Re: Approval of Aboriginal Consultation Plan – Cougar Creek Debris Flood Retention Structure Project

The Aboriginal Consultation Office (ACO) has reviewed the revised Aboriginal Consultation Plan submitted on September 30th, 2015 for the proposed Cougar Creek Debris Flood Retention Structure Project. On the basis of our review we have concluded that the revised Aboriginal Consultation Plan is consistent with the requirements outlined in The Government of Alberta’s Guidelines on Consultation with First Nations on Land and Natural Resource Management for projects requiring an EIA. All consultation activities with First Nations must be carried out in the manner described by the Guidelines and proceed according to the approved Consultation Plan. The ACO may require further consultation based on the receipt of new or additional information at any time during the regulatory approval process.

Pursuant to the Government of Alberta’s First Nations Consultation Policy and Guidelines, the ACO will remain responsible for all substantive aspects of consultation and any procedural aspects not delegated to the proponent. The responsibilities of the ACO include:

• Ensuring potentially affected First Nations receive early and adequate notification regarding the project application(s), • Reviewing and approving the Aboriginal Consultation Plan, • Overseeing the consultation process by evaluating reports submitted by the proponent, and • Assessing adequacy of Aboriginal Consultation and making recommendations to Alberta Environment and Parks.

From October 1st, 2015, every two months following this date, you are required to provide to the ACO (Raila Dollevoet) with a report that outlines all of your First Nations Consultation activities for the proposed project. The ACO also requires that the bi-monthly consultation reports be shared with those First Nations identified in the Consultation Plan.

If you have any questions about the First Nations Consultation process or requirements, please contact Raila Dollevoet at 403-845-8276 or by email at [email protected]

Best Regards,

Raila Dollevoet Consultation Advisor, South Saskatchewan Region Aboriginal Consultation Office Alberta Aboriginal Relations cc:

Meghan Jurijew, EIA coordinator, EAP

Margot trembath, EIA coordinator, EAP

Town of Canmore

Cougar Creek Debris Flood Retention Structure Project

Aboriginal Consultation Plan

September 30, 2015

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 2

Table of Contents

Table of Contents ...... 2 1.0 Introduction ...... 3 2.0 Contact Information ...... 3 3.0 Project Overview ...... 4 4.0 Consultation Requirements ...... 5 5.0 Potential Project Effects on First Nations Rights ...... 5 6.0 Consultation Activities ...... 5 6.1 Project Notification Letter and Information Package for First Nations ...... 6 6.1.1 Content ...... 6 6.1.2 Delivery Methods ...... 6 6.1.3 Process ...... 6 6.2 Terms of Reference ...... 7 6.3 Application Submission ...... 7 6.4 Project Specific Consultation Meetings and Follow-Up ...... 8 6.5 Ongoing Public Consultation Activities ...... 8 7.0 Consultation Contacts ...... 8 8.0 Consultation Schedule ...... 9 9.0 Reporting ...... 11 9.1 Bi-Monthly Consultation Reports ...... 11 9.2 Record of Consultation ...... 12 Appendix A Notification Letter and Information Package ...... 13 Appendix B Public Notification – Proposed Terms of Reference ...... 27

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 3

1.0 Introduction Heavy rains in the in 2013 caused a debris flood on Cougar Creek that resulted in widespread damage to municipal infrastructure, flood protection works, homes, property, businesses, the Trans-Canada Highway, Highway 1a and the Canadian Pacific Railway. Immediately following this flood event, the Town of Canmore (the Town) implemented short-term mitigation measures on Cougar Creek including channel armouring and the installation of a debris net. These short-term mitigation measures were designed to reduce the amount of debris travelling from the watershed onto the alluvial fan and to reduce bank erosion in the creek channel if another flood event occurs prior to the implementation of long-term mitigation plans.

The Town conducted an extensive hazard and risk assessment to identify and analyze options for long-term hazard mitigation on Cougar Creek. Multiple location and design options were evaluated for mitigating debris- flood hazards on Cougar Creek while protecting the Bow Valley Regional Wildlife Corridor, maintaining recreational access and fitting aesthetically with the natural landscape. As a result of this assessment, the Town is proposing to construct a debris-flood retention structure.

The Director responsible for Environmental Assessment has directed that an Environmental Impact Assessment (EIA) Report be prepared for the Cougar Creek Debris Flood Retention Structure (the Project) and this Consultation Plan has been prepared to fulfill requirements for Level 3 extensive consultation for projects requiring an EIA.

2.0 Contact Information

Table 1 Proponent Contact Information

Contact Project Role

Primary Contact Proponent representative and Project Manager. Mr. Félix Camiré, E.I.T. Town of Canmore Engineering Services Primary contact for Project information and consultation activities. 902 7th Avenue Canmore, AB T1W 3K1 Email preferred method of communication. 403.678.1512 [email protected]

Secondary Contact Consultant responsible for consultation plan development and Ms. Rochelle Harding, M.Sc., P.Eng. implementation. Matrix Solutions Inc. Suite 300 150 13th Avenue SW Please copy on all correspondence related to consultation activities. Calgary AB T2R 0V2 403.827.5844 Email preferred method of communication. [email protected]

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 4

Table 2 Government of Alberta Contact Information Contact

ACO Consultation Advisor Raila Dollevoet Consultation Advisor Red Deer/South Saskatchewan Southern Region Aboriginal Relations Box 1720 2nd Floor, Provincial Building 4919 – 51 Street Rocky Mountain House AB T4T 1B3 403.845.8276 [email protected]

Alberta Environment and Parks EIA Coordinator Ms. Meghan Jurijew Environmental Assessment Coordinator Environmental Assessment Environment and Parks Main fl Twin Atria Building 4999 - 98 Avenue Edmonton, AB T6B 2X3 780.643.6853 [email protected]

3.0 Project Overview The proposed Project consists of a debris flood retention structure on Cougar Creek that will be approximately 30 m high and will span a bedrock confined channel. The footprint of the debris flood retention structure is approximately 1.3 ha. For a maximum probable flood scenario the footprint of the inundation area behind the structure would be approximately 6 ha. A 0.5 km maintenance road with a footprint of 0.3 ha is also required. During normal weather conditions water and sediment will flow unimpeded through the structure. During a flood event the structure will be designed to hold back up to 600,000 cubic meters of water and debris with an outlet discharge rate of 45 cubic metres per second. The structure will not permanently hold water and is designed to manage a debris flood over a variety of return period and rainfall duration scenarios. The structure includes a spillway to release water during a major event that is beyond design parameters, during which evacuation procedures would be initiated.

