System Training Manual Vol. C-209 Pickering N.G.S. "A" System Training Manual Vol. C-210 Douglas Point N.G.S. System Training Manual Vol. C-211 Douglas Point N.G.S. System Training Manual Vol. C-212 Douglas Point N.G.S. System Training Manual Vol. C-213 Douglas Point N.G.S. System Training Manual Vol. C-21* Douglas Point N.G.S. System Training Manual Vol. C-215 Douglas Point N.G.S. System Training Manual Vol. C-216 NPD G.S. System Training Manual Vol. C-217 NPD G.S. System Training Manual

Reports Requested By The Select Committee • Controlled Access Vat. Report No. Number Title

C-212 78151 A Safety-Reliability Assessment of Emergency Power Supply (EPS) System, Bruce GS B 74075 Aircraft Strikes at Bruce 74440 Aircraft Strikes at Bruce GS 74074 Aircraft Strikes at Pickering GS B 74281 Aircraft Strikes at Pickering GS 74320 Boiler Feëdwater System Reliability of Bruce B GS - E/37 -

C-219 78227 Bruce GS A Probability of a Cl IV Power Failure Following a Loss of Coolant Accident

79004 Bruce GS B Safety-Reliability Assessment of Emergency Power Supply (EPS) System

7*305 Control Centre Complex Large Object Penetration 78330 Pickering GS B Consequences After a Loss-of- Coolant Accident with Vacuum, Dousing or Pressure Relief Valves Unavailable 79107 Pickering GS B Power Transient Following Loss of Coolant with only one Shutdown System Assumed Available 78213 Pickering GS B Secondary Side Loss of Coolant Analysis 75275 Pipe Ruptures in Primary Heat Transport System Distribution List Bruce GS 76265 Postulated Loss of Collant Accidents in NA44 Airlock Impairment Assessment 76263 Postulated Loss of Coolant plus Loss of Dousing Accidents Assessment NA44 76264 Postulated Loss of Coolant plus Loss of Vacuum Accidents Assessment NA44

C-220 77201 Primary Heat Transport System IQC Reliability of Pickering B G5 75162 Turbine Generators Fires - Nuclear Safety Aspects 74055 Turbogenerator Missiles at Pickering GS 76044 Turbogenerator Missiles at Bruce GS Supplement CNS-IR-211-2 Review of the Pickering GS Containment System Under Accident Conditions CNS-IR-411-3 Reliability Analysis of the Turbine Generator Overspeed Protection System at NPD NGS RMEP-IR-015-6 Pickering NGS A Long Term Post-Loca Releases RMEP-IR-015-8 Long Term Releases of Fission Products from Containment at Bruce NGS A foiowing postulated Loss of Coolant Accidents APPENDIX F CORRESPONDENCE BETWEEN AECL-AECB-ONTARIO HYDRO SUBMITTED TO THE LEGISLATIVE LIBRARY FOR THE PURPOSES OF, AND USE BY, THE PUBUC AND THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS APPENDIX F

CORRESPONDENCE BETWEEN AECL - AECB - ONTARIO HYDRO

SUBMITTED TO THE LEGISLATIVE LIBRARY

FOR THE PURPOSES OF, AND USE BY,

THE PUBLIC AND

THE SELECT COMMITTEE ON ONTARIO HYDRO AFFAIRS

Volume AECL-1 Correspondence between AECL - AECB - Ontario Hydro relating to no significant fuel failures, loss of coolant accidents and emergency core cooling at Nuclear Power Demonstration Generating Station from July 13, 1976.

Volume AECL-2 Douglas Point correspondence between 3uly 16th, 1976 and April 7th, 1978.

Volume AECL-3 Douglas Point correspondence between April 13th, 1978 and January 16th, 1979.

