Cultural and Natural Heritage Protection and Development Project Procurement Plan

Project Name: Guizhou Cultural and Natural Heritage Protection and Development Project PPMO: Guizhou Cultural and Natural Heritage Protection and Development Project Management Office (Add.: 5/F, No. 90, Feishan Street, , 550001, Public Disclosure Authorized Guizhou, Tel: 0851-6820750) PPMO: Cultural and Natural Heritage Protection and Development Project Management Office (Add.: Anshun Tourism Bureau, Anshun Municipality Government Yard, 561000, Guizhou, Tel: 0853-3527636) PPMO: Qiandongnan Prefecture Cultural and Natural Heritage Protection and Development Project Management Office (Add.: Qiandongnan Prefecture Tourism Bureau, Yingpan Road, Kaili 556000, Guizhou, Tel: 0855-8230912) PPMO: Qianxinan Prefecture Cultural and Natural Heritage Protection and Development Project Management Office (Add.: Qianxinan Prefecture Tourism Bureau, Beijing Road, Xingyi 562400, Guizhou, Tel: 0859-3113898) PPMO: Guizhou Normal University Cultural and Natural Heritage Protection and Development Project Management Office (Add.: No.116, Baoshan South Road, Guiyang 550001, Guizhou, Tel: 0851-6702119) Amounts of Loan: USD60, 000,000 Public Disclosure Authorized The objective of the Project is to assist Guizhou Province in increasing economic benefits to local communities (including, minority groups) through increased tourism and better protection of cultural and natural heritages.

1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date 1. Anshun 1.1 Anshun Tianlong Tunbao Cultural Heritage Protection Project Construction of infrastructure

Public Disclosure Authorized facilities and buildings, including: ASTL/ Tunbao Culture Museum (540 m2); Civil 512.3 3,500 438.5 2,996 NCB Post 4/2010 12 C1 Information Center in Cherry works Blossoms Garden (600m2) ; drainage (4km)

1 Public Disclosure Authorized 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date Restoration of Anshun TianLong traditional private houses: Community ASTL/ Block demonstrative private house ( 6 585.5 4,000 430 2,938 Participation- Post 1/2010 10 C2 Grants households ) , traditional private Force Account houses(65 households) ASTL/ Training Training and Study (many times) 9.1 62 9.1 62 SOE Post 6/2010 24 C3 and study 1.2 Anshun Jiuzhou Tunbao Cultural Heritage Protection Project Construction for public and historical buildings, including: Tourists Information Center (500m2); museum (2000m2) and rehabilitation of Catholic Church (3100m2);Qingyuan Palace (650 m2), Guanyue Temple (300 m2), Wanshou Palace (350 m2) ASJZ/C Civil Construction of local infrastructure 2,634.6 18,000 2,400.5 16,400 NCB Prior 5/2010 24 1 including: parking place (3020m2), works pedestrian roads (4.2km), drainage pipe (1km), garbage disposal station (160m2) , public toilets(6), river training works, indication signature boards (120), cultural explanation signature boards (120, rubbish bin(80) Private Houses Protection: Community ASJZ/C traditional private houses(88 ), Block 439.1 3,000 449 3,068 Participation- Post 4/2011 12 2 demonstrative residential houses Grants Force Account (5) ASJZ/C Training Training and Study (many times) 29.9 204 29.8 204 SOE Post 6/2010 24 3 and study 1.3 Guanlin National Geo-Park Heritage Protection Project Retroactive finance: parking lot Prior ASGL/ Civil retroactive (36 car-park space), the exhibiting 658.7 4,500 599 4,092 NCB (Finish 11/2009 12 C1 works financing excavated site (2000 m2), tourist ed)