The proposed Project location (LSD 14-34-24-10W5) is at the site of an existing debris net on Cougar Creek, approximately two kilometres northwest of the Trans-Canada Highway. The Project is located within the Bow Valley Wildland Park.

Additional Project details are available in Appendix A – Notification Letter and Information Package. Figure 1 (Appendix A) presents the location of the Project. Figure 2 (Appendix A) presents the location of the Project in relation to Treaty 7 First Nation reserves.

Alberta Environment and Parks (AEP) is pursuing the potential re-classification of a small section of the Project area from a wildland provincial park to a provincial park (conditional on approval of the EIA). First Nations consultation with respect to the potential re-classification is not within the scope of this Consultation Plan. AEP will conduct First Nation consultation and public engagement on the re-classification of this area.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 5

4.0 Consultation Requirements The Project requires an EIA pursuant to the Environmental Protection and Enhancement Act (EPEA) and First Nations consultation is required prior to any Alberta Environment and Parks (AEP) or Natural Resources Conservation Board (NRCB) decisions regarding Project approval.

A Pre-Consultation Assessment was provided by the ACO on August 11, 2015 indicating that all Treaty 7 First Nations will be consulted: • Bearspaw First Nation (Stoney Nakoda); • Chiniki First Nation (Stoney Nakoda); • Wesley First Nation (Stoney Nakoda); • Blood Tribe (Blackfoot); • Piikani Nation (Blackfoot); • Siksika Nation (Blackfoot); and • Tsuut’ina Nation (Sarcee).

5.0 Potential Project Effects on First Nations Rights Recognizing that consultation activities have not been initiated and an EIA has not been completed, the Town of Canmore is not aware of any specific short-or long-term adverse impacts to First Nations rights and traditional uses resulting from the Project. Specifically: • the debris-flood retention structure and flood event inundation area are located in a highly scoured steep mountain creek bed with limited potential for vegetation or wildlife habitat; • the topography and hydrology of Cougar Creek minimize the likelihood of historical features in the debris- flood retention structure and flood event inundation area; • the debris flood retention structure will be designed to maintain access for recreational and traditional activities in Cougar Creek; • the debris flood retention structure will be designed to minimize potential effects on the Bow Valley Regional Wildlife Corridor and wildlife movement up and across Cougar Creek will be maintained; and • Cougar Creek is not a fish bearing waterway and the Project is not expected to alter fish habitat.

6.0 Consultation Activities The Town will conduct consultation activities in accordance with the Government of Alberta’s First Nation Consultation Policy and Guidelines. Prior to submitting any information to First Nations the Town will determine each community’s preferred method of delivery (e.g., email, registered mail, hand delivery).

Specific consultation activities included in this Consultation Plan and described below are: • Project notification letter and information package for First Nations (Section 6.1); • notifications related to the EIA process (Section 6.2 and 6.3), specifically:

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 6

. public notice of the proposed Terms of Reference (TOR) and opportunity to provide input; and . public notice of the EIA report submission, including a description of the process and deadline for submitting Statements of Concern. • Project specific consultation meetings and follow-up with First Nation communities (Section 6.4); • First Nation opportunities to participate in ongoing Town of Canmore public consultation activities (Section 6.5); and • The Town of Canmore will provide bi-monthly reporting and Project updates to both the ACO and First Nations in accordance with the schedule determined by the ACO (Section 9).

6.1 Project Notification Letter and Information Package for First Nations

6.1.1 Content The Town has prepared a draft notification letter and plain language information package (Appendix A) that includes all requirements outlined in the Government of Alberta’s (GOA) Guidelines on Consultation with First Nations on Land and Natural Resource Management (July 28, 2014) and the Proponent Guide to First Nations Consultation Procedures for Land Dispositions1 (February 3, 2015). The notification letter and information package includes: • confirmation that the Town has been notified by the ACO to consult with the First Nation and indicates the level of consultation required; • a description of the consultation process; • a plain language description of the Project including activity, location, and potential impacts (maps and detailed sketches); • a description of the GOA or regulatory approvals being sought; • any information provided by the GOA about potential First Nations concerns in the area (such as known historical or cultural sites); and • a request that the First Nation provide feedback to the Town within the prescribed time period.

6.1.2 Delivery Methods The notification letter and information package will be delivered to the consultation contacts at each First Nation community identified in this Consultation Plan (Section 7) according to the community’s preferred method of delivery (e.g., email, registered mail, hand delivery) and in accordance with ACO delivery verification requirements.

6.1.3 Process As per ACO Level 3 extensive consultation requirements, delivery of the notification letter and information package will initiate the 20 day review period for each First Nation (20 working days beginning on the

1 While no land dispositions pursuant to the Public Lands Act are required for this Project, this guide provides a clear and consistent approach for preparing and implementing Consultation Plans.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 7

Government of Alberta working day following verified receipt of notification). The Town of Canmore will follow-up with each First Nation that has not responded within 10 days and a second follow-up will occur after 15 days from when receipt of notification was received. Subsequent consultation activities will be determined by how each First Nation responds during this 20 day review period: • for First Nations that do not respond during the 20 day period the Town will submit a Record of Consultation (ROC) to those First Nations to review and they will have 10 working days to respond to the ROC; • for First Nations that do provide feedback within the 20 day period, the Town of Canmore will initiate Project specific consultation meetings and follow up as described in Section 6.3; and • for First Nations that provide a Letter of No-Concern (LNC) for the Project the Town of Canmore will document the receipt of the LNC in the ROC for that First Nation to review and they will have 10 working days to respond to the ROC.

6.2 Terms of Reference

The EIA Proposed Terms of Reference (TOR) will be delivered to the consultation contacts at each First Nation identified in this Consultation Plan (Section 7) according to the community’s preferred method of delivery (e.g., email, registered mail, hand delivery) and in accordance with ACO delivery verification requirements.

Public notice for the EIA Proposed TOR (Appendix B) will also be posted in the following publications: • Rocky Mountain Outlook – weekly distribution across the Bow Valley between and Kananaskis; • Alberta Native News – monthly distribution to all First Nation and Inuit communities, Métis Settlements and Friendship Centres in Alberta, Manitoba, Saskatchewan, Northern , Yukon, Nunavut and the Northwest Territories; • Calgary Herald; and • Edmonton Journal. The Public Notice and Proposed TOR will be made available at: • the Town of Canmore Civic Centre (902 7th Avenue Canmore Alberta T1W 3K1) and online at www.canmore.ca; and • Alberta Environment and Park’s Register of Environmental Assessment, 2nd Floor, Petroleum Plaza, South Tower, 9915 – 108 Street, Edmonton, Alberta, T5K 2G8 and online at http://www.esrd.alberta.ca/ea, (choose Current Projects). First Nations may provide feedback on the Proposed TOR directly to AEP as indicated on the published Public Notice or to the Town of Canmore as will be indicated on the covering letter submitted to each consultation contact with the Proposed TOR.