Volume AECL-* Douglas Point correspondence between January 16th, 1979 and September 25th, 1979. APPENDIX G UST OF RECOMMENDATIONS APPENDIX G

LIST OF RECOMMENDATIONS

RECOMMENDATION 1 ONTARIO HYDRO SHOULD CONTINUE TO PROVIDE PUBLIC ACCESS TO ALL OF THE INFORMATION MADE AVAILABLE TO THE COMMITTEE BY KEEPING THE REPORTS NOW AVAILABLE IN THE LEGISLATIVE LIBRARY REGULARLY UPDATED AND CURRENT.

RECOMMENDATION U ONTARIO HYDRO SHOULD IMMEDIATELY ADVISE THE LEGISLATIVE ASSEMBLY, THROUGH THE MINISTER OF ENERGY, OF ANY DECISION, OCCURRENCE OR DESIGN REANALYS1S WHICH MIGHT BE OF PARTICULAR INTEREST OR CONCERN TO THE PUBLIC.

RECOMMENDATION III A COUNCIL SHOULD BE FORMED BY THE GOVERNMENT OF ONTARIO WITH GIVEN TERMS OF REFERENCE AND REPRESENTATION FROM WITHIN AND OUTSIDE THE NUCLEAR ESTABLISHMENT TO PROVIDE AN INSTITUTIONAL FORUM FOR PUBUC PARTICIPATION AND A FOCUS FOR CONCERNS ABOUT RADIATION PROBLEMS IN ONTARIO, TO BUILD UP ONTARIO-BASED TECHNICAL KNOWLEDGE AND TO OVERSEE AS MUCH EPIDEMIOLOGICAL WORK AS IS NECESSARY TO DECIDE WHAT THE STANDARDS SHOULD BE FOR THE HEALTH AND SAFETY OF PEOPLE IN ONTARIO.

THE COUNCIL SHOULD REVIEW PARTICULAR PROBLEMS OF RADIATION ASSOCIATED WITH OPERATING OR PLANNED REACTORS, INDEPENDENT OF ONTARIO HYDRO AND THE GOVERNMENT. THE COUNCIL SHOULD WORK TOWARD THE ESTABLISHMENT OF A FEDERAL- PROVINCIAL WORKING GROUP TO CO- ORDINATE THE NATIONAL STANDARDS WITH THE WORK AND FINDINGS OF THE PROVINCIAL GROUP. THE POWERS OF THE COUNCIL SHOULD BE THAT OF MAKING INDEPENDENT AND PUBLIC RECOMMENDATIONS TO AN APPROPRIATE MINISTER.

RECOMMENDATION IV ONE OF THE FIRST TASKS THE COUNCIL SHOULD TAKE ON AND GIVE HIGH PRIORITY TO IS AN INDEPENDENT REVIEW OF THE ADEQUACY OF CURRENT PROPOSED RELEASE LIMITS FOR CARBON-14 AND TRITIUM, TAKING INTO ACCOUNT BOTH LOCAL AND GLOBAL CONCERNS. -G/2-

REC0MMENDAT10N V ONTARIO HYDRO SHOULD ENSURE THAT THE NUCLEAR INTEGRITY REVIEW PANEL REPORTS ANNUALLY ON ITS ACTIVITIES TO IMPROVE THE RELIABILITY, EFFECTIVENESS AND INDEPENDENCE OF NUCLEAR SYSTEMS, HIGH- LIGHTING CONCLUSIONS OF COMPLETED PROJECTS AND PROBLEMS UNDER ACTIVE STUDY. SUCH A REPORT SHOULD BE MADE AVAILABLE TO THE PUBLIC FROM ONTARIO HYDRO AND AT ALL INFORMATION CENTRES AND SHOULD BE TABLED IN THE LEGISLATIVE ASSEMBLY BY THE MINISTER RESPONSIBLE FOR ONTARIO HYDRO.

RECOMMENDATION VI THE AECB IN ITS ANNUAL REPORT SHOULD REVIEW AND COMMENT ON REPORTED UNAVAILABILITY OF SYSTEMS IN NUCLEAR POWER PLANTS AND SHOULD 5UMMARIZE THE ACTIVITIES OF ITS COMPLIANCE BRANCH.

