Recruitment for Emergency & Shelter Project Officer

Written Test

Construction Management of a Contractor Build project

Date:

Name of Applicant: Time Finished:

Instructions: Applicants will have up to 2 hours to complete the test. Answers should be typed on this WORD document. For Question #7, please send your WORD or EXCEL file back. All documents / files should be sent by email within 2 hours of starting the test.

Question #1: Please insert in the table below key stages of a construction project starting from brief creation to hand over and maintenance and an outline of the activities needing to be achieved at each stage for a contractor lead school building project.

Stages / Activities needed to be achieved at this stage
Front end engineering and design
Completion and Handover
After completion

Question #2: Whenever one become involved in a construction project there are organizational risks, please describe your understanding of these terms and as a Construction Manager you would manage to minimize these risks.

Risks / What is your understanding of this risk and why is it important. / How would you manage to minimize these risks
Collusion
Theft
Threat
Site Safety
Delays
Cost increase
Low quality

Question #3: Please explain what a construction contract is?

Answer;

Which parties are a signatory a construction contract?

Answer;

Explain what the following documents are;

a)  Engineering design drawings,

Answer;

b)  Bill of quantities,

Answer;

c)  Specifications

Answer;

Are these documents a part of the construction contract? Yes/ No

Please list the most important clauses in a construction contract that binds the parties to each other and which may help you manage the contract.

Answer;

Question #4. In estimating a project sand and cement are measured in units respectively:

A. m3, kg / B. kg, m3
C. m3, m3 / D. kg, kg

Answer:

Question #5. You are tasked to setup Quality Control procedures. Explain the following terms;

a)  Inspection report;

Answer;

b)  Day-to-day inspection

Answer;

c)  Weekly inspection

Answer;

d)  Hold points /key inspection points

Answer;

Question #6. One day, on a weekly inspection you observe that the foundations which are nearly completed is not what you thought was agreed. What steps would you take to ensure the corrective measure is taken.

Question #7: Using MS Word table or Excel, prepare a shelter construction program given the following information below.

You are charged with developing a construction schedule to construct schools spread over 4 locations in a refugee camp. Develop a construction schedule to construct the 12 semi-permanent classrooms (half timber, half blockwork), with 8 latrine blocks fencing for the school ground and a guard house within 5 months. Please refer to your answers from question 1 to provide the key stages. Provide notes in your construction schedule for number of classrooms, latrine and fencing achieved.