6.3 Application Submission

The Town of Canmore will inform each First Nation community according to the community’s preferred method of delivery (e.g., email, registered mail, hand delivery) and in accordance with ACO delivery verification

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 8

requirements when the Public Notice of Application is posted by AEP. This notification will include information about submission of Statements of Concern, including a deadline.

6.4 Project Specific Consultation Meetings and Follow-Up

For First Nations that express interest in the Project, the Town will schedule a meeting for elected leaders or delegated representatives that will be attended by Town leadership, the Project Manager and technical experts as required to address the concerns and areas of interest identified by the community. These meetings can be held via conference call or in-person as agreed upon with each community. Subsequent meetings will be scheduled to address outstanding issues as required.

Issues and concerns identified by each community will be documented as described in Section 9.1 and follow-up actions will be taken by the Town as required to address First Nation concerns to the extent practical. Bi- monthly consultation and Project update reports will be provided to the ACO and to each interested First Nation throughout the regulatory process.

Project specific concerns raised by any First Nation community with respect to the Project will be addressed through additional consultation efforts that may include meetings or provision of additional information. Consultation efforts made to resolve identified issues will be documented as described in Section 9.

6.5 Ongoing Public Consultation Activities

In addition to activities that are specific to First Nations consultation, the Town continues to engage the public in discussions about this Project on Cougar Creek and about other activities conducted under the broader Mountain Creek Hazard Mitigation Program aimed at mitigating risks at several mountain creeks in Canmore.

First Nations community members may be interested in attending Project open houses, receiving Project newsletters or reviewing information on the Town of Canmore website. The Town will advertise Project open houses on the Town website, in the Rocky Mountain Outlook and on 106.5 Mountain FM. The Town will also inform the community consultation contacts when a Project open house is scheduled.

7.0 Consultation Contacts Consultation contacts (Table 2) were identified using the ACO listing dated April 28, 20152. Consultation contacts and preferred methods of communication will be confirmed prior to delivery of the notification letter and information package to First Nations.

2 http://www.aboriginal.alberta.ca/documents/Treaty7-FNContacts.pdf?0.5589619101956487. Current as of August 11, 2015.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 9

Table 2 Consultation Contacts Community Consultation Contact Preferred Communication Methods Stoney (Bearspaw) Band William (Bill) Snow None indicated – to be determined prior Stoney (Chiniki) Band Stoney Tribal Administration to delivery of proponent notification to Stoney (Wesley) Band PO Box 120 Morely, AB T0L 1N0 First Nations Office: (403) 881-4760 Cell: (587) 580-6212 Email: [email protected]

Blood Tribe Mike Oka None indicated – to be determined prior Consultation Coordinator to delivery of proponent notification to Tribal Government and External Affairs First Nations PO Box 60 Standoff, AB T0L 1Y0 Offic: (403) 737-8236 Cell: (403) 634-6358 Email: [email protected]

Piikani Nation Dustin Wolfe None indicated – to be determined prior Consultation Manager to delivery of proponent notification to PO Box 70 Brocket, AB T0K 0H0 First Nations Office: (403) 965-3940 Email: [email protected] Siksika Nation Richard Right Hand Email and hard copy via mail Consultation Manager Executive Manager’s Office PO Box 1100 Siksika, AB T0J 3W0 Cell: (587) 727-1957 Email: [email protected]

Copy to: Scotty Many Guns Consultation Officer Cell: (587) 437-5188 Email: [email protected]

Tsuut’ina Nation Tonya Crowchild None indicated – to be determined prior Consultation Director Tsuu T’ina Nation to delivery of proponent notification to 9911 Chiila Blvd Tsuu T’ina, AB T2W 6H6 First Nations Office: (403) 238-6403 Email: [email protected]

8.0 Consultation Schedule The following schedule (Table 3) aligns consultation activities with the Town of Canmore’s desired Project schedule. Table 4 describes the consultation activities that will occur during the regulatory process. The Town of Canmore has set an aggressive schedule for this Project as its primary aim is to increase public safety; however, the Town recognizes that meaningful First Nations engagement takes time and that adjustments to this schedule may be required to meet the needs of First Nations communities.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 10

Table 4 Consultation Activities and Timing Consultation Milestone Activities Timing Pre-Consultation Consultation Plan Town of Canmore working with the ACO to develop a Consultation Q2/Q3 2015 Development and Approval Plan for the Project.

Pre-Application Consultation Project Information Packages The Town of Canmore will provide each First Nation with a plain October 2015 language Project Information Package that meets ACO requirements. The Town of Canmore will follow up with each First Nation to October / November confirm community interest in the Project 2015

Proposed Terms of Reference The Town of Canmore will provide each First Nation with a copy of October 2015 the Proposed Terms of Reference (PTOR) that includes information on how the community can provide comment on the PTOR First Nations will have an opportunity to provide comments on the October to December PTOR during the 45-day public review period. 2015

AEP will consider First Nation input into the PTOR December to March 2015

Project Specific Consultation The Town of Canmore will schedule and participate in consultation Ongoing after Meetings and Follow Up meetings with interested First Nations. These meetings will November 2015 Actions include information on the effects assessment conducted by the Town of Canmore and will seek to gather First Nations input into the mitigation of potential project effects.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 11

Table 4 Consultation Activities and Timing Consultation Milestone Activities Timing The Town of Canmore will conduct necessary follow-up actions Ongoing after arising from the consultation meetings (e.g., provision of additional November 2015 information).

The Town of Canmore will provide each First Nation with bi- Ongoing after monthly consultation reports. November 2015

Post-Application Consultation (Application Review) Notification of Submission The Town of Canmore will notify each First Nation when the EIA May 2016 report is submitted and provide access to the EIA report in a format acceptable to each First Nation. This notification will include a description of the process and deadline for submitting Statements of Concern. Project Specific Consultation The Town of Canmore will continue to schedule and participate in Ongoing after Meetings and Follow Up consultation meetings with First Nations who have ongoing November 2015 Actions interest in the Project. These meetings will include discussions on mitigation for potential project effects and accommodation if required. Record of Consultation The Town of Canmore will provide each First Nation with a Record TBD of Consultation for their review at an appropriate time.