RECOMMENDATION VU HYDRO SHOULD UNDERTAKE A COMPREHENSIVE REVIEW OF PROCESSES FOR DEALING WITH HUMAN RESOURCES TO IMPROVE THE ORGANIZATIONAL CLIMATE AND THE FUNCTIONING OF THOSE PARTS OF THE ORGANIZATION THAT DEAL WITH THE SPECIAL PROBLEMS OF NUCLEAR POWER.

RECOMMENDATION VOI HYDRO SHOULD TIGHTEN ITS SYSTEM FOR MANAGING THE FOLLOW-UP TO SIGNIFICANT EVENTS IN ORDER TO ENSURE THAT APPROPRIATE REMEDIAL ACTION RESULTS, THAT EVENTS ARE CLASSIFIED BY TYPE AND/OR COMPONENT AND THAT EVENTS ARE CROSS-REFERENCED TO OTHER PLANTS IN A MANNER WHICH CAN BE TRACED THROUGH THE REPORTING SYSTEM.

RECOMMENDATION IX ONTARIO HYDRO SHOULD ENSURE THAT A COMPLETE ENGINEERING REVIEW OF THE NPD STATION IN ITS MODIFIED STATE IS UNDERTAKEN AS A BASIS FOR A NEW FINAL HAZARDS REPORT THAT REFLECTS BOTH THE PLANT MODIFICATIONS AND THE MOST CURRENT RESEARCH INFORMATION. AFTER AECB REVIEW AND APPROVAL THE REPORT SHOULD BE PRINTED WITHIN TWELVE MONTHS AS A NEW SAFETY REPORT AVAILABLE FOR PUBLIC SCRUTINY. -G/3-

RECOMMENOATION X THE AECB SHOULD COMMISSION A STUDY TO ANALYZE THE LIKELIHOOD AND CONSEQUENCES OF A CATASTROPHIC ACCIDENT IN A CANDU REACTOR. THE STUDY SHOULD BE DIRECTED BY RECOGNIZED EXPERTS OUTSIDE THE AECB, AECL AND ONTARIO HYDRO. IT SHOULD BE FUNDED BY A SPECIAL GRANT FROM THE FEDERAL GOVERNMENT. IF THIS STUDY IS NOT COMMISSIONED BY JULY 31, 1980, THE PROVINCE OF ONTARIO SHOULD ENSURE THAT IT IS UNDERTAKEN.

RECOMMENDATION XI THE AECB SHOULD MAKE SIGNIFICANTLY MORE SPECIFIC ITS OWN CURRENT CRITERIA FOR BOTH SINGLE AND DUAL FAILURE ACCIDENTS AS WELL AS FOR MINIMIZING THE PROBABILITY OF A CATASTROPHIC ACCIDENT, INCORPORATING WHERE APPROPRIATE, THE TIGHTENING IMPLICIT IN THE REPORT OF THE INTER-ORGANIZATIONAL WORKING GROUP (IOWG). RECOMMENDATION XII THE GOVERNMENT OF ONTARIO SHOULD PUBLICLY URGE THE FEDERAL GOVERNMENT TO ENSURE THAT THE AECB IS ADEQUATELY FUNDED, PARTICULARLY IN LIGHT OF THE SIGNIFICANCE OF ITS CURRENT AND ONGOING WORK AND THE PUBLIC TRUST IT MUST FULFILL.

RECOMMENDATION XIII THE AECB SHOULD SET OUT A SPECIFIC TIMETABLE FOR THE RECEIPT AND APPROVAL OF DOCUMENTS AT EACH STEP IN THE LICENSING PROCESS. RECOMMENDATION XIV THE AECB SHOULD DEFINE AS CLEARLY AS POSSIBLE THE KEY PHRASES, SUCH AS "REQUEST" OR "ORDER" THAT FORM PART OF THE ON-GOING COMMUNICATION WITH THE LICENSEE AND SHOULD TELL THE LICENSEE EXACTLY WHAT AUTHORITIES HAVE BEEN GRANTED TO STAFF MEMBERS.