2 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date service center (2539 m2), Visitors' break room (360 m2) Construction of the Shastasauridae Park and affiliated facilities, including in situ demonstration facility (450m2), the theme hall of the demonstrative facility and ASGL/ Civil afforestation of the whole park, 4,244.7 29,000 3,470.2 23,709 NCB Prior 09/2010 30 C2 science research center (1000 works m2),public toilet, garbage transfer station, indication sign boards (35), culture interpretation sign boards (35) ,rubbish bin(10) ASGL/ Training Training and Study (many times) 42.6 291 42.6 291 SOE Post 06/2010 24 C3 and study 2 Qiandongnan Congjiang Miao &Dong Ethnic Village Cultural Heritage Protection 2.1 Project Basha Miao Ethnic Village Cultural Heritage Protection: Construction of local public building and infrastructure facilities including: pedestrian roads (12km) and ecological walking path (4km), Parking lot QDNBS ( 4000m2 ) , drainage channel Civil 1,024.6 7,000 899.4 6,145 NCB Post 4/2010 18 /C1 (3km), fire-fighting pools(5), fire works hydrants(15 sets),rubbish bin (60), rubbish pools(3), public toilets(3), afforestation ( 1000m2 ) , Miao cultural heritage center (300 m2), indication sign boards (200) as well as cultural interpretation sign boards (200). QDNBS Protection of traditional Miao Block Community 102.5 700 102 697 Post 3/2010 18 /C2 ethnical residential house ( 80 Grants Participation-

3 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date households ) , demonstrative Force Account private house (5 households) 2.2 Duliujiang Dong Ethnic Cultural Heritage Protection Project Construction of local infrastructure facilities in Xiaohuang Dong Village including: walking path, maintenance of the village roads, Parking lot (1500 m2), drainage channel (4000m), sewage treatment (600 m3), fire hydrant pool (200 m3), fire hydrant (30 QDND sets), rubbish bin (50), garbage Civil 1,390.5 9,500 1,235.5 8,441 NCB Post 4/2010 18 L/C1.1 transfer station (100m2), river works treatment for the Dong songs performance on the water (2.5 km), the environment improvement of pool, affroestation, traditional cultural heritage center (1000 m2) , indicative sign boards and traditional cultural interpretation sign boards ( 100 sets) Construction of local infrastructure facilities in ZengChong Dong Village including: maintenance of the village roads, Parking lot (800 m2), reservoir (300 m3),drainage channel (3200m), sewage treatment (200 m3), fire hydrant QDND pool(200 m3), fire hydrant and fire Civil 1,097.8 7,500 959.8 6,557 NCB Post 4/2010 18 L/C1.2 hose (30 sets ), rubbish bin ( 40), works the environment improvement of pool, construction technique heritage center, the protection of outdoor sing hall and traditional wind and rain bridge, indicative sign boards and traditional cultural interpretation sign boards ( 100 4 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date sets).

Community QDND Residences Houses Protection(60 Block 117.1 800 117 799 participation- Post 3/2010 18 L/C2 Grants households )in XiaoHuang Force Account Community QDND Residences Houses Protection (10 Block 29.3 200 29 198 participation- Post 3/2011 18 L/C3 country inn) in Zengchong Grants Force Account QDND Training Training and Study (many times) 35.1 240 35.1 240 SOE Post 6/2010 24 L/C4 and study 2.3 Shiqiao Village Handmade Paper Skill Protection Project, Danzhai Construction of local infrastructure facilities including: parking lot (800 m2), walking path (2.5km), water supplying pipe (2000m), drainage channel (1600m), sewage treatment (200 m3), fire hydrant (25 sets), rubbish bin (50) , rubbish QDND pool, public toilet, river treatment, Civil 761.1 5,200 692.1 4,728 NCB Post 4/2010 24 Z/C1 improvement of the village works environment, the tourism service and information center(150m2), the protection of paper making historic site and restoration of the ancient village door, indication sign boards (50) and cultural heritage sign boards (200) The protection of the paper making Community QDND workshops ( 50) and demonstrative Block 175.6 1,200 176 1,202 Participation- Post 4/2010 24 Z/C2 traditional private house (30 Grants Force Account households) QDND Training Training and Study (many times) 9.2 63 9.2 63 SOE Post 6/2010 24 Z/C3 and study 2.4 Huangping Jiuzhou Ancient Town Heritage Protection Project QDNH Construction of local infrastructure Civil 1,976 13,500 1,762.3 12,040 NCB Post 4/2010 24 P/C1.1 facilities, including: renovation of works