9.0 Reporting

9.1 Bi-Monthly Consultation Reports

As required by the ACO, bi-monthly consultation reports will be submitted to First Nations and to the ACO. These bi-monthly reports will be prepared in accordance with the templates provided in the Government of Alberta’s Guidelines on Consultation with First Nations on Land and Natural Resource Management (July 28, 2014) (Tables 5 and 6) and confirmed by the ACO on August 11, 2015. Reporting will also include relevant Project updates as required.

Table 5 Bi-Monthly Reporting Template Date of Proponent Individuals / Method of Summary of Outcomes Follow-Up / Stakeholder Primary Groups Contact Issues Discussed Outstanding Issues Contact Lead/Contact Contacted

Table 6 Specific Issues and Concerns Template Document Specific Project Specific Proponent Response on Effort First Nation Response to or Meeting Concern Aspect of the to Avoid or Mitigate Concern Proponent Effort to Avoid or Reference Expressed Concern Expressed Mitigate Concern

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 12

9.2 Record of Consultation

The Town of Canmore will maintain a ROC for each Treaty 7 First Nation using the ACO ROC template3. Each ROC will include a detailed and accurate chronological account of all consultation activities along with supporting documentation. Both successful and unsuccessful attempts to engage First Nations will be documented. For every consultation activity the First Nations specific ROC will document: • names of person(s) contacted and method(s) of contact (e.g., phone, fax, email, voice mail, in person, letter); • details of contact with (or attempt to contact) the First Nation indicating dates and details of conversations or other type of response; • details of identified concerns and how they were addressed; • details of identified issues where agreements could not be reached and the reasons why; and • details of the outcomes of consultation (i.e., agreements reached, accommodation strategies agreed upon, etc.); and • supporting documentation as required.

3 http://esrd.alberta.ca/forms-maps-services/forms/lands-forms/esrd-forms/documents/FNC-RecordofConsultationLog-Feb27-2013%20B.pdf

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 13

Appendix A Notification Letter and Information Package

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 14

[DATE]

[Consultation contact name First Nation Address]

Dear [First Nation contact]:

Re: Town of Canmore Cougar Creek Debris Flood Retention Structure

The Aboriginal Consultation Office has directed the Town of Canmore to notify you of our proposed Cougar Creek Debris Flood Retention Structure (the Project). The Project has been assessed as a Level 3 extensive consultation and we have prepared the attached Information Package for your review.

Heavy rains in the Bow Valley in 2013 caused a debris flood on Cougar Creek that resulted in widespread damage to municipal infrastructure, flood protection works, homes, property, businesses, the Trans-Canada Highway, Highway 1a and the Canadian Pacific Railway. Immediately following this flood event, the Town of Canmore implemented short-term mitigation measures and initiated planning for long-term hazard mitigation on Cougar Creek. Based on the results of an extensive hazard and risk assessment and options analysis, the Town is proposing to construct an approximately 30 m high debris flood retention structure designed to provide significant risk reduction to the 4,000 residents and one third of Canmore’s business activity that exist on Cougar Creek alluvial fan.

The Town of Canmore is not aware of any specific short-or long-term adverse impacts to First Nations rights and traditional use resulting from the Project and is seeking input from you to identify any potential impacts to your community.

Construction on the Project is expected to begin as soon as regulatory approvals have been granted. The Town of Canmore has set an aggressive schedule for this Project as its primary aim is to increase public safety. We are working to secure key regulatory approvals in 2016 with construction complete in late 2018 to mid-2019.

Please review the enclosed information and let us know whether this Project may adversely impact your Treaty rights and traditional uses in the area within 20 business days of receiving this information. If you state that there are potential impacts, please specify the site-specific concerns and their location, in writing, that your First Nation may have.

If you wish to meet to discuss this Project further, please contact me at 403.678.1512 to arrange a meeting at your earliest convenience.

Sincerely,

Félix Camiré, E.I.T. Town of Canmore Engineering Services [email protected] 403.678.1512

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 15

Town of Canmore Cougar Creek Debris Flood Retention Structure Project Information Package

Introduction

Heavy rains in the Bow Valley in 2013 caused a debris flood on Cougar Creek that resulted in widespread damage to municipal infrastructure, flood protection works, homes, property, businesses, the Trans-Canada Highway, Highway 1a and the Canadian Pacific Railway. Immediately following this flood event, the Town of Canmore (the Town) implemented short-term mitigation measures on Cougar Creek including channel armouring and the installation of a debris net. These short-term mitigation measures are designed to reduce the amount of debris travelling from the watershed onto the alluvial fan and to reduce bank erosion in the creek channel if another flood event occurs prior to the implementation of long-term mitigation plans.

The Town conducted an extensive hazard and risk assessment and options analysis for long-term hazard mitigation on Cougar Creek. Multiple location and design options were evaluated for mitigating debris-flood hazards on Cougar Creek while protecting the Bow Valley Regional Wildlife Corridor, maintaining recreational access and fitting aesthetically with the natural landscape. This assessment resulted in the selection of a proposed debris flood retention structure (the Project) designed to provide significant risk reduction to the 4,000 residents and businesses on the Cougar Creek alluvial fan.

Completion of an Environmental Impact Assessment (EIA) Report is required for the Project so Level 3 extensive consultation is required. A Pre-Consultation Assessment provided by the Aboriginal Consultation Office on August 11, 2015 confirmed that [INSERT FIRST NATION NAME] will be consulted on the Project.

Project Location

The proposed Project location (LSD 14-34-24-10W5) is at the site of an existing debris net on Cougar Creek, approximately two kilometres northwest of the Trans-Canada Highway. The Project is located within the Bow Valley Wildland Park. Alberta Parks is pursuing the potential re-classification of a small section of the Project area to a provincial park (conditional on approval of the EIA). Alberta Parks will conduct First Nation consultation and public engagement on the re-classification of this area separately from the Town of Canmore’s efforts regarding this Project.

Figure 1 presents the location of the Project and includes the Bow Valley Wildland Park boundary. Figure 2 presents the location of the Project in relation to Treaty 7 First Nation reserves.

Project Description

Design The proposed Project consists of a debris flood retention structure on Cougar Creek that will be approximately 30 m high and will span a bedrock confined channel. The structure will be rock and earth filled with a reinforced concrete central sealing wall and will include an open outflow and debris rake. During normal weather conditions water and sediment will flow unimpeded through the structure. The structure has been designed to protect residents, business and infrastructure on the Cougar Creek alluvial fan and will be capable of holding back up to 600,000 cubic meters of water and debris with an outlet discharge rate of 45 cubic metres per second. The structure will not permanently hold water and is designed to allow water to pass through in a controlled manner.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 16

The structure includes a spillway to release water during a major event that is beyond design parameters, during which evacuation procedures would be initiated. The Project includes considerations for ensuring that wildlife movement and human access to Cougar Creek are not impeded. The structure will be a permanent installation and will not be decommissioned. A maintenance road will be constructed to access the structure.