RECOMMENDATION XV THE AECB SHOULD, AS A MATTER OF ROUTINE, BRING DEBATES WITH A LICENSEE TO A FIRM CONCLUSION BY INDICATING, AT THE APPROPRIATE TIME, THE BOARD'S DECISION AND THE REASONS THEREFORE. WHERE THE BOARD IS NOT YET IN A POSITION TO MAKE A DECISION IT SHOULD PLACE AN APPROPRIATE TIME CONSTRAINT ON THE DURATION OF UNRESOLVED DISAGREEMENTS RELATING TO VITAL SAFETY MATTERS. -G/*-

RECOMMENDATION XVI THE BOARD SHOULD SET OUT THE FUNDAMENTAL REQUIREMENTS FOR THE CRITICAL SYSTEMS IN A NUCLEAR PLANT - PROCESS SYSTEMS, EMERGENCY COOLING SYSTEMS AND CONTAINMENT SYSTEMS -AND THE WAYS IN WHICH ACCIDENT ANALYSIS MUST BE DONE TO SATISFY THE REQUIREMENTS.

RECOMMENDATION XVII THE BOARD SHOULD SPECIFY THE ROUTINE REQUIREMENTS OF ITS OWN ON-S1TE INSPECTORS, DEVELOP APPROPRIATE DAY- TO-DAY OPERATIONAL AUDITING ROUTINES AND BEGIN A REGULAR SYSTEM OF INSPECTION REPORTS.

RECOMMENDATION XVIII THE AECB SHOULD STRIVE TO ADOPT THE MOST OPEN AND PUBLIC POSITION POSSIBLE BY BROADLY INTERPRETING ITS CURRENT LEGISLATION.

RECOMMENDATION XIX THE AECB SHOULD BROADEN ITS MEMBERSHIP TO INCLUDE REPRESENTATION FROM THE GENERAL PUBLIC AS WELL AS THE INFORMED TECHNICAL COMMUNITY.

RECOMMENDATION XX THE AECB SHOULD SEEK AN INCREASE IN ITS FUNDING TO ENABLE IT TO INCREASE ITS CONTRACTING FOR INDEPENDENT OUTSIDE RESEARCH INTO MATTERS OF NUCLEAR SAFETY.

RECOMMENDATION XXI THE AECB SHOULD REPORT TO THE HOUSE OF COMMONS THROUGH A MINISTER OTHER THAN THE MINISTER RESPONSIBLE FOR AECL.

RECOMMENDATION XXII THE AECB SHOULD MAKE ITS PROCEEDINGS OF DECISION MORE WIDELY KNOWN. ITS MEETINGS SHOULD BE OPEN TO THE PUBLIC UNLESS THERE IS A REASON FOR KEEPING ONE CLOSED.

RECOMMENDATION XXfll THE AECB SHOULD WORK WITH ITS LICENSEES TO ENSURE THAT DOCUMENTS MADE AVAILABLE TO THE PUBLIC ARE, TO THE GREATEST EXTENT POSSIBLE, ACCURATE, COMPLETE AND COMPREHENSIBLE. -G/5-

RECOMMENDATION XXIV THE RULES UNDER WHICH THE BOARD OPERATES, INCLUDING SPECIFIC LICENSING CRITERIA, SHOULD BE THE SUBJECT OF PUBLIC HEARINGS W HEN FORMULATED OR CHANGED. THE AECB SHOULD HAVE GENERAL POWERS OF INTERPRETATION AND THE POWER TO GRi\NT EXEMPTIONS. INTERPRETATIONS AND EXEMPTIONS MUST, HOWEVER, BE PUBLICLY EXPLAINED IN A TIMELY MANNER IN THE BOARD'S REASONS FOR A PARTICULAR DECISION.