5 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date the ancient residential house in the west street (65households), the house of Zhu’s , “Dayuanfa” residential house, the monument of the mother of Guomoruo, rubbish truck, public toilet, the protection of ancient village gate, garbage transfer station (10 t/d), rubbish bin (100), fire hydrant (120 sets), indication signal system boards (100) as well as heritage interpretation sign boards (200) QDNH Restoration of Tianhou temple and Civil 878.2 6,000 704.2 4,811 NCB Post 12/2010 12 P/C1.2 Catholic Church works QDNH Protection of the ancient river Civil 644 4,400 578.1 3,950 NCB Post 06/2011 12 P/C1.3 embankment and the ancient wharf works QDNH Training Training and Study (many times) 31.9 218 31.9 218 SOE Post 06/2010 24 P/C2 and study 2.5 Yang’asha Miao Ethnic Cultural Heritage Protection Project 1)Construction of the local infrastructurefacilities in ZhanLiu including: walking path in the village (10.8 km), walkway access to village (3.5 km), bridle path (4 km), pedestrian walkway (500m), parking lot (500 m2), Wind-Rain Bridge and rest pavilion , wharf QDNY (500 m2), water supplying pipe Civil 1,902.8 13,000 1,733.7 11,845 NCB Post 05/2010 18 A/C1 (2000m), high level water pool works (200 m3), drainage channel (1000m), sewage treatment (200 m3/d), fire hydrant pool (100 m3 ), fire hydrant (8 sets), fire hose (7), rubbish bin (30), rubbish pool (3), public toilet (3), improvement the environment, afforestation (15000 m2), CaiGu place (800 m2), Dating 6 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date corridor (320 m2), Tin Embroidery heritage center (200 m2),indication sign boards (100), cultural interpretation sign boards (200).

2)Construction of the local infrastructure in WuBao, including: Plank Road (2.5 km), parking lot (2700 m2), water supplying pipe (2500m ), high level water pool (100 m3), drainage channel (500m), sewage treatment (100 m3/d), fire hydrant (8 sets), fire hose ( 8), rubbish bin (40), rubbish pool (3), public toilet (2), the entrance door for WuBao village, wind and rain bridge (4), barn (800 m2), Bull fighting place (1000 m2), the restoration of TuDi shrine , holly tree rest place, Yang’a Sha well and Jianjing pavilion, the improvement environment of QiXing pool, red embroidery culture heritage center (200 m2), souvenir selling center (200 m2) , information center (300 m2), cultural interpretation sign boards (200) ,environment improvement, afforestation (5000 m2). Jianhe ( new county ) : tourists information service and training center (8400 m2), parking lot and QDNY Civil 2 2,634.6 18,000 2,358.9 16,116 NCB Prior 05/2010 21 A/C2 square (2000 m ), water supply works pipe (500m), drainage channel (500m), rubbish bin (20), public toilet (150 m2), garbage transfer

7 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date station (10 t/d), fire fighting equipment and afforestation (1000m2) The renovation of private houses in Community QDNY ZhanLiu (5 households of Block 146.4 1,000 147 1,004 participation- Post 03/2010 18 A/C3 demonstrative houses, 30 Grants Force Account households of traditional houses). The renovation of private house in Community QDNY Block WuBao, 3 households of 117.1 800 117 799 participation- Post 03/2010 18 A/C4 Grants demonstrative houses Force Account QDNY Training Training and Study (many times) 45.8 313 45.8 313 SOE Post 06/2010 24 A/C5 and study 2.6 Jinping Longli Ancient Town Heritage Protection Project Construction of the local infrastructure facilities, including: path (1.2m), drainage system (3000 m), sewage treatment (30 m3/d), fire hydrant pool (100 m2), fire hydrant (20 sets), reconstruction of the city rive, the clean up the river QDNLL cause, city moat, ShuFang bridge, Civil 4,098.3 28,000 3,732.5 25,501 NCB Prior 5/2010 24 /C1 protection of ancient wall, the works improvement environment of LongWu village, HuaZhai village, indication sign boards (200), cultural interpretation sign boards (100), tourist information center (1090 m2), tourists service center (600 m2) Residential house reparation (20 traditional houses and 5 ) QDNLL demonstrative houses , Longbiao Civil 819.7 5,600 736.8 5,034 NCB Post 5/2010 28 /C2 ancient academy, Zhuang Yuan works temple, Zhuang Yuan pavilion, Zhuang Yuan monument, Feishan temple, Guanyu temple, Zhengwu