The Public Disclosure Summary Table that was provided to the Government of Alberta by the Town of Canmore on January 27, 2015 is attached. The Public Disclosure Summary Table contains information that has changed since the January submission and reflects project design and schedule at that time.

Project Footprint The footprint of the debris flood retention structure is approximately 1.3 ha. For a maximum probable flood scenario the footprint of the inundation area behind the structure would be approximately 6 ha. A 0.5 km maintenance road with a footprint of 0.3 ha is also required. The Project footprint is shown on Figure 1. A preliminary upstream view of the structure is provided in Figure 3.

Construction and Maintenance Construction on the Project is expected to begin as soon as regulatory approvals have been granted. The Town of Canmore has set an aggressive schedule for this Project as its primary aim is to increase public safety. The Town is working to secure key regulatory approvals and begin construction in 2016. Project construction will take up to two years and is expected to be complete in late 2018 to mid-2019. Construction activities will include installing a sub-surface grout curtain under the structure, installation of a concrete sealing wall and outlet structure, building up the structure with rock and soil and then re-vegetating the surface. Construction areas will be reclaimed as part of the overall reclamation and landscaping planned for Cougar Creek. A 0.5 km maintenance road will be constructed to remove debris from behind the structure as needed.

Historical Resources

There are no known archaeological or paleontological resources within the Project footprint but there are sites in the area. The Project team has reviewed historical resource impact assessments for other developments in the area (e.g., adjacent residential developments) and is working with the Historic Resources Management Branch of Alberta Culture and Tourism to determine what additional work is required to identify and mitigate any potential impacts to historical resources.

Potential Impacts to First Nations Rights and Traditional Uses

The Town of Canmore is seeking project specific concerns from each Treaty 7 First Nation regarding potential impacts to First Nations rights and traditional uses. Recognizing that consultation activities have not been initiated and an EIA has not been completed, at this time the Town of Canmore is not aware of any specific short-or long-term adverse impacts to First Nations rights and traditional uses resulting from the Project. For consideration in your assessment of potential impacts, the Town of Canmore provides the following information: • the debris-flood retention structure and flood event inundation area are located in a highly scoured steep mountain creek bed with limited potential for vegetation or wildlife habitat; • the topography and hydrology of Cougar Creek minimize the likelihood of historical features in the debris- flood retention structure and flood event inundation area; • the debris flood retention structure will be designed to maintain access for recreational and traditional activities in Cougar Creek;

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 17

• the debris flood retention structure will be designed to minimize potential effects on the Bow Valley Regional Wildlife Corridor and wildlife movement up and across Cougar Creek will be maintained; and • Cougar Creek is not a fish bearing waterway and the Project is not expected to alter fish habitat.

Regulatory Approvals Required

The Project requires an EIA under the Environmental Protection and Enhancement Act (EPEA). Technical specialists at Alberta Environment and Parks (AEP) will review the EIA and the Natural Resources Conservation Board (NRCB) will make a Project decision based on that review. If Project approval is granted by the NRCB, required Water Act and Provincial Parks Act approvals and dispositions will be secured prior to construction.

Regulatory Approvals Required Regulatory Body Relevant Legislation Application / Contact Submission Alberta Environmental Protection Environmental Impact Environmental Assessment Environment and and Enhancement Act Assessment Report Environment and Parks Parks and Natural Main fl Twin Atria Building Resources 4999 - 98 Avenue Edmonton, AB T6B 2X3 Conservation Board 780.643.3853 Alberta Water Act Dam Safety and Dam Safety Environment and Water Act Approval Alberta Environment and Parks Parks Application 8th fl Oxbridge Place 9820 - 106 Street Edmonton, AB T5K 2J6 780.644.7437 Alberta Culture and Historical Resources Act Archaeological and Historic Resources Management Branch Tourism Paleontological Alberta Culture and Tourism Impact Assessment Old St. Stephen's College or Clearance 8820 - 112 Street NW Application Edmonton AB T6G 2P8 780.431.2300 Alberta Provincial Parks Act Application for Parks Kananaskis Region Environment and disposition Environment and Parks Parks (dependent on project 2nd fl Provincial Building approval and re- 800 Railway Avenue classification of Canmore, AB T1W 1P1 project area to 403.678,5508 Provincial Park).

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 18

Consultation Process

As per the ACO Level 3 extensive consultation requirements, delivery of this notification letter and information package initiates the 20 day review period for [FIRST NATION NAME] (20 working days beginning on the Government of Alberta working day following verified receipt of notification). The Town of Canmore will follow-up with [FIRST NATION NAME] if a response has not been received within 10 days and a second follow-up will occur after 15 days.

[FIRST NATION NAME] is requested to provide feedback on potential Project specific impacts to Treaty rights and traditional uses within the 20 day review period. If any potential impacts are identified, site-specific concerns should be described along with their location. Feedback should be in writing and can be provided to:

Mr. Félix Camiré, E.I.T. Town of Canmore Engineering Services 902 7th Avenue Canmore, AB T1W 3K1 403.678.1512 [email protected]

Consultation Schedule

The following tables provide a preliminary consultation schedule for the project and a description of the consultation activities that will occur during the regulatory process.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 19

Consultation Activities and Timing Consultation Milestone Activities Timing

Pre-Consultation Consultation Plan Town of Canmore working with the ACO to develop a Consultation Q2/Q3 2015 Development and Approval Plan for the Project.

Pre-Application Consultation Project Information Packages The Town of Canmore will provide each First Nation with a plain October 2015 language Project Information Package that meets ACO requirements. The Town of Canmore will follow up with each First Nation to October / November confirm community interest in the Project 2015

Proposed Terms of Reference The Town of Canmore will provide each First Nation with a copy of October 2015 the Proposed Terms of Reference (PTOR) that includes information on how the community can provide comment on the PTOR First Nations will have an opportunity to provide comments on the October to December PTOR during the 45-day public review period. 2015

AEP will consider First Nation input into the PTOR December to March 2015

Project Specific Consultation The Town of Canmore will schedule and participate in consultation Ongoing after Meetings and Follow Up meetings with interested First Nations. These meetings will November 2015 Actions include information on the effects assessment conducted by the Town of Canmore and will seek to gather First Nations input into the mitigation of potential project effects.