8 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date temple

QDNLL Training Training and Study (many times) 46.8 320 46.8 320 SOE Post 6/2010 24 /C3 and study 2.7 Bala River Miao Ethnic Cultural Heritage Protection ( Kali area) Construction of the local infrastructure in Jidao Village: walking pass in the village (5 km), the path access to village (300m), parking lot (1200 m2 ), wind and rain bridge, water supplying pipe (2000m), reservoir (300 m3), QDNB drainage channel (2200m), sewage Civil 570.8 3,900 507.2 3,465 NCB Post 4/2010 18 K/C1.1 treatment (100 m3/d), rubbish pool works (5 m3), rubbish bin (20), fire hydrant pool (4), public toilet (3 ), Barn, Cultural and information Communication Center (600 m2), indication sign boards (200), and cultural interpretation sign boards (100) Construction of the local infrastructure in Huai Enbao Village: walking pass in the QDNB village (2500m), parking lot (1200 Civil 292.7 2,000 242.4 1,656 NCB Post 4/2010 18 K/C1.2 m2), drainage channel (3200m), works sewage treatment (100 m3/d), rubbish pool (5 m3), fire hydrant pool (4), public toilet (1) Construction of the infrastructure facilities in Nanhua Village: path (17km), parking lot (1600 m2), QDNB drainage channel (4200m), sewage Civil 761.1 5,200 681.3 4,655 NCB Post 4/2010 12 K/C2 treatment (150 m3/d), 5 fire works hydrant pools, rubbish pool, public toilet, NanHua tourism service center (600 m2), Bala river

9 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date information center in San Keshu, Ba La River signage. The reparation of JiDao residential house (5000 ㎡ ), protection of Community QDNB hundred years old granary (300 Block 512.3 3,500 519 3,546 Participation- Post 5/2010 12 K/C3 ㎡ Grants ), demonstrative households of Force Account rural tourism (5), family tavern( 30 beds of guesthouse) The renovation of HuaiEnBao Community QDNB Block residential house (20 households, 29.3 200 29 198 Participation- Post 5/2010 12 K/C4 Grants 3000 ㎡) Force Account QDNB Training Training and Study (many times) 20.9 143 21 143 SOE Post 6/2010 24 K/C5 and study Bala River Miao Ethnic Cultural Heritage Protection and 2.8 informationization Project (Leishan area) 2.8.1 Bala River Miao Ethnic Cultural Heritage Protection (Leishan area) Construction of the local infrastructure in Langde upper QDNB Village including :walking path Civil 409.8 2,800 528.4 3,610 NCB Post 4/2010 12 L/C1 (1.6km), parking place (1000m2), works public toilet (150m2), information center. LeiShan cultural display center and QDNB Civil Information center as well as 585.5 4,000 595.2 4,066 NCB Post 4/2010 24 L/C2 works training center Community QDNB The restoration of ancient private Block 117.1 800 117 799 participation- Post 4/2010 24 L/C3 houses(35 households,1660 m2) Grants Force Account 2.8.2 Xijiang Miao Ethnic Cultural Heritage Protection Construction of the local infrastructure including: walking QDNXJ path around the village (35km), 2 Civil 819.7 5,600 1,212.4 8,283 NCB post 4/2010 12 /C1 parking lots (4600 m2),2 public works toilets(200m2), 2 tourists information centers (2000 m2), 2

10 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date village entrance doors

Private house protection in XiJiang Community QDNXJ ( 208 households traditional Block 541.6 3,700 544 3,717 Participation- post 6/2010 24 /C2 private houses, 5 demonstrative Grants Force Account private houses) QDNXJ Training Training and Study (many times) 31.8 217 31.8 217 SOE post 6/2010 24 /C3 and study 2.9 Zhaoxing Dong Ethnic Cultural Heritage Protection () Construction of infrastructure in XiaGe village, including: path (4km), road link from DaWan to XiaGe (1km), parking lot (800 m2), village entrance door(1), fire hydrant pool (150 m2), fire hydrant (20 sets), machine fire pump(3), water supplying station (480 m3), QDNZ water service pipe Civil 629.4 4,300 572.3 3,910 NCB Post 6/2010 18 X/C1.1 ( 3km ) ,drainage channel works (2700m), sewage treatment (200 m3/d), rubbish bin (50), rubbish pool (1), public toilet (2,20squatting places),medical station (300 m2), the improvement of pools(10), indication sign boards (8)and cultural heritage sign boards (2). Construction of infrastructure in Tang’An village, including: walking pass (3km), parking lot (800 m2), village entrance door(1), QDNZ 3 Civil fire hydrant pool (100 m ), fire 453.7 3,100 412.1 2,816 NCB Post 2/2012 18 X/C1.2 hydrant (20 sets), machine fire works pump (2), water supplying station ( 480 m3), water supply pipe ( 3km ) ,drainage channel