The Town of Canmore will conduct necessary follow-up actions Ongoing after arising from the consultation meetings (e.g., provision of additional November 2015 information).

The Town of Canmore will provide each First Nation with bi- Ongoing after monthly consultation reports. November 2015

Post-Application Consultation (Application Review) Notification of Submission The Town of Canmore will notify each First Nation when the EIA May 2016 report is submitted and provide access to the EIA report in a format acceptable to each First Nation. This notification will include a description of the process and deadline for submitting Statements of Concern. Project Specific Consultation The Town of Canmore will continue to schedule and participate in Ongoing after Meetings and Follow Up consultation meetings with First Nations who have ongoing November 2015 Actions interest in the Project. These meetings will include discussions on mitigation for potential project effects and accommodation if required. Record of Consultation The Town of Canmore will provide each First Nation with a Record TBD of Consultation for their review at an appropriate time.

-94000 -93500 -93000 -92500 -92000 -91500 Existing Flood Mitigation Measure 0 0 5 3

6 ACO Boundary 6 5 Cadastral Fabric Town of Canmore Municipal Boundary 03-04 W 02-04

01-04 5 Watercourse

04-03 2 03-03 02-03 . 01-03 p Highway w T Road Site Access Route (1.02 km) Railway Proposed Project Footprint Debris Flood Retention Structure Road Inundation Area 0 0 0 3 6 6 5 14-33 15-33 16-33 13-34 14-34 15-34 16-34

k e e r C r a

0 11-33

0 g

5 u 2 10-33

6 o 6

5 C 12-34 11-34 10-34 09-34

B en chl and 06-33 s Tra 07-33 il 4 2

. 08-33 p w 0 T

0 05-34

0 06-34 07-34 2 08-34 6 6 5 d x P m . n o o i t l a i c c o

L e _

e m r u t c a u r t n S _ n C o

i 03-33 t n r E e

t e e 02-33 e l R k Reference: Data obtained from AltaLIS © Government of Alberta used under license. _ k d GDM transportation infrastructure data provided by IHS © 2015 used under license. o R o l

F 1:10,000

_ u

s 03-34 i r n 02-34 01-34 b e 250 0 250 D B _ 1 Metres e r UV

o o m

0 u n NAD 1983 3TM 114 a 0

C l 5

_ e 1 f o 6 v _ 6 n

5 a w o r T - d 1 - e r u g i F \ O C A \ y t r a P d

r 14-28 i h T

\ Cougar Creek Debris Flood Retention Structure

5 15-28 1 0 2 \ A

I 16-28 E \ s 13-27 e 14-27 l 15-27 b 16-27 a Town of Canmore Debris Flood T d n A s e r Retention Structure Location u g i F \

6 Date: Project:

4 DRAFT

7 28 Sep 2015 20746-514 0 2 \ Technical: Reviewer: Drawn: e r I. Trimble R. Harding C. Beaumont o m 0 n

0 Disclaimer: Prepared solely for the use of the Town of Canmore as a Figure 0 C f

1 specified in the accompanying report. No representation of any kind O 6

n is made to other parties with which the Town of Canmore has not 6 w 5 o Rg. 10 entered into contract. T \

: W5M I 1 -150000 -100000 -50000 0 50000 100000 UV795 Samson Lake Red Deer aptiste B 822 Lake B iver Rive UV a Heisler ksto r t ac n R Aurora Ponoka t l g Open 854 l B e g UV River e e 20A d Creek UV R r i o 821 v Welch Parkland UV e N r Creek Beach Donalda 604 UV605 Bashaw UV53 771 792 UV J.J. Magee UV UV Collett Lake W Buffalo Gull Gadsby Lake Lake Big Mill Medicine Lake Lodge Lacombe Clive Knife 11 ask Island Gull Rochon 850 UV hS atchewan River UV12 Hills UV50 UV rt 761 Lake 815 Sands o 756 UV UV Big Horn N UV B l 855 in 601 UV 144a d Blackfalds Alix UV Rocky UV598 Sylvan m 0 Mountain an 852 0 Eckville Lake Ri UV 0 House 20 ver 597

0 UV M UV 0 Heatburg 8 e 11A Stettler Botha Gadsby 5 Cow d UV N ic Sylvan orth RamR Lake in Halkirk i e Red ver Lake Creek 752 R Deer rie UV Cow Lake i 808 835 Douglas ai v UV UV r e Fir P r UV595 594 Marion Chedderville UV781 Delburne Ewing UV 816 Lake UV Lake Lowden 592 UV593 Abraham UV Penhold Lake Lake UV42 Ram Clearwater nRiver 54 Pine Falls Ricinus Rave UV Markerville Lake Tolman UV734 UV591 G UV853 Kootenay h Badlands Big Gough o 590 s Heritage Lake Plains River K UV tp Valley m n i a Clearw r Schrader n Rangeland a e Burnstick Innisfail e e R t Creek e C Elnora 56 e i v h UV r R Lake i r 589 - l e UV l Dry Island s 805 e Red UV k 587 Red C Buffalo Jump iver UV Lodge r Heart Deer e

0 R es Bowden e 0 Lake Jam River k 0

0 Farrell 5 584 7 UV Snakes Rumsey Lake 5 585 S UV i f Head f l e Trochu u Scalp Bentz r Sundre R Creek Lake 27 UV 839 iv Bearberry UV e Olds r Prairie iver rR 791 851 ee 760 UV UV D UV 2A UV583 Three Red UV Hills 582 Lonep UV806 Morrin

Didsbury UV ine

k C Delia eek e re

Cr e e Banff timber k 836 en r all UV 837

National F C Linden UV d

Park n Carstairs 581 UV21 Munson u UV 838 849 Cremona o R UV UV p 580 o g UV se o bu 575 r D dR Acme UV e Carbon Drumheller 579 v iv 576

0 i UV UV C e 0 R r r 0 L r o 0 Ri ittle ee s 0 ade ver Red D sfield 7 asc 574 Cr 5 Little C UV Crossfield eek 10X Don 72 9 UV UV10 Fish Lake Stoney UV Beiseker UV 841 Yoho Getty UV766 UV UV573 142b National 772 B UV Irricana Park o Airdrie 569 w R 567 UV iv Lake Big Hill UV 570 er Waiparous 848 UV Kootenay Minnewanka Springs UV National Stoney Rockyford Park Project 142, Cochrane UV566 UV840 143, 144 UV782 UV564 Banff Location UV1A Standard 201 Deadhorse K 563 UV o S UV Lake ot p Strathmore e r ^_ n ay a Canmore 68 1 Hussar R y UV Calgary UV 0 iv R 8 Chestermere 561

0 UV e iv Bow UV

0 r er 797 0 Valley UV Eagle 5 Tsuu T'ina 560 C 6 UV 817 Lake ro 5 Fish UV w Barkenhouse Spray Lakes Nation 145 fo 758 o Lake

Reservoir UV Creek tC

r

e r 22X 901 e

e UV UV 842 k Spray iv UV 862

R 66 s UV UV i 762

Valley k

s UV a

n Wyndham-Carseland Siksika

a Brown-Lowery Highwood

n Bassano a 146 95 River UV550

K k UV int Cree UV549 UV552 iv r epo 24 sR e e re UV s r v Th Arrowwood ro i Sheep Okotoks C R 547 UV k 40 ow Creek 7 e 93 UV Elb UV re UV Sheep 799 C UV d Radium Peter o River 783 o UV w Hot Lougheed Sheep River Springs w o ie r Horseth f Creek Bluerock UV543 High r A

0 t 542 River s Milo

0 Frank e UV

0 iser Elbow-Sheep Pall R W 0 iver Lake 0 Longview 6 ek E 541 5 re l UV C Windermere k UV23 y R b 540 o Lake iv Eden UV T e r Valley 216 804 er UV 539 iv UV od R Emerson McGregor Highwo Vulcan 534 Creek UV Lake 22 531 UV Nanton UV Lomond

Mos h Creek qu Dutc 533 ito UV C Columbia 532 ree k 529 Lake Plateau UV UV Champion Little er Chain iv Mountain Bow Fi Canal R Lakes W nd te il Travers la Flats W hi lo 526 y C w 527 Reservoir UV ree Whiteswan Mt. Creek UV Stavely k L 522 u Lake Willow UV

0 Livingstone Carmangay s

0 s i 2 0 e Creek UV r 0

R

5 845 25 i UV 5 v Beehive UV 5 e Elkford

r Claresholm Litt UV843 le B 520 o 521 ck Creek UV Barons w UV

kookumchu Bob R

S i v

Creek Keho e Lake r

43 UV Nobleford Picture a Granum UV519 Butte

i

a O

h l

b d t m B Park

s r a e

i n Lake R a 811 m i Lake e t v UV v Koocanusa e Barnwell i e r r u b r C l Coalhurst l re Coaldale ek Fort

o B 785

A UV UV95A Macleod UV512 r C 0 Kimberley ve Lethbridge 0 i

0 R l 0 l 511

0 u UV 5 B 508 5 UV510 UV Cranbrook 3A UV Cowley Piikani UV61 Fernie Reserve UV810 Pincher Stirling Creek Blood 52 r UV e 775 148 v UV 844 i 507 r UV R UV ve t i Magrath Go 774 Beauvais R Milk a l 3 F UV ly o d UV l l C ath Lake e UV5 River Ridge G re ea B 4 e dR Glenwood UV k iv Reservoir 506 Moyie er West Castle UV Lake Wetlands UV505 Waterton St. Mary C r a Reservoir e m s 6 Reservoir v wa R t UV g l i i i v e r

R W e R ve ie r i oy R

i n 0 M rnC ver 62 0 o re o UV h t 0 e ig k r 503

0 B e Cardston UV 5 t

a r 4 e 5 W 800 kR UV v il ive i r 820 h M R UV Ross rt y o Waterton Lakes r Lake N a er Twin d v

x k i

National Park Blood Timber M Shanks R e River m k . t. il n e Limit 148a S Lake M Heritage o Waterton r i t Police a C 501 Rangeland c Lakes e UV o e Outpost

L L _ t c e j o r P - 2 - e r u g i F \

O Community Watercourse C A \ y t r Provincial Park Highway a P d r i h Protected Area Railway T \ 5 1 0

2 Provincial Recreation Area \ A I E

\ Project Location s Natural Area Cougar Creek Debris Flood Retention Structure e l b ^_ a T Ecological Reserve d n A s e

r National Park u g i F \

6 Indian Reserve

4 Project Location 7 0 2 \ Provincial Boundary e r 1:1,200,000 o m n Water Body Date: Project: DRTechnical:AFReviewTer: Drawn: a 20 Aug 2015 20746-514 I. Trimble R. Harding C. Beaumont C f 20 0 20

O Disclaimer: Prepared solely for the use of the Town of Canmore as specified in the accompanying report. No n Reference: Data obtained from AltaLIS © Government of Alberta and GeoGratis © Department of Kilometres Figure w representation of any kind is made to other parties with which the Town of Canmore has not entered into contract. o Natural Resources Canada (all rights reserved) used under license. GDM transportation infrastructure T \

: data provided by IHS © 2015 used under license. NAD 1983 3TM 114 I 2 Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 22

Figure 3 Town of Canmore Debris Flood Retention Structure Rendering

Upstream View of Preliminary Design

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 23

Project Summary Table Original Submission: January 27, 2015 Proponent Name: Town of Canmore Date: Updated: September 28, 2015

Felix Camire Project Engineer Town of Canmore Cougar Creek Debris 902-7th Avenue Company Contact Name Project Name: Flood Retention Canmore, AB and Information: Structure T1W 3K1 [email protected] O: 403-678-1512 F: 403-618-1534

Name of Company that will Town of Canmore Company Website: www.canmore.ca hold Approval:

Structure greater than New Project, Expansion, Type of Project (e.g., in- situ, 15m for flood control Additional Phase or New project mine, quarry, upgrader, etc.): and sediment retention. Modification:

Projected Construction Start Projected Operation Start 02/2017 09/2019 (Month/Year): (Month/Year):

Project Location (Legal Land NW 34-24-10-5 Life of Project (# years, YYYY 2019-indefinite Description and 51° 05’ N, 115° 19’ W – YYYY): Permanent Installation Longitude/Latitude) and Town of Canmore Municipality:

Provincial Wildland Park Private, Federal or Provincial (area to be re-classified to Total Project Area (ha): Approximately 7.3 ha Land: Provincial Park pending approval of the EIA)

Types of Activity (major Temporary water retention Nearest residences are project processes, structure, with a capacity of Nearest Residence(s) (km): 1 km away, not in the components including impoundment of 650,000 impoundment zone. capacity/size, if available): cubic meters.