11 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date (2700m), sewage treatment (200 m3/d), public toilet (2, 20squatting places),rubbish bin (50), rubbish pool (1 pools,), medical station (300m2)and administrative room (300m2). Construction of infrastructure in Zhaoxing village including: main streets (1.2km), walking path (8km), walk path (50 km), biological protection of river embankment (4.7 km), water QDNZ supplying station ( 1000 m3), Civil 1,610 11,000 1,418.4 9,691 NCB Post 2/2012 18 X/C1.3 drainage channel (4.5km), fire works hydrant pool (5), fire hydrant (40 sets), machine fire pump (5), rubbish bin (150), rubbish pool (2 pools), tourist service center(700 m2),renovation of drum tower and flower bridge(1). Renovation of traditional houses in Community QDNZ Block Zhaoxing ( 6 demonstrative 365.9 2,500 357 2,439 participation- Post 6/2010 18 X/C2 Grants households, 100 traditional houses) Force Account Renovation of traditional houses in Community QDNZ Block Tang’An (30 traditional houses, 175.6 1,200 176 1,202 participation- Post 6/2010 18 X/C3 Grants 6000 ㎡) Force Account Renovation of traditional civilian Community QDNZ Block houses in XiaGe (20 traditional 41 280 41 280 participation- Post 6/2010 18 X/C4 Grants civilian houses, 4000 ㎡) Force Account The Information Center in LiPing county, including the parking lot, and square (2000m2), water supply QDNZ pipe (500m), drainage channel Civil 1,097.8 7,500 1,010.8 6,906 NCB Post 3/2010 21 X/C5 (500m), rubbish bin (20), pubic works toilet (150 m2) , rubbish transfer station (10 t/d), planting trees (1000m2)

12 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date QDNZ Training Training and Study (many times) 42.2 288 42.1 288 SOE Post 6/2010 24 X/C6 and study 2.10 Shibing Shanmu River Cultural and Natural Heritage Protection Project Liangcha river administrative room, Jiangjiatian administrative room, walking path (8km), wharf(Liangcha river), 2 Parking lots, wind and rain bridge at Niejiayan, walking bridge at LiangCha river, entrance road at Niejiayan parking lot (240m) , Jiangjiatian scenery bridge, 3 water supplying stations ( Jiangjiatian, Liangcha river, Niejiayan ) , QDNS drainage channe ( 2000m at Civil 2,122.3 14,500 1,508.7 10,308 NCB Prior 6/2010 18 M/C1.1 Jiangjiatian, 2000m at Liangcha works river, 2000m at Niejiayan ) , sewage treatment (100 m3/d in JiangjiaTian, 50 m3/d at Liangcha river, 120 m3/d at Niejiayan ) , rubbish bin (400), 2 garbage transport stations, 3 Public Toilets , indication sign boards (200), construction of barbecue stalls along Shan Mu River, Luojiatian sightseeing bus driver’s Administrative room(200 m2) Electronic monitory system, Securing system (including alarm QDNS telephone, armamentarium, Civil 409.8 2,800 370 2,528 NCB Post 6/2010 12 M/C1.2 broadcasting system hydrological works monitoring system and intercom system) Protection of Niejiayan traditional Community QDNS Block traditional dwelling house (10 307.4 2,100 309 2,111 participation- Post 6/2010 12 M/C2 Grants households ) Force Account 13 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date QDNS Training Training and Study (many times) 23.1 158 23.1 158 SOE Post 6/2010 24 M/C3 and study 2.11 Shidong Miao Ethnic Cultural Heritage Protection (Taijiang County) Parking lot (800m2),walking path (5km), water supplying pipe (6000m), drainage channel (5500m), sewage treatment(200 m3/d), fire hydrant pool (1,including 2 machine fire QDNS Civil pump ), fire hydrant (20 sets), 1,976 13,500 1,762.5 12,042 NCB Post 5/2010 18 D/C1.1 works rubbish bin (100), garbage transport station (10t/d), river bank protection, (2.5km), Miao ethnic art display center (900 m2), 3 public toilets, heritage interpretation sign boards (200). the protection of the ancient architecture, including Lianghu QDNS gathering hall, Shu Yuanchun Civil 512.3 3,500 451.2 3,083 NCB Post 5/2011 18 D/C1.2 mansion, ZhangBoxiu works mansion ,Liu Family ancestor’s temple Residential Protection ( 5 Community QDNS Block households in TangLong village, 5 29.3 200 29 198 participation- Post 5/2010 18 D/C2 Grants households in TangBa village) Force Account QDNS Training Training and Study (many times) 23.6 161 23.5 161 SOE Post 6/2011 24 D/C3 and study 2.12 Sanmentang Dong Ethnic Cultural Heritage Protection (Tianzhu county) Construction of infrastructure including: fire hydrant (20 sets) fire hose (20), 2 machine fire QDNST fighting pumps, rubbish bin (50), Civil 1,463.7 10,000 1,224.6 8,367 NCB Post 4/2010 24 /C1 rubbish pool (6 m3), 3 public works toilets, the protection and restoration of Liu’s ancestor temple (1168 m2), protection of 14 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date ancient steles and ancient wharves, flood-prevention dikes, ethnic culture and performance place (900m2), Maintenance of the residential Community QDNST Block house in SanMenTang (28 96.6 660 97 663 participation- Post 4/2010 24 /C2 Grants households) Force Account QDNST Training Training and Study (many times) 13.9 95 13.9 95 SOE Post 6/2010 24 /C3 and study 2.13 The Training and Promotion of Qiandongnan Minority Cultural Tourism Promotion and Project Operation of Qiandongnan Ethnic Minority ——Tourism propagate promotion Consulta 3-10 /2010 QDNZJ ——Training for Community and nts’ 585.5 4,000 600 4,099 QBS Prior -2012 8×3 /C1 administrative units Services ——Publication of Ethnic Minority Culture QDNZJ Purchasing vehicles (1) Goods 43.9 300 80 547 Shopping Post 4/2010 1 /G2 3 Qianxinan Xingyi Natural Geographical Park Dingxiao Guizhou Dinosaur Heritage 3.1 Protection Project Construction of Guizhou Dragon QXNX Civil Fossil Museum and Square 2,341.9 16,000 2,117.5 14,467 NCB Prior 4/2010 36 Y/C1 works (10,000m2) Training QXNX Training and Study (many times) and 22.2 152 22.2 152 SOE Post 6/2010 24 Y/C2 Study 3.2 Wanfenglin Scenic Area Cultural and Natural Heritage Protection Project Walking path along Nahui River (50km), the bridge over Nahui QXNW River, extend Xifenglin Square Civil 3,293.3 22,500 2,985.7 20,399 NCB Prior 8/2010 36 F/C1.1 (parking lot), the symbol entrance works door and Luoshuitianken view point construction, Water Supply