Nearest First Nation Reserve(s) and Métis Stoney Nation, 20km Project Products: N/A Settlements (name and km): Power Source (if on site Method of Product Transport power generation describe N/A N/A (e.g., pipeline, rail, truck, etc.): quantity (MW) and facilities): Infrastructure Requirements Average Production Access road on the west (e.g., roads, pipelines, water Capacity per Year N/A bank of channel, diversion intake, storage, tankage, (specify units): works for construction etc.): Expected Types of Air Minor dust during Location of End Market: N/A Emissions (e.g., SO2, construction, None during NOX, CO2, etc.): operation

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 24

Minor construction waste during construction, none during operation. Project By-Products: N/A Types of Wastes Generated: Accumulation of debris post flooding that will need to be removed every few years.

Expected Types of Effluent Within Cougar Creek, flowing Releases (note the water Nearest Waterway/Waterbody into the Bow River None bodies the effluent will be (name and km): approximately 2.5km released to): downstream.

None necessary, Waste Management Facilities construction waste will (i.e., Disposal Well, Salt EPEA Approval Required be disposed at Francis Yes Caverns, Landfill, or Third- (Y/N/Unknown): Cook Regional Landfill, Party): 15km east of project site

Water Act Licence Required Watercourse Crossings (Y/N/Unknown. If yes, (type of crossing, any Class N/A Yes purpose, source and A to C waterbodies): estimated volumes):

Waterbodies Required Regulatory Board(s) NRBC (Y/N/Unknown/NA. If yes, None (ERCB/NRCB/AUC): # and ha):

Will any of the components Water Act Approval Required or activities associated with No, Cougar Creek is not fish (Y/N/Unknown. If yes, Yes the project affect fish and/or bearing. purpose): fish habitat? (Y/N): Identify applicable federal Identify applicable sections in legislative or regulatory the Schedule to the Federal requirements referred to in No None Comprehensive Study List the Law List Regulations (i.e., Regulations: (Y/N/Unknown): permits, licenses, authorizations): Are any works or Nearest well is located 2km undertakings proposed to take away from project in a Nearest Water Well (km) place in, on, over, under, No westerly direction. Cougar (Domestic and Commercial): through or across a navigable Creek flows in a southerly water? (Y/N): direction.

Nearest Provincial Trans-Canada Hwy and Access Improvements to Highway (# and Highway 1A (1.5km None Provincial Highway: distance): away)

Traffic Impact Assessment Total Area to be No Currently estimated at 7.3 ha Required (Yes/No/Unknown): Disturbed (ha):

Identify Existing Land and The infrastructure is Water Use(s), Resource permanent so only Residential and Management, or Conservation Post-reclamation Land Use(s): construction disturbance will Wildland Park uses. Plans Within or Near the be reclaimed as per AEP Project site: direction.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 25

Decommissioning Start and Reclamation Start and End No Decommissioning 2018-2019 End (YYYY-YYYY): (YYYY - YYYY):

Infrastructure to be built Unique Environmental or in a Provincial Wildland Historic Resources Impact Social Considerations Park. Alberta Parks has Assessment Required Yes (Describe or None): been engaged for over a (Y/N/Unknown): year.

Estimated Construction Person- Estimated Operation Persons- 1 part-time person, 100 Years of Employment: Years of Employment: continuous.

Construction or Operation Method of Transport of Pick-up trucks during Camp Required Employees to Site No construction, individual (Y/N/Unknown. If yes, (Construction and vehicle during operation. on-site or off-site): Operation):

Is there any federal authority Will the project involve the that is, or may be, providing manufacture and storage No financial support to the Project No of explosives (Y/N): (Y/N. If yes, identify the federal authority):

Stakeholder (Alberta Transportation, CPR, Date Stakeholder Aboriginal engagement not Alberta Environment Aboriginal Groups Involved in Engagement Started yet started. Anticipated to and Parks) engagement Stakeholder Engagement: (Public/Aboriginal): begin in Q4 2015. has been ongoing since June 2014.

Public engagement Public Groups involved in started in early October Stakeholder Engagement: 2014.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 26

Glossary of Terms

Alluvial Fan A fan or triangle shaped deposit of gravel, sand or sediment that forms at the mouth of a mountain stream.

Debris Flood A flood event that contains up to 20% solids that is triggered by excessive bank erosion, debris entrainment or landslide dam outbreak events.

Return Period An estimate of the likelihood of an event occurrence (e.g., earthquake, flood or river discharge flow).

Spillway A structure used for controlled release of water from a dam or retention structure to prevent damage to the structure during high water events.

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 27

Appendix B Public Notification – Proposed Terms of Reference

Town Of Canmore Debris Flood Retention Structure Project September 30, 2015 Aboriginal Consultation Plan Page 28

Public Notice Town Of Canmore Cougar Creek Debris Flood Retention Structure Proposed Terms of Reference for Environmental Impact Assessment

The proposed Project consists of a debris flood retention structure on Cougar Creek that will be approximately 30 m high and will span a bedrock confined channel. During normal weather conditions water and sediment will flow unimpeded through the structure. During a flood event the structure will be designed to hold back up to 600,000 cubic meters of water and debris. The structure will not permanently hold water. The proposed Project location (LSD 14-34-24-10W5) is at the site of an existing debris net on Cougar Creek, approximately 2 km northwest of the Trans-Canada Highway.

The Director responsible for Environmental Assessment has directed that an Environmental Impact Assessment Report be prepared for the Cougar Creek Debris Flood Retention Structure. The Town of Canmore has prepared a proposed Terms of Reference for this Environmental Impact Assessment, and through this public notice, invites the public to review this document. Your comments and personal contact information filed concerning the proposed Terms of Reference will be accessible to the public.

The proposed Terms of Reference and associated project information can be viewed at the following locations: • Town of Canmore Civic Centre located at 902 7th Avenue, C anm ore Alberta • Town of Canmore website at www.canmore.ca • Alberta Environment and Parks Register of Environmental Assessment, 2nd Floor, Petroleum Plaza, South Tower, 9915 – 108 Street, Edmonton, Alberta, T5K 2G8, Attn: Melanie Daneluk; http://www.esrd.alberta.ca/ea, (choose Current Projects)

For further information on the Cougar Creek Debris Flood Retention Structure or copies of the proposed Terms of Reference and associated project information please contact:

Félix Camiré, E.I.T. Town of Canmore Engineering Services 902 7th Avenue, Canm ore, AB T1W 3K1 403.678.1512 [email protected]

Individuals wishing to provide written comments on the proposed Terms of Reference must submit them by [DATE TO BE PROVIDED BY AEP] to:

Director, Environmental Assessment, Operations Division Alberta Environment and Parks 2nd Floor, Petroleum Plaza, South Tower, 9915 – 108 Street, Edmonton, Alberta T5K 2G8 Fax: 780-427-9102, E-mail: [email protected]