15 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date Project, drainage project, 3 Public Toilets, garbage station, walking path, dam construction, the environment protection of village, the protection of ancient trees, rubbish bins, sewage pipe system, Buyi cultural center and holly tree TiaoHua place (building 2600 m2, reconstruction 2000 m 2), tourist information center. The improvement of in Xianahui Village environment : 1)Renovation and protection of hundred years old residential QXNW Civil houses in a way of local technical 585.5 4,000 519.5 3,549 NCB Post 8/2010 36 F/C1.2 Works (8households). 2)maintenance of the residential house (60 households) 3)3 residential house WanFengLin Hiking and mountain bicycling experience system including: main rest station(occupying 450 ㎡×5), rest station(150 ㎡ ×20), camping facilities(10×5000 ㎡), hiking path QXNW Civil , 3,073.7 21,000 2,730.4 18,654 NCB Prior 8/2010 36 F/C2 and bicycle road(L=250km Works W=0.8—1.5m , wooden frame and aluminum sheet indication board 3500), sight seeing platform, the protection of the environment in the scenic area(7, afforestation 15000 ㎡) Training QXNW Training and Study (many times) and 65.3 446 65.3 446 SOE Post 6/2010 24 F/C3 Study (Zhenfeng) Nachan Buyi Ethnic Cultural and Natural Heritage Protection 3.3 Project 16 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date Construction of Buyi Cultural Center (2500 m2),Public Toilet, QXNN Civil walking path(3.5km), dam, village 1,390.5 9,500 1,232.7 8,422 NCB Post 4/2010 18 C/C1 works sewage system, water supply system, afforestation. Residence Renovation in NaChan Community QXNN (130 traditional households, 24000 Block 585.5 4,000 588 4,017 participation- Post 4/2010 24 C/C2 ㎡;20 demonstrative houses, 2000 Grants Force Account ㎡) Training QXNN Training and Study (many times) and 19.3 132 193 132 SOE Post 6/2010 24 C/C3 Study 4 Guizhou Normal University Tourist destination management website of the International Tourism 4.1 Institution of Guizhou Normal University Target information website Research Center ,Training Center, Tourists service Center(17,000 m2,), 17 national characteristic SJSD/C residences, lift, central air- Civil 7,318.4 50,000 6,683.2 45,660 NCB Prior 6/2011 36 1 condition, Fire security works equipments, Power supply, Water supply, CCTV cabling, Telephone Cabling, internet cabling, simple decoration Network devices: Router, Switch, 1000M firewall, Clustering, UPS, special air-con for computer room, professional software, cable rental fee, data server, GIS server, Web SJSD/ server, laptop, GPS, digital camera, Goods 117.1 800 122 834 Shopping Post 2/2012 6 G1 scanner, GIS software, desktop, image software, lens, image workstation, printer, external storage, fax machine, recording pen, DVD burner, KTV software,

17 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date removable white board, photocopy machine, tourism simulation system, multimedia audio network system, projector, Inn management simulation software, tourism finance management simulation software, marketing simulation software, culture heritage and tourism consultant system, and tourism information system. Electronic equipments: Special air-condition for service room, digital video, projector, professional video recording system, monitor, digital recorder, digital special effect switch platform, communication system, PA system, Nonlinear Editing System, lighting system, audio edit system, audio system, LCD, air- conditions, audio devices. Office equipments: Cabinet, SJSD/ Desk, Chair, sofa, fitness Goods 11 75 11 75 Shopping Post 3/2012 3 G2 equipment etc. SJSD/ Vehicle(four): SUV, BPV, coach, Goods 197.6 1,350 200 1,366 Shopping Post 6/2011 3 G3 car Training SJSD/C Training and Study (many times) and 73.5 502 73.5 502 SOE Post 4/2010 24 2 Study Provincial Project(Guizhou 5 Provincial Tourism Bureau ) Capacity Building of Guizhou 5.1 Tuorism SJXM/ 2 vehicles Goods 131.7 900 133 909 Shopping Post 4/2010 2 G1 SJXM/ Official equipments and electric Goods 212.2 1,450 213 1,455 Shopping Post 4/2010 2 G2 equipment as well as project

18 1 2 3 4 5 6 7 8 9 10 Estimated Expected Credit Ceilings Review Contract Ref. Contract Cost Procurement Bid- Type by Duration Comments No. (Description) Method Opening US$ 103 RMB 103 US$ 103 RMB 103 Bank (Month) Date management software

Reviewing and updating of the Consulta SJXM/ Guizhou Tourism Development nts’ 292.7 2,000 300 2,050 QBS Prior 3/2011 18 C1 Master Plan Services SJXM/ Training on tourism at home and Training 314.7 2,150 314 2,145 SOE Prior 4/2010 36 C2 abroad (many times) Project management including bidding documents, design Consulta SJXM/ evaluation, training for staff of nts’ 1,463.7 10,000 1,500 10,248 QCBS Prior 6/2010 36 C3 PMOs and project information Services system Consulta SJXM/ The Fee for Tourist Village Model Retroactive nts’ 197.6 1,350 200 1,366 SSS Prior 1/2010 6 C4 Design Financing Services Incremen SJXM/ tal Incremental Operating Cost 146.4 1,000 150 1,025 SOE Post 4/2010 C5 Operatin g Cost Note: ★ according to the rate on 26th March, 2009, 1 US$ =6.8321RMB. ★ SJXM/C3 is consulting services, total amount of loan is US$1,500,000: PPMO ($700,000) and CPMOs ($800,000). The implementing entity of consulting services is PPMO. ★ SJXM/C4 is The cost for tourist village model design, amounts of loan is $200,000. The cost is apportioned to each PPMO according to their credit line. And the implementing entity of tourist village model design is PPMO.

19 Thresholds for Procurement Methods and Bank Review Requirements ($=USD)

Procurement Methods Bank Review

ICB NCB Shopping QCBS/QBS CQS Prior Post

Works, Supply and >$20 million <$20 million <$300,000 >$2 million <$2million installation

Goods >$1 million <$1 million <$150,000 >$300,000 <$300,000

>$300,000, 1 Consulting firm country not more >$200,000 <$200,000 >$200,000 <$200,000 than 2 shortlist Consulting No prior All post

individual review review

20